VOLUME PEKERJAAN

KEGIATAN : PEMBANGUNAN KANTOR POS SEMARANG SELATAN


TAHUN ANGGARAN 2012

No Jenis Pekerjaan Perhitungan

A LANTAI 1
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan Volume = Luas area
25m = 25 x 20
= 500 m2

20m

2 Pembuatan Kantor Sementara Volume = Luas gudang


dan Gudang = 4 x 4
= 16 m2
4m

4m

3 Pengadaan Air Kerja Volume .= 1 ls

4 Pembuatan Pagar Sementara Volume = Keliling gudang


25m = 2 x ( 25 + 20
= 90 m'

20m

5 Pengadaan Skafolding Volume .= 1 ls

6 Pemasangan Bouwplank Volume = Panjang


= 2 x 68
2m = 136 m'

7 Dokumentasi Volume .= 1 ls

8 Pembuatan Papan Nama Volume .= 1 ls

II PEKERJAAN TANAH
1 Galian Footplat Volume = 1.2 x 1.2 x 2.5 x
= 100.800 m3

2.5 m
2.5 m

1,20 m

2 Galian Pondasi Volume =


1 x 1.1 x 158.00

= 173.800 m3
80

20
10

100
3 Galian Rolag Volume = 0.15 x 0.2 x 16
= 0.480 m3

20

15

4 Urugan pasir bawah pondasi t=10cm Volume = 0.1 x 1 x 158


= 15.800 m3
10

100

5 Urugan pasir bawah lantai t=10cm Volume = 0.10 x 247 m2


= 24.700 m3
10

6 Urugan pasir bawah footplat t=3cm Volume = 0.03 x 1.2 x 1.2 x


= 1.210 m3
3

120

7 Urugan pasir bawah rollag t=5cm Volume = 0.05 x 0.2 x 32


= 0.320 m3
5

15
8 Urugan tanah rollag Volume = 0.15 x 0.15 x 29.650
= 0.667 m3

15

9 Urugan tanah kembali Volume = 1


x( 100.80 + 173.800
3

= 91.533 m3

III PEKERJAAN PASANGAN & PLESTERAN


1 Pemasangan Aanstamping Volume = 0.20 x 1.00 x 158.000
= 31.600 m3
20

100

2 Pas Pondasi Batu kali Volume = 0.3 + 0.8


( )x 0.8
2
30
= 69.520 m3

80
30

80

80

3 Pas. Rolag batu bata Volume = 0.15 x 0.15 x 32


= 0.720 m3

15
4 Pas. Bata camp 1 : 5 Volume sb. X = 58.650 + 5 +
80 + 7.421 + 14.013
+ 7.421 + 22.2
= 253.018 m 2

Volume sb.Y = 47.55 + 10 +


9 + 4.229 + 21.144
+ 14.013 + 10.659
+ 5.863 + 11.421
+ 12.736
= 243.513 m2
Total volume = 253.018 + 243.513
= 496.531 cm
5 Pas. Bata camp 1 : 3 Volume sb. X = 0.35 : 4 x 253.018
= 22.139075 m 2

Volume sb. Y = 0.35 : 4 x 243.513


= 21.307 m2
Total volume = 22.139 + 21.307
= 43.446 cm
6 Plesteran camp 1 : 5 Volume = 2 x( 253.018 + 243.513
= 993.062 m2

7 Plesteran camp 1 : 3 Volume = 2 x( 22.139 + 21.307


= 86.892 m2

8 Acian Volume = 2 x( 496.531 + 43.446


= 1079.95 m2

IV PEKERJAAN BETON
1 Foot plat 120/120

Volume = 1.20 x 1.20 x 0.3 x


= 12.096 m3

KOLOM STRUKTUR 30x30

8-15

D12-20
10
LANTAI KERJA T=5 CM
20

-2.50

120

2 Lantai kerja footplat t=10cm Volume = 1.20 x 1.20 x 0.1 x


= 4.032 m3

3 Sloof 20/25 Volume = 0.20 x 0.25 x 105


= 5.250 m3

25

20
25

20

4 Sloof 15/20 Volume = 0.15 x 0.20 x 53


= 1.590 m3
20

15

5 Kolom Pedestel 30/30 Volume = 0.30 x 0.30 x 2 x


= 5.317 m3

30

30
6 Kolom 30/30 Volume = 0.30 x 0.30 x 4 x
= 10.080 m3

30

30

7 Kolom 15/15 Volume = 0.15 x 0.15 x 4 x


= 2.520 m3

15

15
8 Balok 20/30 Volume = 0.20 x 0.30 x 134
= 8.040 m3

30

20

9 Balok 15/20 Volume = 0.15 x 0.20 x 50


= 1.500 m3
20

15

10 Pelat beton Lantai 2 t= 11 cm Volume = 0.11 x 199 m2


= 21.890 m3
11

11 Pelat dak beton t= 10 cm Volume = 0.10 x 59.5 m2


= 5.950 m3
10

12 Kantilever t= 10 cm Volume = 0.10 x 1 x 3


= 0.300 m3
10

13 Tangga Beton t= 15 cm Volume = 1.5 x 0.35 x( 3.77 +


( 0.15 x 3 x 1.23
23
24
= 4.769 m3
22

21

20

19

18

17

16

15

14

13

12

11

10

09

08

07

06

05

04

03

02

01

V PEKERJAAN KUSEN PINTU + JENDELA


1 Kusen dan daun pintu P1 , 4bh
Kusen
2 KUSEN 6/12

KUPINGAN 10cm Volume = 0.06 x 0.12 x 7.24 x


KACA 5 mm
ANGKUR
= 0.209 m3

1 1

NEUT BETON

POT. 2-2 2
SKALA 1 : 20

POT. 1-1
SKALA 1 : 20

P1 ( 6 bh )
SKALA 1 : 20
2 Kusen dan daun pintu P2, 1bh

2
Kusen
KUPINGAN 10cm
Volume = 0.06 x 0.12 x 6.04 x
= 0.043 m3
ANGKUR

KUSEN 6/12

HANDLE PINTU

Daun = 0.80 x 2.50


= 2.000 m3
1 1

Total volume = 0.043 + 2.000


= 2.043 cm
NEUT BETON

2
POT. 2-2
SKALA 1 : 20

P2 ( 7 bh )
SKALA 1 : 20
POT. 1-1
SKALA 1 : 20

3 Kusen dan daun pintu P3, 4bh

2
Kusen
Volume = 0.06 x 0.12 x 6.04
= 0.043 m3
ANGKUR

KUSEN 6/12

HANDLE PINTU

Daun = 0.80 x 2.50 x 4.00


= 8.000 m3
1 1

NEUT BETON
Total volume = 0.043 + 8.000
2
POT. 2-2
SKALA 1 : 20 = 8.043 cm

P3 ( 4 bh ) POT. 1-1
SKALA 1 : 20

SKALA 1 : 20

4 Kusen dan daun pintu P4, 5bh

2 Volume .= 5 unit
KACA 5 mm

1 1

2
POT. 2-2
SKALA 1 : 20

P4 ( 9 bh )
POT. 1-1
1 1

2
POT. 2-2
SKALA 1 : 20

P4 ( 9 bh )
POT. 1-1
SKALA 1 : 20 SKALA 1 : 20
5 Kusen J1,1bh

Kusen
Volume = 0.06 x 0.12 x 15.5 x
= 0.111 m3

6 Kusen J2

Kusen
Volume = 0.06 x 0.12 x 15.6 x
= 0.113 m3

7 Kusen dan daun jendela J3, 2bh

2
Kusen
KUPINGAN 10cm

Volume = 0.06 x 0.12 x 5.38


ANGKUR

= 0.039 m3
KUSEN 6/12
KACA 5 mm

Daun = (( 0.45 x 2.00 ) - ( 1.92 x


= 0.379 m3
1 1

2 Total volume = 0.039 + 0.379


POT. 2-2
SKALA 1 : 20 = 0.418 cm

J3 ( 11 bh )
POT. 1-1
SKALA 1 : 20 SKALA 1 : 20
9 Kusen BV

2
Kusen
ANGKUR
Volume = 0.06 x 0.12 x 2.48 x
= 0.089 m3
1 1
KUSEN 6/12

BV ( 9 bh )
SKALA 1 : 20
VI PEKERJAAN PLAFOND & CAT
1 Gypsum Board Volume = 24.00 + 168.00 +
28.00 + 12
= 238 m2

2 List Plafond Volume = 55.00 + 74.00 +


18.00
= 232.50 m2

3 Pengecatan tembok Volume = 2 x( 496.531 + 43.446


= 1079.95 m2

4 Pengecatan plafond Volume = 24.00 + 168.00 +


28.00 + 12
= 238 m2

VII PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Kunci tanam biasa Volume = 9 bh
2 Kunci tanam pintu WC Volume = 5 bh
3 Engsel pintu Volume = 30 bh
4 Kaca P1, 4bh Volume = 1 x 2.5 x 2 x
= 20.0 m2

5 Kaca J1 Volume = 0.50 x 3.5


= 1.8 m2

6 Kaca J2 Volume = 4.70 x 3


= 14.1 m2

7 Kaca J3 Volume = 1.92 x 0.37 x 2


= 1.4 m2

8 Kaca BV Volume = 0.25 x 0.25 x 2 x


= 0.6 m2

VIII PEKERJAAN INSTALASI LISTRIK


1 Lampu TL 2x18 W Volume = 14 bh
2 Lampu SL 15 W Volume = 29 bh
3 Saklar tunggal Volume = 5 bh
4 Saklar ganda Volume = 7 bh
5 Stop kontak Volume = 13 bh
6 Box panel Volume = 1 unit
7 Instalasi titik lampu Volume = 43 bh

IX PEKERJAAN LANTAI
1 Pasang Keramik granito 60 x 60 Volume = 28 + 20 + 2 +
+ 4 + 3
= 101.00 m2
2 Pasang Keramik granito 40 x 40 Volume = 6 + 8 + 12
= 26.00 m2

3 Pasang Keramik lantai 30 x 30 Volume = 36 + 16


= 52.00 m2

4 Pasang Keramik lantai 30 x 30 (Tangga) Volume = 10 + 3.69


= 14.04 m2

5 Pasang Keramik lantai 20 x 20 Volume = 15 + 6 + 2 +


(KM/WC dan teras) = 36.00 m2

X PEKERJAAN SANITASI
1 Closet jongkok Volume = 5.0 bh
2 Wastafel Volume = 5.0 bh
3 Septictank & peresapan Volume = 2.0 unit
4 Kran air Volume = 9.0 bh
5 Pipa PVC 1/2" Volume = 24.7 m'
6 Pipa Galvanis 3/4" Volume = 87.5 m'
7 Bak kontrol Volume = 1.0 bh
8 Ground tank Volume = 1.0 bh
9 Tandon air Volume = 1.0 bh
10 Floor drain Volume = 5.0 bh
B LANTAI 2
I PEKERJAAN PASANGAN
1 Pas. Bata camp 1 : 5 Volume sb. X = 47.100 + 42.35 +
6.01 + 22.066 + 18.013
+ 56 + 6.013
= 217.504 m 2

Volume sb.Y = 38.54 + 122.916 +


12.987 + 8.987 +
+ 24.387
= 244.651 m2
Total volume = 217.504 + 244.651
= 462.155 cm
2 Pas. Bata camp 1 : 3 Volume sb. X = 0.35 : 4 x 217.504
= 19.032 m 2

Volume sb. Y = 0.35 : 4 x 244.651


= 21.407 m 2

Total volume = 19.032 + 21.407


= 40.439 cm
3 Plesteran camp 1 : 5 Volume = 2 x( 217.504 + 244.651
= 924.31 m 2

4 Plesteran camp 1 : 3 Volume = 2 x( 19.032 + 21.407


= 80.877 m2

5 Acian Volume = 2 x( 462.155 + 40.439


= 1005.187 m2

II PEKERJAAN BETON
1 Kolom 30/30 Volume = 0.30 x 0.30 x 4 x
= 9.720 m3

30

30

2 Kolom 15/15 Volume = 0.15 x 0.15 x 4 x


= 2.160 m3

15

15
5 Ring Balok 15/20 Volume = 0.15 x 0.20 x 134
= 4.020 m3

20

15
6 Kantilever t=10 cm Volume = 0.10 x 2 x 51
= 10.200 m3
10

III PEKERJAAN KUSEN PINTU + JENDELA


1 Kusen P1 , 2bh

2 KUSEN 6/12

KUPINGAN 10cm Kusen


KACA 5 mm
ANGKUR
Volume = 0.06 x 0.12 x 7.24 x
= 0.104 m3

1 1

NEUT BETON

POT. 2-2 2
SKALA 1 : 20

POT. 1-1
SKALA 1 : 20

P1 ( 6 bh )
SKALA 1 : 20
2 Kusen dan daun pintu P2, 4bh

2 Kusen
KUPINGAN 10cm

ANGKUR
Volume = 0.06 x 0.12 x 6.04
= 0.043 m3
KUSEN 6/12

HANDLE PINTU

Daun = 0.80 x 2.50 x 4.00


= 8.000 m3
1 1

NEUT BETON
Total volume = 0.043 + 8.000
POT. 2-2
2 = 8.043 cm
SKALA 1 : 20

P2 ( 7 bh )
SKALA 1 : 20
POT. 1-1
SKALA 1 : 20

3 Kusen P4 PVC, 5bh

2
Volume .= 4 unit
KACA 5 mm

1 1

2
POT. 2-2
SKALA 1 : 20

P4 ( 9 bh )
POT. 1-1
SKALA 1 : 20 SKALA 1 : 20

4 Kusen dan daun jendela J3, 9bh

2
Kusen
KUPINGAN 10cm
Volume = 0.06 x 0.12 x 5.38
ANGKUR

= 0.039 m3
KUSEN 6/12
KACA 5 mm

Daun = (( 0.45 x 2.00 ) - ( 1.92 x


= 1.706 m3
1 1

Total volume = 0.039 + 1.706


2
= 1.745 cm
POT. 2-2
SKALA 1 : 20
1 1

2
POT. 2-2
SKALA 1 : 20

J3 ( 11 bh )
POT. 1-1
SKALA 1 : 20 SKALA 1 : 20

5 Kusen J5
KACA 5 mm
2
KUPINGAN 10cm Kusen
ANGKUR Volume = 0.06 x 0.12 x 5.28 x
= 0.114 m3
KUSEN 6/12

1 1

POT. 2-2 2
SKALA 1 : 20

J5 ( 3 bh )
SKALA 1 : 20 POT. 1-1
SKALA 1 : 20
6 Kusen J6

KACA 5 mm

2
KUPINGAN 10cm

Kusen
ANGKUR

Volume = 0.06 x 0.12 x 11.6


KUSEN 6/12

= 0.084 m3
1 1

POT. 2-2 2
SKALA 1 : 20

J6 ( 1 bh )
SKALA 1 : 20 POT. 1-1
SKALA 1 : 20

7 Kusen J7,2bh

KACA 5 mm

2
KUPINGAN 10cm

Kusen
ANGKUR

Volume = 0.06 x 0.12 x 8.6 x


KUSEN 6/12

= 0.124 m3
1 1

POT. 2-2 2
SKALA 1 : 20

J6 ( 1 bh )
SKALA 1 : 20 POT. 1-1
SKALA 1 : 20

8 Kusen BV Kusen
Volume = 0.06 x 0.12 x 2.48 x
= 0.071 m3
2

ANGKUR

1 1
KUSEN 6/12

BV ( 9 bh )
SKALA 1 : 20

IV PEKERJAAN PLAFOND & CAT


1 Gypsum Board Volume = 36.0 + 40.0 +
40.0 + 25.0 + 6
= 184 m2

2 List Plafond Volume = 4.00 + 85.55 +

= 107.55 m2
3 Pengecatan tembok Volume = 2 x( 462.155 + 40.439
= 1005.187 m2

4 Pengecatan plafond Volume = 36.0 + 40.0 +


40.0 + 25.0 + 6
= 184 m2

V PEKERJAAN ATAP
1 Nok Volume = 0.08 x 0.12 x 12 =
2 Papan Ruiter Volume = 0.02 x 0.2 x 12 =
3 Papan Listplank Volume = 0.03 x 0.3 x 73 =
4 Atap Genteng
Volume I = 4 + 18
( )x 7.21
2
= 158.620 m2

Volume II = 1
x 12 x 7.21 x
2
= 86.520 m2

Volume III = 4.19 + 8.15


( )x 7.21
2
= 88.971 m2

Volume IV = 1
x 5 x 3.05 x
2
= 7.625 m2

Volume V =
2.5 x 3.05 x 2

= 15.250 m2

Volume total = 158.620 + 86.520 +


+ 7.625 + 15.250
= 356.986 m2
5 Rangka Atap Volume total = 356.986 m2

VI PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Kunci tanam biasa Volume = 7 bh
2 Kunci tanam pintu WC Volume = 4 bh
3 Engsel pintu Volume = 33 bh
4 Kaca J3, 9bh Volume = 1.92 x 0.37 x 9
= 6.39 m2

5 Kaca J5 Volume = 0.40 x 2.00 x 3


= 2.40 m2

6 Kaca J6 Volume = 3.00 x 2.58


= 7.74 m2

7 Kaca J7 Volume = 3.00 x 1.08


= 3.24 m2

8 Kaca BV Volume = 0.25 x 0.25 x 2 x


= 0.50 m2

VII PEKERJAAN INSTALASI LISTRIK


1 Lampu TL 2x18 W Volume = 17 bh
2 Lampu SL 15 W Volume = 15 bh
3 Saklar tunggal Volume = 6 bh
4 Saklar ganda Volume = 5 bh
5 Stop kontak Volume = 6 bh
6 Instalasi titik lampu Volume = 32 unit

VIII PEKERJAAN LANTAI


1 Pasang Keramik lantai 40 x40 Volume = 50 + 12 + 28 +
+ 16.5
= 119.00 m2
2 Pasang Keramik lantai 30 x30 Volume = 32 + 6
= 38.00 m2

3 Pasang Keramik lantai 20 x 20 (KM/WC) = 18 + 7 + 4


= 29.00 m2

IX PEKERJAAN SANITASI
1 Closet jongkok Volume = 4 bh
2 Wastafel Volume = 2.0 bh
3 Kran air Volume = 10 bh
4 Pipa PVC 2" Volume = 6.4 m'
5 Pipa PVC 1/2" Volume = 9.0 m'
6 Floor Drain Volume = 4 bh
X PEKERJAAN RANGKA BAJA

Batang Tarik = 51 x 2 =
Batang Vertikal = 14.9 x 2 =
Batang Diagonal = 16.4 x 2 =
Batang Miring = 74.3 x 2 =
Jumlah total =
1000

Kuda-kuda Baja, 2bh = 313.1 x 2


= 626.22 Kg

Batang Tarik = 51 x 1 =
Batang Vertikal = 14.9 x 1 =
Batang Diagonal = 16.4 x 1 =
Batang Miring = 74.3 x 1 =
Jumlah total =

500 Kuda-kuda Baja, 2bh = 156.55 x 2


= 313.1 Kg

1 Kuda-kuda Baja Volume = 626.2 Kg


2 1/2 Kuda-kuda Volume = 313.10 Kg
3 Jurai Volume = 148.53 Kg
4 Gording CNP 125.50.20.3,2 mm Volume = 835.213 Kg
5 Baut 10mm Volume = 160 buah
6 Baut 12mm Volume = 288 buah

C INFRASTRUKTUR
I PEKERJAAN TANAH
1 Galian Pondasi Pagar

Volume =
1 x 1.1 x 57.00
80 = 62.700 m3

20
10

100

2 Urugan Pasir bawah pondasi, t=10cm


Volume = 0.1 x 1 x 57
10 = 5.700 m3
100

3 Urugan tanah kembali Volume = 1


x( 62.70 )
3

= 20.900 m3

II PEKERJAAN PASANGAN
1 Pemasangan Aanstamping
Volume = 0.20 x 1.00 x 57.000
= 11.400 m3
20

100

2 Pas Pondasi Batu kali


Volume = 0.3 + 0.8
30 ( )x 0.8
2
= 25.080 m3

80

80

3 Pas. Bata camp 1 : 5


Volume sb. X = 1 x 0.15 x ( 6 +
18 + 8 )
= 8.550 m2
III PEKERJAAN BETON
1 kolom 15/15
Volume = 0.15 x 0.15 x 15
= 0.338 m3

15

15
2 sloof 15/20
Volume = 0.15 x 0.20 x 57
= 1.710 m3
20

15

IV PEKERJAAN LANTAI
1 Pasang paving block Volume = 25 x 20 - 242.9
= 257.100 m3

V PEKERJAAN INSTALASI AC & VENT. MEKANIK


1 Pengadaan dan Pemasangan Unit AC Sentral
- Type : Air cooled split duct Volume = 9.0 bh
Kapasitas pendingin : 100.000,00 btu / h
Karakteristik : 380 V, 1 Ph, 50 Hz
- Refrigerant : R - 22 Volume = 2.0 can
- Dudukan out door Volume = 9.0 bh
- Ongkos Pasang Volume = 9.0 bh

D POS SATPAM 2 UNIT


I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan Volume = Luas area
= 2 x 2 x 2
= 8 m2

2 Pemasangan Bouwplank Volume = Panjang x jumlah


= 2 x 4 x 2
2m = 16 m'

II PEKERJAAN TANAH
1 Galian Pondasi Volume
= 1 x 1.1 x 8 x
= 17.600 m3

80

20
10

100
20
10

100

2 Urugan pasir bawah pondasi t=10cm Volume = 0.1 x 1 x 8 x


= 1.600 m3
10

100

3 Urugan pasir bawah lantai t=10cm Volume = 0.10 x 4 x 2


= 0.800 m3
10

9 Urugan tanah kembali Volume = 1


x( 17.60 )
3

= 5.867 m3
III PEKERJAAN PASANGAN & PLESTERAN
1 Pemasangan Aanstamping Volume = 0.20 x 1.00 x 8x
= 3.200 m3

20

100

2 Pas Pondasi Batu kali Volume = 0.3 + 0.8


( )x 0.8
2
30 = 3.520 m3 x 2
= 7.04 m3

80

80

3 Pas. Bata camp 1 : 5 Volume = 2 x 4 x 4 x


= 64.000 m2

4 Pas. Bata camp 1 : 3 Volume sb. X = 0.35 : 4 x 64.000


= 5.6 m2

5 Plesteran camp 1 : 5 Volume = 2 x( 64.000 )


= 128 m2

6 Plesteran camp 1 : 3 Volume = 2 x( 5.600 )


= 11.200 m2

7 Acian Volume = 2 x( 64.000 + 5.600


= 139.20 m2

IV PEKERJAAN BETON
1 Sloof 15/20 Volume = 0.15 x 0.20 x 8 x
= 0.480 m3
20

15
2 Kolom 15/15 Volume = 0.15 x 0.15 x 4 x
= 0.720 m3

15

15
3 Ring Balk 15/20 Volume = 0.15 x 0.20 x 8 x
= 0.480 m3
20

15
20

15

4 Pelat dak beton t= 10 cm Volume = 0.10 x 2.5 x 2.5


= 1.250 m3
10
V PEKERJAAN KUSEN PINTU + JENDELA
1 Kusen dan daun pintu P2, 1bh
Kusen
2
KUPINGAN 10cm Volume = 0.06 x 0.12 x 6.04
ANGKUR = 0.043 m3

