Rab SDN Baloi Permai Batam Kota
Rab SDN Baloi Permai Batam Kota
JUMLAH Rp 7,598,733,423
DIBULATKAN Rp 7,598,733,000
Terbilang : ###
Batam, .....................
Konsultan Perencana
CV. ALMATRA BUANA
Ir. H. SUPRIYANTO, MT
Direktur
1/28 REKAP1
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
I PEKERJAAN PERSIAPAN
2/28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
BLOK A
A PEKERJAAN PERSIAPAN
1 Pembersihan lahan m2 363.00 1,600.00 580,800.00
2 Pengukuran dan pemasangan bowplank m' 88.00 41,100.00 3,616,800.00
C PEKERJAAN BETON
1 Sloof type S1 20/40 cm
- Galian tanah m3 31.58 24,100.00 760,957.50
- Pasir urug t = 5 cm m3 2.11 11,800.00 24,839.00
- Lantai kerja t = 5 cm m3 2.11 111,600.00 234,918.00
- Beton K-250 m3 16.84 959,700.00 16,161,348.00
- Pembesian kg 2,605.91 12,500.00 32,573,902.13
- Bekisting m2 168.40 95,500.00 16,082,200.00
2 Kolom K1 25X40 cm
- Beton K-250 m3 7.92 959,700.00 7,600,824.00
- Pembesian kg 1,473.62 12,500.00 18,420,193.00
- Bekisting m2 102.96 165,600.00 17,050,176.00
3 Kolom K3 25X25 cm
- Beton K-250 m3 2.25 959,700.00 2,159,325.00
- Pembesian kg 388.21 12,500.00 4,852,650.00
- Bekisting m2 36.00 165,600.00 5,961,600.00
4 Balok B1 25/50 cm
- Beton K-250 m3 1.75 959,700.00 1,679,475.00
- Pembesian kg 272.55 12,500.00 3,406,837.50
- Bekisting m2 17.50 167,200.00 2,926,000.00
5 Balok B2 20/40 cm
- Beton K-250 m3 11.96 959,700.00 11,478,012.00
- Pembesian kg 1,196.64 12,500.00 14,957,939.00
- Bekisting m2 149.50 167,200.00 24,996,400.00
6 Balok B3 20/40 cm
- Beton K-250 m3 2.16 959,700.00 2,072,952.00
- Pembesian kg 390.78 12,500.00 4,884,807.00
Page 3 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
E PEKERJAAN LANTAI/KERAMIK
1 Urugan pasir, tebal : 5 cm m3 14.38 111,600.00 1,604,250.00
2 Lantai kerja, tebal : 5 cm m3 14.38 741,200.00 10,654,750.00
3 Keramik lantai homogeneous 60 x 60 cm m2 277.00 147,300.00 40,802,100.00
4 Keramik lantai 20 x 20 cm (pada KM/WC) m2 10.50 88,400.00 928,200.00
5 Keramik dinding 20 x 25 cm (pada KM/WC) tinggi = 1,5 m m2 25.50 117,990.00 3,008,745.00
6 Plint keramik 10 x 60 cm m1 135.50 24,550.00 3,326,525.00
7 Lantai rabat beton keliling bangunan tebal 10 cm m3 5.20 741,200.00 3,854,240.00
-
SUB TOTAL E. PEKERJAAN LANTAI/KERAMIK 64,178,810.00
G PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 98.00 73,600.00 7,212,800.00
2 List Plafond cornice gypsum m' 103.00 23,500.00 2,420,500.00
3 Plafond GRC tebal 3,5 mm m2 123.20 75,000.00 9,240,000.00
Page 4 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
H PEKERJAAN PENGECATAN
1 Cat dinding m2 933.40 23,900.00 22,308,245.66
2 Cat plafond m2 221.20 15,300.00 3,384,360.00
3 Cat listplank beton m2 153.30 23,900.00 3,663,870.00
I PEKERJAAN TANGGA
1 Railing tangga utama m' 9.00 700,000.00 6,300,000.00
2 Keramik tangga utama 30 x 30 cm unpolish ( termasuk bordes ) m2 33.00 93,150.00 3,073,950.00
3 Pekerjaan tangga selasar ( 2 tangga ) -
- Pasangan bata (1:4) m2 1.70 73,300.00 124,610.00
- Plesteran (1:4) + acian halus termasuk lantai tangga m2 5.78 24,700.00 142,766.00
- Lantai rabat beton tebal 8 cm m3 0.37 741,200.00 277,208.80
- Grill besi lebar 20 cm ( finhising cat ) m' 8.50 150,000.00 1,275,000.00
J PEKERJAAN SANITAIR
1 Kran air bh 2.00 39,900.00 79,800.00
2 Floor drain bh 1.00 36,300.00 36,300.00
3 Pasang pipa air bersih PVC 1/2 inch + acsesoris m' 30.00 9,100.00 273,000.00
4 Pasang pipa air kotor PVC 3 inch + acsesoris m' 6.00 74,800.00 448,800.00
