TSI-374 PERENCANAAN
BIAYA DAN JADWAL PROYEK
A 2 10
B 2 10
C 3 15
D 4 20
E 7 35
F 4 10
3. DISTRIBUSI BOBOT
PEKERJAAN
KE DU Bo Durasi
G R bot 1 2 3 4 5 6 7 8 9 10
(%)
A 2 10 5 5
B 2 10 5 5
C 3 15 5 5 5
D 4 20 5 5 5 5
E 7 35 5 5 5 5 5 5 5
A 2 10 5 5
B 2 10 5 5
C 3 15 5 5 5
D 4 20 5 5 5 5
E 7 35 5 5 5 5 5 5 5
A 2 10 5 5
B 2 10 5 5
C 3 15 5 5 5
D 4 20 5 5 5 5
E 7 35 5 5 5 5 5 5 5
Bobot 10 20 35 50 65 75 83 90 98 100
Kumulatif
6. PLOT KURVA S
KE DU Bo Durasi
G R bot 1 2 3 4 5 6 7 8 9 10
(%)
100%
A 2 10 5 5
B 2 10 5 5
C 3 15 5 5 5 50%
D 4 20 5 5 5 5
E 7 35 5 5 5 5 5 5 5
Bobot 10 20 35 50 65 75 83 90 98 100
Kumulatif
KURVA S RENCANA
KURVA S
PELAKSANAAN
1.PENGECEKAN VOLUME
PEKERJAAN
KEG DUR Bob Volu Satu Realisasi
ot me an 1 2
(%)
A 2 10 20 M3 8 5
B 2 10 200 M2 100 40
C 3 15
D 4 20
E 7 35
F 4 10
2. PROGRES PEKERJAAN
(%)
KEG DUR Bob Volu Satu Realisasi
ot me an =
1 2
(%) (8/20)*100%
A 2 10 20 M3 40 25
B 2 10 200 M2 50 20
C 3 15
D 4 20
E 7 35
F 4 10
2. BOBOT REALISASI
(%)
KEG DUR Bob Volu Satu Realisasi
ot me an = 40% * 10%
1 2
(%)
A 2 10 20 M3 4 2,5
B 2 10 200 M2 5 2
C 3 15
D 4 20
E 7 35
F 4 10
Bobot realisasi 9 4,5
Bobot kumulatif 9 13,5
3. PLOT REALISASI
KE DU Bo Durasi
G R bot 1 2 3 4 5 6 7 8 9 10
(%)
100%
A 2 10 5 5
B 2 10 5 5
C 3 15 5 5 5 50%
D 4 20 5 5 5 5
E 7 35 5 5 5 5 5 5 5
Bobot 10 20 35 50 65 75 83 90 98 100
Kumulatif
Bobot 9 4,5
Realisasi