ACTION PLAN PABRIK 6 & 7

4M Masalah Sebab Tindakan Adat Target PIC Hasil S/D


4M Masalah Sebab Tindakan Adat Target PIC Hasil S/D
PROGRAM COST REDUCTION PABRIK 6 & 7

Action Plan
No Thema CR Target PIC Kapan S/D Keterangan
4M1L
1. Pengurangan time table 2 X,
- Type CW632 0.5 Jam/Org 5 Line
- Mempercepat proses isi forming ke Marsono 31-05-17 10%
2. ( 10X 0.5 = 5 jam / hr )
- Type CW631 0.5 Jam/Org 2 Line
- Merubah cara pengeringan body Slamet R. 01-06-17 0%
finishing. ( 4 X 0.5 = 2 jam / hr )
- SK500 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.30 )
- Mempercepat proses finishing body. Priytano
- LW248 0.5 Jam/Org 2 line = 4 X 0.5 = 2 jam / hr ( 16.00 )
01-06-17 50%
- L525 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- Mempercepat proses isi forming ke Slamet R.
- LW572 0.5 Jam/Org 2. 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- LW643 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- Mempercepat proses kerja.
- L650 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- LW828 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- Menghilangkan gerakan sia - sia.
- LW824 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- LW830 0.5 Jam/Org Penambahan sarana / alat kerja 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- LW952 0.5 Jam/Org - sesuai kondisi type ( bentuk dan 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
ukuran polinet ).
- LW542 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )
- LW528 0.5 Jam/Org 1 line = 2 X 0.5 = 1 jam / hr ( 16.00 )

Pengurangan time table 3 X,


- LW540 0.5 Jam/Org Slamet R. 01-06-17 60% 4 Line = 8 X 0.5 = 4 jam / hr
- LW526 0.5 Jam/Org 1 Line = 3 X 0.5 = 1.5 jam / hr ( 17.30 )
- LW248 0.5 Jam/Org 2 Line = 4 X 0.5 = 2 jam / hr ( 17.30 )
- L521 0.5 Jam/Org 1 Line = 3 X 0.5 = 1.5 jam / hr ( 17.30 )
- LW660 0.5 Jam/Org 1 Line = 2 X 0.5 = 1.5 jam / hr ( 17.30 )
- LW651 0.5 Jam/Org 1 Line = 2 X 0.5 = 1.5 jam / hr ( 17.30 )

2. Pengurangan time table


forming ( 2X )
- CW811 0.5 Jam/Org - Mempercepat proses kerja. Priyatno 12-06-17 0% 1 Line = 3 X 0.5 = 1.5 jam / hr ( 17.00 )
- CW895 0.5 Jam/Org - Menghilangkan gerakan sia - sia. Priyatno 12-06-17 50%
- LW645 0.5 Jam/Org - Mempercepat waktu isi 1 Line = 2 X 0.5 = 1 jam / hr ( 16.30 )
- LW952 0.5 Jam/Org - Mempercepat proses buka PT 1 Line = 2 X 0.5 = 1 jam / hr ( 16.30 )

Action Plan
No Thema CR Target PIC Kapan S/D Keterangan
4M1L

Peningkatan Effisiensi
- Type CW632, CW811 Up 20% - Perbaikan metode cek, tidak Marsono 12-06-17 0% - Ambil 1 orang DB.
banyak gosok.
- Perbaikan kwalitas body forming.

3. Mengurangi personil turun 2 Kama - Menyiapkan sarana dan prasarana Suyatno Awal Mei 100% - Habis kontrak tidak diperpanjang.
body kama ( posisi belakang ) ( 1 orang ) kerja di siang hari.

Pengurangan time table


- Type CW744 0.5 Jam/Org Sutrisno 12-06-17 0% 2 Line = 6 X 0.5 = 3 jam / hr ( 17.00 )
- Type CW 635 0.5 Jam/Org Suharno 15-06-17 0% 5 Line = 15 X 0.5 = 7.5 jam / hr ( 16.30 )

4. Peningkatan effisiensi periksa db

Type CW243 Up 20% - Perbaikan struktur ( case ). A. Rohman28-08-17 0% - 1 orang DB bisa diambil
Cost down material menghilangkan plat Tidak pakai plat - Perbaikan struktur kaki ( case ). 28-08-17 0%
bakar type CW243

Cek flushing Up 30 % 22-05-17 100% - Ambil 1 orang DB.