5 Pasang pipa air limbah PVC 4 inch + acsesoris m' 6.00 80,000.00 480,000.00
6 Pasang pipa air hujan ( talang ) PVC 3 inch + acsesoris m1 50.00 74,800.00 3,740,000.00
7 Pemasangan saluran pas. bata lebar 20 cm m' 60.50 73,600.00 4,452,800.00
8 Bak kontrol 40 x 40 cm bh 3.00 79,000.00 237,000.00
BLOK B
A PEKERJAAN PERSIAPAN
1 Pembersihan lahan m2 418.00 1,600.00 668,800.00
2 Pengukuran dan pemasangan bowplank m' 98.00 41,100.00 4,027,800.00
Page 5 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
- Pengadaan tiang pancang spun pile dia 35 cm m' 432.00 336,000.00 145,152,000.00
- Pemancangan tiang pancang spun pile dia 35 cm m' 432.00 184,000.00 79,488,000.00
- Penyambungan tiang pancang buah 48.00 102,000.00 4,896,000.00
- Pemotongan tiang pancang buah 24.00 70,000.00 1,680,000.00
- Galian tanah m3 28.80 24,100.00 694,080.00
- Urugan kembali m3 17.47 11,800.00 206,169.60
- Pasir urug t = 5 cm m3 1.20 111,600.00 133,920.00
- Lantai kerja t = 5 cm m3 1.20 741,200.00 889,440.00
- Beton K-250 m3 8.93 959,700.00 8,568,201.60
- Pembesian kg 1,816.22 12,500.00 22,702,704.00
- Bekisting m2 42.24 83,200.00 3,514,368.00
2 Pondasi Pile Cape P2 80 x 80 x 50 cm -
- Pengadaan tiang pancang uk. 20,3 x 20,3 cm m' 162.00 336,000.00 54,432,000.00
- Pemancangan tiang pancang uk. 20,3 x 20,3 cm m' 162.00 184,000.00 29,808,000.00
- Penyambungan tiang pancang buah 18.00 102,000.00 1,836,000.00
- Pemotongan tiang pancang buah 9.00 70,000.00 630,000.00
- Galian tanah m3 10.80 24,100.00 260,280.00
- Urugan kembali m3 6.73 11,800.00 79,384.50
- Pasir urug t = 5 cm m3 0.45 111,600.00 50,220.00
- Lantai kerja t = 5 cm m3 0.45 741,200.00 333,540.00
- Beton K-250 m3 3.17 959,700.00 3,044,648.25
- Pembesian kg 581.07 12,500.00 7,263,403.20
- Bekisting m2 18.00 83,200.00 1,497,600.00
3 Timbunan tanah untuk leveling lantai m3 129.60 42,400.00 5,495,040.00
C PEKERJAAN BETON
1 Sloof type S1 20/40 cm
- Galian tanah m3 36.33 24,100.00 875,553.00
- Pasir urug t = 5 cm m3 2.42 111,600.00 270,295.20
- Lantai kerja t = 5 cm m3 2.42 741,200.00 1,795,186.40
- Beton K-250 m3 19.38 959,700.00 18,595,147.20
- Pembesian kg 3,115.21 12,500.00 38,940,127.00
- Bekisting m2 193.76 95,500.00 18,504,080.00
2 Sloof type S2 20/30 cm
- Galian tanah m3 2.55 24,100.00 61,455.00
- Pasir urug t = 5 cm m3 0.21 111,600.00 23,715.00
- Lantai kerja t = 5 cm m3 0.21 741,200.00 157,505.00
- Beton K-250 m3 1.28 959,700.00 1,223,617.50
- Pembesian kg 175.76 12,500.00 2,197,037.50
- Bekisting m2 12.75 95,500.00 1,217,625.00
3 Kolom K1 25X40 cm
- Beton K-250 m3 6.91 959,700.00 6,633,446.40
- Pembesian kg 1,674.24 12,500.00 20,928,048.00
- Bekisting m2 31.20 165,600.00 5,166,720.00
4 Kolom K3 25x25 cm
- Beton K-250 m3 0.56 959,700.00 539,831.25
- Pembesian kg 396.66 12,500.00 4,958,226.00
- Bekisting m2 9.00 165,600.00 1,490,400.00
5 Kolom KP 15/15 cm
- Beton 1:2:3 m3 1.05 959,700.00 1,010,564.10
- Pembesian kg 176.81 12,500.00 2,210,130.00
- Bekisting m2 14.04 165,600.00 2,325,024.00
6 Balok B1 25/50 cm
- Beton K-250 m3 2.63 959,700.00 2,519,212.50
- Pembesian kg 390.94 12,500.00 4,886,706.00
- Bekisting m2 26.25 167,200.00 4,389,000.00
7 Balok B2 20/40 cm
- Beton K-250 m3 12.68 959,700.00 12,168,996.00
- Pembesian kg 1,714.94 12,500.00 21,436,729.00
- Bekisting m2 158.50 167,200.00 26,501,200.00
8 Balok B3 20/40 cm
- Beton K-250 m3 2.52 959,700.00 2,418,444.00
Page 6 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
E PEKERJAAN LANTAI/KERAMIK
