Backup BWS
Backup BWS
SKETSA :
430
220 T. WUDHU
EL - 0.150
77 77 207 E
90
POMPA
D
185
45
80
335 315 45
325
58
C
MUSHOLLAH
EL ± 0.000
AULA
345
EL - 0.100
325
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 1
SKALA 1 : 100
II.1 Lantai 1
1 Pasangan batu bata ( 1 Pc : 5 Pasir ) 0.60 4.00 1.00 2.40 M2
2.20 4.00 1.00 8.80 M2
0.77 4.00 2.00 6.16 M2
2.07 4.00 1.00 8.28 M2
3.35 4.00 1.00 13.40 M2
0.80 4.00 2.00 6.40 M2
3.15 4.00 1.00 12.60 M2
0.45 4.00 1.00 1.80 M2
0.58 2.50 1.00 1.45 M2
4.30 4.00 1.00 17.20 M2
JUMLAH 78.49 M2
- Rangka Hollow
3.50 8.00 9.00 252.00 M1
3.50 4.00 1.00 14.00 M1
3.50 5.00 1.00 17.50 M1
3.65 8.00 3.00 87.60 M1
JUMLAH 371.10 M1
ornamen
0.25 3.9 1.95
0.45 3.9 1.755
3.705
7.41 m2
8 3.9 31.2 m1
kaca lt.1
22 bovenlight ukuran kaca
20 dg ukuran 50.20 50 20 46 16 0.07 m2 1.47
1 dg ukuran 60.20 60 20 56 16 0.09 m2
1 dg ukuran 55.20 55 20 51 16 0.08 m2
kebutuhan kaca lt.1 1.64
7 jendela dg keliling
8.28
57.96 m1
2 jendela dg keliling
6.8 6050000
13.6 m1
71.56 84500 6046820
1.75
0.497
2.247
6.741 m2 ACP
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
kolom 25.15 II
tulangan 12 sgkg 8 jarak 15cm pjg sgkg 1
kolom 25.15 14 66 2
2.42 9.68 m' 0.66
38.72 m' 9.24 m' III
34.37407 kg 36.96 m' 1
14.58294 kg
48.4 m'
kolom 15.15
sgkg 8 jarak 15 pjg
kg 14 0.45 ITEM PEKERJAAN
6.3 m' SATUAN PEMBAYAR
31.5 m'
12.42864 kg
NO
I
1
2
3
m2 20 buah kaca dg ukuran
46 cm x 16 cm II
1 dg ukuran 56cm x 16cm 1
m2 2 dg ukuran 51cm x 16cm 2
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
2000 II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
5
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
4
II
1
2
3
4
5
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
NO
I
1
2
II
1
2
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
1
2
3
4
II
1
2
3
4
III
1
ITEM PEKERJAAN
SATUAN PEMBAYAR
NO
I
2
4
III
1
ANALISA HARGA
ITEM PEKERJAAN
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0359 165,000.00 5,923.50
TUKANG ORG/HARI 0.0358 150,000.00 5,370.00
PEKERJA ORG/HARI 0.1437 130,000.00 18,681.00
BAHAN
HOLLOW METAL FURING m 1.1000 29,166.67 32,083.33
SEKRUP kg 0.4785 26,000.00 12,441.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0359 165,000.00 5,923.50
TUKANG ORG/HARI 0.0358 150,000.00 5,370.00
PEKERJA ORG/HARI 0.1437 130,000.00 18,681.00
BAHAN
HOLLOW METAL FURING m 1.1000 20,000.00 22,000.00
SEKRUP kg 0.4788 26,000.00 12,447.50
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0060 165,000.00 990.00
TUKANG ORG/HARI 0.0600 150,000.00 9,000.00
PEKERJA ORG/HARI 0.0600 130,000.00 7,800.00
BAHAN
Baja Profil WF 150 kg 1.1000 21,238.10 23,361.90
Las kg 1.0000 2,500.00 2,500.00
Zincromate + cat finishing m2 0.0300 26,000.00 780.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
ITEM PEKERJAAN : -
SATUAN PEMBAYARAN : 0
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0350 165,000.00 5,775.00
TUKANG ORG/HARI 0.2500 150,000.00 37,500.00
PEKERJA ORG/HARI 0.7000 130,000.00 91,000.00
BAHAN
SEMEN kg 1.1400 1,400.00 1,596.00
SEMEN WARNA kg 0.5000 17,000.00 8,500.00
PASIR PASANG m3 0.0450 225,000.00 10,125.00
KERAMIK 20x20 buah 26.5000 2,320.00 61,480.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.4000 150,000.00 60,000.00
PEKERJA ORG/HARI 0.0100 130,000.00 1,300.00
BAHAN
Kran buah 1.0000 45,000.00 45,000.00
Seal buah 0.0250 17,000.00 425.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0100 165,000.00 1,650.00
TUKANG ORG/HARI 0.8500 150,000.00 127,500.00
PEKERJA ORG/HARI 0.2500 130,000.00 32,500.00
BAHAN
glasswoll roll 1.3000 38,888.89 50,555.56
Seal buah 0.2500 17,000.00 4,250.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0500 165,000.00 8,250.00
TUKANG ORG/HARI 0.2500 150,000.00 37,500.00
PEKERJA ORG/HARI 0.1250 130,000.00 16,250.00
BAHAN
Urinoir buah 1.0000 1,450,000.00 1,450,000.00
Semen kg 1.0000 1,400.00 1,400.00
Pasir Pasang m3 0.5000 155,000.00 77,500.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.1000 150,000.00 15,000.00
PEKERJA ORG/HARI 0.0100 130,000.00 1,300.00
BAHAN
floor drain buah 1.0000 75,000.00 75,000.00
-
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0060 165,000.00 990.00
TUKANG ORG/HARI 0.6000 150,000.00 90,000.00
PEKERJA ORG/HARI 1.2000 130,000.00 156,000.00
BAHAN
Semen kg 230.0000 1,400.00 322,000.00
Pasir Beton m3 0.5370 400,000.00 214,800.00
Kerilkil m3 0.5710 550,000.00 314,050.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
JUMLAH TOTAL TENAGA, BAHAN, DAN ALAT 1,098,340.00
OVERHEAD + PROFIT (15%) 164,751.00
HARGA SATUAN PEKERJAAN 1,263,091.00
HARGA SATUAN PEKERJAAN DIBULATKAN 1,263,091.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.0250 150,000.00 3,750.00
PEKERJA ORG/HARI 0.5000 130,000.00 65,000.00
BAHAN
Pintu PVC Kamar Mandi set 1.0000 195,000.00 195,000.00
-
-
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0100 165,000.00 1,650.00
TUKANG ORG/HARI 0.3550 150,000.00 53,250.00
PEKERJA ORG/HARI 0.1500 130,000.00 19,500.00
BAHAN
Tiang Baja m 6.8000 144,750.00 984,300.00
Las kg 1.0000 2,500.00 2,500.00
Plat Besi kg 1.8240 125,000.00 228,000.00
CAT BESI DASAR kg 0.4500 80,000.00 36,000.00
CAT BESI FINISHING kg 0.5000 80,000.00 40,000.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0050 165,000.00 825.00
TUKANG ORG/HARI 0.0400 150,000.00 6,000.00
PEKERJA ORG/HARI 0.6000 130,000.00 78,000.00
BAHAN
Cor Beton M3 0.0500 1,299,602.00 64,980.10
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0150 165,000.00 2,475.00
TUKANG ORG/HARI 0.0150 150,000.00 2,250.00
PEKERJA ORG/HARI 0.1600 130,000.00 20,800.00
BAHAN
waterproofing dumplix kg 0.4500 625,000.00 281,250.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
MANDOR ORG/HARI 0.0450 165,000.00 7,425.00
KEPALA TUKANG ORG/HARI 0.3000 160,000.00 48,000.00
TUKANG ORG/HARI 0.7000 150,000.00 105,000.00
PEKERJA ORG/HARI 0.3500 130,000.00 45,500.00
BAHAN
Main Truss m1 2.8000 Err:509 Err:509
Roof Bottom R33-0.45 m1 5.1000 11,000.00 56,100.00
Self Drilling Screw 6x20mm (truss Screw) bh 25.0000 1,000.00 25,000.00
Self Drilling Screw 4x16mm(roof bottom screw) bh 35.0000 800.00 28,000.00
Dynabolt bh 25.0000 2,500.00 62,500.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
TUKANG ORG/HARI 0.2470 150,000.00 37,050.00
PEKERJA ORG/HARI 0.2470 130,000.00 32,110.00
BAHAN
Downlight buah 1.0000 79,500.00 79,500.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
TUKANG ORG/HARI 0.2470 150,000.00 37,050.00
PEKERJA ORG/HARI 0.2470 130,000.00 32,110.00
BAHAN
Downlight buah 1.0000 - -
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
TENAGA
TUKANG ORG/HARI 0.2470 150,000.00 37,050.00
PEKERJA ORG/HARI 0.2470 130,000.00 32,110.00
KEPALA TUKANG ORG/HARI
BAHAN
BESI SIKU 40.40.4 KG 6.2830 15,833.00 99,478.74
BESI DIA. 16MM KG 6.3200 8,391.00 53,031.12
LAS kg 1.0000 26,000.00 26,000.00
Zinc chromate + cat finishing m2 0.0300 65,000.00 1,950.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
TUKANG ORG/HARI 0.2000 150,000.00 30,000.00
PEKERJA ORG/HARI 0.1000 130,000.00 13,000.00
KEPALA TUKANG ORG/HARI 0.0100 160,000.00 1,600.00
Mandor ORG/HARI 0.0100 165,000.00 1,650.00
BAHAN
Gentang Multiroof Lembar 1.1000 95,000.00 104,500.00
Paku KG 0.2000 18,000.00 3,600.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
HARGA TOTAL
URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
TENAGA
PEKERJA ORG/HARI 0.1000 130,000.00 13,000.00
Mandor ORG/HARI 0.1000 165,000.00 16,500.00
BAHAN
KABEL NYY 4x16mm m1 1.0000 209,000.00 209,000.00
ALAT
ALAT BANTU LS 1.0000 500.00 500.00
0.99648
0.2574
1.25388 m3
2 1
2320
0.0784 0.8624
1 kg 48000
1.579008
6.316032
2.41666666666667 6.283333
95000
15833.3333333333
18.72
262.08
168
430.08
1m2
i tenaga
mandor 0.01 165,000.00 1,650.00
tukang 0.2 150,000.00 30,000.00
pekerja 0.15 130,000.00 19,500.00
ii bahan
Paving 25 6,500.00 162,500.00
pasir pasang 0.15 225,000.00 33,750.00
iii Alat
alat bantu 500.00
247,900.00
i tenaga
mandor 0.007 165,000.00 1,155.00
tukang 0.650 150,000.00 97,500.00
kepala tukang 0.066 160,000.00 10,492.80
pekerja 0.330 130,000.00 42,900.00
ii bahan
acp 1.1 800,000.00 880,000.00
hollow 4x4x1mm 1 22,000.00 22,000.00
bracket siku/stiffner 0.28 60,000.00 16,800.00
paku skrup 0.07 21,600.00 1,512.00
paku beton 0.2 21,600.00 4,320.00
sealant 0.25 25,000.00 6,250.00
iii Alat
stager 0.02 110000 2,200.00
lisstrik kerja 1 5000 5,000.00
alat bantu 1 500 500.00
1,090,629.80 Rp 1,080,730.00
i tenaga
mandor 0.007 165,000.00 1,155.00
tukang 0.0857 150,000.00 12,855.00
kepala tukang 160,000.00 -
pekerja 0.39 130,000.00 50,700.00
ii bahan
-
-
-
-
-
sealant 0.25 25,000.00 6,250.00
iii Alat
-
-
alat bantu 1 500 500.00
70,960.00
1 m2 calsiplank
i tenaga
mandor 0.07 165,000.00 11,550.00
tukang 0.35 150,000.00 52,500.00
kepala tukang 0.022 160,000.00 3,520.00
pekerja 0.11 130,000.00 14,300.00
ii bahan
kalsiplank 1.50 125,000.00 187,500.00
paku 0.115 21,600.00 2,484.00
Paku Skrup 0.1 21,600.00 2,160.00
-
-
sealant 0.25 -
iii Alat
-
-
alat bantu 1 500 500.00
274,014.00
i tenaga
mandor 0.007 165,000.00 1,155.00
tukang 0.650 150,000.00 97,500.00
kepala tukang 0.066 160,000.00 10,492.80
pekerja 0.330 130,000.00 42,900.00
ii bahan
acp 1.1 800,000.00 880,000.00
hollow 4x4x1mm 1 22,000.00 22,000.00
bracket siku/stiffner 0.28 60,000.00 16,800.00
paku skrup 0.07 21,600.00 1,512.00
paku beton 0.2 21,600.00 4,320.00
sealant 0.25 25,000.00 6,250.00
Kaca 1 125,000.00 125,000.00
iii Alat
stager 0.02 110000 2,200.00
lisstrik kerja 1 5000 5,000.00
alat bantu 1 500 500.00
1,210,129.80
WF 150 x 75 x 5 x 7 mm – 12 M
0.04
25
hollow 40 1 9 9
2.2 2 4.4
4.15 2 8.3
2.8 2 5.6
3.13 2 6.26
33.56
JUMLAH HARGA
NO URAIAN PEKERJAAN PEKERJAAN
(RP)
I PEKERJAAN PERSIAPAN 60,903,875.80
II PEKERJAAN PASANGAN DAN PLESTERAN 285,300,985.59
III PEKERJAAN KERAMIK LANTAI 174,508,652.38
IV PEKERJAAN PLAFOND 73,572,098.71
V PEKERJAAN PENGECATAN 49,275,309.44
VI PEKERJAAN KUZEN PINTU DAN JENDELA 160,484,502.39
VII PEKERJAAN RALLING 67,935,167.84
VIII PEKERJAAN SANITAIR / FIXTURES 13,449,556.52
IX PEKERJAAN ELEKTRIKAL DAN MEKANIKAL 67,259,468.00
X PEKERJAAN SISTEM KEBAKARAN 3,000,000.00
XI PEKERJAAN LANDSCAPE 36,004,714.11
XII PEKERJAAN PARTISI 141,352,429.88
XIII PEKERJAAN AREA PARKIR 139,684,246.37
(A) Jumlah Harga Pekerjaan 1,272,731,007.03
(B) Pajak Pertambahan Nilai (PPN) = 10% x (A) 127,273,100.70
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 1,400,004,107.73
(D) PEMBULATAN 1,400,004,000.00
Terbilang :
#NAME?
