REKAPITULASI

RENCANA ANGGARAN BIAYA (RAB)

RENCANA ANGGARAN BIAYA Proyek : Pembangunan Penginapan Type 529 m


Pekerjaan : Pembangunan Penginapan Type 529 m
RAB
Lokasi : Mataram

REKAPITULASI

I PEKERJAAN FISIK Rp. #N/A

II PEKERJAAN MECHANICAL ELEKTRIKAL Rp. 331,293,256.00

GRAND TOTAL Rp #N/A


DIBULATKAN Rp ###
REKAPITULASI I
RENCANA ANGGARAN BIAYA (RAB) FISIK

RENCANA ANGGARAN BIAYA Proyek : Pembangunan Penginapan Type 529 m


Pekerjaan : Pembangunan Penginapan Type 529 m
RAB
Lokasi : Mataram

REKAPITULASI

I PEKERJAAN PENDAHULUAN Rp. 5,314,756.01

II PEKERJAAN TANAH & PASIR Rp. 10,869,063.37

III PEKERJAAN BETON


LANTAI 1 Rp. #N/A
LANTAI 2 Rp. #N/A
LANTAI 3 Rp. #N/A

IV PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN


LANTAI 1 Rp. 108,266,326.12
LANTAI 2 Rp. 70,235,397.55
LANTAI 3 Rp. 67,320,019.67

V PEKERJAAN KUSEN PINTU, JENDELA DAN KELENGKAPAN


LANTAI 1 Rp. #N/A
LANTAI 2 Rp. #N/A
LANTAI 3 Rp. #N/A

VI PEKERJAAN ATAP Rp. #N/A

VII PEKERJAAN LANTAI DAN PLAFON


LANTAI 1 Rp. 86,097,707.11
LANTAI 2 Rp. 89,275,852.97
LANTAI 3 Rp. 88,070,981.12

VIII PEKERJAAN FINISING DAN PENGECATAN Rp. 66,999,952.39

IX. PEKERJAAN SANITER Rp. 109,979,100.30

SUB JUMLAH I Rp #N/A


DIBULATKAN Rp ###
NOMOR HARGA
No. U RAIAN P E K E R JAAN VOLUME SAT SUB JUMLAH TOTAL
ANALISA SATUAN

I PEKERJAAN PENDAHULUAN
1 Pemasangan Bowplank 82.83 m1 A. 4 64,168.50 5,314,756.01 5,314,756.01

II PEKERJAAN TANAH & PASIR


1 Galian tanah pondasi 167.94 m3 B. 1 18,304.00 3,073,946.30
2 Urugan Tanah Kembali 83.97 m3 B. 9 8,771.40 736,527.88
3 Urugan Tanah Peninggi Lantai 33.50 m3 B.10 106,964.00 3,583,294.00
4 Urugan Pasir Di bawah Pondasi 12.13 m3 B.11 120,318.00 1,459,968.69
5 Urugan Pasir Dibawah Lantai 16.75 m3 B.11 120,318.00 2,015,326.50 10,869,063.37

III PEKERJAAN BETON


LANTAI 1
1 Rabat Lantai 16.75 m3 G. 1 544,405.95 9,118,799.66
2 Beton Foot Plat 1 0.41 m3 #N/A #N/A #N/A
3 Beton Foot Plat 2 3.83 m3 #N/A #N/A #N/A
4 Beton Foot Plat 3 0.64 m3 #N/A #N/A #N/A
5 Beton Foot Plat 4 15.30 m3 #N/A #N/A #N/A
6 Beton Sloof S1 20/40 4.00 m3 #N/A #N/A #N/A
7 Beton Sloof S2 20/40 0.00 m3 #N/A #N/A #N/A
8 Beton Kolom K1 14/75 Pedestal 0.63 m3 #N/A #N/A #N/A
9 Beton Kolom K2 30/100 Pedestal 3.00 m3 #N/A #N/A #N/A
10 Beton Kolom K3 14/100 Pedestal 0.56 m3 #N/A #N/A #N/A
11 Beton Kolom K4 30/200 Pedestal 14.40 m3 #N/A #N/A #N/A
12 Beton Kolom K1 14/75 1.10 m3 #N/A #N/A #N/A
13 Beton Kolom K2 18/100 3.15 m3 #N/A #N/A #N/A
14 Beton Kolom K3 14/100 0.98 m3 #N/A #N/A #N/A
15 Beton Kolom K4 18/200 15.12 m3 #N/A #N/A #N/A
16 Beton Kolom Praktis 1.72 m3 G.40.e 4,776,207.61 8,192,867.72
17 Balok Lantai (B1)20/40 2.14 m3 #N/A #N/A #N/A
18 Balok Lantai (B2)20/40 1.35 m3 #N/A #N/A #N/A
19 Balok Lantai (B3)20/30 2.64 m3 #N/A #N/A #N/A
20 Balok Latay 15/20 - m3 G.39.a 3,022,815.04 -
21 Plat Lantai 12 cm 12.24 m3 #N/A #N/A #N/A
22 Plat Tangga 3.24 m3 #N/A #N/A #N/A #N/A

LANTAI 2
1 Beton Kolom K1 14/75 1.10 m3 #N/A #N/A #N/A
2 Beton Kolom K2 18/100 3.15 m3 #N/A #N/A #N/A
3 Beton Kolom K3 14/100 0.98 m3 #N/A #N/A #N/A
4 Beton Kolom K4 18/200 15.12 m3 #N/A #N/A #N/A
5 Beton Kolom Praktis 1.83 m3 G.40.e 4,776,207.61 8,757,893.08
6 Balok Lantai (B1)20/40 - m3 #N/A #N/A #N/A
7 Balok Lantai (B2)20/40 - m3 #N/A #N/A #N/A
8 Balok Lantai (B3)20/30 - m3 #N/A #N/A #N/A
9 Balok Latay 15/20 - m3 G.39.a 3,022,815.04 -
11 Plat Lantai 12 cm 8.40 m3 #N/A #N/A #N/A
12 Plat Tangga 15 cm 4.05 m3 #N/A #N/A #N/A #N/A

LANTAI 3
1 Beton Kolom K1 14/75 1.10 m3 #N/A #N/A #N/A
2 Beton Kolom K2 18/100 10.71 m3 #N/A #N/A #N/A
3 Beton Kolom K3 14/100 0.98 m3 #N/A #N/A #N/A
4 Beton Kolom Praktis 1.77 m3 G.40.e 4,776,207.61 8,475,380.40
5 Balok Atap (BA1)20/40 - m3 #N/A #N/A #N/A
6 Balok Atap (BA2)20/40 - m3 #N/A #N/A #N/A
7 Plat Sunshiding 8 cm 0.51 m3 #N/A #N/A #N/A
8 Plat Lantai 10 cm 19.38 m3 #N/A #N/A #N/A #N/A

IV PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN


LANTAI 1
1 Pasangan Batu Kosong 24.27 m3 C.14 267,804.90 6,499,223.22
2 Pasangan Batu Kali 53.93 m3 C. 5 511,777.20 27,600,144.40
NOMOR HARGA
No. U RAIAN P E K E R JAAN VOLUME SAT SUB JUMLAH TOTAL
ANALISA SATUAN
3 Pasangan bata merah tebal bata. 1 Pc : 3 Ps 60.00 m2 D.10 75,386.96 4,523,217.60
4 Pasangan bata merah tebal bata. 1 Pc : 5 Ps 497.13 m2 D.12 70,265.42 34,930,820.91
5 Pelesteran 1 Pc : 3 Ps tebal 15 mm. 120.00 m2 E. 3 27,817.41 3,338,088.60
6 Pelesteran 1 Pc : 4 Ps tebal 15 mm. 844.25 m2 E. 5 25,521.43 21,546,559.15
7 Tali Air 84.48 m2 @ 2,000.00 168,960.00
8 Pasang Batu Alam Susun Sirih 10.00 m2 M.67.b 213,326.41 2,133,264.10
9 Pasang Batu Alam 33.00 m2 M.50.c 228,062.07 7,526,048.15
10 Pasangan Waterproofing 0.00 m2 E. 3 27,817.41 - 108,266,326.12

LANTAI 2
1 Pasangan bata merah tebal bata. 1 Pc : 3 Ps 60.00 m2 D.10 75,386.96 4,523,217.60
2 Pasangan bata merah tebal bata. 1 Pc : 5 Ps 512.88 m2 D.12 70,265.42 36,037,901.71
3 Pelesteran 1 Pc : 3 Ps tebal 15 mm. 120.00 m2 E. 3 27,817.41 3,338,088.60
4 Pelesteran 1 Pc : 4 Ps tebal 15 mm. 1,025.77 m2 E. 5 25,521.43 26,178,989.64
5 Pasang Batu Alam 0.00 m2 M.67.b 213,326.41 -
6 Tali Air 78.60 m2 @ 2,000.00 157,200.00
7 Pasangan Waterproofing 0.00 m2 E. 3 27,817.41 - 70,235,397.55

LANTAI 3
1 Pasangan bata merah tebal bata. 1 Pc : 3 Ps 51.00 m2 D.10 75,386.96 3,844,734.96
2 Pasangan bata merah tebal bata. 1 Pc : 5 Ps 459.76 m2 D.12 70,265.42 32,305,121.80
3 Pelesteran 1 Pc : 3 Ps tebal 15 mm. 102.00 m2 E. 3 27,817.41 2,837,375.31
4 Pelesteran 1 Pc : 4 Ps tebal 15 mm. 919.52 m2 E. 5 25,521.43 23,467,388.75
5 Pasang Batu Alam 0.00 m2 M.67.b 213,326.41 -
6 Tali Air 68.22 m2 @ 2,000.00 136,440.00
7 Pasangan Waterproofing 170.00 m2 E. 3 27,817.41 4,728,958.85 67,320,019.67

V PEKERJAAN KUSEN PINTU, JENDELA DAN KELENGKAPAN


LANTAI 1
1 Kusen Pintu Dan Jendela 0.54 m3 F. 1 10,180,280.00 5,533,267.23
2 Daun Pintu 19.33 m2 F. 7 435,517.50 8,417,900.00
3 Daun Jendela 3.80 m2 F. 2 340,697.50 1,294,650.50
5 Roster Kayu 0.00 m3 -
6 Pintu Aluminium PJ1 1.00 unit @ 7,500,000.00 7,500,000.00
7 Hendel Pintu 11.00 bh #N/A #N/A #N/A
8 Kunci Pintu 11.00 bh L. 3 270,935.50 2,980,290.50
9 Engsel Pintu 7.50 set L. 5 41,813.20 313,599.00
10 Expanolet 0.00 set L.11.a 63,817.60 -
11 Rel Geser 6.00 set @ 750,000.00 4,500,000.00
12 Engsel Jendela 4.00 set L. 6 27,508.80 110,035.20
13 Grendel Jendela 4.00 bh L.11 34,667.60 138,670.40
14 Hak Angin 8.00 bh L. 9 24,763.20 198,105.60 #N/A

LANTAI 2
1 Kusen Pintu Dan Jendela 0.51 m3 F. 1 10,180,280.00 5,160,180.33
2 Daun Pintu 17.63 m2 F. 7 435,517.50 7,678,173.53
3 Daun Jendela 3.80 m2 F. 2 340,697.50 1,294,650.50
4 Roster Kayu - m3 -
5 Pintu Aluminium P3 1.00 unit @ 6,500,000.00 6,500,000.00
6 Jendela Aluinium J2 1.00 unit @ 7,000,000.00 7,000,000.00
7 Hendel Pintu 10.00 bh #N/A #N/A #N/A
8 Kunci Pintu 10.00 bh L. 3 270,935.50 2,709,355.00
9 Engsel Pintu 7.50 set L. 5 41,813.20 313,599.00
10 Expanolet 0.00 set L.11.a 63,817.60 -
11 Rel Geser 5.00 set @ 750,000.00 3,750,000.00
12 Engsel Jendela 4.00 set L. 6 27,508.80 110,035.20
13 Grendel Jendela 4.00 bh L.11 34,667.60 138,670.40
14 Hak Angin 8.00 bh L. 9 24,763.20 198,105.60 #N/A

LANTAI 3
1 Kusen Pintu Dan Jendela 0.40 m3 F. 1 10,180,280.00 4,032,123.86
2 Daun Pintu 12.28 m2 F. 7 435,517.50 5,346,630.59
3 Daun Jendela 3.80 m2 F. 2 340,697.50 1,294,650.50
4 Pintu Aluminium P3 1.00 unit @ 6,500,000.00 6,500,000.00
NOMOR HARGA
No. U RAIAN P E K E R JAAN VOLUME SAT SUB JUMLAH TOTAL
ANALISA SATUAN
5 Pintu Aluminium P5 1.00 unit @ 4,500,000.00 4,500,000.00
6 Jendela Aluminium J3 1.00 unit @ 4,500,000.00 4,500,000.00
7 Roster Kayu - m3 -
8 Hendel Pintu 9.00 bh #N/A #N/A #N/A
9 Kunci Pintu 9.00 bh L. 3 270,935.50 2,438,419.50
10 Engsel Pintu 4.50 set L. 5 41,813.20 188,159.40
11 Expanolet 2.00 set L.11.a 63,817.60 127,635.20
12 Rel Geser 4.00 set @ 750,000.00 3,000,000.00
13 Engsel Jendela 4.00 set L. 6 27,508.80 110,035.20
14 Grendel Jendela 4.00 bh L.11 34,667.60 138,670.40
15 Hak Angin 8.00 bh L. 9 24,763.20 198,105.60 #N/A

VI PEKERJAAN ATAP

VII PEKERJAAN LANTAI DAN PLAFON


LANTAI 1
1 Rangka Plafon 167.50 m2 F.42 161,232.50 27,006,443.75
2 Penutup Plafon Gypsum Board 167.50 m2 I.24 89,034.55 14,913,287.13
3 Pasang Lis Gypsum C7 211.00 m1 I.25.a 27,472.50 5,796,697.50
4 Pasangan Keramik Lantai 40x40 152.00 m2 M.48.b 179,941.41 27,351,094.32
5 Pasangan Keramik Dinding km/wc 30 x 50 42.75 m2 M.68.a 191,440.37 8,184,075.82
6 Pasangan Batu Koral Sikat 4.00 m2 M.71.b 172,058.10 688,232.38
7 Pasangan Keramik Lantai km/wc 20 x 20 11.50 m2 M.44 187,641.41 2,157,876.22 86,097,707.11

LANTAI 2
1 Rangka Plafon 172.00 m2 F.42 161,232.50 27,731,990.00
2 Penutup Plafon Gypsum Board 172.00 m2 I.24 89,034.55 15,313,942.60
3 Pasang Lis Gypsum C7 212.50 m1 I.25.a 27,472.50 5,837,906.25
4 Pasangan Keramik Lantai 40x40 157.00 m2 M.48.b 179,941.41 28,250,801.37
5 Pasangan Keramik Dinding km/wc 30 x 50 49.13 m2 M.68.a 191,440.37 9,404,508.18
6 Pasangan Batu Koral Sikat 5.00 m2 M.71.b 172,058.10 860,290.48
7 Pasangan Keramik Lantai km/wc 20 x 20 10.00 m2 M.44 187,641.41 1,876,414.10 89,275,852.97

LANTAI 3
1 Rangka Plafon 171.00 m2 F.42 161,232.50 27,570,757.50
2 Penutup Plafon Gypsum Board 171.00 m2 I.24 89,034.55 15,224,908.05
3 Pasang Lis Gypsum C7 192.00 m1 I.25.a 27,472.50 5,274,720.00
4 Pasangan Keramik Lantai 40x40 158.00 m2 M.48.b 179,941.41 28,430,742.78
5 Pasangan Keramik Dinding km/wc 20 x 25 43.20 m2 M.68.a 191,440.37 8,270,223.98
6 Pasangan Batu Koral Sikat 5.00 m2 M.71.b 172,058.10 860,290.48
7 Pasangan Keramik Lantai km/wc 20 x 20 13.00 m2 M.44 187,641.41 2,439,338.33 88,070,981.12

VIII PEKERJAAN FINISING DAN PENGECATAN


1 Cat Tembok Interior 3,131.54 m2 N.14.b 15,569.13 48,755,269.20
2 Cat Tembok Exterior 63.00 m2 N.14.a 42,241.93 2,661,241.28
3 Pengecatan Plafon Gypsum 510.50 m2 N.14.b 15,569.13 7,948,038.31
4 Cat Kusen + Daun 215.20 m2 N. 8 35,480.50 7,635,403.60
5 Cat Lisplank 0.00 m2 N. 8 35,480.50 - 66,999,952.39

IX. PEKERJAAN SANITER


1 Closed Duduk 13.00 unit J. 3 2,721,369.75 35,377,806.75
2 Closed Jongkok 0.00 unit J. 2 411,244.35 -
Wastafel Meja 13.00 unit J. 5 1,753,288.35 22,792,748.55
4 Wastafel Gantung 0.00 unit @ 2,500,000.00 -
5 Sink tunggal 0.00 unit @ 350,000.00 -
6 Tempat Sabun 14.00 unit @ 75,000.00 1,050,000.00
7 Kran km/wc 15.00 unit @ 125,000.00 1,875,000.00
8 Kran sink tunggal 0.00 unit @ 250,000.00 -
9 Floor Drain 15.00 unit J.36 56,903.00 853,545.00
10 Roof Drain 2.00 unit @ 65,000.00 130,000.00
11 Septiktank 2.00 unit @ 3,500,000.00 7,000,000.00
12 Sumur Resapan 1.00 unit @ 3,000,000.00 3,000,000.00
13 Bak Kontrol 5.00 unit @ 2,500,000.00 12,500,000.00
14 Shower 13.00 unit @ 1,800,000.00 23,400,000.00
NOMOR HARGA
No. U RAIAN P E K E R JAAN VOLUME SAT SUB JUMLAH TOTAL
ANALISA SATUAN
15 Bathup 1.00 unit @ 2,000,000.00 2,000,000.00 109,979,100.30
No. U RAIAN P E K E R JAAN VOLUME SAT

I PEKERJAAN PENDAHULUAN
1 1 Pemasangan Bowplank 134.83 m1
Balok Kayu Klas III 1.62 m
Paku Pjg 4-6 Cm 2.70 Kg
Papan Kayu Klas III 0.94 m

Tukang Kayu 13.48 OH


Pekerja 13.48 OH
Kepala Tukang Kayu 1.35 OH
Mandor 0.67 OH

II PEKERJAAN TANAH & PASIR


3 1 Galian tanah pondasi 167.94 m3
Pekerja 67.18 OH
Tukang Gali - OH
Kepala Tukang Gali - OH
Mandor 6.72 OH

4 2 Urugan Tanah Kembali 83.97 m3


Pekerja 16.12 OH
Tukang Gali - OH
Kepala Tukang Gali - OH
Mandor 1.60 OH
5 3 Urugan Tanah Peninggi Lantai 33.50 m3
Tanah Urug Biasa 40.20 m

Pekerja 16.75 OH
Tukang Gali - OH
Kepala Tukang Gali - OH
Mandor 1.68 OH

6 4 Urugan Pasir Di bawah Pondasi 12.13 m3


Pasir Pasang 14.56 m

Pekerja 3.64 OH
Tukang Gali - OH
Kepala Tukang Gali - OH
Mandor 0.12 OH

6 5 Urugan Pasir Dibawah Lantai 16.75 m3


Pasir Pasang 20.10 m

Pekerja 5.03 OH
Tukang Gali - OH
Kepala Tukang Gali - OH
Mandor 0.17 OH

III PEKERJAAN BETON


60 1 Rabat Lantai 16.75 m3
Semen Portland 3,651.50 Kg
Pasir Ayak Untuk Beton 8.71 m
Kerikil Alam 2/3 Cm 14.57 m

Pekerja 27.64 OH
Tukang Batu 4.19 OH
Kepala Tukang Batu 0.42 OH
Mandor 1.34 OH

68c 2 Beton Foot Plat 0.41 m3


Beton K 175 0.41 m3
Semen Portland 136.08 Kg
Pasir Ayak Untuk Beton 0.22 m
Batu Pecah 2-3 Cm (Pecah Mesin) 0.33 m

Pekerja 0.67 OH
Tukang Batu 0.10 OH
Kepala Tukang Batu 0.01 OH
Mandor 0.03 OH

Besi Beton 67.43 kg


Besi Beton Polos 70.81 Kg
Besi 14 1.80 Btg
Besi 12 3.00 Btg
Kawat Ikat Beton 1.01 Kg

Pekerja 0.47 OH
Tukang Besi 0.47 OH
Kepala Tukang Besi 0.05 OH
Mandor 0.02 OH

Begisting Pondasi 2.31 m2


Papan Kayu Klas III 0.09 m
Paku Pjg 7-12 Cm 0.69 m
Minyak Begisting 0.23 m

Pekerja 0.69 m
Tukang Kayu 0.60 m
Kepala Tukang Kayu 0.06 m
Mandor 0.01 m

69 3 Beton Sloof Praktis 15/20 4.00 m3


Papan Kayu Klas III 1.08 m
Paku Pjg 7-12 Cm 8.00 Kg
Minyak Begisting - ltr
Besi Beton Polos 554.11 Kg
Besi 8 60.29 btg
Besi 6 72.46 btg
Kawat Ikat Beton 12.00 Kg
Semen Portland 1,292.00 Kg
Pasir Ayak Untuk Beton 2.08 m
Kerikil Alam 2/3 Cm 3.12 m

Pekerja 19.40 OH
Tukang Batu 1.40 OH
Tukang Kayu 6.24 OH
Tukang Besi 5.60 OH
Kepala Tukang Batu 1.32 OH
Mandor 0.68 OH

71 4 Beton Kolom Praktis 13/13 1.72 m3


Papan Kayu Klas III 0.69 m
Paku Pjg 7-12 Cm 6.86 Kg
Minyak Begisting - ltr
Besi Beton Polos 314.45 Kg
Besi 8 63.40 btg
Besi 6 46.84 btg
Kawat Ikat Beton 7.72 Kg
Semen Portland 554.06 Kg
Pasir Ayak Untuk Beton 0.89 m
Kerikil Alam 2/3 Cm 1.34 m
Balok Kayu Klas III 0.26 m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja 12.52 OH
Tukang Batu 0.60 OH
Tukang Kayu 5.66 OH
Tukang Besi 3.60 OH
Kepala Tukang Batu 0.98 OH
Mandor 0.43 OH

69c 5 Beton Kolom Kolom 20/20 3.15 m3


Beton K 175 3.15 m3
Semen Portland 1,058.40 Kg
Pasir Ayak Untuk Beton 1.70 m
Batu Pecah 2-3 Cm (Pecah Mesin) 2.55 m
Pekerja 5.20 OH
Tukang Batu 0.79 OH
Kepala Tukang Batu 0.08 OH
Mandor 0.25 OH

Besi Beton 1,100.00 kg


Besi Beton Polos 1,155.00 Kg
Besi 14 13.70 btg
Besi 8 13.82 btg
Kawat Ikat Beton 16.50 Kg

Pekerja 7.70 Kg
Tukang Besi 7.70 Kg
Kepala Tukang Besi 0.77 Kg
Mandor 0.33 Kg

Begisting Kolom 63.00 m2


Papan Kayu Klas III 2.52 m
Balok Kayu Klas II 0.95 m
Tripleks 122 X 242 X 9 mm 22.05 lmbr
Dolken dia. 10 Cm - 4 m 126.00 btng
Paku Pjg 7-12 Cm 25.20 Kg
Minyak Begisting 12.60 ltr

Pekerja 18.90 OH
Tukang Kayu 20.79 OH
Kepala Tukang Kayu 2.08 OH
Mandor 0.38 OH
69b 6 Beton Kolom Kolom 25/25 1.10 m3
Beton K 175 1.10 m3
Semen Portland 370.44 Kg
Pasir Ayak Untuk Beton 0.60 m
Batu Pecah 2-3 Cm (Pecah Mesin) 0.89 m

Pekerja 1.82 OH
Tukang Batu 0.28 OH
Kepala Tukang Batu 0.03 OH
Mandor 0.09 OH

Besi Beton 260.32 kg


Besi Beton Polos 273.34 Kg
Besi 14 14.09 btg
Besi 8 10.47 btg
Kawat Ikat Beton 3.90 Kg

Pekerja 1.82 OH
Tukang Besi 1.82 OH
Kepala Tukang Besi 0.18 OH
Mandor 0.08 OH

Begisting Kolom 17.64 m2


Papan Kayu Klas III 0.71 m
Balok Kayu Klas II 0.26 m
Tripleks 122 X 242 X 9 mm 6.17 m
Dolken dia. 10 Cm - 4 m 35.28 m
Paku Pjg 7-12 Cm 7.06 m
Minyak Begisting 3.53 m
Pekerja 5.29 m
Tukang Kayu 5.82 m
Kepala Tukang Kayu 0.58 m
Mandor 0.11 m

69c 7 Beton Kolom Kolom 20/20 elv. 7.20 m 0.98 m3


Beton K 175 0.98 m3
Semen Portland 329.28 ltr
Pasir Ayak Untuk Beton 0.53 m
Batu Pecah 2-3 Cm (Pecah Mesin) 0.79 lmbr

Pekerja 1.62 -
Tukang Batu 0.25 OH
Kepala Tukang Batu 0.02 OH
Mandor 0.08 OH

Besi Beton 342.22 kg


Besi Beton Polos 359.33 Kg
Besi 14 4.26 btg
Besi 8 4.30 btg
Kawat Ikat Beton 5.13 Kg

Pekerja 2.40 OH
Tukang Besi 2.40 OH
Kepala Tukang Besi 0.24 OH
Mandor 0.10 OH
Begisting Kolom 19.60 m2
Papan Kayu Klas III 0.78 m
Balok Kayu Klas II 0.29 m
Tripleks 122 X 242 X 9 mm 6.86 lmbr
Dolken dia. 10 Cm - 4 m 39.20 btng
Paku Pjg 7-12 Cm 7.84 Kg
Minyak Begisting 3.92 ltr

Pekerja 5.88 OH
Tukang Kayu 6.47 OH
Kepala Tukang Kayu 0.65 OH
Mandor 0.12 OH

72c 8 Beton Balok Lantai/Dak 15/25 2.14 m3


Beton K 175 2.14 m3
Semen Portland 718.20 ltr
Pasir Ayak Untuk Beton 1.15 m
Batu Pecah 2-3 Cm (Pecah Mesin) 1.73 lmbr

Pekerja 3.53 -
Tukang Batu 0.53 OH
Kepala Tukang Batu 0.05 OH
Mandor 0.17 OH

Besi Beton 684.59 kg


Besi Beton Polos 718.82 Kg
Besi 14 26.60 btg
Besi 8 22.46 btg
Kawat Ikat Beton 10.27 Kg
Pekerja 4.79 OH
Tukang Besi 4.79 OH
Kepala Tukang Besi 0.48 OH
Mandor 0.21 OH

Begisting Balok 31.35 m2


Papan Kayu Klas III 1.25 m
Paku Pjg 7-12 Cm 12.54 Kg
Minyak Begisting 6.27 ltr
Balok Kayu Klas II 0.56 m
Tripleks 122 X 242 X 9 mm 10.97 lmbr
Dolken dia. 10 Cm - 4 m 62.70 btng

Pekerja 10.03 OH
Tukang Kayu 10.35 OH
Kepala Tukang Kayu 1.03 OH
Mandor 0.19 OH

Dolken dia. 10 Cm - 4 m 166.73 btng

70 9 Beton Balok Sunshiding 12/15 1.35 m3


Papan Kayu Klas III 0.36 m
Paku Pjg 7-12 Cm 2.70 Kg
Minyak Begisting - ltr
Besi Beton Polos 207.90 Kg
Besi 8 32.61
Besi 6 23.48
Kawat Ikat Beton 4.05 Kg
Semen Portland 436.05 Kg
Pasir Ayak Untuk Beton 0.70 m
Kerikil Alam 2/3 Cm 1.05 m

Pekerja 6.55 OH
Tukang Batu 0.47 OH
Tukang Kayu 2.11 OH
Tukang Besi 1.89 OH
Kepala Tukang Batu 0.45 OH
Mandor 0.23 OH

72c 10 Beton Ring Balok 15/25 elv. 4.85 2.64 m3


Beton K 175 2.64 m3
Semen Portland 888.30 ltr
Pasir Ayak Untuk Beton 1.43 m
Batu Pecah 2-3 Cm (Pecah Mesin) 2.14 lmbr

Pekerja 4.36 -
Tukang Batu 0.66 OH
Kepala Tukang Batu 0.07 OH
Mandor 0.21 OH

Besi Beton 846.73 kg


Besi Beton Polos 889.07 Kg
Besi 14 32.90 btg
Besi 8 27.78 btg
Kawat Ikat Beton 12.70 Kg

Pekerja 5.93 OH
Tukang Besi 5.93 OH
Kepala Tukang Besi 0.59 OH
Mandor 0.25 OH

Begisting Balok 38.78 m2


Papan Kayu Klas III 1.55 m
Paku Pjg 7-12 Cm 15.51 Kg
Minyak Begisting 7.76 ltr
Balok Kayu Klas II 0.70 m
Tripleks 122 X 242 X 9 mm 13.57 lmbr
Dolken dia. 10 Cm - 4 m 77.55 btng

Pekerja 12.41 OH
Tukang Kayu 12.80 OH
Kepala Tukang Kayu 1.28 OH
Mandor 0.23 OH

Dolken dia. 10 Cm - 4 m 206.21 btng

72c 11 Beton Ring Balok 15/25 elv. 7.20 - m3


Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr

Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - kg
Besi Beton Polos - Kg
Besi 14 - btg
Besi 8 - btg
Kawat Ikat Beton - Kg

Pekerja - OH
Tukang Besi - OH
Kepala Tukang Besi - OH
Mandor - OH

Begisting Balok - m2
Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - Kg
Minyak Begisting - ltr
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH

Dolken dia. 10 Cm - 4 m - -

72c 12 Beton Balok Tangga 15/20 - m3


Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr
Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - kg
Besi Beton Polos - Kg
Besi 14 -
Besi 8 -
Kawat Ikat Beton - Kg

Pekerja - OH
Tukang Besi - OH
Kepala Tukang Besi - OH
Mandor - OH

Begisting Balok - m2
Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - Kg
Minyak Begisting - ltr
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH
Dolken dia. 10 Cm - 4 m - -

75b 13 Beton Plat Talang 10 cm - m3


Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr

Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - kg
Besi Beton Polos - Kg
Besi 8 - btg
Kawat Ikat Beton - Kg

Pekerja - OH
Tukang Besi - OH
Kepala Tukang Besi - OH
Mandor - OH

Begisting Plat Lantai - m2


Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - m
Minyak Begisting - m
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - m
Dolken dia. 10 Cm - 4 m - m
Pekerja - m
Tukang Kayu - m
Kepala Tukang Kayu - m
Mandor - m

Dolken dia. 10 Cm - 4 m - btng

75b 14 Beton Plat Sunshiding 10 cm - m3


Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr

Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - ltr


Besi Beton Polos - -
Besi 8 - btg
Kawat Ikat Beton - -

Pekerja - m
Tukang Besi - m
Kepala Tukang Besi - lmbr
Mandor - btng
Begisting Plat Lantai - Kg
Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - Kg
Minyak Begisting - ltr
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH

Dolken dia. 10 Cm - 4 m - Kg

75a 15 Beton Plat Lantai 12 cm 12.24 m3


Beton K 175 12.24 m3
Semen Portland 4,112.64 ltr
Pasir Ayak Untuk Beton 6.61 m
Batu Pecah 2-3 Cm (Pecah Mesin) 9.91 lmbr