1 Urugan pasir, tebal : 5 cm m3 16.20 111,600.00 1,807,920.00
2 Lantai kerja, tebal : 5 cm m3 16.20 741,200.00 12,007,440.00
3 Keramik lantai homogeneous 60 x 60 cm m2 283.50 147,300.00 41,759,550.00
4 Keramik lantai 20 x 20 cm (pada kamar mandi) m2 40.50 88,400.00 3,580,200.00
5 Keramik dinding 20 x 25 cm tinggi = 1,75 m m2 140.88 117,990.00 16,621,841.25
6 Plint keramik 10 x 60 cm m1 135.00 24,550.00 3,314,250.00
7 Lantai rabat beton keliling bangunan tebal 10 cm m3 7.15 741,200.00 5,299,580.00
Page 7 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
G PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 195.75 73,600.00 14,407,200.00
2 List Plafond cornice gypsum m' 148.50 23,500.00 3,489,750.00
3 Plafond GRC tebal 3,5 mm m2 112.50 75,000.00 8,437,500.00
H PEKERJAAN PENGECATAN
1 Cat dinding m2 1,035.90 23,900.00 24,758,115.16
2 Cat plafond m2 308.25 15,300.00 4,716,225.00
3 Cat listplank beton m2 159.60 23,900.00 3,814,440.00
I PEKERJAAN TANGGA
1 Railing tangga utama m' 9.00 700,000.00 6,300,000.00
2 Keramik tangga utama 30 x 30 cm unpolish ( termasuk bordes ) m2 34.75 93,150.00 3,236,962.50
3 Pekerjaan tangga selasar ( 1 tangga )
- Pasangan bata (1:4) m2 1.04 73,300.00 76,232.00
- Plesteran (1:4) + acian halus termasuk lantai tangga m2 3.06 24,700.00 75,582.00
- Lantai rabat beton tebal 8 cm m3 0.20 741,200.00 146,757.60
- Grill besi lebar 20 cm ( finhising cat ) m' 5.00 150,000.00 750,000.00
BLOK C
A PEKERJAAN PERSIAPAN
1 Pembersihan lahan m2 368.50 1,600.00 589,600.00
2 Pengukuran dan pemasangan bowplank m' 89.00 41,100.00 3,657,900.00
Page 8 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
C PEKERJAAN BETON
1 Sloof type S1 20/40 cm
- Galian tanah m3 30.75 24,100.00 741,075.00
- Pasir urug t = 5 cm m3 2.05 111,600.00 228,780.00
- Lantai kerja t = 5 cm m3 2.05 741,200.00 1,519,460.00
- Beton K-250 m3 16.40 959,700.00 15,739,080.00
- Pembesian kg 2,841.05 12,500.00 35,513,087.25
- Bekisting m2 164.00 95,500.00 15,662,000.00
2 Sloof type S2 20/30 cm
- Galian tanah m3 0.66 24,100.00 15,906.00
- Pasir urug t = 5 cm m3 0.06 111,600.00 6,138.00
- Lantai kerja t = 5 cm m3 0.06 741,200.00 40,766.00
- Beton K-250 m3 0.33 959,700.00 316,701.00
- Pembesian kg 45.49 12,500.00 568,645.00
- Bekisting m2 3.30 95,500.00 315,150.00
3 Kolom K1 20X40 cm
- Beton K-250 m3 6.34 959,700.00 6,080,659.20
- Pembesian kg 1,513.87 12,500.00 18,923,344.00
- Bekisting m2 26.40 93,400.00 2,465,760.00
4 Kolom K3 25x25 cm
- Beton K-250 m3 0.50 959,700.00 479,850.00
- Pembesian kg 352.58 12,500.00 4,407,312.00
- Bekisting m2 8.00 93,400.00 747,200.00
5 Kolom KP 15/15 cm
- Beton 1:2:3 m3 0.57 859,200.00 487,166.40
- Pembesian kg 95.21 12,500.00 1,190,070.00
- Bekisting m2 7.56 93,400.00 706,104.00
6 Balok B1 25/50 cm
- Beton K-250 m3 1.75 959,700.00 1,679,475.00
- Pembesian kg 264.96 12,500.00 3,311,998.00
- Bekisting m2 17.50 167,200.00 2,926,000.00
7 Balok B2 20/40 cm
- Beton K-250 m3 11.48 959,700.00 11,017,356.00
- Pembesian kg 1,329.55 12,500.00 16,619,388.00
- Bekisting m2 143.50 167,200.00 23,993,200.00
Page 9 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
8 Balok B3 20/40 cm
- Beton K-250 m3 2.52 959,700.00 2,418,444.00
- Pembesian kg 331.60 12,500.00 4,145,011.50
- Bekisting m2 31.50 167,200.00 5,266,800.00
9 Balok B4 20/40 cm
- Beton K-250 m3 2.88 959,700.00 2,763,936.00
- Pembesian kg 425.60 12,500.00 5,319,990.00
- Bekisting m2 36.00 167,200.00 6,019,200.00
10 Listplank beton (LP) 10/70 cm