KUSEN 6/12

HANDLE PINTU

1 1

Daun = 0.80 x 2.50 x 2.00


NEUT BETON

2 = 4.000 m3
POT. 2-2
SKALA 1 : 20

Total volume = 0.043 + 4.000


= 4.043 cm

P2 ( 7 bh )
SKALA 1 : 20
POT. 1-1
SKALA 1 : 20

2 Kusen J4

Kusen
2
KACA 5 mm
Volume = 0.06 x 0.12 x 7.5 x
KUPINGAN 10cm
= 0.108 m3

ANGKUR

KUSEN 6/12
1 1

POT. 2-2 2
SKALA 1 : 20

J4 ( 2 bh )
SKALA 1 : 20
POT. 1-1
SKALA 1 : 20

VI PEKERJAAN PLAFOND & CAT


1 Gypsum Board Volume = 2.00 x 2.00 x
= 8 m2

2 List Plafond Volume = 4.00 x 6.00 x

= 48.00 m2

3 Pengecatan tembok Volume = 2 x( 64.000 + 5.600


= 139.20 m2

4 Pengecatan plafond Volume = 2.00 x 2.00 x


= 8 m2

VII PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Kunci tanam biasa Volume = 2 bh
2 Engsel pintu Volume = 6 bh
3 Kaca J4 Volume = 0.50 x 1 x 6 x
= 6.0 m2

VIII PEKERJAAN INSTALASI LISTRIK


1 Lampu SL 15 W Volume = 2 bh
2 Saklar tunggal Volume = 2 bh
3 Stop kontak Volume = 2 bh
4 Instalasi titik lampu Volume = 2 bh

IX PEKERJAAN LANTAI
1 Pasang Keramik lantai 30 x 30 Volume = 2 x 2 x 2
= 8.00 m2
E PEKERJAAN
KANTOR POS SEMARANG SELATAN
NGGARAN 2012

Perhitungan

28
28

173.800 )

x 158.00
44.813 +
14.013 + 14

37.608 +
21.144
+ 47.7
+ 11.59

253.018

243.513

243.513 )

21.307 )

43.446 )

28

28
28
28

28

4.26 ) +
)
4
1
1

0.37 )) x 2
5
6.00 +

85.50 +

43.446 )

6.00 +

32 + 12
9 + 4
19.949 +
18.013

14.013 +
22.821

217.504

244.651

244.651 )

21.407 )

40.439 )

27

24
2
0.37 )) x 9
3
2.00

9.0 +
+ 28

18.00
40.439 )

9.0 +
+ 28

0.1152 m3
0.048 m3
0.657 m3
x 2

x 2

88.971

4
8 + 4.5
102.0
29.78
32.80
148.53 +
313.07046 kg

51.0
14.89
16.40
74.26 +
156.54 kg
x 57.00

25 +
2
2
2

x 8.00

64.000

5.600 )

4 x 2

2
x 2
2

2.00

2.00

5.600 )

2.00
2
VOLUME PEKERJAAN
KEGIATAN : PEMBANGUNAN RUMAH TINGGAL SEDERHANA BLOK E
TAHUN ANGGARAN 2013

NO JENIS PEKERJAAN (SKET) PERHITUNGAN VOLUME


BQ (BILL OF QUANTITY)

NO. URAIAN PEKERJAAN VOL SAT NO. URAIAN PEKERJAAN VOL SAT
I PEKERJAAN PERSIAPAN VI PEKERJAAN LANTAI & DINDING
1 Pembersihan Lahan m2
1 Pasang Keramik polos 30 x 30, ex. Asia Tile m2
2 Pengukuran dan pemasangan bowplank m2 2 Pasang Keramik lantai 20 x 20 (KM/WC) m2
3 Pembuatan Direksi Keet m2 3 Pasang Keramik dinding 20 x 25 (KM/WC) m2
4 Pengadaan Air kerja ls 4 Pasang List Keramik 10 x 20 (KM/WC) m2
5 Pembuatan pagar sementara m2
6 Pengadaan skafolding ls VII PEKERJAAN KUSEN PINTU + JENDELA
7 Dokumentasi ls 1 Kusen P1 , 4bh m3
8 Papan IMB ls Daun pintu P1 m2
2 P2 pintu PVC set kamar mandi unit
II PEKERJAAN TANAH 3 Kusen J1 , 2bh m3
1 Galian pondasi t=90 cm m3 Daun jendela J1 m2
2 Galian Pondasin rollag t=80 cm m3 4 Kusen J2 , 4bh m3
3 Urugan pasir bawah pondasi t=10cm m3 Daun jendela J2 m2
4 Urugan pasir bawah rollag t=10cm m3 5 Kusen J3 , 2bh m3
5 Urugan pasir bawah lantai t=10cm m3 6 Kusen J4 , 1bh m3
6 Urugan tanah kembali m3 Daun jendela J4 m2
7 Kusen J5 , 1bh m3
III PEKERJAAN PONDASI Daun jendela J4 m2
1 Pas Pondasi Batu kali 1pc:5pp m3
2 Pas Pondasi Batu kali rollag m3 VIII PEKERJAAN ATAP
3 Pas. Rollag batu bata 1pc:3pp m3 1 Pasang konstruksi kuda-kuda rangka kayu kamfer bentang 7,5m m3
2 Pasang gording 8/12 kayu kamfer m3
IV PEKERJAAN BETON 3 Pasang usuk 5/7 dan reng 2/3 kayu jati m3
1 Kolom 15/30 m3 4 Pasang Lisplank 3/30 kayu kamfer m1
2 Kolom 15/15 m3 5 Pasang atap genteng kodok/ glasur m3
3 Kolom 15/15 gunungan m3
4 Sloof 15/20 m3 IX PEKERJAAN LANGIT-LANGIT
5 Ring Balk 15/15 m3 1 Pasang rangka kayu jati plafond gypsumboard (60x120), t=9mm, m3
6 Pelat dak beton, t=11 cm m3 2 Pasang plafond gypsumboard (60x120), t=9mm, m2
7 Lantai kerja bawah keramik t=5 cm m3 3 List plafond gypsum lebar 5-10 cm m1
8 Kantilever, t=10 cm m3
X PEKERJAAN KUNCI, KACA & PENGGANTUNG
V PEKERJAAN DINDING & PLESTERAN 1 Pasang kunci tanam pintu 2 slag bh
1 Pas. Batu bata 1pc:5pp m2
2 Pasang handle pintu bh
2 Pas. Batu bata 1pc:3pp m2 3 Engsel pintu standar 4" bh
3 Plesteran dinding 1pc:5pp m2 4 Engsel jendela standar 3" bh
4 Plesteran dinding 1pc:3pp m2 5 Engsel bebas J5 bh
5 Acian m2 6 Pasang grendel jendela bh
7 Pasang kaca t=5mm m2
8 Pasang angkur pintu & jendela bh
NO. URAIAN PEKERJAAN VOL SAT
XI PEKERJAAN SANITASI AIR
Instalasi Air Bersih
1 Pasang pipa PVC 3/4" m1
2 Pasang pipa galvanis 1" m1
3 Pasang keni 1" bh
4 Pasang Tee 1" ke 3/4" bh
5 Pasang penyambung air bersih dari PAM bh
Instalasi Air Kotor
1 Pasang pipa PVC 3" m1
2 Pasang keni 1" bh
3 Pasang Tee 2" ke 3" bh
4 Pasang Septictank & Peresapan unit
5 Pasang bak kontrol bh
6 Pasang Closet jongkok, ex.INA bh
7 Floor drain KM/WC bh
8 Wastafel bh
9 Kran air bh
9 Tandon air bh
10 Pasang bak mandi fiberglass v=1m3 unit

XII PEKERJAAN INSTALASI LISTRIK


1 Pasang instalasi lampu kabel NYM3 x 2,5mm m1
2 Pasang saklar tunggal bh
3 Pasang saklar ganda bh
4 Pasang Stop kontak bh
5 Lampu SL 18 W bh
6 Lampu SL 10 W bh
7 Pasang panel listrik bh
8 Pasang Box sekering bh
9 Pasang penyambung daya ke PLN unit
10 Instalasi titik lampu bh

XIII PEKERJAAN PENGECATAN


1 Cat tembok dalam, ex. Mowillex m2
2 Cat tembok luar, ex. Catylac m2
3 Pengecatan plafond m2
4 Pengecatan list plafond m1
5 Pengecatan kusen pintu &jendela m2

XIV PEKERJAAN FINISHING


1 Pembersihan lahan setelah pekerjaan m2
2 Landscaping taman unit
3 Pasang ornamen batu alam m2
4 Pasang paving block m2
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )

No. Uraian Pekerjaan Total Harga

I PEKERJAAN PERSIAPAN Rp
II PEKERJAAN TANAH Rp
III PEKERJAAN PONDASI Rp
IV PEKERJAAN BETON Rp
V PEKERJAAN DINDING & PLESTERAN Rp
VI PEKERJAAN LANTAI & DINDING Rp
VII PEKERJAAN KUSEN PINTU + JENDELA Rp
VIII PEKERJAAN ATAP Rp
IX PEKERJAAN LANGIT-LANGIT Rp
X PEKERJAAN KUNCI, KACA & PENGGANTUNG Rp
XI PEKERJAAN SANITASI AIR Rp
XII PEKERJAAN INSTALASI LISTRIK Rp
XIII PEKERJAAN PENGECATAN Rp
XIV PEKERJAAN FINISHING Rp

Jumlah ( A ) Rp
PPN 10% ( B ) Rp
Jumlah Total ( B ) Rp
Jumlah Dibulatkan Rp
Terbilang :

Yogyakarta, Mei 2013

Perencana
RENCANA ANGGARAN BIAYA (RAB )
Err:509
Err:509

NO. URAIAN PEKERJAAN VOL SAT HARGA SAT. JML HARGA JML TOTAL
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan 177.000 m2 Rp. 6,300.00 Rp. 1,115,100.00
2 Pengukuran dan pemasangan bowplank 112.000 m2 Rp. 747,887.50 Rp. 83,763,400.00
3 Pembuatan Direksi Keet 16.000 m2 Rp. 500,000.00 Rp. 8,000,000.00
4 Pengadaan Air kerja 1.000 ls Rp. 128,560.00 Rp. 128,560.00
5 Pembuatan pagar sementara 55.400 m2 Rp. 664,418.75 Rp. 36,808,798.75
6 Pengadaan skafolding 1 ls Rp. 106,960.00 Rp. 106,960.00
7 Dokumentasi 1 ls Rp. 750,000.00 Rp. 750,000.00
8 Papan IMB 1 ls Rp. 750,000.00 Rp. 750,000.00
Rp. 131,422,818.75

II PEKERJAAN TANAH
1 Galian pondasi t=90 cm 92.615 m3 Rp. Err:509 Rp. Err:509
2 Galian Pondasin rollag t=80 cm 5.581 m3 Rp. 29,750.00 Rp. 166,033.56
3 Urugan pasir bawah pondasi t=10cm 8.991 m3 Rp. 29,750.00 Rp. 267,482.25
4 Urugan pasir bawah rollag t=10cm 0.581 m3 Rp. 119,900.00 Rp. 69,703.87
5 Urugan pasir bawah lantai t=10cm 6.150 m3 Rp. Err:509 Rp. Err:509
6 Urugan tanah kembali 32.732 m3 Rp. 29,750.00 Rp. 973,780.57
Rp. Err:509

III PEKERJAAN PONDASI


1 Pas Pondasi Batu kali 1pc:5pp 42.848 m3 Rp. Err:509 Rp. Err:509
2 Pas Pondasi Batu kali rollag 2.325 m3 Rp. 461,305.00 Rp. 1,072,718.65
3 Pas. Rollag batu bata 1pc:3pp 0.062 m3 Rp. 66,115.00 Rp. 4,118.14
Rp. Err:509

IV PEKERJAAN BETON
1 Kolom 15/30 0.545 m3 Rp. Err:509 Rp. Err:509
2 Kolom 15/15 1.755 m3 Rp. 526,634.00 Rp. 924,479.66
3 Kolom 15/15 gunungan 0.558 m3 Rp. 2,952,411.00 Rp. 1,648,773.92
4 Sloof 15/20 2.997 m3 Rp. 2,952,411.00 Rp. 8,848,375.77
5 Ring Balk 15/15 2.248 m3 Rp. 5,710,371.00 Rp. 12,835,486.42
6 Pelat dak beton, t=11 cm 1.210 m3 Rp. 5,710,371.00 Rp. 6,907,978.56
7 Lantai kerja bawah keramik t=5 cm 3.075 m3 Rp. 5,710,371.00 Rp. 17,559,390.83
8 Kantilever, t=10 cm 0.739 m3 Rp. 2,889,931.00 Rp. 2,135,659.01
Rp. Err:509
V PEKERJAAN DINDING & PLESTERAN
1 Pas. Batu bata 1pc:5pp 222.391 m2 Rp. 6,500,000.00 Rp. 1,445,541,500.00
2 Pas. Batu bata 1pc:3pp 28.211 m2 Rp. 6,500,000.00 Rp. 183,371,500.00
3 Plesteran dinding 1pc:5pp 444.782 m2 Rp. 6,500,000.00 Rp. 2,891,083,000.00
4 Plesteran dinding 1pc:3pp 56.422 m2 Rp. 250,000.00 Rp. 14,105,500.00
5 Acian 501.204 m2 Rp. 6,500,000.00 Rp. 3,257,826,000.00
Rp. 7,791,927,500.00

VI PEKERJAAN LANTAI & DINDING


1 Pasang Keramik polos 30 x 30, ex. Asia Tile 57.000 m2 Rp. 26,395.00 Rp. 1,504,515.00
2 Pasang Keramik lantai 20 x 20 (KM/WC) 2.250 m2 Rp. 19,303.00 Rp. 43,431.75
3 Pasang Keramik dinding 20 x 25 (KM/WC) 1.020 m2 Rp. 54,794.10 Rp. 55,889.98
4 Pasang List Keramik 10 x 20 (KM/WC) 5.180 m2 Rp. 54,794.10 Rp. 283,833.44
Rp. 1,887,670.17

VII PEKERJAAN KUSEN PINTU + JENDELA


1 Kusen P1 , 4bh 0.151 m3 Rp. 13,630.00 Rp. 2,056.93
Daun pintu P1 6.921 m2 Rp. 2,203,385.10 Rp. 15,249,187.60
2 P2 pintu PVC set kamar mandi 1.000 unit Rp. 41,998.00 Rp. 41,998.00
3 Kusen J1 , 2bh 0.060 m3 Rp. 28,700.00 Rp. 1,727.51
Daun jendela J1 0.573 m2 Rp. 0.00 Rp. 0.00
4 Kusen J2 , 4bh 0.130 m3 Rp. 0.00 Rp. 0.00
Daun jendela J2 1.488 m2 Rp. 690.00 Rp. 1,026.72
5 Kusen J3 , 2bh 0.086 m3 Rp. 76,000.00 Rp. 6,566.40
6 Kusen J4 , 1bh 0.046 m3 Rp. Err:509 Rp. Err:509
Daun jendela J4 0.230 m2 Rp. 0.00 Rp. 0.00
7 Kusen J5 , 1bh 0.125 m3 Rp. 71,200.00 Rp. 8,889.18
Daun jendela J4 2.056 m2 Rp. 70,600.00 Rp. 145,153.60
Rp. Err:509

VIII PEKERJAAN ATAP


1 Pasang konstruksi kuda-kuda rangka kayu kamfer bentang 7 0.916 m3 Rp. Err:509 Rp. Err:509
2 Pasang gording 8/12 kayu kamfer 0.177 m3 Rp. 129,099.00 Rp. 22,804.05
3 Pasang usuk 5/7 dan reng 2/3 kayu jati 0.874 m3 Rp. 112,492.69 Rp. 98,318.62
4 Pasang Lisplank 3/30 kayu kamfer 20.500 m1 Rp. 112,492.69 Rp. 2,306,100.25
5 Pasang atap genteng kodok/ glasur 78.900 m3 Rp. 114,655.00 Rp. 9,046,279.50
Rp. Err:509

IX PEKERJAAN LANGIT-LANGIT
1 Pasang rangka kayu jati plafond gypsumboard (60x120), t=9 0.806 m3 Rp. 319,825.00 Rp. 257,778.95
2 Pasang plafond gypsumboard (60x120), t=9mm, 57.000 m2 Rp. 984,825.00 Rp. 56,135,025.00
3 List plafond gypsum lebar 5-10 cm 70.000 m1 Rp. 2,203,385.10 Rp. 154,236,957.00
Rp. 210,629,760.95
X PEKERJAAN KUNCI, KACA & PENGGANTUNG
1 Pasang kunci tanam pintu 2 slag 5 bh Rp. 0.00 Rp. 0.00
2 Pasang handle pintu 5 bh Rp. 0.00 Rp. 0.00
3 Engsel pintu standar 4" 15 bh Rp. 0.00 Rp. 0.00
4 Engsel jendela standar 3" 14 bh Rp. 0.00 Rp. 0.00
5 Engsel bebas J5 8 bh Rp. 0.00 Rp. 0.00
6 Pasang grendel jendela 9 bh Rp. 0.00 Rp. 0.00
7 Pasang kaca t=5mm 11.8 m2 Rp. 0.00 Rp. 0.00
8 Pasang angkur pintu & jendela 60 bh Rp. 0.00 Rp. 0.00
Rp. 0.00

XI PEKERJAAN SANITASI AIR


Instalasi Air Bersih
1 Pasang pipa PVC 3/4" 27.400 m1 Rp. 0.00 Rp. 0.00
2 Pasang pipa galvanis 1" 32.500 m1 Rp. 0.00 Rp. 0.00
3 Pasang keni 1" 8 bh Rp. 0.00 Rp. 0.00
4 Pasang Tee 1" ke 3/4" 1 bh Rp. 0.00 Rp. 0.00
5 Pasang penyambung air bersih dari PAM 1 bh Rp. 0.00 Rp. 0.00
Instalasi Air Kotor
1 Pasang pipa PVC 3" 31.500 m1 Rp. 0.00 Rp. 0.00
2 Pasang keni 1" 2 bh Rp. 0.00 Rp. 0.00
3 Pasang Tee 2" ke 3" 1 bh Rp. 0.00 Rp. 0.00
4 Pasang Septictank & Peresapan 1 unit Rp. 0.00 Rp. 0.00
5 Pasang bak kontrol 2 bh Rp. 0.00 Rp. 0.00
6 Pasang Closet jongkok, ex.INA 1 bh Rp. 0.00 Rp. 0.00
7 Floor drain KM/WC 1 bh Rp. 0.00 Rp. 0.00
8 Wastafel 1 bh Rp. 0.00 Rp. 0.00
9 Kran air 4 bh Rp. 0.00 Rp. 0.00
9 Tandon air 1 bh Rp. 0.00 Rp. 0.00
10 Pasang bak mandi fiberglass v=1m 3 1 unit Rp. 0.00 Rp. 0.00
Rp. 0.00

XII PEKERJAAN INSTALASI LISTRIK


1 Pasang instalasi lampu kabel NYM3 x 2,5mm 46.250 m1 Rp. 0.00 Rp. 0.00
2 Pasang saklar tunggal 4 bh Rp. 0.00 Rp. 0.00
3 Pasang saklar ganda 2 bh Rp. 0.00 Rp. 0.00
4 Pasang Stop kontak 5 bh Rp. 0.00 Rp. 0.00
5 Lampu SL 18 W 5 bh Rp. 0.00 Rp. 0.00
6 Lampu SL 10 W 3 bh Rp. 0.00 Rp. 0.00
7 Pasang panel listrik 1 bh Rp. 0.00 Rp. 0.00
8 Pasang Box sekering 1 bh Rp. 0.00 Rp. 0.00
9 Pasang penyambung daya ke PLN 1 unit Rp. 0.00 Rp. 0.00
10 Instalasi titik lampu 8 bh Rp. 0.00 Rp. 0.00
Rp. 0.00
XIII PEKERJAAN PENGECATAN
1 Cat tembok dalam, ex. Mowillex 9.000 m2 Rp. 0.00 Rp. 0.00
2 Cat tembok luar, ex. Catylac 32.600 m2 Rp. 0.00 Rp. 0.00
3 Pengecatan plafond 0.000 m2 Rp. 0.00 Rp. 0.00
4 Pengecatan list plafond 0.000 m1 Rp. 0.00 Rp. 0.00
5 Pengecatan kusen pintu &jendela 17.157 m2 Rp. 0.00 Rp. 0.00
Rp. 0.00

XIV PEKERJAAN FINISHING


1 Pembersihan lahan setelah pekerjaan 1.000 m2 Rp. 0.00 Rp. 0.00
2 Landscaping taman 1 unit Rp. 0.00 Rp. 0.00
3 Pasang ornamen batu alam 28.703 m2 Rp. 0.00 Rp. 0.00
4 Pasang paving block 21.000 m2 Rp. 0.00 Rp. 0.00
Rp. 0.00
JML TOTAL : Rp. Err:509
Dibulatkan: Rp. Err:509
Terbilang :Satu Milyar Lima Ratus Empat Puluh Tiga Juta Rupiah

Yogyakarta, Mei 2013

Perencana
RENCANA ANGGARAN BIAYA (RAB )