Pekerja 20.20 -
Tukang Batu 3.06 OH
Kepala Tukang Batu 0.31 OH
Mandor 0.98 OH

Besi Beton 1,673.06 kg


Besi Beton Polos 1,756.71 Kg
Besi 8 368.70 btg
Kawat Ikat Beton 25.10 ltr

Pekerja 11.71 btng


Tukang Besi 11.71 -
Kepala Tukang Besi 1.17 -
Mandor 0.50 OH

Begisting Plat Lantai 102.00 m2


Papan Kayu Klas III 4.08 m
Paku Pjg 7-12 Cm 40.80 Kg
Minyak Begisting 20.40 ltr
Balok Kayu Klas II 1.53 m
Tripleks 122 X 242 X 9 mm 35.70 lmbr
Dolken dia. 10 Cm - 4 m 612.00 btng
- -

Pekerja 32.64 OH
Tukang Kayu 33.66 OH
Kepala Tukang Kayu 3.37 OH
Mandor 0.61 OH

Dolken dia. 10 Cm - 4 m 612.00 btng

75b 16 Beton Plat Dak 10 cm elv. 3.50 - m3


Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr

Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - -
Besi Beton Polos - Kg
Besi 8 - btg
Kawat Ikat Beton - ltr

Pekerja - btng
Tukang Besi - -
Kepala Tukang Besi - -
Mandor - OH

Begisting Plat Lantai - -


Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - Kg
Minyak Begisting - ltr
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH

Dolken dia. 10 Cm - 4 m - -
75b 17 Beton Plat Dak 10 cm elv. 7.20 - m3
Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr

Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - -
Besi Beton Polos - m3
Besi 8 - btg
Kawat Ikat Beton - kg

Pekerja - -
Tukang Besi - -
Kepala Tukang Besi - -
Mandor - -

Begisting Plat Lantai - OH


Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - Kg
Minyak Begisting - ltr
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH

Dolken dia. 10 Cm - 4 m - OH

75b 18 Beton Plat Meja 10 cm - m3


Beton K 175 - m3
Semen Portland - ltr
Pasir Ayak Untuk Beton - m
Batu Pecah 2-3 Cm (Pecah Mesin) - lmbr

Pekerja - -
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

Besi Beton - -
Besi Beton Polos - m3
Besi 8 - btg
Kawat Ikat Beton - kg

Pekerja - -
Tukang Besi - -
Kepala Tukang Besi - -
Mandor - -

Begisting Plat Lantai - OH


Papan Kayu Klas III - m
Paku Pjg 7-12 Cm - Kg
Minyak Begisting - ltr
Balok Kayu Klas II - m
Tripleks 122 X 242 X 9 mm - lmbr
Dolken dia. 10 Cm - 4 m - btng

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH

Dolken dia. 10 Cm - 4 m - OH

75a 19 Beton Plat Tangga 15 cm 3.24 m3


Beton K 175 3.24 m3
Semen Portland 1,088.64 ltr
Pasir Ayak Untuk Beton 1.75 m
Batu Pecah 2-3 Cm (Pecah Mesin) 2.62 lmbr

Pekerja 5.35 -
Tukang Batu 0.81 OH
Kepala Tukang Batu 0.08 OH
Mandor 0.26 OH

Besi Beton 442.87 kg


Besi Beton Polos 465.01 Kg
Kawat Ikat Beton 6.64 ltr

Pekerja 3.10 btng


Tukang Besi 3.10 -
Kepala Tukang Besi 0.31 -
Mandor 0.13 OH

Begisting Plat Lantai 27.00 m2


Papan Kayu Klas III 1.08 m
Paku Pjg 7-12 Cm 10.80 Kg
Minyak Begisting 5.40 ltr
Balok Kayu Klas II 0.41 m
Tripleks 122 X 242 X 9 mm 9.45 lmbr
Dolken dia. 10 Cm - 4 m 162.00 btng

Pekerja 8.64 OH
Tukang Kayu 8.91 OH
Kepala Tukang Kayu 0.89 OH
Mandor 0.16 OH

Dolken dia. 10 Cm - 4 m 162.00 btng

IV PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN


11 1 Pasangan Batu Kosong 24.27 m3
Batu Kali Belah 29.12 m
Pasir Urug 7.28 m

Pekerja 18.93 OH
Tukang Batu 9.46 OH
Kepala Tukang Batu 0.95 OH
Mandor 0.95 OH
9 2 Pasangan Batu Kali 53.93 m3
Batu Kali Belah 59.32 m
Semen Portland 8,790.59 Kg
Pasir Pasang 28.04 m

Pekerja 80.90 OH
Tukang Batu 32.36 OH
Kepala Tukang Batu 3.24 OH
Mandor 4.04 OH

16 3 Pasangan bata merah tebal bata. 1 Pc : 3 Ps 60.00 m2


Bata Merah Klas I 4,200.00 bh
Semen Portland 862.20 Kg
Pasir Pasang 2.40 m

Pekerja 19.20 OH
Tukang Batu 6.00 OH
Kepala Tukang Batu 0.60 OH
Mandor 0.90 OH

17 4 Pasangan bata merah tebal bata. 1 Pc : 5 Ps 497.13 m2


Bata Merah Klas I 34,798.88 bh
Semen Portland 4,812.19 Kg
Pasir Pasang 22.37 m

Pekerja 159.08 OH
Tukang Batu 49.71 OH
Kepala Tukang Batu 4.97 OH
Mandor 7.46 OH
24 5 Pelesteran 1 Pc : 3 Ps tebal 15 mm. 120.00 m2
Semen Portland 777.60 Kg
Pasir Pasang 2.28 m

Pekerja 24.00 OH
Tukang Batu 18.00 OH
Kepala Tukang Batu 1.80 OH
Mandor 1.20 OH

25 6 Pelesteran 1 Pc : 4 Ps tebal 15 mm. 994.25 m2


Semen Portland 4,295.18 Kg
Pasir Pasang 21.87 m

Pekerja 198.85 OH
Tukang Batu 149.14 OH
Kepala Tukang Batu 14.91 OH
Mandor 9.94 OH

24x 7 Plesteran Acian Gurat - m2


Semen Portland - Kg
Pasir Pasang - m
Benangan - m'

Pekerja - OH
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH

24 8 Pasangan Waterproofing 26.74 m2


Semen Portland 173.26 Kg
Pasir Pasang 0.51 m

Pekerja 5.35 OH
Tukang Batu 4.01 OH
Kepala Tukang Batu 0.40 OH
Mandor 0.27 OH

V PEKERJAAN KUSEN PINTU, JENDELA DAN KELENGKAPAN


28 1 Kusen Pintu Dan Jendela 0.54 m3
Balok Kayu Klas I 0.60 m

Pekerja 3.26 OH
Tukang Kayu 10.87 OH
Kepala Tukang Kayu 1.09 OH
Mandor 0.16 OH

30 2 Daun Pintu 19.33 m2


Papan Kayu Klas I 0.77 m

Pekerja 19.33 OH
Tukang Kayu 48.32 OH
Kepala Tukang Kayu 4.83 OH
Mandor 0.97 OH
29 3 Daun Jendela 3.80 m2
Balok Kayu Klas II 0.07 m
Paku Pjg 1-3 Cm 0.30 Kg
Kaca Polos t=5 mm 3.65 m

Pekerja 1.90 OH
Tukang Kayu 5.70 OH
Kepala Tukang Kayu 0.57 OH
Mandor 0.10 OH

4 Pintu Super Vinil 5.00 Unit

124 5 Kaca S - m2
Kaca Polos t=5 mm - m

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH

A 6 Hendel Pintu Dobel 2.00 bh


Handle Double Klas Menengah 2.00 bh

Pekerja 0.02 OH
Tukang Kayu 1.00 OH
Kepala Tukang Kayu 0.02 OH
Mandor 0.01 OH

116 7 Kunci Pintu 11.00 bh


Kunci Tanam 2 Slag Klas Menengah 11.00 bh

Pekerja 0.11 OH
Tukang Kayu 5.50 OH
Kepala Tukang Kayu 0.11 OH
Mandor 0.06 OH

117 8 Engsel Pintu 7.50 set


Engsel Pintu Klas Tinggi 7.50 set

Pekerja 0.11 OH
Tukang Kayu 1.13 OH
Kepala Tukang Kayu 0.11 OH
Mandor 0.01 OH

122 9 Espayolet - set


Expanolet Klas Tinggi - set

Pekerja - OH
Tukang Kayu - OH
Kepala Tukang Kayu - OH
Mandor - OH
118 10 Engsel Jendela 4.00 set
Engsel Jendela Klas Tinggi 4.00 set

Pekerja 0.04 OH
Tukang Kayu 0.40 OH
Kepala Tukang Kayu 0.04 OH
Mandor 0.00 OH

119 11 Hak Angin Jendela 8.00 bh


Hak Angin Besar 8.00 bh

Pekerja 0.12 OH
Tukang Kayu 1.20 OH
Kepala Tukang Kayu 0.12 OH
Mandor 0.01 OH

121 12 Grendel Jendela 4.00 bh


Grendel Besar 4.00 bh

Pekerja 0.08 OH
Tukang Kayu 0.80 OH
Kepala Tukang Kayu 0.08 OH
Mandor 0.00 OH

VI PEKERJAAN ATAP
1 Rangka Atap Baja Ringan 36.00 m2
94d 2 Penutup Atap Genteng Glazur 67.71 m2
Genteng Keramik (Warna Natural) 744.76 bh
Paku Pjg 4-6 Cm 2.03 Kg

Pekerja 13.54 OH
Tukang Kayu 6.77 OH
Kepala Tukang Kayu 0.68 OH
Mandor 0.68 OH

94e 3 Bubungan Atap Genteng Glazur 17.43 m1


Bubungan Genteng Keramik Keramik 61.00 bh
Paku Pjg 4-6 Cm 0.87 Kg
Semen Portland 188.24 Kg
Pasir Pasang 0.56 m
Semen Warna 17.43 Kg

Pekerja 6.97 OH
Tukang Kayu 3.49 OH
Kepala Tukang Kayu 0.35 OH
Mandor 0.35 OH

94a 4 Besi Kisi-Kisi Hollo 50x50x2 - kg


Baja profil - kg
mesin gergaji - jam
mata gergaji - bh
mesin bor - jam
Mata bor - bh
Listrik - Kwh

Kepala Tukang Las - OH


Tukang Las - OH
Pekerja - OH

52 5 Lisplank Kayu Klas I 9.19 m2


Papan Kayu Klas I 0.13 m
Paku Pjg 7-12 Cm 0.55 Kg

Pekerja 1.38 OH
Tukang Kayu 2.30 OH
Kepala Tukang Kayu 0.23 OH
Mandor 0.69 OH

VII PEKERJAAN LANTAI DAN PLAFON


47 1 Rangka Plafon 167.50 m2
Balok Kayu Klas I 2.01 m
Paku Pjg 7-12 Cm 16.75 Kg

Pekerja 16.75 OH
Tukang Kayu 16.75 OH
Kepala Tukang Kayu 1.68 OH
Mandor 0.84 OH

96 2 Penutup Plafon Gypsum Board 167.50 m2


Gypsumboard (120x240x9) mm 60.97 lmbr
Paku Pjg 4-6 Cm 18.43 Kg

Pekerja 16.75 OH
Tukang Kayu 8.38 OH
Kepala Tukang Kayu 0.84 OH
Mandor 0.84 OH

99 3 Pasang Lis Gypsum C7 211.00 m1


Profil Beton 4/11 221.76 m'

Pekerja 4.43 OH
Tukang Kayu 4.43 OH
Kepala Tukang Kayu 0.63 OH
Mandor 0.21 OH

129 4 Pasangan Keramik Lantai 40x40 152.00 m2


Keramik Lantai Warna Klas Tinggi 152.00 m
Semen Portland 1,729.76 Kg
Pasir Pasang 6.38 m
Semen Warna 228.00 Kg

Pekerja 94.24 OH
Tukang Batu 53.20 OH
Kepala Tukang Batu 5.32 OH
Mandor 4.56 OH

126 5 Pasangan Keramik Lantai 20 x 20 4.00 m2


Keramik Lantai Bermotif Klas Tinggi 4.00 m
Semen Portland 45.52 Kg
Pasir Pasang 0.17 m
Semen Warna 6.00 Kg
Pekerja 2.48 OH
Tukang Batu 1.40 OH
Kepala Tukang Batu 0.14 OH
Mandor 0.12 OH

138 6 Pasangan Keramik Dinding 20 x 25 42.75 m2


Keramik Dinding Warna Klas Tinggi 42.75 m
Semen Portland 397.58 Kg
Pasir Pasang 0.77 m
Semen Warna 64.13 Kg

Pekerja 25.65 OH
Tukang Batu 4.28 OH
Kepala Tukang Batu 1.92 OH
Mandor 1.28 OH

126 7 Pasangan Keramik Meja Dapur 20 x 20 - m2


Keramik Lantai Bermotif Klas Tinggi - m
Semen Portland - Kg
Pasir Pasang - m
Semen Warna - Kg

Pekerja - OH
Tukang Batu - OH
Kepala Tukang Batu - OH
Mandor - OH
VIII PEKERJAAN FINISING DAN PENGECATAN
144 1 Cat Tembok Interior 1,114.25 m2
Plamir Tembok 167.14 Kg
Cat Tembok Mutu Tinggi 189.42 Kg
Cat Tembok Mutu Tinggi 289.71 Kg

Pekerja 22.29 OH
Tukang Cat 70.20 OH
Kepala Tukang Cat 7.02 OH
Mandor 2.79 OH

145 2 Cat Tembok Exterior 63.00 m2


Plamir Tembok 10.71 Kg
Cat Tembok Eksterior 10.71 Kg
Cat Tembok Eksterior 16.38 Kg

Pekerja 1.26 OH
Tukang Cat 3.97 OH
Kepala Tukang Cat 0.40 OH
Mandor 0.16 OH

144 3 Pengecatan Plafon Gypsum 167.50 m2


Plamir Tembok 25.13 Kg
Cat Tembok Mutu Tinggi 28.48 Kg
Cat Tembok Mutu Tinggi 43.55 Kg

Pekerja 3.35 OH
Tukang Cat 10.55 OH
Kepala Tukang Cat 1.06 OH
Mandor 0.42 OH

140 4 Cat Kusen + Daun 77.81 m2


Meni Kayu 15.56 Kg
Plamir Kayu 11.67 Kg
Cat Kayu Klas Menengah 13.23 Kg
Cat Kayu Klas Menengah 20.23 Kg

Pekerja 5.45 OH
Tukang Cat 0.70 OH
Kepala Tukang Cat 0.47 OH
Mandor 0.19 OH

140 5 Cat Lisplank 9.19 m2


Meni Kayu 1.84 Kg
Plamir Kayu 1.38 Kg
Cat Kayu Klas Menengah 1.56 Kg
Cat Kayu Klas Menengah 2.39 Kg

Pekerja 0.64 OH
Tukang Cat 0.08 OH
Kepala Tukang Cat 0.06 OH
Mandor 0.02 OH
###
###
###
###
###
###
###

###
NOMOR
HARGA SATUAN SUB JUMLAH TOTAL
ANALISA

A. 4 48,022.98 6,474,697.60
1,868,500.00 3,023,046.15
10,100.00 27,234.65
1,868,500.00 1,763,443.59

50,500.00 680,866.25
21,210.00 285,963.83
55,550.00 74,895.29
45,450.00 30,638.98
5,886,088.73
588,608.87 6,474,697.60 -

B. 1 11,332.20 1,903,112.67
21,210.00 1,424,790.23
35,350.00 -
45,450.00 -
45,450.00 305,312.19
1,730,102.43
173,010.24 1,903,112.67 -

B. 9 5,429.46 455,907.43
21,210.00 341,949.66
35,350.00 -
45,450.00 -
45,450.00 72,511.65
414,461.30
41,446.13 455,907.43 -
B.10 60,827.25 2,037,712.88
35,350.00 1,421,070.00

21,210.00 355,267.50
35,350.00 -
45,450.00 -
45,450.00 76,128.75
1,852,466.25
185,246.63 2,037,712.88 -

B.11 74,159.25 899,866.88


50,500.00 735,335.55

21,210.00 77,210.23
35,350.00 -
45,450.00 -
45,450.00 5,515.02
818,060.80
81,806.08 899,866.88 -

B.11 74,159.25 1,242,167.44


50,500.00 1,015,050.00

21,210.00 106,580.25
35,350.00 -
45,450.00 -
45,450.00 7,612.88
1,129,243.13
112,924.31 1,242,167.44 -
G. 1 363,052.58 6,081,130.72
767.60 2,802,891.40
70,700.00 615,797.00
85,850.00 1,251,049.13

21,210.00 586,191.38
45,450.00 190,321.88
50,500.00 21,146.88
45,450.00 60,903.00
5,528,300.65
552,830.07 6,081,130.72 -

#N/A #N/A #N/A


494,607.10 200,315.88
767.60 104,455.01
70,700.00 15,462.09
181,800.00 59,639.49

21,210.00 14,173.58
45,450.00 4,601.81
50,500.00 511.31
45,450.00 1,472.58
200,315.88 -
20,031.59

7,545.21 508,804.24
6,565.00 464,840.23

9,090.00 9,194.64

21,210.00 10,011.94
45,450.00 21,454.16
50,500.00 2,383.80
45,450.00 919.46
508,804.24 -
50,880.42

99,439.55 230,131.53
1,868,500.00 172,969.71
10,100.00 7,012.29
5,050.00 1,168.71

21,210.00 14,725.80
50,500.00 30,386.57
55,550.00 3,342.52
45,450.00 525.92
230,131.53 -
23,013.15
1,033,176.81 1,033,176.81 #N/A

G.39 2,308,554.32 9,234,217.29


1,868,500.00 2,017,980.00
10,100.00 80,800.00
5,050.00 -
6,565.00 3,637,723.79

9,090.00 109,080.00
767.60 991,739.20
70,700.00 147,056.00
85,850.00 267,852.00

21,210.00 411,474.00
45,450.00 63,630.00
50,500.00 315,120.00
45,450.00 254,520.00
50,500.00 66,862.00
45,450.00 30,906.00
8,394,742.99
839,474.30 9,234,217.29 -

G.40.e 3,450,805.20 5,919,338.69


1,868,500.00 1,282,052.59
10,100.00 69,300.14
5,050.00 -
6,565.00 2,064,373.69

9,090.00 70,166.39
767.60 425,294.96
70,700.00 63,063.13
85,850.00 114,864.98
1,868,500.00 480,769.72
143,041.25 -
7,575.00 -

21,210.00 265,592.79
45,450.00 27,286.93
50,500.00 285,863.08
45,450.00 163,721.58
50,500.00 49,376.35
45,450.00 19,490.66
5,381,216.99
538,121.70 5,919,338.69 -

#N/A #N/A #N/A


494,607.10 1,558,012.37
767.60 812,427.84
70,700.00 120,260.70
181,800.00 463,862.70
21,210.00 110,238.98
45,450.00 35,791.88
50,500.00 3,976.88
45,450.00 11,453.40
1,558,012.37
155,801.24
7,545.21 8,299,737.95
6,565.00 7,582,586.37

9,090.00 149,985.22

21,210.00 163,317.24
45,450.00 349,965.52
50,500.00 38,885.06
45,450.00 14,998.52
8,299,737.95
829,973.79
208,013.29 13,104,837.11
1,868,500.00 4,708,620.00
2,525,000.00 2,386,125.00
143,041.25 3,154,059.56
7,575.00 954,450.00
10,100.00 254,520.00
5,050.00 63,630.00

21,210.00 400,869.00
50,500.00 1,049,895.00
55,550.00 115,488.45
45,450.00 17,180.10
13,104,837.11
1,310,483.71
25,258,846.17 25,258,846.17 #N/A
#N/A #N/A #N/A
494,607.10 545,304.33
767.60 284,349.74
70,700.00 42,091.25
181,800.00 162,351.95

21,210.00 38,583.64
45,450.00 12,527.16
50,500.00 1,391.91
45,450.00 4,008.69
545,304.33
54,530.43

7,545.21 1,964,177.53
6,565.00 1,794,459.76

9,090.00 35,494.81

21,210.00 38,649.90
45,450.00 82,821.22
50,500.00 9,202.36
45,450.00 3,549.48
1,964,177.53
196,417.75

208,013.29 3,669,354.39
1,868,500.00 1,318,413.60
2,525,000.00 668,115.00
143,041.25 883,136.68
7,575.00 267,246.00
10,100.00 71,265.60
5,050.00 17,816.40
21,210.00 112,243.32
50,500.00 293,970.60
55,550.00 32,336.77
45,450.00 4,810.43
3,669,354.39
366,935.44
6,796,719.88 6,796,719.88 #N/A

#N/A #N/A #N/A


494,607.10 484,714.96
767.60 252,755.33
70,700.00 37,414.44
181,800.00 144,312.84

21,210.00 34,296.57
45,450.00 11,135.25
50,500.00 1,237.25
45,450.00 3,563.28
484,714.96
48,471.50
7,545.21 2,582,140.70
6,565.00 2,359,026.87

9,090.00 46,662.07

21,210.00 50,809.81
45,450.00 108,878.16
50,500.00 12,097.57
45,450.00 4,666.21
2,582,140.70
258,214.07
208,013.29 4,077,060.44
1,868,500.00 1,464,904.00
2,525,000.00 742,350.00
143,041.25 981,262.98
7,575.00 296,940.00
10,100.00 79,184.00
5,050.00 19,796.00

21,210.00 124,714.80
50,500.00 326,634.00
55,550.00 35,929.74
45,450.00 5,344.92
4,077,060.44
407,706.04
7,858,307.70 7,858,307.70 #N/A

#N/A #N/A #N/A


494,607.10 1,057,222.68
767.60 551,290.32
70,700.00 81,605.48
181,800.00 314,763.98

21,210.00 74,805.02
45,450.00 24,287.34
50,500.00 2,698.59
45,450.00 7,771.95
1,057,222.68
105,722.27
7,545.21 5,165,392.26
6,565.00 4,719,068.63

9,090.00 93,344.21
21,210.00 101,641.48
45,450.00 217,803.17
50,500.00 24,200.35
45,450.00 9,334.42
5,165,392.26
516,539.23
216,012.49 6,771,991.48
1,868,500.00 2,343,099.00
10,100.00 126,654.00
5,050.00 31,663.50
2,525,000.00 1,424,857.50
143,041.25 1,569,520.12
7,575.00 474,952.50

21,210.00 212,778.72
50,500.00 522,447.75
55,550.00 57,469.25
45,450.00 8,549.15
6,771,991.48
677,199.15
7,575.00 1,262,941.88
126,294.19
15,683,303.13 15,683,303.13 #N/A

G.39.a 2,420,272.37 3,267,367.70


1,868,500.00 681,068.25
10,100.00 27,270.00
5,050.00 -
6,565.00 1,364,840.29

9,090.00 36,814.50
767.60 334,711.98
70,700.00 49,631.40
85,850.00 90,400.05

21,210.00 138,872.48
45,450.00 21,475.13
50,500.00 106,353.00
45,450.00 85,900.50
50,500.00 22,565.93
45,450.00 10,430.78
2,970,334.27
297,033.43 3,267,367.70 -

#N/A #N/A #N/A


494,607.10 1,307,617.52
767.60 681,859.08
70,700.00 100,933.09
181,800.00 389,313.34

21,210.00 92,522.00
45,450.00 30,039.61
50,500.00 3,337.73
45,450.00 9,612.68
1,307,617.52
130,761.75
7,545.21 6,388,774.64
6,565.00 5,836,742.78

9,090.00 115,452.05

21,210.00 125,714.46
45,450.00 269,388.13
50,500.00 29,932.01
45,450.00 11,545.21
6,388,774.64
638,877.46
216,012.49 8,375,884.20
1,868,500.00 2,898,043.50
10,100.00 156,651.00
5,050.00 39,162.75
2,525,000.00 1,762,323.75
143,041.25 1,941,248.56
7,575.00 587,441.25

21,210.00 263,173.68
50,500.00 646,185.38
55,550.00 71,080.39
45,450.00 10,573.94
8,375,884.20
837,588.42
7,575.00 1,562,059.69
156,205.97
19,397,769.66 19,397,769.66 #N/A

#N/A #N/A #N/A


494,607.10 -
767.60 -
70,700.00 -
181,800.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
216,012.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A

#N/A #N/A #N/A


494,607.10 -
767.60 -
70,700.00 -
181,800.00 -
21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
216,012.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A

#N/A #N/A #N/A


494,607.10 -
767.60 -
70,700.00 -
181,800.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
238,737.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -
21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A

#N/A #N/A #N/A


494,607.10 -
767.60 -
70,700.00 -
181,800.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
238,737.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A

#N/A #N/A #N/A


494,607.10 6,053,990.90
767.60 3,156,862.46
70,700.00 467,298.72
181,800.00 1,802,437.92

21,210.00 428,357.16
45,450.00 139,077.00
50,500.00 15,453.00
45,450.00 44,504.64
6,053,990.90
605,399.09
7,545.21 12,623,581.75
6,565.00 11,532,821.82
9,090.00 228,121.75

21,210.00 248,399.24
45,450.00 532,284.08
50,500.00 59,142.68
45,450.00 22,812.18
12,623,581.75
1,262,358.17
238,737.49 24,351,223.73
1,868,500.00 7,623,480.00
10,100.00 412,080.00
5,050.00 103,020.00
2,525,000.00 3,863,250.00
143,041.25 5,106,572.63
7,575.00 4,635,900.00
-

21,210.00 692,294.40
50,500.00 1,699,830.00
55,550.00 186,981.30
45,450.00 27,815.40
24,351,223.73
2,435,122.37
7,575.00 4,635,900.00
463,590.00
52,431,166.01 52,431,166.01 #N/A

#N/A #N/A #N/A


494,607.10 -
767.60 -
70,700.00 -
181,800.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
238,737.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A
#N/A #N/A #N/A
494,607.10 -
767.60 -
70,700.00 -
181,800.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
238,737.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A

#N/A #N/A #N/A


494,607.10 -
767.60 -
70,700.00 -
181,800.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
7,545.21 -
6,565.00 -

9,090.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
-
238,737.49 -
1,868,500.00 -
10,100.00 -
5,050.00 -
2,525,000.00 -
143,041.25 -
7,575.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
-
7,575.00 -
-
- - #N/A

#N/A #N/A #N/A


494,607.10 1,602,527.00
767.60 835,640.06
70,700.00 123,696.72
181,800.00 477,115.92

21,210.00 113,388.66
45,450.00 36,814.50
50,500.00 4,090.50
45,450.00 11,780.64
1,602,527.00
160,252.70
7,545.21 3,341,536.35
6,565.00 3,052,805.78
9,090.00 60,385.17

21,210.00 65,752.74
45,450.00 140,898.73
50,500.00 15,655.41
45,450.00 6,038.52
3,341,536.35
334,153.63
238,737.49 6,445,912.16
1,868,500.00 2,017,980.00
10,100.00 109,080.00
5,050.00 27,270.00
2,525,000.00 1,022,625.00
143,041.25 1,351,739.81
7,575.00 1,227,150.00

21,210.00 183,254.40
50,500.00 449,955.00
55,550.00 49,495.05
45,450.00 7,362.90
6,445,912.16
644,591.22
7,575.00 1,227,150.00
122,715.00
13,878,838.06 13,878,838.06 #N/A

C.14 153,801.29 3,732,526.49


75,750.00 2,206,006.65
36,360.00 264,720.80

21,210.00 401,493.21
45,450.00 430,171.30
50,500.00 47,796.81
45,450.00 43,017.13
3,393,205.90
339,320.59 3,732,526.49 -
C. 5 330,250.31 17,810,398.95
75,750.00 4,493,717.25
767.60 6,747,656.88
50,500.00 1,416,201.80

21,210.00 1,715,782.95
45,450.00 1,470,671.10
50,500.00 163,407.90
45,450.00 183,833.89
16,191,271.77
1,619,127.18 17,810,398.95 -

D.10 45,624.55 2,737,472.89


227.25 954,450.00
767.60 661,824.72
50,500.00 121,200.00

21,210.00 407,232.00
45,450.00 272,700.00
50,500.00 30,300.00
45,450.00 40,905.00
2,488,611.72
248,861.17 2,737,472.89 -

D.12 41,942.25 20,850,616.43


227.25 7,908,044.57
767.60 3,693,835.07
50,500.00 1,129,720.65

21,210.00 3,374,099.02
45,450.00 2,259,441.31
50,500.00 251,049.03
45,450.00 338,916.20
18,955,105.84
1,895,510.58 20,850,616.43 -

E. 3 20,025.55 2,403,066.34
767.60 596,885.76
50,500.00 115,140.00

21,210.00 509,040.00
45,450.00 818,100.00
50,500.00 90,900.00
45,450.00 54,540.00
2,184,605.76
218,460.58 2,403,066.34 -

E. 5 18,368.39 18,262,833.11
767.60 3,296,976.75
50,500.00 1,104,615.75

21,210.00 4,217,623.77
45,450.00 6,778,323.92
50,500.00 753,147.10
45,450.00 451,888.26
16,602,575.56
1,660,257.56 18,262,833.11 -

#N/A #N/A #N/A


767.60 -
50,500.00 -
3,500.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
- - #N/A

E. 3 20,025.55 535,433.22
767.60 132,993.61
50,500.00 25,654.63

21,210.00 113,420.48
45,450.00 182,282.91
50,500.00 20,253.66
45,450.00 12,152.19
486,757.47
48,675.75 535,433.22 -

F. 1 7,743,114.50 4,208,599.54
5,252,000.00 3,140,069.96

21,210.00 69,169.37
50,500.00 548,963.28
55,550.00 60,385.96
45,450.00 7,411.00
3,825,999.58
382,599.96 4,208,599.54 -

F. 7 291,082.00 5,626,178.44
2,525,000.00 1,952,178.50

21,210.00 409,957.49
50,500.00 2,440,223.13
55,550.00 268,424.54
45,450.00 43,924.02
5,114,707.67
511,470.77 5,626,178.44 -

F. 2 242,159.12 920,204.64
2,525,000.00 173,669.50
13,130.00 3,991.52
80,800.00 294,758.40

21,210.00 40,299.00
50,500.00 287,850.00
55,550.00 31,663.50
45,450.00 4,317.75
836,549.67
83,654.97 920,204.64 -

a 300,000.00 1,500,000.00 1,500,000.00

a 107,404.54 -
80,800.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
- - -

#N/A #N/A #N/A


151,500.00 303,000.00

21,210.00 424.20
50,500.00 50,500.00
55,550.00 1,111.00
45,450.00 454.50
355,489.70
35,548.97 391,038.67 #N/A

L. 3 181,631.84 1,997,950.19
138,875.00 1,527,625.00

21,210.00 2,333.10
50,500.00 277,750.00
55,550.00 6,110.50
45,450.00 2,499.75
1,816,318.35
181,631.84 1,997,950.19 -

L. 5 40,189.04 301,417.77
27,775.00 208,312.50

21,210.00 2,386.13
50,500.00 56,812.50
55,550.00 6,249.38
45,450.00 255.66
274,016.16
27,401.62 301,417.77 -

L.11.a 61,732.72 -
44,440.00 -

21,210.00 -
50,500.00 -
55,550.00 -
45,450.00 -
-
- - -
L. 6 26,422.36 105,689.43
18,180.00 72,720.00

21,210.00 848.40
50,500.00 20,200.00
55,550.00 2,222.00
45,450.00 90.90
96,081.30
9,608.13 105,689.43 -