- Beton K-250 m3 5.43 959,700.00 5,213,090.40
- Pembesian kg 733.45 12,500.00 9,168,157.25
- Bekisting m2 116.40 167,200.00 19,462,080.00
11 Plat lantai tebal 12 cm -
- Beton K-250 m3 27.13 959,700.00 26,038,580.40
- Pembesian kg 3,348.09 12,500.00 41,851,110.00
- Bekisting m2 226.10 183,060.00 41,389,866.00
12 Plat kanopi tebal 10 cm -
- Beton K-250 m3 7.56 959,700.00 7,255,332.00
- Pembesian kg 1,119.48 12,500.00 13,993,560.00
- Bekisting m2 75.60 183,060.00 13,839,336.00
13 Balok lantai diatas kusen 12/12 cm -
- Beton 1:2:3 m3 0.91 859,200.00 779,466.24
- Pembesian kg 199.03 12,500.00 2,487,909.38
- Bekisting m2 15.12 167,200.00 2,528,064.00
E PEKERJAAN LANTAI/KERAMIK
1 Urugan pasir, tebal : 5 cm m3 12.60 111,600.00 1,406,160.00
2 Lantai kerja, tebal : 5 cm m3 12.60 741,200.00 9,339,120.00
3 Keramik lantai homogeneous 60 x 60 cm m2 220.50 147,300.00 32,479,650.00
4 Keramik lantai 20 x 20 cm (pada kamar mandi) m2 31.50 88,400.00 2,784,600.00
5 Keramik dinding 20 x 25 cm tinggi = 1,75 m m2 58.45 117,990.00 6,896,515.50
6 Plint keramik 10 x 60 cm m1 128.00 24,550.00 3,142,400.00
7 Keramik lantai 30 x 30 cm (kantin + dapur) m2 31.50 93,150.00 2,934,225.00
8 Lantai rabat beton keliling bangunan tebal 10 cm m3 4.20 741,200.00 3,113,040.00
G PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 173.25 73,600.00 12,751,200.00
2 List Plafond cornice gypsum m' 170.00 23,500.00 3,995,000.00
Page 10 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
H PEKERJAAN PENGECATAN
1 Cat dinding m2 1,019.60 23,900.00 24,368,320.50
2 Cat plafond m2 285.10 15,300.00 4,362,030.00
3 Cat listplank beton m2 155.40 23,900.00 3,714,060.00
I PEKERJAAN TANGGA
1 Keramik lantai 30 x 30 cm (kantin dan koperasi) m2 31.50 93,150.00 2,934,225.00
2 Pekerjaan tangga selasar ( 1 tangga ) -
- Pasangan bata (1:4) m2 0.90 73,300.00 65,970.00
- Plesteran (1:4) + acian halus termasuk lantai tangga m2 2.25 24,700.00 55,575.00
- Lantai rabat beton tebal 8 cm m3 0.20 741,200.00 146,757.60
- Grill besi lebar 20 cm ( finhising cat ) m' 4.50 150,000.00 675,000.00
J PEKERJAAN PANTRY
1 Meja beton, camp. 1 : 2 : 3 m3 0.14 859,200.00 119,600.64
2 Penulangan kg 8.08 12,500.00 101,033.75
3 Bekisting m2 3.00 165,600.00 496,800.00
4 Kitchen zink unit 1.00 350,000.00 350,000.00
5 Kran Kitchen zink unit 1.00 100,000.00 100,000.00
K PEKERJAAN PANGGUNG
1 RoolLag bata m' 15.48 -
2 Tanah urug m3 1.95 -
3 Pasir urug t = 5 cm m3 0.49 -
4 Lantai kerja, 5 cm m3 0.49 -
Page 11 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
Page 12 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
BLOK A
A PEKERJAAN BETON
1 Kolom K1 (25/40)
- Beton K-250 m3 7.56 959,700.00 7,255,332.00
- Pembesian kg 1,464.96 12,500.00 18,312,042.00
- Bekisting m2 98.28 165,600.00 16,275,168.00
2 Kolom K3 (25/25)
- Beton K-250 m3 1.80 959,700.00 1,727,460.00
- Pembesian kg 310.57 12,500.00 3,882,120.00
- Bekisting m2 28.80 165,600.00 4,769,280.00
3 Balok B1 (25/50)
- Beton K-250 m3 2.63 959,700.00 2,519,212.50
- Pembesian kg 390.94 12,500.00 4,886,706.00
- Bekisting m2 26.25 167,200.00 4,389,000.00
4 Balok B2 (20/40)
- Beton K-250 m3 10.24 959,700.00 9,827,328.00
- Pembesian kg 1,307.15 12,500.00 16,339,412.00
- Bekisting m2 128.00 167,200.00 21,401,600.00
5 Balok B3 (20/40)
- Beton K-250 m3 2.16 959,700.00 2,072,952.00
- Pembesian kg 405.04 12,500.00 5,062,991.50
- Bekisting m2 27.00 167,200.00 4,514,400.00
6 Balok B4 20/40 cm
- Beton K-250 m3 2.72 959,700.00 2,610,384.00
