Soal
Soal Nomer 1

Buatlah dua simulasi perhitungan EOQ


- ketika 100% bahan baku yang digunakan kayu log
- ketika 100% bahan baku yang digunakan kayu papan
Carilah data rendemen produksi furniture diatas?
Soal Nomer 2
Diketahui :

Lead Time : 1 Bulan Batas


Toleransi eror : 5%
Ditanya :
a. Buatlah 2 simulasi perhitungan Q opt?
b. SS? Reoder Point?
c. Maximum Inventory?
d. Total Cost?
e. Buatlah grafik
Soal Nomer 3
Diketahui:

Evaluasilah kedua simulasi perhitungan EOQ tersebut? Kesimpulannya


bagaimana?
Kondisi PT. X

Harga bahan baku = Sama soal


Biaya pemesanan: Biaya telepon dan administrasi sama.
Rate pengiriman = 1 Teus (1Truck) = 11.000.000
2 Teus (1 Truck) = 15.000.000
Biaya penyimpanan = Sama soal
jawaban
Jawaban Nomer 1
 •
Rendeman proses sawn timber =

=
= 0,77
= 77%

• Rendeman proses papan ke furnitur =

=
= 0,42
= 42%
 •
Rendeman proses log ke furnitur =

=
= 0,29
= 29%
Jawaban Nomer 2

Log Papan

Qopt D 125,0287 125,0287

S Rp 938.394 Rp 888.394

H Rp 2.019.450 Rp 3.019.450
Q opt untuk 2 simulasi perhitungan
 
 Q opt Log = =
= 19,993 unit

 Q opt Papan = =
= 16,181 unit
Safety Stock
Pengeluaran (m3) (Pengeluaran
Pcs Vol (m3)   1/11 Rata-rata)^2 ((1) x (2))^2 ((30) x (3))^2)^0,5
1182   (1) (2) (3)  
15,4553
10,41905833 0,091 25,364      
1396 19,5141
944     82,720      
19,7253
    86,606      
1105 13,864
    11,868      
331 3,939
    41,991      
775 9,5743     0,714      
382 5,4551     24,641      
96 1,2671     83,758      
476 8,4     4,077      
724 9,2126     1,456      
855 9,6499     0,592      
577 8,972     2,094      
Total 125,0287 Total   363.785 Safety Stock
Rata -rata 10,41905833 5,75 31,49 51,65
Reorder Point
• ● Kayu
  Log
dL = (/365) x 30 • Kayu Papan
= 33,35 dL = (297,568306/365) x 30
Safety Stock = 1,64 x 31,589 = 24,46
= 51,81 Safety Stock = 1,64 x 31,589
R = 33,35 + 51,81 = 87,15620 = 51,81
R = 24,46 + 51,81 = 76,26329
Maximum Inventory
Maximum Inventory = Safety Stock + EOQ

• Kayu Log
Safety Stock = 51,6572
EOQ = 19,993
Maximum Inventory = 51,6572 + 19,993 = 71,6502

• Kayu Papan
Safety Stock = 51,6572
EOQ = 16,181
Maximum Inventory = 51,6572 + 16,181 = 67,8382
Total Cost

Rumus Kayu Log Kayu Papan


DC Rp 2.054.611.731 Rp 3.124.467.213
D/Q*S Rp 20.187.300 Rp 16.337.955
Q/2H Rp 20.187.300,361 Rp 16.337.955,141
Total Rp 2.094.986.331 Rp 3.157.143.123
Grafik
40000000 1900000000

35000000 1800000000

1700000000
30000000
1600000000
25000000
1500000000
20000000
1400000000
15000000
1300000000
10000000
1200000000
5000000 1100000000

0 1000000000
5 10 15 20 25 30 35
Jawaban Nomer 3
Diketahui :

O 445,85 LOG 322,7387 PAPAN


C Rp 4.777.070 LOG Rp 10.500.000 PAPAN
OC Rp 488.394 Log Rp 500.000
Papan Rp 450.000

R Log 20 " (3) Rp 11.000.000 Papan 20 " (4) Rp 11.000.000


Rp 15.000.000
40"(7) Rp 15.000.000 40"(5)
SC Rp 2.019.450 Rp 2.019.450
TC Kayu Log Kayu Papan
 

OxC Rp 2.129.856.660 Rp 3.388.756.350  

OC x R Rp 138.500.000 Rp 119.450.000 Rp 138.000.000

SC x O Rp 900.371.783 Rp 651.754.668  

 Total Rp 3.168.728.442 Rp 4.159.961.018  


 Perbandingan antara Soal nomer 2 dan 3
• Kayu Log
= Total cost kayu log pada soal no 3 – Total cost kayu log pada soal no 2
=
= Rp 1.073.742.111

Persentase = = 34%

• Kayu Papan
= Total cost kayu papan pada soal no 3– Total cost kayu papan pada soal no 2
= Rp 4.159.961.018 - Rp 3.157.143.123
= Rp 1.002.817.895

Persentase = = 24%
Thank you