SUMMARY PROGRESS PROYEK TANGKI TIMBUN LAMERURU

PT. DAMAI JAYA LESTARI


Periode S/D 11 Agustus 2015

1.00 PEKERJAAN PENDAHULUAN/PERSIAPAN

1 Lot

7.82

PROGRESS
STASIUN
98.74

2.00 PENYIAPAN LAHAN DAN TANAH

1 Lot

7.17

100.00

7.17

3.00 BANGUNAN UTAMA DAN PEKERJAAN SIPIL

1 Lot

25.85

99.92

25.83

4.00 BANGUNAN PENDUKUNG

1 Lot

4.99

99.57

4.97

5.00 STASIUN TIMBANGAN

1 Lot

1.11

100.00

1.11

6.00 STASIUN GUDANG KERNEL

1 Lot

3.63

99.82

3.63

7.00 STASIUN PENIMBUNAN CPO

1 Lot

36.59

99.99

36.59

8.00 STASIUN PEMBANGKIT TENAGA DAN THERMAL OIL

1 Lot

7.79

100.00

7.79

9.00 STASIUN PENAMPUNGAN AIR

1 Lot

1.01

100.00

1.01

10.00 SISTEM PEMIPAAN DAN VALVE

1 Lot

2.70

92.51

2.49

11.00 PERALATAN LABORATORIUM

1 Lot

0.36

100.00

0.36

12.00 KELISTRIKAN

1 Lot

0.98

100.00

0.98

No

NAMA STASIUN

TOTAL

KWANTITAS

BOBOT
(%)

100.00

NILAI
PROGRES
7.72

99.65

Diketahui Oleh

Diperiksa Oleh

(Aman Sihombing )

( Junjungan Sinambela)

Pimpro

Pnjwb. Proyek

Disusun Oleh,

URU

KETERANGAN

Lameruru, 12 Agustus 2015

Disusun Oleh,

PROGRESS DETAIL STASIUN PEKERJAAN PROYEK TAN


PT. DAMAI JAYA LESTARI
Periode S/D 11 Agustus 2015
No

NAMA STASIUN

KWANTITAS

1.00
1.01
1.02
1.03
1.04
1.06
1.07

PEKERJAAN PENDAHULUAN/PERSIAPAN
Desain dan Penggambaran
Perekayasaan dan Supervisi
Mobilisasi dan Demobilisasi
Transportasi
Legal dan Dokumentasi
Perkantoran
Total

1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls

2.00
2.01
2.02
2.03
2.04

PENYIAPAN LAHAN DAN TANAH


Pembersihan dan Setting Lokasi
Analisa Tanah dan Topograf
Pekerjaan Cutting, Timbun dan Pembentukan Tanah
Penanaman Rumput dan Taman
Total

1 Ls
1 Ls
1 Ls
1 Ls

3.00 BANGUNAN UTAMA DAN PEKERJAAN SIPIL


Bangunan Utama Pembangkit Tenaga dan
3.01 a.
Thermal Oil
b. Bangunan Utama Gudang Produksi
3.02 a. Pondasi dan Lantai Bangunan Utama
b. Dinding Bangunan Utama
3.03 Pondasi Permesinan dan Struktur dan Tanki
a. Pondasi Mesin Timbangan
b. Pondasi Mesin Kernel Elevator
c. Pondasi Mesin Air Compressor
d. Pondasi Mesin Pompa Loading I
e. Pondasi Mesin Pompa Loading II
f. Pondasi Mesin Generator Set
g. Pondasi Mesin Thermal Oil Heater
h. Pondasi Mesin Diesel Pump
i. Pondasi Oil Tank Loading
j. Pondasi Oil Storage Tank
k. Pondasi Struktur Kernel Hopper Loading
l. Pondasi Struktur Kernel Loading Shed
m. Pondasi Struktur Kernel Hopper
n. Pondasi Struktur Oil Loading Shed
o. Pondasi Struktur Diesel Storage Tank
p. Pondasi Struktur Water Tower
q. Pondasi Support Piping
r. Sedimentasi Buck
s. Soft Tank
t Pondasi LB3
3.04 a. Pekerjaan Parit I
b. Pekerjaan Parit II
3.05 Pekerjaan Jalan