- Pembesian kg 632.79 12,500.00 7,909,875.00
- Bekisting m2 34.00 167,200.00 5,684,800.00
7 Plat lantai 3 tebal 12 cm
- Plat Beton K 250 m3 30.12 959,700.00 28,906,164.00
- Pembesian kg 3,716.81 12,500.00 46,460,100.00
- Bekisting m2 251.00 183,060.00 45,948,060.00
8 Plat kanopi tebal 10 cm -
- Beton K-250 m3 7.30 959,700.00 7,005,810.00
- Pembesian kg 1,080.98 12,500.00 13,512,300.00
- Bekisting m2 73.00 183,060.00 13,363,380.00
9 Balok latei (12/12)
- Beton 1 : 2 : 3 m3 0.85 859,200.00 729,976.32
- Pembesian kg 186.40 12,500.00 2,329,946.88
- Bekisting m2 14.16 95,500.00 1,352,280.00
10 Plate tangga + balok bordes + bordes (tangga tipe 2)
- Beton K-250 m3 4.47 959,700.00 4,287,219.83
- Pembesian kg 781.77 12,500.00 9,772,109.38
- Bekisting m2 40.15 183,060.00 7,349,401.35
11 Listplank ( 10/70 )
- Beton K-250 m3 5.39 859,200.00 4,631,088.00
Page 13
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
C PEKERJAAN PANGGUNG
1 Rolaag bata m' 11.50 16,200.00 186,300.00
2 Tanah urug m3 1.41 11,800.00 16,593.75
3 Pasir urug t = 5 cm m3 0.56 111,600.00 62,775.00
4 Lantai kerja, 2.5 cm m3 0.28 741,200.00 208,462.50
5 Keramik lantai homogeneous 60 x 60 cm m2 14.55 147,300.00 2,143,215.00
D PEKERJAAN LANTAI/KERAMIK
1 Keramik lantai homogeneous 60 x 60 cm m2 272.20 147,300.00 40,095,060.00
2 Plint keramik 10 x 60 cm m1 122.80 43,800.00 5,378,640.00
F PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 189.00 73,600.00 13,910,400.00
2 List Plafond cornice gypsum m' 127.00 23,500.00 2,984,500.00
3 Plafond GRC tebal 3,5 mm m2 69.20 75,000.00 5,190,000.00
G PEKERJAAN PENGECATAN
1 Cat pada dinding m2 698.35 23,900.00 16,690,541.10
2 Cat pada plafond m2 258.20 15,300.00 3,950,460.00
3 Cat listplank beton m2 153.30 23,900.00 3,663,870.00
H PEKERJAAN TANGGA
1 Railing tangga utama m' 9.00 700,000.00 6,300,000.00
2 Keramik tangga utama 30 x 30 cm unpolish ( termasuk bordes ) m2 19.00 93,150.00 1,769,850.00
I PEKERJAAN SANITAIR
1 Pasang pipa air hujan ( talang ) PVC 3 inch + acsesoris m1 50.00 74,800.00 3,740,000.00
Page 14
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
BLOK B
A PEKERJAAN BETON
1 Kolom K1 25X40 cm
- Beton K-250 m3 8.64 959,700.00 8,291,808.00
- Pembesian kg 1,674.24 12,500.00 20,928,048.00
- Bekisting m2 31.20 165,600.00 5,166,720.00
2 Kolom K3 25x25 cm
- Beton K-250 m3 0.56 959,700.00 539,831.25
- Pembesian kg 396.66 12,500.00 4,958,226.00
- Bekisting m2 9.00 165,600.00 1,490,400.00
3 Kolom KP 15/15 cm
- Beton 1:2:3 m3 0.41 859,200.00 347,976.00
- Pembesian kg 75.90 12,500.00 948,770.00
- Bekisting m2 5.40 165,600.00 894,240.00
4 Balok B1 25/50 cm
- Beton K-250 m3 2.63 959,700.00 2,519,212.50
- Pembesian kg 390.94 12,500.00 4,886,706.00
- Bekisting m2 26.25 167,200.00 4,389,000.00
5 Balok B2 20/40 cm
- Beton K-250 m3 12.68 959,700.00 12,168,996.00
- Pembesian kg 1,714.94 12,500.00 21,436,729.00
- Bekisting m2 158.50 167,200.00 26,501,200.00
6 Balok B3 20/40 cm
- Beton K-250 m3 2.52 959,700.00 2,418,444.00
- Pembesian kg 352.77 12,500.00 4,409,661.50
- Bekisting m2 31.50 167,200.00 5,266,800.00
7 Balok B4 20/40 cm
- Beton K-250 m3 2.96 959,700.00 2,840,712.00
- Pembesian kg 437.42 12,500.00 5,467,767.50
- Bekisting m2 37.00 167,200.00 6,186,400.00
9 Balok B5 15/30 cm
- Beton K-250 m3 0.15 959,700.00 140,356.13
- Pembesian kg 17.27 12,500.00 215,869.06
- Bekisting m2 2.44 167,200.00 408,553.20
8 Plat lantai tebal 12 cm -
- Beton K-250 m3 35.10 959,700.00 33,685,470.00
- Pembesian kg 4,331.34 12,500.00 54,141,750.00
