Laporan Tugas Gambar Construction Sofia Triana Sari
Laporan Tugas Gambar Construction Sofia Triana Sari
Disusun ole
h :
PROGRAM STU
DI
TEKNIK PERENCANAAN DAN KONSTRUKS
I KAPALJURUSAN TEKNIK BANGUNAN KA
PAL
POLITEKNIK NEGERI MADURA
SURABAYA
2014
Lembar Pengesahan
Laporan Tugas Gambar
KONSTRUKSI KAPAL (STEEL PLAN)
Menyetujui, Dosen
Pembimbing
Dosen Pembimbing I
Dosen Pembimbing II
TRI KARYONO,ST.,MT.
NIP.
Mahasiswa:
DAFTAR I
SI
Halaman Sampul .....................................................
.............................1
Halaman Pengesahan ...............................................
.............................2
Daftar Isi .............................................................
................................3
1. L Konstruksi .......................................................
............................10
2. Perhitungan Perencanaan Beban ...............................
........................10
2.1. Beban Pada Geladak Cuaca ...................................
.....................12
2.2. Beban Pada Sisi Kapal ........................................
......................12
2 . 2 . 1 . U n t u k D a e r a h A (B u r i t a n ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..................12
2.2.1.1. Beban Dibawah Garis Air ....................
................13
2.2.1.2. Beban Diatas Garis Air .......................
................13
2 . 2 . 2 . U n t u k D a e r a h M (M i d d l e ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..................13
2.2.2.1. Beban Dibawah Garis Air ....................
................14
2.2.2.2. Beban Diatas Garis Air .......................
................14
2 . 2 . 3 . U n t u k D a e r a h F (H a l u a n ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..................14
2.2.3.1. Beban Dibawah Garis Air ....................
................14
2.2.3.2. Beban Diatas Garis Air .......................
................15
2.3. Beban Pada Sisi Bangunan Atas Kapal ......................
..................15
2.3.1. Main Deck ...............................................
.......................15
2.3.2. Poop Deck ...............................................
.......................15
2.3.3. Boat Deck ................................................
.......................16
2.3.4. Bridge Deck .............................................
.......................16
2.3.5. Navigation Deck ........................................
.....................16
2.3.6. Forecastle Deck ........................................
......................16
2.4. Beban Pada Struktur Depan Kapal ..........................
....................17
2.5. Beban Pada Dasar Kapal ......................................
.....................17
2.6. Beban Pada Geladak Bangunan Atas & Rumah Geladak ..
.............17
2.6.1. Beban Pada Poop Deck .................................
...................17
2.6.2. Beban Pada Boat Deck .................................
....................18
2.6.3. Beban Pada Bridge Deck ...............................
...................18
2.6.4. Beban Pada Navigation Deck .........................
...................18
2.6.5. Beban Pada Top Deck ...................................
...................18
STEEL PLAN
33311201020
2.7. Beban Pada Forecastle Deck .................................
.....................19
2.8. Beban Beban Pada Plat Alas Dalam .........................
...................19
2 . 8 . 1 . P a d a D a e r a h A (0 < x / L < 0 , 2 ) . . . . . . . . . . . . . . . . . . . . . . . . . .
................19
2 . 8 . 2 . P a d a D a e r a h M (0 , 2 < x / L < 0 , 7 ) . . . . . . . . . . . . . . . . . . . . . . .
...............19
2 . 8 . 3 . P a d a D a e r a h F (0 , 7 < x / L < 1 ) . . . . . . . . . . . . . . . . . . . . . . . . . .