1 Ls
1 Ls
1 Lot
1 Lot
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls

3.06 Pekerjaan Talud


3.07 Balok Beton Pemecah Ombak ( Tahu Tahu )
3.08 Pemancangan Pondasi
Total
4.00
4.01
4.02
4.03
4.04
4.05
4.06
4.07
4.08
4.09
4.10

BANGUNAN PENDUKUNG
Pagar dan Pintu Dorong
Pos Jaga
Parkiran
Kantor, Ruangan Timbangan dan Laboratorium
Perumahan Staf
Perumahan Pegawai Type I
Perumahan Pegawai Type II
Rumah Pompa I
Rumah Pompa II
Gudang LB3
Total

5.00 STASIUN TIMBANGAN


5.01 Weight Bridge (Jembatan Timbang)
5.02 Weight Bridge House
Total

1 Ls
1 Ls
1 Ls

1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot

1 Unit
1 Ls

6.00
6.01
6.02
6.03
6.04
6.05
6.06

STASIUN GUDANG KERNEL


Kernel Hopper Loading (Pembongkaran Kernel)
Kernel Loading Shed
Kernel Conveyor to Elevator
Kernel Elevator
Kernel Distributing Conveyor
Kernel Hopper (Penampungan Kernel)
Total

1 Ls
1 Ls
1 Unit
1 Unit
1 Unit
1 Ls

7.00
7.01
7.02
7.03
7.04
7.05
7.06
7.07
7.08
7.09
7.10

STASIUN PENIMBUNAN CPO


Oil Storage Tank Kap. 2000 Ton
Oil Tank Loading (Tanki Pembongkaran Minyak)
Oil Loading Shed
Pompa Loading I ( pompa transfer ke Storage Tank )
Pompa Loading II ( Pompa muat ke Kapal Cpo )
Flow Meter
Agitator
Air Compressor
Soft Tank
Soft Tank Pump
Total

1 Unit
1 Ls
1 Ls
2 Unit
2 Unit
1 Unit
2 Unit
1 Unit
1 Lot
1 Unit

8.00
8.01
8.02
8.03
8.04

STASIUN PEMBANGKIT TENAGA DAN THERMAL OIL


Generator Set 400 Kw
Thermal Oil Heater
Diesel Storage Tank
Diesel Pump
Total

1 Unit
1 Unit
1 Ls
1 Unit

9.00 STASIUN PENAMPUNGAN AIR

9.01 Sumur Bor


9.02 Water Tower Tank

1 Unit
1 Ls
Total

10.00
10.01
10.02
10.03
10.04
10.05

SISTEM PEMIPAAN DAN VALVE


Valve dan Accessories
Oil Heater Piping and Fitting
Palm Oil Piping and Fitting
Water Piping and Fitting
Piping Support
Total

1 Lot
1 Lot
1 Lot
1 Lot
1 Lot

11.00 PERALATAN LABORATORIUM


11.01 Peralatan Laboratorium
Total
12.00
12.01
12.02
12.03
12.04

KELISTRIKAN
Panel and Cabling
Instalasi Penerangan Bangunan
Instalasi Penerangan Lokasi/Penerangan Jalan
Instalasi Penyalur Petir
Total

1 Lot
1 Lot
1 Lot
1 Lot

Diketahui Oleh :

Diperiksa Oleh :

( Aman Sihombing )

( Junjungan Sinambela )

Pimpro

Pnjwb. Proyek

N PEKERJAAN PROYEK TANGKI TIMBUN LAMERURU


PT. DAMAI JAYA LESTARI

Periode S/D 11 Agustus 2015


BOBOT
(%)

PROGRESS
%

Nilai
Progres

24.78
36.58
4.62
10.04
21.88
2.13
100.00

100.00
100.00
100.00
98.00
95.00
100.00

24.78
36.58
4.62
9.84
20.79
2.13
98.74

0.14
0.65
99.00
0.22
100.00

100.00
100.00
100.00
98.00

0.14
0.65
99.00
0.21
100.00

6.33

100.00

6.33

13.05
3.58
5.34

100.00
100.00
100.00

13.05
3.58
5.34

0.20
0.24
0.02
0.04
0.04
0.06
0.24
0.02
0.27
10.96
0.95
0.70
1.96
0.85
0.19
0.42
0.33
0.64
5.66

