NETWORK PLANNING

Belanja Modal Pembangunan Ruang Kelas Baru (RKB) SDN Cipadung 3

PEKERJAAN PERSIAPAN
START
Start: 6/20/16 ID: 2
Milestone Date: Mon 6/20/16 Finish: 6/26/16 Dur: 7 days
ID: 1 Res:

PEKERJAAN STRUKTUR STRUKTUR UTAMA STRUKTUR RINGAN


Start: 6/27/16 ID: 3 Start: 6/27/16 ID: 4 Start: 8/15/16 ID: 5
Finish: 8/28/16 Dur: 63 days Finish: 8/21/16 Dur: 56 days Finish: 8/28/16 Dur: 14 days
Comp: 0% Res: Res:

PEKERJAAN ARSITEKTUR PEKERJAAN DINDING PEKERJAAN KUSEN DAN ALAT PENGGANTUNG


Start: 8/15/16 ID: 6 Start: 8/15/16 ID: 7 Start: 8/22/16 ID: 8
Finish: 10/2/16 Dur: 49 days Finish: 9/11/16 Dur: 28 days Finish: 9/18/16 Dur: 28 days
Comp: 0% Res: Res:

PEKERJAAN LANTAI KERAMIK


Start: 8/22/16 ID: 9
Finish: 9/18/16 Dur: 28 days
Res:

PEKERJAAN PENGECATAN
FINISH
Start: 9/19/16 ID: 10
Finish: 10/2/16 Dur: 14 days Milestone Date: Sun 10/9/16
Res: ID: 16

PEKERJAAN MEKANIKAL/ELEKTRIKAL PEKERJAAN MEKANIKAL (KM/WC) LANTAI 1 PEKERJAAN MEKANIKAL LANTAI 2 PEKERJAAN ELEKTRIKAL PEKERJAAN LAIN-LAIN
Start: 7/4/16 ID: 11 Start: 7/4/16 ID: 12 Start: 8/15/16 ID: 13 Start: 9/26/16 ID: 14 Start: 9/5/16 ID: 15
Finish: 10/9/16 Dur: 98 days Finish: 9/25/16 Dur: 84 days Finish: 10/9/16 Dur: 56 days Finish: 10/9/16 Dur: 14 days Finish: 10/9/16 Dur: 35 days
Comp: 0% Res: Res: Res: Res:

CV. BANI JAYA BERSAUDARA Critical Critical Milestone Critical Summary Critical Inserted Critical Marked Critical External Project Summary Highlighted Noncritical

Noncritical Milestone Summary Inserted Marked External Highlighted Critical


NIKON SAMOSIR