BAU SANTI
Direktur
DAFTAR KUANTITAS DAN HARGA
CHANGE CONTRACT ORDER ( CCO )
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
1 2 3 4 5 6=4x5 7 8 9=7x8
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi ls 1.00 Rp. 2,200,000.00 Rp. 2,200,000.00 1.00 Rp 2,200,000.00 Rp 2,200,000.00 TETAP
2 Pembongkaran Bangunan Lama m2 8.82 Rp. 271,659.00 Rp. 2,396,032.38 - Rp - Rp - DIHILANGKAN
3 Gudang dan Barak Kerja m2 10.00 Rp. 2,108,815.00 Rp. 21,088,150.00 - Rp - Rp - DIHILANGKAN
4 Pengukuran Lokasi m2 49.40 Rp. 9,257.00 Rp. 457,295.80 49.40 Rp 9,257.00 Rp 457,295.80 TETAP
5 Alat dan keselamatan kerja ( K-3) ls 1.00 Rp. 21,370,000.00 Rp. 21,370,000.00 1.00 Rp 21,370,000.00 Rp 21,370,000.00 TETAP
6 Pembuatan papan nama proyek ls 1.00 Rp. 500,000.00 Rp. 500,000.00 1.00 Rp 500,000.00 Rp 500,000.00 TETAP
7 Listrik Kerja ls 1.00 Rp. 5,000,000.00 Rp. 5,000,000.00 1.00 Rp 5,000,000.00 Rp 5,000,000.00 TETAP
8 Air Kerja ls 1.00 Rp. 3,000,000.00 Rp. 3,000,000.00 1.00 Rp 3,000,000.00 Rp 3,000,000.00 TETAP
9 Pagar Lokasi m' 15.00 Rp. 472,943.00 Rp. 7,094,145.00 60.00 Rp 472,943.00 Rp 28,376,580.00 BERTAMBAH
Jumlah Harga Pekerjaan I (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 63,105,623.18 Rp 60,903,875.80
1 2 3 4 5 6=4x5 7 8 9=7x8
II.2 LANTAI 3
1 Pasangan batu bata 1/2 bata ( 1 Pc : 5 Pasir ) m2 32.00 Rp. 236,596.00 Rp. 7,571,072.00 31.61 Rp 236,596.00 Rp 7,478,799.56 BERKURANG
2 Plesteran dinding ( 1 Pc : 5 Pasir ) m2 288.44 Rp. 61,196.00 Rp. 17,651,374.24 275.69 Rp 61,196.00 Rp 16,871,125.24 BERKURANG
3 Acian dinding m2 230.50 Rp. 44,340.00 Rp. 10,220,370.00 296.11 Rp 44,340.00 Rp 13,129,517.40 BERKURANG
4 Benangan m1 192.00 Rp. 26,976.00 Rp. 5,179,392.00 119.75 Rp 26,976.00 Rp 3,230,376.00 BERKURANG
5 Kolom H-Beam Kg - - - 168.00 Rp 53,017.00 Rp 8,906,856.00 ITEM PEKERJAAN BARU
6 Balok Iwf-150 Kg - - - 262.08 Rp 53,017.00 Rp 13,894,695.36 ITEM PEKERJAAN BARU
7 Beton m3 - - - 2.36 Rp 1,299,602.00 Rp 3,067,060.72 ITEM PEKERJAAN BARU
10 Rabat Lantai m3 - - - 1.12 Rp 1,263,091.00 Rp 1,414,661.92 ITEM PEKERJAAN BARU
11 Ringbalk Ruang Urinoir m1 - - - 9.80 Rp 309,599.00 Rp 3,034,070.20 ITEM PEKERJAAN BARU
12 Saluran Urinoir m1 - - - 2.80 Rp 172,850.00 Rp 483,980.00 ITEM PEKERJAAN BARU
II.3 LANTAI 2
1 Kolom H. BEAM 250x250x9x14 mm di bungkus ACP m2 - - - 16.80 Rp 1,291,007.00 Rp 21,688,917.60 ITEM PEKERJAAN BARU
2 Balok H.BEAM dibungkus ACP m2 - - - 9.50 Rp 1,291,007.00 Rp 12,264,566.50 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan II (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 79,436,373.74 Rp 285,300,985.59
III.2 LANTAI 2
1 Lantai Homogeneus tangga m2 15.60 Rp. 464,524.00 Rp. 7,246,574.40 15.93 Rp 464,524.00 Rp 7,399,867.32 BERTAMBAH
2 Plin tangga m1 - - - 16.20 Rp 64,826.00 Rp 1,050,181.20 ITEM PEKERJAAN BARU
3 Keramik Lantai Balkon m2 - - - 15.13 Rp 464,524.00 Rp 7,028,248.12 ITEM PEKERJAAN BARU
III.3 LANTAI 3
1 Lantai homogenius 60 cm x 60 cm( Polished) m2 159.21 Rp. 464,524.00 Rp. 73,956,866.04 179.60 Rp 464,524.00 Rp 83,428,510.40 BERTAMBAH
2 Plin keramik 10 x 60 cm m1 76.75 Rp. 64,826.00 Rp. 4,975,395.50 72.76 Rp 64,826.00 Rp 4,716,739.76 BERKURANG
3 Lapisan creed 3 cm - 7 cm m2 159.21 Rp. 57,454.00 Rp. 9,147,251.34 179.60 Rp 57,454.00 Rp 10,318,738.40 BERTAMBAH
4 Keramik lantai ruang Urinoir m2 - - - 8.33 Rp 312,335.00 Rp 2,601,750.55 ITEM PEKERJAAN BARU
5 Keramik Dinding ruang Urinoir m2 - - - 8.07 Rp 312,335.00 Rp 2,520,543.45 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan III (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 116,382,960.20 Rp 174,508,652.38
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN
1 2 3 4 5 6=4x5 7 8 9=7x8
IV PEKERJAAN PLAFOND
IV.1 LANTAI 1
1 Plafond gypsum m2 106.88 Rp. 42,584.00 Rp. 4,551,377.92 118.61 Rp 42,584.00 Rp 5,050,888.24 BERTAMBAH
2 Rangka Plafond Hollow metal Furing m2 106.88 Rp. 143,234.00 Rp. 15,308,849.92 129.37 Rp 143,234.00 Rp 18,530,182.58 BERTAMBAH
3 List Plafond Gypsum m1 41.50 Rp. 58,735.00 Rp. 2,437,502.50 50.26 Rp 58,735.00 Rp 2,952,021.10 BERTAMBAH
4 Plafond gypsum Canopy m2 - - - 10.76 Rp 42,584.00 Rp 458,203.84 ITEM PEKERJAAN BARU
IV.2 LANTAI 3
1 Plafond gypsum m2 171.44 Rp. 42,584.00 Rp. 7,300,600.96 189.23 Rp 42,584.00 Rp 8,058,170.32 BERTAMBAH
2 Rangka Plafond Hollow metal Furing m2 171.44 Rp. 143,234.00 Rp. 24,556,036.96 189.23 Rp 143,234.00 Rp 27,104,169.82 BERTAMBAH
3 List Flapond Gypsum m1 57.98 Rp. 58,735.00 Rp. 3,405,455.30 120.72 Rp 58,735.00 Rp 7,090,489.20 BERTAMBAH
IV.3 LANTAI 2
1 Plafond Balkon m2 - - - 14.52 Rp 42,584.00 Rp 618,319.68 ITEM PEKERJAAN BARU
2 Rangka Plafond Hollow metal Furing m2 - - - 14.52 Rp 143,234.00 Rp 2,079,757.68 ITEM PEKERJAAN BARU
3 List Plafond Gypsum m1 - - - 27.75 Rp 58,735.00 Rp 1,629,896.25 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan IV (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 57,559,823.56 Rp 73,572,098.71
V PEKERJAAN PENGECATAN
V.1 LANTAI 1
1 Pengecatan dinding luar m2 34.75 Rp. 62,718.00 Rp. 2,179,450.50 82.41 Rp 62,718.00 Rp 5,168,590.38 BERTAMBAH
2 Pengecatan dinding dalam m2 34.75 Rp. 51,793.00 Rp. 1,799,806.75 82.41 Rp 51,793.00 Rp 4,268,261.13 BERTAMBAH
3 Pengecatan plafond gypsum m2 106.88 Rp. 50,068.00 Rp. 5,351,267.84 129.37 Rp 50,068.00 Rp 6,477,297.16 BERTAMBAH
4 Pengecatan list plafond gypsum m1 41.50 Rp. 29,241.00 Rp. 1,213,501.50 50.26 Rp 29,241.00 Rp 1,469,652.66 BERTAMBAH
5 Pengecatan kolom m2 70.40 Rp. 50,341.00 Rp. 3,544,006.40 - Rp - Rp - DIHILANGKAN
V.2 LANTAI 3
1 Pengecatan dinding dalam m2 220.01 Rp. 51,793.00 Rp. 11,394,977.93 296.11 Rp 51,793.00 Rp 15,336,425.23 BERTAMBAH
2 Pengecatan plafond gypsum m2 171.44 Rp. 50,068.00 Rp. 8,583,657.92 189.23 Rp 50,068.00 Rp 9,474,367.64 BERTAMBAH
3 Pengecatan list plafond gypsum m1 57.98 Rp. 29,241.00 Rp. 1,695,393.18 120.72 Rp 29,241.00 Rp 3,529,973.52 BERTAMBAH
V.3 LANTAI 2
1 Pengecatan dinding dalam m2 - - - 54.52 Rp 51,793.00 Rp 2,823,754.36 ITEM PEKERJAAN BARU
2 Pengecatan plafond gypsum m2 - - - 14.52 Rp 50,068.00 Rp 726,987.36 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan V (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 35,762,062.02 Rp 49,275,309.44
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN
1 2 3 4 5 6=4x5 7 8 9=7x8
VI PEKERJAAN KUZEN PINTU DAN JENDELA
VI.1 LANTAI 1
1 Pembuatan kusen pintu alumunium 4" m1 16.80 Rp. 155,431.00 Rp. 2,611,240.80 - Rp - Rp - DIHILANGKAN
2 Pembuatan pintu alumunium (2 daun) Unit 1.00 Rp. 2,368,137.00 Rp. 2,368,137.00 - Rp - Rp - DIHILANGKAN
3 Pemasangan kaca tebal 5 mm m2 7.34 Rp. 220,070.00 Rp. 1,615,313.80 1.20 Rp 220,070.00 Rp 264,084.00 BERKURANG
VI.1 LANTAI 1
1 Pembuatan Kusen Bovenlight Alumunium m1 - - - - Rp - Rp - DIHILANGKAN
1 Pemasangan Kaca tebal 5 mm m2 - - - - Rp - Rp - DIHILANGKAN
2 Pemasangan Pintu Geser Alumunium unit - - - 1.00 Rp 3,500,000.00 Rp 3,500,000.00 ITEM PEKERJAAN BARU
3 Kusen Pintu Alumunium m1 - - - 4.90 Rp 155,431.00 Rp 761,611.90 ITEM PEKERJAAN BARU
VI.1.2 LANTAI 2
1 Sealant Jendela m1 - - - 71.56 Rp 93,328.00 Rp 6,678,551.68 ITEM PEKERJAAN BARU
2 Pembuatan kusen pintu alumunium 4" m1 - - - 30.23 Rp 155,431.00 Rp 4,698,679.13 ITEM PEKERJAAN BARU
3 Pemasangan kaca tebal 5 mm m2 - - - 5.66 Rp 220,070.00 Rp 1,245,596.20 ITEM PEKERJAAN BARU
4 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) bh - - - 3.00 Rp 4,500,000.00 Rp 13,500,000.00 ITEM PEKERJAAN BARU
VI. 2 LANTAI 3
VI.2. 1 PEKERJAAN KUZEN PINTU DAN JENDELA
1 Pembuatan kusen pintu alumunium 4" m1 389.16 Rp. 155,431.00 Rp. 60,487,527.96 208.52 Rp 155,431.00 Rp 32,410,472.12 BERKURANG
2 Pembuatan Jendela alumunium Unit 38.00 Rp. 1,310,137.00 Rp. 49,785,206.00 40.00 Rp 1,310,137.00 Rp 52,405,480.00 BERTAMBAH
3 Pasang engsel jungkit bh 76.00 Rp. 128,800.00 Rp. 9,788,800.00 80.00 Rp 128,800.00 Rp 10,304,000.00 BERTAMBAH
4 Grendel jendela bh 38.00 Rp. 48,217.00 Rp. 1,832,246.00 40.00 Rp 48,217.00 Rp 1,928,680.00 BERTAMBAH
5 Pemasangan kaca tebal 5 mm m2 41.58 Rp. 220,070.00 Rp. 9,150,510.60 42.68 Rp 220,070.00 Rp 9,392,587.60 BERTAMBAH
6 Pemasangan 1 pintu kaca dan kusen allumunium ( 2 daun) bh 1.00 Rp. 6,500,000.00 Rp. 6,500,000.00 1.00 Rp 6,500,000.00 Rp 6,500,000.00 TETAP
7 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) bh 1.00 Rp. 4,500,000.00 Rp. 4,500,000.00 3.00 Rp 4,500,000.00 Rp 13,500,000.00 BERTAMBAH
8 Glass block m2 - - - 0.24 Rp 811,499.00 Rp 194,759.76 ITEM PEKERJAAN BARU
9 Pemasangan Kusen + Pintu Alu. Ruangan Urinoir set - - - 1.00 Rp 3,200,000.00 Rp 3,200,000.00 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan VI (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 148,638,982.16 Rp 160,484,502.39