................19
2.9. Beban Pada Geladak ..........................................
.......................20
2.9.1. Beban Pada Geladak Akomodasi ......................
.................20
2.9.2. Beban Pada Geladak Mesin ............................
..................20
2.9.3. Beban Pada Geladak Second Deck Mesin ............
...............20
3. Perhitungan Tebal Plat ............................................
........................20
3.1. Tebal Plat Dasar ...............................................
........................20
3.1.1. Pada Daerah 0,14 L Amidship .........................
.................20
3.1.2. Pada Daerah 0,1 L dari AP dan 0,5 L dari FP .........
............21
3 . 1 . 2 . 1 . H a l u a n (F P ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
.............. .....21
3 . 1 . 2 . 2 . B u r i t a n (A P ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
...................21
3.2. Lebar dan Tebal Plat Bilga ...................................
.....................21
3 . 2 . 1 . D a e r a h A (B u r i t a n ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
.....................21
3 . 2 . 2 . D a e r a h M (M i d d l e ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
....................21
3 . 2 . 3 . D a e r a h F (H a l u a n ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
.....................22
3.3. Tebal dan Lebar Plat Lunas ..................................
.....................22
Design Construction A 09
Surabaya Shipbuilding State Of
Polythecnic
STEEL PLAN
33311201020
4.6.1. Tebal Wrang Kedap ...................................
......................36
4.6.2. Modulus Penegar Wrang Kedap .....................
...................37
4.7. Konstruksi Pada Haluan & Buritan Adalah Single Botto
m ............38
4.7.1. Tebal Wrang Plat .....................................
.......................38
4.7.2. Tinggi Wrang Plat Pada Haluan .....................
...................38
4.8. Center Girder ..................................................
.........................38
4.8.1. Pada Daerah 0,7 L Amidship .........................
...................38
4.8.2. Pada Ujung Ujung Kapal ...........................
....................38
4.9. Sectional Area Plat ...........................................
........................38
4.10. Side Girder ...................................................
.........................39
4.11. Sea Chest ......................................................
.........................39
4.12. Modulus Penegar Sea Chest ................................
.....................39
4.13. Pada Kamar Mesin ...........................................
.......................39
4.13.1. Modulus Wrang Plat ...............................
.....................39
4.13.2. Tinggi Wrang Plat .................................
......................39
4.13.3. Tebal Web Wrang Plat .............................
....................39
4.13.4. Center Girder Pada Ruang Mesin Induk .........
................40
4.13.5. Luas Area Dok Intercostal ........................
....................40
4.13.6. Luas Area Top Plate ...............................
.....................40
4.13.7. Rencana Penempatan Mesin ......................
....................40
Design Construction A 14
Surabaya Shipbuilding State Of
Polythecnic
Design Construction A 09
Surabaya Shipbuilding State Of
Polythecnic
1
0
STEEL PLAN
33311201020
DAFTAR GAMB
AR
Gambar 1. Tebal Plat Dasar ........................................
.........................20
G a m b a r 2 . L e b a r & T e b a l P l a t B i l g a D a e r a h S t e r n (A ) . . . . . . . . . .
.................21
G a m b a r 3 . L e b a r & T e b a l P l a t B i l g a D a e r a h M i d d l e (M ) . . . . . . . .
................22
G a m b a r 4 . L e b a r & T e b a l P l a t B i l g a D a e r a h F o r e (F ) . . . . . . . . . . . .
........... ......22
Gambar 5. Tebal Plat Lunas Amidship ............................
......................22
Gambar 6. Tebal Plat Lunas AP dan FP ............................
....................23
Gambar 7. Tebal Plat Sisi Daerah M ...............................
......................23
Gambar 8. Tebal Plat Sisi Daerah FP ..............................
......................24
Gambar 9. Tebal Plat Sisi Daerah AP .............................
......................25
Gambar 10. Tebal Plat Geladak Daerah Amidship ...............
...................25
Gambar 11. Tebal Plat Geladak Daerah AP .......................
....................26
Gambar 12. Tebal Plat Geladak Daerah FP ........................
....................26
Gambar 13. Tebal dan Lebar Plat Sheerstrike Pada Amidship .
................27
Gambar 14. Tebal dan Lebar Plat Sheerstrike Pada AP ..........
.................27
Gambar 15. Tebal dan Lebar Plat Sheerstrike Pada FP ..........
.................28
Gambar 16. Tebal Plat Sisi Main Deck ............................
.....................28
Gambar 17. Tebal Plat Sisi Poop Deck ............................
