Anda di halaman 1dari 1

FORMULIR STANDAR UNTUK

PEREKAMAN ANALISA MASING-MASING HARGA SATUAN



PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA : SUMATERA BARAT / KOTA PARIAMAN
ITEM PEMBAYARAN NO. : AGREGAT KELAS A (kondisi lepas) :
JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS A :
SATUAN PEMBAYARAN : M3 :
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) jam 0.0630 8,751.43 551.31
2. Mandor (L03) jam 0.0315 10,210.00 321.60
872.91
B. BAHAN
1. Agregat 20-30 M93 M3 0.2940 210,000.00 61,740.00
2. Agregat 5-10 & 10-20 M92 M3 0.4410 235,000.00 103,635.00
3 Pasir Urug M44 M3 0.3150 76,500.00 24,097.50
189,472.50
C. PERALATAN
1. Wheel Loader (E15) jam 0.0315 306,001.57 9,638.60
2. Blending Equpment (E52) jam 0.0482 182,164.66 8,779.02
3 Alat Bantu Ls 1.0000 0.00 0.00
18,417.62
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 208,763.04
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN