Asumsi 1 org pergi dan pulang ke kantor dgn menghabiskan waktu di dalam LRT = 1 jam
BIAYA PENGELUARAN SKENARIO 2
Biaya Pengeluaran Harga Rp (Milyar)
Initial Cost Rp 2,693,665,000,000.00
O&M Prasarana & Sarana Rp 538,733,000.00
Disbenefit :
Biaya Polusi / thn Rp 10,618,835.50
Corridor 1 Skenario 2
Total Investment Rp 2,716,665,000,000.00
Tahun Cost
0 Rp 2,716,665,000,000
1 Rp 549,351,835.50
2 Rp 549,351,835.50
3 Rp 549,351,835.50
4 Rp 549,351,835.50
5 Rp 549,351,835.50
6 Rp 549,351,835.50
7 Rp 549,351,835.50
8 Rp 549,351,835.50
9 Rp 549,351,835.50
10 Rp 549,351,835.50
11 Rp 549,351,835.50
12 Rp 549,351,835.50
13 Rp 549,351,835.50
14 Rp 549,351,835.50
15 Rp 549,351,835.50
16 Rp 549,351,835.50
17 Rp 549,351,835.50
18 Rp 549,351,835.50
19 Rp 549,351,835.50
20 Rp 549,351,835.50
21 Rp 549,351,835.50
22 Rp 549,351,835.50
23 Rp 549,351,835.50
24 Rp 549,351,835.50
25 Rp 549,351,835.50
26 Rp 549,351,835.50
27 Rp 549,351,835.50
28 Rp 549,351,835.50
29 Rp 549,351,835.50
30 Rp 549,351,835.50
31 Rp 549,351,835.50
32 Rp 549,351,835.50
33 Rp 549,351,835.50
34 Rp 549,351,835.50
35 Rp 549,351,835.50
36 Rp 549,351,835.50
37 Rp 549,351,835.50
38 Rp 549,351,835.50
39 Rp 549,351,835.50
40 Rp 549,351,835.50
147 KM)
Harga (Rp)
Rp 15,948,133,595.00
Rp 97,994,555,826
Rp 979,945,558,264
Rp 88,067,002,785
Rp 100,876,748,645
Rp 154,117,254,874
Rp 550,000,000,000
Rp 83,263,348,088
Rp 1,837,397,922
Rp 2,072,050,000,000
Rp 621,615,000,000
Rp 2,693,665,000,000
RT = 1 jam
i (%) 6%
Rp 192,345,250,000.00 Rp 176,172,604,872.69
Rp 210,002,543,950.00 Rp 161,359,777,315.16
Rp 229,280,777,484.61 Rp 147,792,432,052.72
Rp 250,328,752,857.70 Rp 135,365,847,273.05
Rp 273,308,932,370.03 Rp 123,984,106,313.47
Rp 298,398,692,361.60 Rp 113,559,357,312.21
Rp 325,791,692,320.40 Rp 104,011,135,109.19
Rp 355,699,369,675.41 Rp 95,265,740,162.29
Rp 388,352,571,811.61 Rp 87,255,669,685.19
Rp 424,003,337,903.92 Rp 79,919,096,615.85
Rp 462,926,844,323.50 Rp 73,199,392,394.08
Rp 505,423,528,632.40 Rp 67,044,689,864.52
Rp 551,821,408,560.85 Rp 61,407,482,931.41
Rp 602,478,613,866.74 Rp 56,244,259,874.90
Rp 657,786,150,619.70 Rp 51,515,167,498.53
Rp 718,170,919,246.59 Rp 47,183,703,515.78
Rp 784,099,009,633.43 Rp 43,216,434,801.05
Rp 856,079,298,717.78 Rp 39,582,739,330.51
Rp 934,667,378,340.07 Rp 36,254,569,820.94
Rp 1,020,469,843,671.69 Rp 33,206,237,242.12