L. 9 22,968.54 183,748.29
12,120.00 96,960.00

21,210.00 2,545.20
50,500.00 60,600.00
55,550.00 6,666.00
45,450.00 272.70
167,043.90
16,704.39 183,748.29 -
L.11 32,291.22 129,164.86
17,675.00 70,700.00

21,210.00 1,696.80
50,500.00 40,400.00
55,550.00 4,444.00
45,450.00 181.80
117,422.60
11,742.26 129,164.86 -

a 300,000.00 10,800,000.00 10,800,000.00


#N/A #N/A #N/A
5,151.00 3,836,233.01
10,100.00 20,514.62

21,210.00 287,204.61
50,500.00 341,910.25
55,550.00 37,610.13
45,450.00 30,771.92
4,554,244.53
455,424.45 5,009,668.98 #N/A

#N/A #N/A #N/A


16,160.00 985,832.10
10,100.00 8,802.07
767.60 144,494.82
50,500.00 28,166.63
3,535.00 61,614.51

21,210.00 147,874.82
50,500.00 176,041.45
55,550.00 19,364.56
45,450.00 15,843.73
1,588,034.68
158,803.47 1,746,838.15 #N/A

#N/A #N/A #N/A


7,900.00 -
7,500.00 -
100,000.00 -
9,500.00 -
85,000.00 -
1,500.00 -

41,745.00 -
37,950.00 -
22,150.00 -
-
- - #N/A

F.51 111,933.25 1,028,386.73


5,555,000.00 740,030.16
10,100.00 5,567.63

21,210.00 29,230.03
50,500.00 115,992.19
55,550.00 12,759.14
45,450.00 31,317.89
934,897.03
93,489.70 1,028,386.73 -

F.41 79,186.53 13,263,742.94


5,252,000.00 10,556,520.00
10,100.00 169,175.00

21,210.00 355,267.50
50,500.00 845,875.00
55,550.00 93,046.25
45,450.00 38,064.38
12,057,948.13
1,205,794.81 13,263,742.94 -

I.24 31,152.44 5,218,033.70


60,600.00 3,694,782.00
10,100.00 186,092.50

21,210.00 355,267.50
50,500.00 422,937.50
55,550.00 46,523.13
45,450.00 38,064.38
4,743,667.00
474,366.70 5,218,033.70 -
I.25.a 29,913.68 6,311,785.43
24,240.00 5,375,486.64

21,210.00 93,981.51
50,500.00 223,765.50
55,550.00 35,163.15
45,450.00 9,589.95
5,737,986.75
573,798.68 6,311,785.43 -

M.48.b 103,177.24 15,682,939.99


45,450.00 6,908,400.00
767.60 1,327,763.78
50,500.00 322,392.00
3,535.00 805,980.00

21,210.00 1,998,830.40
45,450.00 2,417,940.00
50,500.00 268,660.00
45,450.00 207,252.00
14,257,218.18
1,425,721.82 15,682,939.99 -

M.44 100,399.74 401,598.95


42,925.00 171,700.00
767.60 34,941.15
50,500.00 8,484.00
3,535.00 21,210.00
21,210.00 52,600.80
45,450.00 63,630.00
50,500.00 7,070.00
45,450.00 5,454.00
365,089.95
36,509.00 401,598.95 -

M.68.b 85,955.85 3,674,612.50


43,884.50 1,876,062.38
767.60 305,178.57
50,500.00 38,859.75
3,535.00 226,681.88

21,210.00 544,036.50
45,450.00 194,298.75
50,500.00 97,149.38
45,450.00 58,289.63
3,340,556.82
334,055.68 3,674,612.50 -

M.44 100,399.74 -
42,925.00 -
767.60 -
50,500.00 -
3,535.00 -

21,210.00 -
45,450.00 -
50,500.00 -
45,450.00 -
-
- - -
N.14 31,766.27 35,395,677.92
8,484.00 1,417,999.13
55,550.00 10,522,453.87
55,550.00 16,093,164.74

21,210.00 472,666.38
45,450.00 3,190,498.05
50,500.00 354,499.78
45,450.00 126,607.07
32,177,889.02
3,217,788.90 35,395,677.92 -

N.14.a 48,673.47 3,066,428.33


8,484.00 90,863.64
90,900.00 973,539.00
90,900.00 1,488,942.00

21,210.00 26,724.60
45,450.00 180,391.05
50,500.00 20,043.45
45,450.00 7,158.38
2,787,662.12
278,766.21 3,066,428.33 -

N.14 31,766.27 5,320,849.81


8,484.00 213,160.50
55,550.00 1,581,786.25
55,550.00 2,419,202.50

21,210.00 71,053.50
45,450.00 479,611.13
50,500.00 53,290.13
45,450.00 19,032.19
4,837,136.19
483,713.62 5,320,849.81 -

N. 8 26,339.03 2,049,440.12
15,907.50 247,552.52
10,100.00 117,882.15
39,390.00 521,039.10
39,390.00 796,883.33

21,210.00 115,524.51
45,450.00 31,828.18
50,500.00 23,576.43
45,450.00 8,841.16
1,863,127.38
186,312.74 2,049,440.12 -

N. 8 26,339.03 241,989.86
15,907.50 29,230.03
10,100.00 13,919.06
39,390.00 61,522.26
39,390.00 94,092.86

21,210.00 13,640.68
45,450.00 3,758.15
50,500.00 2,783.81
45,450.00 1,043.93
219,990.78
21,999.08 241,989.86 -

370,761,979.36 1,750,000.00

-
-
370,761,979.36
185,380,989.68
#REF! #REF!
No.

5,314,756.01 1,159,941.59

3,073,946.30 (1,170,833.63)

736,527.88 (280,620.45)
3,583,294.00 (1,545,581.13)

1,459,968.69 (560,101.81)

2,015,326.50 (773,159.06)
9,118,799.66 (3,037,668.95)
#N/A #N/A
#N/A #N/A

#N/A #N/A
#N/A #N/A
#N/A #N/A
8,192,867.72 (334,560.03)
#N/A #N/A
#N/A #N/A
#N/A #N/A
#REF! #REF!
#REF! #REF!
- -
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

6,499,223.22 (2,766,696.73)
27,600,144.40 (9,789,745.45)

4,523,217.60 (1,785,744.71)
34,930,820.91 (14,080,204.48)

3,338,088.60 (935,022.26)

21,546,559.15 (3,283,726.04)
2,133,264.10 (2,133,264.10)

- 535,433.22

5,533,267.23 (1,324,667.69)
8,417,900.00 (2,791,721.56)

1,294,650.50 (374,445.86)

#REF! #REF!
#N/A #N/A

2,980,290.50 (982,340.32)

313,599.00 (12,181.23)

#REF! #REF!
#REF! #REF!

#REF! #REF!

#REF! #REF!

- 10,800,000.00
#N/A #N/A

#N/A #N/A
#N/A #N/A

- 1,028,386.73

27,006,443.75 (13,742,700.81)
14,913,287.13 (9,695,253.43)

5,796,697.50 515,087.93

27,351,094.32 (11,668,154.33)
#REF! #REF!

#REF! #REF!

#REF! #REF!
48,755,269.20 (13,359,591.28)

2,661,241.28 405,187.05
7,948,038.31 (2,627,188.51)

7,635,403.60 (5,585,963.48)

- 241,989.86

156.00 273,000,000.00 97,761,979.36


-
-
Baja profil - kg
Balok Kayu Klas I 2.61 m
Balok Kayu Klas I 2.61 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas II 4.77 m
Balok Kayu Klas III 1.88 m
Balok Kayu Klas III 1.88 m
Bata Merah Klas I 38,998.88 bh
Bata Merah Klas I 38,998.88 bh
Batu Kali Belah 88.45 m
Batu Kali Belah 88.45 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Batu Pecah 2-3 Cm (Pecah Mesin) 20.98 m
Begisting Balok 70.13 m2
Begisting Balok 70.13 m2
Begisting Balok 70.13 m2
Begisting Balok 70.13 m2
Begisting Kolom 100.24 m2
Begisting Kolom 100.24 m2
Begisting Kolom 100.24 m2
Begisting Plat Lantai 129.00 m2
Begisting Plat Lantai 129.00 m2
Begisting Plat Lantai 129.00 m2
Begisting Plat Lantai 129.00 m2
Begisting Plat Lantai 129.00 m2
Begisting Plat Lantai 129.00 m2
Begisting Plat Lantai 129.00 m2
Begisting Pondasi 2.31 m2
Benangan - m'
Besi 12 3.00 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 14 93.35 Btg
Besi 6 142.79 btg
Besi 6 142.79 btg
Besi 6 142.79 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi 8 603.82 btg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 3,301.31 kg
Besi Beton 2,115.93 kg
Besi Beton 2,115.93 kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Besi Beton Polos 6,764.55 Kg
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Beton K 175 25.90 m3
Bubungan Genteng Keramik Keramik 61.00 bh
Cat Kayu Klas Menengah 37.41 Kg
Cat Kayu Klas Menengah 37.41 Kg
Cat Kayu Klas Menengah 37.41 Kg
Cat Kayu Klas Menengah 37.41 Kg
Cat Tembok Eksterior 27.09 Kg
Cat Tembok Eksterior 27.09 Kg
Cat Tembok Mutu Tinggi 551.15 Kg
Cat Tembok Mutu Tinggi 551.15 Kg
Cat Tembok Mutu Tinggi 551.15 Kg
Cat Tembok Mutu Tinggi 551.15 Kg
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Dolken dia. 10 Cm - 4 m 2,261.67 btng
Engsel Jendela Klas Tinggi 4.00 set
Engsel Pintu Klas Tinggi 7.50 set
Expanolet Klas Tinggi - set
Genteng Keramik (Warna Natural) 744.76 bh
Grendel Besar 4.00 bh
Gypsumboard (120x240x9) mm 60.97 lmbr
Hak Angin Besar 8.00 bh
Handle Double Klas Menengah 2.00 bh
Kaca Polos t=5 mm 3.65 m
Kaca Polos t=5 mm 3.65 m
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kawat Ikat Beton 105.03 Kg
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Batu 38.07 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Besi 3.79 OH
Kepala Tukang Cat 8.99 OH
Kepala Tukang Cat 8.99 OH
Kepala Tukang Cat 8.99 OH
Kepala Tukang Cat 8.99 OH
Kepala Tukang Cat 8.99 OH
Kepala Tukang Gali - OH
Kepala Tukang Gali - OH
Kepala Tukang Gali - OH
Kepala Tukang Gali - OH
Kepala Tukang Gali - OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Kayu 22.66 OH
Kepala Tukang Las - OH
Keramik Dinding Warna Klas Tinggi 42.75 m
Keramik Lantai Bermotif Klas Tinggi 4.00 m
Keramik Lantai Bermotif Klas Tinggi 4.00 m
Keramik Lantai Warna Klas Tinggi 152.00 m
Kerikil Alam 2/3 Cm 20.08 m
Kerikil Alam 2/3 Cm 20.08 m
Kerikil Alam 2/3 Cm 20.08 m
Kerikil Alam 2/3 Cm 20.08 m
Kunci Tanam 2 Slag Klas Menengah 11.00 bh
Listrik - Kwh
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mandor 58.34 OH
Mata bor - bh
mata gergaji - bh
Meni Kayu 17.40 Kg
Meni Kayu 17.40 Kg
mesin bor - jam
mesin gergaji - jam
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Minyak Begisting 60.10 m
Paku Pjg 1-3 Cm 0.30 Kg
Paku Pjg 4-6 Cm 24.02 Kg
Paku Pjg 4-6 Cm 24.02 Kg
Paku Pjg 4-6 Cm 24.02 Kg
Paku Pjg 4-6 Cm 24.02 Kg
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Paku Pjg 7-12 Cm 155.30 m
Papan Kayu Klas I 0.91 m
Papan Kayu Klas I 0.91 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Papan Kayu Klas III 15.14 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Ayak Untuk Beton 26.37 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Pasang 120.02 m
Pasir Urug 7.28 m
Pekerja - OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Pekerja 1,109.89 OH
Plamir Kayu 13.05 Kg
Plamir Kayu 13.05 Kg
Plamir Tembok 202.97 Kg
Plamir Tembok 202.97 Kg
Plamir Tembok 202.97 Kg
Profil Beton 4/11 221.76 m'
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Portland 36,707.70 Kg
Semen Warna 315.55 Kg
Semen Warna 315.55 Kg
Semen Warna 315.55 Kg
Semen Warna 315.55 Kg
Semen Warna 315.55 Kg
Tanah Urug Biasa 40.20 m
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tripleks 122 X 242 X 9 mm 104.78 lmbr
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Batu 340.69 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Besi 49.01 OH
Tukang Cat 85.50 OH
Tukang Cat 85.50 OH
Tukang Cat 85.50 OH
Tukang Cat 85.50 OH
Tukang Cat 85.50 OH
Tukang Gali - OH
Tukang Gali - OH
Tukang Gali - OH
Tukang Gali - OH
Tukang Gali - OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Kayu 243.91 OH
Tukang Las - OH
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
- #N/A
KEBUTUHAN BAHAN
1 Baja profil Hollow 295.65 kg
2 Balok Kayu Klas I 3.59 m
3 Balok Kayu Klas III 2.17 m
4 Bata Merah Klas I 45,224.97 bh
5 Batu Kali Belah 85.94 m
6 Batu Pecah 2-3 Cm (Pecah Mesin) 26.21 m
7 Begisting Balok 121.80 m2
8 Begisting Kolom 123.58 m2
9 Begisting Plat Lantai 138.51 m2
10 Begisting Pondasi 13.30 m2
11 Benangan 1,277.91 m'
7 Besi 12 23.75 Btg
8 Besi 14 271.67 Btg
9 Besi 6 194.08 btg
10 Besi 8 716.38 btg
16 Besi Beton 5,549.78 kg
17 Besi Beton 974.21 kg
18 Besi Beton Polos 8,253.78 Kg
19 Beton K 175 32.36 m3
11 Bubungan Genteng Keramik Keramik 123.56 bh
12 Cat Kayu Klas Menengah 101.87 Kg
13 Cat Tembok Eksterior 151.86 Kg
14 Cat Tembok Mutu Tinggi 678.39 Kg
15 Dolken dia. 10 Cm - 4 m 2,800.70 btng
16 Engsel Jendela Klas Tinggi 28.00 set
17 Engsel Pintu Klas Tinggi 13.50 set
18 Expanolet Klas Tinggi 2.00 set
19 Genteng Keramik (Warna Natural) 1,730.30 bh
20 Grendel Besar 28.00 bh
21 Gypsumboard (120x240x9) mm 65.34 lmbr
22 Hak Angin Besar 56.00 bh
23 Handle Double Klas Menengah 2.00 bh
24 Kaca Polos t=5 mm 25.64 m
25 Kawat Ikat Beton 130.07 Kg
26 Keramik Dinding Warna Klas Tinggi 20.25 m
27 Keramik Lantai Bermotif Klas Tinggi 20.07 m
28 Keramik Lantai Warna Klas Tinggi 172.50 m
29 Kerikil Alam 2/3 Cm 23.14 m
30 Kunci Tanam 2 Slag Klas Menengah 9.00 bh
31 Mata bor 0.21 bh
32 mata gergaji 0.43 bh
33 Meni Kayu 47.38 Kg
34 mesin bor 11.57 jam
35 mesin gergaji 10.28 jam
36 Minyak Begisting 78.11 ltr
37 Paku Pjg 1-3 Cm 2.04 Kg
38 Paku Pjg 4-6 Cm 28.85 Kg
39 Paku Pjg 7-12 Cm 201.64 kg
40 Papan Kayu Klas I 0.86 m
41 Papan Kayu Klas III 19.68 m
42 Pasir Ayak Untuk Beton 31.77 m
43 Pasir Pasang 135.28 m
44 Pasir Urug 7.07 m
45 Plamir Kayu 35.54 Kg
46 Plamir Tembok 296.68 Kg
47 Profil Beton 4/11 234.71 m'
48 Semen Portland 43,346.32 Kg
49 Semen Warna 354.53 Kg
50 Tanah Urug Biasa 225.00 m
51 Tripleks 122 X 242 X 9 mm 134.36 lmbr

