Anda di halaman 1dari 326

BACK UP DATA

PEKERJAAN : PEMBANGUNAN PUSKESMAS PLANTUNGAN


LOKASI : KECAMATAN PLANTUNGAN
TAHUN ANGGARAN : 2017

NO URAIAN PEKERJAAN PERHITUNGAN

Pusk. Plantungan
PEKERJAAN LT. I
PONDASI FOOTPLAT Footplat 1 (150x 150)
GALIAN TANAH BIASA P =
Sedalam 1 Meter L =
T =
Jumlah =

V Total =

Lantai Kerja Bawah Footplat


Footplat 1 (150x 150)
P =
L =
T =
Jumlah =

V Total =

Pasir urug Bawah Footplat


P
P =
L =
T =
Jumlah =

V Total =

PONDASI FOOTPLAT
BETON Footplat 1 (150 x 150) A
P =
L =
T =
Jumlah =

V Total =

Footplat 1 (150 x 150) B


(A+B)/2 =
(A+B)/2 =
T =
Jumlah =

V Total =

Footplat 1 (150 x 150) C


P =
L =
T =
Jumlah =

V Total =

VOLUME TOTAL BETON FOOTPLAT

PONDASI FOOTPLAT Tulangan melintang atas =


FP1 (150 x 150) Jumlah =
PEMBESIAN Tulangan melintang bawah =
Jumlah =
Jumlah Pondasi =

P =
Tulangan besi D13 =
Jarak Beugel 8 =
Jumlah =

V Tulangan besi D 13 =
V Tulangan besi 12 =
V Beugel 8 =
V Total =
BEKESTING footplat P =
FP1 (150 x 150) L =
Jumlah =

P =
L =
Jumlah =

LUAS TOTAL BEGESTING FOOTPLAT

URUGAN KEMBALI FOOTPLAT Volume =

Pusk. Plantungan
PEKERJAAN LT. I
PONDASI FOOTPLAT Footplat 2 (120x 120)
GALIAN TANAH BIASA P =
Sedalam 1 Meter L =
T =
Jumlah =

V Total =

Lantai Kerja Bawah Footplat


Footplat 2 (120x 120)
P =
L =
T =
Jumlah =

V Total =

Pasir urug Bawah Footplat


P
P =
L =
T =
Jumlah =

V Total =

PONDASI FOOTPLAT
BETON Footplat 1 (120 x 120) A
P =
L =
T =
Jumlah =
V Total =

Footplat 1 (120 x 120) B


(A+B)/2 =
(A+B)/2 =
T =
Jumlah =

V Total =

Footplat 1 (120 x 120) C


P =
L =
T =
Jumlah =

V Total =

VOLUME TOTAL BETON FOOTPLAT

PONDASI FOOTPLAT Tulangan melintang atas =


FP1 (120 x 120) Jumlah =
PEMBESIAN Tulangan melintang bawah =
Jumlah =
Jumlah Pondasi =

P =
Tulangan besi D13 =
Jarak Beugel 8 =
Jumlah =

V Tulangan besi D 13 =
V Tulangan besi 12 =
V Beugel 8 =
V Total =
BEKESTING footplat P =
FP1 (120 x 120) L =
Jumlah =

P =
L =
Jumlah =

LUAS TOTAL BEGESTING FOOTPLAT

PONDASI BT BELAH Pondasi PB 1


GALIAN TANAH P =
L =
T =

V Total =

Rolag bata
P =
L =
T =

V Total =

PONDASI BT BELAH Pondasi PB 1


URUGAN PASIR P =
BAWAH PONDASI L =
T =

V Total =

Rolag bata
P =
L =
T =

V Total =

PAS. BATU BELAH Pondasi PB 1


P =
L =
T =

V Total =

PAS. Astamping PAS. Astamping


P =
T =
l
L Total =

PAS. BATA ROLAG Rolag (RG)


P =
T =

L Total =

PEERJAAN SLOOF
BETON
S 1 (20 X 30) P =
L =
T =

L Total =

BETON
SP (15 X 20) P =
L =
T =

L Total =

Volume Total Beton =

PEMBESIAN SLOOF
S 1 (20 X 30) P =
Tulangan besi D 16 =
Jarak Beugel 8 =

S2 (15 X 20) P =
Tulangan besi 10 =
Jarak Beugel 8 =

S 1 (20 X 30) V Tulangan besi D 16 =


V Beugel 8 =
V Total =

S2 (15 X 20) V Tulangan besi 10 =


V Beugel 8 =
V Total =

Volume Total Pembasian =

BEKESTING SLOOF 1/3


S 1 (20 X 30) P =
L =
Jumlah =

S2 (15 X 20) P =
L =
Jumlah =
LUAS TOTAL BEGESTING SLOOF 2X PAKAI

PEKERJAAN TANAH
URUGAN TANAH PADAS Luasan Bangunan =
T =

Volume

URUGAN PASIR Luasan Bangunan =


T =

Volume

LANTAI KERJA TB : 5cm Luasan Bangunan =


T =

Volume

PEKERJAAN BETON
KOLOM 1 30/30
BETON
P =
L =
T =

Jumlah =
L Total =

KOLOM 1 30/30
Pembesian P Tulangan =
Jumlah Tulangan =
Jumlah =

P Beugel =
Jumlah Beugel =
Jumlah =
V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =

KOLOM 1 30/30
BEGESTING
P =
L =
T =

Jumlah =
Pemakaian =
L Total =

KOLOM PRAKTIS 15/15


BETON
P =
L =
T =

Jumlah =
L Total =

KOLOM PRAKTIS 15/15


Pembesian P Tulangan =
Jumlah Tulangan =
Jumlah =

P Beugel =
Jumlah Beugel =
Jumlah =

V Tulangan besi 10 =
V Tulangan besi 8 =
V Total =

KOLOM PRAKTIS 15/15


BEGESTING
P =
L =
T =

Jumlah =
Pemakaian =
L Total =
BALOK LATAI 1 15/20
BETON
P =
L =
T =

V Total =

BALOK LATAI 1 15/15


Pembesian P Tulangan =
Jumlah Tulangan =

P Beugel =
Jumlah Beugel =

V Tulangan besi 10 =
V Tulangan besi 8 =
V Total =

BALOK LATAI 1 15/15


BEGESTING
P =
T =

Pemakaian =
L Total =

PLAT LEUFEL
BETON
P =
Luas penampang =

V Total =

PLAT LEUFEL
Pembesian Tulangan memanjang =
Jumlah Tulangan =

Tulangan melintang =
Jumlah Tulangan =

V Tulangan besi 10 =
V Total =

PLAT LEUFEL
BEGESTING
P =
l =
Pemakaian =
L Total =

BALOK 1 20/50
BETON
P =
L =
T =

L Total =

BALOK 1 20/50
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Samping =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi D 16 =
V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =

BALOK 1 20/50
BEGESTING
P =
L =

Pemakaian =
L Total =

BALOK 2 20/40
BETON
P =
L =
T =
L Total =
BALOK 2 20/40
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Samping =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi D 16 =
V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =

BALOK 2 20/40
BEGESTING
P =
L =

Pemakaian =
L Total =

BALOK 3 20/30
BETON
P =
L =
T =

L Total =

BALOK 3 20/30
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Samping =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi D 16 =
V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =
BALOK 3 20/30
BEGESTING
P =
L =

Pemakaian =
L Total =

BALOK 4 20/30
BETON
P =
L =
T =

L Total =

BALOK 4 20/30
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi D 16 =
V Tulangan besi 8 =
V Total =

BALOK 4 20/30
BEGESTING
P =
L =

Pemakaian =
L Total =

PLAT BETON LANTAI 2


BETON luas bangunan
P =
L =
T =
Jumlah =

L Total =
luas void
P =
L =
T =
Jumlah =

L Total =

PLAT BETON LANTAI 2


memanjang
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Bawah =

V Tulangan besi D 10 =
V Total =
PLAT BETON LANTAI 2
melintang
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Bawah =

V Tulangan besi D 10 =
V Total =

V TOTAL PEMBESIAN PLAT LANTAI 2


PLAT BETON LANTAI 2
BEGESTING
P =
L =
LUAS VOID =

L Total =
Beton Tangga Lt 1 ke Lt 2
Beton Plat tangga Bordes
Panjang 8.12 0.9
lebar 1.5 1.85
tinggi 0.2 0.2
volume 2.436 0.333
Total 3.462

Pembesian
Anak Tangga
panjang 0.9
jrk beugel 0.15
jml tulangan 0.9 0.15
8.12

D-12 15 6.00 8.12


86.72

10-15 54.13 0.9


60.12
10-15 23.00 0.9
12.77
10-15 14.95 6
55.34
volume 214.96
Bordes
panjang 1.85
lebar 0.9
jrk beugel 0.15
jml tulangan 1.85 0.15
12.3333333333
0.9 0.15
6
10-15 12.3333333333 0.9
13.6974 0
D-12 15 6 1.85
23.088
volume 36.7854
Balok
panjang 2.6
jrk beugel 0.15
S beugel 2.6 0.15
pjg /begel 0.26 0.26
0.05
1.09
4D12 4 2.6
9.26
8-15 18.33 1.09
7.89
volume 17.15

Total Volume besi 214.95888


268.894
Bekisting
volume 1.2 8.12
1 1.6
0.38 8.12
0.38 8.12
1.1 1.3
0.9 2.6

RABAT BETON LUAR


BETON
P =
L =
T =
V Total =

RABAT BETON LUAR


PASIR URUG
P =
L =
T =
V Total =

SALURAN DRAINASE
GOT U -20 P =

PAS. BATA TASRAAM


P =
T =
L Total =

PAS. BATU - BATA


GEDUNG PUSKESMAS
P =
T =
L Total =
L total pas. Bata =

Lubang Pintu dan Jendela =


Tasraam =

TOTAL PAS BATU BATA =

PLESTERAN DINDING luas total pas. Batu bata =


area keramik dinding =

Luas Total Plesteran Dinding =

ACIAN DINDING luas total pas. Batu bata =


area keramik dinding =

Luas Total Acian Dinding =

SKONENGAN Sudut bangunan =


kusen p1 =
Kusen P 2 =
Kusen P 3 =
Kusen P 4 =
Kusen J 1 =
Kusen J 2 =
Kusen J 3 =
Kusen J 4 =
Kusen J 6 =
kusen j5 =
Kusen BV =

ACIAN BETON
plat leufel
P =
L =
L Total =
Luas Total acian beton =

KUSEN PINTU ALUMUNIUM


KUSEN P1
L =
T =
Jumlah =

KUSEN P2
L =
T =
Jumlah =

KUSEN P3
L =
T =
Jumlah =

KUSEN P4
L =
T =
Jumlah =

KUSEN J1
L =
T =
Jumlah =

KUSEN J2
L =
T =
Jumlah =

KUSEN J3
L =
T =
Jumlah =

KUSEN J4
L =
T =
Jumlah =

KUSEN J5
L =
T =
Jumlah =

KUSEN J6
L =
T =
Jumlah =

KUSEN Bv
L =
T =
Jumlah =
TOTAL PANJANG KUSEN ALUMUNIUM

PINTU PLYWOOD KUSEN P1


L =
T =
Jumlah =
Luas

KUSEN P2
L =
T =
Jumlah =
Luas

KUSEN P3
L =
T =
Jumlah =
Luas

TOTAL DAUN PINTU PLYWOOD

PINTU KACA p4
TEMPERED 12mm L =
T =
Jumlah =
Luas

DAUN JENDELA KACA KUSEN J1


RANGKA ALUMUNIUM L =
T =
Jumlah =
Luas
KUSEN J2
L =
T =
Jumlah =
Luas
KUSEN J3
L =
T =
Jumlah =
Luas