.....................29
Gambar 18. Tebal Plat Sisi Boat, Bridge & Navigation Deck ..
................30
Gambar 19. Tebal Plat Geladak Poop Deck .......................
Design Construction A 14
Surabaya Shipbuilding State Of
Polythecnic
1
1
....................30
Gambar 20. Tebal Plat Geladak Boat Deck ........................
....................31
Gambar 21. Tebal Plat Geladak Bridge, Navigation & Top Dec
k .............31
Gambar 22. Tebal Plat Inner Bottom ..............................
......................32
Gambar 23. Tebal Plat Geladak Second Deck Kamar Mesin ....
................32
Gambar 24. Tebal Plat Sisi Untuk Forecastle ....................
....................33
Gambar 25. Tinggi Dasar Ganda ...................................
.......................33
Gambar 26. Tebal Center Girder 0,7 L Tengah Kapal ............
.................34
Gambar 27. Tebal Side Girder .....................................
........................34
Gambar 28. Tebal Wrang Plat ......................................
........................35
Gambar 29. Profile Pembujur Alas ................................
.......................36
Gambar 30. Profile Penegar Wrang Kedap .......................
.....................37
Gambar 31. Tebal Center Girder Amidship ......................
.....................38
Design Construction A 09
Surabaya Shipbuilding State Of
Polythecnic
1
4
STEEL PLAN
33311201020
Lpp
: 96,80
Lwl
: 100,672 m
: 14,40
: 7,20
: 6,29
Cb
: 0,77
Vs
: 12
Lkonst
: 96.645 m
T yp e K a p a l
: OIL TANKER
Nama Kapal
: KM. SURAWIJAYA
Konstuksi
: Memanjang
knots
1. L KONSTRUKSI
Jarak pada garis musim panas dari depan linggi buritan (garis sumbu tongkat kemudi),
jika tidak ada linggi kemudi L tidak boleh kurang dari 96% LWL L 97% LWL
L
Konstruksi (Lc) :
96% LwL =
96.645m
L Konstruksi (Lc) : 97% LwL = 90.792m
Lc diambil 90.792 m
Co =
= 7.707
CL = 1
1
5
Range
A
Factor cD
Factor cF
1.2 - x/L
1.041
1.272
0.16*Lpp
14.4
x/L =
0.159
0.2 < x/L < 0.7
M
0.5*Lpp
46.08
x/L =
0.7 < x/L
< 1,0
x
F
1.000
0.508
1+ 20/Cb*[x/L - 0.7]2
0.9*Lpp
81.207
Lmin = 100 m
0.902
diambil L = 100 m
x/L =
1.000
= 0.15*L - 10
2.077
maka c = 0.15 L - 10
c=
3.5
Shg cD =
A pada frame
M pada frame
24.000
:
167
:
F pada frame
179
Design Construction A 09
Surabaya Shipbuilding State Of
Polythecnic
1.236
16.2 m
84 m
6.8 m
1
6
STEEL PLAN
33311201020
2.1. BEBAN PADA GELADAK CUACA / WEATHER DECK
Diman
a:
B pada bagian A
17.29 m
B pada bagian M
18.4
B pada bagian F
10.77 m
Sehingga,
(1/3 camber)
(1/3 camber)
(1/3 camber)
lebar
1500 mm
lebar
1500 mm
lebar
1500 mm
lebar
1500 mm
lebar
Z1 = 1,600 m
Z4 = 4,412 m
Z2 = 2,160 m
Z5 = 5,537 m
Z3 = 3,280 m
Z6 = 6,629 m
Design Construction A 14
Surabaya Shipbuilding State Of
Polythecnic
1
7
lebar
1500 mm
Plat 2
lebar
1500 mm
Plat 3
lebar
1500 mm
Plat 4
lebar
1500 mm
Plat 5
lebar
Z1 = 1,600 m
Z4 = 4,412 m
Z2 = 2,160 m
Z5 = 5,537 m
Z3 = 3,280 m
Z6 = 6,629 m