- Bekisting m2 292.50 183,060.00 53,545,050.00
9 Plat kanopi tebal 10 cm -
- Beton K-250 m3 8.12 959,700.00 7,792,764.00
- Pembesian kg 1,202.41 12,500.00 15,030,120.00
- Bekisting m2 81.20 183,060.00 14,864,472.00
10 Balok latei 12/12 cm
- Beton 1 : 2 : 3 m3 0.91 859,200.00 779,466.24
- Pembesian kg 199.03 12,500.00 2,487,909.38
- Bekisting m2 15.12 167,200.00 2,528,064.00
11 Plat tangga + bordes + balok bordes (type 1)
- Beton K-250 m3 4.85 959,700.00 4,658,383.80
Page 15
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
C PEKERJAAN PANGGUNG
1 Rolaag bata m' 11.50 16,200.00 186,300.00
2 Tanah urug m3 1.41 11,800.00 16,593.75
3 Pasir urug t = 5 cm m3 0.56 111,600.00 62,775.00
4 Lantai kerja, 5 cm m3 0.56 741,200.00 416,925.00
5 Keramik lantai homogeneous 60 x 60 cm m2 14.55 147,300.00 2,143,215.00
D PEKERJAAN LANTAI/KERAMIK
1 Keramik lantai homogeneous 60 x 60 cm m2 202.70 147,300.00 29,857,710.00
2 Keramik lantai 20 x 20 cm (pada kamar mandi) m2 31.50 88,400.00 2,784,600.00
3 Keramik dinding 20 x 25 cm tinggi = 1,75 m m2 58.45 117,990.00 6,896,515.50
4 Plint keramik 10 x 60 cm m1 198.90 43,800.00 8,711,820.00
F PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 315.00 73,600.00 23,184,000.00
2 List Plafond cornice gypsum m' 260.00 23,500.00 6,110,000.00
3 Plafond GRC tebal 3,5 mm m2 171.00 75,000.00 12,825,000.00
G PEKERJAAN PENGECATAN
1 Cat pada dinding m2 1,144.20 23,900.00 27,346,399.12
2 Cat pada plafond m2 486.00 15,300.00 7,435,800.00
3 Cat listplank beton m2 127.50 23,900.00 3,047,250.00
Page 16
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
H PEKERJAAN TANGGA
1 Railing tangga utama m' 9.00 700,000.00 6,300,000.00
2 Keramik tangga utama 30 x 30 cm unpolish ( termasuk bordes ) m2 34.75 93,150.00 3,236,962.50
BLOK C
A PEKERJAAN BETON
1 Kolom K1 25X40 cm
- Beton K-250 m3 8.64 959,700.00 8,291,808.00
- Pembesian kg 1,607.58 12,500.00 20,094,756.00
- Bekisting m2 31.20 165,600.00 5,166,720.00
2 Kolom K3 25x25 cm
- Beton K-250 m3 0.56 959,700.00 539,831.25
- Pembesian kg 396.66 12,500.00 4,958,226.00
- Bekisting m2 9.00 165,600.00 1,490,400.00
3 Kolom KP 15/15 cm
- Beton 1:2:3 m3 0.49 859,200.00 417,571.20
- Pembesian kg 176.81 12,500.00 2,210,130.00
- Bekisting m2 6.48 165,600.00 1,073,088.00
4 Balok B1 25/50 cm
- Beton K-250 m3 1.75 959,700.00 1,679,475.00
- Pembesian kg 264.96 12,500.00 3,311,998.00
- Bekisting m2 17.50 167,200.00 2,926,000.00
5 Balok B2 20/40 cm
- Beton K-250 m3 11.48 959,700.00 11,017,356.00
- Pembesian kg 1,329.55 12,500.00 16,619,388.00
- Bekisting m2 143.50 167,200.00 23,993,200.00
6 Balok B3 20/40 cm
- Beton K-250 m3 2.52 959,700.00 2,418,444.00
- Pembesian kg 331.60 12,500.00 4,145,011.50
- Bekisting m2 31.50 167,200.00 5,266,800.00
7 Balok B4 20/40 cm
Page 17
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
C PEKERJAAN PANGGUNG
1 Rolaag bata m' 11.50 16,200.00 186,300.00
2 Tanah urug m3 1.41 11,800.00 16,593.75
3 Pasir urug t = 5 cm m3 0.56 111,600.00 62,775.00
4 Lantai kerja, 5 cm m3 0.56 741,200.00 416,925.00
5 Keramik lantai homogeneous 60 x 60 cm m2 14.55 147,300.00 2,143,215.00
D PEKERJAAN LANTAI/KERAMIK
1 Keramik lantai homogeneous 60 x 60 cm m2 238.93 147,300.00 35,193,652.50
2 Keramik lantai 20 x 20 cm (pada kamar mandi) m2 38.03 88,400.00 3,361,410.00
3 Keramik dinding 20 x 25 cm tinggi = 1,75 m m2 58.45 117,990.00 6,896,515.50
4 Plint keramik 10 x 60 cm m1 132.00 43,800.00 5,781,600.00
Page 18