TOTAL DAUN JENDELA KACA RANGKA ALUMUNIUM


PEK. PENUTUP LANTAI DAN DINDING

KERAMIK 40 X 40 luas bangunan

teras
P =
L =
Luas =

ruang tunggu
P =
L =
Luas =

rekan medik
P =
L =
Luas =

2 bh lorong akses kebelkang


P =
L =
Luas =

apotik
P =
L =
Luas =

ruang farmasi
P =
L =
Luas =

ruang pemeriksaan umum


P =
L =
Luas =

ruang gawat darurat


P =
L =
Luas =

persalinan
P =
L =
Luas =

LUAS TOTAL SELURUH RUANG =


(dikurangi tembok/dinding)
KERAMIK 20 X 20 Km/WC
(dikurangi tembok) P =
L =
Jumlah =
Luas =

KERAMIK DINDING 20 X 40 Km/WC


(dikurangi tembok) P =
T =
Jumlah =
Luas =

PLAFOND CALSIBOARD =
TOTAL LUASAN PLAFOND CALSIBOARD

PLAFOND GYPSUM
luas bangunan

teras
P =
L =
Luas =

ruang tunggu
P =
L =
Luas =

rekan medik
P =
L =
Luas =

2 bh lorong akses kebelkang


P =
L =
Luas =

apotik
P =
L =
Luas =
ruang farmasi
P =
L =
Luas =

ruang pemeriksaan umum


P =
L =
Luas =

ruang gawat darurat


P =
L =
Luas =

persalinan
P =
L =
Luas =

LUAS TOTAL SELURUH GYBSUM =


(dikurangi tembok/dinding)

LIST PROFIL GYPSUM


TOTAL LIST PROFIL GYPSUM

RANGKA ATAP BAJA RINGAN


A =
T =
Jumlah =
Luas =

(A+B)/2 =
T =
Jumlah =
Luas =

A =
T =
Jumlah =
Luas =

(A+B)/2 =
T =
Jumlah =
Luas =

LAPIS PLAT alumunium foil


Luas =

GENTENG KODOK
Luas =

BUBUNGAN PANJANG =
TOTAL PANJANG BUBUNGAN

LISPLANK PANJANG =

PEKERJAAN INSTALASI LISTRIK


(K3) Pemasangan 1 buah titik lampu
Lampu TL (2x18)
Lampu downlight inbow, LED 13w
(K3) Pemasangan 1 buah stop kontak
SDP
Box Panel 40x60x20 cm

PEKERJAAN SANITAIR
1 Pemasangan 1 buah closet duduk
2 Pemasangan 1 buah wastafel
3 Pemasangan 1 buah floor drain
4 Pemasangan 1 buah kran diameter " atau 3/4"
5 Pemasangan 1 m' pipa PVC tipe AW diameter 1"
6 Pemasangan 1 m pipa PVC tipe AW diameter 3
7 Pemasangan 1 m pipa PVC tipe AW diameter 4
9 Pekerjaan Septictank dan Peresapan
BACK UP DATA LANTAI 2
PEKERJAAN : PEMBANGUNAN PUSKESMAS PLANTUNGAN
LOKASI : KECAMATAN PLANTUNGAN
TAHUN ANGGARAN : 2017

NO URAIAN PEKERJAAN PERHITUNGAN


KOLOM PRAKTIS 15/15
BETON
P =
L =
T =

Jumlah =
L Total =

KOLOM PRAKTIS 15/15


Pembesian P Tulangan =
Jumlah Tulangan =
Jumlah =

P Beugel =
Jumlah Beugel =
Jumlah =

V Tulangan besi 10 =
V Tulangan besi 8 =
V Total =

KOLOM PRAKTIS 15/15


BEGESTING
P =
L =
T =

Jumlah =
Pemakaian =
L Total =

PEKERJAAN BETON
KOLOM 1 30/30
BETON
P =
L =
T =

Jumlah =
L Total =

KOLOM 1 30/30
Pembesian P Tulangan =
Jumlah Tulangan =
Jumlah =

P Beugel =
Jumlah Beugel =
Jumlah =

V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =

KOLOM 1 30/30
BEGESTING
P =
L =
T =

Jumlah =
Pemakaian =
L Total =

PEERJAANRING BALK.1
RB 1 20/30
BETON
P =
L =
T =

L Total =

RB 1 20/30
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =

RB 1 20/30
BEGESTING
P =
L =

Pemakaian =
L Total =

PEERJAANRING BALK.2
RB 2 15/30
BETON
P =
L =
T =

L Total =

RB 2 15/30
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi D 13 =
V Tulangan besi 8 =
V Total =

RB 2 15/30
BEGESTING
P =
L =

Pemakaian =
L Total =

PEERJAANRING BALK.3
RB 3 15/25
BETON
P =
L =
T =

L Total =
RB 3 15/25
Pembesian P Tulangan =
Tulangan Atas =
P Tulangan =
Tulangan Bawah =

P Beugel =
Jumlah Beugel =

V Tulangan besi 12 =
V Tulangan besi 8 =
V Total =

RB 3 15/25
BEGESTING
P =
L =

Pemakaian =
L Total =

KUSEN PINTU ALUMUNIUM


KUSEN P1
L =
T =
Jumlah =

KUSEN P2
L =
T =
Jumlah =

KUSEN P3
L =
T =
Jumlah =

KUSEN J1
L =
T =
Jumlah =

KUSEN J2
L =
T =
Jumlah =

KUSEN J3
L =
T =
Jumlah =

KUSEN J5
L =
T =
Jumlah =

KUSEN J6
L =
T =
Jumlah =

KUSEN Bv
L =
T =
Jumlah =

TOTAL PANJANG KUSEN ALUMUNIUM

PINTU PLYWOOD KUSEN P1


L =
T =
Jumlah =
Luas

KUSEN P2
L =
T =
Jumlah =
Luas

KUSEN P3
L =
T =
Jumlah =
Luas
TOTAL DAUN PINTU PLYWOOD

DAUN JENDELA KACA KUSEN J1


RANGKA ALUMUNIUM L =
T =
Jumlah =
Luas
KUSEN J2
L =
T =
Jumlah =
Luas

KUSEN J3
L =
T =
Jumlah =
Luas

TOTAL DAUN JENDELA KACA RANGKA ALUMUNIUM

KERAMIK 20 X 20 Km/WC
(dikurangi tembok) P =
L =
Jumlah =
Luas =

KERAMIK DINDING 20 X 40 Km/WC


(dikurangi tembok) P =
T =
Jumlah =
Luas =

KERAMIK 40 X 40
luas bangunan

luas bangunan =
P =
L =
Luas

luas = luas bangunan - luas km - luas void


ACK UP DATA
ANTUNGAN

PERHITUNGAN VOLUME SAT

1.500 M
1.500 M
1.500 M
16.000 bh

PXLXT 54.00 M3

1.500 M
1.500 M
0.050 M
16.000 bh

PXLXT 1.80 M3

1.500 M
1.500 M
0.050 M
16.000 bh

PXLXT 1.80 M3

1.500 M
1.500 M
0.200 M
16.000 bh

PxLxT 7.200 M3

0.725 M
0.825 M
0.100 M
16.000 bh

PxLxT 0.957 M3

0.300 M
0.300 M
2.050 M
16.000 bh

PxLxT 2.952 M3

11.109 M3

2.020 M
22.000 bh 631.404 KG
1.700 M
22.000 bh 531.379 KG
16.000 bh

2.100 M
8.000 bh
0.150 M
16.000 bh

P x (1,04 kg/m') 279.552 KG


P x (0,888 kg/m') 1162.783 KG
P : Jarak Beugel x (0,40 kg/m') 89.600 KG
1531.93 KG
4.800 M
0.300 M
16.000 Bh 23.04 M2

1.900 M
1.500 M
16.000 Bh 45.60 M2

ESTING FOOTPLAT 68.64 M2

Galian - Urugan pasir - Lantai Kerja - Beton 41.09 M3

1.200 M
1.200 M
1.500 M
8.000 bh

PXLXT 17.28 M3

1.200 M
1.200 M
0.050 M
8.000 bh

PXLXT 0.58 M3

1.200 M
1.200 M
0.050 M
8.000 bh

PXLXT 0.58 M3

1.200 M
1.200 M
0.200 M
8.000 bh
PxLxT 2.304 M3

0.625 M
0.725 M
0.100 M
8.000 bh

PxLxT 0.363 M3

0.300 M
0.300 M
2.050 M
8.000 bh

PxLxT 1.476 M3

4.143 M3

1.720 M
14.000 bh 171.064 KG
1.400 M
14.000 bh 139.238 KG
8.000 bh

2.100 M
8.000 bh
0.150 M
8.000 bh

P x (1,04 kg/m') 139.776 KG


P x (0,888 kg/m') 310.303 KG
P : Jarak Beugel x (0,40 kg/m') 44.800 KG
494.88 KG
4.800 M
0.300 M
8.000 Bh 11.52 M2

1.900 M
1.200 M
8.000 Bh 18.24 M2

ESTING FOOTPLAT 29.76 M2

121.000 M
0.850 M
0.800 M

PXLXT 82.28 M3

38.000 M
0.300 M
0.300 M

PXLXT 3.42 M3
PB 1 + Rolag 85.700 M3

104.000 M
0.800 M
0.050 M

PXLXT 4.16 M3

38.000 M
0.300 M
0.050 M

PXLXT 0.57 M3
PB 1 + Rolag 4.730 M3

104.000 M
(0,30 + 6,00) : 2 M
0.600 M

PXLXT 28.08 M3

104.000 M
0.200 M
0.800
PXTxl 16.64 M2

38.000 M
0.300 M

PXT 11.40 M2

138.000 M
0.200 M
0.300 M

PxLxT 8.280 M3

16.000 M
0.150 M
0.200 M

PxLxT 0.480 M3

8.760 M3

138.000 M
4.000 bh 552.000 M'
0.150 M 920.000 M'

16.000 M
4.000 bh 64.000 M'
0.150 M 64.000 M'

P x (1,58 kg/m') 871.056 KG


P : Jarak Beugel x (0,40 kg/m') 368.000 KG
1239.06 KG

P x (0,62 kg/m') 39.680 KG


P : Jarak Beugel x (0,40 kg/m') 25.600 KG
65.28 KG

1304.336 KG

138.000 M
0.300 M
2.000 Bh x 1/2 41.40 M2

16.000 M
0.150 M
2.000 Bh x 1/2 2.40 M2
ING SLOOF 2X PAKAI 43.80 M2

170.000 M2
0.200 M'

34.000 M3

170.000 M2
0.050 M'

8.500 M3

170.000 M2
0.050 M'

8.500 M3

0.300 M
0.300 M
4.000 M

28.000 BH
PxLxT 10.080 M3

4.000 M
8.000 BH
28.000 BH

1.300 M
24.000 BH
28.000 BH
P x Jumlah Tulangan x (1,04 kg/m') 931.840 KG
P x Jumlah Tulangan x (0,40 kg/m') 349.440 KG
1281.28 KG

0.300 M
0.300 M
3.500 M

28.000
2 x pakai
(2 P + L ) x T 58.800 M2

0.150 M
0.150 M
3.500 M

10.000 BH
PxLxT 0.788 M3

3.500 M
4.000 BH
10.000 BH

0.700 M
24.000 BH
10.000 BH

P x Jumlah Tulangan x (0,62 kg/m') 86.800 KG


P x Jumlah Tulangan x (0,40 kg/m') 67.200 KG
154.00 KG

0.150 M
0.150 M
3.500 M

10.000
2 x pakai
(2 P + L ) x T 10.500 M2
63.340 M
0.150 M
0.200 M

PxLxT 1.900 M3

63.340 M
4.000 BH

0.700 M
426.500 BH

P x Jumlah Tulangan x (0,62 kg/m') 157.083 KG


P x Jumlah Tulangan x (0,40 kg/m') 119.420 KG
276.50 KG

63.340 M
0.200 M

2 x pakai
(2) x T 9.501 M2

14.700 M
0.035 M2

P x Luas Penampang 0.515 M3

14.700 M
4.000 BH 58.800 M'

0.500 M
98.000 BH 49.000 M'

P x Jumlah Tulangan x (0,62 kg/m') 102.410 KG


102.41 KG

14.700 M
0.600 M
2 x pakai
PxT 4.410 M2

20.000 M
0.200 M
0.500 M

PxLxT 2.000 M3

20.000 M
2.000 BH 40.000 M'
20.000 M
8.000 BH 160.000 M'
20.000 M
2.000 BH 40.000 M'

1.500 M
133.333 BH

P x Jumlah Tulangan x (1,578 kg/m') 126.240 KG


P x Jumlah Tulangan x (1,04 kg/m') 166.400 KG
P x Jumlah Tulangan x (0,40 kg/m') 80.000 KG
372.64 KG

