PERHITUNGAN VOLUME

PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III


LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :

430

220 T. WUDHU
EL - 0.150
77 77 207 E

90
POMPA
D

185
45

80
335 315 45

325
58
C
MUSHOLLAH
EL ± 0.000

AULA

345
EL - 0.100

325
A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 1
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

II.1 Lantai 1
1 Pasangan batu bata ( 1 Pc : 5 Pasir ) 0.60 4.00 1.00 2.40 M2
2.20 4.00 1.00 8.80 M2
0.77 4.00 2.00 6.16 M2
2.07 4.00 1.00 8.28 M2
3.35 4.00 1.00 13.40 M2
0.80 4.00 2.00 6.40 M2
3.15 4.00 1.00 12.60 M2
0.45 4.00 1.00 1.80 M2
0.58 2.50 1.00 1.45 M2
4.30 4.00 1.00 17.20 M2
JUMLAH 78.49 M2

2 Plesteran dinding ( 1 Pc : 5 Pasir ) 78.49 2.00 156.98 M2


LUAS PLESTERAN 156.98 M2

3 Kolom Praktis 4.00 10.00 40.00 M1

4 Acian dinding 156.98 1.00 156.98 M2


LUAS ACIAN 156.98 M2
No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

7 Kolom H. BEAM 250x250x9x14 mm di bungkus ACP jumlah sisi jumlah tiang


- ACP 0.25 3.50 4.00 9.00 31.50 M2
0.07 3.50 4.00 9.00 8.82 M2
0.25 3.50 2.00 1.00 1.75 M2
0.07 3.50 2.00 1.00 0.49 M2
0.05 3.50 1.00 1.00 0.18 M2
0.06 3.50 1.00 1.00 0.22 M2
0.25 3.50 2.00 1.00 1.75 M2
0.07 3.50 2.00 1.00 0.49 M2
0.05 3.50 1.00 1.00 0.18 M2
0.13 3.50 1.00 1.00 0.44 M2
0.25 3.65 4.00 3.00 10.95 M2
0.07 3.65 4.00 3.00 3.07 M2
JUMLAH 59.83 M2

- Rangka Hollow
3.50 8.00 9.00 252.00 M1
3.50 4.00 1.00 14.00 M1
3.50 5.00 1.00 17.50 M1
3.65 8.00 3.00 87.60 M1
JUMLAH 371.10 M1

8 Balok H.BEAM dibungkus ACP


- ACP 1.16 2.20 1.00 2.54 M2
1.16 4.15 1.00 4.79 M2
1.16 5.10 1.00 5.89 M2
1.16 2.95 1.00 3.41 M2
1.16 3.50 1.00 4.04 M2
JUMLAH 20.67 M2

- Rangka Hollow 2.20 2.00 1.00 4.40 M1


12.35 2.00 1.00 24.70 M1
4.15 2.00 1.00 8.30 M1
7.20 2.00 1.00 14.40 M1
5.10 2.00 1.00 10.20 M1
12.13 2.00 1.00 24.25 M1
2.95 2.00 1.00 5.90 M1
6.90 2.00 1.00 13.80 M1
3.50 2.00 1.00 7.00 M1
JUMLAH 112.95 M1

9 Pekerjaan Ornamen Musholla - ACP + Cermin + Cutting MDF


- ACP 0.25 3.90 2.00 2.00 3.90 M2
0.45 3.90 1.00 2.00 3.51 M2
JUMLAH 3.05 0.90 1.00 2.75 M2
10.16 M2

- Rangka Hollow 3.90 8.00 31.20 M1


3.05 2.00 6.10 M1
0.90 3.00 2.70 M1
JUMLAH 40.00 M1
I PEKERJAAN PERSIAPAN
II PEKERJAAN PASANGAN DAN PLESTERAN
III PEKERJAAN KERAMIK LANTAI
IV PEKERJAAN PLAFOND
V PEKERJAAN PENGECATAN
VI PEKERJAAN KUZEN PINTU DAN JENDELA
VII PEKERJAAN RALLING
VIII PEKERJAAN SANITAIR / FIXTURES
IX PEKERJAAN ELEKTRIKAL DAN MEKANIKAL
X PEKERJAAN SISTEM KEBAKARAN
XI PEKERJAAN LANDSCAPE
XII PEKERJAAN PARTISI
XIII PEKERJAAN AREA PARKIR
luas acp h-beam 25.25 luas acp h-beam 25.25
0.25 4 3.5 3.5 0.25 2 3.5
0.071 4 3.5 0.994 0.071 2 3.5
4.494

jumlah tiang jumlah tiang


9 40.446 3

ornamen
0.25 3.9 1.95
0.45 3.9 1.755
3.705
7.41 m2

8 3.9 31.2 m1

tambahan urinoir 2 unit volume


kolom 4 buah tinggi 4]kolom tulangan d12,s8
25.15 2.00 0.075 0.3 m3

kolom 5 buah tinggi 5kolom


15.15 2.00 0.045 0.225 m3
tul. 12
9.68
atap dak urinoir wiremesh m8 volume
tebal 12 cm 0.91 m3
panjang 2.95 m 42.96758
lebar 2.58 m

berat wiremesh m8 = 5.45 /m2 berat besi tulangan


luas dak 12 77.34165 kg
7.611 m2 8 27.01158 kg
41.47995 kg

kaca lt.1
22 bovenlight ukuran kaca
20 dg ukuran 50.20 50 20 46 16 0.07 m2 1.47
1 dg ukuran 60.20 60 20 56 16 0.09 m2
1 dg ukuran 55.20 55 20 51 16 0.08 m2
kebutuhan kaca lt.1 1.64

7 jendela dg keliling
8.28
57.96 m1

2 jendela dg keliling
6.8 6050000
13.6 m1
71.56 84500 6046820
1.75
0.497
2.247

6.741 m2 ACP

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

kolom 25.15 II
tulangan 12 sgkg 8 jarak 15cm pjg sgkg 1
kolom 25.15 14 66 2
2.42 9.68 m' 0.66
38.72 m' 9.24 m' III
34.37407 kg 36.96 m' 1
14.58294 kg

48.4 m'
kolom 15.15
sgkg 8 jarak 15 pjg
kg 14 0.45 ITEM PEKERJAAN
6.3 m' SATUAN PEMBAYAR
31.5 m'
12.42864 kg
NO

I
1
2
3
m2 20 buah kaca dg ukuran
46 cm x 16 cm II
1 dg ukuran 56cm x 16cm 1
m2 2 dg ukuran 51cm x 16cm 2

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

2000 II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO
NO

I
1
2
3

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4

III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4

III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4
5

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3

II
1
2

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3
4

II
1
2
3
4
5

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO
NO

I
1
2

II
1
2

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR
NO

I
1
2
3

II
1
2
3
4

III
1

ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
1
2
3
4

II
1
2
3
4

III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR

NO

I
2
4

harga kabel nyy 4x16mm II


tahun 2020 samarinda 1
sesuai hspk 2
Rp 208,554.98 3
4

III
1
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Railing tangga hollow 40.40.0,4


SATUAN PEMBAYARAN : m1

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0359 165,000.00 5,923.50
TUKANG ORG/HARI 0.0358 150,000.00 5,370.00
PEKERJA ORG/HARI 0.1437 130,000.00 18,681.00

BAHAN
HOLLOW METAL FURING m 1.1000 29,166.67 32,083.33
SEKRUP kg 0.4785 26,000.00 12,441.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 74,998.83


OVERHEAD + PROFIT (15%) 11,249.83
HARGA SATUAN PEKERJAAN 86,248.66
HARGA SATUAN PEKERJAAN DIBULATKAN 86,248.00
ITEM PEKERJAAN : Railing tangga hollow 20.40.0,4
SATUAN PEMBAYARAN : m1

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0359 165,000.00 5,923.50
TUKANG ORG/HARI 0.0358 150,000.00 5,370.00
PEKERJA ORG/HARI 0.1437 130,000.00 18,681.00

BAHAN
HOLLOW METAL FURING m 1.1000 20,000.00 22,000.00
SEKRUP kg 0.4788 26,000.00 12,447.50

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 64,922.00


OVERHEAD + PROFIT (15%) 9,738.30
HARGA SATUAN PEKERJAAN 74,660.30
HARGA SATUAN PEKERJAAN DIBULATKAN 74,660.00

ITEM PEKERJAAN : pemasangan baja wf 150


SATUAN PEMBAYARAN : kg

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0060 165,000.00 990.00
TUKANG ORG/HARI 0.0600 150,000.00 9,000.00
PEKERJA ORG/HARI 0.0600 130,000.00 7,800.00

BAHAN
Baja Profil WF 150 kg 1.1000 21,238.10 23,361.90
Las kg 1.0000 2,500.00 2,500.00
Zincromate + cat finishing m2 0.0300 26,000.00 780.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 44,931.90


OVERHEAD + PROFIT (15%) 6,739.79
HARGA SATUAN PEKERJAAN 51,671.69
HARGA SATUAN PEKERJAAN DIBULATKAN 51,671.00

ITEM PEKERJAAN : -
SATUAN PEMBAYARAN : 0

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0350 165,000.00 5,775.00
TUKANG ORG/HARI 0.2500 150,000.00 37,500.00
PEKERJA ORG/HARI 0.7000 130,000.00 91,000.00

BAHAN
SEMEN kg 1.1400 1,400.00 1,596.00
SEMEN WARNA kg 0.5000 17,000.00 8,500.00
PASIR PASANG m3 0.0450 225,000.00 10,125.00
KERAMIK 20x20 buah 26.5000 2,320.00 61,480.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 216,476.00


OVERHEAD + PROFIT (15%) 32,471.40
HARGA SATUAN PEKERJAAN 248,947.40
HARGA SATUAN PEKERJAAN DIBULATKAN 248,947.00

ITEM PEKERJAAN : 1 unit kran dia. 1/2"


SATUAN PEMBAYARAN : unit

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.4000 150,000.00 60,000.00
PEKERJA ORG/HARI 0.0100 130,000.00 1,300.00

BAHAN
Kran buah 1.0000 45,000.00 45,000.00
Seal buah 0.0250 17,000.00 425.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 108,050.00


OVERHEAD + PROFIT (15%) 16,207.50
HARGA SATUAN PEKERJAAN 124,257.50
HARGA SATUAN PEKERJAAN DIBULATKAN 124,257.00

ITEM PEKERJAAN : 1 m2 lapisan peredam


SATUAN PEMBAYARAN : unit

HARGA TOTAL
URAIAN SATUAN KOEFISIEN
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0100 165,000.00 1,650.00
TUKANG ORG/HARI 0.8500 150,000.00 127,500.00
PEKERJA ORG/HARI 0.2500 130,000.00 32,500.00

BAHAN
glasswoll roll 1.3000 38,888.89 50,555.56
Seal buah 0.2500 17,000.00 4,250.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 216,955.56


OVERHEAD + PROFIT (15%) 32,543.33
HARGA SATUAN PEKERJAAN 249,498.89
HARGA SATUAN PEKERJAAN DIBULATKAN 249,498.00

ITEM PEKERJAAN : 1 unit urinoir


SATUAN PEMBAYARAN : unit

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0500 165,000.00 8,250.00
TUKANG ORG/HARI 0.2500 150,000.00 37,500.00
PEKERJA ORG/HARI 0.1250 130,000.00 16,250.00

BAHAN
Urinoir buah 1.0000 1,450,000.00 1,450,000.00
Semen kg 1.0000 1,400.00 1,400.00
Pasir Pasang m3 0.5000 155,000.00 77,500.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,591,400.00


OVERHEAD + PROFIT (15%) 238,710.00
HARGA SATUAN PEKERJAAN 1,830,110.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,830,110.00
ITEM PEKERJAAN : 1 buah floor drain
SATUAN PEMBAYARAN : unit

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.1000 150,000.00 15,000.00
PEKERJA ORG/HARI 0.0100 130,000.00 1,300.00

BAHAN
floor drain buah 1.0000 75,000.00 75,000.00
-

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 92,625.00


OVERHEAD + PROFIT (15%) 13,893.75
HARGA SATUAN PEKERJAAN 106,518.75
HARGA SATUAN PEKERJAAN DIBULATKAN 106,518.00

ITEM PEKERJAAN : 1 m3 Rabat Lantai


SATUAN PEMBAYARAN : m3

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0060 165,000.00 990.00
TUKANG ORG/HARI 0.6000 150,000.00 90,000.00
PEKERJA ORG/HARI 1.2000 130,000.00 156,000.00

BAHAN
Semen kg 230.0000 1,400.00 322,000.00
Pasir Beton m3 0.5370 400,000.00 214,800.00
Kerilkil m3 0.5710 550,000.00 314,050.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00
JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,098,340.00
OVERHEAD + PROFIT (15%) 164,751.00
HARGA SATUAN PEKERJAAN 1,263,091.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,263,091.00

ITEM PEKERJAAN : 1 set Pemasangan Pintu PVC Kamar Mandi


SATUAN PEMBAYARAN : set

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.0250 150,000.00 3,750.00
PEKERJA ORG/HARI 0.5000 130,000.00 65,000.00

BAHAN
Pintu PVC Kamar Mandi set 1.0000 195,000.00 195,000.00
-
-

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 265,075.00


OVERHEAD + PROFIT (15%) 39,761.25
HARGA SATUAN PEKERJAAN 304,836.25
HARGA SATUAN PEKERJAAN DIBULATKAN 304,836.00

ITEM PEKERJAAN : Pemasangan Tiang baja


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0100 165,000.00 1,650.00
TUKANG ORG/HARI 0.3550 150,000.00 53,250.00
PEKERJA ORG/HARI 0.1500 130,000.00 19,500.00

BAHAN
Tiang Baja m 6.8000 144,750.00 984,300.00
Las kg 1.0000 2,500.00 2,500.00
Plat Besi kg 1.8240 125,000.00 228,000.00
CAT BESI DASAR kg 0.4500 80,000.00 36,000.00
CAT BESI FINISHING kg 0.5000 80,000.00 40,000.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,365,700.00


OVERHEAD + PROFIT (15%) 204,855.00
HARGA SATUAN PEKERJAAN 1,570,555.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,570,555.00

ITEM PEKERJAAN : Saluran Urinoir


SATUAN PEMBAYARAN : M1

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.0400 150,000.00 6,000.00
PEKERJA ORG/HARI 0.6000 130,000.00 78,000.00

BAHAN
Cor Beton M3 0.0500 1,299,602.00 64,980.10

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 150,305.10


OVERHEAD + PROFIT (15%) 22,545.77
HARGA SATUAN PEKERJAAN 172,850.87
HARGA SATUAN PEKERJAAN DIBULATKAN 172,850.00

ITEM PEKERJAAN : 1 m2 Waterproofing dak


SATUAN PEMBAYARAN : m2

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0150 165,000.00 2,475.00
TUKANG ORG/HARI 0.0150 150,000.00 2,250.00
PEKERJA ORG/HARI 0.1600 130,000.00 20,800.00

BAHAN
waterproofing dumplix kg 0.4500 625,000.00 281,250.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 307,275.00


OVERHEAD + PROFIT (15%) 46,091.25
HARGA SATUAN PEKERJAAN 353,366.25
HARGA SATUAN PEKERJAAN DIBULATKAN 353,366.00

ITEM PEKERJAAN : 1 m2 pasangan Rangka Atap


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
MANDOR ORG/HARI 0.0450 165,000.00 7,425.00
KEPALA TUKANG ORG/HARI 0.3000 160,000.00 48,000.00
TUKANG ORG/HARI 0.7000 150,000.00 105,000.00
PEKERJA ORG/HARI 0.3500 130,000.00 45,500.00

BAHAN
Main Truss m1 2.8000 Err:509 Err:509
Roof Bottom R33-0.45 m1 5.1000 11,000.00 56,100.00
Self Drilling Screw 6x20mm (truss Screw) bh 25.0000 1,000.00 25,000.00
Self Drilling Screw 4x16mm(roof bottom screw) bh 35.0000 800.00 28,000.00
Dynabolt bh 25.0000 2,500.00 62,500.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT Err:509


OVERHEAD + PROFIT (15%) Err:509
HARGA SATUAN PEKERJAAN Err:509
HARGA SATUAN PEKERJAAN DIBULATKAN Err:509

ITEM PEKERJAAN : Instalasi Lampu Downlight


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
URAIAN SATUAN KOEFISIEN
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
TUKANG ORG/HARI 0.2470 150,000.00 37,050.00
PEKERJA ORG/HARI 0.2470 130,000.00 32,110.00

BAHAN
Downlight buah 1.0000 79,500.00 79,500.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 149,160.00


OVERHEAD + PROFIT (15%) 22,374.00
HARGA SATUAN PEKERJAAN 171,534.00
HARGA SATUAN PEKERJAAN DIBULATKAN 171,534.00

ITEM PEKERJAAN : Timbunan tanah bawah lantai


SATUAN PEMBAYARAN : m3

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
TUKANG ORG/HARI 0.2470 150,000.00 37,050.00
PEKERJA ORG/HARI 0.2470 130,000.00 32,110.00

BAHAN
Downlight buah 1.0000 - -

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 69,660.00


OVERHEAD + PROFIT (15%) 10,449.00
HARGA SATUAN PEKERJAAN 80,109.00
HARGA SATUAN PEKERJAAN DIBULATKAN 80,109.00

ITEM PEKERJAAN : PASANGAN GRILL


SATUAN PEMBAYARAN : M1
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
TUKANG ORG/HARI 0.2470 150,000.00 37,050.00
PEKERJA ORG/HARI 0.2470 130,000.00 32,110.00
KEPALA TUKANG ORG/HARI

BAHAN
BESI SIKU 40.40.4 KG 6.2830 15,833.00 99,478.74
BESI DIA. 16MM KG 6.3200 8,391.00 53,031.12
LAS kg 1.0000 26,000.00 26,000.00
Zinc chromate + cat finishing m2 0.0300 65,000.00 1,950.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 250,119.86


OVERHEAD + PROFIT (15%) 37,517.98
HARGA SATUAN PEKERJAAN 287,637.84
HARGA SATUAN PEKERJAAN DIBULATKAN 287,637.00

ITEM PEKERJAAN : PASANGAN atap multiroof


SATUAN PEMBAYARAN : m1

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
TUKANG ORG/HARI 0.2000 150,000.00 30,000.00
PEKERJA ORG/HARI 0.1000 130,000.00 13,000.00
KEPALA TUKANG ORG/HARI 0.0100 160,000.00 1,600.00
Mandor ORG/HARI 0.0100 165,000.00 1,650.00

BAHAN
Gentang Multiroof Lembar 1.1000 95,000.00 104,500.00
Paku KG 0.2000 18,000.00 3,600.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 154,850.00


OVERHEAD + PROFIT (15%) 23,227.50
HARGA SATUAN PEKERJAAN 178,077.50
HARGA SATUAN PEKERJAAN DIBULATKAN 178,077.00

ITEM PEKERJAAN : Pemasangan Kabel NYY 4 x 16


SATUAN PEMBAYARAN : m1

HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

TENAGA
PEKERJA ORG/HARI 0.1000 130,000.00 13,000.00
Mandor ORG/HARI 0.1000 165,000.00 16,500.00

BAHAN
KABEL NYY 4x16mm m1 1.0000 209,000.00 209,000.00

ALAT
ALAT BANTU LS 1.0000 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 239,000.00


OVERHEAD + PROFIT (15%) 35,850.00
HARGA SATUAN PEKERJAAN 274,850.00
HARGA SATUAN PEKERJAAN DIBULATKAN 274,850.00
1,400,004,000.00

harga satuan /6m


Rp 1,784,000.00
harga per m
Rp 297,333.33 perlu wf m
berat /12m 2.4 3 7.2
168 3.46 1 3.46
berat per m 1.3 1 1.3
14 5.11 1 5.11
1.65 1 1.65 kg
Rp 21,238.10 4 3 12
30.72 430.08
5.12
6

0.99648
0.2574
1.25388 m3

2 1
2320
0.0784 0.8624

2.9768 590000 198199.4


0.288
3.168

1 kg 48000
1.579008
6.316032

2.41666666666667 6.283333
95000
15833.3333333333
18.72
262.08

168
430.08
1m2
i tenaga
mandor 0.01 165,000.00 1,650.00
tukang 0.2 150,000.00 30,000.00
pekerja 0.15 130,000.00 19,500.00

ii bahan
Paving 25 6,500.00 162,500.00
pasir pasang 0.15 225,000.00 33,750.00

iii Alat
alat bantu 500.00
247,900.00

i tenaga
mandor 0.007 165,000.00 1,155.00
tukang 0.650 150,000.00 97,500.00
kepala tukang 0.066 160,000.00 10,492.80
pekerja 0.330 130,000.00 42,900.00

ii bahan
acp 1.1 800,000.00 880,000.00
hollow 4x4x1mm 1 22,000.00 22,000.00
bracket siku/stiffner 0.28 60,000.00 16,800.00
paku skrup 0.07 21,600.00 1,512.00
paku beton 0.2 21,600.00 4,320.00
sealant 0.25 25,000.00 6,250.00

iii Alat
stager 0.02 110000 2,200.00
lisstrik kerja 1 5000 5,000.00
alat bantu 1 500 500.00

1,090,629.80 Rp 1,080,730.00

i tenaga
mandor 0.007 165,000.00 1,155.00
tukang 0.0857 150,000.00 12,855.00
kepala tukang 160,000.00 -
pekerja 0.39 130,000.00 50,700.00

ii bahan
-
-
-
-
-
sealant 0.25 25,000.00 6,250.00

iii Alat
-
-
alat bantu 1 500 500.00

70,960.00
1 m2 calsiplank
i tenaga
mandor 0.07 165,000.00 11,550.00
tukang 0.35 150,000.00 52,500.00
kepala tukang 0.022 160,000.00 3,520.00
pekerja 0.11 130,000.00 14,300.00

ii bahan
kalsiplank 1.50 125,000.00 187,500.00
paku 0.115 21,600.00 2,484.00
Paku Skrup 0.1 21,600.00 2,160.00
-
-
sealant 0.25 -

iii Alat
-
-
alat bantu 1 500 500.00

274,014.00

i tenaga
mandor 0.007 165,000.00 1,155.00
tukang 0.650 150,000.00 97,500.00
kepala tukang 0.066 160,000.00 10,492.80
pekerja 0.330 130,000.00 42,900.00

ii bahan
acp 1.1 800,000.00 880,000.00
hollow 4x4x1mm 1 22,000.00 22,000.00
bracket siku/stiffner 0.28 60,000.00 16,800.00
paku skrup 0.07 21,600.00 1,512.00
paku beton 0.2 21,600.00 4,320.00
sealant 0.25 25,000.00 6,250.00
Kaca 1 125,000.00 125,000.00

iii Alat
stager 0.02 110000 2,200.00
lisstrik kerja 1 5000 5,000.00
alat bantu 1 500 500.00

1,210,129.80
WF 150 x 75 x 5 x 7 mm – 12 M

0.04
25

hollow 40 1 9 9
2.2 2 4.4
4.15 2 8.3
2.8 2 5.6
3.13 2 6.26
33.56

HOLLOW 20 0.03 12 0.36


9,899.80 0.12 12 1.44
0.74 12 8.88
0.8 12 9.6
0.84 14 11.76
0.82 14 11.48
1.17 14 16.38
0.6 14 8.4
68.3
M1
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

JUMLAH HARGA
NO URAIAN PEKERJAAN PEKERJAAN
(RP)
I PEKERJAAN PERSIAPAN 60,903,875.80
II PEKERJAAN PASANGAN DAN PLESTERAN 285,300,985.59
III PEKERJAAN KERAMIK LANTAI 174,508,652.38
IV PEKERJAAN PLAFOND 73,572,098.71
V PEKERJAAN PENGECATAN 49,275,309.44
VI PEKERJAAN KUZEN PINTU DAN JENDELA 160,484,502.39
VII PEKERJAAN RALLING 67,935,167.84
VIII PEKERJAAN SANITAIR / FIXTURES 13,449,556.52
IX PEKERJAAN ELEKTRIKAL DAN MEKANIKAL 67,259,468.00
X PEKERJAAN SISTEM KEBAKARAN 3,000,000.00
XI PEKERJAAN LANDSCAPE 36,004,714.11
XII PEKERJAAN PARTISI 141,352,429.88
XIII PEKERJAAN AREA PARKIR 139,684,246.37
(A) Jumlah Harga Pekerjaan 1,272,731,007.03
(B) Pajak Pertambahan Nilai (PPN) = 10% x (A) 127,273,100.70
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 1,400,004,107.73
(D) PEMBULATAN 1,400,004,000.00
Terbilang :

#NAME?

