No Uraian Pengeluaran
1 Pembelian Lahan
2 Biaya Pembukaan Lahan ( Via Hotman )
3 Bahan Bangunan
- Upah Buat Papan dan Broti
- Belanja Panglong
- Besi
- Belanja Panglong
- Belanja Papan
- Belanja Panglong
4 Panjar Upah Tukang
5 Upah Buat Batagi
6 Upah Angkat Bahan /Papan dan Broti
7 Biaya Angkat Air Tukang
Harga (Rp)
150,000,000
6,200,000
31,127,000
6,000,000
10,040,000
350,000
7,437,000
3,900,000
3,400,000
10,100,000
600,000
1,500,000
500,000
Total (Rp)
150,000,000
156,200,000
187,327,000
197,427,000
198,027,000
199,527,000
200,027,000