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
F PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 189.00 73,600.00 13,910,400.00
2 List Plafond cornice gypsum m' 150.50 23,500.00 3,536,750.00
3 Plafond GRC tebal 3,5 mm m2 102.50 75,000.00 7,687,500.00
G PEKERJAAN PENGECATAN
1 Cat dinding m2 1,109.16 23,900.00 26,508,924.00
2 Cat plafond m2 291.50 15,300.00 4,459,950.00
3 Cat listplank beton m2 172.20 23,900.00 4,115,580.00
H PEKERJAAN TANGGA
1 Railing tangga utama m' 8.40 450,000.00 3,780,000.00
2 Keramik tangga utama 30 x 30 cm unpolish ( termasuk bordes ) m2 33.00 93,150.00 3,073,950.00
Page 19
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
BLOK A
A PEKERJAAN BETON
1 Kolom K2 25/40 cm
- Beton K-250 m3 9.25 959,700.00 8,877,225.00
- Pembesian kg 1,319.58 12,500.00 16,494,706.25
- Bekisting m2 120.25 165,600.00 19,913,400.00
2 Kolom K4 (25/25)
- Beton K-250 m3 2.31 959,700.00 2,219,306.25
- Pembesian kg 309.06 12,500.00 3,863,255.00
- Bekisting m2 37.00 165,600.00 6,127,200.00
3 Kolom KP ( Elv. + 08.00 )
- Beton 1:2:3 m3 0.09 859,200.00 73,461.60
- Pembesian kg 75.90 12,500.00 948,770.00
- Bekisting m2 1.14 165,600.00 188,784.00
4 Kolom K5 20/20 cm ( Elv. + 12.00 )
- Beton K-250 m3 0.28 959,700.00 268,716.00
- Pembesian kg 35.15 12,500.00 439,372.50
- Bekisting m2 5.60 165,600.00 927,360.00
5 Balok latai diatas kusen 12/12 cm
- Beton 1:2:3 m3 1.04 859,200.00 890,818.56
- Pembesian kg 240.26 12,500.00 3,003,300.00
- Bekisting m2 17.28 167,200.00 2,889,216.00
6 Ring balk RB1 20/30 cm ( Elv. + 12.00 )
- Beton K-250 m3 3.27 959,700.00 3,138,219.00
- Pembesian kg 432.61 12,500.00 5,407,657.50
- Bekisting m2 42.00 167,200.00 7,022,400.00
7 Ring balk RB2 20/30 cm ( Elv. + 12.00 )
- Beton K-250 m3 5.64 959,700.00 5,412,708.00
- Pembesian kg 858.05 12,500.00 10,725,682.00
- Bekisting m2 75.20 167,200.00 12,573,440.00
8 Ring balk RB3 15/20 cm ( Elv. + 12.00 )
- Beton K-250 m3 2.04 959,700.00 1,957,788.00
- Pembesian kg 376.63 12,500.00 4,707,929.00
- Bekisting m2 27.20 167,200.00 4,547,840.00
9 Ring balk RB3 15/20 cm ( Elv. + 12.50 )
- Beton K-250 m3 2.94 959,700.00 2,821,518.00
- Pembesian kg 542.80 12,500.00 6,784,956.50
- Bekisting m2 39.20 167,200.00 6,554,240.00
10 Balok listplank beton LP 10/70 cm
- Beton K-250 m3 6.86 959,700.00 6,583,542.00
- Pembesian kg 926.03 12,500.00 11,575,382.75
- Bekisting m2 147.00 167,200.00 24,578,400.00
11 Plat talang beton tebal : 10 cm
- Beton K-250 m3 13.80 959,700.00 13,243,860.00
- Pembesian kg 2,043.50 12,500.00 25,543,800.00
- Bekisting m2 138.00 183,060.00 25,262,280.00
Page 20 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
D PEKERJAAN LANTAI/KERAMIK
1 Keramik lantai homogeneous 60 x 60 cm m2 317.10 147,300.00 46,708,830.00
2 Plint keramik 10 x 60 cm m1 160.30 43,800.00 7,021,140.00
F PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 252.00 73,600.00 18,547,200.00
2 List Plafond cornice gypsum m' 154.50 23,500.00 3,630,750.00
3 Plafond GRC tebal 3,5 mm m2 116.20 75,000.00 8,715,000.00
G PEKERJAAN PENGECATAN
1 Cat dinding m2 1,091.62 23,900.00 26,089,646.30
2 Cat plafond m2 368.20 15,300.00 5,633,460.00
3 Cat listplank beton m2 247.00 23,900.00 5,903,300.00
4 Cat listplank tekstur kayu lebar 20 cm m2 18.20 23,900.00 434,980.00
Page 21 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
Page 22 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
C PEKERJAAN PANGGUNG
1 Rolaag bata m' 17.50 16,200.00 283,500.00
2 Tanah urug m3 2.34 11,800.00 27,656.25