VII.2 LANTAI 2
1 Handrail stainless steel dia 2 " m1 26.40 Rp. 991,375.00 Rp. 26,172,300.00 9.00 Rp 1,686,992.00 Rp 15,182,928.00 BERKURANG
2 Railing Balkon m1 - - - 5.87 Rp 1,686,992.00 Rp 9,902,643.04 ITEM PEKERJAAN BARU
VII.3 LANTAI 3
1 Railing Balkon m1 - - - 8.40 Rp 1,686,992.00 Rp 14,170,732.80 ITEM PEKERJAAN BARU
2 Railing Sisi Ruang Urinoir m1 - - - 0.80 Rp 1,686,992.00 Rp 1,349,593.60 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan VII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 26,172,300.00 Rp 67,935,167.84
1 2 3 4 5 6=4x5 7 8 9=7x8
1 Tissue holder bh 2.00 Rp. 120,000.00 Rp. 240,000.00 - Rp 120,000.00 Rp - DIHILANGKAN
2 Tempat sabun bh 2.00 Rp. 100,000.00 Rp. 200,000.00 - Rp 100,000.00 Rp - DIHILANGKAN
3 Kaca cermin tebal 5 mm 200 cm x 100 cm m2 2.00 Rp. 379,370.00 Rp. 758,740.00 - Rp 379,370.00 Rp - DIHILANGKAN
4 Tandon air 1200 Lt Stainless unit 2.00 Rp. 4,200,000.00 Rp. 8,400,000.00 - Rp 4,200,000.00 Rp - DIHILANGKAN
VIII.2 LANTAI 3
1 Urinoir unit - - - 2.00 Rp 3,020,360.00 Rp 6,040,720.00 ITEM PEKERJAAN BARU
2 Pasangan Kran unit - - - 2.00 Rp 181,757.00 Rp 363,514.00 ITEM PEKERJAAN BARU
3 pasangan Floor Drain unit - - - 2.00 Rp 106,518.00 Rp 213,036.00 ITEM PEKERJAAN BARU
4 Waterproofing m2 - - - 15.22 Rp 353,366.00 Rp 5,378,230.52 ITEM PEKERJAAN BARU
VIII.3 LANTAI 1
1 Pasangan Kran unit - - - 8.00 Rp 181,757.00 Rp 1,454,056.00 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan VIII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 9,598,740.00 Rp 13,449,556.52
IX.1.2 LANTAI 3
1 Pasang lampu RM 3 x 36 w bh 24.00 Rp. 631,350.00 Rp. 15,152,400.00 26.00 Rp 631,350.00 Rp 16,415,100.00 TETAP
2 Instalasi titik lampu titik 24.00 Rp. 235,328.00 Rp. 5,647,872.00 26.00 Rp 235,328.00 Rp 6,118,528.00 TETAP
3 Saklar serie titik 4.00 Rp. 41,144.00 Rp. 164,576.00 5.00 Rp 41,144.00 Rp 205,720.00 TETAP
4 Stop kontak dinding, 1 Ph, 10 A bh 10.00 Rp. 41,144.00 Rp. 411,440.00 16.00 Rp 41,144.00 Rp 658,304.00 BERTAMBAH
5 Stop kontak AC bh 8.00 Rp. 75,644.00 Rp. 605,152.00 11.00 Rp 75,644.00 Rp 832,084.00 BERTAMBAH
6 Instalasi stop kontak bh 10.00 Rp. 245,103.00 Rp. 2,451,030.00 16.00 Rp 245,103.00 Rp 3,921,648.00 BERTAMBAH
7 Instalasi titik lampu - Downlight titik - - - 3.00 Rp 235,328.00 Rp 705,984.00 ITEM PEKERJAAN BARU
1 2 3 4 5 6=4x5 7 8 9=7x8
IX.2.2 PP - 3 LANTAI 3
1 MCB - 3 Ph ( 50 A ) 10 KA bh 1.00 Rp. 1,397,825.00 Rp. 1,397,825.00 1.00 Rp 1,397,825.00 Rp 1,397,825.00 TETAP
2 MCB - 1 Ph ( 10 A ) 10 KA bh 8.00 Rp. 125,637.00 Rp. 1,005,096.00 8.00 Rp 125,637.00 Rp 1,005,096.00 BERKURANG
3 Pilot lamp bh 3.00 Rp. 110,000.00 Rp. 330,000.00 3.00 Rp 110,000.00 Rp 330,000.00 TETAP
4 Fuse patron bh 3.00 Rp. 95,000.00 Rp. 285,000.00 3.00 Rp 95,000.00 Rp 285,000.00 TETAP
5 Kwh meter bh 1.00 Rp. 1,280,000.00 Rp. 1,280,000.00 1.00 Rp 1,280,000.00 Rp 1,280,000.00 TETAP
6 CU. Bar 4 x (12 mm x 2 mm) lot 3.00 Rp. 600,000.00 Rp. 1,800,000.00 3.00 Rp 600,000.00 Rp 1,800,000.00 TETAP
7 Box panel bh 1.00 Rp. 1,330,000.00 Rp. 1,330,000.00 1.00 Rp 1,330,000.00 Rp 1,330,000.00 TETAP
8 Kabel dalam panel lot 1.00 Rp. 700,000.00 Rp. 700,000.00 1.00 Rp 700,000.00 Rp 700,000.00 TETAP
9 Kawat BC - 6 mm2 lot 1.00 Rp. 700,000.00 Rp. 700,000.00 1.00 Rp 700,000.00 Rp 700,000.00 TETAP
10 Material lain - lain lot 1.00 Rp. 1,000,000.00 Rp. 1,000,000.00 1.00 Rp 1,000,000.00 Rp 1,000,000.00 TETAP
11 Biaya pemasangan lot 1.00 Rp. 1,500,000.00 Rp. 1,500,000.00 1.00 Rp 1,500,000.00 Rp 1,500,000.00 TETAP
12 Instalasi titik lampu - Downlight titik - - - 3.00 Rp 235,328.00 Rp 705,984.00 ITEM PEKERJAAN BARU
IX.2.3 PP - 2 LANTAI 2
1 Instalasi titik lampu - Downlight titik - - - 2.00 Rp 235,328.00 Rp 470,656.00 ITEM PEKERJAAN BARU
2 Saklar serie titik - - - 1.00 Rp 41,144.00 Rp 41,144.00 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan IX (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 116,127,807.00 Rp 67,259,468.00
X.2 LANTAI 3
1 Instalasi pipa splinker titik 26.00 Rp. 1,823,900.00 Rp. 47,421,400.00 - Rp - Rp - DIHILANGKAN
2 Pemasangan splinker titik 26.00 Rp. 254,150.00 Rp. 6,607,900.00 - Rp - Rp - DIHILANGKAN
3 Instalasi smoke detector titik 26.00 Rp. 1,133,900.00 Rp. 29,481,400.00 - Rp - Rp - DIHILANGKAN
4 Pemasangan smoke detector titik 26.00 Rp. 728,525.00 Rp. 18,941,650.00 - Rp - Rp - DIHILANGKAN
5 Pengadaan alat pemadam api ringan 5 kg bh 7.00 Rp. 1,000,000.00 Rp. 7,000,000.00 1.00 Rp 1,000,000.00 Rp 1,000,000.00 TETAP
Jumlah Harga Pekerjaan X (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 185,380,900.00 Rp 3,000,000.00
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN
1 2 3 4 5 6=4x5 7 8 9=7x8
XI PEKERJAAN LANDSCAPE
1 Grill dilapisi besi plat bordes m1 50.00 Rp. 260,162.00 Rp. 13,008,100.00 14.00 Rp 260,162.00 Rp 3,642,268.00 DIHILANGKAN
2 Railing pagar m1 41.40 Rp. 912,398.00 Rp. 37,773,277.20 - Rp - Rp - DIHILANGKAN
3 cor beton tebal 12 cm ( K-175) m3 0.84 Rp. 1,299,602.00 Rp. 1,091,665.68 - Rp - Rp - DIHILANGKAN
4 cor beton tebal 8 cm ( K-175) m3 - - - 0.38 Rp 1,299,602.00 Rp 493,848.76 ITEM PEKERJAAN BARU
5 Pekerjaan kanopi m2 95.35 Rp. 353,372.00 Rp. 33,694,020.20 19.44 Rp 363,635.00 Rp 7,069,064.40 BERKURANG
6 Pekerjaan kansteen m1 55.80 Rp. 133,710.00 Rp. 7,461,018.00 - Rp - Rp - DIHILANGKAN
7 Pengecatan kansteen m2 33.48 Rp. 60,993.00 Rp. 2,042,045.64 - Rp - Rp - DIHILANGKAN
8 Gebalan rumput m2 44.64 Rp. 54,816.00 Rp. 2,446,986.24 - Rp - Rp - DIHILANGKAN
9 Penutup atap m2 40.80 Rp. 149,671.00 Rp. 6,106,576.80 44.38 Rp 149,671.00 Rp 6,642,398.98 BERTAMBAH
10 Pasangan Calci-plank m2 - - - 20.57 Rp 302,668.00 Rp 6,225,880.76 ITEM PEKERJAAN BARU
11 Rangka Pekerjaan Calci-plank m2 - - - 20.57 Rp 267,743.00 Rp 5,507,473.51 ITEM PEKERJAAN BARU
12 Penutup Atap Selasar Penghubung m2 - - - 11.70 Rp 149,671.00 Rp 1,751,150.70 ITEM PEKERJAAN BARU
13 Pekerjaan Rangka Atap Selasar Penghubung m2 - - - 11.70 Rp 267,743.00 Rp 3,132,593.10 ITEM PEKERJAAN BARU
14 Talang Air Selasar m2 - - - 3.90 Rp 394,881.00 Rp 1,540,035.90 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan XI (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 103,623,689.76 Rp 36,004,714.11
XII.2 LANTAI 2
XII.2.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi m2 71.30 Rp. 258,217.00 Rp. 18,410,872.10 - Rp - Rp - DIHILANGKAN
2 Pekerjaan pasang papan gypsum 2 muka m2 142.60 Rp. 231,552.00 Rp. 33,019,315.20 - Rp - Rp - DIHILANGKAN
3 Pekerjaan kusen alumunium dan daun pintu panel lapis HPL bh 4.00 Rp. 3,186,276.00 Rp. 12,745,104.00 - Rp - Rp - DIHILANGKAN
4 Pekerjaan list plan lantai 10 cm m1 22.00 Rp. 83,240.00 Rp. 1,831,280.00 - Rp - Rp - DIHILANGKAN
5 Pekerjaan list gypsum m1 22.00 Rp. 58,735.00 Rp. 1,292,170.00 - Rp - Rp - DIHILANGKAN
6 Pekerjaan pengecatan m2 142.60 Rp. 50,068.00 Rp. 7,139,696.80 - Rp - Rp - DIHILANGKAN
KONTRAK CHANGE CONTRACT ORDER
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA JUMLAH VOLUME HARGA SATUAN JUMLAH
KETERANGAN
1 2 3 4 5 6=4x5 7 8 9=7x8
XII.2 LANTAI 3
XII.2.1 PARITISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi m2 - - - 71.11 Rp 258,217.00 Rp 18,361,810.87 ITEM PEKERJAAN BARU
2 Pekerjaan pasang papan gypsum 2 muka m2 - - - 142.22 Rp 231,552.00 Rp 32,931,325.44 ITEM PEKERJAAN BARU
3 Pekerjaan kusen alumunium + daun pintu alu. + kaca bh - - - - Rp - Rp - DIHILANGKAN
4 Pekerjaan list plan lantai 10 cm m1 - - - 66.29 Rp 83,240.00 Rp 5,517,979.60 ITEM PEKERJAAN BARU
5 Pekerjaan list gypsum m1 - - - 33.93 Rp 58,735.00 Rp 1,992,878.55 ITEM PEKERJAAN BARU
6 Pekerjaan pengecatan m2 - - - 142.22 Rp 50,068.00 Rp 7,120,670.96 ITEM PEKERJAAN BARU
7 Pekerjaan Peredam Ruangan m2 - - - 64.64 Rp 278,568.00 Rp 18,006,635.52 ITEM PEKERJAAN BARU
Jumlah Harga Pekerjaan XII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 204,009,894.45 Rp 141,352,429.88
Jumlah Harga Pekerjaan XIII (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp. 126,931,793.82 Rp 139,684,246.37
ANALISA HARGA
ITEM PEKERJAAN
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.01 150,000.00 1,500.00
3 PEKERJA ORG/HARI 0.03 130,000.00 3,900.00
II BAHAN
III ALAT
1 ALAT BANTU LS 1.00 1,000.00 1,000.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.20 130,000.00 26,000.00
II BAHAN
1 DOLKEN KAYU DIA. 8-10/400 CM BATANG 1.05 25,000.00 26,250.00
2 SEMEN KG 2.50 1,400.00 3,500.00
3 SENG GELOMBANG LEMBAR 1.05 74,500.00 78,225.00
4 PASIR BETON M3 0.01 400,000.00 2,000.00
5 KORAL BETON M3 0.01 550,000.00 4,950.00
6 KAYU 5/7 M3 0.06 3,500,000.00 217,000.00
7 PAKU BIASA KG 0.06 18,000.00 1,080.00
8 CAT BESI KG 0.45 80,000.00 36,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,176.47