Design Construction A 09
Surabaya Shipbuilding State Of
Polythecnic
1
8
STEEL PLAN
33311201020
2.2.2.1. BEBAN DI BAWAH GARIS AIR
Ps1M = 10 (T - Z1) + Po * CFM (1 + Z1/T)
= 10 ( 5 1,6 ) + 17,97 * 1 ( 1 + 1,6/5 )
= 57,723 kN/m
Ps2M = 10 (T Z2) + Po * CFM (1 + Z2/T)
= 10 ( 5 2,16 ) + 17,97 * 1 ( 1 + 2,16/5 )
= 54,136 kN/m
Ps3M = 10 (T Z3) + Po * CFM (1 + Z3/T)
= 10 ( 5 3,28 ) + 17,97 * 1 ( 1 + 3,28/5 )
= 46,962 kN/m
2.2.2.2. BEBAN DI ATAS GARIS AIR
Ps4M = Po * CFM * { 20 / (10 + Z5 T) } = 17,97 * 1 { 20 / (10 + 5,537 5) }
= 35,356 kN/m
Ps5M = Po * CFM * { 20 / (10 + Z6 T) } = 17,97 * 1 { 20 / (10 + 6,629 5) }
= 36,481 kN/m
2.2.3. UNTUK DAERAH F (HALUAN)
Diambil pada frame no.104, rencana lebar plat dengan tinggi plat bilga = 1000 mm
Pl
at
Pl
at
2
Pl
at
4
Z1
=
Z2
=
Z3
=
lebar
1500 mm
lebar
1500 mm
lebar
1500 mm
lebar
1500 mm
lebar
Z4
=
Z5
=
Z1 = 6,700 m
Z1 = 9,100 m
Z1 = 11,500 m
Z1 = 13,900 m
Z1 = 16,300 m
Z1 = 6,700 m
(kN/m)
n = 1- {( z H) / 10 }
n min = 0,5
n
= 1 (untuk forecastle)
Plat 1 = 1400 mm
Plat 2 = 1000 mm (100 mm untuk las)
Maka, Z = 9 + 2,4
n = 1 {(11,4 9) / 10 }
= 11,400 m
= 0,760 m
Plat 1 = 1400 mm
Plat 2 = 1000 mm (100 mm untuk las)
= 13,800 m
= 0,520 m
Plat 1 = 1400 mm
Plat 2 = 1000 mm (100 mm untuk las)
= 16,200 m
= 0,280 m
Plat 1 = 1500 mm
Plat 2 = 1000 mm (100 mm untuk las)
= 0,040 m
= 1,360 kN/m
Plat 1 = 1500 mm
Plat 2 = 1000 mm (100 mm untuk las)
= 21,000 m
= - 0,200 m
= 1,000
(mm)
tk
ao = 0,6 m
PBM = 67,972 kN/m
tBM = 1,9 * 1 * 0,6 * 67,972 * 0,91 + 1,5 = 10,053 mm ~ 11 mm
3.1.2. Tebal plat dasar pada daerah 0,1 L dari AP dan 0,05 L dari FP, tidak boleh
kurang dari :
3.1.2.1. Haluan ( F )
tBF = 1,21 * ao * PBF * k + tk (mm)
dimana :
= 8 mm
= 9 mm
= 9 mm
C
Gambar 2. Lebar dan Tebal Plat Bilga Daerah Stern (A)
= 10 mm
= 11 mm
= 11 mm
= 8 mm
= 8 mm
= 8 mm
C
Gambar 4. Lebar dan Tebal Plat Bilga Daerah Fore (F)
(mm)
= 11 + 2 = 13 mm
CL
CL
Gambar 6. Tebal Plat Lunas AP dan FP
Design Construction A 14
Surabaya Shipbuilding State Of
Polythecnic
2
4
STEEL PLAN
33311201020
3.4.2. Daerah 0,8 L dari FP (haluan)
ts1 = 1,21 * nf * ao * PSF1 * k + tk
C
L
Gambar 8. Tebal Plat Sisi daerah FP
2
5
= 7,106 mm ~ 8 mm
C
Gambar 9. Tebal Plat Sisi daerah AP
= 7,803 ~ 8 mm
= 6,885 ~ 7 mm
= 6,885 ~ 7 mm
= 6,885 ~ 7 mm
C
Gambar 12. Tebal Plat Geladak Pada Daerah FP
CL
Gambar 15. Tebal & Lebar Sheerstrike Pada FP
P OOP DEC K
C H IEF C O O
KROOM
MAI N DE CK
Gambar 16. Tebal Plat Sisi Main Deck
B OAT DE CK
ELEC TR IC
IAN R O O
M
P OOP DE CK
Pada poop deck tebal (ta) sudah lebih kecil dari (tD) (6 mm < 7 mm) maka hal yang
sama juga akan terjadi pada plat plat sisi yang berada diatasnya karena beban sisi
makin keatas akan makin kecil dan dengan sendirinya tebal plat sisinya juga akan
makin kecil. t1 = 7 mm
Karena selalu dipilih yang terbesar maka tebal plat sisi pada bridge, boat dan nav. deck
akan selalu sama yaitu = tb = 7 mm baik pada plat 1 maupun pada plat 2. t2 = 7 mm.