100.00
100.00

0.20
0.24
0.04
0.04
0.06
0.24
0.02
0.27
10.96
0.95
0.70
1.96
0.85
0.19
0.42
0.27
0.64
5.66
1.27
0.54
10.74

1.27
0.54
10.74

100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
80.00
100.00
100.00
100.00
100.00
100.00
100.00

Keterangan

22.55
0.30
12.52
100.00

100.00
100.00
100.00

22.55
0.30
12.52
99.92

22.78
2.90
0.77
15.43
14.72
11.47
28.70
1.38
1.85

100.00
100.00
100.00
100.00
100.00
99.00
99.00
99.00
99.00
100.00

22.78
2.90
0.77
15.43
14.72
11.36
28.41
1.37
1.83

100.00

99.57

82.46
17.54
100.00

100.00
100.00

82.46
17.54
100.00

2.92
3.40
6.15
17.81
16.12
53.60
100.00

100.00
99.00
99.00
100.00
99.50
100.00

2.92
3.37
6.09
17.81
16.04
53.60
99.82

19.63
0.15
0.92
3.16
10.42
3.45
2.32
0.12
59.04
0.79
100.00

100.00
100.00
100.00
100.00
100.00
100.00
100.00
95.00
100.00
100.00

19.63
0.15
0.92
3.16
10.42
3.45
2.32
0.11
59.04
0.79
99.99

41.62
55.49
1.45
1.44
100.00

100.00
100.00
100.00
100.00

41.62
55.49
1.45
1.44
100.00

10.02
89.98
100.00

100.00
100.00

40.47
15.63
31.25
5.21
7.44
100.00

98.00
98.00
82.00
100.00
90.00

100.00
100.00

32.10
8.71
9.37
49.82
100.00

###

100.00
100.00
100.00
100.00

10.02
89.98
100.00

39.66
15.31
25.63 s/d 1 Juni 80%
5.21
6.70
92.51

100.00
100.00

32.10
8.71
9.37
49.82
100.00

Lameruru, 12 Agustus 2015


Diperiksa Oleh :

( Junjungan Sinambela )
Pnjwb. Proyek

Disusun Oleh :

PROGRESS DETAIL STASIUN PEKERJAAN PROYEK TANGK


PT. DAMAI JAYA LESTARI
Periode S/D 5 September 2015
No

NAMA STASIUN

KWANTITAS

1.00
1.01
1.02
1.03
1.04
1.06
1.07

PEKERJAAN PENDAHULUAN/PERSIAPAN
Desain dan Penggambaran
Perekayasaan dan Supervisi
Mobilisasi dan Demobilisasi
Transportasi
Legal dan Dokumentasi
Perkantoran
Total

1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls

2.00
2.01
2.02
2.03
2.04

PENYIAPAN LAHAN DAN TANAH


Pembersihan dan Setting Lokasi
Analisa Tanah dan Topograf
Pekerjaan Cutting, Timbun dan Pembentukan Tanah
Penanaman Rumput dan Taman
Total

1 Ls
1 Ls
1 Ls
1 Ls

3.00 BANGUNAN UTAMA DAN PEKERJAAN SIPIL


Bangunan Utama Pembangkit Tenaga dan Thermal
3.01 a.
Oil
b. Bangunan Utama Gudang Produksi
3.02 a. Pondasi dan Lantai Bangunan Utama
b. Dinding Bangunan Utama
3.03 Pondasi Permesinan dan Struktur dan Tanki
a. Pondasi Mesin Timbangan
b. Pondasi Mesin Kernel Elevator
c. Pondasi Mesin Air Compressor
d. Pondasi Mesin Pompa Loading I
e. Pondasi Mesin Pompa Loading II
f. Pondasi Mesin Generator Set
g. Pondasi Mesin Thermal Oil Heater
h. Pondasi Mesin Diesel Pump
i. Pondasi Oil Tank Loading
j. Pondasi Oil Storage Tank
k. Pondasi Struktur Kernel Hopper Loading
l. Pondasi Struktur Kernel Loading Shed
m. Pondasi Struktur Kernel Hopper
n. Pondasi Struktur Oil Loading Shed
o. Pondasi Struktur Diesel Storage Tank
p. Pondasi Struktur Water Tower
q. Pondasi Support Piping
r. Sedimentasi Buck
s. Soft Tank
t Pondasi LB3
3.04 a. Pekerjaan Parit I
b. Pekerjaan Parit II
3.05 Pekerjaan Jalan