20.000 M
0.800 M

1 x pakai
(2 P + L ) x T 16.000 M2

103.000 M
0.200 M
0.400 M
PxLxT 8.240 M3

103.000 M
2.000 BH 206.000 M'
103.000 M
2.000 BH 206.000 M'
103.000 M
2.000 BH 206.000 M'

1.000 M
686.667 BH

P x Jumlah Tulangan x (1,578 kg/m') 650.136 KG


P x Jumlah Tulangan x (1,04 kg/m') 214.240 KG
P x Jumlah Tulangan x (0,40 kg/m') 274.667 KG
1139.04 KG

103.000 M
1.000 M

1 x pakai
(2 P + L ) x T 103.000 M2

30.000 M
0.200 M
0.300 M

PxLxT 1.800 M3

30.000 M
2.000 BH 60.000 M'
30.000 M
1.000 BH 30.000 M'
30.000 M
2.000 BH 60.000 M'

1.100 M
200.000 BH

P x Jumlah Tulangan x (1,578 kg/m') 189.360 KG


P x Jumlah Tulangan x (1,04 kg/m') 31.200 KG
P x Jumlah Tulangan x (0,40 kg/m') 88.000 KG
308.56 KG
30.000 M
0.800 M

1 x pakai
(2 P + L ) x T 24.000 M2

30.000 M
0.200 M
0.300 M

PxLxT 1.800 M3

30.000 M
2.000 BH 60.000 M'
30.000 M
2.000 BH 60.000 M'

1.100 M
200.000 BH

P x Jumlah Tulangan x (1,578 kg/m') 189.360 KG


P x Jumlah Tulangan x (0,40 kg/m') 88.000 KG
277.36 KG

30.000 M
0.800 M

1 x pakai
(2 P + L ) x T 24.000 M2

10.000 M
17.000 M
0.120 M
20.400

PxLxT M3

3.000 M
8.000 M
0.120 M
2.880

l bangunan - l void 17.520 M3

17.000 M
56.000 BH 952.000 M'
17.000 M
56.000 BH 952.000 M'

P x Jumlah Tulangan x (0,62 kg/m') 1180.480 KG


1180.48 KG

10.000 M
34.000 BH 340.000 M'
10.000 M
34.000 BH 340.000 M'

P x Jumlah Tulangan x (0,62 kg/m') 421.600 KG


421.60 KG

IAN PLAT LANTAI 2 1602.08 KG

10.000 M
17.000 M
24.000 M2

P x L - LUAS VOID - balok 83.800 M3


ank tgga 23 Balok
0.900 2.60
0.300 0.30
0.170 0.30
0.459 0.23
M3

6.000

0.890 2.00

0.617 2.00
0.000
0.617 1.00

0.617 1.00
55.345

12.333

6.000

0.617 2.00

1.040 2.00

18.333
0.260 0.26

0.890

0.395
36.785 17.15
KG

9.744
1.600
3.086
3.086
1.430
2.340
21.285 M2

54.000 M
0.750 M
0.100 M
Pxlxt 4.050 M3

54.000 M
0.750 M
0.050 M
Pxlxt 2.025 M3

58.000 M 58.000 M'

6.350 M
2.000 M
PxT 12.700 M2

93.000 M2
3.800 M
PxT 353.400 M2
353.400 M2

89.430 m2
12.700 M2 12.700 M2

L total pas. Bata - lubang pintu jendela - opening 251.270 M2

263.970 M2
12.700 M2

( Luas batu bata x 2 ) - Area keramik dinding 515.240 M2

263.970 M2
12.700 M2

( Luas batu bata x 2 ) - Area keramik dinding 515.240 M2

3,70 x4 M 14.800 M'


6,6 x 8 m 52.800 M'
6,3 x 2 M 12.600 M'
6,1 x 2 M 12.200 M'
7,8 x 2 M 15.600 M'
6,05 x 7 M 42.350 M'
6,1 x 1 M 6.100 M'
5,4x 1 M 5.400 M'
M M'
M M'
2,8 x 2 m 4.400 M'
2,20 x 2 M 4.400 M'
170.650 M'

14.700 M
0.600 M
PxL M2
8.820 M2

1.400 M
2.600 M
8.000 bh
80.000 M'

0.900 M
2.600 M
2.000 bh
19.600 M'

0.900 M
2.600 M
2.000 bh
19.200 M'

2.400 M
2.700 M
2.000 bh
15.600 M'

1.350 M
2.350 M
5.000 bh
62.250 M'

0.700 M
2.350 M
1.000 bh
9.850 M'

2.100 M
2.350 M
1.000 bh
17.800 M'

0.800 M
1.800 M
2.000 bh
7.000 M'

0.700 M
1.900 M
2.000 bh
7.100 M'

3.600 M
2.500 M
1.000 bh
9.000 M'

0.600 M
0.500 M
2.000 bh
4.400 M'

USEN ALUMUNIUM 251.800 M2

1.300 M
2.100 M
8.000 bh
21.840 M2

0.800 M
2.100 M
2.000 bh
3.360 M2

0.800 M
2.100 M
2.000 bh
3.360 M2

28.560 M2

1.850 M
2.400 M
2.000 bh
8.880 M2

0.600 M
1.350 M
10.000 bh
8.100 M2

0.600 M
1.350 M
1.000 bh
0.810 M2

0.600 M
1.350 M
3.000 bh
2.430 M2

ALUMUNIUM 11.340 M2
M2

5.850 M
0.850 M
PXL 4.973 M2

7.850 M
7.850 M
PXL 61.623 M2

2.850 M
2.850 M
PXL 8.123 M2

1.850 M
2.850 M
PXL 10.545 M2

3.850 M
3.850 M
PXL 14.823 M2

2.850 M
2.850 M
PXL 8.123 M2

2.850 M
2.850 M
PXL 8.123 M2

3.850 M
4.850 M
PXL 18.673 M2

5.850 M
3.350 M
PXL 19.598 M2

149.050 M2

1.850 M
1.500 M
2.000 bh
PXL 5.550 M2

5.600 M
2.000 M
2.000 bh
PXL 11.200 M2

10.820 M2

5.850 M
0.850 M
PXL 4.973 M2

7.850 M
7.850 M
PXL 61.623 M2

2.850 M
2.850 M
PXL 8.123 M2

1.850 M
2.850 M
PXL 5.273 M2

3.850 M
3.850 M
PXL 14.823 M2
2.850 M
2.850 M
PXL 8.123 M2

2.850 M
2.850 M
PXL 8.123 M2

3.850 M
4.850 M
PXL 18.673 M2

5.850 M
3.350 M
PXL 19.598 M2

149.328 M2

262.000 M'

12.000 M
6.820 M
2.000 sisi
1/2 A x T 81.840 M2

13.000 M
6.820 M
2.000 sisi
AxT 177.320 M2

8.000 M
2.450 M
2.000 sisi
1/2 A x T M2

8.000 M
2.450 M
2.000 sisi
AxT M2
259.160 M2

259.160 259.160 M2

259.160 259.160 M2

58.000 M'
NG BUBUNGAN 58.000 M'

84.000 84.000 M'

31 Titik
9 BH
22 BH
17 BH
1 BH
1 BH

2.000 bh
5.000 unit
2.000 m'
" atau 3/4" 2.000 m'
diameter 1" 34.000 m'
diameter 3 25.000 m'
diameter 4 15.000 set
2.000 BH
A LANTAI 2
ANTUNGAN

PERHITUNGAN

0.150 M
0.150 M
3.700 M

13.000 BH
PxLxT 1.082 M3

3.500 M
4.000 BH
13.000 BH

0.700 M
24.000 BH
13.000 BH

P x Jumlah Tulangan x (0,62 kg/m') 112.840 KG


P x Jumlah Tulangan x (0,40 kg/m') 87.360 KG
200.20 KG

0.150 M
0.150 M
3.700 M

13.000
2 x pakai
(2 P + L ) x T 14.430 M2

0.300 M
0.300 M
4.000 M

24.000 BH
PxLxT 8.640 M3
4.000 M
8.000 BH
24.000 BH

1.300 M
24.000 BH
24.000 BH

P x Jumlah Tulangan x (1,04 kg/m') 798.720 KG


P x Jumlah Tulangan x (0,40 kg/m') 299.520 KG
1098.24 KG

0.300 M
0.300 M
3.500 M

24.000
3 x pakai
(2 P + L ) x T 50.400 M2

46.000 M
0.200 M
0.300 M

PxLxT 2.760 M3

46.000 M
2.000 BH 92.000 M'
46.000 M
2.000 BH 92.000 M'

1.100 M
306.667 BH

P x Jumlah Tulangan x (1,04 kg/m') 191.360 KG


P x Jumlah Tulangan x (0,40 kg/m') 134.933 KG
326.29 KG

46.000 M
0.800 M

2 x pakai
(2 P + L ) x T 18.400 M2

89.000 M
0.150 M
0.300 M

PxLxT 4.005 M3

89.000 M
2.000 BH 178.000 M'
89.000 M
2.000 BH 178.000 M'

1.000 M
593.333 BH

P x Jumlah Tulangan x (1,04 kg/m') 370.240 KG


P x Jumlah Tulangan x (0,40 kg/m') 237.333 KG
607.57 KG

89.000 M
0.750 M

2 x pakai
(2 P + L ) x T 33.375 M2

30.000 M
0.150 M
0.250 M

PxLxT 1.125 M3
30.000 M
2.000 BH 60.000 M'
30.000 M
2.000 BH 60.000 M'

1.000 M
200.000 BH

P x Jumlah Tulangan x (0,89 kg/m') 106.800 KG


P x Jumlah Tulangan x (0,40 kg/m') 80.000 KG
186.80 KG

30.000 M
0.650 M

2 x pakai
(2 P + L ) x T 9.750 M2

1.400 M
2.600 M
2.000 bh
16.000 M'

0.900 M
2.600 M
1.000 bh
7.000 M'

0.900 M
2.600 M
1.000 bh
7.000 M'

1.350 M
2.350 M
5.000 bh
55.500 M'

0.700 M
2.350 M
2.000 bh
19.700 M'

2.100 M
2.350 M
1.000 bh
17.800 M'

0.700 M
1.900 M
2.000 bh
7.100 M'

1.150 M
0.600 M
1.000 bh
M'

0.600 M
0.500 M
3.000 bh
6.600 M'

USEN ALUMUNIUM 136.700 M2

1.300 M
2.100 M
2.000 bh
5.460 M2

0.800 M
2.100 M
1.000 bh
1.680 M2

0.800 M
2.100 M
1.000 bh
1.680 M2
8.820 M2

0.600 M
1.350 M
10.000 bh
8.100 M2

0.600 M
1.350 M
2.000 bh
1.620 M2

0.600 M
1.350 M
3.000 bh
2.430 M2

ALUMUNIUM 12.150 M2

1.850 M
1.500 M
1.000 bh
PXL 2.775 M2

5.600 M
2.000 M
1.000 bh
PXL 11.200 M2

10.000 M
17.000 M
PXL 170.000 M2

n - luas km - luas void


Dihit. A.4.1.1.a Pemasangan 1 m2 bekisting kolom praktis
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Paku 5 cm - 12 cm kg 0.4000 15,000.00
Minyak bekisting Liter 0.2000 14,500.00
Balok Kayu Kruing m3 0.0150 5,500,000.00
Plywood tebal 9 mm Lbr 0.3500 140,000.00
Bambu Apus 8-10 cm Pjg 4 m Batang 2.0000 28,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Dihit. A.4.1.1.b Pemasangan 1 m2 bekisting untuk ringbalok


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0400 4,000,000.00
Paku biasa 1" - 4" kg 0.4000 15,000.00
Minyak bekisting Liter 0.2000 14,500.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