Nunukan, 03 Februari 2021


Dibuat;
CV. SANDRILLA PRATAMA

BAU SANTI
Direktur
DAFTAR KUANTITAS DAN HARGA
CHANGE CONTRACT ORDER ( CCO )
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

KONTRAK CHANGE CONTRACT ORDER


No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi ls 1.00 Rp. 2,200,000.00 Rp. 2,200,000.00 1.00 Rp 2,200,000.00 Rp 2,200,000.00 TETAP
2 Pembongkaran Bangunan Lama m2 8.82 Rp. 271,659.00 Rp. 2,396,032.38 - Rp - Rp - DIHILANGKAN
3 Gudang dan Barak Kerja m2 10.00 Rp. 2,108,815.00 Rp. 21,088,150.00 - Rp - Rp - DIHILANGKAN
4 Pengukuran Lokasi m2 49.40 Rp. 9,257.00 Rp. 457,295.80 49.40 Rp 9,257.00 Rp 457,295.80 TETAP
5 Alat dan keselamatan kerja ( K-3) ls 1.00 Rp. 21,370,000.00 Rp. 21,370,000.00 1.00 Rp 21,370,000.00 Rp 21,370,000.00 TETAP
6 Pembuatan papan nama proyek ls 1.00 Rp. 500,000.00 Rp. 500,000.00 1.00 Rp 500,000.00 Rp 500,000.00 TETAP
7 Listrik Kerja ls 1.00 Rp. 5,000,000.00 Rp. 5,000,000.00 1.00 Rp 5,000,000.00 Rp 5,000,000.00 TETAP
8 Air Kerja ls 1.00 Rp. 3,000,000.00 Rp. 3,000,000.00 1.00 Rp 3,000,000.00 Rp 3,000,000.00 TETAP
9 Pagar Lokasi m' 15.00 Rp. 472,943.00 Rp. 7,094,145.00 60.00 Rp 472,943.00 Rp 28,376,580.00 BERTAMBAH

Jumlah Harga Pekerjaan I (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 63,105,623.18 Rp 60,903,875.80

II PEKERJAAN PASANGAN DAN PLESTERAN


II.1 LANTAI 1
1 Pasangan batu bata ( 1 Pc : 5 Pasir ) m2 34.75 Rp. 236,596.00 Rp. 8,221,711.00 82.41 Rp 236,596.00 Rp 19,497,876.36 BERTAMBAH
2 Plesteran dinding ( 1 Pc : 5 Pasir ) m2 69.50 Rp. 61,196.00 Rp. 4,253,122.00 168.19 Rp 61,196.00 Rp 10,292,555.24 BERTAMBAH
3 Kolom Praktis m' 22.50 Rp. 110,156.00 Rp. 2,478,510.00 40.00 Rp 110,156.00 Rp 4,406,240.00 BERTAMBAH
4 Acian dinding m2 69.50 Rp. 44,340.00 Rp. 3,081,630.00 168.19 Rp 44,340.00 Rp 7,457,544.60 BERTAMBAH
5 Benangan m1 30.00 Rp. 26,976.00 Rp. 809,280.00 6.90 Rp 26,976.00 Rp 186,134.40 BERKURANG
6 Kolom H. BEAM 250x250x9x14 mm di bungkus beton Tul.Dia 8 mm m1 37.50 Rp. 532,531.00 Rp. 19,969,912.50 - Rp - Rp - DIHILANGKAN
7 Kolom H. BEAM 250x250x9x14 mm di bungkus beton m1 - - - 2.44 Rp 1,642,149.00 Rp 4,006,843.56 ITEM PEKERJAAN BARU
8 Kolom H. BEAM 250x250x9x14 mm di bungkus ACP m2 - - - 51.31 Rp 1,291,007.00 Rp 66,241,569.17 ITEM PEKERJAAN BARU
9 Balok H.BEAM dibungkus ACP m2 - - - 22.38 Rp 1,291,007.00 Rp 28,892,736.66 ITEM PEKERJAAN BARU
10 Pekerjaan Ornamen Musholla - ACP + Cermin + Cutting MDF m2 - - - 9.40 Rp 1,453,329.00 Rp 13,661,292.60 ITEM PEKERJAAN BARU
11 Balok Latei m1 - - - 1.90 Rp 262,162.00 Rp 498,107.80 ITEM PEKERJAAN BARU
12 Ringbalk m1 - - - 14.40 Rp 309,599.00 Rp 4,458,225.60 ITEM PEKERJAAN BARU
13 Rabat Lantai m3 - - - 12.10 Rp 1,263,091.00 Rp 15,283,401.10 ITEM PEKERJAAN BARU
14 Pengadaan dan Pemasangan Kaligrafi Mushalla LS - - - 1.00 Rp 4,953,832.00 Rp 4,953,832.00 ITEM PEKERJAAN BARU
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
II.2 LANTAI 3
1 Pasangan batu bata 1/2 bata ( 1 Pc : 5 Pasir ) m2 32.00 Rp. 236,596.00 Rp. 7,571,072.00 31.61 Rp 236,596.00 Rp 7,478,799.56 BERKURANG
2 Plesteran dinding ( 1 Pc : 5 Pasir ) m2 288.44 Rp. 61,196.00 Rp. 17,651,374.24 275.69 Rp 61,196.00 Rp 16,871,125.24 BERKURANG
3 Acian dinding m2 230.50 Rp. 44,340.00 Rp. 10,220,370.00 296.11 Rp 44,340.00 Rp 13,129,517.40 BERKURANG
4 Benangan m1 192.00 Rp. 26,976.00 Rp. 5,179,392.00 119.75 Rp 26,976.00 Rp 3,230,376.00 BERKURANG
5 Kolom H-Beam Kg - - - 168.00 Rp 53,017.00 Rp 8,906,856.00 ITEM PEKERJAAN BARU
6 Balok Iwf-150 Kg - - - 262.08 Rp 53,017.00 Rp 13,894,695.36 ITEM PEKERJAAN BARU
7 Beton m3 - - - 2.36 Rp 1,299,602.00 Rp 3,067,060.72 ITEM PEKERJAAN BARU
10 Rabat Lantai m3 - - - 1.12 Rp 1,263,091.00 Rp 1,414,661.92 ITEM PEKERJAAN BARU
11 Ringbalk Ruang Urinoir m1 - - - 9.80 Rp 309,599.00 Rp 3,034,070.20 ITEM PEKERJAAN BARU
12 Saluran Urinoir m1 - - - 2.80 Rp 172,850.00 Rp 483,980.00 ITEM PEKERJAAN BARU

II.3 LANTAI 2
1 Kolom H. BEAM 250x250x9x14 mm di bungkus ACP m2 - - - 16.80 Rp 1,291,007.00 Rp 21,688,917.60 ITEM PEKERJAAN BARU
2 Balok H.BEAM dibungkus ACP m2 - - - 9.50 Rp 1,291,007.00 Rp 12,264,566.50 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan II (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 79,436,373.74 Rp 285,300,985.59

III PEKERJAAN KERAMIK LANTAI


III.1 LANTAI 1
1 Lantai homogenius 60 cm x 60 cm( Polished) m2 45.33 Rp. 464,524.00 Rp. 21,056,872.92 81.23 Rp 464,524.00 Rp 37,733,284.52 BERTAMBAH
2 Keramik Dinding Ruang wudhu m2 - - - 9.64 Rp 464,524.00 Rp 4,478,011.36 ITEM PEKERJAAN BARU
3 Lantai Ruang Wudhu 40 x 60 m2 - - - 21.14 Rp 464,524.00 Rp 9,820,037.36 ITEM PEKERJAAN BARU
4 Plin Lantai m1 - - - 15.14 Rp 64,826.00 Rp 981,465.64 ITEM PEKERJAAN BARU
5 Urugan pasir bawah lantai 10 cm m3 - - - 9.10 Rp 267,173.00 Rp 2,431,274.30 ITEM PEKERJAAN BARU

III.2 LANTAI 2
1 Lantai Homogeneus tangga m2 15.60 Rp. 464,524.00 Rp. 7,246,574.40 15.93 Rp 464,524.00 Rp 7,399,867.32 BERTAMBAH
2 Plin tangga m1 - - - 16.20 Rp 64,826.00 Rp 1,050,181.20 ITEM PEKERJAAN BARU
3 Keramik Lantai Balkon m2 - - - 15.13 Rp 464,524.00 Rp 7,028,248.12 ITEM PEKERJAAN BARU

III.3 LANTAI 3
1 Lantai homogenius 60 cm x 60 cm( Polished) m2 159.21 Rp. 464,524.00 Rp. 73,956,866.04 179.60 Rp 464,524.00 Rp 83,428,510.40 BERTAMBAH
2 Plin keramik 10 x 60 cm m1 76.75 Rp. 64,826.00 Rp. 4,975,395.50 72.76 Rp 64,826.00 Rp 4,716,739.76 BERKURANG
3 Lapisan creed 3 cm - 7 cm m2 159.21 Rp. 57,454.00 Rp. 9,147,251.34 179.60 Rp 57,454.00 Rp 10,318,738.40 BERTAMBAH
4 Keramik lantai ruang Urinoir m2 - - - 8.33 Rp 312,335.00 Rp 2,601,750.55 ITEM PEKERJAAN BARU
5 Keramik Dinding ruang Urinoir m2 - - - 8.07 Rp 312,335.00 Rp 2,520,543.45 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan III (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 116,382,960.20 Rp 174,508,652.38
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
IV PEKERJAAN PLAFOND
IV.1 LANTAI 1
1 Plafond gypsum m2 106.88 Rp. 42,584.00 Rp. 4,551,377.92 118.61 Rp 42,584.00 Rp 5,050,888.24 BERTAMBAH
2 Rangka Plafond Hollow metal Furing m2 106.88 Rp. 143,234.00 Rp. 15,308,849.92 129.37 Rp 143,234.00 Rp 18,530,182.58 BERTAMBAH
3 List Plafond Gypsum m1 41.50 Rp. 58,735.00 Rp. 2,437,502.50 50.26 Rp 58,735.00 Rp 2,952,021.10 BERTAMBAH
4 Plafond gypsum Canopy m2 - - - 10.76 Rp 42,584.00 Rp 458,203.84 ITEM PEKERJAAN BARU

IV.2 LANTAI 3
1 Plafond gypsum m2 171.44 Rp. 42,584.00 Rp. 7,300,600.96 189.23 Rp 42,584.00 Rp 8,058,170.32 BERTAMBAH
2 Rangka Plafond Hollow metal Furing m2 171.44 Rp. 143,234.00 Rp. 24,556,036.96 189.23 Rp 143,234.00 Rp 27,104,169.82 BERTAMBAH
3 List Flapond Gypsum m1 57.98 Rp. 58,735.00 Rp. 3,405,455.30 120.72 Rp 58,735.00 Rp 7,090,489.20 BERTAMBAH

IV.3 LANTAI 2
1 Plafond Balkon m2 - - - 14.52 Rp 42,584.00 Rp 618,319.68 ITEM PEKERJAAN BARU
2 Rangka Plafond Hollow metal Furing m2 - - - 14.52 Rp 143,234.00 Rp 2,079,757.68 ITEM PEKERJAAN BARU
3 List Plafond Gypsum m1 - - - 27.75 Rp 58,735.00 Rp 1,629,896.25 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan IV (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 57,559,823.56 Rp 73,572,098.71

V PEKERJAAN PENGECATAN
V.1 LANTAI 1
1 Pengecatan dinding luar m2 34.75 Rp. 62,718.00 Rp. 2,179,450.50 82.41 Rp 62,718.00 Rp 5,168,590.38 BERTAMBAH
2 Pengecatan dinding dalam m2 34.75 Rp. 51,793.00 Rp. 1,799,806.75 82.41 Rp 51,793.00 Rp 4,268,261.13 BERTAMBAH
3 Pengecatan plafond gypsum m2 106.88 Rp. 50,068.00 Rp. 5,351,267.84 129.37 Rp 50,068.00 Rp 6,477,297.16 BERTAMBAH
4 Pengecatan list plafond gypsum m1 41.50 Rp. 29,241.00 Rp. 1,213,501.50 50.26 Rp 29,241.00 Rp 1,469,652.66 BERTAMBAH
5 Pengecatan kolom m2 70.40 Rp. 50,341.00 Rp. 3,544,006.40 - Rp - Rp - DIHILANGKAN

V.2 LANTAI 3
1 Pengecatan dinding dalam m2 220.01 Rp. 51,793.00 Rp. 11,394,977.93 296.11 Rp 51,793.00 Rp 15,336,425.23 BERTAMBAH
2 Pengecatan plafond gypsum m2 171.44 Rp. 50,068.00 Rp. 8,583,657.92 189.23 Rp 50,068.00 Rp 9,474,367.64 BERTAMBAH
3 Pengecatan list plafond gypsum m1 57.98 Rp. 29,241.00 Rp. 1,695,393.18 120.72 Rp 29,241.00 Rp 3,529,973.52 BERTAMBAH

V.3 LANTAI 2
1 Pengecatan dinding dalam m2 - - - 54.52 Rp 51,793.00 Rp 2,823,754.36 ITEM PEKERJAAN BARU
2 Pengecatan plafond gypsum m2 - - - 14.52 Rp 50,068.00 Rp 726,987.36 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan V (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 35,762,062.02 Rp 49,275,309.44
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
VI PEKERJAAN KUZEN PINTU DAN JENDELA
VI.1 LANTAI 1
1 Pembuatan kusen pintu alumunium 4" m1 16.80 Rp. 155,431.00 Rp. 2,611,240.80 - Rp - Rp - DIHILANGKAN
2 Pembuatan pintu alumunium (2 daun) Unit 1.00 Rp. 2,368,137.00 Rp. 2,368,137.00 - Rp - Rp - DIHILANGKAN
3 Pemasangan kaca tebal 5 mm m2 7.34 Rp. 220,070.00 Rp. 1,615,313.80 1.20 Rp 220,070.00 Rp 264,084.00 BERKURANG

VI.1 LANTAI 1
1 Pembuatan Kusen Bovenlight Alumunium m1 - - - - Rp - Rp - DIHILANGKAN
1 Pemasangan Kaca tebal 5 mm m2 - - - - Rp - Rp - DIHILANGKAN
2 Pemasangan Pintu Geser Alumunium unit - - - 1.00 Rp 3,500,000.00 Rp 3,500,000.00 ITEM PEKERJAAN BARU
3 Kusen Pintu Alumunium m1 - - - 4.90 Rp 155,431.00 Rp 761,611.90 ITEM PEKERJAAN BARU

VI.1.2 LANTAI 2
1 Sealant Jendela m1 - - - 71.56 Rp 93,328.00 Rp 6,678,551.68 ITEM PEKERJAAN BARU
2 Pembuatan kusen pintu alumunium 4" m1 - - - 30.23 Rp 155,431.00 Rp 4,698,679.13 ITEM PEKERJAAN BARU
3 Pemasangan kaca tebal 5 mm m2 - - - 5.66 Rp 220,070.00 Rp 1,245,596.20 ITEM PEKERJAAN BARU
4 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) bh - - - 3.00 Rp 4,500,000.00 Rp 13,500,000.00 ITEM PEKERJAAN BARU

VI. 2 LANTAI 3
VI.2. 1 PEKERJAAN KUZEN PINTU DAN JENDELA
1 Pembuatan kusen pintu alumunium 4" m1 389.16 Rp. 155,431.00 Rp. 60,487,527.96 208.52 Rp 155,431.00 Rp 32,410,472.12 BERKURANG
2 Pembuatan Jendela alumunium Unit 38.00 Rp. 1,310,137.00 Rp. 49,785,206.00 40.00 Rp 1,310,137.00 Rp 52,405,480.00 BERTAMBAH
3 Pasang engsel jungkit bh 76.00 Rp. 128,800.00 Rp. 9,788,800.00 80.00 Rp 128,800.00 Rp 10,304,000.00 BERTAMBAH
4 Grendel jendela bh 38.00 Rp. 48,217.00 Rp. 1,832,246.00 40.00 Rp 48,217.00 Rp 1,928,680.00 BERTAMBAH
5 Pemasangan kaca tebal 5 mm m2 41.58 Rp. 220,070.00 Rp. 9,150,510.60 42.68 Rp 220,070.00 Rp 9,392,587.60 BERTAMBAH
6 Pemasangan 1 pintu kaca dan kusen allumunium ( 2 daun) bh 1.00 Rp. 6,500,000.00 Rp. 6,500,000.00 1.00 Rp 6,500,000.00 Rp 6,500,000.00 TETAP
7 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) bh 1.00 Rp. 4,500,000.00 Rp. 4,500,000.00 3.00 Rp 4,500,000.00 Rp 13,500,000.00 BERTAMBAH
8 Glass block m2 - - - 0.24 Rp 811,499.00 Rp 194,759.76 ITEM PEKERJAAN BARU
9 Pemasangan Kusen + Pintu Alu. Ruangan Urinoir set - - - 1.00 Rp 3,200,000.00 Rp 3,200,000.00 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan VI (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 148,638,982.16 Rp 160,484,502.39

VII PEKERJAAN RALLING


VII.1 LANTAI 1
1 Railing Teras m1 - - - 16.20 Rp 1,686,992.00 Rp 27,329,270.40 ITEM PEKERJAAN BARU

VII.2 LANTAI 2
1 Handrail stainless steel dia 2 " m1 26.40 Rp. 991,375.00 Rp. 26,172,300.00 9.00 Rp 1,686,992.00 Rp 15,182,928.00 BERKURANG
2 Railing Balkon m1 - - - 5.87 Rp 1,686,992.00 Rp 9,902,643.04 ITEM PEKERJAAN BARU

VII.3 LANTAI 3
1 Railing Balkon m1 - - - 8.40 Rp 1,686,992.00 Rp 14,170,732.80 ITEM PEKERJAAN BARU
2 Railing Sisi Ruang Urinoir m1 - - - 0.80 Rp 1,686,992.00 Rp 1,349,593.60 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan VII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 26,172,300.00 Rp 67,935,167.84

VIII PEKERJAAN SANITAIR / FIXTURES


VIII. 1 LANTAI 2
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
1 Tissue holder bh 2.00 Rp. 120,000.00 Rp. 240,000.00 - Rp 120,000.00 Rp - DIHILANGKAN
2 Tempat sabun bh 2.00 Rp. 100,000.00 Rp. 200,000.00 - Rp 100,000.00 Rp - DIHILANGKAN
3 Kaca cermin tebal 5 mm 200 cm x 100 cm m2 2.00 Rp. 379,370.00 Rp. 758,740.00 - Rp 379,370.00 Rp - DIHILANGKAN
4 Tandon air 1200 Lt Stainless unit 2.00 Rp. 4,200,000.00 Rp. 8,400,000.00 - Rp 4,200,000.00 Rp - DIHILANGKAN

VIII.2 LANTAI 3
1 Urinoir unit - - - 2.00 Rp 3,020,360.00 Rp 6,040,720.00 ITEM PEKERJAAN BARU
2 Pasangan Kran unit - - - 2.00 Rp 181,757.00 Rp 363,514.00 ITEM PEKERJAAN BARU
3 pasangan Floor Drain unit - - - 2.00 Rp 106,518.00 Rp 213,036.00 ITEM PEKERJAAN BARU
4 Waterproofing m2 - - - 15.22 Rp 353,366.00 Rp 5,378,230.52 ITEM PEKERJAAN BARU

VIII.3 LANTAI 1
1 Pasangan Kran unit - - - 8.00 Rp 181,757.00 Rp 1,454,056.00 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan VIII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 9,598,740.00 Rp 13,449,556.52

IX PEKERJAAN ELEKTRIKAL DAN MEKANIKAL


IX.1 PEKERJAAN INSTALASI PENERANGAN DAN STOP KONTAK
IX.1.1 LANTAI 1
1 Pemasangan meteran listrik daya 33.000 watt bh 1.00 Rp. 70,000,000.00 Rp. 70,000,000.00 - Rp - Rp - DIHILANGKAN
2 Pasang lampu RM 2 x 18 w bh 12.00 Rp. 579,887.00 Rp. 6,958,644.00 13.00 Rp 579,887.00 Rp 7,538,531.00 BERTAMBAH
3 Instalasi titik lampu titik 12.00 Rp. 235,328.00 Rp. 2,823,936.00 13.00 Rp 235,328.00 Rp 3,059,264.00 BERTAMBAH
4 saklar serie titik 2.00 Rp. 41,144.00 Rp. 82,288.00 3.00 Rp 41,144.00 Rp 123,432.00 BERTAMBAH
5 Instalasi titik lampu - Downlight titik - - - 6.00 Rp 235,328.00 Rp 1,411,968.00 ITEM PEKERJAAN BARU
6 Pemasangan Kabel NYY 4 x 16 m - - - 50.00 Rp 274,464.00 Rp 13,723,200.00 ITEM PEKERJAAN BARU

IX.1.2 LANTAI 3
1 Pasang lampu RM 3 x 36 w bh 24.00 Rp. 631,350.00 Rp. 15,152,400.00 26.00 Rp 631,350.00 Rp 16,415,100.00 TETAP
2 Instalasi titik lampu titik 24.00 Rp. 235,328.00 Rp. 5,647,872.00 26.00 Rp 235,328.00 Rp 6,118,528.00 TETAP
3 Saklar serie titik 4.00 Rp. 41,144.00 Rp. 164,576.00 5.00 Rp 41,144.00 Rp 205,720.00 TETAP
4 Stop kontak dinding, 1 Ph, 10 A bh 10.00 Rp. 41,144.00 Rp. 411,440.00 16.00 Rp 41,144.00 Rp 658,304.00 BERTAMBAH
5 Stop kontak AC bh 8.00 Rp. 75,644.00 Rp. 605,152.00 11.00 Rp 75,644.00 Rp 832,084.00 BERTAMBAH
6 Instalasi stop kontak bh 10.00 Rp. 245,103.00 Rp. 2,451,030.00 16.00 Rp 245,103.00 Rp 3,921,648.00 BERTAMBAH
7 Instalasi titik lampu - Downlight titik - - - 3.00 Rp 235,328.00 Rp 705,984.00 ITEM PEKERJAAN BARU

IX.2 PEKERJAAN PANEL PENRANGAN


IX.2.1 PP - 1 LANTAI 1
1 MCB - 1 Ph ( 10 A ) 10 KA bh 4.00 Rp. 125,637.00 Rp. 502,548.00 - Rp - Rp - DIHILANGKAN
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
IX.2.2 PP - 3 LANTAI 3
1 MCB - 3 Ph ( 50 A ) 10 KA bh 1.00 Rp. 1,397,825.00 Rp. 1,397,825.00 1.00 Rp 1,397,825.00 Rp 1,397,825.00 TETAP
2 MCB - 1 Ph ( 10 A ) 10 KA bh 8.00 Rp. 125,637.00 Rp. 1,005,096.00 8.00 Rp 125,637.00 Rp 1,005,096.00 BERKURANG
3 Pilot lamp bh 3.00 Rp. 110,000.00 Rp. 330,000.00 3.00 Rp 110,000.00 Rp 330,000.00 TETAP
4 Fuse patron bh 3.00 Rp. 95,000.00 Rp. 285,000.00 3.00 Rp 95,000.00 Rp 285,000.00 TETAP
5 Kwh meter bh 1.00 Rp. 1,280,000.00 Rp. 1,280,000.00 1.00 Rp 1,280,000.00 Rp 1,280,000.00 TETAP
6 CU. Bar 4 x (12 mm x 2 mm) lot 3.00 Rp. 600,000.00 Rp. 1,800,000.00 3.00 Rp 600,000.00 Rp 1,800,000.00 TETAP
7 Box panel bh 1.00 Rp. 1,330,000.00 Rp. 1,330,000.00 1.00 Rp 1,330,000.00 Rp 1,330,000.00 TETAP
8 Kabel dalam panel lot 1.00 Rp. 700,000.00 Rp. 700,000.00 1.00 Rp 700,000.00 Rp 700,000.00 TETAP
9 Kawat BC - 6 mm2 lot 1.00 Rp. 700,000.00 Rp. 700,000.00 1.00 Rp 700,000.00 Rp 700,000.00 TETAP
10 Material lain - lain lot 1.00 Rp. 1,000,000.00 Rp. 1,000,000.00 1.00 Rp 1,000,000.00 Rp 1,000,000.00 TETAP
11 Biaya pemasangan lot 1.00 Rp. 1,500,000.00 Rp. 1,500,000.00 1.00 Rp 1,500,000.00 Rp 1,500,000.00 TETAP
12 Instalasi titik lampu - Downlight titik - - - 3.00 Rp 235,328.00 Rp 705,984.00 ITEM PEKERJAAN BARU

IX.2.3 PP - 2 LANTAI 2
1 Instalasi titik lampu - Downlight titik - - - 2.00 Rp 235,328.00 Rp 470,656.00 ITEM PEKERJAAN BARU
2 Saklar serie titik - - - 1.00 Rp 41,144.00 Rp 41,144.00 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan IX (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 116,127,807.00 Rp 67,259,468.00

X PEKERJAAN SISTEM KEBAKARAN


X.1 LANTAI 2
1 Instalasi pipa splinker titik 18.00 Rp. 1,823,900.00 Rp. 32,830,200.00 - Rp - Rp - DIHILANGKAN
2 Pemasangan splinker titik 18.00 Rp. 254,150.00 Rp. 4,574,700.00 - Rp - Rp - DIHILANGKAN
3 Instalasi smoke detector titik 18.00 Rp. 1,133,900.00 Rp. 20,410,200.00 - Rp - Rp - DIHILANGKAN
4 Pemasangan smoke detector titik 18.00 Rp. 728,525.00 Rp. 13,113,450.00 - Rp - Rp - DIHILANGKAN
5 Pengadaan alat pemadam api ringan 5 kg bh 5.00 Rp. 1,000,000.00 Rp. 5,000,000.00 2.00 Rp 1,000,000.00 Rp 2,000,000.00 TETAP

X.2 LANTAI 3
1 Instalasi pipa splinker titik 26.00 Rp. 1,823,900.00 Rp. 47,421,400.00 - Rp - Rp - DIHILANGKAN
2 Pemasangan splinker titik 26.00 Rp. 254,150.00 Rp. 6,607,900.00 - Rp - Rp - DIHILANGKAN
3 Instalasi smoke detector titik 26.00 Rp. 1,133,900.00 Rp. 29,481,400.00 - Rp - Rp - DIHILANGKAN
4 Pemasangan smoke detector titik 26.00 Rp. 728,525.00 Rp. 18,941,650.00 - Rp - Rp - DIHILANGKAN
5 Pengadaan alat pemadam api ringan 5 kg bh 7.00 Rp. 1,000,000.00 Rp. 7,000,000.00 1.00 Rp 1,000,000.00 Rp 1,000,000.00 TETAP

Jumlah Harga Pekerjaan X (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 185,380,900.00 Rp 3,000,000.00
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
XI PEKERJAAN LANDSCAPE
1 Grill dilapisi besi plat bordes m1 50.00 Rp. 260,162.00 Rp. 13,008,100.00 14.00 Rp 260,162.00 Rp 3,642,268.00 DIHILANGKAN
2 Railing pagar m1 41.40 Rp. 912,398.00 Rp. 37,773,277.20 - Rp - Rp - DIHILANGKAN
3 cor beton tebal 12 cm ( K-175) m3 0.84 Rp. 1,299,602.00 Rp. 1,091,665.68 - Rp - Rp - DIHILANGKAN
4 cor beton tebal 8 cm ( K-175) m3 - - - 0.38 Rp 1,299,602.00 Rp 493,848.76 ITEM PEKERJAAN BARU
5 Pekerjaan kanopi m2 95.35 Rp. 353,372.00 Rp. 33,694,020.20 19.44 Rp 363,635.00 Rp 7,069,064.40 BERKURANG
6 Pekerjaan kansteen m1 55.80 Rp. 133,710.00 Rp. 7,461,018.00 - Rp - Rp - DIHILANGKAN
7 Pengecatan kansteen m2 33.48 Rp. 60,993.00 Rp. 2,042,045.64 - Rp - Rp - DIHILANGKAN
8 Gebalan rumput m2 44.64 Rp. 54,816.00 Rp. 2,446,986.24 - Rp - Rp - DIHILANGKAN
9 Penutup atap m2 40.80 Rp. 149,671.00 Rp. 6,106,576.80 44.38 Rp 149,671.00 Rp 6,642,398.98 BERTAMBAH
10 Pasangan Calci-plank m2 - - - 20.57 Rp 302,668.00 Rp 6,225,880.76 ITEM PEKERJAAN BARU
11 Rangka Pekerjaan Calci-plank m2 - - - 20.57 Rp 267,743.00 Rp 5,507,473.51 ITEM PEKERJAAN BARU
12 Penutup Atap Selasar Penghubung m2 - - - 11.70 Rp 149,671.00 Rp 1,751,150.70 ITEM PEKERJAAN BARU
13 Pekerjaan Rangka Atap Selasar Penghubung m2 - - - 11.70 Rp 267,743.00 Rp 3,132,593.10 ITEM PEKERJAAN BARU
14 Talang Air Selasar m2 - - - 3.90 Rp 394,881.00 Rp 1,540,035.90 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan XI (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 103,623,689.76 Rp 36,004,714.11

XII PEKERJAAN PARTISI


XII.1 LANTAI 2
XII.1.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi m2 93.00 Rp. 258,217.00 Rp. 24,014,181.00 35.91 Rp 258,217.00 Rp 9,272,572.47 BERKURANG
2 Pekerjaan pasang papan gypsum 2 muka m2 186.00 Rp. 231,552.00 Rp. 43,068,672.00 71.82 Rp 231,552.00 Rp 16,630,064.64 BERKURANG
3 Pekerjaan kusen alumunium + daun pintu alu. + kaca bh 4.00 Rp. 3,186,276.00 Rp. 12,745,104.00 - Rp - Rp - DIHILANGKAN
4 Pekerjaan list plan lantai 10 cm m1 53.00 Rp. 83,240.00 Rp. 4,411,720.00 32.13 Rp 83,240.00 Rp 2,674,501.20 BERKURANG
5 Pekerjaan list gypsum m1 53.00 Rp. 58,735.00 Rp. 3,112,955.00 16.85 Rp 58,735.00 Rp 989,684.75 BERKURANG
6 Pekerjaan pengecatan m2 186.00 Rp. 50,068.00 Rp. 9,312,648.00 71.82 Rp 50,068.00 Rp 3,595,883.76 BERKURANG

XII.1.2 PARTISI RUANG RAPAT


1 Pekerjaan rangka partisi m2 32.55 Rp. 258,217.00 Rp. 8,404,963.35 27.26 Rp 258,217.00 Rp 7,038,995.42 BERKURANG
2 Pekerjaan pasang papan gypsum 2 muka m2 65.10 Rp. 231,552.00 Rp. 15,074,035.20 54.52 Rp 231,552.00 Rp 12,624,215.04 BERKURANG
3 Pekerjaan kusen alumunium + daun pintu alu. + kaca bh 1.00 Rp. 3,186,276.00 Rp. 3,186,276.00 - Rp - Rp - DIHILANGKAN
4 Pekerjaan list plan lantai 10 cm m1 21.00 Rp. 83,240.00 Rp. 1,748,040.00 14.72 Rp 83,240.00 Rp 1,225,292.80 BERKURANG
5 Pekerjaan list gypsum m1 21.00 Rp. 58,735.00 Rp. 1,233,435.00 10.90 Rp 58,735.00 Rp 640,211.50 BERKURANG
6 Pekerjaan pengecatan m2 65.10 Rp. 50,068.00 Rp. 3,259,426.80 54.52 Rp 50,068.00 Rp 2,729,707.36 BERKURANG

XII.2 LANTAI 2
XII.2.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi m2 71.30 Rp. 258,217.00 Rp. 18,410,872.10 - Rp - Rp - DIHILANGKAN
2 Pekerjaan pasang papan gypsum 2 muka m2 142.60 Rp. 231,552.00 Rp. 33,019,315.20 - Rp - Rp - DIHILANGKAN
3 Pekerjaan kusen alumunium dan daun pintu panel lapis HPL bh 4.00 Rp. 3,186,276.00 Rp. 12,745,104.00 - Rp - Rp - DIHILANGKAN
4 Pekerjaan list plan lantai 10 cm m1 22.00 Rp. 83,240.00 Rp. 1,831,280.00 - Rp - Rp - DIHILANGKAN
5 Pekerjaan list gypsum m1 22.00 Rp. 58,735.00 Rp. 1,292,170.00 - Rp - Rp - DIHILANGKAN
6 Pekerjaan pengecatan m2 142.60 Rp. 50,068.00 Rp. 7,139,696.80 - Rp - Rp - DIHILANGKAN
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN

1 2 3 4 5 6=4x5 7 8 9=7x8
XII.2 LANTAI 3
XII.2.1 PARITISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi m2 - - - 71.11 Rp 258,217.00 Rp 18,361,810.87 ITEM PEKERJAAN BARU
2 Pekerjaan pasang papan gypsum 2 muka m2 - - - 142.22 Rp 231,552.00 Rp 32,931,325.44 ITEM PEKERJAAN BARU
3 Pekerjaan kusen alumunium + daun pintu alu. + kaca bh - - - - Rp - Rp - DIHILANGKAN
4 Pekerjaan list plan lantai 10 cm m1 - - - 66.29 Rp 83,240.00 Rp 5,517,979.60 ITEM PEKERJAAN BARU
5 Pekerjaan list gypsum m1 - - - 33.93 Rp 58,735.00 Rp 1,992,878.55 ITEM PEKERJAAN BARU
6 Pekerjaan pengecatan m2 - - - 142.22 Rp 50,068.00 Rp 7,120,670.96 ITEM PEKERJAAN BARU
7 Pekerjaan Peredam Ruangan m2 - - - 64.64 Rp 278,568.00 Rp 18,006,635.52 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan XII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 204,009,894.45 Rp 141,352,429.88

XIII PEKERJAAN AREA PARKIR


XIII.1 PEKERJAAN BETON
1 Galian Pondasi Tiang m3 - - - 3.17 Rp 124,918.00 Rp 395,990.06 ITEM PEKERJAAN BARU
2 Cor beton tebal 12 cm (K-175) m3 24.76 Rp. 1,299,602.00 Rp. 32,178,145.52 3.17 Rp 1,299,602.00 Rp 4,119,738.34 BERKURANG
3 Pekerjaan Pasangan Paving Block m2 - - - 207.72 Rp 253,485.00 Rp 52,653,904.20 ITEM PEKERJAAN BARU
4 Pembesian kg 1,110.28 Rp. 17,903.00 Rp. 19,877,342.84 35.75 Rp 17,903.00 Rp 640,032.25 BERKURANG
5 Bekisting m2 6.91 Rp. 204,930.00 Rp. 1,416,066.30 3.30 Rp 204,930.00 Rp 676,269.00 BERKURANG
6 Penutup atap - Spandex m2 206.36 Rp. 149,671.00 Rp. 30,886,107.56 151.38 Rp 149,671.00 Rp 22,657,195.98 BERKURANG
7 Rangka atap baja m2 206.36 Rp. 206,310.00 Rp. 42,574,131.60 151.38 Rp 267,743.00 Rp 40,530,935.34 BERKURANG
8 Pemasangan Tiang Baja Titik - - - 11.00 Rp 1,598,270.00 Rp 17,580,970.00 ITEM PEKERJAAN BARU
9 Beton Sikat m2 - - - 9.68 Rp 44,340.00 Rp 429,211.20 ITEM PEKERJAAN BARU

Jumlah Harga Pekerjaan XIII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 126,931,793.82 Rp 139,684,246.37
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGUKURAN LOKASI


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.01 150,000.00 1,500.00
3 PEKERJA ORG/HARI 0.03 130,000.00 3,900.00

II BAHAN

III ALAT
1 ALAT BANTU LS 1.00 1,000.00 1,000.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 8,050.00


OVERHEAD + PROFIT (15%) 1,207.50
HARGA SATUAN PEKERJAAN 9,257.50
HARGA SATUAN PEKERJAAN DIBULATKAN 9,257.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PAGAR LOKASI


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.20 130,000.00 26,000.00

II BAHAN
1 DOLKEN KAYU DIA. 8-10/400 CM BATANG 1.05 25,000.00 26,250.00
2 SEMEN KG 2.50 1,400.00 3,500.00
3 SENG GELOMBANG LEMBAR 1.05 74,500.00 78,225.00
4 PASIR BETON M3 0.01 400,000.00 2,000.00
5 KORAL BETON M3 0.01 550,000.00 4,950.00
6 KAYU 5/7 M3 0.06 3,500,000.00 217,000.00
7 PAKU BIASA KG 0.06 18,000.00 1,080.00
8 CAT BESI KG 0.45 80,000.00 36,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 411,255.00


OVERHEAD + PROFIT (15%) 61,688.25
HARGA SATUAN PEKERJAAN 472,943.25
HARGA SATUAN PEKERJAAN DIBULATKAN 472,943.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMASANGAN BATU BATA (1 PC : 5 PASIR)


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,176.47
2 TUKANG ORG/HARI 0.20 150,000.00 29,411.76
3 PEKERJA ORG/HARI 0.59 130,000.00 76,470.59

II BAHAN
1 BATA MERAH BUAH 70.00 850.00 59,500.00
2 SEMEN KG 9.68 1,400.00 13,552.00
3 PASIR PASANG M3 0.05 225,000.00 10,125.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 205,735.82


OVERHEAD + PROFIT (15%) 30,860.37
HARGA SATUAN PEKERJAAN 236,596.20
HARGA SATUAN PEKERJAAN DIBULATKAN 236,596.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PLESTERAN DINDING (1 PC : 5 PASIR)


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.06 165,000.00 9,269.66
2 TUKANG ORG/HARI 0.06 150,000.00 8,426.97
3 PEKERJA ORG/HARI 0.17 130,000.00 21,910.11

II BAHAN
1 SEMEN KG 5.18 1,400.00 7,257.60
2 PASIR PASANG M3 0.03 225,000.00 5,850.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 53,214.34


OVERHEAD + PROFIT (15%) 7,982.15
HARGA SATUAN PEKERJAAN 61,196.49
HARGA SATUAN PEKERJAAN DIBULATKAN 61,196.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : KOLOM PRAKTIS


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,375.00
2 TUKANG ORG/HARI 0.01 150,000.00 1,250.00
3 PEKERJA ORG/HARI 0.03 130,000.00 4,333.33

II BAHAN
1 KAYU BEKISTING M3 0.00 2,200,000.00 4,400.00
2 PAKU KG 0.01 18,000.00 180.00
3 MINYAK BEKISTING LITER 0.09 5,000.00 450.00
4 BESI BETON POLOS KG 3.00 12,500.00 37,500.00
5 KAWAT BETON KG 0.45 25,000.00 11,250.00
6 SEMEN KG 4.00 1,400.00 5,600.00
7 PASIR BETON M3 0.06 400,000.00 24,000.00
8 KORAL BETON M3 0.01 550,000.00 4,950.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 95,788.33


OVERHEAD + PROFIT (15%) 14,368.25
HARGA SATUAN PEKERJAAN 110,156.58
HARGA SATUAN PEKERJAAN DIBULATKAN 110,156.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : ACIAN DINDING


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,621.19
2 TUKANG ORG/HARI 0.04 150,000.00 6,019.26
3 PEKERJA ORG/HARI 0.16 130,000.00 20,866.77

II BAHAN
1 SEMEN KG 3.25 1,400.00 4,550.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 38,557.22


OVERHEAD + PROFIT (15%) 5,783.58
HARGA SATUAN PEKERJAAN 44,340.81
HARGA SATUAN PEKERJAAN DIBULATKAN 44,340.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : BENANGAN


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.02 150,000.00 3,000.00
3 PEKERJA ORG/HARI 0.04 130,000.00 5,200.00

II BAHAN
1 SEMEN KG 5.18 1,400.00 7,257.60
2 PASIR PASANG M3 0.03 225,000.00 5,850.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 23,457.60


OVERHEAD + PROFIT (15%) 3,518.64
HARGA SATUAN PEKERJAAN 26,976.24
HARGA SATUAN PEKERJAAN DIBULATKAN 26,976.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : KOLOM H. BEAM 250x250x9x14 MM DIBUNGKUS BETON


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.06 165,000.00 10,312.50
2 TUKANG ORG/HARI 0.06 150,000.00 9,375.00
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00

II BAHAN
1 BAJA H. BEAM KG 14.48 22,000.00 318,633.33
2 BESI TULANGAN KG 4.74 12,500.00 59,250.00
3 SEMEN KG 315.00 1,400.00 441,000.00
4 PASIR M3 0.52 400,000.00 208,857.14
5 KERIKIL M3 0.57 550,000.00 315,027.78

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,427,955.75


OVERHEAD + PROFIT (15%) 214,193.36
HARGA SATUAN PEKERJAAN 1,642,149.12
HARGA SATUAN PEKERJAAN DIBULATKAN 1,642,149.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : LANTAI HOMOGENIUS 60 CM X 60 CM (POLISHED)


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 7,432.43
2 TUKANG ORG/HARI 0.09 150,000.00 13,513.51
3 PEKERJA ORG/HARI 0.18 130,000.00 23,423.42

II BAHAN
1 SEMEN KG 9.60 1,400.00 13,440.00
2 SEMEN WARNA KG 1.50 17,000.00 25,500.00
3 PASIR PASANG M3 0.05 225,000.00 10,125.00
4 HOMOGENIUS TILE 60 x 60 BUAH 3.10 100,000.00 310,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 403,934.37


OVERHEAD + PROFIT (15%) 60,590.16
HARGA SATUAN PEKERJAAN 464,524.52
HARGA SATUAN PEKERJAAN DIBULATKAN 464,524.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : LANTAI HOMOGENIUS TANGGA


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 7,432.43
2 TUKANG ORG/HARI 0.09 150,000.00 13,513.51
3 PEKERJA ORG/HARI 0.18 130,000.00 23,423.42

II BAHAN
1 SEMEN KG 9.60 1,400.00 13,440.00
2 SEMEN WARNA KG 1.50 17,000.00 25,500.00
3 PASIR PASANG M3 0.05 155,000.00 6,975.00
4 HOMOGENIUS TILE 60 x 60 BUAH 3.10 100,000.00 310,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 400,784.37


OVERHEAD + PROFIT (15%) 60,117.66
HARGA SATUAN PEKERJAAN 460,902.02
HARGA SATUAN PEKERJAAN DIBULATKAN 460,902.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PLIN KERAMIK 10 CM x 60 CM


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,600.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.08 130,000.00 10,400.00

II BAHAN
1 SEMEN KG 1.14 1,400.00 1,596.00
2 SEMEN WARNA KG 0.10 17,000.00 1,700.00
3 PASIR PASANG M3 0.00 155,000.00 465.00
4 PLIN KERAMIK 10X60 BUAH 1.70 17,000.00 28,900.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 56,161.00


OVERHEAD + PROFIT (15%) 8,424.15
HARGA SATUAN PEKERJAAN 64,585.15
HARGA SATUAN PEKERJAAN DIBULATKAN 64,585.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : LAPIS CREED 3 CM - 7 CM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,884.30
2 TUKANG ORG/HARI 0.01 150,000.00 1,713.00
3 PEKERJA ORG/HARI 0.05 130,000.00 5,938.41

II BAHAN
1 SEMEN KG 22.25 1,400.00 31,150.00
2 PASIR PASANG M3 0.04 155,000.00 6,045.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 47,230.72


OVERHEAD + PROFIT (15%) 7,084.61
HARGA SATUAN PEKERJAAN 54,315.33
HARGA SATUAN PEKERJAAN DIBULATKAN 54,315.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PLAFOND GYPSUM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 988.07
2 TUKANG ORG/HARI 0.01 150,000.00 898.25
3 PEKERJA ORG/HARI 0.02 130,000.00 3,113.92

II BAHAN
1 GYPSUM BOARD 9 MM LEMBAR 0.38 70,000.00 26,250.00
2 PAKU SEKRUP KG 0.11 55,000.00 6,050.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 37,800.24


OVERHEAD + PROFIT (15%) 5,670.04
HARGA SATUAN PEKERJAAN 43,470.28
HARGA SATUAN PEKERJAAN DIBULATKAN 43,470.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : RANGKA PLAFOND HOLLOW METAL FURING


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 5,928.43
2 TUKANG ORG/HARI 0.04 150,000.00 5,389.48
3 PEKERJA ORG/HARI 0.14 130,000.00 18,683.53

II BAHAN
1 HOLLOW METAL FURING M' 4.10 22,000.00 90,200.00
2 SEKRUP KG 0.11 55,000.00 6,050.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 126,751.44


OVERHEAD + PROFIT (15%) 19,012.72
HARGA SATUAN PEKERJAAN 145,764.15
HARGA SATUAN PEKERJAAN DIBULATKAN 145,764.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : LIST PLAFOND GYPSUM


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 2,357.14
2 TUKANG ORG/HARI 0.01 150,000.00 2,142.86
3 PEKERJA ORG/HARI 0.03 130,000.00 3,714.29

II BAHAN
1 LIST GYPSUM PROFIL M' 1.05 40,000.00 42,000.00
2 TEPUNG GYPSUM KG 0.15 2,400.00 360.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 51,074.29


OVERHEAD + PROFIT (15%) 7,661.14
HARGA SATUAN PEKERJAAN 58,735.43
HARGA SATUAN PEKERJAAN DIBULATKAN 58,735.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGECATAN DINDING LUAR


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22

II BAHAN
1 PLAMUR TEMBOK KG 0.10 15,000.00 1,500.00
2 CAT TEMBOK DASAR KG 0.10 54,000.00 5,400.00
3 CAT TEMBOK FINISHNG KG 0.10 245,000.00 24,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 54,537.80


OVERHEAD + PROFIT (15%) 8,180.67
HARGA SATUAN PEKERJAAN 62,718.46
HARGA SATUAN PEKERJAAN DIBULATKAN 62,718.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGECATAN DINDING DALAM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22

II BAHAN
1 PLAMUR TEMBOK KG 0.10 15,000.00 1,500.00
2 CAT TEMBOK DASAR KG 0.10 54,000.00 5,400.00
3 CAT TEMBOK FINISHNG KG 0.10 150,000.00 15,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 45,037.80


OVERHEAD + PROFIT (15%) 6,755.67
HARGA SATUAN PEKERJAAN 51,793.46
HARGA SATUAN PEKERJAAN DIBULATKAN 51,793.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGECATAN PLAFOND GYPSUM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22

II BAHAN
1 CAT DASAR KG 0.10 54,000.00 5,400.00
2 CAT FINISHNG KG 0.10 150,000.00 15,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 43,537.80


OVERHEAD + PROFIT (15%) 6,530.67
HARGA SATUAN PEKERJAAN 50,068.46
HARGA SATUAN PEKERJAAN DIBULATKAN 50,068.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGECATAN LIST PLAFOND GYPSUM


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,299.21
2 TUKANG ORG/HARI 0.01 150,000.00 1,181.10
3 PEKERJA ORG/HARI 0.02 130,000.00 2,047.24

II BAHAN
1 CAT DASAR KG 0.10 54,000.00 5,400.00
2 CAT FINISHNG KG 0.10 150,000.00 15,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 25,427.56


OVERHEAD + PROFIT (15%) 3,814.13
HARGA SATUAN PEKERJAAN 29,241.69
HARGA SATUAN PEKERJAAN DIBULATKAN 29,241.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGECATAN KOLOM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,133.83
2 TUKANG ORG/HARI 0.04 150,000.00 5,576.21
3 PEKERJA ORG/HARI 0.07 130,000.00 9,665.43

II BAHAN
1 PLAMUR TEMBOK KG 0.10 15,000.00 1,500.00
2 CAT TEMBOK DASAR KG 0.10 54,000.00 5,400.00
3 CAT TEMBOK FINISHNG KG 0.10 150,000.00 15,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 43,775.46


OVERHEAD + PROFIT (15%) 6,566.32
HARGA SATUAN PEKERJAAN 50,341.78
HARGA SATUAN PEKERJAAN DIBULATKAN 50,341.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMBUATAN KUSEN ALUMINIUM 4"


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,173.08
2 TUKANG ORG/HARI 0.02 150,000.00 2,884.62
3 PEKERJA ORG/HARI 0.04 130,000.00 5,000.00

II BAHAN
1 PROFIL ALUMINIUM M 1.10 110,000.00 121,000.00
2 SEKRUP BUAH 2.00 400.00 800.00
3 SEALENT KG 0.06 30,000.00 1,800.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 135,157.69


OVERHEAD + PROFIT (15%) 20,273.65
HARGA SATUAN PEKERJAAN 155,431.35
HARGA SATUAN PEKERJAAN DIBULATKAN 155,431.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMBUATAN PINTU ALUMINIUM (2 DAUN)


SATUAN PEMBAYARAN : UNIT

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.25 165,000.00 41,250.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00

II BAHAN
1 PROFIL ALUMINIUM M 6.00 110,000.00 660,000.00
2 DAUN PINTU ALUMINIUM M 2.10 350,000.00 735,000.00
3 KUNCI TANAM SELINDER BUAH 2.00 260,000.00 520,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 2,059,250.00


OVERHEAD + PROFIT (15%) 308,887.50
HARGA SATUAN PEKERJAAN 2,368,137.50
HARGA SATUAN PEKERJAAN DIBULATKAN 2,368,137.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMASANGAN KACA TEBAL 5 MM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,156.25
2 TUKANG ORG/HARI 0.06 150,000.00 9,375.00
3 PEKERJA ORG/HARI 0.03 130,000.00 4,062.50

II BAHAN
1 KACA 5 MM M2 1.05 162,640.00 170,772.00
2 SEALENT KG 0.05 30,000.00 1,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 191,365.75