2 TUKANG ORG/HARI 0.20 150,000.00 29,411.76
3 PEKERJA ORG/HARI 0.59 130,000.00 76,470.59
II BAHAN
1 BATA MERAH BUAH 70.00 850.00 59,500.00
2 SEMEN KG 9.68 1,400.00 13,552.00
3 PASIR PASANG M3 0.05 225,000.00 10,125.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.06 165,000.00 9,269.66
2 TUKANG ORG/HARI 0.06 150,000.00 8,426.97
3 PEKERJA ORG/HARI 0.17 130,000.00 21,910.11
II BAHAN
1 SEMEN KG 5.18 1,400.00 7,257.60
2 PASIR PASANG M3 0.03 225,000.00 5,850.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,375.00
2 TUKANG ORG/HARI 0.01 150,000.00 1,250.00
3 PEKERJA ORG/HARI 0.03 130,000.00 4,333.33
II BAHAN
1 KAYU BEKISTING M3 0.00 2,200,000.00 4,400.00
2 PAKU KG 0.01 18,000.00 180.00
3 MINYAK BEKISTING LITER 0.09 5,000.00 450.00
4 BESI BETON POLOS KG 3.00 12,500.00 37,500.00
5 KAWAT BETON KG 0.45 25,000.00 11,250.00
6 SEMEN KG 4.00 1,400.00 5,600.00
7 PASIR BETON M3 0.06 400,000.00 24,000.00
8 KORAL BETON M3 0.01 550,000.00 4,950.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,621.19
2 TUKANG ORG/HARI 0.04 150,000.00 6,019.26
3 PEKERJA ORG/HARI 0.16 130,000.00 20,866.77
II BAHAN
1 SEMEN KG 3.25 1,400.00 4,550.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.02 150,000.00 3,000.00
3 PEKERJA ORG/HARI 0.04 130,000.00 5,200.00
II BAHAN
1 SEMEN KG 5.18 1,400.00 7,257.60
2 PASIR PASANG M3 0.03 225,000.00 5,850.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.06 165,000.00 10,312.50
2 TUKANG ORG/HARI 0.06 150,000.00 9,375.00
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00
II BAHAN
1 BAJA H. BEAM KG 14.48 22,000.00 318,633.33
2 BESI TULANGAN KG 4.74 12,500.00 59,250.00
3 SEMEN KG 315.00 1,400.00 441,000.00
4 PASIR M3 0.52 400,000.00 208,857.14
5 KERIKIL M3 0.57 550,000.00 315,027.78
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 7,432.43
2 TUKANG ORG/HARI 0.09 150,000.00 13,513.51
3 PEKERJA ORG/HARI 0.18 130,000.00 23,423.42
II BAHAN
1 SEMEN KG 9.60 1,400.00 13,440.00
2 SEMEN WARNA KG 1.50 17,000.00 25,500.00
3 PASIR PASANG M3 0.05 225,000.00 10,125.00
4 HOMOGENIUS TILE 60 x 60 BUAH 3.10 100,000.00 310,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 7,432.43
2 TUKANG ORG/HARI 0.09 150,000.00 13,513.51
3 PEKERJA ORG/HARI 0.18 130,000.00 23,423.42
II BAHAN
1 SEMEN KG 9.60 1,400.00 13,440.00
2 SEMEN WARNA KG 1.50 17,000.00 25,500.00
3 PASIR PASANG M3 0.05 155,000.00 6,975.00
4 HOMOGENIUS TILE 60 x 60 BUAH 3.10 100,000.00 310,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,600.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.08 130,000.00 10,400.00
II BAHAN
1 SEMEN KG 1.14 1,400.00 1,596.00
2 SEMEN WARNA KG 0.10 17,000.00 1,700.00
3 PASIR PASANG M3 0.00 155,000.00 465.00
4 PLIN KERAMIK 10X60 BUAH 1.70 17,000.00 28,900.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,884.30
2 TUKANG ORG/HARI 0.01 150,000.00 1,713.00
3 PEKERJA ORG/HARI 0.05 130,000.00 5,938.41
II BAHAN
1 SEMEN KG 22.25 1,400.00 31,150.00
2 PASIR PASANG M3 0.04 155,000.00 6,045.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 988.07
2 TUKANG ORG/HARI 0.01 150,000.00 898.25
3 PEKERJA ORG/HARI 0.02 130,000.00 3,113.92
II BAHAN
1 GYPSUM BOARD 9 MM LEMBAR 0.38 70,000.00 26,250.00
2 PAKU SEKRUP KG 0.11 55,000.00 6,050.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 5,928.43
2 TUKANG ORG/HARI 0.04 150,000.00 5,389.48
3 PEKERJA ORG/HARI 0.14 130,000.00 18,683.53
II BAHAN
1 HOLLOW METAL FURING M' 4.10 22,000.00 90,200.00
2 SEKRUP KG 0.11 55,000.00 6,050.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 2,357.14
2 TUKANG ORG/HARI 0.01 150,000.00 2,142.86
3 PEKERJA ORG/HARI 0.03 130,000.00 3,714.29
II BAHAN
1 LIST GYPSUM PROFIL M' 1.05 40,000.00 42,000.00
2 TEPUNG GYPSUM KG 0.15 2,400.00 360.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22
II BAHAN
1 PLAMUR TEMBOK KG 0.10 15,000.00 1,500.00
2 CAT TEMBOK DASAR KG 0.10 54,000.00 5,400.00
3 CAT TEMBOK FINISHNG KG 0.10 245,000.00 24,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22
II BAHAN
1 PLAMUR TEMBOK KG 0.10 15,000.00 1,500.00
2 CAT TEMBOK DASAR KG 0.10 54,000.00 5,400.00
3 CAT TEMBOK FINISHNG KG 0.10 150,000.00 15,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22
II BAHAN
1 CAT DASAR KG 0.10 54,000.00 5,400.00
2 CAT FINISHNG KG 0.10 150,000.00 15,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,299.21
2 TUKANG ORG/HARI 0.01 150,000.00 1,181.10
3 PEKERJA ORG/HARI 0.02 130,000.00 2,047.24
II BAHAN
1 CAT DASAR KG 0.10 54,000.00 5,400.00
2 CAT FINISHNG KG 0.10 150,000.00 15,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,133.83
2 TUKANG ORG/HARI 0.04 150,000.00 5,576.21
3 PEKERJA ORG/HARI 0.07 130,000.00 9,665.43
II BAHAN
1 PLAMUR TEMBOK KG 0.10 15,000.00 1,500.00
2 CAT TEMBOK DASAR KG 0.10 54,000.00 5,400.00
3 CAT TEMBOK FINISHNG KG 0.10 150,000.00 15,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,173.08
2 TUKANG ORG/HARI 0.02 150,000.00 2,884.62
3 PEKERJA ORG/HARI 0.04 130,000.00 5,000.00
II BAHAN
1 PROFIL ALUMINIUM M 1.10 110,000.00 121,000.00
2 SEKRUP BUAH 2.00 400.00 800.00
3 SEALENT KG 0.06 30,000.00 1,800.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.25 165,000.00 41,250.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00
II BAHAN
1 PROFIL ALUMINIUM M 6.00 110,000.00 660,000.00
2 DAUN PINTU ALUMINIUM M 2.10 350,000.00 735,000.00
3 KUNCI TANAM SELINDER BUAH 2.00 260,000.00 520,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,156.25
2 TUKANG ORG/HARI 0.06 150,000.00 9,375.00
3 PEKERJA ORG/HARI 0.03 130,000.00 4,062.50
II BAHAN
1 KACA 5 MM M2 1.05 162,640.00 170,772.00
2 SEALENT KG 0.05 30,000.00 1,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.25 165,000.00 41,250.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00
II BAHAN
1 DAUN PINTU ALUMINIUM Unit 1.00 1,200,000.00 1,200,000.00
2 KUNCI TANAM SELINDER BUAH 1.00 260,000.00 260,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,300.00
2 TUKANG ORG/HARI 0.02 150,000.00 3,000.00
3 PEKERJA ORG/HARI 0.04 130,000.00 5,200.00
II BAHAN
1 ENGSEL BUAH 1.00 100,000.00 100,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 4,714.29
2 TUKANG ORG/HARI 0.03 150,000.00 4,285.71
3 PEKERJA ORG/HARI 0.06 130,000.00 7,428.57
II BAHAN
1 GRANDEL JENDELA BUAH 1.00 25,000.00 25,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,750.00
2 TUKANG ORG/HARI 0.02 150,000.00 2,500.00
3 PEKERJA ORG/HARI 0.05 130,000.00 6,500.00
II BAHAN
1 BESI STAINLESS STEEL DIA. 2" M 9.57 122,500.00 1,172,325.00
2 KAWAT LAS KG 0.48 26,000.00 12,441.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,178.57
2 TUKANG ORG/HARI 0.01 150,000.00 1,071.43
3 PEKERJA ORG/HARI 0.01 130,000.00 1,857.14
II BAHAN
1 CERMIN TEBAL 5 MM M2 2.00 162,640.00 325,280.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00
II BAHAN
1 LAMPU RM 2 x 18 WATT BUAH 1.00 380,000.00 380,000.00
2 ACCESSORIES % 5.00 19,000.00 95,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33
II BAHAN
1 PIPA LISTRIK 5/8" BATANG 1.00 22,800.00 22,800.00
2 KABEL NYM 3 x 2.5 MM M 6.00 21,250.00 127,500.00
3 T DUS BUAH 1.00 3,000.00 3,000.00
4 L BOW BUAH 1.00 3,000.00 3,000.00
5 LAS DOP BUAH 1.00 2,500.00 2,500.00
6 KLEM BUAH 4.00 500.00 2,000.00
7 MANGKOK BUAH 1.00 5,000.00 5,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,666.67
2 TUKANG ORG/HARI 0.02 150,000.00 3,333.33
3 PEKERJA ORG/HARI 0.04 130,000.00 5,777.78
II BAHAN
1 SAKLAR SERIE BUAH 1.00 18,000.00 18,000.00
2 PERLENGKAPAN INSTALASI % 5.00 900.00 4,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,500.00
2 TUKANG ORG/HARI 0.03 150,000.00 5,000.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00
II BAHAN
1 LAMPU RM 3 x 36 WATT BUAH 1.00 420,000.00 420,000.00
2 ACCESSORIES % 5.00 21,000.00 105,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,666.67
2 TUKANG ORG/HARI 0.02 150,000.00 3,333.33
3 PEKERJA ORG/HARI 0.04 130,000.00 5,777.78
II BAHAN
1 STOP KONTAK BUAH 1.00 18,000.00 18,000.00
2 PERLENGKAPAN INSTALASI % 5.00 900.00 4,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 3,666.67
2 TUKANG ORG/HARI 0.02 150,000.00 3,333.33
3 PEKERJA ORG/HARI 0.04 130,000.00 5,777.78
II BAHAN
1 STOP KONTAK AC BUAH 1.00 42,000.00 42,000.00
2 PERLENGKAPAN INSTALASI % 5.00 2,100.00 10,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33
II BAHAN
1 PIPA LISTRIK 5/8" BATANG 1.00 22,800.00 22,800.00
2 KABEL NYM 3 x 2.5 MM M 6.00 21,250.00 127,500.00
3 T DUS BUAH 2.00 3,000.00 6,000.00
4 L BOW BUAH 2.00 3,000.00 6,000.00
5 LAS DOP BUAH 2.00 2,500.00 5,000.00
6 KLEM BUAH 4.00 500.00 2,000.00
7 MANGKOK BUAH 1.00 5,000.00 5,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00
II BAHAN