6,000.00
2,900.00
82,500.00
49,000.00
56,000.00
196,400.00

276,425.00
37,317.38
313,742.38

Jumlah Harga
(Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

160,000.00
6,000.00
2,900.00
168,900.00

248,925.00
33,604.88
282,529.88
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : PELAYANAN KESEHATAN DASAR
PEKERJAAN : PEMBANGUNAN PUSKESMAS PLANTUNGAN
LOKASI : KECAMATAN PLANTUNGAN
TH ANGGARAN : 2017

NO URAIAN PEKERJAAN ANALISA VOLUME

A PEKERJAAN LANTAI I
I. PEKERJAAN PERSIAPAN :
1 Pengukuran dan pemasangan 1 m' Bouwplank A. 2.2.1.4 53.00 m
2 Pembuatan Papan Nama Proyek ls 1.00 ls
3 Pembersihan 1 m2 lapangan dan perataan A. 2.2.1.9 170.00 m2
4 Direksi Keet ls 24.00 m2

II Pekerjaan tanah
1 Penggalian 1 m3 tanah biasa sedalam 1 m (Pondasi foot plat) A.2.3.1.1 71.28 m3
2 Penggalian 1 m3 tanah biasa sedalam 1 m (pondasi batu belah) A.2.3.1.1 82.28 m3
3 Penggalian 1 m3 tanah biasa sedalam 1 m (rollag bata) A.2.3.1.1 3.42 m3
4 Pengurugan kembali 1 m3 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9 51.19 m3
5 Pemasangan 1 m3 Urugan Tanah Padas ( dipadatkan dengan alat pemadat tangan ) Dihit. UTP 1 34.00 m3
6 Pengurugan 1 m3 dengan Pasir urug ( Pondasi + Foot Plat ) A.2.3.1.11 7.11 m3

III Pekerjaan pondasi


1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4 28.08 m3
2 (K3) Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9 16.64 m3
3 Pemasangan 1 m2 dinding bata merah tebal 1 batu campuran 1SP : 3PP (rollag) A.4.4.1.2 3.42 m2

IV Pekerjaan beton
1 Pondasi footplat fp 1
a (K3) Pemasangan 1 m2 bekisting untuk pondasi A.4.1.1.20 68.64 m2
b Pembesian dengan besi polos A.4.1.1.17.p 1,162.78 kg
c Pembesian dengan besi ulir A.4.1.1.17.u 279.55 kg
d Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 11.11 m3
e Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa slump (3-6) cm, w/c = 0,87 (K 100) A.4.1.1.4 1.80 m3
2 Pondasi footplat fp 2
a (K3) Pemasangan 1 m2 bekisting untuk pondasi A.4.1.1.20 29.76 m2
b Pembesian dengan besi polos A.4.1.1.17.p 310.30 kg
c Pembesian dengan besi ulir A.4.1.1.17.u 139.78 kg
d Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 4.14 m3
e Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa slump (3-6) cm, w/c = 0,87 (K 100) A.4.1.1.4 0.58 m3
4 Sloof beton S1 20/30
(K3) Pemasangan 1 m2 bekisting untuk Sloof 2 x pakai A.4.1.1.21 41.40 m2
Pembesian dengan besi polos A.4.1.1.17.p 368.00 kg
Pembesian dengan besi ulir A.4.1.1.17.u 871.06 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 8.28 m3
5 Sloof beton SP 15/20
(K3) Pemasangan 1 m2 bekisting untuk Sloof 2 x pakai A.4.1.1.21 2.40 m2
Pembesian dengan besi polos A.4.1.1.17.p 65.28 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 0.48 m3
7 Kolom praktis
Pemasangan 1 m2 bekisting untuk Kolom 2 x pakai Dihit. A.4.1.1.a 10.50 m2
Pembesian dengan besi polos A.4.1.1.17.p 154.00 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 0.79 m3
8 Kolom beton K.1. 30/30
Pemasangan 1 m2 bekisting untuk Kolom 3 x pakai A.4.1.1.22 58.80 m2
Pembesian dengan besi polos A.4.1.1.17.p 349.44 kg
Pembesian dengan besi ulir A.4.1.1.17.u 931.84 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 10.08 m3
11 Membuat 1 m' balok lateau (15 x 20) cm
(K3) Pemasangan 1 m2 bekisting untuk balok 2 x pakai Dihit. A.4.1.1.b 9.50 m2
Pembesian dengan besi polos A.4.1.1.17.p 276.50 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 1.90 m3
12 Plat leufel
Pemasangan 1 m2 bekisting untuk balok 2 x pakai A.4.1.1.23 4.41 m2
Pembesian dengan besi polos A.4.1.1.17.p 102.41 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 0.51 m3
13 Balok beton B1. 20/50
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23 16.00 m2
Pembesian dengan besi polos A.4.1.1.17.p 80.00 kg
Pembesian dengan besi ulir A.4.1.1.17.u 292.64 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 2.00 m3
14 Balok beton B2. 20/40
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23 103.00 m2
Pembesian dengan besi polos A.4.1.1.17.p 274.67 kg
Pembesian dengan besi ulir A.4.1.1.17.u 864.38 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 8.24 m3
15 Balok beton B3. 20/30
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23 24.00 m2
Pembesian dengan besi polos A.4.1.1.17.p 88.00 kg
Pembesian dengan besi ulir A.4.1.1.17.u 220.56 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 1.80 m3
16 Balok beton B4. 20/30
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23 24.00 m2
Pembesian dengan besi polos A.4.1.1.17.p 88.00 kg
Pembesian dengan besi ulir A.4.1.1.17.u 189.36 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 1.80 m3

17 Plat Lantai beton (lantai 1-2) +4.00


Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24 83.80 m2
Pembesian dengan besi polos A.4.1.1.17.p 1,602.08 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 17.52 m3
18 Tangga beton (lantai 1-2)
Pemasangan 1 m2 bekisting untuk tangga A.4.1.1.26 21.29 m2
Pembesian dengan besi polos A.4.1.1.17.p 268.89 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 3.46 m3

V Pekerjaan Pasangan Dinding


1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal batu campuran 1SP : 3PP A.4.4.1.8 12.70 m2
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal batu campuran 1SP : 6PP A.4.4.1.11 251.27 m2

VI Pekerjaan Plesteran dan Acian


1 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15 mm A.4.4.2.3 25.40 m2
2 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6 502.54 m2
3 Pemasangan 1 m' plesteran skoning 1SP : 3PP A.4.4.2.20 170.65 m'
4 Pemasangan 1 m2 acian. A.4.4.2.27 527.94 m2

VII Pekerjaan penutup lantai & penutup dinding


1 Pemasangan 1 m2 Lantai Keramik 40x40 cm (putih/polos) Dihit. A.4.4.3.G.40/40. P 149.05 m2
2 Pemasangan 1 m2 lantai keramik 20x20 cm A.4.4.3.36 5.55 m2
3 Pemasangan 1 m2 lantai tangga keramik ukuran 30 cm x 30 cm A.4.4.3.35 7.07 m2
3 Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa slump (3-6) cm, w/c = 0,87 A.4.1.1.4 8.50 m3
4 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11 8.50 m3
5 Pemasangan 1 m2 Dinding Keramik 20 x 40 cm Dihit. A.4.4.3. W 20/40 11.20 m2
6 rabat beton mutu f'c = 14,5 MPa (K 175) slump (12 2) cm w/c = 0,66 A.4.1.1.5 4.05 m3
VIII Pekerjaan List Dak expose
1 Pemasangan 1 m List Langit - Langit Profil Gipsum Lebar 10 cm Dihit. Progips 10 262.00 m

IX Pekerjaan Pintu dan Jendela


1 Pintu (P.1), jumlah 8.00 unit
Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 80.00 m
Pemasangan 1 m2 pintu double Multipleks lapis hpl rangka kayu A.4.6.1.8 21.84 m2
Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17 4.50 m2
Engsel pintu A.4.6.2.5 48.00 bh
Grendel Dihit. Grend 4 16.00 bh
Handle Dihit. HP 30 16.00 ps
Pemasangan 1 buah kunci tanam biasa A.4.6.2.2 8.00 bh

2 Pintu (P.2), jumlah 2.00


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 19.60 m
Pemasangan 1 m2 pintu alluminium strip lebar 8 cm A.4.2.1.12 3.36 m2
Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17 1.20 m2
Engsel pintu A.4.6.2.5 6.00 bh
Grendel Dihit. Grend 4 2.00 bh
Handle Dihit. HP 30 2.00 ps
Pemasangan 1 buah kunci tanam biasa A.4.6.2.2 2.00 bh

3 Pintu (P.3), jumlah 2.00


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 19.20 m
Pemasangan 1 m2 pintu double Multipleks lapis hpl rangka kayu A.4.6.1.8 3.36 m2
Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17 3.50 m2
Engsel pintu A.4.6.2.5 6.00 bh
Grendel Dihit. Grend 4 2.00 bh
Handle Dihit. HP 30 2.00 ps
Pemasangan 1 buah kunci tanam biasa A.4.6.2.2 2.00 bh

4 Pintu Utama (P.4), jumlah 2.00 unit


Pemasangan Pintu Kaca temperred 12 mm Dihit. TF 12 8.88 m2
Patch Fitting ls 8.00 bh
Pull Handle Dihit. HP 30 4.00 ps
Patch Lock (kls I) ls 4.00 bh

5 Jendela 1 (J.1), jumlah 5.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 62.25 m
Pemasangan 1 m2 jendela kaca aluminium A.4.2.1.13 8.10 m2
Pemasangan 1 Kaca T 5mm A.4.6.2.17 8.00 m2
Engsel jendela A.4.6.2.6 20.00 bh
kait jendela A.4.6.2.9 20.00 bh
Pemasangan 1 Buah Rambuncis Jendela Allumunium 12" Dihit. Rambuncis 5.00 ps

6 Jendela (J.3), jumlah 1.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 17.80 m
Pemasangan 1 m2 jendela kaca aluminium A.4.2.1.13 2.43 m2
Pemasangan 1 Kaca T 5mm A.4.6.2.17 4.90 m2
Engsel jendela A.4.6.2.6 6.00 bh
kait jendela A.4.6.2.9 6.00 bh
Pemasangan 1 Buah Rambuncis Jendela Allumunium 12" Dihit. Rambuncis 3.00 ps
7 Jendela (J.4), jumlah 2.00 unit
Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 7.00 m
Pemasangan 1 Kaca T 5mm A.4.6.2.17 3.00 m2

8 Jendela (J.5), jumlah 2.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 7.00 m
Pemasangan 1 Kaca T 5mm A.4.6.2.17 2.80 m2

9 Jendela (BV.1), jumlah 2.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 4.40 m
Pemasangan 1 Kaca T 5mm A.4.6.2.17 1.35 m2

X Pekerjaan Pengecatan
1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.10 502.54 m2
2 Pengecatan 1 m2 Dak expose A.4.7.1.10 160.15 m2
3 Pengomponan m2 Dak expose ls 160.15 m2
4 Pengecatan 1 m2 Partisi A.4.7.1.10 139.58 m2

XI Pekerjaan Sanitasi Gedung


1 Pemasangan 1 buah closet duduk A.5.1.1.1 2.00 buah
2 Pemasangan 1 buah wastafel A.5.1.1 5 5.00 buah
3 Pemasangan 1 buah floor drain A.5.1.1 14 2.00 buah
4 Pemasangan 1 buah kran diameter " atau 3/4" A.5.1.1 19 2.00 buah
5 Pemasangan 1 m' pipa PVC tipe AW diameter 1" A.5.1.1 27 34.00 m'
6 Pemasangan 1 m pipa PVC tipe AW diameter 3 A.5.1.1 31 25.00 m'
7 Pemasangan 1 m pipa PVC tipe AW diameter 4 A.5.1.1 32 15.00 m'
8 Pasang got type U 20 cm termasuk pasangan dinding dihit 15.2. 58.00 m'
9 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm A.5.1.1 15 4.00 bh
10 Pekerjaan Septictank dan Peresapan ls 2.00 buah
11 Pas. Pipa Stainleess steel 1" tebal. 1mm untuk Pegangan (kamar mandi) ls 2.00 bh