1 Ls
1 Ls
1 Lot
1 Lot
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls
1 Ls

3.06 Pekerjaan Talud


3.07 Balok Beton Pemecah Ombak ( Tahu Tahu )
3.08 Pemancangan Pondasi
Total
4.00
4.01
4.02
4.03
4.04
4.05
4.06
4.07
4.08
4.09
4.10

BANGUNAN PENDUKUNG
Pagar dan Pintu Dorong
Pos Jaga
Parkiran
Kantor, Ruangan Timbangan dan Laboratorium
Perumahan Staf
Perumahan Pegawai Type I
Perumahan Pegawai Type II
Rumah Pompa I
Rumah Pompa II
Gudang LB3
Total

5.00 STASIUN TIMBANGAN


5.01 Weight Bridge (Jembatan Timbang)
5.02 Weight Bridge House
Total

1 Ls
1 Ls
1 Ls

1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot
1 Lot

1 Unit
1 Ls

6.00
6.01
6.02
6.03
6.04
6.05
6.06

STASIUN GUDANG KERNEL


Kernel Hopper Loading (Pembongkaran Kernel)
Kernel Loading Shed
Kernel Conveyor to Elevator
Kernel Elevator
Kernel Distributing Conveyor
Kernel Hopper (Penampungan Kernel)
Total

1 Ls
1 Ls
1 Unit
1 Unit
1 Unit
1 Ls

7.00
7.01
7.02
7.03
7.04
7.05
7.06
7.07
7.08
7.09
7.10

STASIUN PENIMBUNAN CPO


Oil Storage Tank Kap. 2000 Ton
Oil Tank Loading (Tanki Pembongkaran Minyak)
Oil Loading Shed
Pompa Loading I ( pompa transfer ke Storage Tank )
Pompa Loading II ( Pompa muat ke Kapal Cpo )
Flow Meter
Agitator
Air Compressor
Soft Tank
Soft Tank Pump
Total

1 Unit
1 Ls
1 Ls
2 Unit
2 Unit
1 Unit
2 Unit
1 Unit
1 Lot
1 Unit

8.00
8.01
8.02
8.03
8.04

STASIUN PEMBANGKIT TENAGA DAN THERMAL OIL


Generator Set 400 Kw
Thermal Oil Heater
Diesel Storage Tank
Diesel Pump
Total

1 Unit
1 Unit
1 Ls
1 Unit

9.00 STASIUN PENAMPUNGAN AIR

9.01 Sumur Bor


9.02 Water Tower Tank

1 Unit
1 Ls
Total

10.00
10.01
10.02
10.03
10.04
10.05

SISTEM PEMIPAAN DAN VALVE


Valve dan Accessories
Oil Heater Piping and Fitting
Palm Oil Piping and Fitting
Water Piping and Fitting
Piping Support
Total

1 Lot
1 Lot
1 Lot
1 Lot
1 Lot

11.00 PERALATAN LABORATORIUM


11.01 Peralatan Laboratorium
Total
12.00
12.01
12.02
12.03
12.04

KELISTRIKAN
Panel and Cabling
Instalasi Penerangan Bangunan
Instalasi Penerangan Lokasi/Penerangan Jalan
Instalasi Penyalur Petir
Total

1 Lot
1 Lot
1 Lot
1 Lot

Diketahui Oleh :

Diperiksa Oleh :

Asmer Pardosi

Januarison Butar-Butar

Kasie. Teknik

Asst. Teknik Sipil

N PEKERJAAN PROYEK TANGKI TIMBUN LAMERURU


PT. DAMAI JAYA LESTARI

riode S/D 5 September 2015


BOBOT
(%)

PROGRESS
%

Nilai
Progres

24.78
36.58
4.62
10.04
21.88
2.13
100.00

100.00
100.00
100.00
98.00
95.00
100.00

24.78
36.58
4.62
9.84
20.79
2.13
98.74

0.14
0.65
99.00
0.22
100.00

100.00
100.00
100.00
98.00

0.14
0.65
99.00
0.21
100.00

6.33

100.00

6.33

13.05
3.58
5.34

100.00
100.00
100.00

13.05
3.58
5.34

0.20
0.24
0.02
0.04
0.04
0.06
0.24
0.02
0.27
10.96
0.95
0.70
1.96
0.85
0.19
0.42
0.33
0.64
5.66