OVERHEAD + PROFIT (15%) 28,704.86
HARGA SATUAN PEKERJAAN 220,070.61
HARGA SATUAN PEKERJAAN DIBULATKAN 220,070.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMBUATAN PINTU ALUMINIUM


SATUAN PEMBAYARAN : UNIT

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.25 165,000.00 41,250.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00

II BAHAN
1 DAUN PINTU ALUMINIUM Unit 1.00 1,200,000.00 1,200,000.00
2 KUNCI TANAM SELINDER BUAH 1.00 260,000.00 260,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,604,250.00


OVERHEAD + PROFIT (15%) 240,637.50
HARGA SATUAN PEKERJAAN 1,844,887.50
HARGA SATUAN PEKERJAAN DIBULATKAN 1,844,887.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMASANGAN ENGSEL JUNGKIT


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,300.00
2 TUKANG ORG/HARI 0.02 150,000.00 3,000.00
3 PEKERJA ORG/HARI 0.04 130,000.00 5,200.00

II BAHAN
1 ENGSEL BUAH 1.00 100,000.00 100,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 112,000.00


OVERHEAD + PROFIT (15%) 16,800.00
HARGA SATUAN PEKERJAAN 128,800.00
HARGA SATUAN PEKERJAAN DIBULATKAN 128,800.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : GRANDEL JENDELA


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 4,714.29
2 TUKANG ORG/HARI 0.03 150,000.00 4,285.71
3 PEKERJA ORG/HARI 0.06 130,000.00 7,428.57

II BAHAN
1 GRANDEL JENDELA BUAH 1.00 25,000.00 25,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 41,928.57


OVERHEAD + PROFIT (15%) 6,289.29
HARGA SATUAN PEKERJAAN 48,217.86
HARGA SATUAN PEKERJAAN DIBULATKAN 48,217.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : RAILLING TANGGA


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,750.00
2 TUKANG ORG/HARI 0.02 150,000.00 2,500.00
3 PEKERJA ORG/HARI 0.05 130,000.00 6,500.00

II BAHAN
1 BESI STAINLESS STEEL DIA. 2" M 9.57 122,500.00 1,172,325.00
2 KAWAT LAS KG 0.48 26,000.00 12,441.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,197,016.00


OVERHEAD + PROFIT (15%) 179,552.40
HARGA SATUAN PEKERJAAN 1,376,568.40
HARGA SATUAN PEKERJAAN DIBULATKAN 1,376,568.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : KACA CERMIN TEBAL 5 MM 200 CM x 100 CM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,178.57
2 TUKANG ORG/HARI 0.01 150,000.00 1,071.43
3 PEKERJA ORG/HARI 0.01 130,000.00 1,857.14

II BAHAN
1 CERMIN TEBAL 5 MM M2 2.00 162,640.00 325,280.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 329,887.14


OVERHEAD + PROFIT (15%) 49,483.07
HARGA SATUAN PEKERJAAN 379,370.21
HARGA SATUAN PEKERJAAN DIBULATKAN 379,370.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PASANG LAMPU RM 2 x 18 WATT


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00

II BAHAN
1 LAMPU RM 2 x 18 WATT BUAH 1.00 380,000.00 380,000.00
2 ACCESSORIES % 5.00 19,000.00 95,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 504,250.00


OVERHEAD + PROFIT (15%) 75,637.50
HARGA SATUAN PEKERJAAN 579,887.50
HARGA SATUAN PEKERJAAN DIBULATKAN 579,887.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : INSTALASI TITIK LAMPU


SATUAN PEMBAYARAN : TITIK

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33

II BAHAN
1 PIPA LISTRIK 5/8" BATANG 1.00 22,800.00 22,800.00
2 KABEL NYM 3 x 2.5 MM M 6.00 21,250.00 127,500.00
3 T DUS BUAH 1.00 3,000.00 3,000.00
4 L BOW BUAH 1.00 3,000.00 3,000.00
5 LAS DOP BUAH 1.00 2,500.00 2,500.00
6 KLEM BUAH 4.00 500.00 2,000.00
7 MANGKOK BUAH 1.00 5,000.00 5,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 204,633.33


OVERHEAD + PROFIT (15%) 30,695.00
HARGA SATUAN PEKERJAAN 235,328.33
HARGA SATUAN PEKERJAAN DIBULATKAN 235,328.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : SAKLAR SERIE


SATUAN PEMBAYARAN : TITIK

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,666.67
2 TUKANG ORG/HARI 0.02 150,000.00 3,333.33
3 PEKERJA ORG/HARI 0.04 130,000.00 5,777.78

II BAHAN
1 SAKLAR SERIE BUAH 1.00 18,000.00 18,000.00
2 PERLENGKAPAN INSTALASI % 5.00 900.00 4,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 35,777.78


OVERHEAD + PROFIT (15%) 5,366.67
HARGA SATUAN PEKERJAAN 41,144.44
HARGA SATUAN PEKERJAAN DIBULATKAN 41,144.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PASANG LAMPU RM 3 x 36 WATT


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,500.00
2 TUKANG ORG/HARI 0.03 150,000.00 5,000.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00

II BAHAN
1 LAMPU RM 3 x 36 WATT BUAH 1.00 420,000.00 420,000.00
2 ACCESSORIES % 5.00 21,000.00 105,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 549,000.00


OVERHEAD + PROFIT (15%) 82,350.00
HARGA SATUAN PEKERJAAN 631,350.00
HARGA SATUAN PEKERJAAN DIBULATKAN 631,350.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : STOP KONTAK DINIDNG, 1 PH, 10 A


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,666.67
2 TUKANG ORG/HARI 0.02 150,000.00 3,333.33
3 PEKERJA ORG/HARI 0.04 130,000.00 5,777.78

II BAHAN
1 STOP KONTAK BUAH 1.00 18,000.00 18,000.00
2 PERLENGKAPAN INSTALASI % 5.00 900.00 4,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 35,777.78


OVERHEAD + PROFIT (15%) 5,366.67
HARGA SATUAN PEKERJAAN 41,144.44
HARGA SATUAN PEKERJAAN DIBULATKAN 41,144.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : STOP KONTAK AC


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,666.67
2 TUKANG ORG/HARI 0.02 150,000.00 3,333.33
3 PEKERJA ORG/HARI 0.04 130,000.00 5,777.78

II BAHAN
1 STOP KONTAK AC BUAH 1.00 42,000.00 42,000.00
2 PERLENGKAPAN INSTALASI % 5.00 2,100.00 10,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 65,777.78


OVERHEAD + PROFIT (15%) 9,866.67
HARGA SATUAN PEKERJAAN 75,644.44
HARGA SATUAN PEKERJAAN DIBULATKAN 75,644.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : INSTALASI STOP KONTAK


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33

II BAHAN
1 PIPA LISTRIK 5/8" BATANG 1.00 22,800.00 22,800.00
2 KABEL NYM 3 x 2.5 MM M 6.00 21,250.00 127,500.00
3 T DUS BUAH 2.00 3,000.00 6,000.00
4 L BOW BUAH 2.00 3,000.00 6,000.00
5 LAS DOP BUAH 2.00 2,500.00 5,000.00
6 KLEM BUAH 4.00 500.00 2,000.00
7 MANGKOK BUAH 1.00 5,000.00 5,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 213,133.33


OVERHEAD + PROFIT (15%) 31,970.00
HARGA SATUAN PEKERJAAN 245,103.33
HARGA SATUAN PEKERJAAN DIBULATKAN 245,103.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : MCB - 1 PH (10 A) 10 KA


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00

II BAHAN
1 MCB - 1 PH (10 A) 10 KA BUAH 1.00 80,000.00 80,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 109,250.00


OVERHEAD + PROFIT (15%) 16,387.50
HARGA SATUAN PEKERJAAN 125,637.50
HARGA SATUAN PEKERJAAN DIBULATKAN 125,637.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : MCB - 3 PH (50 A) 10 KA


SATUAN PEMBAYARAN : BUAH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.20 165,000.00 33,000.00
2 TUKANG ORG/HARI 0.20 150,000.00 30,000.00
3 PEKERJA ORG/HARI 0.40 130,000.00 52,000.00

II BAHAN
1 MCB - 3 PH (50 A) 10 KA BUAH 1.00 1,100,000.00 1,100,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,215,500.00


OVERHEAD + PROFIT (15%) 182,325.00
HARGA SATUAN PEKERJAAN 1,397,825.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,397,825.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : INSTALASI PIPA SPLINKER


SATUAN PEMBAYARAN : TITIK

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 PIPA GALVANIS 3/4" METER 25.00 60,000.00 1,500,000.00
2 PERLENGKAPAN INSTALASI % 5.00 3,000.00 15,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,586,000.00


OVERHEAD + PROFIT (15%) 237,900.00
HARGA SATUAN PEKERJAAN 1,823,900.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,823,900.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMASANGAN SPLINKER


SATUAN PEMBAYARAN : TITIK

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 SPLINKE BUAH 1.00 120,000.00 120,000.00
2 ACCESSORIES % 5.00 6,000.00 30,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 221,000.00


OVERHEAD + PROFIT (15%) 33,150.00
HARGA SATUAN PEKERJAAN 254,150.00
HARGA SATUAN PEKERJAAN DIBULATKAN 254,150.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : INSTALASI SMOKE DETECTOR


SATUAN PEMBAYARAN : TITIK

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 PIPA GALVANIS 3/4" METER 15.00 60,000.00 900,000.00
2 PERLENGKAPAN INSTALASI % 5.00 3,000.00 15,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 986,000.00


OVERHEAD + PROFIT (15%) 147,900.00
HARGA SATUAN PEKERJAAN 1,133,900.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,133,900.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMASANGAN SMOKE DETECTOR


SATUAN PEMBAYARAN : TITIK

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 SMOKE DETECTOR BUAH 1.00 450,000.00 450,000.00
2 ACCESSORIES % 5.00 22,500.00 112,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 633,500.00


OVERHEAD + PROFIT (15%) 95,025.00
HARGA SATUAN PEKERJAAN 728,525.00
HARGA SATUAN PEKERJAAN DIBULATKAN 728,525.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : GRILL DI LAPISI BESI PLAT BORDES


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33

II BAHAN
1 PLAT BORDES LEMBAR 0.67 185,000.00 123,395.00
2 BESI SIKU 40.40.4 M' 2.00 32,000.00 64,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 226,228.33


OVERHEAD + PROFIT (15%) 33,934.25
HARGA SATUAN PEKERJAAN 260,162.58
HARGA SATUAN PEKERJAAN DIBULATKAN 260,162.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : RAILING PAGAR


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.20 130,000.00 26,000.00

II BAHAN
1 BESI HOLLOW 40x40 Mm M' 4.40 99,250.00 436,700.00
2 BESI HOLLOW 20x40 Mm M' 5.00 74,500.00 372,500.00
3 BESI HOLLOW Dia.2" M' 1.52 99,250.00 150,860.00
4 KAWAT LAS KG 0.39 26,000.00 10,140.00

III ALAT
1 ALAT BANTU LS 1.00 455,000.00 455,000.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,466,950.00


OVERHEAD + PROFIT (15%) 220,042.50
HARGA SATUAN PEKERJAAN 1,686,992.50
HARGA SATUAN PEKERJAAN DIBULATKAN 1,686,992.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : COR BETON TEBAL 12 CM (K-175)


SATUAN PEMBAYARAN : M3

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.14 165,000.00 22,916.67
2 TUKANG ORG/HARI 0.28 150,000.00 41,666.67
3 PEKERJA ORG/HARI 1.11 130,000.00 144,444.44

II BAHAN
1 SEMEN KG 229.28 1,400.00 320,989.20
2 PASIR BETON M3 0.35 400,000.00 140,680.00
3 KERIKIL M3 0.63 550,000.00 348,535.00
4 AIR LTR 215.00 100.00 21,500.00

III ALAT
1 CONCRETE MIXER JAM 0.71 75,300.00 53,570.57
2 CONCRETE VIBRATOR JAM 0.71 49,600.00 35,286.86
3 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,130,089.41


OVERHEAD + PROFIT (15%) 169,513.41
HARGA SATUAN PEKERJAAN 1,299,602.82
HARGA SATUAN PEKERJAAN DIBULATKAN 1,299,602.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEKERJAAN KANOPI


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.15 130,000.00 19,500.00

II BAHAN
1 BESI HOLLOW 40x40 mm M' 2.10 99,250.00 208,425.00
2 KAWAT LAS KG 0.11 26,000.00 2,730.00
3 ATAP ZINCALUME 0.3 MM M2 1.10 63,000.00 69,300.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 316,205.00


OVERHEAD + PROFIT (15%) 47,430.75
HARGA SATUAN PEKERJAAN 363,635.75
HARGA SATUAN PEKERJAAN DIBULATKAN 363,635.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEKERJAAN KANSTEEN


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,600.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.16 130,000.00 20,800.00

II BAHAN
1 KANSTEEN 15 x 20 x 30 x 50 CM BUAH 2.00 40,000.00 80,000.00
2 SEMEN KG 0.09 1,400.00 120.40
3 PASIR PASANG M3 0.01 225,000.00 2,250.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 116,270.40


OVERHEAD + PROFIT (15%) 17,440.56
HARGA SATUAN PEKERJAAN 133,710.96
HARGA SATUAN PEKERJAAN DIBULATKAN 133,710.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENGECATAN KANSTEEN


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22

II BAHAN
1 CAT DASAR KG 0.10 54,000.00 5,400.00
2 CAT FINISHNG KG 0.10 245,000.00 24,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 53,037.80


OVERHEAD + PROFIT (15%) 7,955.67
HARGA SATUAN PEKERJAAN 60,993.46
HARGA SATUAN PEKERJAAN DIBULATKAN 60,993.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : GEMBALAN RUMPUT


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,500.00
2 PEKERJA ORG/HARI 0.07 130,000.00 8,666.67

II BAHAN
1 GEMBALAN RUMPUT M2 1.10 30,000.00 33,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 47,666.67


OVERHEAD + PROFIT (15%) 7,150.00
HARGA SATUAN PEKERJAAN 54,816.67
HARGA SATUAN PEKERJAAN DIBULATKAN 54,816.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PENUTUP ATAP


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,498.17
2 TUKANG ORG/HARI 0.07 150,000.00 9,996.67
3 PEKERJA ORG/HARI 0.13 130,000.00 17,327.56

II BAHAN
1 ATAP ZINCALUME 0.3 MM M2 1.43 63,000.00 90,027.00
2 SCREW CTEKS 12-4 x 50 BUAH 6.00 800.00 4,800.00
3 SCREW CTEKS 10 X 16-16 BUAH 2.00 1,000.00 2,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 130,149.39


OVERHEAD + PROFIT (15%) 19,522.41
HARGA SATUAN PEKERJAAN 149,671.80
HARGA SATUAN PEKERJAAN DIBULATKAN 149,671.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEKERJAAN RANGKA PARTISI


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,883.33
2 TUKANG ORG/HARI 0.07 150,000.00 10,803.02
3 PEKERJA ORG/HARI 0.29 130,000.00 37,450.49

II BAHAN
1 HOLLOW METAL FURING M' 7.20 22,000.00 158,400.00
2 ACCESSORIES % 5.00 1,100.00 5,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 224,536.84


OVERHEAD + PROFIT (15%) 33,680.53
HARGA SATUAN PEKERJAAN 258,217.36
HARGA SATUAN PEKERJAAN DIBULATKAN 258,217.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEKERJAAN PASANG PAPAN GYPSUM 2 MUKA


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.20 130,000.00 26,000.00

II BAHAN
1 GYPSUM BOARD LEMBAR 2.10 70,000.00 147,000.00
2 PAKU SEKRUP KG 0.22 55,000.00 12,100.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 201,350.00


OVERHEAD + PROFIT (15%) 30,202.50
HARGA SATUAN PEKERJAAN 231,552.50
HARGA SATUAN PEKERJAAN DIBULATKAN 231,552.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEKERJAAN KUSEN ALUMINIUM DAUN PINTU PANEL LAPIS HPL
SATUAN PEMBAYARAN : BH

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.50 165,000.00 82,500.00
2 TUKANG ORG/HARI 0.50 150,000.00 75,000.00
3 PEKERJA ORG/HARI 1.00 130,000.00 130,000.00

II BAHAN
1 PROFIL PINTU ALUMINIUM M2 2.84 350,000.00 992,250.00
2 HPL M2 4.73 245,000.00 1,157,625.00
3 SEALANT KG 0.06 30,000.00 1,800.00
4 NEOPRENE GASKET ROLL 2.50 110,000.00 275,000.00
5 STRUCTURAL SEALANT BUAH 1.00 24,000.00 24,000.00
6 ANGKUR PLAT BAJA BUAH 8.00 4,000.00 32,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 2,770,675.00


OVERHEAD + PROFIT (15%) 415,601.25
HARGA SATUAN PEKERJAAN 3,186,276.25
HARGA SATUAN PEKERJAAN DIBULATKAN 3,186,276.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEKERJAAN LIST PLAN LANTAI 10 CM


SATUAN PEMBAYARAN : M'

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33

II BAHAN
1 LIST PLAN KAYU 10 CM M 1.10 25,000.00 27,500.00
2 PAKU SKRUP KG 0.11 55,000.00 6,050.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 72,383.33


OVERHEAD + PROFIT (15%) 10,857.50
HARGA SATUAN PEKERJAAN 83,240.83
HARGA SATUAN PEKERJAAN DIBULATKAN 83,240.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : PEMBESIAN


SATUAN PEMBAYARAN : KG

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.00 165,000.00 471.43
2 TUKANG ORG/HARI 0.00 150,000.00 428.57
3 PEKERJA ORG/HARI 0.01 130,000.00 742.86

II BAHAN
1 BESI TULANGAN (POLOS/ULIR) KG 1.05 12,500.00 13,125.00
2 KAWAT BETON KG 0.02 40,000.00 600.00

III ALAT
1 ALAT BANTU LS 1.00 200.00 200.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 15,567.86


OVERHEAD + PROFIT (15%) 2,335.18
HARGA SATUAN PEKERJAAN 17,903.04
HARGA SATUAN PEKERJAAN DIBULATKAN 17,903.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : BEKISTING


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.40 130,000.00 52,000.00

II BAHAN
1 PAPAN BEKISTING M3 0.02 2,200,000.00 52,800.00
2 KASO 5/7 CM M3 0.01 3,500,000.00 35,000.00
3 PAKU KG 0.30 18,000.00 5,400.00
4 MINYAK BEKISTING LITER 0.20 5,000.00 1,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 178,200.00


OVERHEAD + PROFIT (15%) 26,730.00
HARGA SATUAN PEKERJAAN 204,930.00
HARGA SATUAN PEKERJAAN DIBULATKAN 204,930.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : RANGKA ATAP BAJA RINGAN 5 CM


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,600.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.16 130,000.00 20,800.00

II BAHAN
1 PROFIL C BAJA RINGAN M' 3.00 22,000.00 66,000.00
2 RENG BAJA RINGAN M' 2.00 11,000.00 22,000.00
3 DINABOLT KG 0.50 60,000.00 30,000.00
4 SEKRUP FIXER KG 0.50 55,000.00 27,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 179,400.00


OVERHEAD + PROFIT (15%) 26,910.00
HARGA SATUAN PEKERJAAN 206,310.00
HARGA SATUAN PEKERJAAN DIBULATKAN 206,310.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : GLASS BLOCK 20X20


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 GLASS BLOCK 20X20 UNIT 25.00 25,000.00 625,000.00
2 PASIR PASANG M3 0.05 225,000.00 10,125.00
3 SEMEN KG 9.68 1,400.00 13,552.00
4 - - -

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 705,652.00


OVERHEAD + PROFIT (15%) 105,847.80
HARGA SATUAN PEKERJAAN 811,499.80
HARGA SATUAN PEKERJAAN DIBULATKAN 811,499.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 M1 BALOK LATEI


SATUAN PEMBAYARAN : M1

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 COR BETON M3 0.02 1,299,602.00 25,992.04
2 BESI TULANGAN POLOS KG 11.60 12,500.00 145,000.00
3 -
4 -

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 227,967.04


OVERHEAD + PROFIT (15%) 34,195.06
HARGA SATUAN PEKERJAAN 262,162.10
HARGA SATUAN PEKERJAAN DIBULATKAN 262,162.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 M1 ringbalk


SATUAN PEMBAYARAN : M1

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00

II BAHAN
1 COR BETON M3 0.02 1,299,602.00 25,992.04
2 BESI TULANGAN POLOS KG 14.90 12,500.00 186,250.00
3 -
4 -

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 269,217.04


OVERHEAD + PROFIT (15%) 40,382.56
HARGA SATUAN PEKERJAAN 309,599.60
HARGA SATUAN PEKERJAAN DIBULATKAN 309,599.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Kolom H. BEAM 250x250x9x14 mm di bungkus ACP


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,155.00
2 KEPALA TUKANG ORG/HARI 0.65 150,000.00 97,500.00
3 TUKANG ORG/HARI 0.07 160,000.00 10,560.00
4 PEKERJA ORG/HARI 0.33 130,000.00 42,900.00

II BAHAN
1 ACP M3 1.10 840,000.00 924,000.00
2 HOLLOW 4X4X1MM KG 1.00 22,000.00 22,000.00
3 BRACKET BUAH 0.28 60,000.00 16,800.00
4
III ALAT
1 STAGER SET 0.02 110,000.00 2,200.00
2 LISTRIK KERJA LS 1.00 5,000.00 5,000.00
3 ALAT BANTU SET 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,122,615.00


OVERHEAD + PROFIT (15%) 168,392.25
HARGA SATUAN PEKERJAAN 1,291,007.25
HARGA SATUAN PEKERJAAN DIBULATKAN 1,291,007.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pekerjaan Ornamen Musholla - ACP + Cermin + Cutting MDF


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,155.00
2 KEPALA TUKANG ORG/HARI 0.65 150,000.00 97,500.00
3 TUKANG ORG/HARI 0.07 160,000.00 10,560.00
4 PEKERJA ORG/HARI 0.33 130,000.00 42,900.00

II BAHAN
1 ACP M2 1.10 840,000.00 924,000.00
2 HOLLOW 4X4X1MM M 1.00 22,000.00 22,000.00
3 BRACKET Buah 0.28 60,000.00 16,800.00
4 PAKU SCRUP KG 0.10 55,000.00 5,500.00
5 PAKU BETON DUS 0.20 22,000.00 4,400.00
6 SEALANT BUAH 0.25 25,000.00 6,250.00
7 KACA CERMIN M2 1.00 125,000.00 125,000.00

III ALAT
1 STAGER SET 0.02 110,000.00 2,200.00
2 LISTRIK KERJA LS 1.00 5,000.00 5,000.00
3 ALAT BANTU SET 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,263,765.00


OVERHEAD + PROFIT (15%) 189,564.75
HARGA SATUAN PEKERJAAN 1,453,329.75
HARGA SATUAN PEKERJAAN DIBULATKAN 1,453,329.00###
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Instalasi Lampu Downlight


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 TUKANG ORG/HARI 0.25 150,000.00 37,050.00
2 PEKERJA ORG/HARI 0.25 130,000.00 32,110.00

II BAHAN
1 Downlight BUAH 1.00 79,500.00 79,500.00
2 SKRUP BUAH 10.00 400.00 4,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 153,160.00


OVERHEAD + PROFIT (15%) 22,974.00
HARGA SATUAN PEKERJAAN 176,134.00
HARGA SATUAN PEKERJAAN DIBULATKAN 176,134.00###
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : pemasangan baja wf 150


SATUAN PEMBAYARAN : kg

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 990.00
2 TUKANG ORG/HARI 0.06 150,000.00 9,000.00
3 PEKERJA ORG/HARI 0.06 130,000.00 7,800.00

II BAHAN
1 Baja Profil WF 150 kg 1.10 21,238.10 23,361.90
2 Las kg 1.00 2,500.00 2,500.00
3 Zincromate + cat finishing m2 0.03 65,000.00 1,950.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 46,101.90


OVERHEAD + PROFIT (15%) 6,915.29
HARGA SATUAN PEKERJAAN 53,017.19
HARGA SATUAN PEKERJAAN DIBULATKAN 53,017.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 m3 Rabat Lantai


SATUAN PEMBAYARAN : m3

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 990.00
2 TUKANG ORG/HARI 0.60 150,000.00 90,000.00
3 PEKERJA ORG/HARI 1.20 130,000.00 156,000.00

II BAHAN
1 Semen kg 230.00 1,400.00 322,000.00
2 Pasir Beton m3 0.54 400,000.00 214,800.00
3 Kerilkil m3 0.57 550,000.00 314,050.00
4

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,098,340.00


OVERHEAD + PROFIT (15%) 164,751.00
HARGA SATUAN PEKERJAAN 1,263,091.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,263,091.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Saluran Urinoir