T OP DE CK
CHAR
TROO
M
WHEE
LHOU
SE
RAD
IO R O
OM
NA V. D ECK
C A P TA IN
GANG WAY
ROOM
B RI D GE DE CK
D O C TE R
GANG WAY
ROOM
BOA T D ECK
CL
Gambar 18. Tebal Plat Sisi Boat, Bridge dan Navogation Deck
tD = 6 mm
E LE C T R IC IA N
CL
= 5,980 ~ 6 mm
DE C
P O OP
K
= 5,980 ~ 6 mm
tD = 6 mm
Design Construction A 14
Surabaya Shipbuilding State Of
Polythecnic
3
1
B OAT
K
DE C
D O C TER
G AN G W AY
CL
ROO
M
T OP DE CK
C H AR
TROO
M
NA V. D E CK
G AN G W AY
W H EEL H O U SE
R AD
IO R
OO
M
C
APTAIN
ROOM
BRI D GE DE C K
C
Gambar 21. Tebal Plat Geladak Bridge, Navigation dan Top Deck
= 6,544 ~ 7 mm
atau
t = 1,1 * a * PL * k + tk = 1,1 * 0,6 * 38,455 * 0,91 + 1,5 = 5,404 ~ 6 mm
maka dipilih t = 7 mm
C
Gambar 23. Tebal Plat Geladak Second Deck Kamar Mesin
C
Gambar 24. Tebal Plat Sisi Untuk Forecastle
4.
Dalam satu bagian double bottom satu side girder dipasang bila jarak antara sisi
kapal dan penumpu tengah > 4,5 m
Dua side girder dipasang bila jarak antara sisi kapal dan center girder > 8 m
Diketahui jarak antara center girder dan sisi kapal = B/2 = 11/2 = 5,50 m jadi
direncanakan dipasang satu side girder disetiap sisi dari double bottom.