1 MCB - 1 PH (10 A) 10 KA BUAH 1.00 80,000.00 80,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.20 165,000.00 33,000.00
2 TUKANG ORG/HARI 0.20 150,000.00 30,000.00
3 PEKERJA ORG/HARI 0.40 130,000.00 52,000.00
II BAHAN
1 MCB - 3 PH (50 A) 10 KA BUAH 1.00 1,100,000.00 1,100,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 PIPA GALVANIS 3/4" METER 25.00 60,000.00 1,500,000.00
2 PERLENGKAPAN INSTALASI % 5.00 3,000.00 15,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 SPLINKE BUAH 1.00 120,000.00 120,000.00
2 ACCESSORIES % 5.00 6,000.00 30,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 PIPA GALVANIS 3/4" METER 15.00 60,000.00 900,000.00
2 PERLENGKAPAN INSTALASI % 5.00 3,000.00 15,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 SMOKE DETECTOR BUAH 1.00 450,000.00 450,000.00
2 ACCESSORIES % 5.00 22,500.00 112,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33
II BAHAN
1 PLAT BORDES LEMBAR 0.67 185,000.00 123,395.00
2 BESI SIKU 40.40.4 M' 2.00 32,000.00 64,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.20 130,000.00 26,000.00
II BAHAN
1 BESI HOLLOW 40x40 Mm M' 4.40 99,250.00 436,700.00
2 BESI HOLLOW 20x40 Mm M' 5.00 74,500.00 372,500.00
3 BESI HOLLOW Dia.2" M' 1.52 99,250.00 150,860.00
4 KAWAT LAS KG 0.39 26,000.00 10,140.00
III ALAT
1 ALAT BANTU LS 1.00 455,000.00 455,000.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.14 165,000.00 22,916.67
2 TUKANG ORG/HARI 0.28 150,000.00 41,666.67
3 PEKERJA ORG/HARI 1.11 130,000.00 144,444.44
II BAHAN
1 SEMEN KG 229.28 1,400.00 320,989.20
2 PASIR BETON M3 0.35 400,000.00 140,680.00
3 KERIKIL M3 0.63 550,000.00 348,535.00
4 AIR LTR 215.00 100.00 21,500.00
III ALAT
1 CONCRETE MIXER JAM 0.71 75,300.00 53,570.57
2 CONCRETE VIBRATOR JAM 0.71 49,600.00 35,286.86
3 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.15 130,000.00 19,500.00
II BAHAN
1 BESI HOLLOW 40x40 mm M' 2.10 99,250.00 208,425.00
2 KAWAT LAS KG 0.11 26,000.00 2,730.00
3 ATAP ZINCALUME 0.3 MM M2 1.10 63,000.00 69,300.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,600.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.16 130,000.00 20,800.00
II BAHAN
1 KANSTEEN 15 x 20 x 30 x 50 CM BUAH 2.00 40,000.00 80,000.00
2 SEMEN KG 0.09 1,400.00 120.40
3 PASIR PASANG M3 0.01 225,000.00 2,250.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,496.06
2 TUKANG ORG/HARI 0.04 150,000.00 5,905.51
3 PEKERJA ORG/HARI 0.08 130,000.00 10,236.22
II BAHAN
1 CAT DASAR KG 0.10 54,000.00 5,400.00
2 CAT FINISHNG KG 0.10 245,000.00 24,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,500.00
2 PEKERJA ORG/HARI 0.07 130,000.00 8,666.67
II BAHAN
1 GEMBALAN RUMPUT M2 1.10 30,000.00 33,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 5,498.17
2 TUKANG ORG/HARI 0.07 150,000.00 9,996.67
3 PEKERJA ORG/HARI 0.13 130,000.00 17,327.56
II BAHAN
1 ATAP ZINCALUME 0.3 MM M2 1.43 63,000.00 90,027.00
2 SCREW CTEKS 12-4 x 50 BUAH 6.00 800.00 4,800.00
3 SCREW CTEKS 10 X 16-16 BUAH 2.00 1,000.00 2,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,883.33
2 TUKANG ORG/HARI 0.07 150,000.00 10,803.02
3 PEKERJA ORG/HARI 0.29 130,000.00 37,450.49
II BAHAN
1 HOLLOW METAL FURING M' 7.20 22,000.00 158,400.00
2 ACCESSORIES % 5.00 1,100.00 5,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.05 150,000.00 7,500.00
3 PEKERJA ORG/HARI 0.20 130,000.00 26,000.00
II BAHAN
1 GYPSUM BOARD LEMBAR 2.10 70,000.00 147,000.00
2 PAKU SEKRUP KG 0.22 55,000.00 12,100.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
ITEM PEKERJAAN : PEKERJAAN KUSEN ALUMINIUM DAUN PINTU PANEL LAPIS HPL
SATUAN PEMBAYARAN : BH
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.50 165,000.00 82,500.00
2 TUKANG ORG/HARI 0.50 150,000.00 75,000.00
3 PEKERJA ORG/HARI 1.00 130,000.00 130,000.00
II BAHAN
1 PROFIL PINTU ALUMINIUM M2 2.84 350,000.00 992,250.00
2 HPL M2 4.73 245,000.00 1,157,625.00
3 SEALANT KG 0.06 30,000.00 1,800.00
4 NEOPRENE GASKET ROLL 2.50 110,000.00 275,000.00
5 STRUCTURAL SEALANT BUAH 1.00 24,000.00 24,000.00
6 ANGKUR PLAT BAJA BUAH 8.00 4,000.00 32,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,000.00
2 TUKANG ORG/HARI 0.07 150,000.00 10,000.00
3 PEKERJA ORG/HARI 0.13 130,000.00 17,333.33
II BAHAN
1 LIST PLAN KAYU 10 CM M 1.10 25,000.00 27,500.00
2 PAKU SKRUP KG 0.11 55,000.00 6,050.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.00 165,000.00 471.43
2 TUKANG ORG/HARI 0.00 150,000.00 428.57
3 PEKERJA ORG/HARI 0.01 130,000.00 742.86
II BAHAN
1 BESI TULANGAN (POLOS/ULIR) KG 1.05 12,500.00 13,125.00
2 KAWAT BETON KG 0.02 40,000.00 600.00
III ALAT
1 ALAT BANTU LS 1.00 200.00 200.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.10 165,000.00 16,500.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.40 130,000.00 52,000.00
II BAHAN
1 PAPAN BEKISTING M3 0.02 2,200,000.00 52,800.00
2 KASO 5/7 CM M3 0.01 3,500,000.00 35,000.00
3 PAKU KG 0.30 18,000.00 5,400.00
4 MINYAK BEKISTING LITER 0.20 5,000.00 1,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 6,600.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.16 130,000.00 20,800.00
II BAHAN
1 PROFIL C BAJA RINGAN M' 3.00 22,000.00 66,000.00
2 RENG BAJA RINGAN M' 2.00 11,000.00 22,000.00
3 DINABOLT KG 0.50 60,000.00 30,000.00
4 SEKRUP FIXER KG 0.50 55,000.00 27,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 GLASS BLOCK 20X20 UNIT 25.00 25,000.00 625,000.00
2 PASIR PASANG M3 0.05 225,000.00 10,125.00
3 SEMEN KG 9.68 1,400.00 13,552.00
4 - - -
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 COR BETON M3 0.02 1,299,602.00 25,992.04
2 BESI TULANGAN POLOS KG 11.60 12,500.00 145,000.00
3 -
4 -
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.30 130,000.00 39,000.00
II BAHAN
1 COR BETON M3 0.02 1,299,602.00 25,992.04
2 BESI TULANGAN POLOS KG 14.90 12,500.00 186,250.00
3 -
4 -
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,155.00
2 KEPALA TUKANG ORG/HARI 0.65 150,000.00 97,500.00
3 TUKANG ORG/HARI 0.07 160,000.00 10,560.00
4 PEKERJA ORG/HARI 0.33 130,000.00 42,900.00
II BAHAN
1 ACP M3 1.10 840,000.00 924,000.00
2 HOLLOW 4X4X1MM KG 1.00 22,000.00 22,000.00
3 BRACKET BUAH 0.28 60,000.00 16,800.00
4
III ALAT
1 STAGER SET 0.02 110,000.00 2,200.00
2 LISTRIK KERJA LS 1.00 5,000.00 5,000.00
3 ALAT BANTU SET 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,155.00
2 KEPALA TUKANG ORG/HARI 0.65 150,000.00 97,500.00
3 TUKANG ORG/HARI 0.07 160,000.00 10,560.00
4 PEKERJA ORG/HARI 0.33 130,000.00 42,900.00
II BAHAN
1 ACP M2 1.10 840,000.00 924,000.00
2 HOLLOW 4X4X1MM M 1.00 22,000.00 22,000.00
3 BRACKET Buah 0.28 60,000.00 16,800.00
4 PAKU SCRUP KG 0.10 55,000.00 5,500.00
5 PAKU BETON DUS 0.20 22,000.00 4,400.00
6 SEALANT BUAH 0.25 25,000.00 6,250.00
7 KACA CERMIN M2 1.00 125,000.00 125,000.00
III ALAT
1 STAGER SET 0.02 110,000.00 2,200.00
2 LISTRIK KERJA LS 1.00 5,000.00 5,000.00
3 ALAT BANTU SET 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 TUKANG ORG/HARI 0.25 150,000.00 37,050.00
2 PEKERJA ORG/HARI 0.25 130,000.00 32,110.00
II BAHAN
1 Downlight BUAH 1.00 79,500.00 79,500.00
2 SKRUP BUAH 10.00 400.00 4,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 990.00
2 TUKANG ORG/HARI 0.06 150,000.00 9,000.00
3 PEKERJA ORG/HARI 0.06 130,000.00 7,800.00
II BAHAN
1 Baja Profil WF 150 kg 1.10 21,238.10 23,361.90
2 Las kg 1.00 2,500.00 2,500.00
3 Zincromate + cat finishing m2 0.03 65,000.00 1,950.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 990.00
2 TUKANG ORG/HARI 0.60 150,000.00 90,000.00
3 PEKERJA ORG/HARI 1.20 130,000.00 156,000.00
II BAHAN
1 Semen kg 230.00 1,400.00 322,000.00
2 Pasir Beton m3 0.54 400,000.00 214,800.00
3 Kerilkil m3 0.57 550,000.00 314,050.00
4
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 TUKANG ORG/HARI 0.04 150,000.00 6,000.00
3 PEKERJA ORG/HARI 0.60 130,000.00 78,000.00
II BAHAN
1 Cor Beton M3 0.05 1,299,602.00 64,980.10
2
3
4
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 PEKERJA ORG/HARI 0.30 150,000.00 45,000.00
II BAHAN
1 PASIR PASANG M3 1.20 155,000.00 186,000.00
2
3
4
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.04 165,000.00 5,775.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.70 130,000.00 91,000.00
II BAHAN
1 SEMEN kg 1.14 1,400.00 1,596.00
2 SEMEN WARNA kg 0.50 17,000.00 8,500.00
3 PASIR PASANG m3 0.05 225,000.00 10,125.00
4 KERAMIK 20x20 buah 26.50 4,400.00 116,600.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,155.12
3 PEKERJA ORG/HARI 0.50 130,000.00 65,000.00
II BAHAN
1 SEALANT BUAH 0.25 30,000.00 7,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 8,250.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.13 130,000.00 16,250.00
II BAHAN