SATUAN PEMBAYARAN : M1

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.60 130,000.00 78,000.00

II BAHAN
1 Cor Beton M3 0.05 1,299,602.00 64,980.10
2
3
4

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 150,305.10


OVERHEAD + PROFIT (15%) 22,545.77
HARGA SATUAN PEKERJAAN 172,850.87
HARGA SATUAN PEKERJAAN DIBULATKAN 172,850.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Urugan pasir bawah lantai 10 cm


SATUAN PEMBAYARAN : M3

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 PEKERJA ORG/HARI 0.30 150,000.00 45,000.00

II BAHAN
1 PASIR PASANG M3 1.20 155,000.00 186,000.00
2
3
4

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 232,325.00


OVERHEAD + PROFIT (15%) 34,848.75
HARGA SATUAN PEKERJAAN 267,173.75
HARGA SATUAN PEKERJAAN DIBULATKAN 267,173.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Keramik lantai ruang Urinoir


SATUAN PEMBAYARAN : m2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 5,775.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.70 130,000.00 91,000.00

II BAHAN
1 SEMEN kg 1.14 1,400.00 1,596.00
2 SEMEN WARNA kg 0.50 17,000.00 8,500.00
3 PASIR PASANG m3 0.05 225,000.00 10,125.00
4 KERAMIK 20x20 buah 26.50 4,400.00 116,600.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 271,596.00


OVERHEAD + PROFIT (15%) 40,739.40
HARGA SATUAN PEKERJAAN 312,335.40
HARGA SATUAN PEKERJAAN DIBULATKAN 312,335.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Sealant Jendela


SATUAN PEMBAYARAN : m1

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,155.12
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00

II BAHAN
1 SEALANT BUAH 0.25 30,000.00 7,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 81,155.13


OVERHEAD + PROFIT (15%) 12,173.27
HARGA SATUAN PEKERJAAN 93,328.39
HARGA SATUAN PEKERJAAN DIBULATKAN 93,328.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 unit urinoir


SATUAN PEMBAYARAN : unit

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.13 130,000.00 16,250.00

II BAHAN
1 Urinoir buah 1.00 2,485,000.00 2,485,000.00
2 Semen kg 1.00 1,400.00 1,400.00
3 Pasir Pasang m3 0.50 155,000.00 77,500.00
4

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 2,626,400.00


OVERHEAD + PROFIT (15%) 393,960.00
HARGA SATUAN PEKERJAAN 3,020,360.00
HARGA SATUAN PEKERJAAN DIBULATKAN 3,020,360.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 unit kran dia. 1/2"


SATUAN PEMBAYARAN : unit

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 TUKANG ORG/HARI 0.40 150,000.00 60,000.00
3 PEKERJA ORG/HARI 0.01 130,000.00 1,300.00

II BAHAN
1 Kran buah 1.00 95,000.00 95,000.00
2 Seal buah 0.03 17,000.00 425.00
3
4

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 158,050.00


OVERHEAD + PROFIT (15%) 23,707.50
HARGA SATUAN PEKERJAAN 181,757.50
HARGA SATUAN PEKERJAAN DIBULATKAN 181,757.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 buah floor drain


SATUAN PEMBAYARAN : unit

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.01 130,000.00 1,300.00

II BAHAN
1 floor drain buah 1.00 75,000.00 75,000.00
2 -
3
4

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 92,625.00


OVERHEAD + PROFIT (15%) 13,893.75
HARGA SATUAN PEKERJAAN 106,518.75
HARGA SATUAN PEKERJAAN DIBULATKAN 106,518.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 m2 Waterproofing dak


SATUAN PEMBAYARAN : m2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.02 150,000.00 2,250.00
3 PEKERJA ORG/HARI 0.16 130,000.00 20,800.00

II BAHAN
1 waterproofing dumplix kg 0.45 625,000.00 281,250.00
2

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 307,275.00


OVERHEAD + PROFIT (15%) 46,091.25
HARGA SATUAN PEKERJAAN 353,366.25
HARGA SATUAN PEKERJAAN DIBULATKAN 353,366.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Instalasi Lampu Downlight


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 TUKANG ORG/HARI 0.25 150,000.00 37,050.00
2 PEKERJA ORG/HARI 0.25 130,000.00 32,110.00

II BAHAN
1 Downlight buah 1.00 79,500.00 79,500.00
2

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 149,160.00


OVERHEAD + PROFIT (15%) 22,374.00
HARGA SATUAN PEKERJAAN 171,534.00
HARGA SATUAN PEKERJAAN DIBULATKAN 171,534.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pasangan Calci-plank


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,550.00
2 KEPALA TUKANG ORG/HARI 0.02 160,000.00 3,520.00
3 TUKANG ORG/HARI 0.11 150,000.00 16,500.00
4 PEKERJA ORG/HARI 0.11 130,000.00 14,300.00

II BAHAN
1 KALSIPLANK M2 1.50 139,500.00 209,250.00
2 PAKU KG 0.12 18,000.00 2,070.00
3 PAKU SKRUP KG 0.10 55,000.00 5,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 263,190.00


OVERHEAD + PROFIT (15%) 39,478.50
HARGA SATUAN PEKERJAAN 302,668.50
HARGA SATUAN PEKERJAAN DIBULATKAN 302,668.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pekerjaan Peredam Ruangan


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.85 150,000.00 127,500.00
3 PEKERJA ORG/HARI 0.25 130,000.00 32,500.00

II BAHAN
1 glasswoll m2 1.30 58,333.33 75,833.33
2 Seal buah 0.25 17,000.00 4,250.00
3

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 242,233.33


OVERHEAD + PROFIT (15%) 36,335.00
HARGA SATUAN PEKERJAAN 278,568.33
HARGA SATUAN PEKERJAAN DIBULATKAN 278,568.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Galian Pondasi Tiang


SATUAN PEMBAYARAN : M3

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 4,125.00
2 PEKERJA ORG/HARI 0.80 130,000.00 104,000.00

II BAHAN
1
2
3

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 108,625.00


OVERHEAD + PROFIT (15%) 16,293.75
HARGA SATUAN PEKERJAAN 124,918.75
HARGA SATUAN PEKERJAAN DIBULATKAN 124,918.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : 1 m2 pasangan Rangka Atap


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 7,425.00
2 KEPALA TUKANG ORG/HARI 0.30 160,000.00 48,000.00
3 TUKANG ORG/HARI 0.70 150,000.00 105,000.00
4 PEKERJA ORG/HARI 0.35 130,000.00 45,500.00

II BAHAN
1 Main Truss m1 2.80 -
2 Roof Bottom R33-0.45 m1 5.10 11,000.00 56,100.00
3 Self Drilling Screw 6x20mm (truss Screw) bh 25.00 1,000.00 25,000.00
4 Self Drilling Screw 4x16mm(roof bottom screw) bh 35.00 800.00 28,000.00
5 Dynabolt bh 25.00 2,500.00 62,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 378,025.00


OVERHEAD + PROFIT (15%) 56,703.75
HARGA SATUAN PEKERJAAN 434,728.75
HARGA SATUAN PEKERJAAN DIBULATKAN 434,728.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pemasangan Tiang baja


SATUAN PEMBAYARAN : Titik

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.36 150,000.00 53,250.00
3 PEKERJA ORG/HARI 0.15 130,000.00 19,500.00

II BAHAN
1 Tiang Baja m 6.80 144,750.00 984,300.00
2 Las kg 1.00 26,000.00 26,000.00
3 Plat Besi kg 1.82 125,000.00 228,000.00
4 CAT BESI DASAR kg 0.45 80,000.00 36,000.00
5 CAT BESI FINISHING kg 0.50 80,000.00 40,000.00

III ALAT
1 ALAT BANTU LS 1.00 1,100.00 1,100.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,389,800.00


OVERHEAD + PROFIT (15%) 208,470.00
HARGA SATUAN PEKERJAAN 1,598,270.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,598,270.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pemasangan Kanopi


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1
2
3

II BAHAN
1 PENUTUP ATAP M2 1.00 130,149.39 130,149.39
2 PASANGAN RANGKA ATAP TITIK 1.00 378,025.00 378,025.00

III ALAT
1

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 508,174.39


OVERHEAD + PROFIT (15%) 76,226.16
HARGA SATUAN PEKERJAAN 584,400.55
HARGA SATUAN PEKERJAAN DIBULATKAN 584,400.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pekerjaan Pasangan Paving Block


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.13 150,000.00 19,522.50
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00

II BAHAN
1 PAVING BLOCK BUAH 25.00 6,500.00 162,500.00
2 PASIIR PASANG M3 0.15 155,000.00 23,250.00

III ALAT
1 ALAT BANTU SET 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 220,422.50


OVERHEAD + PROFIT (15%) 33,063.38
HARGA SATUAN PEKERJAAN 253,485.88
HARGA SATUAN PEKERJAAN DIBULATKAN 253,485.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Pemasangan Kabel NYY 4 x 16


SATUAN PEMBAYARAN : M1

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.00 165,000.00 165.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00

II BAHAN
1 KABEL NYY 4 x 16mm M1 1.00 209,000.00 209,000.00
2 Aksesoris LS 1.00 1,000.00 1,000.00

III ALAT
1 ALAT BANTU SET 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 238,665.00


OVERHEAD + PROFIT (15%) 35,799.75
HARGA SATUAN PEKERJAAN 274,464.75
HARGA SATUAN PEKERJAAN DIBULATKAN 274,464.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Rangka Pekerjaan Calci-plank


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.00 165,000.00 165.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.01 130,000.00 1,690.00

II BAHAN
1 BESI HOLLOW 40x40 Mm M1 3.50 99,250.00 347,375.00
2 Aksesoris LS 1.00 -

III ALAT
1 ALAT BANTU SET 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 387,230.00


OVERHEAD + PROFIT (15%) 58,084.50
HARGA SATUAN PEKERJAAN 445,314.50
HARGA SATUAN PEKERJAAN DIBULATKAN 445,314.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Rangka Atap


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 2,145.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.25 130,000.00 32,500.00

II BAHAN
1 BESI HOLLOW 40x40 mm M1 1.10 99,250.00 109,175.00
2 Las KG 1.00 26,000.00 26,000.00
3 Dyna bolt Buah 10.00 2,500.00 25,000.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 232,820.00


OVERHEAD + PROFIT (15%) 34,923.00
HARGA SATUAN PEKERJAAN 267,743.00
HARGA SATUAN PEKERJAAN DIBULATKAN 267,743.00
ANALISA HARGA
ITEM PEKERJAAN

ITEM PEKERJAAN : Talang


SATUAN PEMBAYARAN : M2

HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)

I TENAGA
1 MANDOR ORG/HARI 0.01 150,000.00 1,950.00
2 TUKANG ORG/HARI 0.25 160,000.00 40,000.00
3 PEKERJA ORG/HARI 0.25 165,000.00 41,250.00

II BAHAN
1 BESI HOLLOW 40x40 mm M1 1.10 99,250.00 109,175.00
2 Las KG 1.00 26,000.00 26,000.00
3 Dyna bolt Buah 10.00 2,500.00 25,000.00
4 Seng Plat Lembar 1.00 99,500.00 99,500.00

III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00

JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 343,375.00


OVERHEAD + PROFIT (15%) 51,506.25
HARGA SATUAN PEKERJAAN 394,881.25
HARGA SATUAN PEKERJAAN DIBULATKAN 394,881.00
DAFTAR HARGA UPAH DAN BAHAN
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. URAIAN SATUAN HARGA


(Rp.)
1 2 4 5

A TENAGA
1 PEKERJA/PEMBANTU TUKANG OH Rp. 130,000.00
2 TUKANG OPERATOR OH Rp. 150,000.00
3 KEPALA TUKANG OH Rp. 160,000.00
4 MANDOR OH Rp. 165,000.00

B BAHAN
1 KAYU KASO 5/7 M3 Rp. 3,500,000.00
2 KAYU BEKISTING M3 Rp. 2,200,000.00
3 KAYU MERANTI M3 Rp. 3,500,000.00
4 DOLKEN KAYU DIA. 8-10/400 CM BATANG Rp. 25,000.00
5 PLYWOOD 4 MM LEMBAR Rp. 70,000.00
6 SEMEN KG Rp. 1,400.00
7 SEMEN WARNA KG Rp. 17,000.00
8 PASIR BETON M3 Rp. 400,000.00
9 PASIR PASANG M3 Rp. 155,000.00
10 KORAL BETON M3 Rp. 550,000.00
11 BATU GUNUNG M3 Rp. 350,000.00
12 BATU BATA BUAH Rp. 850.00
13 PAKU KG Rp. 18,000.00
14 PAKU BETON DUS Rp. 22,000.00
15 SEKRUP KG Rp. 55,000.00
16 SEKRUP BUAH Rp. 400.00
17 PLAFON ASBES 3 MM LEMBAR Rp. 28,000.00
18 ASBES GELOMBANG LEMBAR Rp. 33,000.00
19 SENG GELOMBANG LEMBAR Rp. 74,500.00
20 SENG PLAT LEMBAR Rp. 99,500.00
21 ATAP ZINCALUME 0.3 MM LEMBAR Rp. 63,000.00
22 BETON MUTU K-175 M3 Rp. 1,593,000.00
23 BETON MUTU K-250 M3 Rp. 1,789,000.00
24 BETON MUTU K-300 M3 Rp. 1,823,000.00
25 PINTU DOUBEL TEAKWOOD M2 Rp. 150,000.00
No. URAIAN SATUAN HARGA
(Rp.)
1 2 4 5
26 JENDELA NAKO DAUN Rp. 400,000.00
27 CAT DINDING DASAR KG Rp. 54,000.00
28 CAT DINDING FINISHING INTERIOR KG Rp. 150,000.00
29 CAT DINDING FINISHING EXTERIOR KG Rp. 245,000.00
30 CAT BESI DASAR KG Rp. 80,000.00
31 CAT BESI FINISHING KG Rp. 80,000.00
32 PLAMIR KG Rp. 15,000.00
33 PREMIUM LITER Rp. 10,500.00
34 SOLAR LITER Rp. 11,500.00
35 MINYAK PELUMAS LITER Rp. 30,000.00
36 MINYAK BEKISTING LITER Rp. 5,000.00
37 AIR LITER Rp. 100.00
38 BESI BETON POLOS KG Rp. 12,500.00
39 BESI BETON ULIR KG Rp. 13,000.00
40 BESI BAJA KG Rp. 21,238.10
41 KAWAT BETON KG Rp. 25,000.00
42 HOMOGENIUS TILE 60 x 60 BUAH Rp. 100,000.00
43 PLINT HOMOGENIUS TILE 10 x 60 BUAH Rp. 17,000.00
44 GYPSUM BOARD 9 MM LEMBAR Rp. 70,000.00
45 HOLLOW METAL FURING METER Rp. 22,000.00
46 LIST PROFIL GYPSUM METER Rp. 40,000.00
47 TEPUNG GYPSUM KG Rp. 2,400.00
48 PROFIL ALUMUNIUM M Rp. 110,000.00
49 SEALENT KG Rp. 30,000.00
50 PINTU ALUMINIUM M Rp. 350,000.00
51 KUNCI TANAM SELINDER BUAH Rp. 260,000.00
52 KACA 5 MM M2 Rp. 162,640.00
53 ENGSEL BUAH Rp. 100,000.00
54 GRANDEL JENDELA BUAH Rp. 25,000.00
55 BESI STAINLESS STEEL DIA. 2" M Rp. 122,500.00
56 BESI STAINLESS STEEL DIA. 3" M Rp. 144,750.00
57 KAWAT LAS KG Rp. 26,000.00
58 LAMPU RM 2 x 18 WATT BUAH Rp. 380,000.00
59 LAMPU RM 3 x 36 WATT BUAH Rp. 420,000.00
60 PIPA LISTRIK 5/8" BATANG Rp. 22,800.00
61 KABEL NYM 3 x 2.5 MM M Rp. 21,250.00
62 KABEL NYY 4 x 16mm M Rp. 209,000.00
63 T DUS BUAH Rp. 3,000.00
64 L BOW BUAH Rp. 3,000.00
65 LAS DOP BUAH Rp. 2,500.00
66 KLEM BUAH Rp. 500.00
No. URAIAN SATUAN HARGA
(Rp.)
1 2 4 5
67 MANGKOK BUAH Rp. 5,000.00
68 SAKLAR BUAH Rp. 18,000.00
69 STOP KONTAK BUAH Rp. 18,000.00
70 STOP KONTAK AC BUAH Rp. 42,000.00
71 MCB - 1 PH (10 A) 10 KA BUAH Rp. 80,000.00
72 MCB - 3 PH (50 A) 10 KA BUAH Rp. 1,100,000.00
73 PIPA GALVANIS 3/4" M Rp. 60,000.00
74 SPLINKE BUAH Rp. 120,000.00
75 SMOKE DETECTOR BUAH Rp. 450,000.00
76 PLAT BORDES LEMBAR Rp. 185,000.00
77 BESI SIKU 40.40.4 M' Rp. 32,000.00
78 BESI HOLLOW 40x40 Mm M' Rp. 99,250.00
79 BESI HOLLOW 20x40 Mm M' Rp. 74,500.00
80 BESI HOLLOW Dia. 2" M' Rp. 99,250.00
81 KANSTEEN 15 x 20 x 30 x 50 CM, K-225 BUAH Rp. 40,000.00
82 GEMBALAN RUMPUT M2 Rp. 30,000.00
83 SCREW CTEKS 12-4 x 50 BUAH Rp. 800.00
84 SCREW CTEKS 10 X 16-16 BUAH Rp. 1,000.00
85 HPL M2 Rp. 255,000.00
86 NEOPRENE GASKET ROLL Rp. 22,000.00
87 STRUCTURAL SEALANT BUAH Rp. 24,000.00
88 ANGKUR PLAT BAJA BUAH Rp. 4,000.00
89 LIST PLAN KAYU 10 CM M Rp. 25,000.00
90 PROFIL C BAJA RINGAN M' Rp. 22,000.00
91 RENG BAJA RINGAN M' Rp. 11,000.00
92 DINABOLT BUAH Rp. 2,500.00
93 SEKRUP FIXER KG Rp. 55,000.00
94 PLAT BESI 2MM KG Rp. 125,000.00
95 DOWNLIGHT 4" BUAH Rp. 79,500.00
96 BRACKET BUAH Rp. 60,000.00
97 GLASS BLOCK BUAH Rp. 25,000.00
98 ACP LEMBAR Rp. 840,000.00
99 ZINC CHROMATE KG Rp. 65,000.00
100 KERAMIK 20x20 DUS Rp. 110,000.00
101 KERAMIK 20x20 BUAH Rp. 4,400.00
102 URINOIR BUAH Rp. 2,485,000.00
103 KRAN AIR BUAH Rp. 95,000.00
104 FLOOR DRAIN BUAH Rp. 75,000.00
105 CAT PELAPIS WATERPROOF KG Rp. 625,000.00
106 KALSIPLANK M2 Rp. 139,500.00
107 GLASSWOOL ROLL Rp. 1,750,000.00
108 GLASSWOOL M Rp. 58,333.33
109 BESI DIA. 16mm KG Rp. 8,391.00
No. URAIAN SATUAN HARGA
(Rp.)
1 2 4 5
110 GENTENG MULTIROOF 0.35MM LEMBAR Rp. 95,000.00
111 KACA CERMIN M2 Rp. 125,000.00
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
LANTAI 1 E

90
D

325
C

345
B

325
A
400 400 250 445 290 250

7 6 5 4 3 2 1
RENC. INSTALASI & TITIK LAMPU LT. 1
LANTAI 3
SKALA 1 : 100

90
D

325
C

345
B

325
A
400 400 250 445 290 250

7 6 5 4 3 2 1
RENC. INSTALASI & TITIK LAMPU LT. 3
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

IX.1.1 LANTAI 1
1 Pemasangan meteran listrik daya 33.000 watt - - - 1.00 1.00 Buah
2 Pasang lampu RM 2 x 18 w - - - 13.00 13.00 Buah
3 Instalasi titik lampu - - - 13.00 13.00 Titik
4 saklar serie - - - 3.00 3.00 Titik
5 Instalasi titik lampu - Downlight - - - 6.00 6.00 Titik
6 Pemasangan Kabel NYY 4 x 16 50.00 - - 1.00 50.00 M1

IX.1.2 LANTAI 3
1 Pasang lampu RM 3 x 36 w - - - 26.00 26.00 Buah
2 Instalasi titik lampu - - - 26.00 26.00 Titik
3 Saklar serie - - - 5.00 5.00 Titik
4 Stop kontak dinding, 1 Ph, 10 A - - - 16.00 16.00 Buah
5 Stop kontak AC - - - 11.00 11.00 Buah
6 Instalasi stop kontak - - - 16.00 16.00 Buah
7 Instalasi titik lampu - Downlight 3.00 3.00 Titik
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
E

90
D

325
C

345
B

325
A
400 400 250 445 290 250

7 6 5 4 3 2 1
RENC. INSTALASI & TITIK LAMPU LT. 3
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

IX.2.1 PP - 1 LANTAI 1
1 MCB - 1 Ph ( 10 A ) 10 KA - - bh

IX.2.2 PP - 3 LANTAI 3
1 MCB - 3 Ph ( 50 A ) 10 KA 1.00 1.00 bh
2 MCB - 1 Ph ( 10 A ) 10 KA 8.00 8.00 bh
3 Pilot lamp 3.00 3.00 bh
4 Fuse patron 3.00 3.00 bh
5 Kwh meter 1.00 1.00 bh
6 CU. Bar 4 x (12 mm x 2 mm) 3.00 3.00 lot
7 Box panel 1.00 1.00 bh
8 Kabel dalam panel 1.00 1.00 lot
9 Kawat BC - 6 mm2 1.00 1.00 lot
10 Material lain - lain 1.00 1.00 lot
11 Biaya pemasangan 1.00 1.00 lot
12 Instalasi Titik Lampu 3.00 3.00 titik
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

X.1 LANTAI 2
5 Pengadaan alat pemadam api ringan 5 kg 5.00 Buah

X.2 LANTAI 3
5 Pengadaan alat pemadam api ringan 5 kg 7.00 Buah
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

XI PEKERJAAN LANDSCAPE
1 Grill dilapisi besi plat bordes
- Besi siku 4.60 - - 2.00 9.20 M1
1.80 - - 1.00 1.80 M1
0.60 - - 5.00 3.00 M1
JUMLAH 14.00 M1

3 cor beton tebal 12 cm ( K-175) 9.40 0.50 0.08 1.00 0.38 M3

4 Pekerjaan kanopi
- kanopi tempat wudhu 10.22 0.85 - 1.00 8.69 M2
- kanopi depan Aula 12.65 0.85 - 1.00 10.75 M2
JUMLAH 19.44 M2

8 Penutup atap 0.77 0.77 - 60.00 35.71 M2


5.10 0.85 - 2.00 8.67 M2
44.38 M2

9 Pasangan Calci-plank 7.00 - 1.26 1.00 8.82 M2


2.50 - 1.50 1.00 3.75 M2
4.00 - 2.00 1.00 8.00 M2
JUMLAH 20.57 M2

10 Penutup Atap Selasar Penghubung 13.00 0.90 - 1.00 11.70 M2

11 Talang Air Selasar 13.00 0.30 - 1.00 3.90 M2


PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
220 60 120

50
SKETSA :
400
220 60 120

300
300
X X X

300
X X

300

275
PARKIRAN

300

1800
EL - 0,600

1800

325
300
Y

280
Y

80 200

280

260

140
460

60
260

140

60
EL - 0,200
PARKIRAN

120
400

75
EL - 0,600

140
60

60
60

120
300 300 290 200 120

80
50 1210

300 300 290 200 120


Y ATAP PARKIRAN
1210

2800 600 1200 1400 600 2600

450

300
300

ATAP SPANDEK ATAP SPANDEK

HOLLOW 40.40 HOLLOW 40.40

PIPA GALVANIS 4"


PIPA GALVANIS 4"

2700
2700

PAVING BLOCK PAVING BLOCK


300

300
2200 600 1200 800 600 2600
4000 4000

POT. X-X PARKIRAN POT. Y-Y PARKIRAN


SKALA 1:50 SKALA 1:50

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN


(M) (M) (M)
XIII PEKERJAAN AREA PARKIR
1 Pekerjaan pasangan Paving Block M2
12.00 17.31 - - 1.00 207.72 M2
JUMLAH 207.72 M2

2 Beton Pedestal 30.30.50


- Beton K-200 0.30 0.30 0.50 22.00 - 0.99 M3

Berat/m2
3 Pembesian - Angkur M16 - - 4.00 22.00 - 88.00 Buah
- Plat Strip 20.20.5 0.20 0.20 - 22.00 40.63 35.75 KG