KEBUTUHAN UPAH
1 Mandor 72.40 OH
2 Kepala Tukang Batu 46.71 OH
3 Kepala Tukang Besi 4.57 OH
4 Kepala Tukang Cat 13.59 OH
5 Kepala Tukang Gali - OH
6 Kepala Tukang Kayu 33.03 OH
7 Kepala Tukang Las 5.78 OH
8 Tukang Batu 424.57 OH
9 Tukang Besi 60.70 OH
10 Tukang Cat 123.77 OH
11 Tukang Gali - OH
12 Tukang Kayu 353.27 OH
13 Tukang Las 17.35 OH
14 Pekerja 1,379.79 OH
10.20 242.36 kg
13.89 3,773.38 kg
2.55 495.14 kg
4.54 3,249.07 kg
50.00 866.93 ZAK
PANJANGBATUKALI
ARAHX ARAHY
KODE P(M) KODE P(M)
25.00 4.25
25.00 33.00
23.50 1.00
2.00 3.00
1.00 3.00
2.00
1.00
1.00
3.58
2.50
4.00

i 90.58 ii 44.25
Total i+ii 134.83
VOLUMEPASANGANBATUKALI

Galian
NO URAIAN B1 B2 BRATA H L VOL
1 Tipe1 0.9 0.9 0.9 0.2 134.83 24.27
TOTAL 24.27

PasanganBatuKosong
NO URAIAN B1 B2 BRATA H L VOL
1 Tipe1 0.9 0.9 0.9 0.2 134.83 24.27
TOTAL 24.27

PasanganBatuKali
NO URAIAN B1 B2 BRATA H L VOL
1 Tipe1 0.3 0.7 0.5 0.8 134.83 53.93
TOTAL 53.93

PasirBawahPondasi
NO URAIAN B1 B2 BRATA H L VOL
1 Tipe1 0.9 0.9 0.9 0.1 134.83 12.13
TOTAL 12.13

REKAPTOTAL
Galian 24.27 M3
PasirBawahPondasi 12.13 M3
PasanganBatuKosong 24.27 M3
PasanganBatuKali 53.93 M3
SAT
M3
M3

SAT
M3
M3

SAT
M3
M3

SAT
M3
M3
PANJANGSLOOF1(S1) PANJANGBALOKLANTAIB1
ARAHX ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M) KODE P(M)
25.00 25.00 19.00

i 25.00 ii 25.00 i 19.00 ii


Total i+ii 50.00 Total i+ii 19.00

PANJANGSLOOF2(S2) PANJANGBALOKLANTAIB3
ARAHX ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M) KODE P(M)
29.75 12.75

i 29.75 ii i 12.75 ii
Total i+ii 29.75 Total i+ii 12.75

PANJANGSLOOF3(S3) PANJANGBALOKATAP(BA1)20/40
ARAHX ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M) KODE P(M)
23.50 4.25
15.00 40.00
3.00 40.00
3.00 4.00
2.00 4.00
1.00 1.80
3.58
1.00
3.00
3.00
2.50
4.00

i 64.58 ii i 94.05 ii
Total i+ii 64.58 Total i+ii 94.05
PANJANGBALOKLANTAIB1A PANJANGBALOKLANTAIB2
ARAHX ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M) KODE
6.00 17.00
6.00 6.50

i 12.00 ii i 23.50 ii
Total i+ii 12.00 Total i+ii

PANJANGBALOKLANTAIB4 PANJANGBALOKLANTAIB5
ARAHX ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M) KODE
13.50 15.00
8.00

i 13.50 ii i 23.00 ii
Total i+ii 13.50 Total i+ii

PANJANGBALOKATAP(BA2)20/40
ARAHX ARAHY
KODE P(M) KODE P(M)
38.25
i 38.25 ii
Total i+ii 38.25
LANTAIB2 PANJANGBALOKATAPR1
ARAHX ARAHY
P(M) KODE P(M) KODE P(M) KODE P(M)
21.25 15.00
15.00

i 21.25 ii 30.00 i
23.50 Total i+ii 51.25 Total i+ii

LANTAIB5
ARAHX ARAHY
P(M) KODE P(M) KODE P(M)

i ii
23.00 Total i+ii
KODE P(M)

ii

VOLUMESLOOF,BALOK,RINGBETON

SLOOFS120/40 BalokLantai3(B3)20/30
NO URAIAN B H L VOL SAT NO
1 SLOOFS120/40 0.2 0.4 50.00 4.00 M3 1
TOTAL 4.00 M3

SLOOFS220/40 BALOKLANTAIB320/40
NO URAIAN B H L VOL SAT NO
1 BALOK 0.2 0.4 29.75 2.38 M3 1
TOTAL 2.38 M3

SLOOFS320/30 BalokAtap(BA2)20/40
NO URAIAN B H L VOL SAT NO
1 BALOK 0.2 0.3 64.58 3.87 M3 1
TOTAL 3.87 M3

BALOKLANTAIB125/45 SloofS220/40
NO URAIAN B H L VOL SAT NO
1 BALOK 0.25 0.45 19.00 2.14 M3 1
TOTAL 2.14 M3

BALOKLANTAIB1A25/45 BalokLatayLantai115/20
NO URAIAN B H L VOL SAT NO
1 BALOK 0.25 0.45 12.00 1.35 M3 1
TOTAL 1.35 M3

BALOKLANTAIB225/45 BalokLatayLantai215/20
NO URAIAN B H L VOL SAT NO
1 BALOK 0.25 0.45 23.50 2.64 M3 1
TOTAL 2.64 M3

BalokLatayLantai315/20
REKAPTOTAL NO
SLOOFS120/40 4.00 M3 1
SLOOFS220/40 2.38 M3
SLOOFS320/30 3.87 M3
BALOKLANTAIB125/45 2.14 M3
BALOKLANTAIB1A25/45 1.35 M3
BALOKLANTAIB225/45 2.64 M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
BalokLantai3(B3)20/30
URAIAN B H L VOL SAT
BALOK 0.2 0.3 12.75 0.77 M3
TOTAL 0.77 M3

BALOKLANTAIB320/40
URAIAN B H L VOL SAT
BALOK 0.2 0.4 94.05 7.52 M3
TOTAL 7.52 M3

BalokAtap(BA2)20/40
URAIAN B H L VOL SAT
BALOK 0.2 0.4 38.25 3.06 M3
TOTAL 3.06 M3

SloofS220/40
URAIAN B H L VOL SAT
SloofS220/40 0.2 0.4 29.75 2.38 M3
TOTAL 2.38 M3

BalokLatayLantai115/20
URAIAN B H L VOL SAT
BalokLatayLantai115/20 0.15 0.2 51.25 1.54 M3
TOTAL 1.54 M3

BalokLatayLantai215/20
URAIAN B H L VOL SAT
BalokLatayLantai215/20 0.15 0.2 M3
TOTAL M3

BalokLatayLantai315/20
URAIAN B H L VOL SAT
BalokLatayLantai315/20 0.15 0.2 M3
TOTAL M3
Lantai1

KODE TINGGI(M) n(unit)


K1 3.50 3 10.50 25/25

K2 3.50 5 17.50 20/20
K3 3.50 2 7.00 20/20

K4 3.50 12 42.00 13/13
KP 3.50 29 101.50

178.50
LANTAI1
KolomK114/75
NO URAIAN b1 b2 L VOL SAT
1 KolomK114/75 0.14 0.75 10.50 1.10 M3
TOTAL 1.10 M3

KolomK218/100
NO URAIAN B H L VOL SAT
1 KolomK218/100 0.18 1 17.50 3.15 M3
TOTAL 3.15 M3

KolomK314/100
NO URAIAN B H L VOL SAT
1 KolomK314/100 0.14 1 7.00 0.98 M3
TOTAL 0.98 M3

KolomK418/200
NO URAIAN B H L VOL SAT
1 KolomK418/200 0.18 2 42.00 15.12 M3
TOTAL 15.12 M3

KolomPraktis
NO URAIAN B H L VOL SAT
1 KolomPraktis 0.13 0.13 101.50 1.72 M3
TOTAL 1.72 M3

REKAPTOTAL
KolomK114/75 1.10 M3
KolomK218/100 3.15 M3
KolomK314/100 0.98 M3
KolomK418/200 15.12 M3
KolomPraktis 1.72 M3

Pedestal

KODE TINGGI(M) n(unit)


K1 2.00 3 6.00

K2 2.00 5 10.00
K3 2.00 2 4.00

K4 2.00 12 24.00

44.00
LANTAI1
KolomK114/75Pedestal
NO URAIAN b1 b2 L VOL SAT
1 KolomK114/75Pedestal 0.14 0.75 6.00 0.63 M3
TOTAL 0.63 M3

KolomK230/100Pedestal
NO URAIAN B H L VOL SAT
1 KolomK230/100Pedestal 0.3 1 10.00 3.00 M3
TOTAL 3.00 M3

KolomK314/100Pedestal
NO URAIAN B H L VOL SAT
1 KolomK314/100Pedestal 0.14 1 4.00 0.56 M3
TOTAL 0.56 M3

KolomK430/200Pedestal
NO URAIAN B H L VOL SAT
1 KolomK430/200Pedestal 0.3 2 24.00 14.40 M3
TOTAL 14.40 M3

REKAPTOTAL
KolomK114/75Pedestal 0.63 M3
KolomK230/100Pedestal 3.00 M3
KolomK314/100Pedestal 0.56 M3
KolomK430/200Pedestal 14.40 M3
Lantai2 Lantai3

KODE TINGGI(M) n(unit) KODE


K1 3.50 3 10.50

K2 3.50 5 17.50
K3 3.50 2 7.00

K4 3.50 12 42.00
KP 3.50 31 108.50

185.50
LANTAI2
KolomK114/75
NO URAIAN b1 b2 L VOL SAT
1 KolomK114/75 0.14 0.75 10.50 1.10 M3
TOTAL 1.10 M3

KolomK218/100
NO URAIAN B H L VOL SAT
1 KolomK218/100 0.18 1 17.50 3.15 M3
TOTAL 3.15 M3

KolomK314/100
NO URAIAN B H L VOL SAT
1 KolomK314/100 0.14 1 7.00 0.98 M3
TOTAL 0.98 M3

KolomK418/200
NO URAIAN B H L VOL SAT
1 KolomK418/200 0.18 2 42.00 15.12 M3
TOTAL 15.12 M3

KolomPraktis
NO URAIAN B H L VOL SAT
1 KolomPraktis 0.13 0.13 108.50 1.83 M3
TOTAL 1.83 M3

REKAPTOTAL
KolomK114/75 1.10 M3
KolomK218/100 3.15 M3
KolomK314/100 0.98 M3
KolomK418/200 15.12 M3
KolomPraktis 1.83 M3
Lantai3

KODE TINGGI(M) n(unit)


K1 3.50 3 10.50

K2 3.50 17 59.50
K3 3.50 2 7.00

K4 3.50
KP 3.50 30 105.00

182.00
LANTAI2
KolomK114/75
NO URAIAN b1 b2 L VOL SAT
1 KolomK114/75 0.14 0.75 10.50 1.10 M3
TOTAL 1.10 M3

KolomK218/100
NO URAIAN B H L VOL SAT
1 KolomK218/100 0.18 1 59.50 10.71 M3
TOTAL 10.71 M3

KolomK314/100
NO URAIAN B H L VOL SAT
1 KolomK314/100 0.14 1 7.00 0.98 M3
TOTAL 0.98 M3

KolomK418/200
NO URAIAN B H L VOL SAT
1 KolomK418/200 0.18 2 M3
TOTAL M3

KolomPraktis
NO URAIAN B H L VOL SAT
1 KolomPraktis 0.13 0.13 105.00 1.77 M3
TOTAL 1.77 M3

REKAPTOTAL
KolomK114/75 1.10 M3
KolomK218/100 10.71 M3
KolomK314/100 0.98 M3
KolomK418/200 M3
KolomPraktis 1.77 M3
PEKERJAANBETON(LANTAIKERJA,FOOTPLAT)

FOOTPLATE1
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 FootPlate 1.8 0.75 0.3 1 0.405

LANTAIKERJA
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 LantaiKerja 1.9 0.9 0.05 1 0.0855

GALIAN
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 Galian 1.9 0.9 2 1 3.42

REKAPTOTAL
Galian 3.42 m3
LantaiKerja 0.0855 m3
FootPlate 0.405 m3
PEKERJAANBETON(LANTAIKERJA,FOOTPLAT)

FOOTPLATE2
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 FootPlate 4.25 1 0.3

LANTAIKERJA
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 LantaiKerja 4.25 1.1 0.05

GALIAN
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 Galian 4.25 1.1 2

REKAPTOTAL
Galian 28.05 m3
LantaiKerja 0.70125 m3
FootPlate 3.825 m3
JA,FOOTPLAT) PEKERJAANBETON(LANTAIKERJA,FO

FOOTPLATE3
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

3 3.825 m3 1 FootPlate 4.25

LANTAIKERJA
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

3 0.70125 m3 1 LantaiKerja 4.25

GALIAN
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

3 28.05 m3 1 Galian 4.25

REKAPTOTAL
Galian 5.1
LantaiKerja 0.1275
FootPlate 0.6375
N(LANTAIKERJA,FOOTPLAT) PEKERJAANBETON(LA

FOOTPLATE4
Dimensi
Jumlah Volume sat No.
L H
d e f g=(cxdxexf) h a

0.5 0.3 1 0.6375 m3 1

LANTAIKERJA
Dimensi
Jumlah Volume sat No.
L H
d e f g=(cxdxexf) h a

0.6 0.05 1 0.1275 m3 1

GALIAN
Dimensi
Jumlah Volume sat No.
L H
d e f g=(cxdxexf) h a

0.6 2 1 5.1 m3 1

m3
m3
m3
PEKERJAANBETON(LANTAIKERJA,FOOTPLAT)

FOOTPLATE4
Dimensi
Uraian Jumlah Volume sat
P L H
b c d e f g=(cxdxexf) h

FootPlate 4.25 2 0.3 6 15.3 m3

LANTAIKERJA
Dimensi
Uraian Jumlah Volume sat
P L H
b c d e f g=(cxdxexf) h

LantaiKerja 4.25 2.1 0.05 6 2.6775 m3

Dimensi
Uraian Jumlah Volume sat
P L H
b c d e f g=(cxdxexf) h

Galian 4.25 2.1 2 6 107.1 m3

REKAPTOTAL
Galian 107.1 m3
LantaiKerja 2.6775 m3
FootPlate 15.3 m3
PEKERJAANBETONPLAT

PLATLANTAI1
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatLantai12cm 24 4.25 0.12 1 12.24



12.24

PLATTALANG
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatTalang10cm 0.1 1
0.1
0.1
0.1
0.1

PLATSUNSHIDING
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatSunshiding10cm
0.5 0.1 1
0.5 0.1 2
0.5 0.1 2
0.5 0.1 1
0.5 0.1 2
0.5 0.1
0.5 0.1
0.5 0.1
0.5 0.1

PLATDAKELV.6.60
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatDak10cm 0.1 1
0.1 1

PLATDAKELV.6.90
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatDak10cm 0.1 1
0.1 1
0.1 1
0.1 1

PLATMEJA
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatMeja10cm 0.1 1

PLATTANGGA
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatTangga15cm 12 1.8 0.15 1 3.24


0.15
0.15
0.15
3.24

REKAPTOTAL
PlatTalang10cm m3
PlatSunshiding10cm m3
PlatLantai12cm 12.24 m3
PLATDAKELV.6.60 m3
PLATDAKELV.6.90 m3
PlatMeja10cm m3
PlatTangga15cm 3.24 m3
PEKERJAANBETONPLAT

