DISTRIBUSI MOMEN ( METODE CROSS )

JOINT I J K I J K
BATANG IT IJ JI JU JK KJ KV TI UJ VK
0.234 0.769 0.769 0.133 0.433 0.769 0.234
FEM 125.880 -125.880 125.880 -125.880
BALANCE -29.494 -96.802 0.000 0.000 0.000 96.802 29.494
CO 0.000 -48.401 48.401 0.000 -14.747 0.000 14.747
BALANCE 0.000 0.000 0.000 0.000 0.000 0.000 0.000
TOTAL -29.494 29.078 -174.281 0.000 174.281 -29.078 29.494 -14.747 0.000 14.747
KONTROL 0 0 0
TABEL PENULANGAN BALOK MEMANJANG

Tumpuan Lapangan
No. Penampang Kritis A B C
AB BC
AB BA BC CB
1 Mu (kNm) 160.604 284.586 284.586 160.604 280.735 280.735
2 b (m) 0.25 0.25 0.25 0.25 0.25 0.25
3 d efektif (m) 0.490 0.490 0.490 0.490 0.490 0.490
4 m 15.69 15.69 15.69 15.69 15.69 15.69
5 Mu/(bd ) (kN/m2)
2
1.836 3.253 3.253 1.836 3.209 3.209
6 0.0048 0.0087 0.0087 0.0048 0.0086 0.0086
7 min = 1,4/fy 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035
8 dipakai 0.0048 0.0087 0.0087 0.0048 0.0086 0.0086
9 As = dipakai bd (mm2) 584.1 1069.5 1069.5 584.1 1053.9 1053.9
10 Tulangan terpakai (mm) 316 316 316 316 316 316
TABEL PENULANGAN BALOK MELINTANG

Tumpuan Lapangan
No. Penampang Kritis I J K
IJ JK
IJ JI JK KJ
1 Mu (kNm) 29.494 174.281 174.281 29.494 125.880 125.880
2 b (m) 0.25 0.25 0.25 0.25 0.25 0.25
3 d efektif (m) 0.490 0.490 0.490 0.490 0.490 0.490
4 m 15.69 15.69 15.69 15.69 15.69 15.69
5 Mu/(bd ) (kN/m2)
2
0.337 1.992 1.992 0.337 1.439 1.439
6 0.0008 0.0052 0.0052 0.0008 0.0037 0.0037
7 min = 1,4/fy 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035
8 dipakai 0.0035 0.0052 0.0052 0.0035 0.0037 0.0037
9 As = dipakai bd (mm2) 428.8 636.0 636.0 428.8 453.9 453.9
10 Tulangan terpakai (mm) 316 316 316 316 316 316
4500000

4000000

3500000

3000000

2500000

4D.13 4D.16 4D.19 4D.22 4D.25 4D.32


2000000

1500000

1000000

500000

0
0 100000000 200000000 300000000 400000000 500000000 600000000