4 Bekisting 0.30 - 0.50 22.00 - 3.30 M2

5 Penutup Atap - Spandex 18.50 4.80 - 1.00 - 88.80 M2


14.90 4.20 - 1.00 - 62.58 M2
JUMLAH 151.38 M2

6 Rangka Atap Baja Ringan 151.38 - - 1.00 - 151.38 M2

7 Tiang Galvanis 3.00 - - 11.00 - 33.00 M1


3.12 - - 11.00 - 34.31 M1
JUMLAH 67.31 M1

8 Pemasangan Tiang Baja - - - 11.00 - 11.00 Titik

9 Galian Pondasi Tiang 0.80 0.60 0.60 11.00 - 3.17 M3

10 Beton sikat
Depan teras musholla 4.28 2.26 - 1.00 - 9.68 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
E E

105

90
90
D D

200
T. WUDHU T. WUDHU

215
EL - 0.150 EL - 0.150
375

95
230
LAV. WANITA
R. SATKER EL + 4.000

325
128
EL + 4.000

325
87 LAV PRIA
EL + 4.000

350 245 100 290


C
C

1115
1190
MUSHOLLAH
EL ± 0.000

345
R.RAPAT
AULA EL + 4.000

345
EL - 0.100

900

900
B
B

325
325
A
400 400 250 445 290 250

A
400 400 250
985
445 290 250 7 6 5 4 3 2 1

7 6 5 4 3 2 1 DENAH LT. 2
2065 SKALA 1 : 100

DENAH LT. 1
1243 SKALA 1 : 100

90
D

OP COMMAND CENTER STAFF STAFF

325
340
+ 8.000

549
+ 8.000 + 8.000

785

1115
120

345
216 120 120 224

120 560
R. SERBA GUNA
640

+ 8.000 B

DSE STAFF
318

303

325
+ 8.000 DSE R. TEKNIS PPK
+ 8.000 + 8.000

A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 3
2050 SKALA 1 : 100

PANJANG LEBAR TINGGI JUMLAH


No. URAIAN VOLUME SATUAN
m m m
XIV Err:509
1 Err:509 - - - 1.00 1.00 LS

- LANTAI 1 12.45 11.90 - 1.00 148.16 M2


- LANTAI 2 20.65 11.15 - 1.00 230.25 M2
- LANTAI 3 20.50 11.15 - 1.00 228.58 M2
LUAS TOTAL 606.98 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 1.00 LS

4 Pengukuran Lokasi 49.40 1.00 1.00 M2

5 Alat dan keselamatan kerja ( K-3) 1.00 1.00 LS

6 Pembuatan papan nama proyek 1.00 1.00 Ls

7 Listrik Kerja 1.00 1.00 Ls

8 Air Kerja 1.00 1.00 Ls

9 Pagar Lokasi 60.00 1.00 60.00 M1


PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGAR: 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH

12.65 11.9
R BWS KALIMANTAN III

VOLUME SATUAN

24.55
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
430
SKETSA :
220 T. WUDHU
EL - 0.150
77 77 207 E

90
POMPA
D

185
45

80
335 315 45

325
58
C
MUSHOLLAH
EL ± 0.000

AULA

345
EL - 0.100

325
A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 1
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

II.1 Lantai 1
1 Pasangan batu bata ( 1 Pc : 5 Pasir ) 0.65 - - 4.00 - 1.00 2.60 M2
2.20 - - 4.00 - 1.00 8.80 M2
0.77 - - 4.00 - 2.00 6.16 M2
2.08 - - 4.00 - 1.00 8.31 M2
3.35 - - 4.00 - 1.00 13.40 M2
0.80 - - 4.00 - 2.00 6.40 M2
3.15 - - 4.00 - 1.00 12.60 M2
0.45 - - 4.00 - 1.00 1.80 M2
0.59 - - 2.50 - 1.00 1.47 M2
4.30 - - 4.00 - 1.00 17.20 M2
0.25 - - 1.22 - 4.00 1.22 M2
0.50 - - 1.22 - 4.00 2.44 M2
JUMLAH 82.41 M2

2 Plesteran dinding ( 1 Pc : 5 Pasir ) 82.41 - - - - 2.00 164.82 M2


Plesteran Kolom Pedestal (tempat wudhu) - 0.30 - 1.22 4.00 1.46 M2
- 0.25 - 1.22 4.00 1.22 M2
- 0.07 - 1.22 8.00 0.68 M2
LUAS PLESTERAN 168.19 M2

3 Kolom Praktis - - - 4.00 - 10.00 40.00 M1

4 Acian dinding 168.19 - - - - 1.00 168.19 M2


LUAS ACIAN 168.19 M2

Kolom H. BEAM 250x250x9x14 mm di bungkus beton


- - - 1.22 - 2.00 2.44 M1

5 Kolom H. BEAM 250x250x9x14 mm di bungkus ACP jumlah sisi jumlah tiang


- ACP - 0.25 0.10 3.50 4.00 9.00 44.10 M2
- 0.55 0.10 2.28 4.00 2.00 7.21 M2

JUMLAH 51.31 M2

6 Balok H.BEAM dibungkus ACP jumlah sisi Jumlah balok


- ACP 2.20 1.25 - - - 1.00 2.75 M2
4.15 1.25 - - - 1.00 5.19 M2
5.10 1.25 - - - 1.00 6.38 M2
2.95 1.25 - - - 1.00 3.69 M2
3.50 1.25 - - - 1.00 4.38 M2
JUMLAH 22.38 M2
No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

7 Pekerjaan Ornamen Musholla - ACP + Cermin + Cutting MDF


- ACP - 0.25 - 3.50 2.00 2.00 3.50 M2
- 0.45 - 3.50 1.00 2.00 3.15 M2
3.05 0.90 - - - 1.00 2.75 M2
JUMLAH 9.40 M2

8 Pengadaan dan Pemasangan Kaligrafi Mushalla 1.00 1.00 LS

8 Balok Latei 0.95 - - - - 2.00 1.90 M1

9 Ringbalk 0.85 - - - - 2.00 1.70 M1


2.15 - - - - 2.00 4.30 M1
1.00 - - - - 1.00 1.00 M1
1.30 - - - - 1.00 1.30 M1
2.70 - - - - 1.00 2.70 M1
3.40 - - - - 1.00 3.40 M1
14.40 M1

10 Benangan - 0.90 2.00 2.00 6.90 M1

11 Rabat Lantai Luas Tebal


- Teras 17.97 - - 0.05 - 1.00 0.90 M2
- Aula 86.26 - - 0.10 - 1.00 8.63 M2
- Ruang antara tempat wudhu 4.95 - - 0.05 - 1.00 0.25 M2
- Ruang wudhu Pria 6.75 - - 0.15 - 1.00 1.01 M2
- Ruang wudhu Wanita 8.72 - - 0.15 - 1.00 1.31 M2
Total luas 12.10 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA : E

90
D

AP COMMAND CENTER STAFF STAFF

498

325
310
+ 8.000 + 8.000 + 8.000

CR
378 285 jadi ppintu
geser

CR
68
224 224

345

230
438

318
B

555

318
R. TEKNIS PPK

325

335
STAFF
DSE + 8.000

203
+ 8.000

168
240
A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 3
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI VOLUME SATUAN


JUMLAH
(M) (M) (M)
II.2 LANTAI 3
1 Pasangan batu bata ( 1 Pc : 5 Pasir )
- 3.10 4.00 - 1.00 12.40 M2
- 0.88 2.00 - 1.00 1.76 M2
- 0.50 2.00 - 2.00 2.00 M2
- 1.08 2.00 - 2.00 4.32 M2
- 1.18 2.00 - 1.00 2.36 M2
- 1.25 2.00 - 2.00 5.00 M2
- 2.42 2.00 - 1.00 3.77 M2

JUMLAH 31.61 M2

2 Plesteran dinding ( 1 Pc : 5 Pasir ) (sisi yang diplester)


- Dinding 2.95 - 4.00 2.00 1.00 23.60 M2
3.15 - 4.00 1.00 1.00 12.60 M2
3.70 - 4.00 4.00 1.00 59.20 M2
0.60 - 4.00 1.00 1.00 2.40 M2
2.20 - 4.00 2.00 1.00 17.60 M2
4.15 - 4.00 2.00 1.00 33.20 M2
5.88 - 4.00 1.00 2.00 47.04 M2
3.75 - 4.00 1.00 2.00 30.00 M2
2.28 - 4.00 1.00 1.00 9.12 M2
3.85 - 4.00 1.00 1.00 15.40 M2
2.60 - 4.00 1.00 1.00 10.40 M2
3.10 - 4.00 1.00 2.00 24.80 M2
2.50 - 2.12 1.00 1.00 5.30 M2
3.38 - 2.12 1.00 1.00 7.17 M2
2.50 - 2.00 1.00 1.00 5.00 M2
0.93 - 2.00 1.00 1.00 1.86 M2
0.50 - 2.00 1.00 3.00 3.00 M2
0.65 - 2.00 1.00 1.00 1.30 M2
1.48 - 2.00 1.00 3.00 8.88 M2
1.25 - 2.00 1.00 2.00 5.00 M2
1.23 - 2.00 1.00 1.00 2.46 M2
2.14 - 1.00 1.00 2.00 4.28 M2
1.07 - 1.00 1.00 2.00 4.51 M2

JUMLAH 334.12 M2

PENGURANGAN
- Jendela 1.55 - 1.90 5.00 - 14.73 M2
2.30 - 1.90 10.00 - 43.70 M2
JUMLAH 58.43 M2
LUAS PLESTERAN 275.69 M2

3 Acian
- Plesteran Lantai 3 275.69 - - 1.00 - 275.69 M2
- Sisi Tangga 2.60 - 2.00 1.00 - 5.20 M2
3.00 - 2.00 0.50 - 3.00 M2
1.00 - 2.00 1.00 - 2.00 M2
3.85 - 2.00 1.00 - 7.70 M2
2.80 - 1.80 0.50 - 2.52 M2
JUMLAH 296.11 M2

4 Benangan
- Jendela - 2.30 1.90 - 10.00 61.00 M1
- 1.55 1.90 - 5.00 26.75 M1
- Pintu - 1.50 2.50 - 1.00 6.50 M1
- 1.00 2.15 - 3.00 15.90 M1
- 0.80 2.00 - 2.00 9.60 M1
JUMLAH 119.75 M1
No. Uraian Pekerjaan PANJANG LEBAR TINGGI VOLUME SATUAN
JUMLAH
(M) (M) (M)
5 Kolom H-beam berat / m'
lantai 2 4.00 3.00 14.00 168.00 KG

6 Balok Iwf 150 2.40 3.00 14.00 100.80 KG


3.46 1.00 14.00 48.44 KG
1.30 1.00 14.00 18.20 KG
5.11 1.00 14.00 71.54 KG
1.65 1.00 14.00 23.10 KG
JUMLAH 262.08 KG

7 Beton tebal
- balkon 3.46 2.40 0.12 - 1.00 1.00 M3
1.65 1.30 0.12 - 1.00 0.26 M3
- atap dak ruangan urinoir 3.55 2.58 0.12 - 1.00 1.10 M3
JUMLAH 2.36 M3

10 Glass Block - 0.20 0.20 - 6.00 0.24 M2

11 Rabat Lantai 2.55 1.20 0.20 - 1.00 0.61 M3


2.80 0.90 0.20 - 1.00 0.50 M3
1.12 M3

12 Saluran Urinoir - drain 2.80 - - - 1.00 2.80 M1

13 Ringbalk Ruang Urinoir 9.80 - - - 1.00 9.80 M1


PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
E

90
D

AP COMMAND CENTER STAFF STAFF

498

325
310
+ 8.000 + 8.000 + 8.000

CR
378 285 jadi ppintu
geser

CR
68
224 224

345

230
438

318
B
555

318
R. TEKNIS PPK

325

335
STAFF
DSE + 8.000

203
+ 8.000

168
240
A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 3
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN


(M) (M) (M)
II.2 LANTAI 2

1 Kolom H. BEAM 250x250x9x14 mm di bungkus ACP


Lantai 2 1.60 - 3.50 3.00 16.80 M2

Jumlah 16.80 M2

2 Balok H.BEAM dibungkus ACP


Lantai 2 5.10 1.25 - 1.00 6.38 M2
2.50 1.25 - 1.00 3.13 M2

Jumlah 9.50 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA

T. WUDHU
EL - 0.150
E

90
POMPA
D E

90
D

325
HOMOGENIUS HOMOGENIUS HOMOGENIUS
60x 60 60x 60 60x 60

325
POLA
C
LANTAI
EXISTING C
- 100 HOMOGENIUS
60x 60

345
- 100 HOMOGENIUS
HOMOGENIUS
60x 60

345
60x 60 HOMOGENIUS
60x 60
B
HOMOGENIUS
60x 60 B

325
HOMOGENIUS
HOMOGENIUS

325
HOMOGENIUS 60x 60
60x 60 60x 60
A
400 400 250 445 290 250

7 6 5 4 3 2 1 A
400 400 250 445 290 250

RENC. POLA LANTAI 1 7 6 5 4 3 2 1


SKALA 1 : 100

RENC. POLA LANTAI 3


No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SKALA 1 : 100
SATUAN
(M) (M) (M)
III.1 LANTAI 1
1 Lantai homogenius 60 cm x 60 cm( Polished) 9.30 9.78 - 1.00 90.95 M2
JUMLAH 90.95 M2
Pengurangan
- Kolom 30.30 0.30 0.30 - 16.00 1.44 M2
- Kolom 40.60 0.40 0.60 - 1.00 0.24 M2
- Kolom 15.15 (KP) 0.15 0.15 - 2.00 0.05 M2
- Ruang dan spasi bawah tangga 2.50 3.20 - 1.00 8.00 M2
JUMLAH 9.73 M2
LUAS KERAMIK LANTAI 1 81.23 M2

2 Keramik Dinding Ruang wudhu 0.95 1.25 2.00 2.38 M2


3.26 1.25 1.00 4.07 M2
2.55 1.25 1.00 3.19 M2
JUMLAH 9.64 M2

3 Keramik Lantai Ruang Wudhu 3.35 2.00 - 1.00 6.70 M2


2.30 2.15 - 1.00 4.94 M2
3.75 2.00 - 1.00 7.50 M2
1.28 0.87 - 1.00 1.11 M2
8.80 - 0.10 1.00 0.88 M2
JUMLAH 21.14 M2

4 Plin Lantai 13.60 - - 1.00 13.60 M1


Plin Kolom 1.28 - 0.10 6.00 0.77 M1
1.28 - 0.20 3.00 0.77 M1
JUMLAH 15.14 M1

5 Urugan pasir bawah lantai 10 cm 9.30 9.78 0.10 1.00 9.10 M3

III.2 LANTAI 2
1 Lantai Homogeneus tangga
- Optrade 1.24 - 0.18 22.00 4.91 M2
- Aantrade 1.24 0.30 - 21.00 7.81 M2
- Bordes 2.68 1.05 - 1.00 2.81 M2
2.60 0.15 - 1.00 0.39 M2
JUMLAH 15.93 M2

2 Plint Tangga 16.20 - - 1.00 16.20 M1

3 Keramik Balkon 6.10 2.48 - 1.00 15.13 M2


7 6 5 4 3 2 1 A
400 400 250 445 290 250

RENC. POLA LANTAI 1 7 6 5 4 3 2 1


SKALA 1 : 100

RENC. POLA LANTAI 3


No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SKALA 1 : 100
SATUAN
(M) (M) (M)
III.3 LANTAI 3
1 Lantai homogenius 60 cm x 60 cm( Polished) 18.08 11.15 - 1.00 201.59 M2
JUMLAH 201.59 M2

Pengurangan
Void Tangga 4.35 2.83 - 1.00 12.31 M2
kolom 30.30 0.30 0.30 - 15.00 1.35 M2
dinding 3.70 0.15 - 4.00 2.22 M2
3.15 0.15 - 2.00 0.95 M2
2.95 0.15 - 2.00 0.89 M2
0.60 0.15 - 1.00 0.09 M2
2.20 0.15 - 2.00 0.66 M2
4.15 0.15 - 2.00 1.25 M2
3.25 0.15 - 1.00 0.49 M2
5.93 0.15 - 1.00 0.89 M2
3.75 0.15 - 1.00 0.56 M2
2.33 0.15 - 1.00 0.35 M2
JUMLAH 21.99 M2
LUAS LANTAI 3 179.60 M2

2 Plin keramik 10 x 60 cm 72.76 - - 1.00 72.76 M1


JUMLAH 72.76 M1

3 Lapisan creed 3 cm - 7 cm 179.60 M2


JUMLAH 179.60 M2

4 Keramik lantai ruang Urinoir 2.57 - 0.95 1.00 2.44 M2


2.80 - 2.33 1.00 6.52 M2
8.97 M2
- Pengurangan
0.15 - 0.50 2.00 0.15 M2
0.15 - 1.38 2.00 0.41 M2
0.15 - 0.25 2.00 0.08 M2
0.64 M2

LUAS LANTAI URINOIR 8.33 M2

5 Keramik Dinding ruang Urinoir 1.00 - 1.05 6.00 6.30 M2


1.46 - 1.28 1.00 1.87 M2
- Pengurangan 0.44 - 0.23 1.00 0.10 M2
JUMLAH 8.07 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN


(M) (M) (M)
IV.1 Lantai 1
1 Plafond gypsum 12.28 9.05 - 1.00 111.14 M2
3.35 1.85 - 1.00 6.20 M2
4.86 1.85 - 1.00 9.00 M2
0.96 1.28 - 1.00 1.23 M2
127.57 M2
Pengurangan
- Kolom 30.30 0.30 0.30 - 7.00 0.63 M2
- Kolom 40.60 0.40 0.60 - 1.00 0.24 M2
- Kolom 30.30 0.30 0.30 - 1.00 0.09 M2
- Ruang dan spasi bawah tangga 2.50 3.20 - 1.00 8.00 M2
JUMLAH 8.96 M2
LUAS LANTAI 1 118.61 M2

2 Rangka Plafond Hollow metal Furing 129.37 1.00 129.37 M2

3 List Flapond Gypsum


- List Keliling 49.62 - - 1.00 49.63 M1
- Sisi Kolom 0.30 0.30 - 7.00 0.63 M1

JUMLAH 50.26 M1

4 Plafond Gypsum Canopy 12.65 0.85 - 1.00 10.76 M2

IV.2 LANTAI 3
1 Plafond gypsum 18.00 11.15 1.00 200.70 M2
JUMLAH 200.70 M2

Pengurangan
- Kolom 30.30 0.30 0.30 - 16.00 1.44 M2
- dinding 2.95 0.15 - 2.00 0.89 M2
3.15 0.15 - 2.00 0.95 M2
3.70 0.15 - 4.00 2.22 M2
0.60 0.15 - 1.00 0.09 M2
2.20 0.15 - 2.00 0.66 M2
4.15 0.15 - 2.00 1.25 M2
2.60 0.15 - 1.00 0.39 M2
3.85 0.15 - 1.00 0.58 M2
7.38 0.15 - 1.00 1.11 M2
3.60 0.15 - 1.00 0.54 M2
3.25 0.15 - 1.00 0.49 M2
2.68 0.15 - 1.00 0.40 M2
3.26 0.15 - 1.00 0.49 M2
JUMLAH 11.48 M2
LUAS LANTAI 3 189.23 M2
No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN
(M) (M) (M)

2 Rangka Plafond Hollow metal Furing 189.23 - - 1.00 189.23 M2

3 List Flapond Gypsum


List Keliling - Ruang Teknis PPK 11.70 - - 1.00 11.70 M1
- Ruang Staff 44.13 - - 1.00 44.13 M1
- Ruang OPC Centre 22.65 - - 1.00 22.65 M1
- ruang Serbaguna 21.69 - - 1.00 21.69 M1
- Void Tangga 20.55 - - 1.00 20.55 M1

JUMLAH 120.72 M1

IV. 3 LANTAI 2
1 List Plafond - Ruang Administrasi & Rapat 27.75 - - 1.00 27.75 M1

2 Plafond gypsum 5.65 2.57 - 1.00 14.52 M2

3 Rangka Plafond Hollow metal Furing 14.52 - - 1.00 14.52 M2


PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN


(M) (M) (M)
V.1 LANTAI 1
1 Pengecatan dinding luar 82.41 1.00 82.41 M2

2 Pengecatan dinding dalam 82.41 1.00 82.41 M2

3 Pengecatan plafond gypsum 129.37 1.00 129.37 M2

4 Pengecatan list plafond gypsum 50.26 1.00 50.26 M1

V.2 LANTAI 3
1 Pengecatan dinding dalam 296.11 1.00 296.11 M2

2 Pengecatan plafond gypsum 189.23 1.00 189.23 M2

3 Pengecatan list plafond gypsum 120.72 1.00 120.72 M1


V.3 LANTAI 2
1 Pengecatan dinding dalam 54.52 1.00 54.52 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
LANTAI 1

600 500 500 500 550 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500

300
2500 4451 2900 2500

5 4 3 2 1

TAMPAK DEPAN PENUTUP ATAP TAMBAHAN


SKALA 1:50

P2
1000x2150

J3 J3 ± 0,000 J2 J3 P2

LANTAI 3 2240x1900

+ 0,600
2240x1900

+ 0,600
1550x1900

+ 0,600
2240x1900

+ 0,600
1000x2150

± 0,000

90
D

J3 STAFF
AP COMMAND CENTER STAFF

325
2240x1900 + 8.000 + 8.000 + 8.000

+ 0,600

P2 C
1000x2150
P1
± 0,000
J3 1900x2500

345
2240x1900 J2 ± 0,000

+ 0,600 1550x1900

B P2
1000x2150

J3 J3 ± 0,000

325
STAFF R. TEKNIS PPK
2240x1900 DSE + 8.000 2240x1900
+ 8.000
+ 0,600 + 0,600

A
400 400 250 445 290 250

7 6 5 4 3 2 1
J3 J3 J2 J3 J2
2240x1900 2240x1900 1550x1900 2240x1900 1550x1900

+ 0,600 + 0,600 + 0,600 + 0,600 + 0,600

RENC. KUSEN LT. 3


SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

VI.1 LANTAI 1

1 Pemasangan Kaca tebal 5 mm


- 12.00 - 0.10 1.00 1.20 M2
Jumlah 1.20 M2

2 Pemasangan Pintu Geser Alumunium - - - 1.00 1.00 unit

3 Kusen Pintu Alumunium - 0.90 2.00 1.00 4.90 M1

VI.1.2 LANTAI 2
1 Perbaikan Jendela - Sealant - 2.24 1.90 7.00 57.96 M1
- 1.50 1.90 2.00 13.60 M1
Jumlah 71.56 M1

2 Pembuatan kusen pintu alumunium 4"


- rangka - - 2.53 6.00 15.18 M1
- 1.05 - 6.00 6.30 M1
Jumlah 21.48 M1

- kusen - - 2.01 2.00 4.02 M1


- 0.97 - 4.00 3.88 M1
- 0.42 - 2.00 0.85 M1
Jumlah 8.75 M1
Total Panjang Alumunium Lantai 2 30.23 M1
No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

3 Pemasangan kaca tebal 5 mm


- kaca mati - 0.82 1.86 3.00 4.58 M2
- 0.82 0.44 3.00 1.08 M2
Jumlah 5.66 M2

4 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) 3.00 3.00 Unit

VI.2 LANTAI 3
1 Pembuatan kusen pintu alumunium 4"
- J2 - 1.51 1.90 5.00 51.15 M1
- J3 - 2.24 1.90 10.00 143.20 M1
- P1 - 1.90 2.50 1.00 8.80 M1
- P2 - 1.07 2.15 1.00 5.37 M1
JUMLAH 208.52 M1

2 Pembuatan Jendela alumunium Jumlah daun Jendela


- J2 2.00 - 5.00 10.00 Unit
- J3 3.00 - - 10.00 30.00 Unit
JUMLAH 40.00 Unit

3 Pasang engsel jungkit 40.00 - - 2.00 80.00 Unit


4 Grendel jendela 40.00 - - 1.00 40.00 Unit
5 Pemasangan kaca tebal 5 mm
- Daun Jendela - 0.60 1.37 40.00 32.88 M2
- kaca mati - 0.72 0.34 40.00 9.79 M2
JUMLAH 42.68 M2

6 Pemasangan 1 pintu kaca dan kusen allumunium ( 2 daun) - - - 1.00 1.00 Unit
7 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) - - - 3.00 3.00 Unit

8 Glass block 0.20 0.20 - 6.00 0.24 M2

9 Pemasangan Kusen + Pintu Alu. Ruangan Urinoir - - - 1.00 1.00 set


PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA : 220
430

T. WUDHU
EL - 0.150
8 12 91 91 12 8 77 77 207 E

90
POMPA
D

185
45

80
5
13 13 10 10 10 10 10 10 13

335 315 45

325
58
C

80
MUSHOLLAH

100
EL ± 0.000

AULA

345
EL - 0.100

10 5

325
8 213 8
A
220 400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 1
SKALA 1 : 100