NO. URAIAN PEKERJAAN VOL SAT HARGA SAT. JML HARGA JML TOTAL NO. URAIAN PEKERJAAN VOL SAT HARGA SA
I PEKERJAAN PERSIAPAN V PEKERJAAN DINDING & PLESTERAN
1 Pembersihan Lahan m2
Rp. Rp. 1 Pas. Batu bata 1pc:5pp m2 Rp.
2 Pengukuran dan pemasangan bowplank m2 Rp. Rp. 2 Pas. Batu bata 1pc:3pp m2 Rp.
3 Pembuatan Direksi Keet m2 Rp. Rp. 3 Plesteran dinding 1pc:5pp m2 Rp.
4 Pengadaan Air kerja ls Rp. Rp. 4 Plesteran dinding 1pc:3pp m2 Rp.
5 Pembuatan pagar sementara m1 Rp. Rp. 5 Acian m2 Rp.
6 Pengadaan skafolding ls Rp. Rp.
7 Dokumentasi ls Rp. Rp.
8 Papan IMB ls Rp. Rp. VI PEKERJAAN LANTAI & DINDING
Rp. 0.00 1 Pasang Keramik polos 30 x 30, ex. Asia Tile m2 Rp.
2 Pasang Keramik lantai 20 x 20 (KM/WC) m2 Rp.
II PEKERJAAN TANAH 3 Pasang Keramik dinding 20 x 25 (KM/WC) m2 Rp.
1 Galian pondasi t=90 cm m3 Rp. Rp. 4 Pasang List Keramik 10 x 20 (KM/WC) m2 Rp.
2 Galian Pondasin rollag t=80 cm m3 Rp. Rp.
3 Urugan pasir bawah pondasi t=10cm m3 Rp. Rp.
4 Urugan pasir bawah rollag t=10cm m3 Rp. Rp. VII PEKERJAAN KUSEN PINTU + JENDELA
5 Urugan pasir bawah lantai t=10cm m3 Rp. Rp. 1 Kusen P1 , 4bh m3 Rp.
6 Urugan tanah kembali m3 Rp. Rp. Daun pintu P1 m2 Rp.
Rp. 0.00 2 P2 pintu PVC set kamar mandi unit Rp.
3 Kusen J1 , 2bh m3 Rp.
III PEKERJAAN PONDASI Daun jendela J1 m2 Rp.
1 Pas Pondasi Batu kali 1pc:5pp m3 Rp. Rp. 4 Kusen J2 , 4bh m3 Rp.
2 Pas Pondasi Batu kali rollag m3 Rp. Rp. Daun jendela J2 m2 Rp.
3 Pas. Rollag batu bata 1pc:3pp m3 Rp. Rp. 5 Kusen J3 , 2bh m3 Rp.
Rp. 0.00 6 Kusen J4 , 1bh m3 Rp.
Daun jendela J4 m2 Rp.
IV PEKERJAAN BETON 7 Kusen J5 , 1bh m3 Rp.
1 Kolom 15/30 m3 Rp. Rp. Daun jendela J4 m2 Rp.
2 Kolom 15/15 m3 Rp. Rp.
3 Kolom 15/15 gunungan m3 Rp. Rp.
4 Sloof 15/20 m3 Rp. Rp. VIII PEKERJAAN ATAP
5 Ring Balk 15/15 m3 Rp. Rp. 1 Konstruksi kuda-kuda rangka kayu kamfer m3 Rp.
6 Pelat dak beton, t=11 cm m3 Rp. Rp. 2 Pasang gording 8/12 kayu kamfer m3 Rp.
7 Lantai kerja bawah keramik t=5 cm m3 Rp. Rp. 3 Pasang usuk 5/7 dan reng 2/3 kayu jati m2 Rp.
8 Kantilever, t=10 cm m3 Rp. Rp. 4 Pasang Lisplank 3/30 kayu kamfer m1 Rp.
Rp. 0.00 5 Pasang atap genteng kodok/ glasur m2 Rp.
IX PEKERJAAN LANGIT-LANGIT XII PEKERJAAN INSTALASI LISTRIK
1 Pasang rangka plafond kayu jati (60x120) m 3
Rp. Rp. 1 Pasang instalasi lampu kabel NYM3 x 2,5mm m1 Rp.
2 Pasang plafond gypsumboard t=9mm, m2 Rp. Rp. 2 Pasang saklar tunggal bh Rp.
3 List plafond gypsum lebar 5-10 cm m1 Rp. Rp. 3 Pasang saklar ganda bh Rp.
Rp. 0.00 4 Pasang Stop kontak bh Rp.
5 Lampu SL 18 W bh Rp.
X PEKERJAAN KUNCI, KACA & PENGGANTUNG 6 Lampu SL 10 W bh Rp.
1 Pasang kunci tanam pintu 2 slag bh Rp. Rp. 7 Pasang panel listrik bh Rp.
2 Pasang handle pintu bh Rp. Rp. 8 Pasang Box sekering bh Rp.
3 Engsel pintu standar 4" bh Rp. Rp. 9 Pasang penyambung daya ke PLN unit Rp.
4 Engsel jendela standar 3" bh Rp. Rp. 10 Instalasi titik lampu bh Rp.
5 Engsel bebas J5 bh Rp. Rp.
6 Pasang grendel jendela bh Rp. Rp.
7 Pasang kaca t=5mm m2 Rp. Rp. XIII PEKERJAAN PENGECATAN
8 Pasang angkur pintu & jendela bh Rp. Rp. 1 Cat tembok dalam, ex. Mowillex m2 Rp.
Rp. 0.00 2 Cat tembok luar, ex. Catylac m2 Rp.
3 Pengecatan plafond m2 Rp.
XI PEKERJAAN SANITASI AIR 4 Pengecatan list plafond m1 Rp.
Instalasi Air Bersih 5 Pengecatan kusen pintu &jendela m2 Rp.
1 Pasang pipa PVC 3/4" m1 Rp. Rp.
2 Pasang pipa galvanis 1" m1 Rp. Rp.
3 Pasang keni 1" bh Rp. Rp. XIV PEKERJAAN FINISHING
4 Pasang Tee 1" ke 3/4" bh Rp. Rp. 1 Pembersihan lahan setelah pekerjaan m2 Rp.
5 Pasang penyambung air bersih dari PAM bh Rp. Rp. 2 Landscaping taman unit Rp.
Instalasi Air Kotor 3 Pasang ornamen batu alam m2 Rp.
1 Pasang pipa PVC 3" m1 Rp. Rp. 4 Pasang paving block m2 Rp.
2 Pasang keni 1" bh Rp. Rp.
3 Pasang Tee 2" ke 3" bh Rp. Rp.
4 Pasang Septictank & Peresapan unit Rp. Rp.
5 Pasang bak kontrol bh Rp. Rp.
6 Pasang Closet jongkok, ex.INA bh Rp. Rp.
7 Floor drain KM/WC bh Rp. Rp.
8 Wastafel bh Rp. Rp.
9 Kran air bh Rp. Rp.
9 Tandon air bh Rp. Rp.
10 Pasang bak mandi fiberglass v=1m3 unit Rp. Rp.
Rp. 0.00
NCANA ANGGARAN BIAYA (RAB )

HARGA SAT. JML HARGA JML TOTAL

Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 0.00

Rp.
Rp.
Rp.
Rp.
Rp. 0.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 0.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 0.00
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 0.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 0.00

Rp.
Rp.
Rp.
Rp.
Rp. 0.00
JML TOTAL : Rp. 0.00

Yogyakarta, Mei 2013

Perencana
JADWAL PELAKSANAAN ( TIME SCH
Err:509
Err:509

BOBOT Bulan 1
No. JENIS PEKERJAAN VOL SAT DURASI
(%) 1.000 2 3 4 5

A Err:509
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan 500.00 m2 1 0.216 0.216
2 Pembuatan Kantor Sementara dan Gudang 16.00 m2 1 0.796 0.796
3 Pengadaan Air Kerja 1.00 ls 20 0.038 0.002 0.002 0.002 0.002 0.002
4 Pembuatan Pagar Sementara 90.00 m' 1 3.214 3.214
5 Pengadaan Skafolding 1.00 ls 1 0.042 0.042
6 Pemasangan Bouwplank 136.00 m' 1 1.044 1.044
7 Dokumentasi 1.00 ls 20 0.056 0.003 0.003 0.003 0.003 0.003
8 Pembuatan Papan Nama 1.00 ls 2 0.056 0.028 0.028

II PEKERJAAN TANAH
1 Galian Footplat 100.80 m3 4 0.254 0.064 0.064 0.064 0.064
2 Galian Pondasi 173.80 m3 4 0.358 0.089 0.089 0.089 0.089
3 Galian Rolag 0.48 m3 1 0.001 0.001
4 Urugan pasir bawah pondasi 15.80 m 3
1 0.113 0.113
5 Urugan tanah kembali 91.53 m 3
1 0.140
6 Urugan pasir bawah lantai 24.70 m 3
1 0.051
7 Urugan pasir bawah footplat 1.21 m 3
1 0.009 0.009
8 Urugan pasir bawah rollag 0.32 m 3
1 0.204 0.204
9 Urugan tanah rollag 0.67 m3 1 0.005

III PEKERJAAN PONDASI


1 Pemasangan Aanstamping 31.600 m3 2 0.581 0.291 0.291
2 Pas Pondasi Batu kali 69.520 m 3
3 2.643 0.881 0.881
3 Pas. Rolag batu bata 0.720 m 3
1 0.004
4 Pas. Bata camp 1 : 5 496.531 m2 3 2.481
5 Pas. Bata camp 1 : 3 43.176 m2 3 0.230
6 Plesteran camp 1 : 5 993.062 m2 2 2.180
7 Plesteran camp 1 : 3 86.352 m 2
2 0.206
8 Acian 1,079.414 m 2
2 1.324

IV PEKERJAAN BETON
1 Foot plat 120/120 12.10 m3 4 2.463 0.616 0.616
2 Lantai kerja footplat t=10 cm 4.03 m3 2 0.154 0.077 0.077
3 Sloof 15/20 1.59 m3 2 0.399
4 Sloof 20/25 5.25 m3 3 1.318
5 Kolom Pedestel 30/30 5.32 m 3
3 2.516
6 Kolom30/30 10.08 m 3
3 4.769
7 Kolom 15/15 2.52 m 3
2 1.192
8 Balok 20/30 8.04 m 3
3 2.945
9 Balok 15/20 1.50 m 3
2 0.510
10 Pelat beton lantai 2, t=11 cm 21.89 m 3
3 7.342
11 Pelat dak beton, t=10 cm 5.95 m 3
3 1.996
12 Kantilever, t=10 cm 0.30 m 3
2 0.101
13 Tangga Beton 4.77 m 3
3 1.623

V PEKERJAAN DINDING & PLESTERAN


1 Kusen P1 , 4bh 0.21 m3 3 0.102
2 Kusen dan daun pintu P2, 1bh 2.04 m 3
1 0.999
3 Kusen dan daun pintu P3, 4bh 8.04 m 3
3 3.934
4 Kusen P4 PVC, 5bh 5.00 unit 2 0.094
5 Kusen J1 0.11 m3 1 0.055
6 Kusen J2 0.11 m 3
2 0.055
7 Kusen dan daun pintu J3, 2 bh 0.42 m 3
2 0.204
8 Kusen BV 0.09 m 3
2 0.044

VI PEKERJAAN LANTAI & DINDING


1 Gypsum Board rangka hollow 238.00 m2 3 0.436
2 List Plafond 232.55 m' 2 0.158
3 Pengecatan tembok 1,079.41 m2 3 0.823
4 Pengecatan plafond 238.00 m2 2 0.182
VII PEKERJAAN KUSEN PINTU + JENDELA
1 Kunci tanam biasa 9.00 bh 1 0.101
2 Kunci tanam pintu WC 5.00 bh 1 0.026
3 Engsel pintu 30.00 bh 1 0.031
4 Kaca P1, 4bh 20.00 m2 1 0.115
5 Kaca J1 1.75 m2 1 0.010
6 Kaca J2 14.10 m 2
1 0.082
7 Kaca J3 1.42 m 2
1 0.008
8 Kaca BV 0.63 m 2
1 0.004

VIII PEKERJAAN ATAP


1 Lampu TL 2x18 W 14.00 bh 1 0.028
2 Lampu SL 15 W 29.00 bh 1 0.034
3 Saklar tunggal 5.00 bh 1 0.008
4 Saklar ganda 7.00 bh 1 0.011
5 Stop kontak 13.00 bh 1 0.020
6 Box panel 1.00 unit 1 0.023
7 Instalasi titik lampu 43.00 bh 3 0.050

IX PEKERJAAN LANGIT-LANGIT
1 Pasang Keramik granito 60 x 60 101.00 m2 3 2.616
2 Pasang Keramik granito 40 x 40 26.00 m 2
3 0.505
3 Pasang Keramik lantai 30 x 30 52.00 m2 2 0.427
4 Pasang Keramik lantai 30 x 30 (Tangga) 14.04 m2 1 0.115
5 Pasang Keramik lantai 20 x 20 (KM/WC dan teras) 36.00 m2 1 0.301

X PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Closet jongkok 5.00 bh 2 0.106
2 Wastafel 5.00 bh 1 0.368
3 Septictank & peresapan 2.00 unit 4 0.332
4 Kran air 9.00 bh 1 0.014
5 Pipa PVC 1/2" 24.70 m' 2 0.023
6 Pipa Galvanis 3/4" 87.50 m' 3 0.137
7 Bak kontrol 1.00 bh 1 0.008
8 Ground tank 1.00 bh 4 0.075
9 Tandon air 1.00 bh 1 0.019
10 Floor drain 5.00 bh 1 0.017
B Err:509
Err:509 Err:509
1 Pas. Bata camp 1 : 5 462.16 m2 3 2.309
2 Pas. Bata camp 1 : 3 40.44 m 2
3 0.216
3 Plesteran camp 1 : 5 924.31 m 2
2 2.029
4 Plesteran camp 1 : 3 80.88 m 2
2 0.192
5 Acian 1,005.19 m 2
2 1.233

Err:509 Err:509
1 Kolom 30/30 9.72 m3 3 4.599
2 Kolom 15/15 2.16 m 3
2 1.022
3 Ring balok 15/20 4.02 m 3
3 1.902
4 Kantilever, t=10 cm 10.20 m 3
2 3.421

Err:509 Err:509
1 Kusen P1 , 2bh 0.10 m3 2 0.051
2 Kusen dan daun pintu P2, 4bh 8.04 m 3
2 3.934
3 Kusen P4 PVC, 5bh 4.00 unit 1 0.075
4 Kusen dan daun jendela J3, 9bh 1.75 m3 2 0.853
5 Kusen J5 0.11 m 3
2 0.056
6 Kusen J6 0.08 m 3
2 0.041
7 Kusen J7, 2bh 0.12 m 3
2 0.061
Kusen BV 0.07 m 3
2 0.035

Err:509 Err:509
1 Gypsum Board rangka hollow 184.00 m2 3 0.337
2 List Plafond 107.55 m' 2 0.073
3 Pengecatan tembok 1,005.19 m2 3 0.767
4 Pengecatan plafond 184.00 m 2
3 0.140

Err:509 Err:509
1 Rangka Atap LT 1 & 2 356.99 m2 4 3.501
2 Nok 0.12 m' 2 0.070
3 Papan Ruiter 0.05 m' 2 0.000
4 Papan Listplank 0.66 m' 1 0.005
5 Atap Genteng 356.99 m 2
4 1.588

Err:509 Err:509
1 Kunci tanam biasa 7.00 bh 1 0.079
2 Kunci tanam pintu WC 12.00 bh 1 0.062
3 Engsel pintu 33.00 bh 1 0.034
4 Kaca J3 6.39 m2 2 0.037
5 Kaca J5 2.40 m2 2 0.014
6 Kaca J6 7.74 m 2
2 0.045
7 Kaca J7 3.24 m 2
2 0.019
8 Kaca BV 3.36 m2 2 0.019

Err:509 Err:509
1 Lampu TL 2x18 W 17.00 bh 1 0.035
2 Lampu SL 15 W 15.00 bh 1 0.017
3 Saklar tunggal 6.00 bh 1 0.009
4 Saklar ganda 5.00 bh 1 0.008
5 Stop kontak 6.00 bh 1 0.009
6 Instalasi titik lampu 32.00 bh 1 0.037

Err:509 Err:509
1 Pasang Keramik granito 40 x 40 119.00 m2 3 1.100
2 Pasang Keramik lantai 30 x30 38.00 m 2
2 0.351
3 Pasang Keramik lantai 20 x 20 (KM/WC) 29.00 m 2
2 0.242

Err:509 Err:509
1 Closet jongkok 4.00 bh 1 0.085
2 Wastafel 2.00 bh 1 0.147
3 Kran air 10.00 bh 1 0.016
4 Pipa PVC 1/2" 6.40 m' 2 0.006
5 Pipa PVC 3/4" 9.00 m' 2 0.014
6 Floor Drain 4.00 bh 1 0.003

Err:509 Err:509
1 Kuda-kuda Baja 626.22 Kg 4 0.734
2 1/2 Kuda-kuda 313.10 Kg 4 0.367
3 Jurai 148.60 Kg 2 0.174
4 Gording CNP 125.50.20.3,2 mm 835.21 Kg 2 0.979
5 Baut 10mm 160.00 buah 3 0.012
6 Baut 12mm 288.00 buah 3 0.033

C Err:509
Err:509 Err:509
1 Galian Pondasi Pagar 62.70 m3 2 0.129 0.065 0.065
2 Urugan Pasir bawah pondasi 5.70 m3 1 0.041 0.041
3 Urugan tanah kembali 20.90 m 3
1 0.149

Err:509 Err:509
1 Pemasangan Aanstamping 11.40 m3 2 0.210
2 Pas Pondasi Batu kali 25.08 m 3
3 0.954
3 Pas. Bata camp 1 : 5 8.55 m 2
2 0.043

Err:509 Err:509
1 kolom 15/15 0.34 m3 2 0.085
2 sloof 15/20 1.71 m3 2 0.809

Err:509 Err:509
1 Pasang paving block 257.10 m2 3 0.297

X Err:509
1 Pengadaan dan Pemasangan Unit AC Sentral
- Type : Air cooled split duct 9.00 bh 3 2.370
Kapasitas pendingin : 100.000,00 btu / h
Karakteristik : 380 V, 1 Ph, 50 Hz
- Refrigerant : R - 22 2.00 can 3 0.301
- Dudukan out door 9.00 bh 3 0.068
- Ongkos Pasang 9.00 bh 3 0.135

D POS SATPAM
Err:509 Err:509
1 Pembersihan Lahan 8.00 m2 1 0.003 0.003
2 Pemasangan Bouwplank 16.00 m' 1 0.123 0.123

Err:509 Err:509
1 Galian Pondasi 17.60 m3 1 0.036 0.036
2 Urugan pasir bawah pondasi 1.60 m 3
1 0.011 0.011
3 Urugan tanah kembali 5.87 m 3
1 0.042 0.042
4 Urugan pasir bawah lantai 0.80 m 3
1 0.006

Err:509 Err:509
1 Pemasangan Aanstamping 3.20 m3 1 0.059 0.059
2 Pas Pondasi Batu kali 7.04 m 3
2 0.268 0.134 0.134
3 Pas. Bata camp 1 : 5 64.00 m2 1 0.320
4 Pas. Bata camp 1 : 3 5.60 m2 1 0.030
5 Plesteran camp 1 : 5 128.00 m 2
1 0.281
6 Plesteran camp 1 : 3 11.20 m 2
1 0.027
7 Acian 139.20 m 2
1 0.171
Err:509 Err:509
1 Sloof 15/20 0.48 m3 2 0.120 0.060 0.060
2 Kolom 15/15 0.72 m3 2 0.341 0.170 0.170
3 Ring balk15/20 0.96 m3 2 0.352 0.176
4 Pelat dak beton, t=10 cm 1.25 m3 3 0.419 0.140 0.140

Err:509 Err:509
1 Kusen P2, 2bh 4.04 m3 2 1.977 0.989 0.989
2 Kusen J4 0.11 m 3
2 0.053 0.026 0.026

Err:509 Err:509
1 Gypsum Board rangka hollow 8.00 m2 1 0.015
2 List Plafond 48.00 m' 1 0.033
3 Pengecatan tembok 139.20 m2 1 0.106
4 Pengecatan plafond p m2 1 0.006

Err:509 Err:509
1 Kunci tanam biasa 2.00 bh 1 0.023
2 Engsel pintu 6.00 bh 1 0.006
3 Kaca J4 6.00 m2 1 0.035

Err:509 Err:509
1 Lampu SL 15 W 2.00 bh 1 0.002
2 Saklar tunggal 2.00 bh 1 0.003
3 Stop kontak 2.00 bh 1 0.003
4 Instalasi titik lampu 2.00 bh 1 0.002

Err:509 Err:509
1 Pasang Keramik lantai 30 x 30 8.00 m2 1 0.066

Rencana Kemajuan Pekerjaan PerMinggu (%) 100.00 0.249 2.08 3.50 3.83 4.07
Komulatif Rencana Kemajuan Pekerjaan (%) 0.249 2.33 5.82 9.65 13.72
N ( TIME SCHEDULLE )
509
509

Bulan 2 Bulan 3 BULAN 4 BULAN 5


%
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

100.000

0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003

0.140
0.051

0.005

0.881
0.004
0.827 0.827 0.827
0.077 0.077 0.077 90.000
1.090 1.090
0.103 0.103
0.662 0.662

0.616 0.616

0.200 0.200
0.439 0.439 0.439
0.839 0.839 0.839
1.590 1.590 1.590
0.596 0.596
0.982 0.982 0.982
0.255 0.255
2.447 2.447 2.447
0.665 0.665 0.665
0.050 0.050
0.541 0.541 0.541

0.034 0.034 0.034


0.999
1.311 1.311 1.311
0.047 0.047
0.055
0.028 0.028 80.000
0.102 0.102
0.022 0.022

0.145 0.145 0.145


0.079 0.079
0.274 0.274 0.274
0.091 0.091
0.101
0.026
0.031
0.115
0.010
0.082
0.008
0.004

0.028
0.034
0.008
0.011
0.020
0.023 70.000
0.017 0.017 0.017

0.872 0.872 0.872


0.168 0.168 0.168
0.213 0.213
0.115
0.301

0.053 0.053
0.368
0.083 0.083 0.083 0.083
0.014
0.011 0.011
0.046 0.046 0.046
0.008
0.019 0.019 0.019 0.019
0.019
0.017
0.770 0.770 0.770
0.072 0.072 0.072
1.014 1.014 60.000
0.096 0.096
0.617 0.617

1.533 1.533 1.533


0.511 0.511
0.634 0.634 0.634
1.711 1.711

0.025 0.025
1.967 1.967
0.075
0.427 0.427
0.028 0.028
0.020 0.020
0.030 0.030
0.017 0.017

0.112 0.112 0.112


0.037 0.037
0.256 0.256 0.256
0.047 0.047 0.047

50.000
0.875 0.875 0.875 0.875
0.035 0.035
0.0002 0.0002
0.005
0.397 0.397 0.397 0.397

0.079
0.062
0.034
0.018 0.018
0.007 0.007
0.022 0.022
0.009 0.009
0.010 0.010

0.035
0.017
0.009
0.008
0.009
0.037

40.000
0.367 0.367 0.367
0.176 0.176
0.121 0.121

0.085
0.147
0.016
0.003 0.003
0.007 0.007
0.003

0.184 0.184 0.184 0.184


0.092 0.092 0.092 0.092
0.087 0.087
0.490 0.490
0.004 0.004 0.004
0.011 0.011 0.011

30.000

0.149
0.105 0.105
0.318 0.318 0.318
0.021 0.021

0.042 0.042
0.405 0.405

0.099 0.099 0.099

0.790 0.790 0.790

0.100 0.100 0.100


0.023 0.023 0.023
0.045 0.045 0.045
20.000

0.006

0.320
0.030
0.281
0.027
0.171
0.176
0.140 10.000

0.015
0.033
0.106
0.006

0.023
0.006
0.035

0.002
0.003
0.003
0.002

0.066
0.000

4.50 6.47 7.80 8.09 8.14 10.47 9.70 9.23 7.89 5.50 3.64 1.88 1.33 0.96 0.67
18.22 24.69 32.49 40.57 48.72 59.19 68.89 78.12 86.01 91.51 95.15 97.03 98.37 99.33 100.00

Semarang, 06 Febru
Perencana
MONASHE
NIS. 08 09 760
HARGA SATUAN PEKERJAAN

No
Uraian Pekerjaan Sat. Harga Satuan (Rp.)
Anal.