3 Pasir urug t = 5 cm m3 0.94 111,600.00 104,625.00
4 Lantai kerja, 5 cm m3 0.94 741,200.00 694,875.00
5 Keramik lantai homogeneous 60 x 60 cm m2 24.25 147,300.00 3,572,025.00
D PEKERJAAN LANTAI/KERAMIK
1 Keramik lantai homogeneous 60 x 60 cm m2 202.70 147,300.00 29,857,710.00
2 Keramik lantai 20 x 20 cm (pada kamar mandi) m2 31.50 88,400.00 2,784,600.00
3 Keramik dinding 20 x 25 cm tinggi = 1,75 m m2 58.45 117,990.00 6,896,515.50
4 Plint keramik 10 x 60 cm m1 198.90 43,800.00 8,711,820.00
F PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 346.50 73,600.00 25,502,400.00
2 List Plafond cornice gypsum m' 274.00 23,500.00 6,439,000.00
3 Plafond GRC tebal 3,5 mm m2 171.00 75,000.00 12,825,000.00
G PEKERJAAN PENGECATAN
1 Cat dinding m2 1,480.23 23,900.00 35,377,494.61
2 Cat pada plafond m2 517.50 15,300.00 7,917,750.00
3 Cat listplank beton m2 279.50 23,900.00 6,680,050.00
4 Cat listplank tekstur kayu lebar 20 cm m2 22.19 23,900.00 530,245.40
Page 23 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
BLOK C
A PEKERJAAN BETON
1 Kolom K2 25/40 cm
- Beton K-250 m3 8.51 959,700.00 8,167,047.00
- Pembesian kg 1,214.01 12,500.00 15,175,129.75
- Bekisting m2 110.63 165,600.00 18,320,328.00
2 Kolom K4 (25/25)
- Beton K-250 m3 2.08 959,700.00 1,997,375.63
- Pembesian kg 278.15 12,500.00 3,476,929.50
- Bekisting m2 32.40 165,600.00 5,365,440.00
3 Kolom KP ( Elv. + 08.00 )
- Beton 1:2:3 m3 0.60 859,200.00 514,231.20
- Pembesian kg 272.02 12,500.00 3,400,200.00
- Bekisting m2 7.77 165,600.00 1,286,712.00
4 Kolom K5 20/20 cm ( Elv. + 12.00 )
- Beton K-250 m3 0.28 959,700.00 268,716.00
- Pembesian kg 35.15 12,500.00 439,372.50
- Bekisting m2 5.60 165,600.00 927,360.00
5 Kolom K6 20/20 cm ( Elv. + 12.00 )
- Beton K-250 m3 0.24 959,700.00 230,328.00
- Pembesian kg 30.13 12,500.00 376,605.00
- Bekisting m2 4.80 165,600.00 794,880.00
6 Kolom K6 20/20 cm ( Elv. + 13.50 )
- Beton K-250 m3 0.24 959,700.00 230,328.00
- Pembesian kg 30.13 12,500.00 376,605.00
Page 24 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
C PEKERJAAN PANGGUNG
1 Rolaag bata m' 5.50 16,200.00 89,100.00
2 Tanah urug m3 0.47 11,800.00 5,531.25
3 Pasir urug t = 5 cm m3 0.19 111,600.00 20,925.00
4 Lantai kerja, 5 cm m3 0.19 741,200.00 138,975.00
5 Keramik lantai homogeneous 60 x 60 cm m2 4.85 147,300.00 714,405.00
D PEKERJAAN LANTAI/KERAMIK
1 Keramik lantai homogeneous 60 x 60 cm m2 248.63 147,300.00 36,622,462.50
2 Keramik lantai 20 x 20 cm (pada kamar mandi) m2 38.03 88,400.00 3,361,410.00
3 Keramik dinding 20 x 25 cm tinggi = 1,75 m m2 58.45 117,990.00 6,896,515.50
4 Plint keramik 10 x 60 cm m1 127.50 43,800.00 5,584,500.00
Page 25 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
F PEKERJAAN PLAFOND
1 Gypsum t=9 mm rangka eka furing m2 189.00 73,600.00 13,910,400.00
2 List Plafond cornice gypsum m' 172.50 23,500.00 4,053,750.00
3 Plafond GRC tebal 3,5 mm m2 150.50 75,000.00 11,287,500.00
G PEKERJAAN PENGECATAN
1 Cat dinding m2 960.42 23,900.00 22,954,028.44
2 Cat pada plafond m2 339.50 15,300.00 5,194,350.00
3 Cat listplank beton m2 213.20 23,900.00 5,095,480.00
4 Cat listplank tekstur kayu lebar 20 cm m2 16.40 23,900.00 391,960.00
Page 26 of 28
RENCANA ANGGARAN BIAYA
( ENGINEER ESTIMATE )
V PEKERJAAN EKSTERNAL
Page 27 of 28
No Sekolah Luas Atap satuan
1 SDN 18 Tembesi 547.81 m2
2 SMPN Kec. Batam Kota 568.98 m2
3 SDN Lanjutan Sei Pelunggut 931.08 m2
4 SDN Kec. Sei Beduk 444.75 m2
5 SMPN Dapur 12 570 m2
TOTAL 3062.62 m2