hDB = 1000 mm
(cm)
e = 4 * ao = 4 * 0,6 = 2,4 m
l = B = 11 m
y = 0,4 * l = 0,4 * 11 = 4,4 m
= 0,3 (untuk ruang muat)
Lebar keseluruhan tidak boleh lebih dari setengah lebar wrang alas penuh
Tinggi lubang peringan tidak boleh lebih dari setengah tinggi wrang alas penuh
m = k * n = 1 * 0,7 = 0,7
l = 4 * ao = 4 * 0,6 = 2,4 m
p = PBM = 67,972 kN/m
m = k * n = 1 * 0,55 = 0,55
l = 4 * ao = 4 * 0,6 = 2,4 m
p = PIM = 59,927 kN/m
atau
t2 = 0,9 * a * p2 * k + tk
h2 = jarak pusat beban dari titik 2,5 m di atas tank top atau
ke pipa limpah diambil pada plat 1 (yang terbesar)
pusat beban = 1/3 hDB = 1/3 * 1 = 0,33 m
h2 = >> (hDB + 2,5) 0,33 = 3,17 m
>> (H + 1) 0,33 = 8,17 m
Jadi diambil h2 =8,17 m
h2 = 9,81 * 8,17 = 80,1477 kN/m
atau
W2 = 0,44 * a * l * P2 * k
l = hDB = 1 m
CL
4.8.2. Tebal center girder pada ujung ujung kapal, boleh dikurangi 10 %
t = 11 [10/100 * 11] = 9,9 ~ 10 mm
t = 10 mm
C
L
Gambar 32. Tebal Center Girder Pada Ujung Ujung Kapal
a = jarak penegar = 0,6 m (dlm hal ini penegar pada ruang mesin dipasang
Tiap jarak gading = 0,6 m)
P = blow out pressure = 2 bar
l = hDB = 1 m
dimana :
= 1720/750 + 70
= 72,29 cm
4.13.7. RENCANA PENEMPATAN MESIN
-
Diameter propeller
: 225 mm
: 1750 mm
: 1500 mm
: 850 mm
CL
Gambar 33. Konstruksi Kedudukan Mesin Kapal
5.
G
A
N
G
W
A
Y
Q U AR
TER M
ASTER R
OOM
G AN
GW
AY
O FFIC
EROO
M
G AN
GW
AY
R AD IO
O PERATO
RROOM
G ANG
W AY
ESEP RO O M
W
HEEL
H
O U SE
C
Gambar 40. Gading Utama Pada First Deck Kamar Mesin
a = 0,6
c = cmin = 0,65
f = fmin = 0,75
l = 3,25 m
Ps1A = 74,198 kN/m
n=1
e = 5 * a = 5 * 0,6 = 3,0
l = 3,5 m
Ps1A = 74,198 kN/m
C
Gambar 42. Gading Besar Pada First Deck Kamar Mesin
MAI N DE CK
CL
Gambar 43. Gading Besar Pada Second Deck Kamar Mesin
dimana
k = 0,09
ln direncanakan = 5,4 m
Sn = lebar palka = 3,5 m
gn direncanakan = 0,65 m
un = jarak cantilever = 4,5 m
hDN = 1,42
ZNN = 0,09 * 350 * (3,5 + 5,4 + 0,65) * 4,5 * 1,42 * 5,4 = 11406,89 cm
0,91
Perhitungan Profil T
l/e = 6,19/3 = 1,38
dengan interpolasi didapat em1 = 0,53 x 4,5 = 2,385 m = 238,5 cm
plat ikut = plat geladak dgn tebal maksimun = 8 mm = 0,8 cm
F = 238,5 x 0,9 = 214,65 cm
Direncanakan :
h = 70 cm
tebal plat di fs = 3 cm
tebal plat di f = 2,5 cm
k = 0,91
e = 5 * ao = 5 * 0,6 = 3,0 m
l = 2,4 m
Ps = PS1F = 43,195 kN/m
6.
l = 4 * a = 4 * 0,6 = 2,4 m
p = PDF = 24,709 kN/m
p = PDM = 30,905 kN/m
m = k * n = 0,91 * 0,75 = 0,6825
c = 0,75
a = 0,6 m
k = 0,91
C
Gambar 46. Balok Geladak Daerah A
BO Y R O O M
G AN G W AY
C
Gambar 47. Balok Geladak Untuk Main Deck
Q U AR
TER M
ASTER R
OOM
G AN G W
AY
O FFIC
EROO
M
G AN G W
AY
R AD IO
O PER ATO
RROOM
G AN G W
AY
l = 0,5 * B = 0,5 * 8 = 8 m
PDA = 15,206 kN/m
ESEP R O O M
WH
EEL
O
UHSE
CL
6.3. BULWARK
C
Gambar 52. Side Comming Engine Casing Kamar Mesin
c = 0,75
e = 3,6
l = 6,6 m
P = PDM = 30,905 kN/m
c = 0,75
e = 3,6
l = 2,4 m
P = PDF = 24,709 kN/m