I Analisa biaya konstruksi pekerjaan persiapan (SNI 2012)


I.1 1 m' Pagar sementara dari seng gelombang tinggi 2 meter m' 128,560.00
I.2 1 m' Pengukuran dan pemasangan bouwplank m' 106,960.00
I.3 1 m2 Pembuatan kantor sementara dengan lantai plesteran m2 747,887.50
I.4 1 m2 Pembuatan gudang semen dan alat-alat m2 664,418.75
I.5 1 m2 Membersihkan lapangan dan peralatan m2 6,300.00

II Analisa biaya konstruksi pekerjaan tanah (SNI 2012)


II.1 1 m3 Galian tanah biasa sedalam 1 meter m3 29,750.00
II.2 Mengurug kembali 1 m3 galian 1/3 x indeks pekerjaan galian
II.3 1 m3 Urugan pasir m3 119,900.00

III Analisa biaya konstruksi pekerjaan pondasi (SNI 2012)


III.1 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps. m3 461,305.00

IV Analisa biaya konstruksi pekerjaan dinding (SNI 2012)


IV.1 1 m2 Pasangan bata merah tebal 1/2 bata, 1 pc : 3 ps m2 71,084.38
IV.2 1 m2 Pasangan bata merah tebal 1/2 bata, 1 pc : 5 ps m2 66,115.00

V Analisa biaya konstruksi pekerjaan plesteran (SNI 2012)


V.1 1 m2 Plesteran 1 pc : 3 ps, tebal 15 mm m2 32,499.00
V.2 1 m2 Plesteran 1 pc : 5 ps, tebal 15 mm m2 29,781.00
V.3 1 m2 Memasang Acian m2 17,529.38

VI Analisa biaya konstruksi pekerjaan kayu (SNI 2012)


VI.1 1 m3 Kosen Pintu & Jendela kayu klas II m3 9,318,600.00
VI.2 1 m2 Pasang daun pintu panel kayu klas I atau II m2 500,500.00
VI.3 1 m3 Pasang Konstruksi kuda-kuda kayu Konvensional kayu I ; II ; III m3 8,477,600.00
VI.4 1 m3 Pasang Konstruksi Gording, kayu klas II m3 8,114,240.00
VI.5 1 m2 Memasang rangka atap genteng kodok/glasur ,kayu klas II m2 130,540.00
VI.6 1 m2 Pasang rangka langit-langit (60 x 1.020) cm, kayu klas I (jati) m2 270,364.00
VI.7 1 m' Pasang listplank ukuran (3 x 20) cm, kayu klas I atau II m' 96,090.00

VII Analisa biaya konstruksi pekerjaan beton (SNI 2012)


VII.1 1 m3 membuat sloof beton bertulang (200 kg besi+bekisting) m3 2,952,411.00
VII.2 1 m3 membuat kolom beton bertulang (300 kg besi+bekisting) m3 5,710,371.00
VII.3 1 m3 membuat balok beton bertulang (200 kg besi+bekisting) m3 2,889,931.00
VII.4 1 m3 membuat dinding beton bertulang (150 kg besi+bekisting) m3 4,199,134.00
VII.5 1 m3 membuat beton cor 1 : 2 : 3 m3 526,634.00
VIII Analisa biaya konstruksi pekerjaan penutup atap (SNI 2012)
VIII.1 1 m2 pasang atap genteng kodok / glasur m2 72,806.00

IX Analisa biaya konstruksi pekerjaan Langit-langit (SNI 2012)


IX.1 1 m2 Langit-langit gypsum board, tebal 9 mm m2 26,395.00
IX.2 1 m' list langit-langit profil cornees gypsum lebar 5-10 cm m' 19,303.00

X Analisa biaya konstruksi pekerjaan sanitasi (SNI 2012)


X.1 memasang 1 buah kloset jongkok bh 319,825.00
X.2 memasang 1 buah wastafel bh 984,825.00
X.3 memasang 1 m' pipa PVC tipe AW diameter 3/4" m' 13,518.75
X.4 memasang 1 m' pipa PVC tipe AW diameter 3" m' 38,845.83
X.5 memasang 1 buah kran air diameter 3/4" atau 1/2" bh 13,630.00
X.6 Pekerjaan Septictank per Unit unit 2,203,385.10
X.7 memasang 1 m' pipa galvanis, diameter 1" m' 41,998.00
X.8 memasang 1 buah floor drain bh 28,700.00
X.9 memasang bak fiberglass volume 1m3 air bh 1,359,300.00
X.10 Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm bh 305,385.50

XI Analisa biaya konstruksi pekerjaan besi dan aluminium (SNI 2012)


XI.1 1 m1 pasang kabel NYM 2x 2,5 mm m1 690.00
XI.2 1 unit pasang Box KWH dan Meter unit 76,000.00
XI.3 1 unit pasang Box panel dan panel kontrol unit 76,000.00
XI.4 1 titik pekerjaan fitting ttk 10,000.00
XI.5 1 bh pasang saklar tunggal bh 33,800.00
XI.6 1 bh pasang saklar ganda bh 44,800.00
XI.7 1 bh pasang stop kontak bh 28,800.00
XI.8 1 bh pasang lampu SL 18 w bh 57,800.00
XI.9 1 bh pasang lampu SL 10 W bh 34,800.00

XII Analisa biaya konstruksi pekerjaan kunci dan kaca (SNI 2012)
XII.1 1 bh pasang kunci tanam biasa bh 71,200.00
XII.2 1 bh pasang kunci tanam kamar mandi bh 70,600.00
XII.3 1 bh pasang engsel pintu bh 11,550.00
XII.4 1 m2 pasang kaca, tebal 5 mm m2 80,462.50
XII.5 1 bh pasang grendel bh 19,450.00

XIII Analisa biaya konstruksi pekerjaan penutup lantai dan dinding (SNI 2012)
XIII.1 1 m2 pasang lantai keramik 20 x 20 cm m2 114,655.00
XIII.2 1 m2 pasang lantai keramik 30 x 30 cm m2 112,492.69
XIII.3 1 m2 Pasang Paving Block t = 8cm K-300 m2 84,275.00
XIII.4 1 m2 pasang dinding keramik 20 x 25 cm m2 129,099.00
XIII.5 1 m2 pasang dinding keramik 10 x 20 cm m2 37,147.00

XIV Analisa biaya konstruksi pekerjaan pengecatan (SNI 2012)


XIV.1 1 m2 pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar 2 lapis cat penutu m2 20,111.00
XIV.2 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar 2 lapis cat penutup) luar m2 30,094.10
XIV.3 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar 2 lapis cat penutup) da m2 54,794.10
HARGA SATUAN BAHAN BANGUNAN

No. Nama Bahan Sat. Harga No. Nama Bahan Sat. Harga

A BAHAN DASAR 12 Kayu Lanan (Papan) m3 Rp 1,950,000.00


1 Batu Belah m 3
Rp 110,000.00 13 Kayu Lanan (Balok) m3 Rp 1,700,000.00
2 Kerikil Beton 1/2 m3 Rp 180,000.00 D BAHAN PENUTUP DINDING / LANTAI
3 Batu bata (5x11x22cm) bh Rp 450.00 1 Keramik uk. 30 x 30 cm m2 Rp 36,500.00
4 Pasir Urug m3 Rp 90,000.00 2 Keramik uk. 20 x 20 cm m2 Rp 35,000.00
5 Pasir Pasang m3 Rp 120,000.00 3 Keramik uk. 33 x 33 cm m2 Rp 30,000.00
6 Pasir Beton m3 Rp 195,000.00 4 Batu tempel hitam m2 Rp 70,000.00
7 Tanah Padas m3 Rp 50,000.00 5 Granito uk. 60 x 60 cm m2 Rp 280,000.00
8 Kapur Pasang m3 Rp 210,000.00 6 Porselen 11 x 11 cm m2 Rp 277.78
9 Portland semen Holcim 40 kg kg Rp 1,187.50 7 Keramik plint uk. 10 x 20 cm m2 Rp 5,000.00
10 Portland semen Holcim 50 kg kg Rp 1,160.00 8 Keramik plint uk. 10 x 10 cm m2 Rp 4,500.00
11 Semen Putih 40 kg kg Rp 1,700.00
12 Semen warna kg Rp 10,000.00 E BAHAN CETAK
1 Buis beton 20cm - 100cm bh Rp 30,000.00
B BAHAN PENUTUP ATAP 2 Buis beton 30cm - 100cm bh Rp 38,000.00
1 Sirap lbr Rp 1,500.00 3 Buis Beton U 20cm - 100cm bh Rp 30,000.00
2 Genteng Kodok / Glasur bh Rp 2,500.00 4 Buis Beton U 30cm - 100cm bh Rp 35,000.00
3 Genteng beton warna standard bh Rp 3,000.00 5 Roster/lubang angin uk. 20 x 20 cm bh Rp 5,500.00
4 Kerpus beton warna standard bh Rp 3,750.00 6 Roster/lubang angin uk. 25 x 25 cm bh Rp 6,250.00
5 Genteng plentong super besar bh Rp 2,800.00 7 Roster/lubang angin uk. 30 x 30 cm bh Rp 6,300.00
6 Nok kerpus plentong super bh Rp 6,750.00
7 Nok kerpus Kodok bh Rp 4,200.00 F BAHAN BESI
8 Asbes gelombang kecil (240cmx105cmx4mm) m2 Rp 50,000.00 1 Besi beton polos kg Rp 8,000.00
9 Asbes plat (100cmx100cmx3mm) m2 Rp 13,500.00 2 Besi beton ulir kg Rp 12,300.00
10 Asbes plat (100cmx100cmx4mm) m2 Rp 14,500.00 3 Besi siku L 40x40x4 btg Rp 130,000.00
11 Seng plat BJLS. 0.28, lebar 55 cm m' Rp 33,000.00 4 Besi siku L 50x50x5 btg Rp 205,000.00
12 Seng plat BJLS. 0.30, lebar 55 cm m' Rp 38,000.00 5 Besi siku L 60x60x6 btg Rp 299,000.00
13 Seng Gelombang BJLS. 0.30 pj. 180 cm lbr Rp 65,000.00 6 Kawat Ikat Beton / Bendrat kg Rp 12,000.00
7 Kawat kasa m2 Rp 12,000.00
C. BAHAN KAYU 8 Saringan Pasir m2 Rp 15,000.00
1 Kayu Kamper (Papan) m3 Rp 7,300,000.00 9 Besi Strip kg Rp 13,000.00
2 Kayu Kamper (Balok) m3 Rp 6,700,000.00
3 Kayu Kruing (Papan) m3 Rp 5,300,000.00 G BAHAN PIPA
4 Kayu Kruing (Balok) m3 Rp 5,000,000.00 1 Pipa PVC DN 20 (") AW JIS m' Rp 4,500.00
5 Kayu Bengkirai (Papan) m3 Rp 9,000,000.00 2 Pipa PVC DN 25 (") AW JIS m' Rp 5,625.00
6 Kayu Bengkirai (Balok) m3 Rp 8,700,000.00 3 Pipa PVC DN 32 (1") AW JIS m' Rp 6,875.00
7 Kayu Dolken 8x10x400cm bt Rp 18,000.00 4 Pipa PVC DN 63 (2") AW JIS m' Rp 10,000.00
8 Kayu Jati (Papan) m3 Rp 21,000,000.00 5 Pipa PVC DN 90 (3") AW JIS m' Rp 20,416.67
9 Kayu Jati (Balok) m3 Rp 19,000,000.00 6 Pipa PVC DN 110 (4") AW JIS m' Rp 25,000.00
10 Kayu Meranti (Papan) m3 Rp 4,700,000.00 7 Pipa Medium B Galvanis DN 25 (3/4") m' Rp 19,500.00
11 Kayu cetakan m3 Rp 1,050,000.00 7 Pipa Medium B Galvanis DN 25 (1") m' Rp 21,666.67
H BAHAN LANGIT - LANGIT N POMPA AIR
1 Gypsum tebal 9 mm lbr Rp 45,000.00 1 Sanyo 100 watt bh Rp 975,000.00
2 Teakwood uk. 90cmx210cmx3mm lbr Rp 40,000.00 2 Fuji 250 watt bh Rp 1,450,000.00
3 Teakwood uk. 120cmx240cmx3mm lbr Rp 75,000.00
4 Tripleks uk. 120cmx240cmx4mm lbr Rp 55,000.00 O PAVING BLOCK
5 Multipleks uk. 120cmx240cmx9mm lbr Rp 105,000.00 1 Trapez Grass Block abu-abu m2 Rp 41,000.00
6 Multipleks uk. 120cmx240cmx12mm lbr Rp 135,000.00 2 Kansteen m' Rp 22,500.00

I BAHAN FINISHING P LAIN-LAIN


1 KAYU 1 Air liter Rp 8,000.00
1 Menie kg Rp 12,500.00 2 Minyak Bekisting & beton ltr Rp 8,000.00
2 Dempul Plamir kg Rp 11,000.00 3 Alumunium Foil m2 Rp 6,500.00
3 Ambril/amplas kg Rp 3,500.00 4 Paku Sekrup doss Rp 13,500.00
4 Cat dasar kg Rp 132,000.00 5 Bak cuci stainless steel bh Rp 145,000.00
5 Yunior 66 (nippon paint) kg Rp 42,000.00 6 Perekat/Lem kg Rp 32,000.00
6 Deculux kg Rp 45,000.00 7 Kayu Profil m1 Rp 4,200.00
TEMBOK 8 Besi profil kg Rp 14,250.00
1 Plamir kg Rp 10,500.00 9 Sealant tube Rp 50,000.00
2 Catylac kg Rp 90,000.00 10 Sekrup bh Rp 750.00
3 Mowillex kg Rp 185,000.00 11 Profil kaca bh Rp 9,000.00
BESI 12 Kawat las kg Rp 52,000.00
1 Menie kg Rp 13,500.00 13 Alumunium Strip m1 Rp 30,000.00
14 List profil cornees gypsum m1 Rp 8,000.00
J BAHAN KACA 15 Tepung gypsum kg Rp 3,500.00
1 Kaca polos 5 mm m2 Rp 65,000.00 16 Alkasit kg Rp 40,000.00
2 Kaca polos 3 mm m2 Rp 55,000.00 17 Bak fiberglass vol 1m3 air bh Rp 825,000.00

K ALAT PENGUNCI DAN PENGGANTUNG Q LISTRIK


1 Kunci tanam union ( 2 x slag ) bh Rp 60,000.00 1 Kabel Overspaneng NYM 3 x 2,5 mm m1 Rp 12,400.00
2 Kunci tanam kuda ( 2 x slag ) bh Rp 60,000.00 2 MCB : 6 A / 5 KA / 1 pole bh Rp 1,750,000.00
3 Kunci tanam yale ( 2 x slag ) bh Rp 125,000.00 3 MCB : 16 A / 10 KA / 3 pole bh Rp 150,000.00
4 Engsel kupu-kupu biasa bh Rp 2,250.00 4 Pilot lamp. Fuse bh Rp 241,500.00
5 Nylon kupu-kupu bh Rp 5,000.00 5 Voltmeter Box panel uk. 100 x 100 x 40 bh Rp 241,500.00
6 Espagnoled bh Rp 30,000.00 6 Arde / Pentanahan ls Rp 90,000.00
7 Grendel tanam luar negeri bh Rp 7,500.00 7 NFB 3 phase 63 A bh Rp 90,000.00
8 Grendel biasa bh Rp 7,500.00 8 NFB 3 phase 20 A bh Rp 240,000.00
9 Kait angin bh Rp 5,000.00 9 .Amperemeter bh Rp 57,000.00
10 Lampu TL 2 x 18. watt Rm.300 Kisi-kisi bh Rp 27,000.00
L BAHAN SANITAIR 11 Lampu SL 15 watt bh Rp 15,500.00
1 Kloset jongkok bh Rp 105,000.00 12 Stop kontak Arde Outbow putih bh Rp 12,500.00
2 Wastavel meja oval bh Rp 700,000.00 13 Sakelar tunggal bh Rp 15,000.00
3 Wastavel gantung sudut kecil bh Rp 210,000.00 14 Sakelar ganda / seri bh Rp 20,500.00
4 Tempat sabun gantung bh Rp 27,500.00 15 Fiting bh Rp 7,500.00
5 Tempat sabun tanam bh Rp 20,000.00 16 Lampu Pintu Gerbang ( taman ) unit Rp 2,750,000.00
6 Kran Air bh Rp 7,500.00
7 Seal tape bh Rp 2,000.00
8 Floor drain bh Rp 22,500.00

M ALAT PENGIKAT KAYU


1 Paku uk. 1" s/d 4" kg Rp 12,000.00
2 Tali ijuk kg Rp 6,000.00
3 Mur baut ( kuda-kuda ) kg Rp 13,000.00
4 Lem kayu kg Rp 18,000.00
HARGA SATUAN BAHAN BANGUNAN
Err:509
Err:509

No. Nama Bahan Sat. Harga

A BAHAN DASAR
1 Batu Belah m3 Rp 110,000.00
2 Kerikil Beton 1/2 m3 Rp 180,000.00
3 Batu bata (5x11x22cm) bh Rp 450.00
4 Pasir Urug m3 Rp 90,000.00
5 Pasir Pasang m3 Rp 120,000.00
6 Pasir Beton m3 Rp 195,000.00
7 Tanah Padas m3 Rp 50,000.00
8 Kapur Pasang m3 Rp 210,000.00
9 Portland semen Holcim 40 kg kg Rp 1,187.50
10 Portland semen Holcim 50 kg kg Rp 1,160.00
11 Semen Putih 40 kg kg Rp 1,700.00
12 Semen warna kg Rp 10,000.00

B BAHAN PENUTUP ATAP


1 Sirap lbr Rp 1,500.00
2 Genteng Kodok / Glasur bh Rp 2,500.00
3 Genteng beton warna standard bh Rp 3,000.00
4 Kerpus beton warna standard bh Rp 3,750.00
5 Genteng plentong super besar bh Rp 2,800.00
6 Nok kerpus plentong super bh Rp 6,750.00
7 Nok kerpus Kodok bh Rp 4,200.00
8 Asbes gelombang kecil (240cmx105cmx4mm) m2 Rp 50,000.00
9 Asbes plat (100cmx100cmx3mm) m2 Rp 13,500.00
10 Asbes plat (100cmx100cmx4mm) m2 Rp 14,500.00
11 Seng plat BJLS. 0.28, lebar 55 cm m' Rp 20,000.00
12 Seng plat BJLS. 0.30, lebar 55 cm m' Rp 23,000.00
13 Seng Gelombang BJLS. 0.30 pj. 180 cm lbr Rp 65,000.00

C. BAHAN KAYU
1 Kayu Kamper (Papan) m3 Rp 7,300,000.00
2 Kayu Kamper (Balok) m3 Rp 6,700,000.00
3 Kayu Kruing (Papan) m3 Rp 5,300,000.00
4 Kayu Kruing (Balok) m3 Rp 5,000,000.00
5 Kayu Bengkirai (Papan) m3 Rp 9,000,000.00
6 Kayu Bengkirai (Balok) m3 Rp 8,700,000.00
7 Kayu Dolken 8x10x400cm bt Rp 18,000.00
8 Kayu Jati (Papan) m3 Rp 21,000,000.00
9 Kayu Jati (Balok) m3 Rp 19,000,000.00
10 Kayu Meranti (Papan) m3 Rp 4,700,000.00
11 Kayu cetakan m3 Rp 1,050,000.00
D BAHAN PENUTUP DINDING / LANTAI
1 Keramik uk. 30 x 30 cm m2 Rp 36,500.00
2 Keramik uk. 20 x 20 cm m2 Rp 35,000.00
3 Keramik uk. 33 x 33 cm m2 Rp 30,000.00
4 Batu tempel hitam m2 Rp 70,000.00
5 Granito uk. 60 x 60 cm m2 Rp 280,000.00
6 Porselen 11 x 11 cm m2 Rp 277.78
7 Keramik plint uk. 10 x 20 cm m2 Rp 5,000.00
8 Keramik plint uk. 10 x 10 cm m2 Rp 4,500.00

E BAHAN CETAK
1 Buis beton 20cm - 100cm bh Rp 30,000.00
2 Buis beton 30cm - 100cm bh Rp 38,000.00
3 Buis Beton U 20cm - 100cm bh Rp 30,000.00
4 Buis Beton U 30cm - 100cm bh Rp 35,000.00
5 Roster/lubang angin uk. 20 x 20 cm bh Rp 5,500.00
6 Roster/lubang angin uk. 25 x 25 cm bh Rp 6,250.00
7 Roster/lubang angin uk. 30 x 30 cm bh Rp 6,300.00

F BAHAN BESI
1 Besi beton polos kg Rp 8,000.00
2 Besi beton ulir kg Rp 12,300.00
3 Besi siku L 40x40x4 btg Rp 130,000.00
4 Besi siku L 50x50x5 btg Rp 205,000.00
5 Besi siku L 60x60x6 btg Rp 299,000.00
6 Kawat Ikat Beton / Bendrat kg Rp 12,000.00
7 Kawat kasa m2 Rp 12,000.00
8 Saringan Pasir m2 Rp 15,000.00
9 Besi Strip kg Rp 13,000.00

G BAHAN PIPA
1 Pipa PVC DN 20 (") AW JIS m' Rp 4,500.00
2 Pipa PVC DN 25 (") AW JIS m' Rp 5,625.00
3 Pipa PVC DN 32 (1") AW JIS m' Rp 6,875.00
4 Pipa PVC DN 63 (2") AW JIS m' Rp 10,000.00
5 Pipa PVC DN 90 (3") AW JIS m' Rp 20,416.67
6 Pipa PVC DN 110 (4") AW JIS m' Rp 25,000.00
7 Pipa Medium B Galvanis DN 25 (3/4") m' Rp 19,500.00
7 Pipa Medium B Galvanis DN 25 (1") m' Rp 21,666.67

H BAHAN LANGIT - LANGIT


1 Gypsum tebal 9 mm lbr Rp 45,000.00
2 Teakwood uk. 90cmx210cmx3mm lbr Rp 40,000.00
3 Teakwood uk. 120cmx240cmx3mm lbr Rp 75,000.00
4 Tripleks uk. 120cmx240cmx4mm lbr Rp 55,000.00
5 Multipleks uk. 120cmx240cmx9mm lbr Rp 105,000.00
6 Multipleks uk. 120cmx240cmx12mm lbr Rp 135,000.00

I BAHAN FINISHING
1 KAYU
1 Menie kg Rp 12,500.00
2 Dempul Plamir kg Rp 11,000.00
3 Ambril/amplas kg Rp 3,500.00
4 Cat dasar kg Rp 13,200.00
5 Yunior 66 (nippon paint) kg Rp 42,000.00
6 Deculux kg Rp 45,000.00
TEMBOK
1 Plamir kg Rp 10,500.00
2 Catylac kg Rp 90,000.00
3 Mowillex kg Rp 185,000.00
BESI
1 Menie kg Rp 13,500.00

J BAHAN KACA
1 Kaca polos 5 mm m2 Rp 65,000.00
2 Kaca polos 3 mm m2 Rp 55,000.00

K ALAT PENGUNCI DAN PENGGANTUNG


1 Kunci tanam union ( 2 x slag ) bh Rp 45,000.00
2 Kunci tanam kuda ( 2 x slag ) bh Rp 60,000.00
3 Kunci tanam yale ( 2 x slag ) bh Rp 125,000.00
4 Engsel kupu-kupu biasa bh Rp 2,250.00
5 Nylon kupu-kupu bh Rp 5,000.00
6 Espagnoled bh Rp 30,000.00
7 Grendel tanam luar negeri bh Rp 7,500.00
8 Grendel biasa bh Rp 7,500.00
9 Kait angin bh Rp 5,000.00