XII Pekerjaan Mekanikal Elektrikal


1 (K3) Pemasangan 1 buah titik lampu A.8.4.6.1 31.00 titik/ls
2 Lampu TL (2x18) Dihit L.1.2.15 9.00 titik/ls
3 Lampu downlight inbow, LED 13w L.1.2.20 22.00 titik/ls
5 (K3) Pemasangan 1 buah stop kontak dihit A.8.4.6.2.a 17.00 titik/ls
6 SDP ls 1.00 unit/ls
7 Box Panel 40x60x20 cm ls 1.00 titik/ls

XIII Pekerjaan Lain-lain


1 Lettering Stainless Steel "PUSKESMAS PLANTUNGAN DAN IGD" ls 1.00 ls
2 Pembuatan Logo Kesehatan dari Acrylic ls 1.00 ls
3 Pembuatan Ralling Tangga ls 1.00 ls
4 pemasangan Partisi rangka Metal Stud Lapis double Calsiboard
a Pemasangan 1 m2 Rangka Partisi Dengan Bahan Metal Stud Dihit. Frame Stud 69.79 m2
b Pasang 1 m2 Dinding Partisi double Calsiboard ukuran (120x40x9) mm tebal 9 mm. Dihit. A.4.5.1. Calsi 139.58 m2
5 Pembuatan Canopi droof off
a Pasang 1 M Atap Carport (Galvalum rangka pipa/holo meni) Dihit. Galvani 22.00 m2
b Pengikat Canopi besi 16 + Plat t - 8 ls 1.00 ls

JUMLAH PEKERJAAN LANTAI 1

B PEKERJAAN LANTAI II :
I Pekerjaan beton
1 Kolom praktis kp. 15/15
Pemasangan 1 m2 bekisting untuk Kolom 2 x pakai Dihit. A.4.1.1.a 14.43 m2
Pembesian dengan besi polos A.4.1.1.17.p 200.20 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 1.08 m3

2 Kolom K1. 30/30


Pemasangan 1 m2 bekisting untuk Kolom 3 x pakai A.4.1.1.22 50.40 m2
Pembesian dengan besi polos A.4.1.1.17.p 299.52 kg
Pembesian dengan besi ulir A.4.1.1.17.u 798.72 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 8.64 m3

5 Balok beton RB1. 20/30


Pemasangan 1 m2 bekisting untuk balok 2 x pakai Dihit. A.4.1.1.b 18.40 m2
Pembesian dengan besi polos A.4.1.1.17.p 134.93 kg
Pembesian dengan besi ulir A.4.1.1.17.u 191.36 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 2.76 m3

6 Balok Ring RB.2 15/30


Pemasangan 1 m2 bekisting untuk balok 2 x pakai Dihit. A.4.1.1.b 33.38 m2
Pembesian dengan besi polos A.4.1.1.17.p 237.33 kg
Pembesian dengan besi ulir A.4.1.1.17.u 370.24 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 4.01 m3

6 Balok Ring RB.2 15/30


Pemasangan 1 m2 bekisting untuk balok 2 x pakai Dihit. A.4.1.1.b 9.75 m2
Pembesian dengan besi polos A.4.1.1.17.p 186.80 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 1.13 m3

7 Plat atap + 7. 50
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24 4.00 m2
Pembesian dengan besi polos A.4.1.1.17.p 111.60 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 0.48 m3

8 Membuat 1 m' balok lateau (15 x 20) cm


(K3) Pemasangan 1 m2 bekisting untuk balok 2 x pakai Dihit. A.4.1.1.b 9.50 m2
Pembesian dengan besi polos A.4.1.1.17.p 276.50 kg
Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 A.4.1.1.7 1.90 m3

II Pekerjaan Rangka Atap


1 Pemasangan 1 m2 Rangka Baja Ringan C.75.75 A.4.2.1.22.j 259.16 m2

III Pekerjaan Penutup atap


1 Pemasangan 1 m2 Atap Genteng Press Jatiwangi Besar Glazur Dihit. A.4.5.2.3 Glaz 259.16 m2
2 Pemasangan 1 m Bubung Genteng Jatiwangi Besar Glazur Dihit. A.4.5.2.6 Glaz 58.00 m'
3 Pemasangan 1 m2 alumunium foil/sisalation A.4.5.2.43 259.16 m2
4 Pemasangan 1 m Lisplank Urat Kayu 20 cm Dihit. A.4.6.1 . GRC Uk 20 84.00 m'

IV Pekerjaan Pasangan Dinding


1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal batu campuran 1SP : 3PP A.4.4.1.8 12.70 m2
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal batu campuran 1SP : 6PP A.4.4.1.11 157.04 m2
V Pekerjaan Plesteran dan Acian
1 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15 mm A.4.4.2.3 25.40 m2
2 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6 314.08 m2
3 Pemasangan 1 m' plesteran skoning 1SP : 3PP lebar 10 cm A.4.4.2.20 115.00 m2
4 Pemasangan 1 m2 acian. A.4.4.2.27 339.48 m2

VI Pekerjaan penutup lantai & penutup dinding


1 Pemasangan 1 m2 lantai keramik 40x40 cm Dihit. A.4.4.3.G.40/40. P 140.45 m2
2 Pemasangan 1 m2 lantai keramik 20x20 cm A.4.4.3.36 2.78 m2

VII Pekerjaan Pintu dan Jendela


1 Pintu (P.1), jumlah 2.00 unit
Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 20.00 m
Pemasangan 1 m2 pintu double Multipleks lapis hpl rangka kayu A.4.6.1.8 5.46 m2
Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17 1.13 m2
Engsel pintu A.4.6.2.5 12.00 bh
Grendel Dihit. Grend 4 4.00 bh
Handle Dihit. HP 30 4.00 ps
Pemasangan 1 buah kunci tanam biasa A.4.6.2.2 2.00 bh

2 Pintu (P.2), jumlah 1.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 7.00 m
Pemasangan 1 m2 pintu alluminium strip lebar 8 cm A.4.2.1.12 1.68 m2
Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17 0.58 m2
Engsel pintu A.4.6.2.5 3.00 bh
Grendel Dihit. Grend 4 1.00 bh
Pemasangan 1 buah kunci tanam biasa A.4.6.2.2 1.00 bh

3 Jendela 1 (J.1), jumlah 5.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 55.50 m
Pemasangan 1 m2 jendela kaca aluminium A.4.2.1.13 8.10 m2
Pemasangan 1 Kaca T 5mm A.4.6.2.17 11.50 m2
Engsel jendela A.4.6.2.6 20.00 bh
kait jendela A.4.6.2.9 20.00 bh
rambuncis Dihit. Rambuncis 16.00 ps

4 Jendela (J.2), jumlah 2.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 19.70 m
Pemasangan 1 m2 jendela kaca aluminium A.4.2.1.13 1.62 m2
Pemasangan 1 Kaca T 5mm A.4.6.2.17 1.26 m2
Engsel jendela A.4.6.2.6 4.00 bh
kait jendela A.4.6.2.9 4.00 bh
Pemasangan 1 Buah Rambuncis Jendela Allumunium 12" Dihit. Rambuncis 2.00 ps

5 Jendela (J.3), jumlah 1.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 17.80 m
Pemasangan 1 m2 jendela kaca aluminium A.4.2.1.13 2.43 m2
Pemasangan 1 Kaca T 5mm A.4.6.2.17 4.90 m2
Engsel jendela A.4.6.2.6 6.00 bh
kait jendela A.4.6.2.9 6.00 bh
Pemasangan 1 Buah Rambuncis Jendela Allumunium 12" Dihit. Rambuncis 3.00 ps

6 Jendela (J5), jumlah 2.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 7.00 m
Pemasangan 1 Kaca T 5mm A.4.6.2.17 2.80 m2

7 Jendela (J.6), jumlah 1.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 9.00 m
Pemasangan 1 Kaca T 5mm A.4.6.2.17 5.10 m2

8 Jendela (BV), jumlah 1.00 unit


Pemasangan 1 m kusen pintu alluminium 4" natural / silver A.4.2.1.11 4.40 m2
Pemasangan 1 Kaca T 5mm A.4.6.2.17 1.35 m2

VIII Pekerjaan Pengecatan


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.10 339.48 m2
2 Pengecatan 1 m2 partisi A.4.7.1.10 138.60 m2
IX Pekerjaan Sanitasi Gedung
1 Pemasangan 1 buah closet duduk A.5.1.1.1 1.00 buah
2 Pemasangan 1 buah kran diameter atau A.5.1.1 19 1.00 buah
3 Pemasangan 1 buah floor drain A.5.1.1 14 1.00 buah
4 Pemasangan 1 m' pipa PVC tipe AW diameter 1" A.5.1.1 27 20.00 m'
5 Pemasangan 1 m pipa PVC tipe AW diameter 4 A.5.1.1 32 20.00 m'

X Pekerjaan Mekanikal Elektrikal


1 (K3) Pemasangan 1 buah titik lampu A.8.4.6.1 35.00 titik
2 Lampu TL (2x18) Dihit L.1.2.15 13.00 titik
3 Lampu downlight inbow, LED 13w L.1.2.20 12.00 titik
4 (K3) Pemasangan 1 buah stop kontak dihit A.8.4.6.2.a 10.00 titik

XI Pekerjaan Lain -Lain


1 pemasangan Partisi rangka Metal Stud Lapis double Calsiboard
a Pemasangan 1 m2 Rangka Partisi Dengan Bahan Metal Stud Dihit. Frame Stud 69.30 m2
b Pasang 1 m2 Dinding Partisi double Calsiboard ukuran (120x40x9) mm tebal 9 mm. Dihit. A.4.5.1. Calsi 138.60 m2
2 Railling besi lantai 2 ls 1.00 ls

JUMLAH PEKERJAAN LANTAI 2

:Disetujui :Dibuat Oleh


PEJABAT PEMBUAT KOMITMEN DINAS Konsultan Perencana
KESEHATAN KABUPATEN KENDAL CV. PRAMBANAN

DWI RESPATI YULIANTA,Amd NGATMIATI, SH


NIP. 19640716 198802 1 003 Direktur

:MENGETAHUI :MENGETAHUI
PLT. KEPALA DINAS PEKERJAAN UMUM DAN PLT. KEPALA DINAS KESE
PENATAAN RUANG KABUPATEN KENDAL KABUPATEN KENDA

WINARNO, SH, MM dr. SRI MULYANI, Sp.A.M


Pembina NIP. 19620520 198910 2
NIP. 19620618 198703 1 001
AB )

HARGA SATUAN
JUMLAH
(Rp.)