Rp 1,114,148,975,320.75 Rp 30,414,212,531.71
Rp 1,216,427,851,255.20 Rp 27,856,944,982.33
Rp 1,328,095,928,000.42 Rp 25,514,695,898.82
Rp 1,450,015,134,190.86 Rp 23,369,386,241.82
Rp 1,583,126,523,509.58 Rp 21,404,457,081.72
Rp 1,728,457,538,367.76 Rp 19,604,741,785.78
Rp 1,887,129,940,389.93 Rp 17,956,348,951.99
Rp 2,060,368,468,917.72 Rp 16,446,555,185.92
Rp 2,249,510,294,364.37 Rp 15,063,706,893.13
Rp 2,456,015,339,387.02 Rp 13,797,130,328.94
Rp 2,681,477,547,542.74 Rp 12,637,049,211.34
Rp 2,927,637,186,407.17 Rp 11,574,509,261.16
Rp 3,196,394,280,119.35 Rp 10,601,309,086.98
Rp 3,489,823,275,034.30 Rp 9,709,936,881.28
Rp 3,810,189,051,682.45 Rp 8,893,512,439.34
Rp 4,159,964,406,626.90 Rp 8,145,734,053.25
Rp 4,541,849,139,155.25 Rp 7,460,829,871.09
Rp 4,958,790,890,129.71 Rp 6,833,513,345.93
Rp 5,414,007,893,843.61 Rp 6,258,942,430.79
Rp 5,911,013,818,498.46 Rp 5,732,682,204.42
i (%) 6%
Rp 258,860,420,000.00 Rp 237,095,090,675.95
Rp 282,623,806,556.00 Rp 217,159,819,267.22
Rp 308,568,671,997.84 Rp 198,900,732,063.76
Rp 336,895,276,087.24 Rp 182,176,893,262.29
Rp 367,822,262,432.05 Rp 166,859,217,129.77
Rp 401,588,346,123.31 Rp 152,829,471,633.79
Rp 438,454,156,297.44 Rp 139,979,365,848.87
Rp 478,704,247,845.54 Rp 128,209,714,094.95
Rp 522,649,297,797.76 Rp 117,429,670,356.25
Rp 570,628,503,335.59 Rp 107,556,027,071.12
Rp 623,012,199,941.80 Rp 98,512,572,880.67
Rp 680,204,719,896.46 Rp 90,229,504,378.71
Rp 742,647,513,182.95 Rp 82,642,887,322.50
Rp 810,822,554,893.15 Rp 75,694,163,145.72
Rp 885,256,065,432.34 Rp 69,329,696,964.39
Rp 966,522,572,239.03 Rp 63,500,363,587.10
Rp 1,055,249,344,370.57 Rp 58,161,168,334.03
Rp 1,152,121,234,183.79 Rp 53,270,899,738.08
Rp 1,257,885,963,481.86 Rp 48,791,811,447.22
Rp 1,373,359,894,929.50 Rp 44,689,330,873.07
Rp 1,499,434,333,284.03 Rp 40,931,792,336.58
Rp 1,637,082,405,079.50 Rp 37,490,192,651.20
Rp 1,787,366,569,865.80 Rp 34,337,967,257.00
Rp 1,951,446,820,979.48 Rp 31,450,785,177.69
Rp 2,130,589,639,145.40 Rp 28,806,361,217.89
Rp 2,326,177,768,018.94 Rp 26,384,283,951.17
Rp 2,539,720,887,123.08 Rp 24,165,858,171.07
Rp 2,772,867,264,560.98 Rp 22,133,960,589.00
Rp 3,027,416,479,447.68 Rp 20,272,907,665.32
Rp 3,305,333,312,260.98 Rp 18,568,334,553.33
Rp 3,608,762,910,326.53 Rp 17,007,084,221.77
Rp 3,940,047,345,494.51 Rp 15,577,105,900.14
Rp 4,301,743,691,810.91 Rp 14,267,362,062.77