L BAHAN SANITAIR
1 Kloset jongkok bh Rp 105,000.00
2 Wastavel meja oval bh Rp 700,000.00
3 Wastavel gantung sudut kecil bh Rp 210,000.00
4 Tempat sabun gantung bh Rp 27,500.00
5 Tempat sabun tanam bh Rp 20,000.00
6 Kran Air bh Rp 7,500.00
7 Seal tape bh Rp 2,000.00
8 Floor drain bh Rp 22,500.00

M ALAT PENGIKAT KAYU


1 Paku uk. 1" s/d 4" kg Rp 12,000.00
2 Tali ijuk kg Rp 6,000.00
3 Mur baut ( kuda-kuda ) kg Rp 13,000.00
4 Lem kayu kg Rp 18,000.00

N POMPA AIR
1 Sanyo 100 watt bh Rp 975,000.00
2 Fuji 250 watt bh Rp 1,450,000.00

O PAVING BLOCK
1 Trapez Grass Block abu-abu m2 Rp 41,000.00
2 Kansteen m' Rp 22,500.00

P LAIN-LAIN
1 Air liter Rp 8,000.00
2 Minyak Bekisting & beton ltr Rp 8,000.00
3 Alumunium Foil m2 Rp 6,500.00
4 Paku Sekrup doss Rp 13,500.00
5 Bak cuci stainless steel bh Rp 145,000.00
6 Perekat/Lem kg Rp 32,000.00
7 Kayu Profil m1 Rp 4,200.00
8 Besi profil kg Rp 14,250.00
9 Sealant tube Rp 50,000.00
10 Sekrup bh Rp 750.00
11 Profil kaca bh Rp 9,000.00
12 Kawat las kg Rp 52,000.00
13 Alumunium Strip m1 Rp 30,000.00
14 List profil cornees gypsum m1 Rp 8,000.00
15 Tepung gypsum kg Rp 3,500.00
16 Alkasit kg Rp 40,000.00
17 Bak fiberglass vol 1m3 air bh Rp 825,000.00

Q LISTRIK
1 Kabel Overspaneng NYM 3 x 2,5 mm m1 Rp 12,400.00
2 MCB : 6 A / 5 KA / 1 pole bh Rp 1,750,000.00
3 MCB : 16 A / 10 KA / 3 pole bh Rp 150,000.00
4 Pilot lamp. Fuse bh Rp 241,500.00
5 Voltmeter Box panel uk. 100 x 100 x 40 bh Rp 241,500.00
6 Arde / Pentanahan ls Rp 90,000.00
7 NFB 3 phase 63 A bh Rp 90,000.00
8 NFB 3 phase 20 A bh Rp 240,000.00
9 .Amperemeter bh Rp 57,000.00
10 Lampu TL 2 x 18. watt Rm.300 Kisi-kisi bh Rp 27,000.00
11 Lampu SL 15 watt bh Rp 15,500.00
12 Stop kontak Arde Outbow putih bh Rp 12,500.00
13 Sakelar tunggal bh Rp 15,000.00
14 Sakelar ganda / seri bh Rp 20,500.00
15 Fiting bh Rp 7,500.00
16 Lampu Pintu Gerbang ( taman ) unit Rp 2,750,000.00

R PENANGKAL PETIR
1 Kawat Penghantar BC 70 mm2 lengkap clamp, bracket m1 Rp 150,000.00
2 Tiang penyangga GIP dia 50 mm2 T 4 mm Unit Rp 200,000.00
3 Bak kontrol ukuran 40 x 40 x 30 cm Unit Rp 1,150,000.00
4 Obstruction Light 60 watt lengkap accessories Unit Rp 14,000.00
5 Instalasi Obstruction Light lengkap dengan kabel, konduite,
dan accessories Titik Rp 95,000.00
HARGA SATUAN UPAH TENAGA

No Daftar Pekerja Sat. Harga (Rp)

1 Pekerja OH 38,000.00

2 Mandor OH 50,000.00

3 Tukang Listrik OH 50,000.00

4 Tukang Kayu OH 50,000.00

5 Kepala Tukang Kayu OH 57,000.00

6 Tukang Batu OH 50,000.00

7 Kepala Tukang Batu OH 57,000.00

8 Tukang Besi OH 50,000.00

9 Kepala Tukang Besi OH 57,000.00

10 Tukang Cat OH 50,000.00

11 Kepala Tukang Cat OH 57,000.00

12 Tukang Plitur OH 50,000.00

13 Tukang Gali OH 37,500.00


I. Analisa biaya konstruksi pekerjaan persiapan (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien
I.1 1 m' Pagar sementara dari seng gelombang tinggi 2 meter I.3.2 Tenaga
I.1.1 Bahan - Tukang kayu 2.000
- Dolken Kayu 8-10/400 cm 1.250 btg x Rp 18,000.00 = Rp 22,500.00 - Tukang batu 1.000
- Seng gelombang BKLS 0.30 pj. 180cm 1.200 Lbr x Rp 65,000.00 = Rp 78,000.00 - Pekerja 2.000
- Paku 0.060 Kg x Rp 12,000.00 = Rp 720.00 - Kepala tukang 0.300
Jumlah (I) = Rp 101,220.00 - Mandor 0.050

I.1.2 Tenaga
- Tukang kayu 0.200 Oh x Rp 50,000.00 = Rp 10,000.00
- Pekerja 0.400 Oh x Rp 38,000.00 = Rp 15,200.00 I.4 1 m2 Pembuatan gudang semen dan alat-alat
- Kepala tukang 0.020 Oh x Rp 57,000.00 = Rp 1,140.00 I.4.1 Bahan
- Mandor 0.020 Oh x Rp 50,000.00 = Rp 1,000.00 - Dolken Kayu 8-10/400 cm 1.700
Jumlah (II) = Rp 27,340.00 - Kayu (utk kntor semntara) 0.210
Jumlah (I)+(II) = Rp 128,560.00 - Paku 0.300
- Semen portland 10.500
I.2 1 m' Pengukuran dan pemasangan bouwplank - Pasir beton (muntilan) 0.030
I.2.1 Bahan - Batu pecah 2/3 0.050
- Kayu 5/7 (utk bowplank&pagar smentara) 0.012 M3
x Rp 5,000,000.00 = Rp 60,000.00 - Seng gelombang bljs 30 1.500
- Paku 0.020 Kg x Rp 12,000.00 = Rp 240.00
- Kayu papan 3/20 (utk bowplank) 0.007 M3 x Rp 5,300,000.00 = Rp 37,100.00
Jumlah (I) = Rp 97,340.00 I.4.2 Tenaga
- Tukang kayu 2.000
I.2.2 Tenaga - Pekerja 1.000
- Tukang kayu 0.100 Oh x Rp 50,000.00 = Rp 5,000.00 - Kepala tukang 0.200
- Pekerja 0.100 Oh x Rp 38,000.00 = Rp 3,800.00 - Mandor 0.050
- Kepala tukang 0.010 Oh x Rp 57,000.00 = Rp 570.00
- Mandor 0.005 Oh x Rp 50,000.00 = Rp 250.00
Jumlah (II) = Rp 9,620.00
Jumlah (I)+(II) = Rp 106,960.00 I.5 1 m2 Membersihkan lapangan dan peralatan
I.5.1 Tenaga
I.3 1 m2 Pembuatan kantor sementara, dengan lantai plesteran - Pekerja 0.100
I.3.1 Bahan - Mandor 0.050
- Dolken Kayu 8-10/400 cm 1.250 btg x Rp 18,000.00 = Rp 22,500.00
- Kayu (utk kntor semntara) 0.180 M3 x Rp 1,700,000.00 = Rp 306,000.00
- Paku 0.850 Kg x Rp 12,000.00 = Rp 10,200.00
- Besi strip 1.100 Kg x Rp 13,000.00 = Rp 14,300.00
- Semen portland 35.000 Kg x Rp 1,187.50 = Rp 41,562.50
- Pasir pasang 0.150 M3 x Rp 120,000.00 = Rp 18,000.00
- Pasir beton 0.100 M3 x Rp 195,000.00 = Rp 19,500.00
- Batu belah 0.150 M3 x Rp 110,000.00 = Rp 16,500.00
- Bata merah 5 x 11 x 22 cm 30.000 Bh x Rp 450.00 = Rp 13,500.00
- Seng plat BJLS 0.28 0.250 Lbr x Rp 20,000.00 = Rp 5,000.00
- Jendela nako 2.000 Bh x Rp 10,500.00 = Rp 21,000.00
- Kaca polos 5mm 0.080 M2 x Rp 55,000.00 = Rp 4,400.00
- Kunci tanam biasa 0.150 Bh x Rp 45,000.00 = Rp 6,750.00
- Engsel 0.300 bh x Rp 2,250.00 = Rp 675.00
- Plywood 3 mm 0.060 Lbr x Rp 40,000.00 = Rp 2,400.00
Jumlah (I) = Rp 502,287.50
Sat Harga bahan Jumlah

Oh x Rp 50,000.00 = Rp 100,000.00
Oh x Rp 50,000.00 = Rp 50,000.00
Oh x Rp 38,000.00 = Rp 76,000.00
Oh x Rp 57,000.00 = Rp 17,100.00
Oh x Rp 50,000.00 = Rp 2,500.00
Jumlah (II) = Rp 245,600.00
Jumlah (I)+(II) = Rp 747,887.50

btg x Rp 18,000.00 = Rp 30,600.00


M3 x Rp 1,700,000.00 = Rp 357,000.00
Kg x Rp 12,000.00 = Rp 3,600.00
Kg x Rp 1,187.50 = Rp 12,468.75
M3 x Rp 195,000.00 = Rp 5,850.00
M3 x Rp 110,000.00 = Rp 5,500.00
Lbr x Rp 65,000.00 = Rp 97,500.000
Jumlah (I) = Rp 512,518.75

Oh x Rp 50,000.00 = Rp 100,000.00
Oh x Rp 38,000.00 = Rp 38,000.00
Oh x Rp 57,000.00 = Rp 11,400.00
Oh x Rp 50,000.00 = Rp 2,500.00
Jumlah (II) = Rp 151,900.00
Jumlah (I)+(II) = Rp 664,418.75

Oh x Rp 38,000.00 = Rp 3,800.00
Oh x Rp 50,000.00 = Rp 2,500.00
Jumlah = Rp 6,300.00
II. Analisa biaya konstruksi pekerjaan tanah (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien Sat
II.1 1 m3 Galian tanah biasa sedalam 1 meter 1 m2 Pasangan bata merah tebal 1/2 bata, 1 pc : 5 ps
II.1.1 Tenaga IV.2.1 Bahan
- Pekerja 0.750 Oh x Rp 38,000.00 = Rp 28,500.00 - Bata merah 5 x 11 x 22 cm 70.000 Bh
- Mandor 0.025 Oh x Rp 50,000.00 = Rp 1,250.00 - Semen portland 9.680 Kg
Jumlah = Rp 29,750.00 - Pasir pasang 0.045 M3

II.2 Mengurug kembali 1 m3 galian


Mengurug kembali 1m3 galian dihitung dari 1/3 kali indeks pekerjaan galian IV.2.2 Tenaga
- Pekerja 0.300 Oh
II.3 1 m3 Urugan pasir - Tukang batu 0.100 Oh
II.3.1 Bahan - Kepala tukang 0.010 Oh
- Pasir urug 1.200 M3 x Rp 90,000.00 = Rp 108,000.00 - Mandor 0.015 Oh
Jumlah (I) = Rp 108,000.00

II.3.2 Tenaga
- Pekerja 0.300 Oh x Rp 38,000.00 = Rp 11,400.00
- Mandor 0.010 Oh x Rp 50,000.00 = Rp 500.00 V. Analisa biaya konstruksi pekerjaan plesteran (SNI 2012)
Jumlah (II) = Rp 11,900.00 Kode Uraian pekerjaan Koefisien Sat
Jumlah (I)+(II) = Rp 119,900.00 V.1 1 m2 Plesteran 1 pc : 3 ps, tebal 15 mm
V.1.1 Bahan
III. Analisa biaya konstruksi pekerjaan pondasi (SNI 2012) - Semen portland 7.776 Kg
- Pasir pasang 0.023 M3
Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah
III.1 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps.
III.1.1 Bahan V.1.2 Tenaga
- Batu belah 15/20 1.2 M3 x Rp 110000 = Rp 132000 - Pekerja 0.300 Oh
- Semen portland 136 Kg x Rp 1187.5 = Rp 161500 - Tukang batu 0.150 Oh
- Pasir pasang 0.544 M3 x Rp 120000 = Rp 65280 - Kepala tukang 0.015 Oh
Jumlah (I) = Rp 358,780.00 - Mandor 0.015 Oh

III.1.2 Tenaga
- Pekerja 1.5 Oh x Rp 38000 = Rp 57000
- Tukang batu 0.75 Oh x Rp 50000 = Rp 37500 V.2 1 m2 Plesteran 1 pc : 5 ps, tebal 15 mm
- Kepala tukang 0.075 Oh x Rp 57000 = Rp 4275 V.2.1 Bahan
- Mandor 0.075 Oh x Rp 50000 = Rp 3750 - Semen portland 5.184 Kg
Jumlah (II) = Rp 102525 - Pasir pasang 0.026 M3
Jumlah (I)+(II) = Rp 461,305.00

IV. Analisa biaya konstruksi pekerjaan dinding (SNI 2012) V.2.2 Tenaga
Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah - Pekerja 0.300 Oh
IV.1 1 m2 Pasangan bata merah tebal 1/2 bata, 1 pc : 3 ps - Tukang batu 0.150 Oh
IV.1.1 Bahan - Kepala tukang 0.015 Oh
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp 450.00 = Rp 31,500.00 - Mandor 0.015 Oh
- Semen portland 14.370 Kg x Rp 1,187.50 = Rp 17,064.38
- Pasir pasang (muntilan) 0.040 M3 x Rp 120,000.00 = Rp Rp 4,800.00
Jumlah (I) = Rp 53,364.38
V.3 1 m2 Memasang Acian
IV.1.2 Tenaga V.3.1 Bahan
- Pekerja 0.300 Oh x Rp 38,000.00 = Rp 11,400.00 - Semen portland 3.250 Kg
- Tukang batu 0.100 Oh x Rp 50,000.00 = Rp 5,000.00
- Kepala tukang 0.010 Oh x Rp 57,000.00 = Rp 570.00
- Mandor 0.015 Oh x Rp 50,000.00 = Rp 750.00 V.3.2 Tenaga
Jumlah (II) = Rp 17,720.00 - Pekerja 0.200 Oh
Jumlah (I)+(II) = Rp 71,084.38 - Tukang batu 0.100 Oh
- Kepala tukang 0.010 Oh
- Mandor 0.010 Oh
Harga bahan Jumlah

x Rp 450.00 = Rp 31,500.00
x Rp 1,187.50 = Rp 11,495.00
x Rp 120,000.00 = Rp Rp 5,400.00
Jumlah (I) = Rp 48,395.00

x Rp 38,000.00 = Rp 11,400.00
x Rp 50,000.00 = Rp 5,000.00
x Rp 57,000.00 = Rp 570.00
x Rp 50,000.00 = Rp 750.00
Jumlah (II) = Rp 17,720.00
Jumlah (I)+(II) = Rp 66,115.00

Harga bahan Jumlah

x Rp 1,187.50 = Rp 9,234.00
BIGBOSS:
x Rp 120,000.00 = Rp 2,760.00
Jumlah (I) = Rp 11,994.00

x Rp 38,000.00 = Rp 11,400.00
x Rp 50,000.00 = Rp 7,500.00
x Rp 57,000.00 = Rp 855.00
x Rp 50,000.00 = Rp 750.00
Jumlah (II) = Rp 20,505.00
Jumlah (I)+(II) = Rp 32,499.00

x Rp 1,187.50 = Rp 6,156.00
x Rp 120,000.00 = Rp 3,120.00
Jumlah (I) = Rp 9,276.00

x Rp 38,000.00 = Rp 11,400.00
x Rp 50,000.00 = Rp 7,500.00
x Rp 57,000.00 = Rp 855.00
x Rp 50,000.00 = Rp 750.00
Jumlah (II) = Rp 20,505.00
Jumlah (I)+(II) = Rp 29,781.00

x Rp 1,187.50 = Rp 3,859.38
Jumlah (I) = Rp 3,859.38

x Rp 38,000.00 = Rp 7,600.00
x Rp 50,000.00 = Rp 5,000.00
x Rp 57,000.00 = Rp 570.00
x Rp 50,000.00 = Rp 500.00
Jumlah (II) = Rp 13,670.00
Jumlah (I)+(II) = Rp 17,529.38
VI. Analisa biaya konstruksi pekerjaan kayu (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien Sat
VI.1 1 m3 Kosen Pintu & Jendela kayu klas II VI.4.2 Tenaga
VI.1.1 Bahan - Pekerja 2.400 Oh x
- Kayu Klas II (Kamfer), Balok 1.200 M x
3
Rp 6,700,000.00 = Rp 8,040,000.00 - Tukang kayu 7.200 Oh x
- Paku biasa 2" - 5" 1.250 Kg x Rp 12,000.00 = Rp 15,000.00 - Kepala tukang 0.720 Oh x
- Lem Kayu 1.000 Kg x Rp 18,000.00 = Rp 18,000.00 - Mandor 0.120 Oh x
Jumlah (I) = Rp 8,073,000.00

VI.1.2 Tenaga
- Pekerja 6.000 Oh x Rp 38,000.00 = Rp 228,000.00 VI.5 1 m2 Memasang rangka atap genteng kodok ,kayu klas II
- Tukang kayu 18.000 Oh x Rp 50,000.00 = Rp 900,000.00 VI.5.1 Bahan
- Kepala tukang 1.800 Oh x Rp 57,000.00 = Rp 102,600.00 - Kayu kamper (balok), Kaso-kaso (5/7) 0.014 M3 x
- Mandor 0.300 Oh x Rp 50,000.00 = Rp 15,000.00 - Reng 0.004 M4 x
Jumlah (II) = Rp 1,245,600.00 - Paku 0.250 Kg x
Jumlah (I)+(II) = Rp 9,318,600.00

VI.2 1 m3 Daun pintu Panel kayu klas I atau II VI.5.2 Tenaga


VI.2.1 Bahan - Pekerja 0.100 Oh x
- Kayu kamper, (papan) 0.040 M3 x Rp 7,300,000.00 = Rp 292,000.00 - Tukang kayu 0.100 Oh x
- Lem Kayu 0.050 Kg x Rp 18,000.00 = Rp 900.00 - Kepala tukang 0.010 Oh x
Jumlah (I) = Rp 292,900.00 - Mandor 0.005 Oh x

VI.2.2 Tenaga
- Pekerja 1.000 Oh x Rp 38,000.00 = Rp 38,000.00
- Tukang kayu 3.000 Oh x Rp 50,000.00 = Rp 150,000.00 VI.6 1 m2 Pasang rangka langit-langit (60 x 120) cm, kayu klas I (jati)
- Kepala tukang 0.300 Oh x Rp 57,000.00 = Rp 17,100.00 VI.6.1 Bahan
- Mandor 0.050 Oh x Rp 50,000.00 = Rp 2,500.00 - Kayu jati, (balok) 0.0130 M3 x
Jumlah (II) = Rp 207,600.00 - Paku usuk 0.120 Kg x
Jumlah (I)+(II) = Rp 500,500.00

VI.3 1 m3 Pasang Konstruksi kuda-kuda kayu Konvensional kayu I ; II ; III VI.6.2 Tenaga
VI.3.1 Bahan - Pekerja 0.170 Oh x
- Kayu kamper, (balok) 1.1000 M3 x Rp 6,700,000.00 = Rp 7,370,000.00 - Tukang kayu 0.270 Oh x
- Besi strip 15.000 Kg x Rp 14,000.00 = Rp 210,000.00 - Kepala tukang 0.027 Oh x
- Paku 5.600 Kg x Rp 12,000.00 = Rp 67,200.00 - Mandor 0.009 Oh x
Jumlah (I) = Rp 7,647,200.00

VI.3.2 Tenaga
- Pekerja 4.000 Oh x Rp 38,000.00 = Rp 152,000.00
- Tukang kayu 12.000 Oh x Rp 50,000.00 = Rp 600,000.00 VI.7 1 m' Pasang listplank ukuran (3 x 30) cm, kayu klas I atau II
- Kepala tukang 1.200 Oh x Rp 57,000.00 = Rp 68,400.00 VI.7.1 Bahan
- Mandor 0.200 Oh x Rp 50,000.00 = Rp 10,000.00 - Kayu kamper, (papan) 0.011 M3 x
Jumlah (II) = Rp 830,400.00 - Paku 0.0500 Kg x
Jumlah (I)+(II) = Rp 8,477,600.00

VI.4 1 m3 Pasang Konstruksi Gording, kayu klas II VI.7.2 Tenaga


VI.4.1 Bahan - Pekerja 0.100 Oh x
- Kayu kamper, (balok) 1.1000 M x
3
Rp 6,700,000.00 = Rp 7,370,000.00 - Tukang kayu 0.200 Oh x
- Besi strip 15.000 Kg x Rp 14,000.00 = Rp 210,000.00 - Kepala tukang 0.020 Oh x
- Paku 3.000 Kg x Rp 12,000.00 = Rp 36,000.00 - Mandor 0.005 Oh x
Jumlah (I) = Rp 7,616,000.00
Harga bahan Jumlah

Rp 38,000.00 = Rp 91,200.00
Rp 50,000.00 = Rp 360,000.00
Rp 57,000.00 = Rp 41,040.00
Rp 50,000.00 = Rp 6,000.00
Jumlah (II) = Rp 498,240.00
Jumlah (I)+(II) = Rp 8,114,240.00

dok ,kayu klas II

Rp 6,700,000.00 = Rp 93,800.00
Rp 6,700,000.00 = Rp 24,120.00
Rp 12,000.00 = Rp 3,000.00
Jumlah (I) = Rp 120,920.00

Rp 38,000.00 = Rp 3,800.00
Rp 50,000.00 = Rp 5,000.00
Rp 57,000.00 = Rp 570.00
Rp 50,000.00 = Rp 250.00
Jumlah (II) = Rp 9,620.00
Jumlah (I)+(II) = Rp 130,540.00

0) cm, kayu klas I (jati)

Rp 19,000,000.00 = Rp 247,000.00
Rp 12,000.00 = Rp 1,440.00
Jumlah (I) = Rp 248,440.00

Rp 38,000.00 = Rp 6,460.00
Rp 50,000.00 = Rp 13,500.00
Rp 57,000.00 = Rp 1,539.00
Rp 50,000.00 = Rp 425.00
Jumlah (II) = Rp 21,924.00
Jumlah (I)+(II) = Rp 270,364.00

kayu klas I atau II

Rp 7,300,000.00 = Rp 80,300.00
Rp 12,000.00 = Rp 600.00
Jumlah (I) = Rp 80,900.00

Rp 38,000.00 = Rp 3,800.00
Rp 50,000.00 = Rp 10,000.00
Rp 57,000.00 = Rp 1,140.00
Rp 50,000.00 = Rp 250.00
Jumlah (II) = Rp 15,190.00
Jumlah (I)+(II) = Rp 96,090.00
VII. Analisa biaya konstruksi pekerjaan beton (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien Sat
VII.1 1 m3 membuat sloof beton bertulang (200 kg besi+bekisting) - Pasir beton 0.810 M3 x Rp
VII.1.1 Bahan - Kayu Klas II Balok 0.140 M3 x Rp
- Kayu Klas III (Terentang) 0.2700 M 3
x Rp 550,000.00 = Rp 148,500.00 - Plywood 9 mm 2.800 Lbr x Rp
- Paku 2.000 Kg x Rp 12,000.00 = Rp 24,000.00 - Dolken kayu galam f-8-10/4 m 16.000 Btg x Rp
- Minyak bekisting 0.600 Lt x Rp 8,000.00 = Rp 4,800.00 Jumlah (I)
- Besi beton polos (U-24) 210.000 Kg x Rp 8,000.00 = Rp 1,680,000.00
- Kawat beton 3.000 Kg x Rp 12,000.00 = Rp 36,000.00 VII.3.2 Tenaga
- Semen portland 336.000 Kg x Rp 1,187.50 = Rp 399,000.00 - Pekerja 6.350 Oh x Rp
- Pasir beton (muntilan) 0.540 M3 x Rp 195,000.00 = Rp 105,300.00 - Tukang batu 0.275 Oh x Rp
- Pasir beton 0.810 M3 x Rp 180,000.00 = Rp 145,800.00 - Tukang kayu 1.650 Oh x Rp
Jumlah (I) = Rp 2,543,400.00 - Tukang besi 1.400 Oh x Rp
- Kepala tukang 0.333 Oh x Rp
VII.1.2 Tenaga - Mandor 0.318 Oh x Rp
- Pekerja 5.650 Oh x Rp 38,000.00 = Rp 214,700.00 Jumlah (II)
- Tukang batu 0.275 Oh x Rp 50,000.00 = Rp 13,750.00 Jumlah (I)+(
- Tukang kayu 1.560 Oh x Rp 50,000.00 = Rp 78,000.00
- Tukang besi 1.400 Oh x Rp 50,000.00 = Rp 70,000.00 VII.4 1 m3 membuat dinding beton bertulang (150 kg besi+bekisting)
- Kepala tukang 0.323 Oh x Rp 57,000.00 = Rp 18,411.00 VII.4.1 Bahan
- Mandor 0.283 Oh x Rp 50,000.00 = Rp 14,150.00 - Kayu Klas III (Terentang) 0.240 M3 x Rp
Jumlah (II) = Rp 409,011.00 - Paku 3.200 Kg x Rp
Jumlah (I)+(II) = Rp 2,952,411.00 - Minyak bekisting 1.600 Lt x Rp
- Besi beton polos (U-24) 157.500 Kg x Rp
VII.2 1 m3 membuat kolom beton bertulang (300 kg besi+bekisting) - Kawat beton 2.250 Kg x Rp
VII.2.1 Bahan - Semen portland 336.000 Kg x Rp
- Kayu Klas III (Terentang) 0.4000 M3 x Rp 550,000.00 = Rp 220,000.00 - Pasir beton 0.540 M3 x Rp
- Paku 4.000 Kg x Rp 12,000.00 = Rp 48,000.00 - Batu pecah 2/3 0.810 M3 x Rp
- Minyak bekisting 2.000 Lt x Rp 8,000.00 = Rp 16,000.00 - Kayu Klas II Balok 0.1600 M3 x Rp
- Besi beton polos (U-24) 315.000 Kg x Rp 8,000.00 = Rp 2,520,000.00 - Plywood 9 mm 2.800 Lbr x Rp
- Kawat beton 4.500 Kg x Rp 12,000.00 = Rp 54,000.00 - Dolken kayu galam f-8-10/4 m 24.000 Btg x Rp
- Semen portland 336.000 Kg x Rp 1,187.50 = Rp 399,000.00 Jumlah (I)
- Pasir beton 0.540 M3 x Rp 195,000.00 = Rp 105,300.00
- Pasir beton 0.810 M3 x Rp 180,000.00 = Rp 145,800.00 VII.4.2 Tenaga
- Kayu Klas II Balok 0.150 M3 x Rp 5,500,000.00 = Rp 825,000.00 - Pekerja 5.300 Oh x Rp
- Plywood 9 mm 3.500 Lbr x Rp 145,000.00 = Rp 507,500.00 - Tukang batu 0.275 Oh x Rp
- Dolken kayu galam f-8-10/4 m 20.000 Btg x Rp 18,000.00 = Rp 360,000.00 - Tukang kayu 1.300 Oh x Rp
Jumlah (I) = Rp 5,200,600.00 - Tukang besi 1.050 Oh x Rp
- Kepala tukang 0.262 Oh x Rp
VII.2.2 Tenaga - Mandor 0.265 Oh x Rp
- Pekerja 7.050 Oh x Rp 38,000.00 = Rp 267,900.00 Jumlah (II)
- Tukang batu 0.275 Oh x Rp 50,000.00 = Rp 13,750.00 Jumlah (I)+(
- Tukang kayu 1.650 Oh x Rp 50,000.00 = Rp 82,500.00
- Tukang besi 2.100 Oh x Rp 50,000.00 = Rp 105,000.00 VII.5 1 m3 membuat beton cor 1:2:3
- Kepala tukang 0.403 Oh x Rp 57,000.00 = Rp 22,971.00 VII.5.1 Bahan
- Mandor 0.353 Oh x Rp 50,000.00 = Rp 17,650.00 - Semen portland 2.125 Kg x Rp
Jumlah (II) = Rp 509,771.00 - Pasir beton 0.540 M3 x Rp
Jumlah (I)+(II) = Rp 5,710,371.00 - Kerikil Beton 0.810 M3 x Rp
Jumlah (I)
VII.3 1 m3 membuat balok beton bertulang (200 kg besi+bekisting)
VII.3.1 Bahan VII.5.2 Tenaga
- Kayu Klas III (Terentang) 0.3200 M3 x Rp 550,000.00 = Rp 176,000.00 - Pekerja 5.3000 Oh x Rp
- Paku 3.200 Kg x Rp 12,000.00 = Rp 38,400.00 - Tukang batu 0.275 Oh x Rp
- Minyak bekisting 1.600 Lt x Rp 8,000.00 = Rp 12,800.00 - Kepala tukang 0.262 Oh x Rp
- Besi beton polos (U-24) 210.000 Kg x Rp 8,000.00 = Rp 1,680,000.00 - Mandor 0.265 Oh x Rp
- Kawat beton 3.000 Kg x Rp 12,000.00 = Rp 36,000.00 Jumlah (II)
- Semen portland 336.000 Kg x Rp 1,187.50 = Rp 399,000.00 Jumlah (I)+(
- Pasir beton 0.540 M3 x Rp 195,000.00 = Rp 105,300.00
Harga bahan Jumlah
180,000.00 = Rp 145,800.00
5,500,000.00 = Rp 770,000.00
145,000.00 = Rp 406,000.00
18,000.00 = Rp 288,000.00
Jumlah (I) = Rp 2,447,500.00

38,000.00 = Rp 241,300.00
50,000.00 = Rp 13,750.00
50,000.00 = Rp 82,500.00
50,000.00 = Rp 70,000.00
57,000.00 = Rp 18,981.00
50,000.00 = Rp 15,900.00
Jumlah (II) = Rp 442,431.00
Jumlah (I)+(II) = Rp 2,889,931.00

g besi+bekisting)

550,000.00 = Rp 132,000.00
12,000.00 = Rp 38,400.00
8,000.00 = Rp 12,800.00
8,000.00 = Rp 1,260,000.00
12,000.00 = Rp 27,000.00
1,187.50 = Rp 399,000.00
195,000.00 = Rp 105,300.00
180,000.00 = Rp 145,800.00
5,500,000.00 = Rp 880,000.00
145,000.00 = Rp 406,000.00
18,000.00 = Rp 432,000.00
Jumlah (I) = Rp 3,838,300.00

38,000.00 = Rp 201,400.00
50,000.00 = Rp 13,750.00
50,000.00 = Rp 65,000.00
50,000.00 = Rp 52,500.00
57,000.00 = Rp 14,934.00
50,000.00 = Rp 13,250.00
Jumlah (II) = Rp 360,834.00
Jumlah (I)+(II) = Rp 4,199,134.00
52,000.00 = Rp 110,500.00
50,000.00 = Rp 27,000.00
180,000.00 = Rp 145,800.00
Jumlah (I) = Rp 283,300.00

38,000.00 = Rp 201,400.00
50,000.00 = Rp 13,750.00
57,000.00 = Rp 14,934.00
50,000.00 = Rp 13,250.00
Jumlah (II) = Rp 243,334.00
Jumlah (I)+(II) = Rp 526,634.00
VIII. Analisa biaya konstruksi pekerjaan penutup atap (SNI 2012) X. Analisa biaya konstruksi pekerjaan sanitasi (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien Sat
VIII.1 1 m2 pasang atap genteng kodok / Glasur X.2 memasang 1 buah wastafel
VIII.1.1 Bahan X.2.1 Bahan
- Genteng kodok / Glasur 25.000 Bh x Rp 2,500.00 = Rp 62,500.00 - Wastafel 1 Bh x Rp
Jumlah (I) = Rp 62,500.00 - Perlengkapan 30% 0.300 - x Rp
- Semen Portland 6.000 Kg x Rp
VIII.1.2 Tenaga - Pasir pasang 0.010 M3 x Rp
- Pekerja 0.150 Oh x Rp 38,000.00 = Rp 5,700.00 Jumlah (I)
- Tukang kayu 0.075 Oh x Rp 50,000.00 = Rp 3,750.00
- Kepala tukang 0.008 Oh x Rp 57,000.00 = Rp 456.00 X.2.2 Tenaga
- Mandor 0.008 Oh x Rp 50,000.00 = Rp 400.00 - Pekerja 1.2 Oh x Rp
Jumlah (II) = Rp 10,306.00 - Tukang batu 0.145 Oh x Rp
Jumlah (I)+(II) = Rp 72,806.00 - Kepala tukang 0.150 Oh x Rp
- Mandor 0.100 Oh x Rp
IX. Analisa biaya konstruksi pekerjaan Langit-langit (SNI2012) Jumlah (II)
Jumlah (I)+(I
Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah
IX.1 1 m2 Langit-langit gypsum board, tebal 9 mm X.3 memasang 1 m' pipa PVC tipe AW diameter 3/4"
IX.1.1 Bahan X.3.1 Bahan
- Gymsum Board (60x120 x 9) mm 0.364 Lbr x Rp 45,000.00 = Rp 16,380.00 - Pipa PVC tipe AW 1/2" 1.2 M' x Rp
- Paku sekrup 0.110 Kg x Rp 13,500.00 = Rp 1,485.00 - Perlengkapan 35% 0.350 - x Rp
- Tepung gypsum 0.450 Kg x Rp 3,500.00 = Rp 1,575.00 Jumlah (I)
- Alkasit 0.003 Kg x Rp 40,000.00 = Rp 120.00
Jumlah (I) = Rp 19,560.00 X.3.2 Tenaga
- Pekerja 0.036 Oh x Rp
IX.1.2 Tenaga - Tukang batu 0.06 Oh x Rp
- Pekerja 0.100 Oh x Rp 38,000.00 = Rp 3,800.00 - Kepala tukang 0.006 Oh x Rp
- Tukang kayu 0.050 Oh x Rp 50,000.00 = Rp 2,500.00 - Mandor 0.002 Oh x Rp
- Kepala tukang 0.005 Oh x Rp 57,000.00 = Rp 285.00 Jumlah (II)
- Mandor 0.005 Oh x Rp 50,000.00 = Rp 250.00 Jumlah (I)+(I
Jumlah (II) = Rp 6,835.00
Jumlah (I)+(II) = Rp 26,395.00 X.4 memasang 1 m' pipa PVC tipe AW diameter 23"
X.4.1 Bahan
IX.2 1 m' list langit-langit profil cornees gypsum lebar 5-10 cm - Pipa PVC tipe AW 2" 1.200 M' x Rp
IX.2.1 Bahan - Perlengkapan 35% 0.350 hrg x Rp
- List profil cornees gypsum 1.100 M1 x Rp 8,000.00 = Rp 8,800.00 Jumlah (I)
- Tepung gypsum 1.050 Kg x Rp 3,500.00 = Rp 3,675.00
- Alkasit 0.005 Kg x Rp 40,000.00 = Rp 212.00 X.4.2 Tenaga
Jumlah (I) = Rp 12,475.00 - Pekerja 0.054 Oh x Rp
- Tukang batu 0.090 Oh x Rp
IX.2.2 Tenaga - Kepala tukang 0.009 Oh x Rp
- Pekerja 0.113 Oh x Rp 38,000.00 = Rp 4,275.00 - Mandor 0.003 Oh x Rp
- Tukang kayu 0.040 Oh x Rp 50,000.00 = Rp 2,000.00 Jumlah (II)
- Kepala tukang 0.004 Oh x Rp 57,000.00 = Rp 228.00 Jumlah (I)+(I
- Mandor 0.007 Oh x Rp 50,000.00 = Rp 325.00
Jumlah (II) = Rp 6,828.00 X.5 memasang 1 buah kran air diameter 3/4" atau 1/2"
Jumlah (I)+(II) = Rp 19,303.00 X.5.1 Bahan
X.1 memasang 1 buah kloset jongkok/porselen - Kran air 1.000 Bh x Rp
X.1.1 Bahan - Seal tape 0.025 Bh x Rp
- Kloset Jongkok 1.000 Bh x Rp 105,000.00 = Rp 105,000.00 Jumlah (I)
- Semen Portland 6.000 Kg x Rp 1,187.50 = Rp 7,125.00
- Pasir Pasang 0.010 Kg x Rp 120,000.00 = Rp 1,200.00 X.5.2 Tenaga
Jumlah (I) = Rp 113,325.00 - Pekerja 0.010 Oh x Rp
X.1.2 Tenaga - Tukang batu 0.100 Oh x Rp
- Pekerja 1.000 Oh x Rp 38,000.00 = Rp 38,000.00 - Kepala tukang 0.010 Oh x Rp
- Tukang batu 1.500 Oh x Rp 50,000.00 = Rp 75,000.00 - Mandor 0.005 Oh x Rp
- Kepala tukang 1.500 Oh x Rp 57,000.00 = Rp 85,500.00 Jumlah (II)
- Mandor 0.160 Oh x Rp 50,000.00 = Rp 8,000.00 Jumlah (I)+(I
Jumlah (II) = Rp 206,500.00
Jumlah (I)+(II) = Rp 319,825.00
X.6 Pekerjaan Septictank per Unit X.10 Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, ting
X.6. 1 Bahan X.10. 1 Bahan
- Galian Tanah 5.586 m x Rp 23,500.00 = Rp 131,261.60 - Batu bata 87.000 bh x Rp
- Urugan Pasir 0.390 m x Rp 17,000.00 = Rp 6,630.00 - PC 40.000 kg x Rp
- Aanstamping 0.599 m x Rp 217,000.00 = Rp 129,874.50 - Pasir pasang 0.070 m3 x Rp
- Pas. Batu Merah 1 : 2 17.950 m x Rp 50,000.00 = Rp 897,500.00 - Batu kerikil 0.070 m3 x Rp
- Plesteran 1 : 2 17.95 m x Rp 21700 = Rp 389,515.00 - Besi beton 1.6 kg x Rp
- Cor Beton Camp. 1:2:3 0.572 m x Rp 457,000.00 = Rp 261,404.00 - Pasir beton 0.060 m3 x Rp
- Berat Besi Tulangan 33.800 m x Rp 9,000.00 = Rp 304,200.00
- Pipa + Asesoris 1.000 set x Rp 80,000.00 = Rp 80,000.00 X.10. 2 Tenaga
- Handle Bak Kontrol 1.000 Buax Rp 3,000.00 = Rp 3,000.00 - Pekerja 3.200 Oh x Rp
= Rp 2,203,385.10 - Tukang batu 1.015 Oh x Rp
X.6. 2 Tenaga - Kepala tukang 0.002 Oh x Rp
- Pekerja 0.000 Oh x Rp 38,000.00 = Rp - - Mandor 0.016 Oh x Rp
- Tukang batu 0.000 Oh x Rp 50,000.00 = Rp -
- Kepala tukang 0.000 Oh x Rp 57,000.00 = Rp -
- Mandor 0.000 Oh x Rp 50,000.00 = Rp -
= Rp -
= Rp 2,203,385.10

X.7 memasang 1 m' pipa galvanis, diameter 1"


X.7.1 Bahan
- Pipa galvanis dia 3/4" 1.200 M' x Rp 21,666.67 = Rp 26,000.00
- Perlengkapan 35% 0.350 - x Rp 21,666.67 = Rp 7,583.33
Jumlah (I) = Rp 33,583.33

X.7.2 Tenaga
- Pekerja 0.054 Oh x Rp 38,000.00 = Rp 2,052.00
- Tukang ledeng 0.090 Oh x Rp 50,000.00 = Rp 4,500.00
- Kepala tukang 0.009 Oh x Rp 57,000.00 = Rp 513.00
- Mandor 0.027 Oh x Rp 50,000.00 = Rp 1,350.00
Jumlah (II) = Rp 8,415.00
Jumlah (I)+(II) = Rp 41,998.00

X.8 memasang 1 buah floor drain


X.8.1 Bahan
- Floor drain 1 Bh x Rp 22,500.00 = Rp 22,500.00
Jumlah (I) = Rp 22,500.00

X.8.2 Tenaga
- Pekerja 0.01 Oh x Rp 38,000.00 = Rp 380.00
- Tukang batu 0.1 Oh x Rp 50,000.00 = Rp 5,000.00
- Kepala tukang 0.01 Oh x Rp 57,000.00 = Rp 570.00
- Mandor 0.005 Oh x Rp 50,000.00 = Rp 250.00
Jumlah (II) = Rp 6,200.00
Jumlah (I)+(II) = Rp 28,700.00
X.9 memasang bak fiberglass volume 1m3 air
X.9.1 Bahan
- Bak fiberglass 1.000 M' x Rp 825,000.00 = Rp 825,000.00
- Perlengkapan 12% 0.120 - x Rp 825,000.00 = Rp 99,000.00
Jumlah (I) = Rp 924,000.00

X.7.2 Tenaga
- Pekerja 3.000 Oh x Rp 38,000.00 = Rp 114,000.00
- Tukang batu 4.500 Oh x Rp 50,000.00 = Rp 225,000.00
- Kepala tukang 0.900 Oh x Rp 57,000.00 = Rp 51,300.00
- Mandor 0.900 Oh x Rp 50,000.00 = Rp 45,000.00
Jumlah (II) = Rp 435,300.00
Jumlah (I)+(II) = Rp 1,359,300.00
Harga bahan Jumlah

700,000.00 = Rp 700,000.00
700,000.00 = Rp 210,000.00
1,187.50 = Rp 7,125.00
130,000.00 = Rp 1,300.00
Jumlah (I) = Rp 918,425.00

38,000.00 = Rp 45,600.00
50,000.00 = Rp 7,250.00
57,000.00 = Rp 8,550.00
50,000.00 = Rp 5,000.00
Jumlah (II) = Rp 66,400.00
Jumlah (I)+(II) = Rp 984,825.00

5,625.00 = Rp 6,750.00
5,625.00 = Rp 1,968.75
Jumlah (I) = Rp 8,718.75

38,000.00 = Rp 1,368.00
50,000.00 = Rp 3,000.00
57,000.00 = Rp 342.00
50,000.00 = Rp 90.00
Jumlah (II) = Rp 4,800.00
Jumlah (I)+(II) = Rp 13,518.75

20,416.67 = Rp 24,500.00
20,416.67 = Rp 7,145.83
Jumlah (I) = Rp 31,645.83

38,000.00 = Rp 2,052.00
50,000.00 = Rp 4,500.00
57,000.00 = Rp 513.00
50,000.00 = Rp 135.00
Jumlah (II) = Rp 7,200.00
Jumlah (I)+(II) = Rp 38,845.83
7,500.00 = Rp 7,500.00
2,000.00 = Rp 50.00
Jumlah (I) = Rp 7,550.00

38,000.00 = Rp 380.00
50,000.00 = Rp 5,000.00
45,000.00 = Rp 450.00
50,000.00 = Rp 250.00
Jumlah (II) = Rp 6,080.00
Jumlah (I)+(II) = Rp 13,630.00
Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm

450.00 = Rp 39,150.00
1,187.50 = Rp 47,500.00
120,000.00 = Rp 8,400.00
180,000.00 = Rp 12,600.00
8000 = Rp 12,800.00
195,000.00 = Rp 11,700.00
= Rp 132,150.00

38,000.00 = Rp 121,600.00
50,000.00 = Rp 50,750.00
57,000.00 = Rp 85.50
50,000.00 = Rp 800.00
= Rp 173,235.50
= Rp 305,385.50
IX. Analisa biaya konstruksi pekerjaan Langit-langit (SNI2011)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah


IX.1 1 m Langit-langit gypsum board, tebal 9 mm
2

IX.1.1 Bahan
- Gymsum Board (60x120 x 9) mm 0.364 Lbr x Rp 45,000.00 = Rp 16,380.00
- Paku sekrup 0.110 Kg x Rp 13,500.00 = Rp 1,485.00
- Tepung gypsum 0.450 Kg x Rp 3,500.00 = Rp 1,575.00
- Alkasit 0.003 Kg x Rp 40,000.00 = Rp 120.00
Jumlah (I) = Rp 19,560.00

IX.1.2 Tenaga
- Pekerja 0.100 Oh x Rp 38,000.00 = Rp 3,800.00
- Tukang kayu 0.050 Oh x Rp 50,000.00 = Rp 2,500.00
- Kepala tukang 0.005 Oh x Rp 57,000.00 = Rp 285.00
- Mandor 0.005 Oh x Rp 50,000.00 = Rp 250.00
Jumlah (II) = Rp 6,835.00
Jumlah (I)+(II) = Rp 26,395.00

IX.2 1 m' list langit-langit profil cornees gypsum lebar 5-10 cm


IX.2.1 Bahan
- List profil cornees gypsum 1.100 M1 x Rp 8,000.00 = Rp 8,800.00
- Tepung gypsum 1.050 Kg x Rp 3,500.00 = Rp 3,675.00
- Alkasit 0.005 Kg x Rp 40,000.00 = Rp 212.00
Jumlah (I) = Rp 12,475.00

IX.2.2 Tenaga
- Pekerja 0.113 Oh x Rp 38,000.00 = Rp 4,275.00
- Tukang kayu 0.040 Oh x Rp 50,000.00 = Rp 2,000.00
- Kepala tukang 0.004 Oh x Rp 57,000.00 = Rp 228.00
- Mandor 0.007 Oh x Rp 50,000.00 = Rp 325.00
Jumlah (II) = Rp 6,828.00
Jumlah (I)+(II) = Rp 19,303.00
X. Analisa biaya konstruksi pekerjaan sanitasi (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat


X.1 memasang 1 buah kloset jongkok/porselen
X.1.1 Bahan
- Kloset Jongkok 1.000 Bh x Rp
- Semen Portland 6.000 Kg x Rp
- Pasir Pasang 0.010 Kg x Rp
Jumlah (I)

X.1.2 Tenaga
- Pekerja 1.000 Oh x Rp
- Tukang batu 1.500 Oh x Rp
- Kepala tukang 1.500 Oh x Rp
- Mandor 0.160 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

X.2 memasang 1 buah wastafel


X.2.1 Bahan
- Wastafel 1.000 Bh x Rp
- Perlengkapan 30% 0.300 - x Rp
- Semen Portland 6.000 Kg x Rp
- Pasir pasang 0.010 M3 x Rp
Jumlah (I)

X.2.2 Tenaga
- Pekerja 1.200 Oh x Rp
- Tukang batu 0.145 Oh x Rp
- Kepala tukang 0.150 Oh x Rp
- Mandor 0.100 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

X.3 memasang 1 m' pipa PVC tipe AW diameter 3/4"


X.3.1 Bahan
- Pipa PVC tipe AW 1/2" 1.200 M' x Rp
- Perlengkapan 35% 0.350 - x Rp
Jumlah (I)

X.3.2 Tenaga
- Pekerja 0.036 Oh x Rp
- Tukang batu 0.060 Oh x Rp
- Kepala tukang 0.006 Oh x Rp
- Mandor 0.0018 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)
X.4 memasang 1 m' pipa PVC tipe AW diameter 23"
X.4.1 Bahan
- Pipa PVC tipe AW 2" 1.200 M' x Rp
- Perlengkapan 35% 0.350 hrg px Rp
Jumlah (I)

X.4.2 Tenaga
- Pekerja 0.054 Oh x Rp
- Tukang batu 0.090 Oh x Rp
- Kepala tukang 0.009 Oh x Rp
- Mandor 0.0027 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)
X.5 memasang 1 buah kran air diameter 3/4" atau 1/2"
X.5.1 Bahan
- Kran air 1.000 Bh x Rp
- Seal tape 0.025 Bh x Rp
Jumlah (I)

X.5.2 Tenaga
- Pekerja 0.010 Oh x Rp
- Tukang batu 0.100 Oh x Rp
- Kepala tukang 0.010 Oh x Rp
- Mandor 0.005 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

X.6 Pekerjaan Septictank per Unit


X.6. 1 Bahan
- Galian Tanah 5.5856 m x Rp
- Urugan Pasir 0.3900 m x Rp
- Aanstamping 0.5985 m x Rp
- Pas. Batu Merah 1 : 2 17.95 m x Rp
- Plesteran 1 : 2 17.95 m x Rp
- Cor Beton Camp. 1:2:3 0.5720 m x Rp
- Berat Besi Tulangan 33.80 m x Rp
- Pipa + Asesoris 1.000 set x Rp
- Handle Bak Kontrol 1.000Buahx Rp

X.6. 2 Tenaga
- Pekerja 0.000 Oh x Rp
- Tukang batu 0.000 Oh x Rp
- Kepala tukang 0.000 Oh x Rp
- Mandor 0.000 Oh x Rp

X.7 memasang 1 m' pipa galvanis, diameter 1"


X.7.1 Bahan
- Pipa galvanis dia 3/4" 1.200 M' x Rp
- Perlengkapan 35% 0.350 - x Rp
Jumlah (I)

X.7.2 Tenaga
- Pekerja 0.054 Oh x Rp
- Tukang ledeng 0.090 Oh x Rp
- Kepala tukang 0.009 Oh x Rp
- Mandor 0.027 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)
X.8 memasang 1 buah floor drain
X.8.1 Bahan
- Floor drain 1.000 Bh x Rp
Jumlah (I)

X.8.2 Tenaga
- Pekerja 0.010 Oh x Rp
- Tukang batu 0.100 Oh x Rp
- Kepala tukang 0.010 Oh x Rp
- Mandor 0.005 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

X.9 memasang bak fiberglass volume 1m3 air


X.9.1 Bahan
- Bak fiberglass 1.000 M' x Rp
- Perlengkapan 12% 0.120 - x Rp
Jumlah (I)

X.7.2 Tenaga
- Pekerja 3.000 Oh x Rp
- Tukang batu 4.500 Oh x Rp
- Kepala tukang 0.900 Oh x Rp
- Mandor 0.900 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

X.10 Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm
X.10. 1 Bahan
- Batu bata 87.0000 bh x Rp
- PC 40.0000 kg x Rp
- Pasir pasang 0.0700 m3 x Rp
- Batu kerikil 0.0700 m3 x Rp
- Besi beton 1.6000 kg x Rp
- Pasir beton 0.0600 m3 x Rp

X.10. 2 Tenaga
- Pekerja 3.200 Oh x Rp
- Tukang batu 1.015 Oh x Rp
- Kepala tukang 0.002 Oh x Rp
- Mandor 0.016 Oh x Rp
Harga bahan Jumlah

105,000.00 = Rp 105,000.00
1,187.50 = Rp 7,125.00
120,000.00 = Rp 1,200.00
Jumlah (I) = Rp 113,325.00

38,000.00 = Rp 38,000.00
50,000.00 = Rp 75,000.00
57,000.00 = Rp 85,500.00
50,000.00 = Rp 8,000.00
Jumlah (II) = Rp 206,500.00
Jumlah (I)+(II) = Rp 319,825.00

700,000.00 = Rp 700,000.00
700,000.00 = Rp 210,000.00
1,187.50 = Rp 7,125.00
130,000.00 = Rp 1,300.00
Jumlah (I) = Rp 918,425.00

38,000.00 = Rp 45,600.00
50,000.00 = Rp 7,250.00
57,000.00 = Rp 8,550.00
50,000.00 = Rp 5,000.00
Jumlah (II) = Rp 66,400.00
Jumlah (I)+(II) = Rp 984,825.00

5,625.00 = Rp 6,750.00
5,625.00 = Rp 1,968.75
Jumlah (I) = Rp 8,718.75

38,000.00 = Rp 1,368.00
50,000.00 = Rp 3,000.00
57,000.00 = Rp 342.00
50,000.00 = Rp 90.00
Jumlah (II) = Rp 4,800.00
Jumlah (I)+(II) = Rp 13,518.75
20,416.67 = Rp 24,500.00
20,416.67 = Rp 7,145.83
Jumlah (I) = Rp 31,645.83

38,000.00 = Rp 2,052.00
50,000.00 = Rp 4,500.00
57,000.00 = Rp 513.00
50,000.00 = Rp 135.00
Jumlah (II) = Rp 7,200.00
Jumlah (I)+(II) = Rp 38,845.83
7,500.00 = Rp 7,500.00
2,000.00 = Rp 50.00
Jumlah (I) = Rp 7,550.00

38,000.00 = Rp 380.00
50,000.00 = Rp 5,000.00
45,000.00 = Rp 450.00
50,000.00 = Rp 250.00
Jumlah (II) = Rp 6,080.00
Jumlah (I)+(II) = Rp 13,630.00

Rp 23,500.00 = Rp 131,261.60
Rp 17,000.00 = Rp 6,630.00
Rp 217,000.00 = Rp 129,874.50
Rp 50,000.00 = Rp 897,500.00
Rp 21,700.00 = Rp 389,515.00
Rp 457,000.00 = Rp 261,404.00
Rp 9,000.00 = Rp 304,200.00
Rp 80,000.00 = Rp 80,000.00
Rp 3,000.00 = Rp 3,000.00
= Rp 2,203,385.10

38,000.00 = Rp -
50,000.00 = Rp -
57,000.00 = Rp -
50,000.00 = Rp -
= Rp -
= Rp 2,203,385.10

21,666.67 = Rp 26,000.00
21,666.67 = Rp 7,583.33
Jumlah (I) = Rp 33,583.33

38,000.00 = Rp 2,052.00
50,000.00 = Rp 4,500.00
57,000.00 = Rp 513.00
50,000.00 = Rp 1,350.00
Jumlah (II) = Rp 8,415.00
Jumlah (I)+(II) = Rp 41,998.00
22,500.00 = Rp 22,500.00
Jumlah (I) = Rp 22,500.00

38,000.00 = Rp 380.00
50,000.00 = Rp 5,000.00
57,000.00 = Rp 570.00
50,000.00 = Rp 250.00
Jumlah (II) = Rp 6,200.00
Jumlah (I)+(II) = Rp 28,700.00

825,000.00 = Rp 825,000.00
825,000.00 = Rp 99,000.00
Jumlah (I) = Rp 924,000.00

38,000.00 = Rp 114,000.00
50,000.00 = Rp 225,000.00
57,000.00 = Rp 51,300.00
50,000.00 = Rp 45,000.00
Jumlah (II) = Rp 435,300.00
Jumlah (I)+(II) = Rp 1,359,300.00

batu bata ukuran (30 x 30) cm, tinggi 35 cm

Rp 450.00 = Rp 39,150.00
Rp 1,187.50 = Rp 47,500.00
Rp 120,000.00 = Rp 8,400.00
Rp 180,000.00 = Rp 12,600.00
Rp 8,000.00 = Rp 12,800.00
Rp 195,000.00 = Rp 11,700.00
= Rp 132,150.00

38,000.00 = Rp 121,600.00
50,000.00 = Rp 50,750.00
57,000.00 = Rp 85.50
50,000.00 = Rp 800.00
= Rp 173,235.50
= Rp 305,385.50
XI. Analisa biaya konstruksi pekerjaan listrik (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien Sat
XI.1 1 m1 pasang kabel NYM 2x 2,5 mm XI.7 1 bh pasang stop kontak
XI.1.1 Tenaga XI.7.1 Bahan
- Tukang listrik 0.005 Oh x Rp 50,000.00 = Rp 250.00 - Saklar ganda 1.000 bh x Rp
- Pekerja 0.005 Oh x Rp 38,000.00 = Rp 190.00 Jumlah (I)
- Mandor 0.005 Oh x Rp 50,000.00 = Rp 250.00
Jumlah (II) = Rp 690.00 XI.7.2 Tenaga
Jumlah (I)+(II) = Rp 690.00 - Pekerja 0.100 Oh x Rp
Jumlah (II)
XI.2 1 unit pasang Box KWH dan Meter Jumlah (I)+(
XI.2.1 Tenaga
- Tukang listrik 0.500 Oh x Rp 50,000.00 = Rp 25,000.00 XI.8 1 bh pasang lampu SL 18 w
- Pekerja 0.750 Oh x Rp 38,000.00 = Rp 28,500.00 XI.8.1 Bahan
- Mandor 0.250 Oh x Rp 50,000.00 = Rp 12,500.00 - Lampu SL 18 W 1.000 bh x Rp
- Pasang panel kontrol 1.0000 Oh x Rp 10,000.00 = Rp 10,000.00 Jumlah (I)
Jumlah (II) = Rp 76,000.00
Jumlah (I)+(II) = Rp 76,000.00 XI.8.2 Tenaga
- Pekerja 0.100 Oh x Rp
Jumlah (II)
XI.3 1 unit pasang Box panel dan panel kontrol Jumlah (I)+(
XI.3.1 Tenaga
- Tukang listrik 0.500 Oh x Rp 50,000.00 = Rp 25,000.00 XI.9 1 bh pasang lampu SL 10 W
- Pekerja 0.750 Oh x Rp 38,000.00 = Rp 28,500.00 XI.9.1 Bahan
- Mandor 0.250 Oh x Rp 50,000.00 = Rp 12,500.00 - Lampu SL 10 W 1.000 bh x Rp
- Pasang panel kontrol 1.0000 Oh x Rp 10,000.00 = Rp 10,000.00 Jumlah (I)
Jumlah (II) = Rp 76,000.00
Jumlah (I)+(II) = Rp 76,000.00 XI.9.2 Tenaga
- Pekerja 0.100 Oh x Rp
XI.4 1 titik pekerjaan fitting Jumlah (II)
XI.4.1 Bahan Jumlah (I)+(
- Titik lampu 1.000 ttk x Rp 10,000.00 = Rp 10,000.00
Jumlah (II) = Rp 10,000.00
Jumlah (I)+(II) = Rp 10,000.00

XI.5 1 bh pasang saklar tunggal


XI.5.1 Bahan
- Saklar tunggal 1.000 bh x Rp 15,000.00 = Rp 15,000.00
Jumlah (I) = Rp 15,000.00
Rp 30,000.00
XI.5.2 Tenaga
- Pekerja 0.100 Oh x Rp 38,000.00 = Rp 3,800.00
Jumlah (II) = Rp 3,800.00
Jumlah (I)+(II) = Rp 33,800.00
XI.6 1 bh pasang saklar ganda
XI.6.1 Bahan
- Saklar ganda 1.000 bh x Rp 20,500.00 = Rp 20,500.00
Jumlah (I) = Rp 20,500.00
Rp 41,000.00
XI.6.2 Tenaga
- Pekerja 0.100 Oh x Rp 38,000.00 = Rp 3,800.00
Jumlah (II) = Rp 3,800.00
Jumlah (I)+(II) = Rp 44,800.00
Harga bahan Jumlah

12,500.00 = Rp 12,500.00
Jumlah (I) = Rp 12,500.00
Rp 25,000.00

38,000.00 = Rp 3,800.00
Jumlah (II) = Rp 3,800.00
Jumlah (I)+(II) = Rp 28,800.00

27,000.00 = Rp 27,000.00
Jumlah (I) = Rp 27,000.00
Rp 54,000.00

38,000.00 = Rp 3,800.00
Jumlah (II) = Rp 3,800.00
Jumlah (I)+(II) = Rp 57,800.00

15,500.00 = Rp 15,500.00
Jumlah (I) = Rp 15,500.00
Rp 31,000.00

38,000.00 = Rp 3,800.00
Jumlah (II) = Rp 3,800.00
Jumlah (I)+(II) = Rp 34,800.00
XII. Analisa biaya konstruksi pekerjaan kunci dan kaca (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan Koefisien Sat
XII.1 1 bh pasang kunci tanam biasa XII.5 1 bh pasang grendel
XII.1.1 Bahan XII.5.1 Bahan
- Kunci tanam biasa 1.000 Bh x Rp 45,000.00 = Rp 45,000.00 - Grendel 1.000 bh
Jumlah (I) = Rp 45,000.00

XII.1.2 Tenaga XII.5.2 Tenaga


- Pekerja 0.010 Oh x Rp 38,000.00 = Rp 380.00 - Pekerja 0.020 Oh
- Tukang kayu 0.500 Oh x Rp 50,000.00 = Rp 25,000.00 - Tukang kayu 0.200 Oh
- Kepala tukang 0.010 Oh x Rp 57,000.00 = Rp 570.00 - Kepala tukang 0.020 Oh
- Mandor 0.005 Oh x Rp 50,000.00 = Rp 250.00 - Mandor 0.001 Oh
Jumlah (II) = Rp 26,200.00
Jumlah (I)+(II) = Rp 71,200.00

XII.2 1 bh pasang kunci tanam kamar mandi


XII.2.1 Bahan
- Kunci tanam kamar mandi 1.000 Bh x Rp 45,000.00 = Rp 45,000.00
Jumlah (I) = Rp 45,000.00

XII.2.2 Tenaga
- Pekerja 0.005 Oh x Rp 38,000.00 = Rp 190.00
- Tukang kayu 0.500 Oh x Rp 50,000.00 = Rp 25,000.00
- Kepala tukang 0.005 Oh x Rp 57,000.00 = Rp 285.00
- Mandor 0.0025 Oh x Rp 50,000.00 = Rp 125.00
Jumlah (II) = Rp 25,600.00
Jumlah (I)+(II) = Rp 70,600.00

XII.3 1 bh pasang engsel pintu


XII.3.1 Bahan
- Engsel pintu 1.000 Bh x Rp 2,250.00 = Rp 2,250.00
Jumlah (I) = Rp 2,250.00

XII.3.2 Tenaga
- Pekerja 0.015 Oh x Rp 38,000.00 = Rp 570.00
- Tukang kayu 0.150 Oh x Rp 50,000.00 = Rp 7,500.00
- Kepala tukang 0.015 Oh x Rp 57,000.00 = Rp 855.00
- Mandor 0.0075 Oh x Rp 50,000.00 = Rp 375.00
Jumlah (II) = Rp 9,300.00
Jumlah (I)+(II) = Rp 11,550.00

XII.4 1 m2 pasang kaca, tebal 5 mm


XII.4.1 Bahan
- Kaca tebal 5mm 1.100 M2 x Rp 65,000.00 = Rp 71,500.00
Jumlah (I) = Rp 71,500.00
XII.4.2 Tenaga
- Pekerja 0.015 Oh x Rp 38,000.00 = Rp 570.00
- Tukang kayu 0.150 Oh x Rp 50,000.00 = Rp 7,500.00
- Kepala tukang 0.015 Oh x Rp 57,000.00 = Rp 855.00
- Mandor 0.00075 Oh x Rp 50,000.00 = Rp 37.50
Jumlah (II) = Rp 8,962.50
Jumlah (I)+(II) = Rp 80,462.50
Harga bahan Jumlah

x Rp 7,500.00 = Rp 7,500.00
Jumlah (I) = Rp 7,500.00

x Rp 38,000.00 = Rp 760.00
x Rp 50,000.00 = Rp 10,000.00
x Rp 57,000.00 = Rp 1,140.00
x Rp 50,000.00 = Rp 50.00
Jumlah (II) = Rp 11,950.00
Jumlah (I)+(II) = Rp 19,450.00
XII. Analisa biaya konstruksi pekerjaan kunci dan kaca (SNI 2011)

Kode Uraian pekerjaan Koefisien Sat


XII.1 1 bh pasang kunci tanam biasa
XII.1.1 Bahan
- Kunci tanam biasa 1.000 Bh x Rp
Jumlah (I)

XII.1.2 Tenaga
- Pekerja 0.010 Oh x Rp
- Tukang kayu 0.500 Oh x Rp
- Kepala tukang 0.010 Oh x Rp
- Mandor 0.005 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

XII.2 1 bh pasang kunci tanam kamar mandi


XII.2.1 Bahan
- Kunci tanam kamar mandi 1.000 Bh x Rp
Jumlah (I)

XII.2.2 Tenaga
- Pekerja 0.005 Oh x Rp
- Tukang kayu 0.500 Oh x Rp
- Kepala tukang 0.005 Oh x Rp
- Mandor 0.0025 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

XII.3 1 bh pasang engsel pintu


XII.3.1 Bahan
- Engsel pintu 1.000 Bh x Rp
Jumlah (I)

XII.3.2 Tenaga
- Pekerja 0.015 Oh x Rp
- Tukang kayu 0.150 Oh x Rp
- Kepala tukang 0.015 Oh x Rp
- Mandor 0.0075 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

XII.4 1 m2 pasang kaca, tebal 5 mm


XII.4.1 Bahan
- Kaca tebal 5mm 1.100 M2 x Rp
Jumlah (I)
XII.4.2 Tenaga
- Pekerja 0.015 Oh x Rp
- Tukang kayu 0.150 Oh x Rp
- Kepala tukang 0.015 Oh x Rp
- Mandor 0.00075 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)

XII.5 1 m2 pasang kaca, tebal 5 mm


XII.5.1 Bahan
- Kait Angin 1.000 bh x Rp
Jumlah (I)

XII.5.2 Tenaga
- Pekerja 0.015 Oh x Rp
- Tukang kayu 0.150 Oh x Rp
- Kepala tukang 0.015 Oh x Rp
- Mandor 0.00075 Oh x Rp
Jumlah (II)
Jumlah (I)+(II)
Harga bahan Jumlah

125,000.00 = Rp 125,000.00
Jumlah (I) = Rp 125,000.00

38,000.00 = Rp 380.00
50,000.00 = Rp 25,000.00
57,000.00 = Rp 570.00
50,000.00 = Rp 250.00
Jumlah (II) = Rp 26,200.00
Jumlah (I)+(II) = Rp 151,200.00

45,000.00 = Rp 45,000.00
Jumlah (I) = Rp 45,000.00

38,000.00 = Rp 190.00
50,000.00 = Rp 25,000.00
57,000.00 = Rp 285.00
50,000.00 = Rp 125.00
Jumlah (II) = Rp 25,600.00
Jumlah (I)+(II) = Rp 70,600.00

5,000.00 = Rp 5,000.00
Jumlah (I) = Rp 5,000.00

38,000.00 = Rp 570.00
50,000.00 = Rp 7,500.00
57,000.00 = Rp 855.00
50,000.00 = Rp 375.00
Jumlah (II) = Rp 9,300.00
Jumlah (I)+(II) = Rp 14,300.00

65,000.00 = Rp 71,500.00
Jumlah (I) = Rp 71,500.00
38,000.00 = Rp 570.00
50,000.00 = Rp 7,500.00
57,000.00 = Rp 855.00
50,000.00 = Rp 37.50
Jumlah (II) = Rp 8,962.50
Jumlah (I)+(II) = Rp 80,462.50

5,000.00 = Rp 5,000.00
Jumlah (I) = Rp 5,000.00

38,000.00 = Rp 570.00
50,000.00 = Rp 7,500.00
57,000.00 = Rp 855.00
50,000.00 = Rp 37.50
Jumlah (II) = Rp 8,962.50
Jumlah (I)+(II) = Rp 13,962.50
XIII. Analisa biaya konstruksi pekerjaan penutup lantai dan dinding (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah Kode Uraian pekerjaan KoefisienSat
XIII.1 1 m2 pasang lantai keramik 20 x 20 cm XIII.4.2 Tenaga
XIII.1.1 Bahan - Pekerja 0.900 Oh x Rp
- Ubin keramik 20 x 20 cm 26.500 Bh x Rp 1,240.00 = Rp 32,860.00 - Tukang batu 0.450 Oh x Rp
- Semen portland 10.400 Kg x Rp 1,187.50 = Rp 12,350.00 - Kepala tukang 0.045 Oh x Rp
- Pasir pasang (muntilan) 0.0450 M3 x Rp 120,000.00 = Rp 5,400.00 - Mandor 0.045 Oh x Rp
- Semen warna 1.620 Kg x Rp 10,000.00 = Rp 16,200.00 Jumlah (II)
Jumlah (I) = Rp 66,810.00 Jumlah (I)+(

XIII.1.2 Tenaga XIII.5 1 m2 pasang dinding keramik 10 x 20 cm


- Pekerja 0.700 Oh x Rp 38,000.00 = Rp 26,600.00 XIII.5.1 Bahan
- Tukang batu 0.350 Oh x Rp 50,000.00 = Rp 17,500.00 - Ubin keramik 10 x 20 cm 5.300 Bh x Rp
- Kepala tukang 0.035 Oh x Rp 57,000.00 = Rp 1,995.00 - Semen portland 1.140 Kg x Rp
- Mandor 0.035 Oh x Rp 50,000.00 = Rp 1,750.00 - Pasir pasang (muntilan) 0.0030 M3 x Rp
Jumlah (II) = Rp 47,845.00 - Semen warna 0.025 Kg x Rp
Jumlah (I)+(II) = Rp 114,655.00 Jumlah (I)