PANJANG LEBAR TINGGI


No. Uraian Pekerjaan (M) (M) (M)
JUMLAH VOLUME SATUAN

VII.1 LANTAI 1
Railing
Hollow 40.40.0,4 1.00 8.00 8.00 M1
2.20 2.00 4.40 M1
4.15 2.00 8.30 M1
2.80 2.00 5.60 M1
3.13 2.00 6.26 M1
JUMLAH 32.56 M1
Hollow 20.40.0,4
0.03 12.00 0.36 M1
0.12 12.00 1.44 M1
0.74 12.00 8.88 M1
0.80 12.00 9.60 M1
0.84 14.00 11.76 M1
0.82 28.00 22.96 M1
1.17 14.00 16.38 M1
0.60 28.00 16.80 M1
JUMLAH 88.18 M1

Railing Pintu
1 Hollow 40.40.0,4 1.00 4.00 4.00 M1
0.90 4.00 3.60 M1
0.80 4.00 3.20 M1
0.70 4.00 2.80 M1
JUMLAH 13.60 M1

2 Hollow 20.40.0,4 0.03 4.00 0.12 M1


0.12 4.00 0.48 M1
0.74 4.00 2.96 M1
0.80 4.00 3.20 M1
0.26 28.00 7.28
0.45 14.00 6.30 M1
JUMLAH 20.34 M1
Total
Hollow 40.40.0,4 46.16 M1
Hollow 20.40.0,4 108.52 M1
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
E

90
D

8 12 91 91 12 8

325
5
13 13 10 10 10 10 10 10 13

CR
C

CR
80

100

345

230
10 5
B
8 213 8

220
R. TEKNIS PPK

325
+ 8.000

203

168
240
A
290 250

3 2 1
TOP
EL + 2.120
DENAH LT. 3
D1 D1 SKALA 1 : 100

D1 D1 D1 D1 D1
UR UR
CR CR

CR CR

C2 C2

E D C

PANJANG LEBAR TINGGI


No. Uraian Pekerjaan JUMLAH VOLUME SATUAN
(M) (M) (M)
VIII.1 LANTAI 1
1 Railing Teras 16.20 - - 1.00 16.20 M1

VIII.2 LANTAI 2
1 Handrail stainless steel dia 2 " 9.00 - - 1.00 9.00 M1
2 Railing Balkon 5.87 - - 1.00 5.87 M2

VIII.3 LANTAI 3
1 Railing Balkon 8.40 - - 1.00 8.40 m1
2 Railing Sisi Urinoir 0.80 - - 1.00 0.80 m2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN


(M) (M) (M)
VIII PEKERJAAN SANITARI / FIXTURES
VIII.1 LANTAI 2
1 Tissue holder - - - - - buah
2 Tempat sabun - - - - - buah
3 Kaca cermin tebal 5 mm 200 cm x 100 cm 2.00 1.00 - - - M2
4 Tandon air 1200 Lt Stainless - - - - - unit

VIII.2 LANTAI 3
1 Urinoir - - - 2.00 2.00 unit
2 Pasangan Kran - - - 2.00 2.00 buah
3 pasangan Floor Drain - - - 2.00 2.00 buah
4 Waterproofing 5.55 2.31 - 1.00 12.82 M2
2.35 1.02 - 1.00 2.40 M2
LUAS Waterproofing 15.22 M2

VIII.3 Pasangan Kran


1 Lantai 1 - - - 6.00 6.00 buah
2 Lantai 3 - - - 2.00 2.00 buah
8.00 buah
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :

90
D
LAV. WANITA
R. SATKER EL + 4.000

325
EL + 4.000

368
LAV PRIA
EL + 4.000

45 C
370

100

345
R.RAPAT
EL + 4.000

100
B
177

368

325
PPK

166
PERENCANA
EL + 4.000

A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 2
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

XII.1 LANTAI 2
XII.1.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi 3.00 - 3.50 1.00 10.50 M2
5.35 - 3.50 1.00 18.72 M2
1.10 - 1.22 1.00 1.34 M2
3.05 - 1.22 1.00 3.72 M3
3.50 - 1.22 1.00 4.27 M2
Jumlah 38.56 M2

- PENGURANGAN
Bukaan pintu 1.05 - 2.52 1.00 2.65 M2
Jumlah Rangka partisi 35.91 M2

2 Pekerjaan pasang papan gypsum 2 muka 35.91 - - 2.00 71.82 M2


3 Pekerjaan Kusen Pintu - - - - 1.00 buah
4 Pekerjaan list plan lantai 10 cm 32.13 - - 1.00 32.13 M1
5 Pekerjaan List Plafond Gypsum 16.85 - - 1.00 16.85 M1
6 Pengecatan pengecatan 71.82 - - 1.00 71.82 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

90
D
LAV. WANITA
R. SATKER EL + 4.000

325
EL + 4.000

368
LAV PRIA
EL + 4.000

45 C
370

100

345
R.RAPAT
EL + 4.000

100
B
177

368

325
PPK

166
PERENCANA
EL + 4.000

A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 2
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

XII.1 LANTAI 2
XII.1.2 PARTISI RUANG RAPAT
1 Pekerjaan rangka partisi
4.65 - 3.50 2.00 32.55 M2
Jumlah 32.55 M2

- Pengurangan
Bukaan Pintu - 1.05 2.52 2.00 5.29 M2
Jumlah Rangka partisi 27.26 M2

2 Pekerjaan pasang papan gypsum 2 muka 27.26 2.00 54.52 M2

3 Pekerjaan Kusen Pinttu 3.00 Buah

4 Pekerjaan list plan lantai 10 cm


3.68 4.00 14.72 M1
JUMLAH 14.72 M1

5 Pekerjaan list gypsum


5.45 - - 2.00 10.90 M1
JUMLAH 10.90 M1

6 Pekerjaan pengecatan 54.52 1.00 54.52 M2


PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021

SKETSA :
E

90
D

AP COMMAND CENTER STAFF STAFF

498

325
310
+ 8.000 + 8.000 + 8.000

CR
455 208

CR
68
224 224

345
438

318
B

555

318
R. TEKNIS PPK

325
STAFF
DSE + 8.000

203
+ 8.000

A
400 400 250 445 290 250

7 6 5 4 3 2 1
DENAH LT. 3
SKALA 1 : 100

No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN

XII.1 LANTAI 3
XII.2.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi 20.07 - 1.22 1.00 24.49 M2
14.83 - 3.50 1.00 51.91 M2
76.40 M2

- Pengurangan bukaan pintu - 1.05 2.52 2.00 5.29 M2


JUMLAH 71.11 M2

2 Pekerjaan pasang papan gypsum 2 muka 71.11 - - 2.00 142.22 M2

3 Pekerjaan Kusen Pintu Alumunium 3.00 3.00 Buah

Pekerjaan Rangka Alumunium atas partisi 20.07 - - 1.00 20.07 M1

Pekerjaan Pemasangan Kaca 5mm atas partisi 20.07 1.00 1.22 20.00 24.40 M2

4 Pekerjaan list plan lantai 10 cm 0.15 - - 5.00 0.75 M1


12.70 - - 2.00 25.40 M1
20.07 - - 2.00 40.14 M1
JUMLAH 66.29 M1

5 Pekerjaan list gypsum 14.83 - - 2.00 29.66 M1


4.27 - - 1.00 4.27 M1
JUMLAH 33.93 M1

6 Pekerjaan pengecatan 142.22 - - 1.00 142.22 M2

7 Pekerjaan Peredam Ruangan 18.47 3.50 1.00 64.64 M2


ANALISA TEKNIK
ITEM PEKERJAAN
PEMBONGKARAN BANGUNAN LAMA

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
PRODUKTIFITAS PER HARI 4.500 M2 PEMBONGKARAN BANGUNAN LAMA
VOLUME PEKERJAAN : 8.82 M2
BAHAN, ALAT DAN TENAGA
BAHAN

ALAT WAKTU PELAKSANAAN YANG DIPERLUKAN


DUMP TRUCK PEMBONGKARAN BANGUNAN LAMA
KAPASITAS BAK 3.500 M3 MASA PELAKSANAAN 1.96 HARI
FAKTOR EFESINSI ALAT 0.800 2.00 HARI
KECEPATAN RATA-RATA BERMUATAN 20.000 KM/JAM
KECEPATAN RATA-RATA KOSONG 30.000 KM/JAM
SIKLUS WAKTU
- MEMUAT 3.779 MENIT
- WAKTU TEMPUH ISI 0.600 MENIT
- WAKTU TEMPUH KOSONG 0.400 MENIT
- LAIN-LAIN 2.000 MENIT
6.779 TS1
KAP. PRODUKSI/JAM 12.908 Q1

KOEFISIEN ALAT / M3 0.077 JAM

ALAT BANTU 1.000 LS


- PALU
- SEKOP
- GEROBAK DORONG
- DLL

TENAGA
PRODUKSI 4.500 M2/HARI
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- PEKERJA 6.000 ORG

KOEFESIEN TENAGA / BUAH :


- MANDOR 0.222 HARI
- PEKERJA 1.333 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GUDANG DAN BARAK KERJA

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
PRODUKTIFITAS PER HARI 7.500 M2 GUDANG DAN BARAK KERJA
VOLUME PEKERJAAN : 10.00 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- KAYU 5/7 0.250 M3
- PLYWOOD 4 MM 1.000 LEMBAR
- PAKU 0.750 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- PLAFON ASBES 3 MM 1.240 LEMBAR GUDANG DAN BARAK KERJA
- ASBES GELOMBANG 0.300 LEMBAR MASA PELAKSANAAN 1.33 HARI
- FLOOR LANTAI 0.150 M3 2.00 HARI
- PINTU DOUBEL TEAKWOOD 0.100 M2
- JENDELA NAKO 1.000 DAUN
- CAT DINDING/PLAFON 0.201 KG

ALAT
ALAT BANTU 1.000 LS
- PALU
- SEKOP
- GEROBAK DORONG
- DLL

TENAGA
PRODUKSI 7.500 M2/HARI
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 6.000 ORG

KOEFESIEN TENAGA / BUAH :


- MANDOR 0.133 HARI
- TUKANG 0.133 HARI
- PEKERJA 0.800 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGUKURAN LOKASI

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 100.000 M2 PENGUKURAN LOKASI
VOLUME PEKERJAAN : 49.40 M2
BAHAN, ALAT DAN TENAGA
BAHAN

WAKTU PELAKSANAAN YANG DIPERLUKAN


ALAT PENGUKURAN LOKASI
ALAT UKUR 1.000 Ls MASA PELAKSANAAN 0.49 HARI
- GPS 1.00 HARI
- TOTAL STATION
- METERAN ROLL

TENAGA
PRODUKSI PER HARI 100.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.010 HARI
- TUKANG 0.010 HARI
- PEKERJA 0.030 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PAGAR LOKASI

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 20.000 M' PAGAR LOKASI
VOLUME PEKERJAAN : 15.00 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- DOLKEN KAYU DIA. 8-10/400 CM 1.050 BATANG
- SEMEN 2.500 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- SENG GELOMBANG 1.050 LEMBAR PAGAR LOKASI
- PASIR BETON 0.005 M3 MASA PELAKSANAAN 0.75 HARI
- KORAL BETON 0.009 M3 1.00 HARI
- KAYU 5/7 0.062 M3
- PAKU BIASA 0.060 KG
- CAT BESI 0.450 KG

ALAT
ALAT BANTU 1.000 Ls

TENAGA
PRODUKSI PER HARI 20.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.200 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN BATU BATA (1 PC : 5 PASIR)

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 10.200 M2 PEMASANGAN BATU BATA (1 PC : 5 PASIR)
VOLUME PEKERJAAN : 66.75 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- BATA MERAH 70.000 BUAH
- SEMEN 9.680 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- PASIR PASANG 0.045 M3 PEMASANGAN BATU BATA (1 PC : 5 PASIR)
MASA PELAKSANAAN 6.54 HARI
ALAT 7.00 HARI
ALAT BANTU 1.000 LS
- SENDOK CAMPURAN
- SEKOP
- GEROBAK DORONG
- DLL

TENAGA
PRODUKSI PER HARI 10.200 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 6.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.098 HARI
- TUKANG 0.196 HARI
- PEKERJA 0.588 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PLESTERAN DINDING (1 PC : 5 PASIR)

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 17.800 M2 PLESTERAN DINDING (1 PC : 5 PASIR)
VOLUME PEKERJAAN : 357.94 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 5.184 KG
- PASIR PASANG 0.026 M3 WAKTU PELAKSANAAN YANG DIPERLUKAN
PLESTERAN DINDING (1 PC : 5 PASIR)
ALAT MASA PELAKSANAAN 20.11 HARI
ALAT BANTU 1.000 LS 21.00 HARI
- SENDOK CAMPURAN
- SEKOP
- DLL

TENAGA
PRODUKSI PER HARI 17.800 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.056 HARI
- TUKANG 0.056 HARI
- PEKERJA 0.169 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
KOLOM PRAKTIS

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 120.000 M' KOLOM PRAKTIS
VOLUME PEKERJAAN : 22.50 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- KAYU BEKISTING 0.002 M3
- PAKU 0.010 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- MINYAK BEKISTING 0.090 LITER KOLOM PRAKTIS
- BESI BETON POLOS 3.000 KG MASA PELAKSANAAN 0.19 HARI
- KAWAT BETON 0.450 KG 1.00 HARI
- SEMEN 4.000 KG
- PASIR BETON 0.060 M3
- KORAL BETON 0.009 M3

ALAT
ALAT BANTU 1.000 LS
- PALU
- PEMOTONG BESI
- GERGAJI
- DLL

TENAGA
PRODUKSI PER HARI 120.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.008 HARI
- TUKANG 0.008 HARI
- PEKERJA 0.033 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
ACIAN DINDING

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 24.920 M2 ACIAN DINDING
VOLUME PEKERJAAN : 300.00 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 3.250 KG
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT ACIAN DINDING
ALAT BANTU 1.000 LS MASA PELAKSANAAN 12.04 HARI
- SENDOK ACIAN 13.00 HARI
- DLL

TENAGA
PRODUKSI PER HARI 24.920 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.161 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
BENANGAN

URAIAN KOEF. SAT WAKTU YANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 100.000 M' BENANGAN
VOLUME PEKERJAAN : 222.00 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 5.184 KG
- PASIR PASANG 0.026 M3 WAKTU PELAKSANAAN YANG DIPERLUKAN
BENANGAN
ALAT MASA PELAKSANAAN 2.22 HARI
ALAT BANTU 1.000 LS 3.00 HARI
- SENDOK CAMPURAN
- DLL

TENAGA
PRODUKSI PER HARI 100.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.010 HARI
- TUKANG 0.020 HARI
- PEKERJA 0.040 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
KOLOM H. BEAM 250x250x9x14 MM DIBUNGKUS BETON TUL. DIA 8 MM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 16.000 M' KOLOM H. BEAM 250x250x9x14 MM DIBUNGKUS BETON TUL. DIA 8 MM
VOLUME PEKERJAAN : 37.50 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- BAJA H. BEAM 14.483 KG
- BESI TULANGAN 4.740 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
KOLOM H. BEAM 250x250x9x14 MM DIBUNGKUS BETON TUL. DIA 8 MM
ALAT MASA PELAKSANAAN 2.34 HARI
ALAT BANTU 1.000 Ls 3.00 HARI
- TRIPOT
- WATERPASS
- SLING

TENAGA
PRODUKSI PER HARI 16.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 8.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.063 HARI
- TUKANG 0.063 HARI
- PEKERJA 0.500 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LANTAI HOMOGENIUS 60 CM X 60 CM (POLISHED)

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 22.200 M2 LANTAI HOMOGENIUS 60 CM X 60 CM (POLISHED)
VOLUME PEKERJAAN : 204.54 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 9.600 KG
- SEMEN WARNA 1.500 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- PASIR PASANG 0.045 M3 LANTAI HOMOGENIUS 60 CM X 60 CM (POLISHED)
- KERAMIK 60X60 (POLISHED) 3.100 BUAH MASA PELAKSANAAN 9.21 HARI
10.00 HARI
ALAT
ALAT BANTU 1.000 Ls
- SENDOK CAMPURAN
- SEKOP
- DLL

TENAGA
PRODUKSI PER HARI 22.200 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.045 HARI
- TUKANG 0.090 HARI
- PEKERJA 0.180 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LANTAI HOMOGENIUS TANGGA

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 22.200 M2 LANTAI HOMOGENIUS TANGGA
VOLUME PEKERJAAN : 45.33 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 9.600 KG
- SEMEN WARNA 1.500 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- PASIR PASANG 0.045 M3 LANTAI HOMOGENIUS TANGGA
- KERAMIK 60X60 (POLISHED) 3.100 BUAH MASA PELAKSANAAN 2.04 HARI
3.00 HARI
ALAT
ALAT BANTU 1.000 Ls
- SENDOK CAMPURAN
- SEKOP
- DLL

TENAGA
PRODUKSI PER HARI 22.200 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.045 HARI
- TUKANG 0.090 HARI
- PEKERJA 0.180 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PLIN KERAMIK 10 CM x 60 CM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.000 M' PLIN KERAMIK 10 CM x 60 CM
VOLUME PEKERJAAN : 76.75 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 1.140 KG
- SEMEN WARNA 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- PASIR PASANG 0.003 M3 PLIN KERAMIK 10 CM x 60 CM
- PLIN KERAMIK 10X60 1.700 BUAH MASA PELAKSANAAN 3.07 HARI
4.00 HARI
ALAT
ALAT BANTU 1.000 Ls
- SENDOK CAMPURAN
- SEKOP
- DLL

TENAGA
PRODUKSI PER HARI 25.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.080 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LAPIS CREED 3 CM - 7 CM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 87.566 M2 LAPIS CREED 3 CM - 7 CM
VOLUME PEKERJAAN : 159.21 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- SEMEN 22.250 KG
- PASIR PASANG 0.039 M3 WAKTU PELAKSANAAN YANG DIPERLUKAN
LAPIS CREED 3 CM - 7 CM
ALAT MASA PELAKSANAAN 1.82 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- SENDOK CAMPURAN
- SEKOP
- DLL

TENAGA
PRODUKSI PER HARI 87.566 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.011 HARI
- TUKANG 0.011 HARI
- PEKERJA 0.046 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PLAFOND GYPSUM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 166.992 M2 PLAFOND GYPSUM
VOLUME PEKERJAAN : 278.32 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- GYPSUM BOARD 9 MM 0.375 LEMBAR
- PAKU SEKRUP 0.110 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PLAFOND GYPSUM
ALAT MASA PELAKSANAAN 1.67 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- PALU
- BOR BAUT
- DLL

TENAGA
PRODUKSI PER HARI 166.992 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.006 HARI
- TUKANG 0.006 HARI
- PEKERJA 0.024 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RANGKA PLAFOND HOLLOW METAL FURING

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 27.832 M2 RANGKA PLAFOND HOLLOW METAL FURING
VOLUME PEKERJAAN : 278.32 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- HOLLOW METAL FURING 4.100 M'
- SEKRUP 0.110 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
RANGKA PLAFOND HOLLOW METAL FURING
ALAT MASA PELAKSANAAN 10.00 HARI
ALAT BANTU 1.000 Ls 10.00 HARI
- PALU
- BOR BAUT
- DLL

TENAGA
PRODUKSI PER HARI 27.832 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.036 HARI
- TUKANG 0.036 HARI
- PEKERJA 0.144 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LIST PLAFOND GYPSUM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 70.000 M' LIST PLAFOND GYPSUM
VOLUME PEKERJAAN : 99.48 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- LIST GYPSUM PROFIL 1.050 M'
- TEPUNG GYPSUM 0.150 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
LIST PLAFOND GYPSUM
ALAT MASA PELAKSANAAN 1.42 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- SENDOK CAMPURAN
- KUAS
- DLL

TENAGA
PRODUKSI PER HARI 70.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.014 HARI
- TUKANG 0.014 HARI
- PEKERJA 0.029 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN DINDING LUAR

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.400 M2 PENGECATAN DINDING LUAR
VOLUME PEKERJAAN : 34.75 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- PLAMUR TEMBOK 0.100 KG
- CAT TEMBOK DASAR 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- CAT TEMBOK FINISHNG 0.100 KG PENGECATAN DINDING LUAR
MASA PELAKSANAAN 1.37 HARI
ALAT 2.00 HARI
ALAT BANTU 1.000 Ls
- KUAS
- SCAFOLDING
- DLL

TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN DINDING DALAM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.400 M2 PENGECATAN DINDING DALAM
VOLUME PEKERJAAN : 254.76 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- PLAMUR TEMBOK 0.100 KG
- CAT TEMBOK DASAR 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- CAT TEMBOK FINISHNG 0.100 KG PENGECATAN DINDING DALAM
MASA PELAKSANAAN 10.03 HARI
ALAT 11.00 HARI
ALAT BANTU 1.000 Ls
- KUAS
- SCAFOLDING
- DLL

TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN PLAFOND GYPSUM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.400 M2 PENGECATAN PLAFOND GYPSUM
VOLUME PEKERJAAN : 278.32 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- CAT DASAR 0.100 KG
- CAT FINISHNG 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PENGECATAN PLAFOND GYPSUM
ALAT MASA PELAKSANAAN 10.96 HARI
ALAT BANTU 1.000 Ls 11.00 HARI
- KUAS
- SCAFOLDING
- DLL

TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN LIST PLAFOND GYPSUM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 127.000 M' PENGECATAN LIST PLAFOND GYPSUM
VOLUME PEKERJAAN : 99.48 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- CAT DASAR 0.100 KG
- CAT FINISHNG 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PENGECATAN LIST PLAFOND GYPSUM
ALAT MASA PELAKSANAAN 0.78 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- KUAS
- SCAFOLDING
- DLL

TENAGA
PRODUKSI PER HARI 127.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.008 HARI
- TUKANG 0.008 HARI
- PEKERJA 0.016 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN KOLOM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 26.900 M2 PENGECATAN KOLOM
VOLUME PEKERJAAN : 70.40 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- PLAMUR TEMBOK 0.100 KG
- CAT TEMBOK DASAR 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- CAT TEMBOK FINISHNG 0.100 KG PENGECATAN KOLOM
MASA PELAKSANAAN 2.62 HARI
ALAT 3.00 HARI
ALAT BANTU 1.000 Ls
- KUAS
- SCAFOLDING
- DLL

TENAGA
PRODUKSI PER HARI 26.900 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.037 HARI
- TUKANG 0.037 HARI
- PEKERJA 0.074 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBUATAN KUSEN ALUMINIUM 4"

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 52.000 M' PEMBUATAN KUSEN ALUMINIUM 4"
VOLUME PEKERJAAN : 405.96 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- PROFIL ALUMINIUM 1.100 M
- SEKRUP 2.000 BUAH WAKTU PELAKSANAAN YANG DIPERLUKAN
- SEALENT 0.060 KG PEMBUATAN KUSEN ALUMINIUM 4"
MASA PELAKSANAAN 7.81 HARI
ALAT 8.00 HARI
ALAT BANTU 1.000 Ls
- GERGAJI BESI
- MESIN PEMOTONG
- DLL

TENAGA
PRODUKSI PER HARI 52.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.019 HARI
- TUKANG 0.019 HARI
- PEKERJA 0.038 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBUATAN PINTU ALUMINIUM (2 DAUN)

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 4.000 UNIT PEMBUATAN PINTU ALUMINIUM (2 DAUN)
VOLUME PEKERJAAN : 1.00 UNIT
BAHAN, ALAT DAN TENAGA
BAHAN
- PROFIL ALUMINIUM 6.000 M
- DAUN PINTU ALUMINIUM 2.100 M WAKTU PELAKSANAAN YANG DIPERLUKAN
- KUNCI TANAM SELINDER 2.000 BUAH PEMBUATAN PINTU ALUMINIUM (2 DAUN)
MASA PELAKSANAAN 0.25 HARI
ALAT 1.00 HARI
ALAT BANTU 1.000 Ls
- GERGAJI BESI
- MESIN PEMOTONG
- DLL

TENAGA
PRODUKSI PER HARI 4.000 UNIT
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.250 HARI
- TUKANG 0.250 HARI
- PEKERJA 0.500 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN KACA TEBAL 5 MM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 32.000 M2 PEMASANGAN KACA TEBAL 5 MM
VOLUME PEKERJAAN : 48.92 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- KACA 5 MM 1.050 M2
- SEALENT 0.050 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PEMASANGAN KACA TEBAL 5 MM
ALAT MASA PELAKSANAAN 1.53 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- PEMOTONG KACA
- KOP KACA
- DLL