PLATLANTAI2
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatLantai12cm 40 4.25 0.12


m3
m3

PLATTALANG
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatTalang10cm 0.1
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3

PLATSUNSHIDING
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatSunshiding10cm
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3 0.1
m3

PLATDAKELV.6.60
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatDak10cm 0.1
0.1
m3

PLATDAKELV.6.90
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatDak10cm 0.1
0.1
0.1
0.1
m3

PLATMEJA
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatMeja10cm 0.1
m3

PLATTANGGA
Dimensi
sat No. Uraian
P L H
h a b c d e

m3 1 PlatTangga15cm 15 1.8 0.15


m3 0.15
m3 0.15
m3 0.15
m3

REKAPTOTAL
PlatTalang10cm m3
PlatSunshiding10cm m3
PlatLantai12cm 20.40 m3
PLATDAKELV.6.60 m3
PLATDAKELV.6.90 m3
PlatMeja10cm m3
PlatTangga15cm 4.05 m3
LAT PEKERJAANBETONPLAT

PLATLANTAI3
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

1 20.40 m3 1 PlatLantai10cm 38
m3
20.40 m3

PLATTALANG
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

1 m3 1 PlatTalang10cm
m3
m3
m3
m3
m3

PLATSUNSHIDING
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

m3 1 PlatSunshiding10cm
m3 2.45
m3 1.8
m3 3
m3
m3
m3
m3
m3
m3
m3

PLATDAKELV.6.60
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

1 m3 1 PlatDak10cm
1
m3

PLATDAKELV.6.90
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

1 m3 1 PlatDak10cm
1
1
1
m3

PLATMEJA
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

1 m3 1 PlatMeja10cm
m3

PLATTANGGA
Dimensi
Jumlah Volume sat No. Uraian
P
f g=(cxdxexf) h a b c

1 4.05 m3 1 PlatTangga15cm
m3
m3
m3
4.05 m3

REKAPTOTAL
PlatTalang10cm
PlatSunshiding10cm 0.51
PlatLantai10cm 19.38
PLATDAKELV.6.60
PLATDAKELV.6.90
PlatMeja10cm
PlatTangga15cm
JAANBETONPLAT

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

4.25 0.12 1 19.38 m3


m3
19.38 m3

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

0.1 1 m3
0.1 m3
0.1 m3
0.1 m3
0.1 m3
m3

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

m3
0.5 0.1 1 0.12 m3
0.5 0.1 1 0.09 m3
0.5 0.1 2 0.30 m3
0.1 m3
0.1 m3
0.1 m3
0.1 m3
0.1 m3
0.1 m3
0.51 m3

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

0.1 1 m3
0.1 1
m3

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

0.1 1 m3
0.1 1
0.1 1
0.1 1
m3

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

0.1 1 m3
m3

Dimensi
Jumlah Volume sat
L H
d e f g=(cxdxexf) h

0.15 m3
0.15 m3
0.15 m3
0.15 m3
m3

m3
m3
m3
m3
m3
m3
m3
PEKERJAANTANAH

LuasRuangan 167.50 m2

t A V Sat
TanahPeninggianLantai 0.20 167.50 33.50 m3
PasirBawahLantai 0.10 167.50 16.75 m3

GalianTanah
Footplat 143.67 m3
Batukali 24.2685 m3
167.9385 m3
PEKERJAANACCESSORIESLANTAI1

No Uraian Jumlah Ases

Pintu
Hendel Kuncipntu Expanolet
Kebutuhan/daun 1 1 1
satuan bh bh set

1 P1 5.00 5 5
2 P2geser 6.00 6 6
PJ1 0 0 0
3 J1 4.00
4 J2
Total 11 11 0

HendelPintu 11 bh
KunciPintu 11 bh
EngselPintu 7.5 set
Expanolet 0 set
RelGeser 6 set
EngselJendela 4 set
GrendelJendela 4 bh
HakAngin 8 bh

PEKERJAANACCESSORIESLANTAI2

No Uraian Jumlah Ases

Pintu
Hendel Kuncipntu Expanolet
Kebutuhan/daun 1 1 1
satuan bh bh set

1 P1 5.00 5 5
2 P2Geser 5.00 5 5
PJ1 0 0 0
3 J1 4.00
4 J2
Total 10 10 0

HendelPintu 10 bh
KunciPintu 10 bh
EngselPintu 7.5 set
Expanolet 0 set
RelGeser 5 set
EngselJendela 4 set
GrendelJendela 4 bh
HakAngin 8 bh

PEKERJAANACCESSORIESLANTAI3

No Uraian Jumlah Ases

Pintu
Hendel Kuncipntu Expanolet
Kebutuhan/daun 1 1 1
satuan bh bh set

1 P1 3.00 3 3
2 P2Geser 4.00 4 4
PJ1 0 0 0
P4DOUBLE 1.00 2 2 2
3 J1 4.00
4 J2
Total 9 9 2

HendelPintu 9 bh
KunciPintu 9 bh
EngselPintu 4.5 set
Expanolet 2 set
RelGeser 4 set
EngselJendela 4 set
GrendelJendela 4 bh
HakAngin 8 bh
SLANTAI1

Asesoris

Pintu Jendela
RelGeser EngselPntu engsel Grendel Hakangin
1 1.5 1 1 2
set set set bh bh

7.5
6
0 0 0 0
4 4 8
0 0 0
6 7.5 4 4 8

SLANTAI2

Asesoris

Pintu Jendela
RelGeser EngselPntu engsel Grendel Hakangin
1 1.5 1 1 2
set set set bh bh

7.5
5
0 0 0 0
4 4 8
0 0 0
5 7.5 4 4 8
SLANTAI3

Asesoris

Pintu Jendela
RelGeser EngselPntu engsel Grendel Hakangin
1 1.5 1 1 2
set set set bh bh

4.5
4
0 0 0 0

4 4 8
0 0 0
4 4.5 4 4 8
PEKERJAANKRAMIKLANTAI1

P L A SAT
a Ruang1,2,3,8,9,selasar 97.00 m2
a ruang11 3.00 1.00 3.00 m2
a ruang7 13.00 4.00 52.00 m2
c ruang5 2.00 4.00 8.00 m2
c ruang6 3.50 m2
b batukoral 1.00 4.00 4.00 m2
a m2
a m2
c m2
a m2
a m2
c m2
a m2
a m2
c m2
a m2
a m2
a m2
b m2
a m2
a m2
b m2
a m2
b m2

a KramikLantai40x40 152.00 m2
b PasangBatuKoralSikat 4.00 m2
c KramikLantaiKM/WC 11.50 m2

REKAPTOTAL
KramikLantai40x40 152.00 m2
PasangBatuKoralSikat 4.00 m2
KramikDinding20x25 42.75 m2
KramikMejadapur20x20 m2
KramikLantaiKM/WC 11.50 m2

PEKERJAANKRAMIKLANTAI2

P L A SAT
a selasar 93.00 m2
a ruang4 4.00 3.00 12.00 m2
c ruang5a 2.00 1.00 2.00 m2
c ruang5 2.00 4.00 8.00 m2
a ruang7 13.00 4.00 52.00 m2
a m2
b batukoral 1.00 5.00 5.00 m2
a m2
a m2
a m2
b m2
d m2

a KramikLantai40x40 157.00 m2
b PasangBatuKoralSikat 5.00 m2
c KramikLantaiKM/WC20x20 10.00 m2
d PasangBatuKoral m2

REKAPTOTAL
KramikLantai40x40 157.00 m2
PasangBatuKoralSikat 5.00 m2
KramikDinding20x25 49.13 m2
KramikMejadapur20x20 m2
KramikLantaiKM/WC 10.00 m2
PasangBatuKoral m2

PEKERJAANKRAMIKLANTAI3

P L A SAT
a selasar 86.00 m2
a ruang10 16.00 m2
c ruang5a 3.00 m2
c ruang5 3.00 2.00 6.00 m2
a ruang7 13.00 m2
a ruang12 23.00 m2
b batukoral 1.00 5.00 5.00 m2
a ruang13 5.00 3.00 15.00 m2
a ruang14 2.00 2.50 5.00 m2
c ruang5b 2.00 2.00 4.00 m2
m2
m2

a KramikLantai40x40 158.00 m2
b PasangBatuKoralSikat 5.00 m2
c KramikLantaiKM/WC20x20 13.00 m2
d PasangBatuKoral m2

REKAPTOTAL
KramikLantai40x40 158.00 m2
PasangBatuKoralSikat 5.00 m2
KramikDinding20x25 43.20 m2
KramikMejadapur20x20 m2
KramikLantaiKM/WC 13.00 m2
PasangBatuKoral m2
PEKERJAANKRAMIKDINDING

P L T A SAT
ruang5 2.75 1.00 3.00 11.25
ruang5 2.75 1.00 3.00 11.25
ruang5 2.75 1.00 3.00 11.25
ruang5 2.75 1.00 3.00 11.25
ruang6 1.50 2.25 1.50 5.63


















m2

KramikDindingKM/WCBruto 50.63 m2
Void 0.7 2.25 5 7.88 m2
KramikDindingKM/WCNeto 42.75 m2

PEKERJAANKRAMIKDINDING

P L T A SAT
m2
ruang5a 1.00 3.00 3.00 12.00 m2
ruang5 1.00 2.75 3.00 11.25 m2
ruang5 1.00 2.75 3.00 11.25 m2
ruang5 1.00 2.75 3.00 11.25 m2
ruang5 1.00 2.75 3.00 11.25 m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

m2
m2
m2
m2
m2

KramikDindingKM/WCBruto 57.00 m2
Void 0.7 2.25 5 7.88 m2

KramikDindingKM/WCNeto 49.13 m2

PEKERJAANKRAMIKDINDING

P L T A SAT
m2
ruang5a 1.00 3.00 3.00 12.00 m2
ruang5 1.00 2.75 3.00 11.25 m2
ruang5 1.00 2.75 3.00 11.25 m2
ruang5b 2.00 3.00 3.00 15.00 m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

m2
m2
m2
m2
m2

KramikDindingKM/WCBruto 49.50 m2
Void 0.7 2.25 4 6.30 m2

KramikDindingKM/WCNeto 43.20 m2
PEKERJAANKRAMIKDINDING

P L T A SAT
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

m2
m2
m2
m2
m2

m2
m2
m2

PEKERJAANKRAMIKDINDING

P L T A SAT
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

m2
m2
m2
m2
m2

m2
m2
m2

PEKERJAANKRAMIKDINDING

P L T A SAT
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

m2
m2
m2
m2
m2

m2
m2
m2
PEKERJAANPLAFONDLANTAI1

P L A SAT
a Ruang1,2,3,8,9,selasar 97.00 m2
a ruang11 3.00 1.00 3.00 m2
a ruang7 13.00 4.00 52.00 m2
a ruang5 2.00 4.00 8.00 m2
a ruang6 3.50 m2
a batukoral 1.00 4.00 4.00 m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2

a PlafondGypsum 167.50 m2
b ListGypsum 211.00 m1

PEKERJAANPLAFONDLANTAI2

P L A SAT
m2
a selasar 93.00 m2
a ruang4 4.00 3.00
12.00 m2
a ruang5a 2.00 1.00
2.00 m2
a ruang5 2.00 4.00
8.00 m2
a ruang7 13.00 4.00
52.00 m2
a m2
a batukoral 1.00 5.00 5.00 m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2

a PlafondGypsum 172.00 m2
b ListGypsum 212.50 m1

PEKERJAANPLAFONDLANTAI3

P L A SAT
m2
a selasar 86.00 m2
a ruang10 16.00 m2
a ruang5a 3.00 m2
a ruang5 3.00 2.00 6.00 m2
a ruang7 13.00 m2
a ruang12 23.00 m2
a batukoral 1.00 5.00 5.00 m2
a ruang13 5.00 3.00 15.00 m2
a ruang14 m2
a ruang5b 2.00 2.00 4.00 m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2
a m2

a PlafondGypsum 171.00 m2
b ListGypsum 192.00 m1
LISTPEKERJAANPLAFONDLNT.1

P L A SAT
Ruang1,2,3,8,9,selasar 95.50 m1
ruang11 8.00 8.00 m1
ruang7 15.00 4.00 60.00 m1
ruang5 8.00 5.00 40.00 m1
ruang6 7.50 m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1

LISTPEKERJAANPLAFONDLNT.2

P L A SAT
selasar 98.50 m1
ruang5a 8.00 m1
ruang5 32.00 m1
ruang7 60.00 m1
ruang4 14.00 m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1

LISTPEKERJAANPLAFONDLNT.3

P L A SAT
selasar 86.50 m1
ruang10 17.00 m1
ruang5a 8.00 m1
ruang5 16.00 m1
ruang7 15.00 m1
ruang12 24.00 m1
batukoral m1
ruang13 15.50 m1
ruang14 m1
ruang5b 10.00 m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
LANTAI1
VOIDBATA

URAIAN P L n A SAT
P1(KAYU) 2.15 0.85 5.00 9.14 m2
P2(KAYU) 2.15 0.79 6.00 10.19 m2
PJ1(KAYU)+KACA 2.15 1.60 m2
1.70 0.50
J1(KAYU)+KACA 1.90 0.50 4.00 3.80 m2
J2(KAYU)+KACA 0.60 0.60 m2
BV(KAYU)+KACAS 0.60 0.60 m2
Roster1(KAYU) 0.15 0.30 m2
aluminiumPJ1 3.42 3.16 1.00 10.81 m2

VoidBata 33.94 M2

LANTAI2
VOIDBATA

URAIAN P L n A SAT
KusenP1 2.15 0.85 5.00 9.14 m2
KusenP2 2.15 0.79 5.00 8.49 m2
KusenPJ1 2.15 1.60 m2
1.70 0.50
J1(KAYU)+KACA 1.90 0.50 4.00 3.80 m2
J2(KAYU)+KACA 0.60 0.60 m2
BV(KAYU)+KACAS 0.60 0.60 m2
J2ALMINUM 2.00 2.50 1.00 5.00 m2
P3 2.50 1.25 1.00 3.13 m2

VoidBata 29.56 M2

LANTAI2
VOIDBATA

URAIAN P L n A SAT
KusenP1 2.15 0.85 3.00 5.48 m2
KusenP2 2.15 0.79 4.00 6.79 m2
KusenPJ1 2.15 1.60 m2
1.70 0.50
J1(KAYU)+KACA 1.90 0.50 4.00 3.80 m2
J3 2.00 1.00 1.00 2.00 m2
P4 2.15 1.60 1.00 3.44 m2
P3 2.50 1.25 1.00 3.13 m2
P5 2.50 1.00 1.00 2.50 m2

VoidBata 27.14 M2
VoidPlesteraneksterior

URAIAN P L n A SAT
P1(KAYU)+KACA 2.15 0.85 m2
P2(KAYU)+KACA 2.15 0.79 m2
PJ1(KAYU)+KACA 2.15 1.60 m2
1.70 0.50
J1(KAYU)+KACA 1.70 0.50 m2
J2(KAYU)+KACA 0.60 0.60 m2
BV(KAYU)+KACAS 0.60 0.60 m2
Roster1(KAYU) 0.15 0.30 m2
aluminiumPJ1 3.42 3.16 1.00 10.81 m2

VoidPlesteran 10.81 M2

VoidPlesteraneksterior

URAIAN P L n A SAT
P1(KAYU)+KACA 2.15 0.85 m2
P2(KAYU)+KACA 2.15 0.85 m2
PJ1(KAYU)+KACA 2.15 1.60 m2
1.70 0.50
J1(KAYU)+KACA 1.70 0.50 m2
J2(KAYU)+KACA 0.60 0.60 m2
BV(KAYU)+KACAS 0.60 0.60 m2
J2ALMINUM 2.00 2.50 1.00 5.00 m2
P3 2.50 1.25 1.00 3.13 m2