100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00

0.20
0.24
0.02
0.04
0.04
0.06
0.24
0.02
0.27
10.96
0.95
0.70
1.96
0.85
0.19
0.42
0.33
0.64
5.66
1.27
0.54
10.74

1.27
0.54
10.74

Keterangan

22.55
0.30
12.52
100.00

100.00
100.00
100.00

22.55
0.30
12.52
100.00

22.78
2.90
0.77
15.43
14.72
11.47
28.70
1.38
1.85

100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00

22.78
2.90
0.77
15.43
14.72
11.47
28.70
1.38
1.85

100.00

100.00

82.46
17.54
100.00

100.00
100.00

82.46
17.54
100.00

2.92
3.40
6.15
17.81
16.12
53.60
100.00

100.00
100.00
100.00
100.00
100.00
100.00

2.92
3.40
6.15
17.81
16.12
53.60
100.00

19.63
0.15
0.92
3.16
10.42
3.45
2.32
0.12
59.04
0.79
100.00

100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00

19.63
0.15
0.92
3.16
10.42
3.45
2.32
0.12
59.04
0.79
100.00

41.62
55.49
1.45
1.44
100.00

100.00
100.00
100.00
100.00

41.62
55.49
1.45
1.44
100.00

10.02
89.98
100.00

100.00
100.00

10.02
89.98
100.00

40.47
15.63
31.25
5.21
7.44
100.00

98.00
98.00
88.00
100.00
95.00

39.66
15.31
27.50
5.21
7.07
94.76

100.00
100.00

32.10
8.71
9.37
49.82
100.00

###

100.00
100.00
100.00
100.00

100.00
100.00

32.10
8.71
9.37
49.82
100.00

Kendari, 7 September 2015


Diperiksa Oleh :

Disusun Oleh :

Januarison Butar-Butar

Yulianus Karurung

Asst. Teknik Sipil

Pers. Teknik Sipil

SUMMARY PROGRESS PROYEK TANGKI TIMBUN LAMERURU


PT. DAMAI JAYA LESTARI
Periode S/D 5 September 2015

1.00 PEKERJAAN PENDAHULUAN/PERSIAPAN

1 Lot

7.82

PROGRESS
STASIUN
98.74

2.00 PENYIAPAN LAHAN DAN TANAH

1 Lot

7.17

100.00

7.17

3.00 BANGUNAN UTAMA DAN PEKERJAAN SIPIL

1 Lot

25.85

100.00

25.85

4.00 BANGUNAN PENDUKUNG

1 Lot

4.99

100.00

4.99

5.00 STASIUN TIMBANGAN

1 Lot

1.11

100.00

1.11

6.00 STASIUN GUDANG KERNEL

1 Lot

3.63

100.00

3.63

7.00 STASIUN PENIMBUNAN CPO

1 Lot

36.59

100.00

36.59

8.00 STASIUN PEMBANGKIT TENAGA DAN THERMAL OIL

1 Lot

7.79

100.00

7.79

9.00 STASIUN PENAMPUNGAN AIR

1 Lot

1.01

100.00

1.01

10.00 SISTEM PEMIPAAN DAN VALVE

1 Lot

2.70

94.76

2.55

11.00 PERALATAN LABORATORIUM

1 Lot

0.36

100.00

0.36

12.00 KELISTRIKAN

1 Lot

0.98

100.00

0.98

No

NAMA STASIUN

TOTAL

KWANTITAS

BOBOT
(%)

100.00

NILAI
PROGRES
7.72

99.76

Diketahui Oleh

Diperiksa Oleh

Disusun Oleh,

Asmer Pardosi

Januarison Butar-Butar

Yulianus Karurung

Kasie. Teknik

Asst. Teknik Sipil

Pers. Teknik Sipil

URU

KETERANGAN

Kendari, 7 September 2015

Disusun Oleh,

Yulianus Karurung
Pers. Teknik Sipil

LAPORAN PROGRESS BANGUNAN PERMANEN LOKASI PKS GANDA MAK


PT. DAMAI JAYA LESTARI PERKEBUNAN WIWIRANO TANI
PERIODE s/d 5 SEPTEMBER 2015
A. PERUMAHAN PIMPINAN, STAF DAN PRASARANA UMUM
PROGRES
NO

NO. BLOCK

NAMA BANGUNAN

JUMLAH

1 Juni

Perumahan Staf keb Kopel 1

Unit

2
3
4
5
6
7
8
9
10
11
12
13
14

Perumahan Staf keb Kopel 2


Perumahan Staf keb Kopel 3
Perumahan Staf keb Kopel 4
Perumahan Staf keb Kopel 5
Perumahan Staf keb Kopel 6
Perumahan Staf keb Kopel 7
Perumahan Staf keb Kopel 8
Perumahan Staf keb Kopel 9
Gereja
Masjid
Pagar Mesjid
Dekker depan kantor afd. II
Dekker

1
1
1
1
1
1
1
1
1
1
1
1
9

Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit

4.65%
99%
98%
96%
100%
100.00%

15

Dekker

Unit

100.00%

27

Unit

18.86%

TOTAL

99.81%
99.79%

7.90%
4.65%

B. AFDELING IIIB
PROGRES
NO

NO. BLOCK

NAMA BANGUNAN

JUMLAH

1 Juni

Kantor,Kedai dan Rumah Mdr I

1 Unit

43.55%

Kopelan pegawai 4 pintu

1 Unit

0%

Mushollah

1 Unit

0%

TOTAL Rata-rata

3 Unit

14.52%

C. PERUMAHAN SUPIR
PROGRES
NO

NO. BLOCK

NAMA BANGUNAN

Rumah Supir 1

1 Unit

100%

2
3

2
3

Rumah Supir 2
Rumah Supir 3

1 Unit
1 Unit

98%
58%

Rumah Supir 4

1 Unit

0%

4 Unit

64.00%

TOTAL Rata-rata

JUMLAH

1 Juni

D. AFDELING VIII
PROGRES
NO

NO. BLOCK

NAMA BANGUNAN

JUMLAH

1 Juni

Kopelan pegawai 4 pintu

1 Unit

99.06%

Mushollah

1 Unit

31.00%

3 Unit

43.35%

TOTAL Rata-rata

Diketahui Oleh,

Diperiksa Oleh,

( Asmer Pardosi )
Kasie Teknik

( Januarison Butar Butar )


Staf Teknik

KASI PKS GANDA MAKMUR


N WIWIRANO TANI
2015

PROGRES
S/D
Sekarang

KETERANGAN

100%
100%

7.90%
4.65%
4.65%
100%
100%
100%
100%
100%

Afd. II

100%

Afd. I

19.16%

PROGRES
S/D
Sekarang

KETERANGAN

100.00%
100.00%

Semi Permanen

15.00%
71.67%

PROGRES
S/D
Sekarang

KETERANGAN

100%
98%
58%

Semi Permanen

0%
64.00%

PROGRES
S/D
Sekarang
100.00%
99.28%

KETERANGAN

Semi permanen

66.43%
Kendari, 7 September 2015
Disusun Oleh,

(Yulianus Karurung )
Pers. Teknik Sipil

PROGRES PEKERJAAN WATARAKI


PT. MULYA TANI
PERIODE S/D 5 SEPTEMBER 2015
NO NAMA BANGUNAN

Perumahan Karyawan Afdeling V


- Kopelan Panggung
- Kopelan 1
- Kopelan 2
- Kopelan 3
- Kopelan 4
- Kopelan 5
- Kopelan 6
- Kopelan 7
- Kopelan 8
- Kopelan 9
- Kopelan 10

JUMLAH

PROGRES

2 Unit

Perumahan Kantor Afdeling


- Afdeling I
- Afdeling V
Dekker
- Dekker di Paka
- Box Culver di Paka
- Dekker 1 di Pondoa

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
99.50%
99.50%
41.81%
51.89%
10.26%

100.00%
99.65%

100.00%
100.00%
100.00%

11 Unit

Cor Jalan
- Cor Jalan di Paka
- Cor Jalan di Pondoa I
- Cor Jalan di Pondoa II

100.00%
100.00%
31.00%

Parit Jalan
- Pekerjaan Parit Jalan di Paka
- Pekerjaan Parit Jalan di Pondoa I
- Pekerjaan Parit Jalan di Pondoa II