1 Urinoir buah 1.00 2,485,000.00 2,485,000.00
2 Semen kg 1.00 1,400.00 1,400.00
3 Pasir Pasang m3 0.50 155,000.00 77,500.00
4
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 TUKANG ORG/HARI 0.40 150,000.00 60,000.00
3 PEKERJA ORG/HARI 0.01 130,000.00 1,300.00
II BAHAN
1 Kran buah 1.00 95,000.00 95,000.00
2 Seal buah 0.03 17,000.00 425.00
3
4
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 825.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.01 130,000.00 1,300.00
II BAHAN
1 floor drain buah 1.00 75,000.00 75,000.00
2 -
3
4
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.02 165,000.00 2,475.00
2 TUKANG ORG/HARI 0.02 150,000.00 2,250.00
3 PEKERJA ORG/HARI 0.16 130,000.00 20,800.00
II BAHAN
1 waterproofing dumplix kg 0.45 625,000.00 281,250.00
2
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 TUKANG ORG/HARI 0.25 150,000.00 37,050.00
2 PEKERJA ORG/HARI 0.25 130,000.00 32,110.00
II BAHAN
1 Downlight buah 1.00 79,500.00 79,500.00
2
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.07 165,000.00 11,550.00
2 KEPALA TUKANG ORG/HARI 0.02 160,000.00 3,520.00
3 TUKANG ORG/HARI 0.11 150,000.00 16,500.00
4 PEKERJA ORG/HARI 0.11 130,000.00 14,300.00
II BAHAN
1 KALSIPLANK M2 1.50 139,500.00 209,250.00
2 PAKU KG 0.12 18,000.00 2,070.00
3 PAKU SKRUP KG 0.10 55,000.00 5,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.85 150,000.00 127,500.00
3 PEKERJA ORG/HARI 0.25 130,000.00 32,500.00
II BAHAN
1 glasswoll m2 1.30 58,333.33 75,833.33
2 Seal buah 0.25 17,000.00 4,250.00
3
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.03 165,000.00 4,125.00
2 PEKERJA ORG/HARI 0.80 130,000.00 104,000.00
II BAHAN
1
2
3
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.05 165,000.00 7,425.00
2 KEPALA TUKANG ORG/HARI 0.30 160,000.00 48,000.00
3 TUKANG ORG/HARI 0.70 150,000.00 105,000.00
4 PEKERJA ORG/HARI 0.35 130,000.00 45,500.00
II BAHAN
1 Main Truss m1 2.80 -
2 Roof Bottom R33-0.45 m1 5.10 11,000.00 56,100.00
3 Self Drilling Screw 6x20mm (truss Screw) bh 25.00 1,000.00 25,000.00
4 Self Drilling Screw 4x16mm(roof bottom screw) bh 35.00 800.00 28,000.00
5 Dynabolt bh 25.00 2,500.00 62,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.36 150,000.00 53,250.00
3 PEKERJA ORG/HARI 0.15 130,000.00 19,500.00
II BAHAN
1 Tiang Baja m 6.80 144,750.00 984,300.00
2 Las kg 1.00 26,000.00 26,000.00
3 Plat Besi kg 1.82 125,000.00 228,000.00
4 CAT BESI DASAR kg 0.45 80,000.00 36,000.00
5 CAT BESI FINISHING kg 0.50 80,000.00 40,000.00
III ALAT
1 ALAT BANTU LS 1.00 1,100.00 1,100.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1
2
3
II BAHAN
1 PENUTUP ATAP M2 1.00 130,149.39 130,149.39
2 PASANGAN RANGKA ATAP TITIK 1.00 378,025.00 378,025.00
III ALAT
1
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 1,650.00
2 TUKANG ORG/HARI 0.13 150,000.00 19,522.50
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00
II BAHAN
1 PAVING BLOCK BUAH 25.00 6,500.00 162,500.00
2 PASIIR PASANG M3 0.15 155,000.00 23,250.00
III ALAT
1 ALAT BANTU SET 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.00 165,000.00 165.00
2 TUKANG ORG/HARI 0.10 150,000.00 15,000.00
3 PEKERJA ORG/HARI 0.10 130,000.00 13,000.00
II BAHAN
1 KABEL NYY 4 x 16mm M1 1.00 209,000.00 209,000.00
2 Aksesoris LS 1.00 1,000.00 1,000.00
III ALAT
1 ALAT BANTU SET 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.00 165,000.00 165.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.01 130,000.00 1,690.00
II BAHAN
1 BESI HOLLOW 40x40 Mm M1 3.50 99,250.00 347,375.00
2 Aksesoris LS 1.00 -
III ALAT
1 ALAT BANTU SET 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 165,000.00 2,145.00
2 TUKANG ORG/HARI 0.25 150,000.00 37,500.00
3 PEKERJA ORG/HARI 0.25 130,000.00 32,500.00
II BAHAN
1 BESI HOLLOW 40x40 mm M1 1.10 99,250.00 109,175.00
2 Las KG 1.00 26,000.00 26,000.00
3 Dyna bolt Buah 10.00 2,500.00 25,000.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
HARGA TOTAL
NO URAIAN SATUAN KOEFISIEN SATUAN HARGA
(RP) (RP)
I TENAGA
1 MANDOR ORG/HARI 0.01 150,000.00 1,950.00
2 TUKANG ORG/HARI 0.25 160,000.00 40,000.00
3 PEKERJA ORG/HARI 0.25 165,000.00 41,250.00
II BAHAN
1 BESI HOLLOW 40x40 mm M1 1.10 99,250.00 109,175.00
2 Las KG 1.00 26,000.00 26,000.00
3 Dyna bolt Buah 10.00 2,500.00 25,000.00
4 Seng Plat Lembar 1.00 99,500.00 99,500.00
III ALAT
1 ALAT BANTU LS 1.00 500.00 500.00
A TENAGA
1 PEKERJA/PEMBANTU TUKANG OH Rp. 130,000.00
2 TUKANG OPERATOR OH Rp. 150,000.00
3 KEPALA TUKANG OH Rp. 160,000.00
4 MANDOR OH Rp. 165,000.00
B BAHAN
1 KAYU KASO 5/7 M3 Rp. 3,500,000.00
2 KAYU BEKISTING M3 Rp. 2,200,000.00
3 KAYU MERANTI M3 Rp. 3,500,000.00
4 DOLKEN KAYU DIA. 8-10/400 CM BATANG Rp. 25,000.00
5 PLYWOOD 4 MM LEMBAR Rp. 70,000.00
6 SEMEN KG Rp. 1,400.00
7 SEMEN WARNA KG Rp. 17,000.00
8 PASIR BETON M3 Rp. 400,000.00
9 PASIR PASANG M3 Rp. 155,000.00
10 KORAL BETON M3 Rp. 550,000.00
11 BATU GUNUNG M3 Rp. 350,000.00
12 BATU BATA BUAH Rp. 850.00
13 PAKU KG Rp. 18,000.00
14 PAKU BETON DUS Rp. 22,000.00
15 SEKRUP KG Rp. 55,000.00
16 SEKRUP BUAH Rp. 400.00
17 PLAFON ASBES 3 MM LEMBAR Rp. 28,000.00
18 ASBES GELOMBANG LEMBAR Rp. 33,000.00
19 SENG GELOMBANG LEMBAR Rp. 74,500.00
20 SENG PLAT LEMBAR Rp. 99,500.00
21 ATAP ZINCALUME 0.3 MM LEMBAR Rp. 63,000.00
22 BETON MUTU K-175 M3 Rp. 1,593,000.00
23 BETON MUTU K-250 M3 Rp. 1,789,000.00
24 BETON MUTU K-300 M3 Rp. 1,823,000.00
25 PINTU DOUBEL TEAKWOOD M2 Rp. 150,000.00
No. URAIAN SATUAN HARGA
(Rp.)
1 2 4 5
26 JENDELA NAKO DAUN Rp. 400,000.00
27 CAT DINDING DASAR KG Rp. 54,000.00
28 CAT DINDING FINISHING INTERIOR KG Rp. 150,000.00
29 CAT DINDING FINISHING EXTERIOR KG Rp. 245,000.00
30 CAT BESI DASAR KG Rp. 80,000.00
31 CAT BESI FINISHING KG Rp. 80,000.00
32 PLAMIR KG Rp. 15,000.00
33 PREMIUM LITER Rp. 10,500.00
34 SOLAR LITER Rp. 11,500.00
35 MINYAK PELUMAS LITER Rp. 30,000.00
36 MINYAK BEKISTING LITER Rp. 5,000.00
37 AIR LITER Rp. 100.00
38 BESI BETON POLOS KG Rp. 12,500.00
39 BESI BETON ULIR KG Rp. 13,000.00
40 BESI BAJA KG Rp. 21,238.10
41 KAWAT BETON KG Rp. 25,000.00
42 HOMOGENIUS TILE 60 x 60 BUAH Rp. 100,000.00
43 PLINT HOMOGENIUS TILE 10 x 60 BUAH Rp. 17,000.00
44 GYPSUM BOARD 9 MM LEMBAR Rp. 70,000.00
45 HOLLOW METAL FURING METER Rp. 22,000.00
46 LIST PROFIL GYPSUM METER Rp. 40,000.00
47 TEPUNG GYPSUM KG Rp. 2,400.00
48 PROFIL ALUMUNIUM M Rp. 110,000.00
49 SEALENT KG Rp. 30,000.00
50 PINTU ALUMINIUM M Rp. 350,000.00
51 KUNCI TANAM SELINDER BUAH Rp. 260,000.00
52 KACA 5 MM M2 Rp. 162,640.00
53 ENGSEL BUAH Rp. 100,000.00
54 GRANDEL JENDELA BUAH Rp. 25,000.00
55 BESI STAINLESS STEEL DIA. 2" M Rp. 122,500.00
56 BESI STAINLESS STEEL DIA. 3" M Rp. 144,750.00
57 KAWAT LAS KG Rp. 26,000.00
58 LAMPU RM 2 x 18 WATT BUAH Rp. 380,000.00
59 LAMPU RM 3 x 36 WATT BUAH Rp. 420,000.00
60 PIPA LISTRIK 5/8" BATANG Rp. 22,800.00
61 KABEL NYM 3 x 2.5 MM M Rp. 21,250.00
62 KABEL NYY 4 x 16mm M Rp. 209,000.00
63 T DUS BUAH Rp. 3,000.00
64 L BOW BUAH Rp. 3,000.00
65 LAS DOP BUAH Rp. 2,500.00
66 KLEM BUAH Rp. 500.00
No. URAIAN SATUAN HARGA
(Rp.)
1 2 4 5
67 MANGKOK BUAH Rp. 5,000.00
68 SAKLAR BUAH Rp. 18,000.00
69 STOP KONTAK BUAH Rp. 18,000.00
70 STOP KONTAK AC BUAH Rp. 42,000.00
71 MCB - 1 PH (10 A) 10 KA BUAH Rp. 80,000.00
72 MCB - 3 PH (50 A) 10 KA BUAH Rp. 1,100,000.00
73 PIPA GALVANIS 3/4" M Rp. 60,000.00
74 SPLINKE BUAH Rp. 120,000.00
75 SMOKE DETECTOR BUAH Rp. 450,000.00
76 PLAT BORDES LEMBAR Rp. 185,000.00
77 BESI SIKU 40.40.4 M' Rp. 32,000.00
78 BESI HOLLOW 40x40 Mm M' Rp. 99,250.00
79 BESI HOLLOW 20x40 Mm M' Rp. 74,500.00
80 BESI HOLLOW Dia. 2" M' Rp. 99,250.00
81 KANSTEEN 15 x 20 x 30 x 50 CM, K-225 BUAH Rp. 40,000.00
82 GEMBALAN RUMPUT M2 Rp. 30,000.00
83 SCREW CTEKS 12-4 x 50 BUAH Rp. 800.00
84 SCREW CTEKS 10 X 16-16 BUAH Rp. 1,000.00
85 HPL M2 Rp. 255,000.00
86 NEOPRENE GASKET ROLL Rp. 22,000.00
87 STRUCTURAL SEALANT BUAH Rp. 24,000.00
88 ANGKUR PLAT BAJA BUAH Rp. 4,000.00
89 LIST PLAN KAYU 10 CM M Rp. 25,000.00
90 PROFIL C BAJA RINGAN M' Rp. 22,000.00
91 RENG BAJA RINGAN M' Rp. 11,000.00
92 DINABOLT BUAH Rp. 2,500.00
93 SEKRUP FIXER KG Rp. 55,000.00
94 PLAT BESI 2MM KG Rp. 125,000.00
95 DOWNLIGHT 4" BUAH Rp. 79,500.00
96 BRACKET BUAH Rp. 60,000.00
97 GLASS BLOCK BUAH Rp. 25,000.00
98 ACP LEMBAR Rp. 840,000.00
99 ZINC CHROMATE KG Rp. 65,000.00
100 KERAMIK 20x20 DUS Rp. 110,000.00
101 KERAMIK 20x20 BUAH Rp. 4,400.00
102 URINOIR BUAH Rp. 2,485,000.00
103 KRAN AIR BUAH Rp. 95,000.00
104 FLOOR DRAIN BUAH Rp. 75,000.00
105 CAT PELAPIS WATERPROOF KG Rp. 625,000.00
106 KALSIPLANK M2 Rp. 139,500.00
107 GLASSWOOL ROLL Rp. 1,750,000.00
108 GLASSWOOL M Rp. 58,333.33
109 BESI DIA. 16mm KG Rp. 8,391.00
No. URAIAN SATUAN HARGA
(Rp.)
1 2 4 5
110 GENTENG MULTIROOF 0.35MM LEMBAR Rp. 95,000.00
111 KACA CERMIN M2 Rp. 125,000.00
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
SKETSA :
LANTAI 1 E
90
D
325
C
345
B
325
A
400 400 250 445 290 250
7 6 5 4 3 2 1
RENC. INSTALASI & TITIK LAMPU LT. 1
LANTAI 3
SKALA 1 : 100
90
D
325
C
345
B
325
A
400 400 250 445 290 250
7 6 5 4 3 2 1
RENC. INSTALASI & TITIK LAMPU LT. 3
SKALA 1 : 100
IX.1.1 LANTAI 1
1 Pemasangan meteran listrik daya 33.000 watt - - - 1.00 1.00 Buah
2 Pasang lampu RM 2 x 18 w - - - 13.00 13.00 Buah
3 Instalasi titik lampu - - - 13.00 13.00 Titik
4 saklar serie - - - 3.00 3.00 Titik
5 Instalasi titik lampu - Downlight - - - 6.00 6.00 Titik
6 Pemasangan Kabel NYY 4 x 16 50.00 - - 1.00 50.00 M1
IX.1.2 LANTAI 3
1 Pasang lampu RM 3 x 36 w - - - 26.00 26.00 Buah
2 Instalasi titik lampu - - - 26.00 26.00 Titik
3 Saklar serie - - - 5.00 5.00 Titik
4 Stop kontak dinding, 1 Ph, 10 A - - - 16.00 16.00 Buah
5 Stop kontak AC - - - 11.00 11.00 Buah
6 Instalasi stop kontak - - - 16.00 16.00 Buah
7 Instalasi titik lampu - Downlight 3.00 3.00 Titik
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
SKETSA :
E
90
D
325
C
345
B
325
A
400 400 250 445 290 250
7 6 5 4 3 2 1
RENC. INSTALASI & TITIK LAMPU LT. 3
SKALA 1 : 100
IX.2.1 PP - 1 LANTAI 1
1 MCB - 1 Ph ( 10 A ) 10 KA - - bh
IX.2.2 PP - 3 LANTAI 3
1 MCB - 3 Ph ( 50 A ) 10 KA 1.00 1.00 bh
2 MCB - 1 Ph ( 10 A ) 10 KA 8.00 8.00 bh
3 Pilot lamp 3.00 3.00 bh
4 Fuse patron 3.00 3.00 bh
5 Kwh meter 1.00 1.00 bh
6 CU. Bar 4 x (12 mm x 2 mm) 3.00 3.00 lot
7 Box panel 1.00 1.00 bh
8 Kabel dalam panel 1.00 1.00 lot
9 Kawat BC - 6 mm2 1.00 1.00 lot
10 Material lain - lain 1.00 1.00 lot
11 Biaya pemasangan 1.00 1.00 lot
12 Instalasi Titik Lampu 3.00 3.00 titik
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
X.1 LANTAI 2
5 Pengadaan alat pemadam api ringan 5 kg 5.00 Buah
X.2 LANTAI 3
5 Pengadaan alat pemadam api ringan 5 kg 7.00 Buah
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
XI PEKERJAAN LANDSCAPE
1 Grill dilapisi besi plat bordes
- Besi siku 4.60 - - 2.00 9.20 M1
1.80 - - 1.00 1.80 M1
0.60 - - 5.00 3.00 M1
JUMLAH 14.00 M1
4 Pekerjaan kanopi
- kanopi tempat wudhu 10.22 0.85 - 1.00 8.69 M2
- kanopi depan Aula 12.65 0.85 - 1.00 10.75 M2
JUMLAH 19.44 M2
50
SKETSA :
400
220 60 120
300
300
X X X
300
X X
300
275
PARKIRAN
300
1800
EL - 0,600
1800
325
300
Y
280
Y
80 200
280
260
140
460
60
260
140
60
EL - 0,200
PARKIRAN
120
400
75
EL - 0,600
140
60
60
60
120
300 300 290 200 120
80
50 1210
450
300
300
2700
2700
300
2200 600 1200 800 600 2600
4000 4000
Berat/m2
3 Pembesian - Angkur M16 - - 4.00 22.00 - 88.00 Buah
- Plat Strip 20.20.5 0.20 0.20 - 22.00 40.63 35.75 KG
10 Beton sikat
Depan teras musholla 4.28 2.26 - 1.00 - 9.68 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
SKETSA :
E E
105
90
90
D D
200
T. WUDHU T. WUDHU
215
EL - 0.150 EL - 0.150
375
95
230
LAV. WANITA
R. SATKER EL + 4.000
325
128
EL + 4.000
325
87 LAV PRIA
EL + 4.000
1115
1190
MUSHOLLAH
EL ± 0.000
345
R.RAPAT
AULA EL + 4.000
345
EL - 0.100
900
900
B
B
325
325
A
400 400 250 445 290 250
A
400 400 250
985
445 290 250 7 6 5 4 3 2 1
7 6 5 4 3 2 1 DENAH LT. 2
2065 SKALA 1 : 100
DENAH LT. 1
1243 SKALA 1 : 100
90
D
325
340
+ 8.000
549
+ 8.000 + 8.000
785
1115
120
345
216 120 120 224
120 560
R. SERBA GUNA
640
+ 8.000 B
DSE STAFF
318
303
325
+ 8.000 DSE R. TEKNIS PPK
+ 8.000 + 8.000
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 3
2050 SKALA 1 : 100
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 1.00 LS
12.65 11.9
R BWS KALIMANTAN III
VOLUME SATUAN
24.55
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
430
SKETSA :
220 T. WUDHU
EL - 0.150
77 77 207 E
90
POMPA
D
185
45
80
335 315 45
325
58
C
MUSHOLLAH
EL ± 0.000
AULA
345
EL - 0.100
325
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 1
SKALA 1 : 100
II.1 Lantai 1
1 Pasangan batu bata ( 1 Pc : 5 Pasir ) 0.65 - - 4.00 - 1.00 2.60 M2
2.20 - - 4.00 - 1.00 8.80 M2
0.77 - - 4.00 - 2.00 6.16 M2
2.08 - - 4.00 - 1.00 8.31 M2
3.35 - - 4.00 - 1.00 13.40 M2
0.80 - - 4.00 - 2.00 6.40 M2
3.15 - - 4.00 - 1.00 12.60 M2
0.45 - - 4.00 - 1.00 1.80 M2
0.59 - - 2.50 - 1.00 1.47 M2
4.30 - - 4.00 - 1.00 17.20 M2
0.25 - - 1.22 - 4.00 1.22 M2
0.50 - - 1.22 - 4.00 2.44 M2
JUMLAH 82.41 M2
JUMLAH 51.31 M2
SKETSA : E
90
D
498
325
310
+ 8.000 + 8.000 + 8.000
CR
378 285 jadi ppintu
geser
CR
68
224 224
345
230
438
318
B
555
318
R. TEKNIS PPK
325
335
STAFF
DSE + 8.000
203
+ 8.000
168
240
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 3
SKALA 1 : 100
JUMLAH 31.61 M2
JUMLAH 334.12 M2
PENGURANGAN
- Jendela 1.55 - 1.90 5.00 - 14.73 M2
2.30 - 1.90 10.00 - 43.70 M2
JUMLAH 58.43 M2
LUAS PLESTERAN 275.69 M2
3 Acian
- Plesteran Lantai 3 275.69 - - 1.00 - 275.69 M2
- Sisi Tangga 2.60 - 2.00 1.00 - 5.20 M2
3.00 - 2.00 0.50 - 3.00 M2
1.00 - 2.00 1.00 - 2.00 M2
3.85 - 2.00 1.00 - 7.70 M2
2.80 - 1.80 0.50 - 2.52 M2
JUMLAH 296.11 M2
4 Benangan
- Jendela - 2.30 1.90 - 10.00 61.00 M1
- 1.55 1.90 - 5.00 26.75 M1
- Pintu - 1.50 2.50 - 1.00 6.50 M1
- 1.00 2.15 - 3.00 15.90 M1
- 0.80 2.00 - 2.00 9.60 M1
JUMLAH 119.75 M1
No. Uraian Pekerjaan PANJANG LEBAR TINGGI VOLUME SATUAN
JUMLAH
(M) (M) (M)
5 Kolom H-beam berat / m'
lantai 2 4.00 3.00 14.00 168.00 KG
7 Beton tebal
- balkon 3.46 2.40 0.12 - 1.00 1.00 M3
1.65 1.30 0.12 - 1.00 0.26 M3
- atap dak ruangan urinoir 3.55 2.58 0.12 - 1.00 1.10 M3
JUMLAH 2.36 M3
SKETSA :
E
90
D
498
325
310
+ 8.000 + 8.000 + 8.000
CR
378 285 jadi ppintu
geser
CR
68
224 224
345
230
438
318
B
555
318
R. TEKNIS PPK
325
335
STAFF
DSE + 8.000
203
+ 8.000
168
240
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 3
SKALA 1 : 100
Jumlah 16.80 M2
Jumlah 9.50 M2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
SKETSA
T. WUDHU
EL - 0.150
E
90
POMPA
D E
90
D
325
HOMOGENIUS HOMOGENIUS HOMOGENIUS
60x 60 60x 60 60x 60
325
POLA
C
LANTAI
EXISTING C
- 100 HOMOGENIUS
60x 60
345
- 100 HOMOGENIUS
HOMOGENIUS
60x 60
345
60x 60 HOMOGENIUS
60x 60
B
HOMOGENIUS
60x 60 B
325
HOMOGENIUS
HOMOGENIUS
325
HOMOGENIUS 60x 60
60x 60 60x 60
A
400 400 250 445 290 250
7 6 5 4 3 2 1 A
400 400 250 445 290 250
III.2 LANTAI 2
1 Lantai Homogeneus tangga
- Optrade 1.24 - 0.18 22.00 4.91 M2
- Aantrade 1.24 0.30 - 21.00 7.81 M2
- Bordes 2.68 1.05 - 1.00 2.81 M2
2.60 0.15 - 1.00 0.39 M2
JUMLAH 15.93 M2
Pengurangan
Void Tangga 4.35 2.83 - 1.00 12.31 M2
kolom 30.30 0.30 0.30 - 15.00 1.35 M2
dinding 3.70 0.15 - 4.00 2.22 M2
3.15 0.15 - 2.00 0.95 M2
2.95 0.15 - 2.00 0.89 M2
0.60 0.15 - 1.00 0.09 M2
2.20 0.15 - 2.00 0.66 M2
4.15 0.15 - 2.00 1.25 M2
3.25 0.15 - 1.00 0.49 M2
5.93 0.15 - 1.00 0.89 M2
3.75 0.15 - 1.00 0.56 M2
2.33 0.15 - 1.00 0.35 M2
JUMLAH 21.99 M2
LUAS LANTAI 3 179.60 M2
JUMLAH 50.26 M1
IV.2 LANTAI 3
1 Plafond gypsum 18.00 11.15 1.00 200.70 M2
JUMLAH 200.70 M2
Pengurangan
- Kolom 30.30 0.30 0.30 - 16.00 1.44 M2
- dinding 2.95 0.15 - 2.00 0.89 M2
3.15 0.15 - 2.00 0.95 M2
3.70 0.15 - 4.00 2.22 M2
0.60 0.15 - 1.00 0.09 M2
2.20 0.15 - 2.00 0.66 M2
4.15 0.15 - 2.00 1.25 M2
2.60 0.15 - 1.00 0.39 M2
3.85 0.15 - 1.00 0.58 M2
7.38 0.15 - 1.00 1.11 M2
3.60 0.15 - 1.00 0.54 M2
3.25 0.15 - 1.00 0.49 M2
2.68 0.15 - 1.00 0.40 M2
3.26 0.15 - 1.00 0.49 M2
JUMLAH 11.48 M2
LUAS LANTAI 3 189.23 M2
No. Uraian Pekerjaan PANJANG LEBAR TINGGI JUMLAH VOLUME SATUAN
(M) (M) (M)
JUMLAH 120.72 M1
IV. 3 LANTAI 2
1 List Plafond - Ruang Administrasi & Rapat 27.75 - - 1.00 27.75 M1
V.2 LANTAI 3
1 Pengecatan dinding dalam 296.11 1.00 296.11 M2
SKETSA :
LANTAI 1
600 500 500 500 550 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500
300
2500 4451 2900 2500
5 4 3 2 1
P2
1000x2150
J3 J3 ± 0,000 J2 J3 P2
LANTAI 3 2240x1900
+ 0,600
2240x1900
+ 0,600
1550x1900
+ 0,600
2240x1900
+ 0,600
1000x2150
± 0,000
90
D
J3 STAFF
AP COMMAND CENTER STAFF
325
2240x1900 + 8.000 + 8.000 + 8.000
+ 0,600
P2 C
1000x2150
P1
± 0,000
J3 1900x2500
345
2240x1900 J2 ± 0,000
+ 0,600 1550x1900
B P2
1000x2150
J3 J3 ± 0,000
325
STAFF R. TEKNIS PPK
2240x1900 DSE + 8.000 2240x1900
+ 8.000
+ 0,600 + 0,600
A
400 400 250 445 290 250
7 6 5 4 3 2 1
J3 J3 J2 J3 J2
2240x1900 2240x1900 1550x1900 2240x1900 1550x1900
VI.1 LANTAI 1
VI.1.2 LANTAI 2
1 Perbaikan Jendela - Sealant - 2.24 1.90 7.00 57.96 M1
- 1.50 1.90 2.00 13.60 M1
Jumlah 71.56 M1
4 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) 3.00 3.00 Unit
VI.2 LANTAI 3
1 Pembuatan kusen pintu alumunium 4"
- J2 - 1.51 1.90 5.00 51.15 M1
- J3 - 2.24 1.90 10.00 143.20 M1
- P1 - 1.90 2.50 1.00 8.80 M1
- P2 - 1.07 2.15 1.00 5.37 M1
JUMLAH 208.52 M1
6 Pemasangan 1 pintu kaca dan kusen allumunium ( 2 daun) - - - 1.00 1.00 Unit
7 Pemasangan 1 pintu kaca dan kusen allumunium ( 1 daun) - - - 3.00 3.00 Unit
SKETSA : 220
430
T. WUDHU
EL - 0.150
8 12 91 91 12 8 77 77 207 E
90
POMPA
D
185
45
80
5
13 13 10 10 10 10 10 10 13
335 315 45
325
58
C
80
MUSHOLLAH
100
EL ± 0.000
AULA
345
EL - 0.100
10 5
325
8 213 8
A
220 400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 1
SKALA 1 : 100
VII.1 LANTAI 1
Railing
Hollow 40.40.0,4 1.00 8.00 8.00 M1
2.20 2.00 4.40 M1
4.15 2.00 8.30 M1
2.80 2.00 5.60 M1
3.13 2.00 6.26 M1
JUMLAH 32.56 M1
Hollow 20.40.0,4
0.03 12.00 0.36 M1
0.12 12.00 1.44 M1
0.74 12.00 8.88 M1
0.80 12.00 9.60 M1
0.84 14.00 11.76 M1
0.82 28.00 22.96 M1
1.17 14.00 16.38 M1
0.60 28.00 16.80 M1
JUMLAH 88.18 M1
Railing Pintu
1 Hollow 40.40.0,4 1.00 4.00 4.00 M1
0.90 4.00 3.60 M1
0.80 4.00 3.20 M1
0.70 4.00 2.80 M1
JUMLAH 13.60 M1
SKETSA :
E
90
D
8 12 91 91 12 8
325
5
13 13 10 10 10 10 10 10 13
CR
C
CR
80
100
345
230
10 5
B
8 213 8
220
R. TEKNIS PPK
325
+ 8.000
203
168
240
A
290 250
3 2 1
TOP
EL + 2.120
DENAH LT. 3
D1 D1 SKALA 1 : 100
D1 D1 D1 D1 D1
UR UR
CR CR
CR CR
C2 C2
E D C
VIII.2 LANTAI 2
1 Handrail stainless steel dia 2 " 9.00 - - 1.00 9.00 M1
2 Railing Balkon 5.87 - - 1.00 5.87 M2
VIII.3 LANTAI 3
1 Railing Balkon 8.40 - - 1.00 8.40 m1
2 Railing Sisi Urinoir 0.80 - - 1.00 0.80 m2
PERHITUNGAN VOLUME
PEKERJAAN : LANJUTAN PEMBANGUNAN DAN RENOVASI KANTOR BWS KALIMANTAN III
LOKASI : SAMARINDA
TAHUN ANGGARAN : 2021
VIII.2 LANTAI 3
1 Urinoir - - - 2.00 2.00 unit
2 Pasangan Kran - - - 2.00 2.00 buah
3 pasangan Floor Drain - - - 2.00 2.00 buah
4 Waterproofing 5.55 2.31 - 1.00 12.82 M2
2.35 1.02 - 1.00 2.40 M2
LUAS Waterproofing 15.22 M2
SKETSA :
90
D
LAV. WANITA
R. SATKER EL + 4.000
325
EL + 4.000
368
LAV PRIA
EL + 4.000
45 C
370
100
345
R.RAPAT
EL + 4.000
100
B
177
368
325
PPK
166
PERENCANA
EL + 4.000
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 2
SKALA 1 : 100
XII.1 LANTAI 2
XII.1.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi 3.00 - 3.50 1.00 10.50 M2
5.35 - 3.50 1.00 18.72 M2
1.10 - 1.22 1.00 1.34 M2
3.05 - 1.22 1.00 3.72 M3
3.50 - 1.22 1.00 4.27 M2
Jumlah 38.56 M2
- PENGURANGAN
Bukaan pintu 1.05 - 2.52 1.00 2.65 M2
Jumlah Rangka partisi 35.91 M2
90
D
LAV. WANITA
R. SATKER EL + 4.000
325
EL + 4.000
368
LAV PRIA
EL + 4.000
45 C
370
100
345
R.RAPAT
EL + 4.000
100
B
177
368
325
PPK
166
PERENCANA
EL + 4.000
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 2
SKALA 1 : 100
XII.1 LANTAI 2
XII.1.2 PARTISI RUANG RAPAT
1 Pekerjaan rangka partisi
4.65 - 3.50 2.00 32.55 M2
Jumlah 32.55 M2
- Pengurangan
Bukaan Pintu - 1.05 2.52 2.00 5.29 M2
Jumlah Rangka partisi 27.26 M2
SKETSA :
E
90
D
498
325
310
+ 8.000 + 8.000 + 8.000
CR
455 208
CR
68
224 224
345
438
318
B
555
318
R. TEKNIS PPK
325
STAFF
DSE + 8.000
203
+ 8.000
A
400 400 250 445 290 250
7 6 5 4 3 2 1
DENAH LT. 3
SKALA 1 : 100
XII.1 LANTAI 3
XII.2.1 PARTISI RUANG ADMINISTRASI
1 Pekerjaan rangka partisi 20.07 - 1.22 1.00 24.49 M2
14.83 - 3.50 1.00 51.91 M2
76.40 M2
Pekerjaan Pemasangan Kaca 5mm atas partisi 20.07 1.00 1.22 20.00 24.40 M2
TENAGA
PRODUKSI 4.500 M2/HARI
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- PEKERJA 6.000 ORG
ALAT
ALAT BANTU 1.000 LS
- PALU
- SEKOP
- GEROBAK DORONG
- DLL
TENAGA
PRODUKSI 7.500 M2/HARI
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 6.000 ORG
TENAGA