VoidPlesteran 8.13 M2

VoidPlesteraneksterior

URAIAN P L n A SAT
P1(KAYU)+KACA 2.15 0.85 m2
P2(KAYU)+KACA 2.15 0.85 m2
PJ1(KAYU)+KACA 2.15 1.60 m2
1.70 0.50
J1(KAYU)+KACA 1.70 0.50 m2
J3 2.00 1.00 1.00 2.00 m2
P4 2.15 1.60 1.00 3.44 m2
P3 2.50 1.25 1.00 3.13 m2
P5 2.50 1.00 1.00 2.50 m2

VoidPlesteran 11.07 M2
PASANGANBATA

LANTAI1 LANTAI2
ARAHX ARAHY ARAHX
KODE P(M) KODE P(M) KODE P(M)
A 40.00 4.25 40.00
B 9.50 27.00 6.00
C 3.58 8.00 5.33
D 1.00 1.50 5.00
E 22.00 2.00 0.50
F 40.00 4.25 22.00
G 4.00 1.80 40.00
H 4.00
I 1.80
J
K
L
M
N
i 120.08 ii 48.80 i 124.63
Total i+ii 168.88 Total i+ii

P T V Sat
PasanganBataLantai1 168.88 3.50 591.06 m2
PasanganBataLantai2 172.13 3.50 602.44 m2
PasanganBataLantai3 163.00 3.30 537.90 m2

TotalPasanganBataLantai1 557.13 m2
TotalPasanganBataLantai2 572.88 m2
TotalPasanganBataLantai3 510.76 m3

PasanganBataKM/WC 40
0

40 1.5

Lantai1
Pasanganbatamerahtebalbata.1Pc:3Ps 60.00 m2
Pasanganbatamerahtebalbata.1Pc:5Ps 497.13 m2
LANTAI3
ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M)
4.25 40.00 4.25
30.00 5.00 27.00
8.00 22.00 6.00
1.00 5.25 0.50
4.25 8.00
40.00
4.00
1.00

ii 47.50 i 125.25 ii 37.75


172.13 Total i+ii 163.00

PasanganBataKM/WC 40
0

60 40 1.5

Lantai2
Pasanganbatamerahtebalbata.1Pc:3 60.00 m2
Pasanganbatamerahtebalbata.1Pc:5 512.88 m2
PasanganBataKM/WC 24
10

60 34 1.5

Lantai3
Pasanganbatamerahtebalbata.1Pc51.00 m2
Pasanganbatamerahtebalbata.1Pc459.76 m2
51
PASANGANBATA

PANJANGBATA PANJANGBATA
ARAHX ARAHY ARAHX
KODE P(M) KODE P(M) KODE P(M)
A 40.00 4.25 40.00
B 9.50 27.00 6.00
C 3.58 8.00 5.33
D 1.00 1.50 5.00
E 22.00 2.00 0.50
F 40.00 4.25 22.00
G 4.00 1.80 40.00
H 4.00
I 1.80
J
K
L
M
N
i 120.08 ii 48.80 i 124.63
Total i+ii 168.88 Total i+ii

P T V Sat
PasanganPlesteranLantai1 168.88 3.50 591.06 m2
PasanganPlesteranLantai2 172.13 3.50 602.44 m2
PasanganPlesteranLantai3 163.00 3.30 537.90 m2
3,462.80 m2

TotalPasanganPlesteranLantai1 1,114.25 m2
TotalPasanganPlesteranLantai2 1,145.77 m2
TotalPasanganPlesteranLantai3 1,021.52 m3
3,281.54
LANTAI1
Pelesteran1Pc:3Pstebal15mm. 120.00 m2
Pelesteran1Pc:4Pstebal15mm. 994.25 m2
1,114.25

PlesterEksterior

80.00
8.50
8.50
80.00

7.00 177.00 1,239.00 m2

80.00
8.50

3.40 88.50 300.90 m2


1,539.90 m2
1,509.90 m2
PANJANGBATA
ARAHY ARAHX ARAHY
KODE P(M) KODE P(M) KODE P(M)
4.25 40.00 4.25
30.00 5.00 27.00
8.00 22.00 6.00
1.00 5.25 0.50
4.25 8.00
40.00
4.00
1.00

ii 47.50 i 125.25 ii 37.75


172.13 Total i+ii 163.00

LANTAI2
Pelesteran1Pc:3Pstebal15mm. 120.00 m2
Pelesteran1Pc:4Pstebal15mm. 1,025.77 m2
1,145.77
LANTAI3
Pelesteran1Pc:3Pstebal15mm. 102.00 m2
Pelesteran1Pc:4Pstebal15mm. 919.52 m2
1,021.52
PEKERJAANKUSEN

PEKERJAANKAYUPINTU+JENDELA
LANTAI1


LUAS DIMENSI PANJAN
URAIAN TINGGI LEBA
(M2) KAYU(M3) GKAYU
R
(M)

P1(KAYU) 2.15 0.85 9.14 0.12 0.06 5.15


P2(KAYU) 2.15 0.79 10.19 0.12 0.06 5.09
PJ1(KAYU)+KACA 2.15 1.60 0.12 0.06 5.90
1.70 0.50 0.12 0.06 5.40
P4(KAYU) 2.15 1.60 0.12 0.06 10.70

J1(KAYU)+KACA 1.90 0.50 3.80 0.12 0.06 4.80


J2(KAYU)+KACA 0.60 0.60 0.12 0.06 2.40
BV(KAYU)+KACAS 0.60 0.60 0.12 0.06 2.40

Roster1(KAYU) 0.15 0.30 0.10 0.03 0.90


Roster2(KAYU) 0.60 0.40 0.10 0.03 3.40

KusenP1 0.19 m3
KusenP2 0.22 m3
KusenPJ1 m3
KusenJ1 0.14 m3
KusenJ2 m3
KusenBV m3
DaunP1 9.14 m2
DaunP2 10.19 m2
DaunPJ1
DaunJ1 3.80 m2
DaunJ2 m2
KacaS m2
RosterKayu m3
PEKERJA

PEKERJAANKAYUPINTU+JEND
LANTAI2

JUMLAH
KUSEN VOLUM URAIAN
(BH) E(M3)
cat sat

5.00 0.19 26.11 m2 P1(KAYU)+KACA


6.00 0.22 30.90 m2 P2(KAYU)+KACA
PJ1(KAYU)+KACA

P4(KAYU)

4.00 0.14 19.56 m2 J1(KAYU)+KACA


0.36 m2 J2(KAYU)+KACA
0.36 m2 BV(KAYU)+KACAS

0.26 m2 Roster1(KAYU)
0.26 m2 Roster2(KAYU)

KusenP1
KusenP2
KusenPJ1
KusenJ1
KusenJ2
KusenBV
DaunP1
DaunP2
DaunPJ1
DaunJ1
DaunJ2
KacaS
RosterKayu
PEKERJAANKUSEN

NKAYUPINTU+JENDELA


JUMLAH
LUAS DIMENSI PANJAN
TINGGI LEBA KUSEN VOLUM
(M2) KAYU(M3) GKAYU
R (BH) E(M3)
(M)

2.15 0.85 9.14 0.12 0.06 5.15 5.00 0.19


2.15 0.79 8.49 0.12 0.06 5.09 5.00 0.18
2.15 1.60 0.12 0.06 5.90
1.70 0.50 0.12 0.06 5.40
2.15 1.60 0.12 0.06 10.70

1.90 0.50 3.80 0.12 0.06 4.80 4.00 0.14


0.60 0.60 0.12 0.06 2.40
0.60 0.60 0.12 0.06 2.40

0.15 0.30 0.10 0.03 0.90


0.60 0.40 0.10 0.03 3.40

0.19 m3
0.18 m3
m3
0.14 m3
m3
m3
9.14 m2
8.49 m2

3.80 m2
m2
m2
m3
PEKERJAANKUSEN

PEKERJAANKAYUPINTU+JENDELA
LANTAI3


LUAS DIMENSI
URAIAN TINGGI LEBA
(M2) KAYU(M3)
R
cat sat

26.11 m2 P1(KAYU)+KACA 2.15 0.85 5.48 0.12


25.81 m2 P2(KAYU)+KACA 2.15 0.79 6.79 0.12
PJ1(KAYU)+KACA 2.15 1.60 0.12
1.70 0.50 0.12
P4(KAYU) 2.15 1.60 3.44 0.12

19.56 m2 J1(KAYU)+KACA 1.90 0.50 3.80 0.12


0.36 m2 J2(KAYU)+KACA 0.60 0.60 0.12
0.36 m2 BV(KAYU)+KACAS 0.60 0.60 0.12

0.26 m2 Roster1(KAYU) 0.15 0.30 0.10


0.26 m2 Roster2(KAYU) 0.60 0.40 0.10

KusenP1 0.11 m3
KusenP2 0.15 m3
KusenPJ1 m3
KusenJ1 0.14 m3
KusenJ2 m3
KusenBV m3
DaunP1 5.48 m2
DaunP2 6.79 m2
DaunPJ1
DaunJ1 3.80 m2
DaunJ2 m2
KacaS m2
RosterKayu m3
N


JUMLAH
DIMENSI PANJAN
KUSEN VOLUM
KAYU(M3) GKAYU
(BH) E(M3)
(M) cat sat

0.06 5.15 3.00 0.11 15.81 m2


0.06 5.09 4.00 0.15 20.72 m2
0.06 5.90 0.36
0.06 5.40 0.36
0.06 10.70 1.00 0.08 11.06

0.06 4.80 4.00 0.14 19.56 m2


0.06 2.40 0.36 m2
0.06 2.40 0.36 m2

0.03 0.90 0.26 m2


0.03 3.40 0.26 m2
TALIAIRLANTAI1

URAIAN P L n l ltot SAT


P1(KAYU) 2.15 0.85 5.00 6.00 30.00 m1
P2(KAYU) 2.15 0.79 6.00 5.88 35.28 m1
PJ1(KAYU)+KACA 2.15 1.60 7.50 m1
1.70 0.50 4.40 m1
J1(KAYU)+KACA 1.90 0.50 4.00 4.80 19.20 m1
J2(KAYU)+KACA 0.60 0.60 2.40 m1
BV(KAYU)+KACAS 0.60 0.60 2.40 m1
Roster1(KAYU) 0.15 0.30 0.90 m1

Taliair 84.48 m1

TALIAIRLANTAI2

URAIAN P L n l ltot SAT


P1(KAYU) 2.15 0.85 5.00 6.00 30.00 m1
P2(KAYU) 2.15 0.79 5.00 5.88 29.40 m1
PJ1(KAYU)+KACA 2.15 1.60 7.50 m1
1.70 0.50 4.40 m1
J1(KAYU)+KACA 1.90 0.50 4.00 4.80 19.20 m1
J2(KAYU)+KACA 0.60 0.60 2.40 m1
BV(KAYU)+KACAS 0.60 0.60 2.40 m1
Roster1(KAYU) 0.15 0.30 0.90 m1

Taliair 78.60 m1

TALIAIRLANTAI3

URAIAN P L n l ltot SAT


P1(KAYU) 2.15 0.85 3.00 6.00 18.00 m1
P2(KAYU) 2.15 0.79 4.00 5.88 23.52 m1
PJ1(KAYU)+KACA 2.15 1.60 1.00 7.50 7.50 m1
1.70 0.50 4.40 m1
J1(KAYU)+KACA 1.90 0.50 4.00 4.80 19.20 m1
J2(KAYU)+KACA 0.60 0.60 2.40 m1
BV(KAYU)+KACAS 0.60 0.60 2.40 m1
Roster1(KAYU) 0.15 0.30 0.90 m1

Taliair 68.22 m1
5,000.00 422,400.00

5,000.00

5,000.00
PEKERJAANWATERPROOF

PLATLANTAI
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatLantai12cm
9 4 0 1

PLATTALANG
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatTalang10cm




PLATSUNSHIDING
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatSunshiding10cm
2 0.5 1 1 1.00
0.8 0.5 1 2 0.80
1.5 0.5 1 2 1.50
1 0.5 1 1 0.50
4 0.5 1 2 4.00
0.5 1
0.5 1
0.5 1
0.5 1
7.80

PLATDAKELV.6.6
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatDak10cm 1.5 4 1 1 6.00


2.25 1.25 1 1 2.81
8.81

PLATDAKELV.6.9
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatDak10cm 0.5 4 1 1 2.00


1 4.25 1 1 4.25
0.5 3.2 1 1 1.60
0.5 4.55 1 1 2.28

10.13

PLATMEJA
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatMeja10cm

PLATTANGGA
Dimensi
No. Uraian Jumlah Volume
P L H
a b c d e f g=(cxdxexf)

1 PlatTangga15cm



REKAPTOTAL
PlatTalang10cm m2
PlatSunshiding10cm 7.80 m2
PlatLantai12cm m2
PlatDak10cm 8.81 m2
PlatDak10cm 10.13 m2
PlatMeja10cm m2
PlatTangga15cm m2
Waterproofing 26.74 m2 184,196.38 4,924,950.58
sat
h

m2
m2
m2

sat
h

m2
m2
m2
m2
m2
m2

sat
h

m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

sat
h

m2
m2

sat
h

m2

m2

sat
h

m2
m2

sat
h

m2
m2
m2
m2
m2
PASANGANBATA

PANJANGBATA PANJANGBATA
ARAHX ARAHY ARAHX
KODE P(M) KODE P(M) KODE P(M)

i ii
Total i+ii
i
Total i+ii

P T V Sat
PasanganPlesteranGuratatassunshiding 1.17 m2
PasanganPlesteranGuratKanopi 0.80 m2
PasanganPlesteranGutratPenebalanpintutera 0.30 m2
PasanganPlesteranGuratgudang 0.50 m2
m2

TotalPasanganPlesteranGurat m2
ARAHY
KODE P(M)

ii

20,351.10
PEKERJAANPROFILHOLLOW

PANJANGBATUKALI
ARAHX ARAHY
KODE P(m) n Ptot(m) KODE P(m) n Ptot(m)
A

B

C

D
E
F
G
H
I
J
K
L
M
N



i ii

P
bj 1.516
W 0
m
kg/m
kg 18,632.87
PEKERJAANATAP

P L A SAT
RngkaAtap 4.00 9.00 36.00 m2

RngkaAtap 36.00 m2

ListPlank
P L Ptot A SAT
ListPlank 9.00 5.20 28.40 7.10 m2
8.35 8.35 2.09

ListPlank 9.19 m2

GENTENG Alas T n A Sat


5.20 1.90 2.00 9.88 m2
3.20 5.25 1.00 16.80
5.15 4.00 1.00 20.60

b1 b2 T n A Sat
8.00 2.75 1.90 2.00 20.43 m2

Genteng 67.71 m2

a t n p sat
JURAI 3.50 1.90 4.00 15.93 m1
1.50 m1
Jurai 17.43 m1
VOLUME GORDING 6/12

NO URAIAN P (M) B (M) H (M)


1 MOORPLAT 34.35 0.06 0.12
2 GORDING 24.55 0.06 0.12
3 NOK KAYU 11.1 0.06 0.12
4 Rangka Kuda-kuda 15.9 0.06 0.12
TOTAL

REKAP
MOORPLAT 0.24732 M3
GORDING 0.17676 M3
NOK 0.07992 M3
Rangka Kuda-kuda 0.22896 M3

usuk 45.6 17.1


50.5 30.3
45

141.1 m

NO URAIAN P (M) B (M) H (M)


1 USUK 5/7 191 0.05 0.07

NO URAIAN P (M) B (M) H (M)


1 RENG 3/4 359.6 0.03 0.04
JUMLAH VOL SAT
1 0.24732 M3
1 0.17676 M3
1 0.07992 M3
2 0.22896 M3
0.504 M3

JUMLAH VOL SAT


1 0.6685 M3 42
44
105
JUMLAH VOL SAT
1 0.43152 M3

21 3.2 67.2
16 5.15 82.4
14 15 210
359.6