100.0%
91.38%
55.00%

Prasarana Umum
- Gudang Umum dan Gudang Kedai

43.00%

Diketahui Oleh,

Diperiksa Oleh,

( Asmer Pardosi )
Kasie Tehnik

( Januarison Butar Butar )


Staff Teknik

AN WATARAKI
TANI
TEMBER 2015
KETERANGAN

Non permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen
Semi permanen

Semi permanen
Semi permanen

Non Permanen

Kendari, 7 September 2015


Disusun Oleh,

(Yulianus Karurung )
Pers. Teknik Sipil

OBJEK KERJA TENAGA SABAR GANDA DAN LOKASI PEKER


No

Lokasi Kerja

1 Kolaka Tani
- PKS Parsambilan

Nama Mandor

Jumlah
Tenaga

Objek Ke

Suprianto

5 Orang - Perbaikan Bak jonder Afdeling XI


- Pemasangan lantai kerja separato
- Rakit Liner Digester No. 1 dan no

M. Sonef

5 Orang - Pengecatan kantor PKS

- Kebun Kolaka

M. Sonef

- ITT Kolaka

Suprianto

3 Orang - Pemasangan tangki air perumaha

2 Hotel Kolaka

M. Sonef

5 Orang - Pembersihan lahan kosong hotel

Total
2 Wiwirano Tani
- PKS Ganda Makmur

- Kebun Wiwirano

30 Orang
M. Sonef

10 Orang

Suprianto

8 Orang - Perbaikan bak mobil tronton


- Perbaikan tangki mobil tangki CP

M. Adil

- Tangki Timbun Lameruru

12 Orang - Buat perabotan Mess


- pekerjaan kusen perumahan PKS

- Buat Fat Fit

23 Orang - Pekerjaan Kopelan personil dan Mushalla Afd


- Pekerjaan Mushalla afd. III B
- Pekerjaan jembatan Afd. II (Sarim
- Pemeliharaan Mess Kebun

M. Sonef

6 Orang - Buat perabotan Mess


- Pekerjaan pegangan tangga dan

Suprianto

9 Orang - Penyetelan angkur support piping


- Pemasangan klem pipa

Total
3 Wataraki

Nurudin

56 Orang
42 Orang - pekerjaan parit jalan di Pondoa
- pekerjaan pengecoran jalan Pondoa

M. Tarom Bayu

30 Orang - Pengerjaan Rumah Afdeling V


- Pekerjaan Kantor Afdeling V
- Pekerjaan Gudang umum dan kedai

4 Proyek kendari (Linggahara) Rojikin


Eko SP
Syarif
Suprianto
Ahmad Somadin
Suwarno
Jarot Mariadi
M. Sonef

Total
Jumlah Total Tenaga Sabar Ganda

72 Orang
75 Orang
52 Orang
46 Orang
7 Orang
28 Orang
56 Orang
10 Orang

Pekerjaan Perumahan
Linggahara II

10 Orang
284 Orang
442 Orang

Proyek Hotel

Diketahui Oleh,

Diperiksa Oleh,

Asmer Pardosi

Januarison Butar-Butar

Kasie. Teknik

Asst. Teknik Sipil

ABAR GANDA DAN LOKASI PEKERJAAN


Objek Kerja
- Perbaikan Bak jonder Afdeling XI
- Pemasangan lantai kerja separator Turbin 1 - 3
- Rakit Liner Digester No. 1 dan no. 2
- Pengecatan kantor PKS

- pekerjaan kusen perumahan PKS


- Pemasangan tangki air perumahan
- Pembersihan lahan kosong hotel

- Perbaikan bak mobil tronton


- Perbaikan tangki mobil tangki CPO
- Pekerjaan Kopelan personil dan Mushalla Afd VIII

- Pekerjaan Mushalla afd. III B


- Pekerjaan jembatan Afd. II (Sarimukti)
- Pemeliharaan Mess Kebun

- Pekerjaan pegangan tangga dan pengecatan gereja


- Penyetelan angkur support piping

- pekerjaan pengecoran jalan Pondoa

- Pekerjaan Gudang umum dan kedai

Kendari, 7 September 2015


Disusun Oleh,

Yulianus Karurung

Pers. Teknik Sipil