XIII.2 1 m2 pasang lantai keramik 30 x 30 cm XIII.5.2 Tenaga


XIII.2.1 Bahan - Pekerja 0.090 Oh x Rp
- Ubin keramik 30 x 30 cm 11.870 Bh x Rp 2,727.27 = Rp 32,372.69 - Tukang batu 0.090 Oh x Rp
- Semen portland 10.000 Kg x Rp 1,187.50 = Rp 11,875.00 - Kepala tukang 0.009 Oh x Rp
- Pasir pasang (muntilan) 0.0450 M3 x Rp 120,000.00 = Rp 5,400.00 - Mandor 0.005 Oh x Rp
- Semen warna 1.500 Kg x Rp 10,000.00 = Rp 15,000.00 Jumlah (II)
Jumlah (I) = Rp 64,647.69 Jumlah (I)+(

XIII.2.2 Tenaga
- Pekerja 0.700 Oh x Rp 38,000.00 = Rp 26,600.00
- Tukang batu 0.350 Oh x Rp 50,000.00 = Rp 17,500.00
- Kepala tukang 0.035 Oh x Rp 57,000.00 = Rp 1,995.00
- Mandor 0.035 Oh x Rp 50,000.00 = Rp 1,750.00
Jumlah (II) = Rp 47,845.00
Jumlah (I)+(II) = Rp 112,492.69

XIII.3 1 m2 Pasang Paving Block t = 8cm K-300


XIII.3.1 Bahan
- Paving block 8 cm. abu-abu K-300 1.000 M2 x Rp 41,000.00 = Rp 41,000.00
- Pasir pasang (Muntilan) 0.0720 M3 x Rp 120,000.00 = Rp 8,640.00
- Alat bantu 0.0174 Unitx Rp 25,000.00 = Rp 435.00
Jumlah (I) = Rp 50,075.00
XIII.3.2 Tenaga
- Pekerja 0.500 Oh x Rp 38,000.00 = Rp 19,000.00
- Tukang batu 0.237 Oh x Rp 50,000.00 = Rp 11,850.00
- Kepala tukang 0.050 Oh x Rp 57,000.00 = Rp 2,850.00
- Mandor 0.010 Oh x Rp 50,000.00 = Rp 500.00
Jumlah (II) = Rp 34,200.00
Jumlah = Rp 84,275.00

XIII.4 1 m2 pasang dinding keramik 20 x 25 cm


XIII.4.1 Bahan
- Ubin keramik 20 x 20 cm 26.500 Bh x Rp 1,320.00 = Rp 34,980.00
- Semen portland 9.300 Kg x Rp 1,187.50 = Rp 11,043.75
- Pasir pasang (muntilan) 0.0180 M3 x Rp 120,000.00 = Rp 2,160.00
- Semen warna 1.940 Kg x Rp 10,000.00 = Rp 19,400.00
Jumlah (I) = Rp 67,583.75
Harga bahan Jumlah

38,000.00 = Rp 34,200.00
50,000.00 = Rp 22,500.00
57,000.00 = Rp 2,565.00
50,000.00 = Rp 2,250.00
Jumlah (II) = Rp 61,515.00
Jumlah (I)+(II) = Rp 129,099.00

5,000.00 = Rp 26,500.00
1,187.50 = Rp 1,353.75
120,000.00 = Rp 360.00
10,000.00 = Rp 250.00
Jumlah (I) = Rp 28,463.75

38,000.00 = Rp 3,420.00
50,000.00 = Rp 4,500.00
57,000.00 = Rp 513.00
50,000.00 = Rp 250.00
Jumlah (II) = Rp 8,683.00
Jumlah (I)+(II) = Rp 37,147.00
XIV. Analisa biaya konstruksi pekerjaan pengecetan (SNI 2012)

Kode Uraian pekerjaan Koefisien Sat Harga bahan Jumlah


XIV.1 1 m2 pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar,
2 lapis cat penutup
XIV.1.1 Bahan
- Meni kayu 0.200 Kg x Rp 12,500.00 = Rp 2,500.00
- Plamir kayu 0.150 Kg x Rp 11,000.00 = Rp 1,650.00
- Cat dasar (cat kayu) 0.170 Kg x Rp 13,200.00 = Rp 2,244.00
- Cat penutup (cat kayu) 0.260 Kg x Rp 39,000.00 = Rp 10,140.00
Jumlah (I) = Rp 16,534.00

XIV.1.2 Tenaga
- Pekerja 0.070 Oh x Rp 38,000.00 = Rp 2,660.00
- Tukang cat 0.009 Oh x Rp 50,000.00 = Rp 450.00
- Kepala tukang 0.0060 Oh x Rp 57,000.00 = Rp 342.00
- Mandor 0.0025 Oh x Rp 50,000.00 = Rp 125.00
Jumlah (II) = Rp 3,577.00
Jumlah (I)+(II) = Rp 20,111.00

XIV.2 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar,


2 lapis cat penutup)
XIV.2.1 Bahan
- Plamir tembok 0.100 Kg x Rp 10,500.00 = Rp 1,050.00
- Cat dasar (cat tembok) 0.100 Kg x Rp 12,500.00 = Rp 1,250.00
- Cat penutup (cat tembok)ex, catylac 0.260 Kg x Rp 90,000.00 = Rp 23,400.00
Jumlah (I) = Rp 25,700.00

XIV.2.2 Tenaga
- Pekerja 0.020 Oh x Rp 38,000.00 = Rp 760.00
- Tukang cat 0.063 Oh x Rp 50,000.00 = Rp 3,150.00
- Kepala tukang 0.0063 Oh x Rp 57,000.00 = Rp 359.10
- Mandor 0.0025 Oh x Rp 50,000.00 = Rp 125.00
Jumlah (II) = Rp 4,394.10
Jumlah (I)+(II) = Rp 30,094.10

XIV.3 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar,


2 lapis cat penutup)
XIV.3.1 Bahan
- Plamir tembok 0.100 Kg x Rp 10,500.00 = Rp 1,050.00
- Cat dasar (cat tembok) 0.100 Kg x Rp 12,500.00 = Rp 1,250.00
- Cat penutup (cat tembok), mowillex 0.260 Kg x Rp 185,000.00 = Rp 48,100.00
Jumlah (I) = Rp 50,400.00

XIV.3.2 Tenaga
- Pekerja 0.020 Oh x Rp 38,000.00 = Rp 760.00
- Tukang cat 0.063 Oh x Rp 50,000.00 = Rp 3,150.00
- Kepala tukang 0.0063 Oh x Rp 57,000.00 = Rp 359.10
- Mandor 0.0025 Oh x Rp 50,000.00 = Rp 125.00
Jumlah (II) = Rp 4,394.10
Jumlah (I)+(II) = Rp 54,794.10
RENCANA ANGGARAN BIAYA (RAB )
Err:509
Err:509
Err:509

NO. URAIAN PEKERJAAN JML HARGA DURASI BOBOT (%)


LANTAI 1
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan Rp. 2,875,000.000 1.000 0.198
2 Pembuatan Kantor Sementara dan Gudang Rp. 10,579,760.000 1.000 0.634
3 Pengadaan Air Kerja Rp. 500,000.000 20.000 0.036
4 Pembuatan Pagar Sementara Rp. 42,717,600.000 1.000 3.118
5 Pengadaan Skafolding Rp. 558,737.500 1.000 0.034
6 Pemasangan Bouwplank Rp. 13,872,680.000 1.000 1.016
7 Dokumentasi Rp. 500,000.000 10.000 0.036
8 Pembuatan Papan Nama Rp. 500,000.000 2.000 0.036

II PEKERJAAN TANAH
1 Galian Footplat Rp. 3,379,320.000 3.000 0.228
2 Galian Pondasi Rp. 4,757,775.000 3.000 0.321
3 Galian Rolag Rp. 13,140.000 1.000 0.001
4 Urugan pasir bawah pondasi Rp. 1,500,210.000 1.000 0.120
5 Urugan tanah kembali Rp. 1,858,126.667 1.000 0.125
6 Urugan pasir bawah lantai Rp. 676,162.500 1.000 0.046
7 Urugan pasir bawah footplat Rp. 114,851.520 1.000 0.009
8 Urugan pasir bawah rollag Rp. 2,716,745.000 1.000 0.183
9 Urugan tanah rollag Rp. 63,343.519 1.000 0.005

III PEKERJAAN PASANGAN


1 Pemasangan Aanstamping Rp. 7,728,570.000 2.000 0.534
2 Pas Pondasi Batu kali Rp. 35,132,279.600 3.000 2.220
3 Pas. Rolag batu bata Rp. 47,818.800 1.000 0.003
4 Pas. Bata camp 1 : 5 Rp. 32,977,106.365 3.000 1.970
5 Pas. Bata camp 1 : 3 Rp. 3,058,641.810 3.000 0.184
6 Plesteran camp 1 : 5 Rp. 28,968,363.337 2.000 1.623
7 Plesteran camp 1 : 3 Rp. 2,731,572.816 2.000 0.155
8 Acian Rp. 17,601,194.538 2.000 1.033

IV PEKERJAAN BETON
1 Foot plat 120/120 Rp. 32,735,404.800 4.000 2.010
2 Lantai kerja footplat t=10 cm Rp. 2,043,216.000 2.000 0.140
3 Sloof 15/20 Rp. 5,303,572.200 3.000 0.324
4 Sloof 20/25 Rp. 17,511,795.000 2.000 1.070
5 Kolom Pedestel 30/30 Rp. 33,439,126.392 3.000 2.137
6 Kolom30/30 Rp. 63,391,708.800 3.000 4.050
7 Kolom 15/15 Rp. 15,847,927.200 2.000 1.013
8 Balok 20/30 Rp. 39,144,227.400 3.000 2.533
9 Balok 15/20 Rp. 6,783,870.000 2.000 0.434
10 Pelat beton lantai 2, t=11 cm Rp. 97,587,809.000 3.000 6.428
11 Pelat dak beton, t=10 cm Rp. 26,525,695.000 3.000 1.747
12 Kantilever, t=10 cm Rp. 1,337,430.000 2.000 0.088
13 Tangga Beton Rp. 21,569,314.665 3.000 1.381
V PEKERJAAN KUSEN PINTU + JENDELA
1 Kusen P1 , 4bh Rp. 1,183,104.000 2.000 0.084
2 Kusen dan daun pintu P2, 1bh Rp. 9,540,232.000 1.000 0.681
3 Kusen dan daun pintu P3, 4bh Rp. 37,425,232.000 3.000 2.670
4 Kusen P4 PVC, 5bh Rp. 1,250,000.000 2.000 0.089
5 Kusen J1 Rp. 338,832.000 1.000 0.024
6 Kusen J2 Rp. 833,040.000 2.000 0.059
7 Kusen J3 Rp. 396,864.000 2.000 0.028
8 Kusen BV Rp. 86,112.000 2.000 0.006

VI PEKERJAAN PLAFOND & CAT


1 Gypsum Board rangka hollow Rp. 5,800,536.000 3.000 0.493
2 List Plafond Rp. 2,101,089.250 2.000 0.158
3 Pengecatan tembok Rp. 10,943,638.84 3.000 0.736
4 Pengecatan plafond Rp. 2,412,963.000 2.000 0.162

VII PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Kunci tanam biasa Rp. 1,346,175.000 1.000 0.095
2 Kunci tanam pintu WC Rp. 345,187.500 1.000 0.024
3 Engsel pintu Rp. 409,875.000 1.000 0.036
4 Kaca P1, 4bh Rp. 1,286,187.000 1.000 0.092
5 Kaca P2,1bh Rp. 19,139.688 1.000 0.001
6 Kaca P3,4bh Rp. 76,982.250 1.000 0.005
7 Kaca J1 Rp. 115,473.375 1.000 0.008
8 Kaca J2 Rp. 1,085,449.725 1.000 0.077
9 Kaca J3 Rp. 114,838.125 1.000 0.008
10 Kaca BV Rp. 321,546.750 1.000 0.023

VIII PEKERJAAN INSTALASI LISTRIK


1 Lampu TL 2x 18W RM DECO Rp. 189,000.000 1.000 0.013
2 Lampu Down light PLC E 15W Rp. 170,500.000 1.000 0.012
3 Saklar tunggal Rp. 102,500.000 1.000 0.007
4 Saklar ganda Rp. 164,000.000 1.000 0.012
5 Stop kontak Rp. 246,000.000 1.000 0.018
6 Box panel Rp. 300,000.000 1.000 0.021
7 Instalasi titik lampu Rp. 387,500.000 3.000 0.028

IX PEKERJAAN LANTAI
1 Pasang Keramik granito 60 x 60 Rp. 34,774,300.000 3.000 2.463
2 Pasang Keramik granito 40 x 40 Rp. 6,710,860.000 3.000 0.474
3 Pasang Keramik lantai 30 x 30 Rp. 5,670,480.135 2.000 0.398
4 Pasang Keramik lantai 30 x 30 (Tangga) Rp. 1,531,029.636 1.000 0.108
5 Pasang Keramik lantai 20 x 20 (KM/WC dan teras) Rp. 3,998,340.000 1.000 0.278

X PEKERJAAN SANITASI
1 Closet jongkok Rp. 1,405,750.000 1.000 0.370
2 Wastafel Rp. 4,894,325.000 1.000 0.371
3 Septictank & peresapan Rp. 4,406,770.200 4.000 0.314
4 Kran air Rp. 187,020.000 1.000 0.013
5 Pipa PVC 1/2" Rp. 301,611.700 2.000 0.021
6 Pipa Galvanis 3/4" Rp. 1,818,250.000 2.000 0.127
7 Bak kontrol Rp. 100,000.000 1.000 0.007
8 Ground tank Rp. 1,000,000.000 4.000 0.071
9 Tandon air Rp. 250,000.000 1.000 0.018
10 Floor drain Rp. 225,000.000 1.000 0.016

JML TOTAL :
NO. URAIAN PEKERJAAN JML HARGA
LANTAI 2
I PEKERJAAN PASANGAN
1 Pas. Bata camp 1 : 5 Rp. 30,694,024.325 3.000 1.834
2 Pas. Bata camp 1 : 3 Rp. 61,986.094 3.000 0.004
3 Plesteran camp 1 : 5 Rp. 26,962,815.933 2.000 1.510
4 Plesteran camp 1 : 3 Rp. 55,357.750 2.000 0.003
5 Acian Rp. 15,100,565.875 2.000 0.886

II PEKERJAAN BETON
1 Kolom 30/30 Rp. 61,127,719.200 3.000 3.906
2 Kolom 15/15 Rp. 13,583,937.600 2.000 0.868
3 Ring balok 15/20 Rp. 25,281,217.200 2.000 1.615
4 Kantilever, t=10 cm Rp. 45,472,620.000 2.000 2.995

III PEKERJAAN KUSEN PINTU + JENDELA


1 Kusen P1 , 2bh Rp. 591,552.000 2.000 0.042
2 Kusen dan daun pintu P2, 4bh Rp. 37,425,232.000 2.000 2.670
3 Kusen P4 PVC, 5bh Rp. 1,000,000.000 1.000 0.071
5 Kusen dan daun jendela J3, 9bh Rp. 1,785,888.000 2.000 0.127
6 Kusen J5 Rp. 291,564.000 2.000 0.021
7 Kusen J6 Rp. 89,856,000.000 2.000 6.411
8 Kusen BV Rp. 21,840,000.000 2.000 1.558

IV PEKERJAAN PLAFOND & CAT


1 Gypsum Board rangka hollow Rp. 4,484,448.000 3.000 0.381
2 List Plafond Rp. 971,714.250 2.000 0.073
3 Pengecatan tembok Rp. 9,388,859.310 3.000 0.632
4 Pengecatan plafond Rp. 1,865,484.000 3.000 0.126

V PEKERJAAN ATAP
1 Rangka Atap LT 1 & 2 Rp. 28,220,083.535 4.000 4.840
2 Gording Rp. 8,697,000.000 2.000 0.621
3 Nok Rp. 5,336,628.000 2.000 0.344
4 Papan Ruiter Rp. 816,172.500 2.000 0.155
5 Papan Listplank 3/30 Rp. 4,180,743.750 1.000 0.793
6 Atap Genteng Rp. 12,801,822.390 4.000 0.645

VI PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Kunci tanam biasa Rp. 1,047,025.000 1.000 0.074
2 Kunci tanam pintu WC Rp. 828,450.000 1.000 0.057
3 Engsel pintu Rp. 450,862.500 1.000 0.040
4 Kaca J3 Rp. 516,771.563 2.000 0.037
5 Kaca J5 Rp. 138,568.050 2.000 0.010
6 Kaca J6 Rp. 1,385,680.500 2.000 0.099
7 Kaca BV Rp. 258,660.360 2.000 0.018

VII PEKERJAAN INSTALASI LISTRIK


1 Lampu TL 2x18W RM DECO Rp. 121,500.000 1.000 0.009
2 Lampu Down light PLC 15W Rp. 93,000.000 1.000 0.007
3 Saklar ganda Rp. 164,000.000 1.000 0.012
4 Stop kontak Rp. 246,000.000 1.000 0.018
5 Instalasi titik lampu Rp. 232,500.000 1.000 0.017
VIII PEKERJAAN LANTAI
1 Pasang Keramik granito 40 x 40 Rp. 30,715,090.000 3.000 2.170
2 Pasang Keramik lantai 30 x30 Rp. 9,808,180.000 2.000 0.693
3 Pasang Keramik lantai 20 x 20 (KM/WC) Rp. 3,220,885.000 2.000 0.224

IX PEKERJAAN SANITASI
1 Closet jongkok Rp. 1,124,600.000 1.000 0.296
2 Wastafel Rp. 1,957,730.000 1.000 0.148
3 Kran air Rp. 207,800.000 1.000 0.015
4 Pipa PVC 1/2" Rp. 78,150.400 2.000 0.005
5 Pipa PVC 3/4" Rp. 187,020.000 2.000 0.013
6 Floor Drain Rp. 38,100.000 1.000 0.009

X PEKERJAAN RANGKA BAJA


1 Kuda-kuda Baja Rp. 30,126,238.800 3.000 2.150
2 1/2 Kuda-kuda Rp. 16,423,428.000 3.000 1.172
3 Jurai Rp. 23,812,412.400 2.000 1.699
5 Gording CNP 125.50.20.3,2 mm Rp. 10,193,588.580 2.000 0.727
6 Trackstang Rp. 471,822.960 1.000 0.034
7 Kres Angin Rp. 646,808.820 2.000 0.046
8 Kupingan Rp. 72,612.120 2.000 0.005
9 Kawat Las, OKSIGEN, Menie & Pengencer Rp. 8,174,628.840 2.000 0.583
10 Spankruff 1/2'' Rp. 80,000.000 1.000 0.006
11 Baut 10mm Rp. 160,000.000 3.000 0.011
12 Baut 12mm Rp. 432,000.000 3.000 0.031

JML TOTAL :
NO. URAIAN PEKERJAAN JML HARGA
INFRASTRUKTUR
I PEKERJAAN TANAH
1 Galian Pondasi Pagar Rp. 1,716,412.500 2.000 0.116
2 Urugan Pasir bawah pondasi Rp. 541215.00 1.000 0.043
3 Urugan tanah kembali Rp. 1,984,455.000 1.00 0.159

II PEKERJAAN PASANGAN
1 Pemasangan Aanstamping Rp. 2,788,155.000 2.000 0.192
2 Pas Pondasi Batu kali Rp. 12,674,303.400 3.000 0.801
3 Pas. Bata camp 1 : 5 Rp. 567,848.250 2.000 0.034

III PEKERJAAN BETON


1 kolom 15/15 Rp. 1,125,758.250 2.000 0.069
2 sloof 15/20 Rp. 10,753,950.600 2.000 0.687

IV PEKERJAAN LANTAI
1 Pasang paving block Rp. 22,178,474.400 3.000 1.491

V PEKERJAAN INSTALASI AC
1 Pengadaan dan Pemasangan Unit AC Sentral
- Type : Air cooled split duct Rp. 2,450,000.00 2.00 0.175
Kapasitas pendingin : 100.000,00 btu / h
Karakteristik : 380 V, 1 Ph, 50 Hz
- Refrigerant : R - 22 Rp. 1,500,000.00 2.00 0.107
- Dudukan out door Rp. 210,000.00 2.00 0.015
- Ongkos Pasang Rp. 300,000.00 2.00 0.021

JML TOTAL :
NO. URAIAN PEKERJAAN JML HARGA
POS SATPAM
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan Rp. 100,000.00 1.000 0.007
2 Pemasangan Bouwplank Rp. 816,040.000 1.00 0.060

II PEKERJAAN TANAH
1 Galian Pondasi Rp. 240,900.000 1.000 0.016
2 Urugan pasir bawah pondasi Rp. 1,500,210.000 1.000 0.120
3 Urugan tanah kembali Rp. 278,520.00 1.000 0.022
4 Urugan pasir bawah lantai Rp. 75,960.000 1.00 0.006

III PEKERJAAN PASANGAN


1 Pemasangan Aanstamping Rp. 391,320.000 1.000 0.027
2 Pas Pondasi Batu kali Rp. 1,778,849.600 2.000 0.112
3 Pas. Bata camp 1 : 5 Rp. 2,125,280.000 1.000 0.127
4 Pas. Bata camp 1 : 3 Rp. 198,355.500 1.000 0.012
5 Plesteran camp 1 : 5 Rp. 1,866,928.000 1.000 0.105
6 Plesteran camp 1 : 3 Rp. 177,144.800 1.000 0.010
7 Acian Rp. 1,134,915.000 1.000 0.067

IV PEKERJAAN BETON
1 Sloof 15/20 Rp. 800,539.200 2.000 0.049
2 Kolom 15/15 Rp. 2,263,989.600 2.000 0.145
3 Ring balk15/20 Rp. 39,144,227.400 2.000 2.533
4 Pelat dak beton, t=10 cm Rp. 3,343,575.000 3.000 0.220

V PEKERJAAN KUSEN PINTU + JENDELA


1 Kusen dan daun pintu P2, 1bh Rp. 9,540,232.000 2.000 0.681
2 Kusen J4 Rp. 350,064.000 2.000 0.025

VI PEKERJAAN PLAFOND & CAT


1 Gypsum Board rangka hollow Rp. 97,488.000 1.000 0.008
2 List Plafond Rp. 216,840.00 1.000 0.016
3 Pengecatan tembok Rp. 705,639.600 1.000 0.047
4 Pengecatan plafond Rp. 40,554.000 1.000 0.003

VII PEKERJAAN KUNCI, KACA & PENGGANTUNG


1 Kunci tanam biasa Rp. 149,575.000 1.000 0.011
2 Engsel pintu Rp. 40,987.500 1.000 0.004
3 Kaca P2,1bh Rp. 19,139.688 1.000 0.001
4 Kaca J4 Rp. 229,676.250 1.000 0.016

VIII PEKERJAAN INSTALASI LISTRIK


1 Lampu Down light PLC 15W Rp. 15,500.000 1.000 0.001
2 Saklar tunggal Rp. 20,500.000 1.000 0.001
3 Stop kontak Rp. 20,500.000 1.000 0.001
4 Instalasi titik lampu Rp. 15,500.000 1.000 0.001

IX PEKERJAAN LANTAI
1 Pasang Keramik lantai 20 x 20 Rp. 436,190.780 1.000 0.031
68,135,140.92
1,511,284,233.44 99.91

PROSENTASE PER MINGGU