PRODUKSI PER HARI 100.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.010 HARI
- TUKANG 0.010 HARI
- PEKERJA 0.030 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PAGAR LOKASI
ALAT
ALAT BANTU 1.000 Ls
TENAGA
PRODUKSI PER HARI 20.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.200 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN BATU BATA (1 PC : 5 PASIR)
TENAGA
PRODUKSI PER HARI 10.200 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 6.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.098 HARI
- TUKANG 0.196 HARI
- PEKERJA 0.588 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PLESTERAN DINDING (1 PC : 5 PASIR)
TENAGA
PRODUKSI PER HARI 17.800 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.056 HARI
- TUKANG 0.056 HARI
- PEKERJA 0.169 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
KOLOM PRAKTIS
ALAT
ALAT BANTU 1.000 LS
- PALU
- PEMOTONG BESI
- GERGAJI
- DLL
TENAGA
PRODUKSI PER HARI 120.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.008 HARI
- TUKANG 0.008 HARI
- PEKERJA 0.033 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
ACIAN DINDING
TENAGA
PRODUKSI PER HARI 24.920 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.161 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
BENANGAN
TENAGA
PRODUKSI PER HARI 100.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.010 HARI
- TUKANG 0.020 HARI
- PEKERJA 0.040 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
KOLOM H. BEAM 250x250x9x14 MM DIBUNGKUS BETON TUL. DIA 8 MM
TENAGA
PRODUKSI PER HARI 16.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 8.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.063 HARI
- TUKANG 0.063 HARI
- PEKERJA 0.500 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LANTAI HOMOGENIUS 60 CM X 60 CM (POLISHED)
TENAGA
PRODUKSI PER HARI 22.200 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.045 HARI
- TUKANG 0.090 HARI
- PEKERJA 0.180 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LANTAI HOMOGENIUS TANGGA
TENAGA
PRODUKSI PER HARI 22.200 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.045 HARI
- TUKANG 0.090 HARI
- PEKERJA 0.180 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PLIN KERAMIK 10 CM x 60 CM
TENAGA
PRODUKSI PER HARI 25.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.080 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LAPIS CREED 3 CM - 7 CM
TENAGA
PRODUKSI PER HARI 87.566 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.011 HARI
- TUKANG 0.011 HARI
- PEKERJA 0.046 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PLAFOND GYPSUM
TENAGA
PRODUKSI PER HARI 166.992 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.006 HARI
- TUKANG 0.006 HARI
- PEKERJA 0.024 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RANGKA PLAFOND HOLLOW METAL FURING
TENAGA
PRODUKSI PER HARI 27.832 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.036 HARI
- TUKANG 0.036 HARI
- PEKERJA 0.144 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
LIST PLAFOND GYPSUM
TENAGA
PRODUKSI PER HARI 70.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.014 HARI
- TUKANG 0.014 HARI
- PEKERJA 0.029 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN DINDING LUAR
TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN DINDING DALAM
TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN PLAFOND GYPSUM
TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN LIST PLAFOND GYPSUM
TENAGA
PRODUKSI PER HARI 127.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.008 HARI
- TUKANG 0.008 HARI
- PEKERJA 0.016 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN KOLOM
TENAGA
PRODUKSI PER HARI 26.900 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.037 HARI
- TUKANG 0.037 HARI
- PEKERJA 0.074 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBUATAN KUSEN ALUMINIUM 4"
TENAGA
PRODUKSI PER HARI 52.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.019 HARI
- TUKANG 0.019 HARI
- PEKERJA 0.038 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBUATAN PINTU ALUMINIUM (2 DAUN)
TENAGA
PRODUKSI PER HARI 4.000 UNIT
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.250 HARI
- TUKANG 0.250 HARI
- PEKERJA 0.500 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN KACA TEBAL 5 MM
TENAGA
PRODUKSI PER HARI 32.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 1.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.031 HARI
- TUKANG 0.063 HARI
- PEKERJA 0.031 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBUATAN PINTU ALUMINIUM
TENAGA
PRODUKSI PER HARI 4.000 UNIT
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.250 HARI
- TUKANG 0.250 HARI
- PEKERJA 0.500 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN ENGSEL JUNGKIT
TENAGA
PRODUKSI PER HARI 50.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.020 HARI
- TUKANG 0.020 HARI
- PEKERJA 0.040 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GRANDEL JENDELA
TENAGA
PRODUKSI PER HARI 35.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.029 HARI
- TUKANG 0.029 HARI
- PEKERJA 0.057 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RAILLING TANGGA
TENAGA
PRODUKSI PER HARI 60.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.017 HARI
- TUKANG 0.017 HARI
- PEKERJA 0.050 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
KACA CERMIN TEBAL 5 MM 200 CM x 100 CM
TENAGA
PRODUKSI PER HARI 140.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.007 HARI
- TUKANG 0.007 HARI
- PEKERJA 0.014 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PASANG LAMPU RM 2 x 18 WATT
TENAGA
PRODUKSI PER HARI 20.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.100 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI TITIK LAMPU
ALAT
ALAT BANTU 1.000 Ls
- OBENG
- TANG
- DLL
TENAGA
PRODUKSI PER HARI 15.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
SAKLAR SERIE
TENAGA
PRODUKSI PER HARI 45.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.022 HARI
- TUKANG 0.022 HARI
- PEKERJA 0.044 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PASANG LAMPU RM 3 x 36 WATT
TENAGA
PRODUKSI PER HARI 30.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.033 HARI
- TUKANG 0.033 HARI
- PEKERJA 0.100 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
STOP KONTAK DINIDNG, 1 PH, 10 A
TENAGA
PRODUKSI PER HARI 45.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.022 HARI
- TUKANG 0.022 HARI
- PEKERJA 0.044 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
STOP KONTAK AC
TENAGA
PRODUKSI PER HARI 45.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.022 HARI
- TUKANG 0.022 HARI
- PEKERJA 0.044 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI STOP KONTAK
ALAT
ALAT BANTU 1.000 Ls
- OBENG
- TANG
- DLL
TENAGA
PRODUKSI PER HARI 15.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
MCB - 1 PH (10 A) 10 KA
TENAGA
PRODUKSI PER HARI 20.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.100 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
MCB - 3 PH (50 A) 10 KA
TENAGA
PRODUKSI PER HARI 5.000 BUAH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.200 HARI
- TUKANG 0.200 HARI
- PEKERJA 0.400 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI PIPA SPLINKER
TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN SPLINKER
TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
INSTALASI SMOKE DETECTOR
TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMASANGAN SMOKE DETECTOR
TENAGA
PRODUKSI PER HARI 10.000 TITIK
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.300 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GRILL DI LAPISI BESI PLAT BORDES
TENAGA
PRODUKSI PER HARI 15.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RAILING PAGAR
TENAGA
PRODUKSI PER HARI 20.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.200 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
COR BETON TEBAL 12 CM (K-175)
CONCRETE VIBRATOR
KEBUTUHAN ALAT PENGGETAR BETON INI DISESUAIKAN
DENGAN KAPASITAS PRODUKSI ALAT PENCAMPUR
(CONCRETE MIXER )
KAP. PROD/JAM = Q2 Q1
Jam Jam
TENAGA
PRODUKSI PER HARI 7.200 M3
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 8.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.139 HARI
- TUKANG 0.278 HARI
- PEKERJA 1.111 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN KANOPI
TENAGA
PRODUKSI PER HARI 20.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 3.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.150 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN KANSTEEN
TENAGA
PRODUKSI PER HARI 25.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.160 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENGECATAN KANSTEEN
TENAGA
PRODUKSI PER HARI 25.400 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.039 HARI
- TUKANG 0.039 HARI
- PEKERJA 0.079 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
GEMBALAN RUMPUT
TENAGA
PRODUKSI PER HARI 30.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.033 HARI
- PEKERJA 0.067 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PENUTUP ATAP
TENAGA
PRODUKSI PER HARI 30.010 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 2.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.033 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN RANGKA PARTISI
TENAGA
PRODUKSI PER HARI 13.885 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.072 HARI
- TUKANG 0.072 HARI
- PEKERJA 0.288 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN PASANG PAPAN GYPSUM 2 MUKA
TENAGA
PRODUKSI PER HARI 20.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.050 HARI
- TUKANG 0.050 HARI
- PEKERJA 0.200 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN KUSEN ALUMINIUM DAUN PINTU PANEL LAPIS HPL
ALAT
ALAT BANTU 1.000 Ls
- GERGAJI BESI
- MESIN PEMOTONG
- DLL
TENAGA
PRODUKSI PER HARI 2.000 BH
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.500 HARI
- TUKANG 0.500 HARI
- PEKERJA 1.000 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEKERJAAN LIST PLAN LANTAI 10 CM
TENAGA
PRODUKSI PER HARI 15.000 M'
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.067 HARI
- TUKANG 0.067 HARI
- PEKERJA 0.133 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
PEMBESIAN
TENAGA
PRODUKSI PER HARI 350.000 KG
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 2.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.003 HARI
- TUKANG 0.003 HARI
- PEKERJA 0.006 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
BEKISTING
TENAGA
PRODUKSI PER HARI 10.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.100 HARI
- TUKANG 0.100 HARI
- PEKERJA 0.400 HARI
ANALISA TEKNIK
ITEM PEKERJAAN
RANGKA ATAP BAJA RINGAN 5 CM
TENAGA
PRODUKSI PER HARI 25.000 M2
KEBUTUHAN TENAGA :
- MANDOR 1.000 ORG
- TUKANG 1.000 ORG
- PEKERJA 4.000 ORG
KOEFESIEN TENAGA / M2 :
- MANDOR 0.040 HARI
- TUKANG 0.040 HARI
- PEKERJA 0.160 HARI
ANALISA HARGA ALAT
PxB Asuransi
b. Asuransi, dll. = F Rp/Jam 1,300.00 1,650.00 300.00 13.50 10.00 4.67 1,430.00 1,270.00 350.00
W p =0,2%
Biaya Pasti per J G = (E + F) G Rp/Jam 155,621.53 197,519.63 35,912.66 1,929.99 1,429.62 667.16 171,183.68 152,030.26 41,898.10
6 Pembantu operator = (n orang/jam) x U2 L Rp/Jam 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43 18,571.43
Biaya Operasi (per Jam) = P Rp/Jam 484,835.00 506,250.00 298,250.00 73,384.38 49,582.50 49,015.83 522,087.50 349,597.50 303,875.00
D. BIAYA OPERASI ALAT / JAM = (G + P) S Rp/Jam 640,456.53 703,769.63 334,162.66 75,314.36 51,012.12 49,682.99 693,271.18 501,627.76 345,773.10
E. LAIN - LAIN
1 Bahan Bakar Premium (non subsidi) Mb Liter 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00 10,500.00
2 Bahan Bakar Solar (non subsidi) Ms Liter 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00 11,500.00
3 Minyak Pelumas Mp Liter 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00
F. BIAYA PERALATAN PER JAM (DIBULATKAN) Rp/Jam 640,400.00 703,700.00 334,100.00 75,300.00 51,000.00 49,600.00 693,200.00 501,600.00 345,700.00