Rp 4,696,643,762,719.15 Rp 13,067,743,233.90
Rp 5,127,795,660,136.77 Rp 11,968,989,955.94
Rp 5,598,527,301,737.32 Rp 10,962,621,318.87
Rp 6,112,472,108,036.81 Rp 10,040,869,498.88
Rp 6,673,597,047,554.59 Rp 9,196,619,801.13
Rp 7,286,233,256,520.10 Rp 8,423,355,743.85
Rp 7,955,109,469,468.65 Rp 7,715,108,759.71
SKENARIO 1
No
1
2
3
4
5
6
SKENARIO 2
No
1
2
3
4
Benefit
Rp 2,032,816,642,653.37
Investment
Rp 2,716,665,000,000
Benefit
Rp 2,735,787,704,142.64
Investment
Rp 2,716,665,000,000
SKENARIO 1
Item Biaya Harga Rp(Milyar)
First Cost Rp 2,448,091,042,011.33
O&M Prasarana & Sarana Rp 538,733,000.00
Biaya Polusi / thn Rp 10,618,835.50
Biaya Tiket Rp 21,845,250,000.00
Benefit Rp 80,250,000,000.00
Advertisment Rp 90,250,000,000.00
SKENARIO 2
Item Biaya Harga Rp
First Cost Rp 2,448,091,042,011.33
O&M Prasarana & Sarana Rp 3,785,250,000.00
Biaya Restrukturisasi Jalan Rp 20,619,448,891,093
Disbenefit:
Biaya Polusi / thn Rp 10,618,835.50
2800
f (%) 3%
O&M
Rp 5,805,870,193.71
inflasi
f (%) 3%
O&M
Rp 5,805,870,193.71
SKENARIO 1
No
1
2
No Uraian Pekerjaan
1 Desain Teknis dan Supervisi
Perancangan Spesifikasi
Biaya Perancangan
2 Pekerjaan Persiapan Konstruksi Teknis
Pekerjaan Persiapan
Pembersihan Lahan
Pekerjaan Galian
Peminjaman alat berat
Pemasangan Pipa dan Saluran Kabel
Pekerjaan Pondasi
3 Upah pekerja (90hari=3bulan)
4 Pekerjaan Konstruksi Jalur Monorel
Lebar Gerbong (40 gerbong)
Tinggi Gerbong (40 gerbong)
Tinggi Rel ke Dek Lantai
Panjang rel
Lebar Rel
Diameter roda
Dek Lantai
Pemasangan Bantalan Rel
Upah Pekerja
6 Pembangunan Stasiun Antara
7 Pembangunan Stasiun Besar
Panjang Stasiun
Lebar Stasiun
Upah Pekerja
Finishing
8 Pembangunan Depo
9 Pekerjaan Sinyal dan Telekomunikasi
Pemasangan Jaringan Kabel
Besar Daya
if Upah Pekerja
10 Pembebasan lahan
0.74668077 11 GRAND TOTAL
12 PPN 10%
Total sesudah PPN
9%
if
1.00489145
9%
SKENARIO 1
Item Biaya Harga Rp(Milyar)
First Cost Rp 2,448,091,042,011.33
O&M Prasarana & Sarana Rp 538,733,000.00
Disbenefit :
Biaya Polusi / thn Rp 10,618,835.50
4200 m
4 m
8 unit
40 titik
30 orang
3.65 m
3.6 m
0.195 m
4200 m
1.067 m
0.66 m
3 m/grbng
4200 m
230 orang
15 m
8 m
27 orang
90 m2
4200 m
750 volt
40 orang
aya Investasi Prasarana Koridor 1 (10147 KM)
Material Volume Kebutuhan Satuan
4200 m
2000 m3
Excavator,Loader 7 hari
Kabel & Pipa Saluran Air
Bore Pile 40 titik
30 orang/hari