TENAGA
PRODUKSI PER HARI 32.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 1.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.031 HARI
- TUKANG 0.063 HARI
- PEKERJA 0.031 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBUATAN PINTU ALUMINIUM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 4.000 UNIT PEMBUATAN PINTU ALUMINIUM
VOLUME PEKERJAAN : 38.00 UNIT
BAHAN, ALAT DAN TENAGA
BAHAN
- DAUN PINTU ALUMINIUM 2.100 M
- KUNCI TANAM SELINDER 1.000 BUAH WAKTU PELAKSANAAN YANG DIPERLUKAN
PEMBUATAN PINTU ALUMINIUM
ALAT MASA PELAKSANAAN 9.50 HARI
ALAT BANTU 1.000 Ls 10.00 HARI
- GERGAJI BESI
- MESIN PEMOTONG
- DLL

TENAGA
PRODUKSI PER HARI 4.000 UNIT
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.250 HARI
- TUKANG 0.250 HARI
- PEKERJA 0.500 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN ENGSEL JUNGKIT

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 50.000 BUAH PEMASANGAN ENGSEL JUNGKIT
VOLUME PEKERJAAN : 76.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- ENGSEL 1.000 BUAH
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT PEMASANGAN ENGSEL JUNGKIT
ALAT BANTU 1.000 Ls MASA PELAKSANAAN 1.52 HARI
- OBENG 2.00 HARI
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 50.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.020 HARI
- TUKANG 0.020 HARI
- PEKERJA 0.040 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GRANDEL JENDELA

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 35.000 BUAH GRANDEL JENDELA
VOLUME PEKERJAAN : 38.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- GRANDEL JENDELA 1.000 BUAH
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT GRANDEL JENDELA
ALAT BANTU 1.000 Ls MASA PELAKSANAAN 1.09 HARI
- OBENG 2.00 HARI
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 35.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.029 HARI
- TUKANG 0.029 HARI
- PEKERJA 0.057 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RAILLING TANGGA

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 60.000 M' RAILLING TANGGA
VOLUME PEKERJAAN : 26.40 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- BESI STAINLESS STEEL DIA. 2" 9.570 M
- KAWAT LAS 0.479 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
RAILLING TANGGA
ALAT MASA PELAKSANAAN 0.44 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- MESIN PEMOTONG
- MESIN LAS
- DLL

TENAGA
PRODUKSI PER HARI 60.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.017 HARI
- TUKANG 0.017 HARI
- PEKERJA 0.050 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
KACA CERMIN TEBAL 5 MM 200 CM x 100 CM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 140.000 M2 KACA CERMIN TEBAL 5 MM 200 CM x 100 CM
VOLUME PEKERJAAN : 2.00 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- CERMIN TEBAL 5 MM 1.100 M2
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT KACA CERMIN TEBAL 5 MM 200 CM x 100 CM
ALAT BANTU 1.000 Ls MASA PELAKSANAAN 0.01 HARI
- PEMOTONG KACA 1.00 HARI
- KOP KACA
- DLL

TENAGA
PRODUKSI PER HARI 140.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.007 HARI
- TUKANG 0.007 HARI
- PEKERJA 0.014 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PASANG LAMPU RM 2 x 18 WATT

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 20.000 BUAH PASANG LAMPU RM 2 x 18 WATT
VOLUME PEKERJAAN : 12.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- LAMPU RM 2 x 18 WATT 1.000 BUAH
- ACCESSORIES 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
PASANG LAMPU RM 2 x 18 WATT
ALAT MASA PELAKSANAAN 0.60 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 20.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.100 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI TITIK LAMPU

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 15.000 TITIK INSTALASI TITIK LAMPU
VOLUME PEKERJAAN : 36.00 TITIK
BAHAN, ALAT DAN TENAGA
BAHAN
- PIPA LISTRIK 5/8" 1.000 BATANG
- KABEL NYM 3 x 2.5 MM 6.000 M WAKTU PELAKSANAAN YANG DIPERLUKAN
- T DUS 1.000 BUAH INSTALASI TITIK LAMPU
- L BOW 1.000 BUAH MASA PELAKSANAAN 2.40 HARI
- LAS DOP 1.000 BUAH 3.00 HARI
- KLEM 4.000 BUAH
- MANGKOK 1.000 BUAH

ALAT
ALAT BANTU 1.000 Ls
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 15.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
SAKLAR SERIE

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 45.000 TITIK SAKLAR SERIE
VOLUME PEKERJAAN : 6.00 TITIK
BAHAN, ALAT DAN TENAGA
BAHAN
- SAKLAR SERIE 1.000 BUAH
- PERLENGKAPAN INSTALASI 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
SAKLAR SERIE
ALAT MASA PELAKSANAAN 0.13 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 45.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.022 HARI
- TUKANG 0.022 HARI
- PEKERJA 0.044 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PASANG LAMPU RM 3 x 36 WATT

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 30.000 BUAH PASANG LAMPU RM 3 x 36 WATT
VOLUME PEKERJAAN : 24.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- LAMPU RM 3 x 36 WATT 1.000 BUAH
- ACCESSORIES 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
PASANG LAMPU RM 3 x 36 WATT
ALAT MASA PELAKSANAAN 0.80 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 30.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.033 HARI
- TUKANG 0.033 HARI
- PEKERJA 0.100 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
STOP KONTAK DINIDNG, 1 PH, 10 A

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 45.000 BUAH STOP KONTAK DINIDNG, 1 PH, 10 A
VOLUME PEKERJAAN : 10.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- STOP KONTAK DINIDNG, 1 PH, 10 A 1.000 BUAH
- PERLENGKAPAN INSTALASI 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
STOP KONTAK DINIDNG, 1 PH, 10 A
ALAT MASA PELAKSANAAN 0.22 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 45.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.022 HARI
- TUKANG 0.022 HARI
- PEKERJA 0.044 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
STOP KONTAK AC

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 45.000 BUAH STOP KONTAK AC
VOLUME PEKERJAAN : 8.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- STOP KONTAK AC 1.000 BUAH
- PERLENGKAPAN INSTALASI 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
STOP KONTAK AC
ALAT MASA PELAKSANAAN 0.18 HARI
ALAT BANTU 1.000 Ls 1.00 HARI
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 45.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.022 HARI
- TUKANG 0.022 HARI
- PEKERJA 0.044 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI STOP KONTAK

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 15.000 BUAH INSTALASI STOP KONTAK
VOLUME PEKERJAAN : 10.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- PIPA LISTRIK 5/8" 1.000 BATANG
- KABELNYM 3 x 2.5 MM 6.000 M WAKTU PELAKSANAAN YANG DIPERLUKAN
- T DUS 2.000 BUAH INSTALASI STOP KONTAK
- L BOW 2.000 BUAH MASA PELAKSANAAN 0.67 HARI
- LAS DOP 2.000 BUAH 1.00 HARI
- KLEM 4.000 BUAH
- MANGKOK 1.000 BUAH

ALAT
ALAT BANTU 1.000 Ls
- OBENG
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 15.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
MCB - 1 PH (10 A) 10 KA

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 20.000 BUAH MCB - 1 PH (10 A) 10 KA
VOLUME PEKERJAAN : 4.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- MCB - 1 PH (10 A) 10 KA 1.000 BUAH
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT MCB - 1 PH (10 A) 10 KA
ALAT BANTU 1.000 Ls MASA PELAKSANAAN 0.20 HARI
- OBENG 1.00 HARI
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 20.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.100 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
MCB - 3 PH (50 A) 10 KA

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 5.000 BUAH MCB - 3 PH (50 A) 10 KA
VOLUME PEKERJAAN : 4.00 BUAH
BAHAN, ALAT DAN TENAGA
BAHAN
- MCB - 3 PH (50 A) 10 KA 1.000 BUAH
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT MCB - 3 PH (50 A) 10 KA
ALAT BANTU 1.000 Ls MASA PELAKSANAAN 0.80 HARI
- OBENG 1.00 HARI
- TANG
- DLL

TENAGA
PRODUKSI PER HARI 5.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.200 HARI
- TUKANG 0.200 HARI
- PEKERJA 0.400 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI PIPA SPLINKER

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 10.000 TITIK INSTALASI PIPA SPLINKER
VOLUME PEKERJAAN : 18.00 TITIK
BAHAN, ALAT DAN TENAGA
BAHAN
- PIPA GALVANIS 3/4" 25.000 METER
- PERLENGKAPAN INSTALASI 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
INSTALASI PIPA SPLINKER
ALAT MASA PELAKSANAAN 1.80 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- MESIN LAS
- MESIN GERGAJI BESI
- DLL

TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN SPLINKER

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 10.000 TITIK PEMASANGAN SPLINKER
VOLUME PEKERJAAN : 18.00 TITIK
BAHAN, ALAT DAN TENAGA
BAHAN
- SPLINKE 1.000 BUAH
- ACCESSORIES 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
PEMASANGAN SPLINKER
ALAT MASA PELAKSANAAN 1.80 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- MESIN LAS
- MESIN GERGAJI BESI
- DLL

TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI SMOKE DETECTOR

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 10.000 TITIK INSTALASI SMOKE DETECTOR
VOLUME PEKERJAAN : 18.00 TITIK
BAHAN, ALAT DAN TENAGA
BAHAN
- PIPA GALVANIS 3/4" 15.000 METER
- PERLENGKAPAN INSTALASI 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
INSTALASI SMOKE DETECTOR
ALAT MASA PELAKSANAAN 1.80 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- MESIN LAS
- MESIN GERGAJI BESI
- DLL

TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN SMOKE DETECTOR

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 10.000 TITIK PEMASANGAN SMOKE DETECTOR
VOLUME PEKERJAAN : 18.00 TITIK
BAHAN, ALAT DAN TENAGA
BAHAN
- SMOKE DETECTOR 1.000 BUAH
- ACCESSORIES 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
PEMASANGAN SMOKE DETECTOR
ALAT MASA PELAKSANAAN 1.80 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- MESIN LAS
- MESIN GERGAJI BESI
- DLL

TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GRILL DI LAPISI BESI PLAT BORDES

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 15.000 M' GRILL DI LAPISI BESI PLAT BORDES
VOLUME PEKERJAAN : 50.00 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- PLAT BORDES 0.667 LEMBAR
- BESI SIKU 40.40.4 2.000 M' WAKTU PELAKSANAAN YANG DIPERLUKAN
GRILL DI LAPISI BESI PLAT BORDES
ALAT MASA PELAKSANAAN 3.33 HARI
ALAT BANTU 1.000 Ls 4.00 HARI
- MESIN PEMOTONG
- MESIN LAS
- DLL

TENAGA
PRODUKSI PER HARI 15.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RAILING PAGAR

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 20.000 M' RAILING PAGAR
VOLUME PEKERJAAN : 41.40 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- BESI HOLLOW 40x40 CM 7.800 M'
- KAWAT LAS 0.390 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
RAILING PAGAR
ALAT MASA PELAKSANAAN 2.07 HARI
ALAT BANTU 1.000 Ls 3.00 HARI
- MESIN PEMOTONG
- MESIN LAS
- DLL

TENAGA
PRODUKSI PER HARI 20.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.200 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
COR BETON TEBAL 12 CM (K-175)

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 7.200 M3 COR BETON TEBAL 12 CM (K-175)
VOLUME PEKERJAAN : 0.84 M3
BAHAN, ALAT DAN TENAGA
BAHAN
SEMEN 229.278 KG
PASIR BETON 0.352 M3 WAKTU PELAKSANAAN YANG DIPERLUKAN
KERIKIL 0.634 M3 COR BETON TEBAL 12 CM (K-175)
AIR 215.000 LTR MASA PELAKSANAAN 0.12 HARI
1.00 HARI
ALAT
CONCRETE MIXER 1.000 Ls
DIPERLUKAN ALAT BANTU ANTARA LAIN :
CONCRETE MIXER
KAPASITAS ALAT 300.000 V
FAKTOR EFESIEN ALAT 0.830 Fa
WAKTU SIKLUS :
- MEMUAT 5.000 T1
- MENGADUK 4.000 T2
- MENUANG 5.000 T3
- MENUNGGU, DLL 7.000 T4
21.000 Ts

KAP. PROD/JAM = 0.711 Q1


1.406 Jam

CONCRETE VIBRATOR
KEBUTUHAN ALAT PENGGETAR BETON INI DISESUAIKAN
DENGAN KAPASITAS PRODUKSI ALAT PENCAMPUR
(CONCRETE MIXER )

KAP. PROD/JAM = Q2 Q1
Jam Jam

TENAGA
PRODUKSI PER HARI 7.200 M3
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 8.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.139 HARI
- TUKANG 0.278 HARI
- PEKERJA 1.111 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN KANOPI

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 20.000 M2 PEKERJAAN KANOPI
VOLUME PEKERJAAN : 95.35 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- BESI HOLLOW 40x40 CM 2.100 M'
- KAWAT LAS 0.105 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- ATAP ZINCALUME 0.3 MM 1.100 M2 PEKERJAAN KANOPI
MASA PELAKSANAAN 4.77 HARI
ALAT 5.00 HARI
ALAT BANTU 1.000 Ls
- MESIN PEMOTONG
- MESIN LAS
- DLL

TENAGA
PRODUKSI PER HARI 20.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.150 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN KANSTEEN

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.000 M' PEKERJAAN KANSTEEN
VOLUME PEKERJAAN : 55.80 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- KANSTEEN 15 x 20 x 30 x 50 CM, K-225 2.000 BUAH
- SEMEN 0.086 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
- PASIR PASANG 0.010 M3 PEKERJAAN KANSTEEN
MASA PELAKSANAAN 2.23 HARI
ALAT 3.00 HARI
ALAT BANTU 1.000 Ls
- SENDOK CAMPURAN
- GEROBAK DORONG
- DLL

TENAGA
PRODUKSI PER HARI 25.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.160 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN KANSTEEN

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.400 M2 PENGECATAN KANSTEEN
VOLUME PEKERJAAN : 33.48 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- CAT DASAR 0.100 KG
- CAT FINISHNG 0.100 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PENGECATAN KANSTEEN
ALAT MASA PELAKSANAAN 1.32 HARI
ALAT BANTU 1.000 Ls 2.00 HARI
- KUAS
- SIKAT
- DLL

TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GEMBALAN RUMPUT

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 30.000 M2 GEMBALAN RUMPUT
VOLUME PEKERJAAN : 44.64 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- GEMBALAN RUMPUT 1.100 M2
WAKTU PELAKSANAAN YANG DIPERLUKAN
ALAT GEMBALAN RUMPUT
ALAT BANTU 1.000 Ls MASA PELAKSANAAN 1.49 HARI
- KUAS 2.00 HARI
- SCAFOLDING
- DLL

TENAGA
PRODUKSI PER HARI 30.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.033 HARI
- PEKERJA 0.067 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENUTUP ATAP

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 30.010 M2 PENUTUP ATAP
VOLUME PEKERJAAN : 40.80 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- ATAP ZINCALUME 0.3 MM 1.429 M2
- SCREW CTEKS 12-4 x 50 6.000 BUAH WAKTU PELAKSANAAN YANG DIPERLUKAN
- SCREW CTEKS 10 X 16-16 2.000 BUAH PENUTUP ATAP
MASA PELAKSANAAN 1.36 HARI
ALAT 2.00 HARI
ALAT BANTU 1.000 Ls
- MESIN PEMOTONG
- MESIN LAS
- DLL

TENAGA
PRODUKSI PER HARI 30.010 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.033 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN RANGKA PARTISI

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 13.885 M2 PEKERJAAN RANGKA PARTISI
VOLUME PEKERJAAN : 71.30 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- HOLLOW METAL FURING 7.200 M'
- ACCESSORIES 5.000 % WAKTU PELAKSANAAN YANG DIPERLUKAN
PEKERJAAN RANGKA PARTISI
ALAT MASA PELAKSANAAN 5.14 HARI
ALAT BANTU 1.000 Ls 6.00 HARI
- MESIN PEMOTONG
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 13.885 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.072 HARI
- TUKANG 0.072 HARI
- PEKERJA 0.288 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN PASANG PAPAN GYPSUM 2 MUKA

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 20.000 M2 PEKERJAAN PASANG PAPAN GYPSUM 2 MUKA
VOLUME PEKERJAAN : 142.60 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- GYPSUM BOARD 0.728 LEMBAR
- PAKU SEKRUP 0.220 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PEKERJAAN PASANG PAPAN GYPSUM 2 MUKA
ALAT MASA PELAKSANAAN 7.13 HARI
ALAT BANTU 1.000 Ls 8.00 HARI
- PALU
- BOR BAUT
- DLL

TENAGA
PRODUKSI PER HARI 20.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.200 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN KUSEN ALUMINIUM DAUN PINTU PANEL LAPIS HPL

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 2.000 BH PEKERJAAN KUSEN ALUMINIUM DAUN PINTU PANEL LAPIS HPL
VOLUME PEKERJAAN : 4.00 BH
BAHAN, ALAT DAN TENAGA
BAHAN
- ROFIL PINTU ALUMINIUM 2.835 M2
- HPL 4.725 M2 WAKTU PELAKSANAAN YANG DIPERLUKAN
- SEALANT 0.060 KG PEKERJAAN KUSEN ALUMINIUM DAUN PINTU PANEL LAPIS HPL
- NEOPRENE GASKET 2.500 ROLL MASA PELAKSANAAN 2.00 HARI
- STRUCTURAL SEALANT 1.000 BUAH 2.00 HARI
- ANGKUR PLAT BAJA 8.000 BUAH

ALAT
ALAT BANTU 1.000 Ls
- GERGAJI BESI
- MESIN PEMOTONG
- DLL

TENAGA
PRODUKSI PER HARI 2.000 BH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.500 HARI
- TUKANG 0.500 HARI
- PEKERJA 1.000 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN LIST PLAN LANTAI 10 CM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 15.000 M' PEKERJAAN LIST PLAN LANTAI 10 CM
VOLUME PEKERJAAN : 53.00 M'
BAHAN, ALAT DAN TENAGA
BAHAN
- LIST PLAN KAYU 10 CM 1.100 M
- PAKU SKRUP 0.110 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PEKERJAAN LIST PLAN LANTAI 10 CM
ALAT MASA PELAKSANAAN 3.53 HARI
ALAT BANTU 1.000 Ls 4.00 HARI
- PALU
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 15.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBESIAN

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 350.000 KG PEMBESIAN
VOLUME PEKERJAAN : 1,110.28 KG
BAHAN, ALAT DAN TENAGA
BAHAN
- BESI TULANGAN (POLOS/ULIR) 1.050 KG
- KAWAT BETON 0.015 KG WAKTU PELAKSANAAN YANG DIPERLUKAN
PEMBESIAN
ALAT MASA PELAKSANAAN 3.17 HARI
ALAT BANTU 1.000 Ls 4.00 HARI
- PALU
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 350.000 KG
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.003 HARI
- TUKANG 0.003 HARI
- PEKERJA 0.006 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
BEKISTING

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 10.000 M2 BEKISTING
VOLUME PEKERJAAN : 6.91 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- PAPAN BEKISTING 0.024 M3
- KASO 5/7 CM 0.010 M3 WAKTU PELAKSANAAN YANG DIPERLUKAN
- PAKU 0.300 KG BEKISTING
- MINYAK BEKISTING 0.200 LITER MASA PELAKSANAAN 0.69 HARI
1.00 HARI
ALAT
ALAT BANTU 1.000 Ls
- PALU
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 10.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.400 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RANGKA ATAP BAJA RINGAN 5 CM

URAIAN KOEF. SAT WAKTUYANG DIPERLUKAN


JAM KERJA EFEKTIF PER - HARI 7.000 JAM VOLUME PEKERJAAN YANG DIPERLUKAN
TARGET PRODUKSI 25.000 M2 RANGKA ATAP BAJA RINGAN 5 CM
VOLUME PEKERJAAN : 206.36 M2
BAHAN, ALAT DAN TENAGA
BAHAN
- PROFIL C BAJA RINGAN 3.000 M'
- RENG BAJA RINGAN 2.000 M' WAKTU PELAKSANAAN YANG DIPERLUKAN
- DINABOLT 0.500 KG RANGKA ATAP BAJA RINGAN 5 CM
- SEKRUP FIXER 0.500 KG MASA PELAKSANAAN 8.25 HARI
9.00 HARI
ALAT
ALAT BANTU 1.000 Ls
- PALU
- MESIN BOR
- DLL

TENAGA
PRODUKSI PER HARI 25.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG

KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.160 HARI
ANALISA HARGA ALAT

NO URAIAN KODE SATUAN Perhitungan Biaya Operasi Peralatan KET.


A. URAIAN PERALATAN
Excavator Crane Dump Truck Concrete Mixer Stamper Concrete Vibrator Bulldozer Vibrator Roller Water Tank Truck
1 Jenis Peralatan
2 Merk/Tipe - 80-140 HP 125HP 3-4 M3 15 HP 4 HP 4 HP 100-150 HP 82 68 HP
3 Tenaga Pw HP 133.00 125.00 100.00 15.00 4.00 4.00 155.00 82.00 100.00
4 Kapasitas Cp - 0.90 35.00 4.00 350.00 0.20 - - 7.05 4.00
5 Umur Ekonomis A Tahun 5.00 5.00 5.00 4.00 4.00 4.00 5.00 5.00 5.00
6 Jam Operasi Dalam 1 Tahun W Jam 2,000.00 2,000.00 2,000.00 2,000.00 1,500.00 1,500.00 2,000.00 2,000.00 2,000.00
7 Harga Alat B Rp 1,300,000,000.00 1,650,000,000.00 300,000,000.00 13,500,000.00 7,500,000.00 3,500,000.00 1,430,000,000.00 1,270,000,000.00 350,000,000.00

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sisa Alat = ixB C Rp 130,000,000.00 165,000,000.00 30,000,000.00 1,350,000.00 750,000.00 350,000.00 143,000,000.00 127,000,000.00 35,000,000.00 Suku bunga
i x ( 1 + i ) ^A i =10%
2 Faktor Angsuran Modal = D - 0.26380 0.26380 0.26380 0.31547 0.31547 0.31547 0.26380 0.26380 0.26380
( 1 + i ) ^A - 1

3 Biaya Pasti Per Jam :


(B-C)xD
a. Biaya Pengembalian Modal = E Rp/Jam 154,321.53 195,869.63 35,612.66 1,916.49 1,419.62 662.49 169,753.68 150,760.26 41,548.10
W

PxB Asuransi
b. Asuransi, dll. = F Rp/Jam 1,300.00 1,650.00 300.00 13.50 10.00 4.67 1,430.00 1,270.00 350.00
W p =0,2%

Biaya Pasti per J G = (E + F) G Rp/Jam 155,621.53 197,519.63 35,912.66 1,929.99 1,429.62 667.16 171,183.68 152,030.26 41,898.10

C. BIAYA OPERASI PER JAM KERJA Koef. Biaya OP alat


1 Bahan Bakar = (12%-15%) x Pw x Ms H Rp/Jam 198,835.00 186,875.00 149,500.00 20,700.00 5,520.00 5,520.00 213,900.00 113,160.00 149,500.00 12% s/d 15%
99,750.00 93,750.00 75,000.00 11,250.00 3,000.00 3,000.00 116,250.00 61,500.00 75,000.00
2 Pelumas = (2.5%-3%) x Pw x Mp I Rp/Jam 2.5% s/d 3%

B 48,750.00 61,875.00 11,250.00 421.88 312.50 145.83 44,687.50 39,687.50 13,125.00


3 Biaya bengkel = (6,25% - 8,75%) x J Rp/Jam 6.25% s/d 8.75%
W
B 97,500.00 123,750.00 22,500.00 1,012.50 750.00 350.00 107,250.00 95,250.00 26,250.00
4 Perawatan dan perbaikan = (12,5%-17,5%) x K Rp/Jam 12.5% s/d 17.5%
W
5 Operator = (m orang/jam) x U1 M Rp/Jam 21,428.57 21,428.57 21,428.57 21,428.57 21,428.57 21,428.57 21,428.57 21,428.57 21,428.57

6 Pembantu operator = (n orang/jam) x U2 L Rp/Jam 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43

Biaya Operasi (per Jam) = P Rp/Jam 484,835.00 506,250.00 298,250.00 73,384.38 49,582.50 49,015.83 522,087.50 349,597.50 303,875.00

D. BIAYA OPERASI ALAT / JAM = (G + P) S Rp/Jam 640,456.53 703,769.63 334,162.66 75,314.36 51,012.12 49,682.99 693,271.18 501,627.76 345,773.10

E. LAIN - LAIN
1 Bahan Bakar Premium (non subsidi) Mb Liter 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00
2 Bahan Bakar Solar (non subsidi) Ms Liter 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00
3 Minyak Pelumas Mp Liter 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00

F. BIAYA PERALATAN PER JAM (DIBULATKAN) Rp/Jam 640,400.00 703,700.00 334,100.00 75,300.00 51,000.00 49,600.00 693,200.00 501,600.00 345,700.00