14,966,468.25
146,585.25 7,769,018.25
275,000.00 275,000.00
12,485.00 2,122,450.00
200,000.00 4,800,000.00

20,121,738.44
61,857.50 4,409,202.60
61,857.50 5,089,635.10
61,857.50 211,552.65
20,619.17 1,055,426.41
213,071.28 7,244,423.52
297,143.00 2,111,498.16

40,755,317.36
1,055,635.13 29,642,234.31
614,006.63 10,217,070.24
261,992.05 896,012.81

464,208,488.10

259,915.00 17,840,565.60
14,151.75 16,455,407.45
15,343.50 4,289,305.41
1,295,798.87 14,395,029.68
1,082,905.90 1,949,230.62

259,915.00 7,735,070.40
14,151.75 4,391,325.74
15,343.50 2,144,652.71
1,295,798.87 5,367,846.83
1,082,905.90 623,753.80

282,615.00 11,700,261.00
14,151.75 5,207,843.08
15,343.50 13,365,045.56
1,295,798.87 10,729,214.67

282,615.00 678,276.00
14,151.75 923,826.08
1,295,798.87 621,983.46

313,742.38 3,294,294.94
14,151.75 2,179,369.12
1,295,798.87 1,020,441.61

522,582.38 30,727,843.65
14,151.75 4,945,186.65
15,343.50 14,297,684.71
1,295,798.87 13,061,652.64

282,529.88 2,684,316.34
14,151.75 3,913,003.47
1,295,798.87 2,462,277.02

541,309.88 2,387,176.55
14,151.75 1,449,280.46
1,295,798.87 666,688.52

541,309.88 8,660,958.00
14,151.75 1,132,139.80
15,343.50 4,490,121.11
1,295,798.87 2,591,597.75

541,309.88 55,754,917.13
14,151.75 3,887,013.31
15,343.50 13,262,551.00
1,295,798.87 10,677,382.71

541,309.88 12,991,437.00
14,151.75 1,245,353.78
15,343.50 3,384,161.81
1,295,798.87 2,332,437.97

541,309.88 12,991,437.00
14,151.75 1,245,353.78
15,343.50 2,905,444.69
1,295,798.87 2,332,437.97

704,182.38 59,010,483.03
14,151.75 22,672,231.63
1,295,798.87 22,702,396.26

476,359.50 10,139,407.23
14,151.75 3,805,315.70
1,295,798.87 4,486,055.70

31,648,066.53
125,154.18 1,589,458.09
119,626.73 30,058,608.45

60,066,353.50
64,934.94 1,649,347.45
61,411.90 30,861,935.72
58,588.70 9,998,161.66
33,255.50 17,556,908.67

56,833,059.14
229,571.91 34,217,693.19
198,607.98 1,102,274.26
202,143.50 1,428,143.83
1,082,905.90 9,204,700.17
297,143.00 2,525,715.50
297,307.58 3,329,844.84
1,240,663.55 5,024,687.36
7,947,956.68
30,335.71 7,947,956.68

88,209,885.39

122,848.43 9,827,874.20
742,658.88 16,219,669.83
142,032.77 639,147.44
45,444.27 2,181,324.72
91,231.30 1,459,700.80
237,646.30 3,802,340.80
142,839.75 1,142,718.00

122,848.43 2,407,829.18
853,274.27 2,867,001.56
142,032.77 170,439.32
45,444.27 272,665.59
91,231.30 182,462.60
237,646.30 475,292.60
142,839.75 285,679.50

122,848.43 2,358,689.81
742,658.88 2,495,333.82
142,032.77 497,114.68
45,444.27 272,665.59
91,231.30 182,462.60
237,646.30 475,292.60
142,839.75 285,679.50

1,574,459.52 13,981,200.49
150,000.00 1,200,000.00
237,646.30 950,585.20
250,000.00 1,000,000.00

122,848.43 7,647,314.61
489,031.78 3,961,157.38
142,032.77 1,136,262.12
39,373.15 787,463.00
47,233.03 944,660.50
29,158.15 145,790.75

122,848.43 2,186,702.01
489,031.78 1,188,347.21
142,032.77 695,960.55
39,373.15 236,238.90
47,233.03 283,398.15
29,158.15 87,474.45
122,848.43 859,938.99
142,032.77 426,098.30

122,848.43 859,938.99
142,032.77 397,691.74

122,848.43 540,533.08
142,032.77 191,744.23

34,451,104.66
38,949.80 19,573,829.98
38,949.80 6,237,712.29
20,000.00 3,202,950.00
38,949.80 5,436,612.39

45,109,527.89
1,894,031.25 3,788,062.50
1,667,221.93 8,336,109.65
74,853.25 149,706.50
148,741.75 297,483.50
25,211.19 857,180.38
90,215.48 2,255,386.88
130,238.41 1,953,576.19
135,305.00 7,847,690.00
456,973.70 1,827,894.80
8,398,218.75 16,796,437.50
1,000,000.00 1,000,000.00

24,294,053.50
335,627.50 10,404,452.50
325,000.00 2,925,000.00
167,000.00 3,674,000.00
248,653.00 4,227,101.00
2,500,000.00 2,500,000.00
563,500.00 563,500.00

40,892,587.20
6,000,000.00 6,000,000.00
2,400,000.00 2,400,000.00
4,000,000.00 4,000,000.00

101,610.88 7,091,422.97
38,552.55 5,381,164.23

660,000.00 14,520,000.00
1,500,000.00 1,500,000.00

929,504,606.64
121,003,431.32

313,742.38 4,527,302.47
14,151.75 2,833,179.85
1,295,798.87 1,402,378.33

522,582.38 26,338,151.70
14,151.75 4,238,731.41
15,343.50 12,255,158.32
1,295,798.87 11,195,702.26

282,529.88 5,198,549.70
14,151.75 1,909,542.46
15,343.50 2,936,131.68
1,295,798.87 3,576,404.89

282,529.88 9,429,434.58
14,151.75 3,358,681.41
15,343.50 5,680,776.51
1,295,798.87 5,189,674.49

282,529.88 2,754,666.28
14,151.75 2,643,546.43
1,295,798.87 1,457,773.73

704,182.38 2,816,729.50
14,151.75 1,579,335.02
1,295,798.87 621,983.46

282,529.88 2,684,316.34
14,151.75 3,913,003.47
1,295,798.87 2,462,277.02

53,940,382.90
208,135.45 53,940,382.90

46,639,713.74
112,677.13 29,201,403.72
109,028.10 6,323,629.80
28,732.53 7,446,321.18
43,670.94 3,668,359.04

20,375,639.77
125,154.18 1,589,458.09
119,626.73 18,786,181.68
38,964,874.33
64,934.94 1,649,347.45
61,411.90 19,288,249.24
58,588.70 6,737,700.50
33,255.50 11,289,577.14

32,794,511.89
229,571.91 32,243,374.76
198,607.98 551,137.13

38,469,346.32

122,848.43 2,456,968.55
742,658.88 4,054,917.46
142,032.77 159,786.86
45,444.27 545,331.18
91,231.30 364,925.20
237,646.30 950,585.20
142,839.75 285,679.50

122,848.43 859,938.99
853,274.27 1,433,500.78
142,032.77 81,952.91
45,444.27 136,332.80
91,231.30 91,231.30
142,839.75 142,839.75

122,848.43 6,818,087.73
489,031.78 3,961,157.38
142,032.77 1,633,376.80
39,373.15 787,463.00
47,233.03 944,660.50
29,158.15 466,530.40

122,848.43 2,420,114.02
489,031.78 792,231.48
142,032.77 178,961.28
39,373.15 157,492.60
47,233.03 188,932.10
29,158.15 58,316.30

122,848.43 2,186,702.01
489,031.78 1,188,347.21
142,032.77 695,960.55
39,373.15 236,238.90
47,233.03 283,398.15
29,158.15 87,474.45

122,848.43 859,938.99
142,032.77 397,691.74
122,848.43 1,105,635.85
142,032.77 724,367.10

122,848.43 540,533.08
142,032.77 191,744.23

18,621,117.99
38,949.80 13,222,676.41
38,949.80 5,398,441.59
4,575,426.19
1,894,031.25 1,894,031.25
148,741.75 148,741.75
74,853.25 74,853.25
25,211.19 504,223.75
130,238.41 1,953,576.19
20,462,492.50
335,627.50 11,746,962.50
325,000.00 4,225,000.00
167,000.00 2,004,000.00
248,653.00 2,486,530.00
17,585,016.37

101,610.88 7,041,633.64
38,552.55 5,343,382.74
5,200,000.00 5,200,000.00

413,431,953.32

Dibuat Oleh
ultan Perencana
PRAMBANAN

ATMIATI, SH
Direktur

ENGETAHUI
A DINAS KESEHATAN
PATEN KENDAL

LYANI, Sp.A.M.Kes
0520 198910 2 001
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : PELAYANAN KESEHATAN DASAR
PEKERJAAN : PEMBANGUNAN PUSKESMAS PLANTUNGAN
LOKASI : KECAMATAN PLANTUNGAN
TH ANGGARAN : 2017

NO URAIAN PEKERJAAN JUMLAH HARGA

A. PEKERJAAN LANTAI I :
I Pekerjaan Persiapan Rp
II Pekerjaan Tanah Rp
III Pekerjaan Pondasi Rp
IV Pekerjaan Beton Rp
V Pekerjaan Pasangan Dinding Rp
VI Pekerjaan Plesteran dan Acian Rp
VII Pekerjaan penutup lantai & penutup dinding Rp
VIII Pekerjaan List Dak expose Rp
IX Pekerjaan Pintu dan Jendela Rp
X Pekerjaan Pengecatan Rp
XI Pekerjaan Sanitasi Gedung Rp
XII Pekerjaan Mekanikal Elektrikal Rp
XIII Pekerjaan Lain Lain Rp
JUMLAH PEKERJAAN LANTAI I Rp

B. PEKERJAAN LANTAI II :
I Pekerjaan Beton Rp
II Pekerjaan Rangka Atap Rp
III Pekerjaan Penutup atap Rp
IV Pekerjaan Pasangan Dinding Rp
V Pekerjaan Plesteran, Acian Rp
VI Pekerjaan penutup lantai & penutup dinding Rp
VIII Pekerjaan Pintu dan Jendela Rp
IX Pekerjaan Pengecatan Rp
X Pekerjaan Sanitasi Gedung Rp
XI Pekerjaan Mekanikal Elektrikal Rp
XII Pekerjaan Lain -Lain Rp
JUMLAH PEKERJAAN LANTAI II Rp

JUMLAH Rp
PPN 10% Rp
JUMLAH TOTAL (Jumlah + PPN 10%) Rp
PEMBULATAN Rp
Terbilang :
Satu Milyar Empat ratus Tujuh Puluh Tujuh Juta Dua Ratus Tiga Puluh Ribu Rupiah
Kendal, 2017
:Disetujui :Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN DINAS Konsultan Perencana
KESEHATAN KABUPATEN KENDAL CV. PRAMBANAN

DWI RESPATI YULIANTA,Amd NGATMIATI, SH


NIP. 19640716 198802 1 003 Direktur
:MENGETAHUI
:MENGETAHUI PLT. KEPALA DINAS KESEHATAN
PLT. KEPALA DINAS PEKERJAAN KABUPATEN KENDAL
UMUM DAN PENATAAN RUANG
KABUPATEN KENDAL

dr. SRI MULYANI, Sp.A.M.Kes


WINARNO, SH, MM NIP. 19620520 198910 2 001
Pembina
NIP. 19620618 198703 1 001
ANA ANGGARAN BIAYA ( RAB )

JUMLAH HARGA

14,966,468.25
20,121,738.44
40,755,317.36
464,208,488.10
31,648,066.53
60,066,353.50
56,833,059.14
7,947,956.68
88,209,885.39
34,451,104.66
45,109,527.89
24,294,053.50
40,892,587.20
929,504,606.64

121,003,431.32
53,940,382.90
46,639,713.74
20,375,639.77
38,964,874.33
32,794,511.89
38,469,346.32
18,621,117.99
4,575,426.19
20,462,492.50
17,585,016.37
413,431,953.32

1,342,936,559.96
134,293,656.00
1,477,230,215.96
1,477,230,000.00

us Tujuh Puluh Tujuh Juta Dua Ratus Tiga Puluh Ribu Rupiah
Kendal, 2017
:Dibuat Oleh
Konsultan Perencana
CV. PRAMBANAN

NGATMIATI, SH
Direktur
:MENGETAHUI
PLT. KEPALA DINAS KESEHATAN
KABUPATEN KENDAL

dr. SRI MULYANI, Sp.A.M.Kes


NIP. 19620520 198910 2 001
LAMPIRAN PERHITUNGAN PEKERJAAN SEPTICTANK DAN PERESAPAN

PEKERJAAN PEMBANGUNAN PUSKESMAS KALIWUNGU


LOKASI KECAMATAN KALIWUNGU
TH ANGGARAN TAHUN ANGGARAN 2017

HARGA SATUAN JUMLAH SUB JUMLAH


NO URAIAN PEKERJAAN ANALISA VOL SAT UPAH + BAHAN ( RP. ) ( RP. )
( RP. )
1 2 3 4 5 6 7 8
I PEKERJAAN SEPTICTANK DAN PERESAPAN
1 Galian Tanah Biasa sedalam 2 M A.2.3.1.2 10.600 m3 75,591.00 801,264.60
2 Urugan Pasir A.2.3.1.11 0.705 m3 297,143.00 209,485.82
3 Pas. Batu Kosong (aanstamping) A.3.2.1.9 0.180 m3 614,006.63 110,521.19
5 Pasangan Bata MerahTebal 1/2 Bata, 1Pc : 3PP A.4.4.1.8 21.190 m2 125,154.18 2,652,017.07
6 Pemasangan 1 m2 plesteran 1SP : 3 PP tebal 20 mm A,4,4,2.14 10.560 m2 74,972.65 791,711.21
7 Pemasangan 1 m2 acian A.4.4.2.27 10.560 m2 33,255.50 351,178.08
8 1 m2 Pemasangan lapisan ijuk tebal 10 cm A.2.3.1.13 15.060 m2 41,881.50 630,735.39
9 1 m3 urugan batu belah 10/20 dihit 2.11.c 0.648 m2 358,171.00 232,094.81
10 1 m3 urugan batu pecah 5/7 dihit 2.11.a 0.360 m2 392,221.00 141,199.56
11 1 m3 urugan batu pecah 2/3 dihit 2.11.b 0.432 m2 426,271.00 184,149.07
12 Pasang Pipa PVC Type AW 3" (dari Septictank Ke Peresapan A.5.1.1.31 6.000 m' 90,215.48 541,292.85
13 Pasang Pipa Galvanis 2" (lubang udara septictank) A.5.1.1.22 2.500 m' 161,306.20 403,265.50
14 Urugan Kembali A.2.3.1.9 0.500 m3 20,619.17 10,309.58
PEKERJAAN BETON
15 Pekerjaan Penutup Septictank
a. Beton mutu f'c= 14,5 MPa (K175) A.4.1.1.5 0.194 m3 1,239,102.92 240,385.97
b. Pembesian dengan Besi Beton A.4.1.1.17.p 24.552 kg 14,151.75 347,453.70
c. Bekisting - 1x pakai A.4.1.1.20 2.890 m2 259,915.00 751,154.35
SUB TOTAL 8,398,218.75
DAFTAR HARGA SATUAN UPAH TENAGA, BAHAN DAN SEWA PERALATAN

NO. JENIS URAIAN SATUAN

I UPAH TENAGA
1 Kepala Tukang Alumunium Hari
2 Kepala Tukang Batu Hari
3 Kepala Tukang Besi Hari
4 Kepala Tukang Cat Hari
5 Kepala Tukang Kayu Hari
6 Kepala Tukang Las Konstruksi Hari
7 Kepala Tukang Las Biasa Hari
8 Kepala Tukang Pipa Hari
9 Mandor Hari
10 Pekerja Hari
11 Tukang Allumunium Hari
12 Tukang Batu Halus Hari
13 Tukang Batu Kasar Hari
14 Tukang Besi Hari
15 Tukang Besi Konstruksi Hari
12 Tukang Cat Hari
13 Tukang Ereksi Hari
14 Tukang Gali Hari
15 Tukang Jalan Hari
16 Tukang Kayu Halus Hari
13 Tukang Kayu Kasar Hari
17 Tukang Listrik Hari

II BAHAN
1 Batu bata Welahan buah
2 Batu Belah m
3 Batu Granit Kg
4 Batu Kali Bulat Bulat/Utuh/Blondos m
5 Batu Paras buah
6 Batu Pecah m
7 Batu Tempel Hitam buah
8 Batu Teraso Kg
9 Beton 1:2:3 m
10 Beton Ready Mix K 175 m
11 Beton Ready Mix K 200 m
12 Beton Ready Mix K 225 m
13 Beton Ready Mix K 250 m
14 Beton Ready Mix K 275 m
15 Beton Ready Mix K 300 m
16 Compound Kg
17 HB-10 buah
18 HB-15 buah
19 HB-20 buah
20 Kapur m
21 Kapur Padam m
22 Kapur Sirih Kg
23 Kerikil beton / Split m
24 Kerikil (2cm/3cm) m
25 Kerikil (maks 30 mm) Kg
26 Kerikil Sawur / Koral Bulat m
27 Koral m
28 Koral Beton m
29 Mortar Siap Pakai kg
30 Pasir Beton m
31 Pasir Pasang m
32 Pasir Urug m
33 Screening kg
34 Semen Grout kg
38 Semen PC kg
39 Semen PC 40 kg zak
40 Semen PC 50 kg zak
41 Semen Portland kg
42 Semen Portland @40 kg kg
43 Semen Putih 40 kg zak
44 Semen Warna kg
45 Sirtu m
46 Tanah Liat m
47 Tanah Padas Quarry - Lokasi Pekerjaan m
48 Tanah Padas Quarry m

III BAHAN PENUTUP ATAP


1 Bubungan Press Jatiwangi Glazur Biru/Hijau Buah
2 Bubungan Press Jatiwangi Glazur Transparan/Coklat/Hitam Buah
3 Genteng Bubung Glazuur Buah
4 Genteng Bubung Besar Buah
5 Genteng Bubungan Keramik Natural (Transparan) Buah
6 Genteng Bubungan Keramik Warna Standar Buah

IV BAHAN KAYU
1 Balok Kayu Jati m
2 Balok Kayu Bengkirai m
3 Balok Kayu Kamper m
4 Balok Kayu Kruing m
5 Balok Kayu Meranti m
6 Balok Kayu Sengon m
7 Balok Kayu Lanan m
8 Dolken kayu 8-10/400 cm batang
7 Kaso 5/7 bengkirai m
8 Kaso 5/7 kamper m
9 Kaso 5/7 Kruing m
10 Kaso 5/7 meranti m
11 Kayu Lambersering m
12 Papan Kayu Jati m
13 Papan Kayu Bengkirai m
14 Papan Kayu Kamper m
15 Papan Kayu Kruing m
16 Papan Kayu Meranti m
17 Papan Kayu Sengon m
18 Papan Kayu Lanan m
19 Parket 7,5 x 75 x 900 mm m
20 Parket 10 x 75 x 490 mm m
21 Parket 9 x 75 x 1500 mm m
22 Phenol film 12 mm Lembar
23 Plywood 4 mm Ukuran 120 x 240 Lembar
24 Plywood tebal 12 mm Lembar
25 Plywood tebal 15 mm Lembar
26 Plywood tebal 3 mm Lembar
27 Plywood tebal 4 mm Lembar
28 Plywood tebal 4 mm Ukuran (90 x 220) cm Lembar
29 Plywood tebal 6 mm Lembar
30 Plywood tebal 9 mm Lembar
31 Reng Bengkirai m
32 Reng Kamper m
33 Reng Kruing m
34 Reng Meranti m
35 Sasak Bambu (Anyaman Bambu) m
36 Teakwood 122 x 244 tebal 4 mm Lembar
37 Teakwood tebal 4 mm (90 x 220) cm Lembar
38 Tripleks Lembar

V BAHAN PENUTUP DINDING / LANTAI


1 ACP Bracing Buah
2 ACP Bracket Buah
3 ACP Coating PE (Indoor) Lembar
4 ACP Coating PVDF (Outdoor) Lembar
5 Batu Alam Andesit Alur Bakar m
6 Batu Alam Andesit Bintik Bakar m
7 Keramik Lantai 20 x 20 cm (Putih/Polos) Mulia,Platinum 25 bh/Doos
8 Keramik Lantai 25 x 25 cm (Motif) Milan, Roman 16 bh/Doos
9 Keramik Lantai 25 x 25 cm (Putih/Polos) 16 bh/Doos
10 Keramik Lantai 30 x 30 cm (Motif) Mulia, Platinum 11 bh/Doos
11 Keramik Lantai 30 x 30 cm (Putih/Polos) Milan, Roman 11 bh/Doos
12 Keramik Lantai 33 x 33 cm (Motif) Mulia, Platinum 9/ bh/Doos
13 Keramik Lantai 33 x 33 cm (Putih/Polos) Mulia, Platinum 9/ bh/Doos
14 Keramik Lantai 40 x 40 cm (Motif) Mulia, Platinum 6 bh/Doos
15 Keramik Lantai 40 x 40 cm (Putih/Polos) Muli,a Platinum 6 bh/Doos
16 Keramik Lantai 50 x 50 cm (Motif) Mulia, Platinum 4 bh/Doos
18 Keramik Lantai 60 x 60 cm (Motif) Mulia, Platinum 3 bh/Doos
19 Keramik Lantai 60 x 60 cm (Putih/Polos) Mulia, Platinum 3 bh/Doos
20 Kuku Macan 10 cm buah
21 Marmer 100 x 10 cm Buah
22 Plint keramik 10 cm x 10 cm Buah
23 Plint keramik 10 cm x 20 cm Buah
24 Plint keramik 5 cm x 20 cm Buah

VII BAHAN BESI DAN ALUMUNIUM


1 Alluminium Strip m'
2 Aluminium Foil m
3 Aluminium Foil Super Woven Double m
4 Aluminium Foil Super Woven Single m
5 Aluminium gel tebal 0,55 Lembar
6 Baja ringan canal dingin C75 Batang
7 Baja strip (0,2 x 2) cm Kg
8 Baja Tulangan Kg
9 Besi Angker diameter 8 Kg
10 Besi Baja IWF Kg
11 Besi beton Kg
19 Besi Beton Polos Kg
20 Besi Beton ulir Kg
21 Besi hollow (50 x 50 x 3) mm Kg
22 Besi Tralis Kaca (1 x 1) cm m
23 Besi Plat Baja Kg
24 Besi Plat Bordes Kg
25 Besi Profil Kg
26 Besi Profil Canal / UNP Kg
27 Besi Profil IWF Kg
28 Besi Profil Siku Kg
29 Besi Square Tube (Hollow Persegi) m
30 Besi Siku L 30.30.3 Kg
31 Besi Strip Kg
32 Besi Strip 3 x 30 mm m
33 Besi strip tebal 5 mm Kg
34 Besi Teralis Nako 10 mm Batang
35 Besi Teralis Nako 12 mm Batang
36 Hollow Alumunium 23 x 34,5 mm Lembar
37 Hollow Alumunium 35 x 35 mm Lembar
38 Hollow Galvanis 20 x 40 x 0,35 mm 4 m/btg
39 Hollow Galvanis 40 x 40 x 0,35 mm 4 m/btg
40 Hollow Meni 20 x 40 x 1,1 mm 4 m/btg
41 Hollow Meni 40 x 40 x 1,1 mm 4 m/btg
43 Kawat Beton Kg
42 Kawat Penggantung Galvanis 4 mm Kg
43 Kusen Alumunium 3" Natural/Silver Batang
44 Kusen Alumunium 3" Urat Kayu Batang
45 Kusen Alumunium 3" Warna Powder Coating Batang
46 Kusen Alumunium 4" Natural/Silver Batang
40 Kusen Alumunium 4" Urat Kayu Batang
41 Kusen Alumunium 4" Warna Powder Coating Batang
42 Kusen U PVC Putih setara Bosca Batang
45 Metal Stud 34x100x 0,4 mm 3 m/btg
46 Metal Stud 34x50x0,4 mm 3 m/btg
47 Metal Stud 34x76x0,4 mm 3 m/btg
42 Pintu Alluminium m
46 Profil "T" Natural/Silver Batang
47 Profil Alluminium m
48 Profil Rangka Jendela U PVC Putih setara Bosca Batang
49 Profil Aluminium Rangka Jendela Natural/Silver Batang
50 Profil Aluminium Rangka Jendela Warna Powder Coating Batang
44 Profil Aluminium Rangka Pintu Natural/Silver Batang
45 Profil Rangka Pintu U PVC Putih setara Bosca Batang
46 Profil Aluminium Rangka Pintu Warna Powder Coating Batang
47 Profil Siku untuk Tatapan Natural/Silver Batang
48 Profil Siku untuk Tatapan Warna Powder Coating Batang
49 Rangka metal hollow 40.40.2 mm m
50 Reng 28.45 ( Profil baja Ringan ) 6 m/btg
51 Reng 30.45 ( Profil baja Ringan ) 6 m/btg
45 Reng 31.45 ( Profil baja Ringan ) 6 m/btg
46 Reng 32.45 ( Profil baja Ringan ) 6 m/btg
47 Reng 40.45 ( Profil baja Ringan ) 6 m/btg
48 Reng 40.60 ( Profil baja Ringan ) 6 m/btg

VIII BAHAN PIPA


1 Pipa Galvanis " m
2 Pipa Galvanis " m
3 Pipa Galvanis 1" m
4 Pipa Galvanis 1" m
5 Pipa Galvanis 3" m
6 Pipa Galvanis 4" m
7 Pipa PVC " m
8 Pipa PVC 1" m
9 Pipa PVC 2" m
10 Pipa PVC 2" m
11 Pipa PVC 3" m
12 Pipa PVC " m
13 Pipa PVC 4" m

IX BAHAN LANGIT - LANGIT


1 Alumunium Foil Super Woven Double 120x50 cm 10/Roll
2 Alumunium Foil Super Woven Single 120x50 cm 10/Roll
3 Gipsum Board 120 x 240 cm tebal 12 mm Lembar
4 Gipsum Board 120 x 240 cm tebal 6,5 mm Lembar
5 Gipsum Board 120 x 240 cm tebal 9 mm Lembar
6 Gypsum Board Lembar
7 Kawat Galvanis 4 mm Kg
8 Kawat 4 mm Kg
14 List Profil Gipsum lebar 10 cm m
19 Paku Ramset buah
20 Papan Semen 122 x 244 cm tebal 4 mm Lembar
21 Papan Semen 122 x 244 cm tebal 6 mm Lembar
22 Papan Semen 122 x 244 cm tebal 8 mm Lembar

X BAHAN FINISHING
1 Cat kg
2 Cat Antara kg
3 Cat Acrilic Waterproofing kg
7 Cat Dasar kg
8 Cat Dasar Besi kg
9 Cat Dasar Kayu kg
10 Cat Genteng kg
11 Cat Kolam kg
12 Cat Meni kg
13 Cat Penutup Besi kg
14 Cat Penutup Kayu kg
15 Cat Penutup Tembok kg
16 Cat Penutup Tembok Eksterior Klas I kg
17 Cat Penutup Tembok Eksterior Klas II kg
18 Cat Penutup Tembok Interior Klas I kg
19 Cat Penutup Tembok Interior Klas II kg
20 Cat Pelapis Waterproofer kg
21 Dempul kg
22 Melamic kg
23 Meni A kg
24 Meni B kg
25 Meni Besi kg
26 Meni Kayu kg
27 Plamur / Dempul Besi kg
29 Plamur Tembok kg
30 Plamur/Dempul Kayu kg
31 Sanding kg
32 Semen Waterproofer kg
33 Serat Fiberglass m
34 Thinner Liter
XI BAHAN KACA (SETARA MULIA/ASAHI)
1 Bening/Polos 5 mm m
2 Bening/Polos 5 mm (Warna Hijau/Biru) m
3 Bening/Polos 8 mm m
4 Es ( Buram ) 5 mm m
5 Flat Tempered 10 mm m
6 Flat Tempered 12 mm m
7 Kaca Polos 5 mm m
8 Kaca tebal 3 mm m
9 Kaca tebal 5 mm m
10 Kaca tebal 8 mm m
11 Kaca wireglassed 5 mm m
12 One Way 5 mm m
13 One Way 8 mm m
14 Profil Kaca m
15 Ray Band 5 mm m
16 Ray Band 8 mm m
17 Sticker Sandblast m

XII BAHAN INSTALASI LISTRIK DAN LAMPU


1 Armatur Down Light 3 buah
2 Armatur Down Light 4 buah
3 Box Panel 40x60x20 cm buah
4 Fitting buah
5 Fitting Bulat buah
6 Fitting Gantung buah
7 Fitting Segi buah
8 FUSE BOX (SEKERING) 1 group buah
9 FUSE BOX (SEKERING) 2 group buah
10 FUSE BOX (SEKERING) 3 group buah
11 Kabel m
12 Klem buah
13 Klem Biasa buah
14 L Bow buah
15 Lampu Gantung buah
16 Lampu RM TL 2x18 Set
17 Lampu RM TL 2x36 Set
18 Lampu Taman buah
19 Lampu Tempel Minimalis buah
20 Las Dop buah
21 Lampu LED 13 Watt buah
22 Lampu LED 4 Watt buah
23 Lampu LED 7 Watt buah
24 Lampu LED 9 Watt buah
25 MCB buah
26 MCB (3 Phasa) 10 A Setara Scheneider Domae buah
27 Mangkok buah
28 NYA 1 x 1 1/2 mm2 100 m/Roll
29 NYA 1 x 2 1/2 mm2 100 m/Roll
30 NYA 1 x 4 mm2 100 m/Roll
31 NYA 1 x 6 mm2 100 m/Roll
32 NYM 2 x 1 1/2 100 m/Roll
33 NYM 3 x 2 1/2 100 m/Roll
34 NYY 2 x 1 1/2 mm2 100 m/Roll
35 NYY 2 x 2 1/2 mm2 100 m/Roll
34 NYY 3 x 1 1/2 mm2 100 m/Roll
35 NYY 3 x 2 1/2 mm2 100 m/Roll
36 NYY 3 x 4 mm2 100 m/Roll
35 NYY 3 x 6 mm2 100 m/Roll
36 Pipa Conduit 5/8" Btg
37 Pipa listrik 5/8" Btg
36 Saklar buah
37 Saklar Ganda buah
38 Saklar Triple buah
37 Saklar Tunggal buah
38 SL 11 Watt buah
39 SL 13 Watt buah
38 SL 18 Watt buah
39 SL 23 Watt buah
40 Stop Kontak AC buah
39 Stop Kontak Dinding Arde Indow buah
40 Stop Kontak Dinding Arde Outbow buah
41 T Dus buah
40 TL 18 Watt buah
41 TL 36 Watt buah
42 TL LED 10 Watt buah
41 TL LED 20 Watt buah
42 Tornado 12 Watt buah
43 Tornado 15 Watt buah
42 Tornado 20 Watt buah

XIII ALAT - ALAT PENGUNCI & PENGGANTUNG


1 Door Stop Buah
2 Engsel Angin Buah
3 Engsel Angin (Pivot) kuning/silver Pasang
4 Engsel Casement kuning/silver Pasang
5 Engsel Kupu-Kupu Buah
6 Engsel Kupu-Kupu Untuk Pintu Geser Garasi Buah
7 Engsel Pintu Buah
8 Floor Hinges (Engsel Lantai) buah
9 Grendel 3" kuning/silver Buah
10 Grendel 4" kuning/silver Buah

11 Grendel Rantai kuning/silver Buah


12 Grendel Tanam 12" kuning/silver Buah
13 Grendel Tanam 3" kuning/silver Buah
14 Grendel Tanam 4" kuning/silver Buah
15 Grendel Tanam 6" kuning/silver Buah
16 Kait Angin Pasang
22 Kunci Slot Buah
23 Kunci Tanam Buah
25 Kunci Tanam Biasa Buah
26 Kunci tanam KM Buah
27 Kunci Tanam Selinder Buah
28 Rambuncis (Handle jendela alumunium) buah
29 Tarikan Pintu Panjang 30 cm Pasang
30 Tarikan Pintu Panjang 40 cm Pasang
31 Tarikan Pintu Panjang 50 cm Pasang

XIV BAHAN SANITAIR


1 Bak teraso Unit
2 Bak Cuci Piring unit
3 Bak fiberglass Unit
4 Bak air fiberglass Unit
5 Closet duduk Biasa (Standar) Unit
6 Closet jongkok Unit
7 Floor Drain buah
8 Floor Drain Bagus Stainlees buah
9 Floor Drain Biasa Stainlees buah
10 Kran Air buah
11 Kran Air Bagus Stainlees buah
12 Kran Air Biasa Stainlees buah
13 Kran Air Shower Bagus buah
14 Kran Air Shower Biasa buah
15 Lem PVC 400 gr/Klg
16 Pintu Alumunium + Kaca Hias buah
17 Wastafel Bak Cuci Piring Kitchen Sink KS3100 buah
18 Wastafel Bak Cuci Piring Kitchen Sink KS3101 buah
19 Wastafel Bak Cuci Piring Kitchen Sink KS3200 buah
20 Wastafel Bak Cuci Piring Kitchen Sink KS4201 buah
21 Wastafel Biasa buah
22 Wastafel Pedestal Medium buah
23 Wastafel Pedestal Mewah / Istimewa buah
N SEWA PERALATAN

HARGA SATUAN

95,000.00
95,000.00
95,000.00
90,000.00
95,000.00
95,000.00
95,000.00
95,000.00
80,000.00
70,000.00
90,000.00
90,000.00
85,000.00
90,000.00
90,000.00
70,000.00
70,000.00
70,000.00
70,000.00
90,000.00
85,000.00
80,000.00

600.00
300,000.00
22,500.00
150,000.00
60,000.00
350,000.00
16,000.00
21,000.00
875,000.00
825,000.00
850,000.00
875,000.00
900,000.00
925,000.00
944,000.00
5,000.00
6,500.00
7,700.00
8,800.00
310,000.00
310,000.00
2,600.00
350,000.00
350,000.00
259.26
350,000.00
350,000.00
350,000.00
3,750.00
400,000.00
400,000.00
200,000.00
259.26
2,430.00
1,400.00
56,000.00
63,000.00
1,400.00
1,400.00
77,500.00
15,000.00
225,000.00
75,000.00
132,800.00
35,000.00

15,000.00
9,500.00
9,500.00
6,500.00
25,000.00
27,000.00

21,000,000.00
10,500,000.00
6,500,000.00
5,500,000.00
4,500,000.00
3,500,000.00
2,500,000.00
40,000.00
10,500,000.00
6,500,000.00
5,500,000.00
4,500,000.00
13,000,000.00
25,000,000.00
11,200,000.00
7,000,000.00
6,500,000.00
5,000,000.00
4,000,000.00
3,000,000.00
245,000.00
305,000.00
325,000.00
160,000.00
60,000.00
160,000.00
202,000.00
45,000.00
60,000.00
105,000.00
75,000.00
140,000.00
10,500,000.00
6,500,000.00
5,500,000.00
4,500,000.00
20,000.00
115,000.00
105,000.00
45,000.00

45,000.00
20,000.00
830,000.00
985,000.00
150,000.00
145,000.00
46,000.00
76,000.00
72,000.00
54,000.00
49,500.00
51,000.00
45,000.00
60,000.00
54,000.00
80,000.00
90,000.00
84,000.00
1,200.00
665,800.00
6,050.00
12,100.00
6,500.00

32,400.00
9,000.00
10,500.00
9,000.00
140,000.00
69,300.00
14,000.00
10,500.00
9,493.67
16,200.00
10,500.00
10,500.00
11,500.00
14,000.00
12,500.00
14,000.00
14,300.00
16,200.00
22,500.00
16,200.00
11,000.00
23,000.00
11,000.00
14,000.00
7,500.00
14,000.00
75,000.00
99,000.00
66,000.00
99,000.00
22,000.00
29,000.00
70,000.00
92,000.00
15,000.00
24,000.00
420,000.00
1,020,000.00
540,000.00
540,000.00
1,140,000.00
630,000.00
1,320,000.00
78,600.00
39,600.00
48,000.00
60,000.00
50,000.00
60,000.00
1,290,000.00
160,000.00
200,000.00
240,000.00
1,896,000.00
280,000.00
30,000.00
36,000.00
21,658.33
30,000.00
33,000.00
33,000.00
42,000.00
51,000.00
72,000.00

25,000.00
32,500.00
49,500.00
75,000.00
169,000.00
244,000.00
4,750.00
15,250.00
19,500.00
15,825.00
38,750.00
6,500.00
61,500.00

1,050,000.00
900,000.00
92,000.00
69,000.00
77,000.00
77,000.00
28,000.00
28,000.00
17,000.00
400.00
65,000.00
128,000.00
183,000.00

77,000.00
77,000.00
47,500.00
34,000.00
34,000.00
34,000.00
67,500.00
68,000.00
46,000.00
77,000.00
77,000.00
80,000.00
90,000.00
80,000.00
70,000.00
35,000.00
83,000.00
30,000.00
54,500.00
71,000.00
53,000.00
46,000.00
46,000.00
30,000.00
35,000.00
30,000.00
53,000.00
22,500.00
15,000.00
27,000.00
95,000.00
185,000.00
235,000.00
148,000.00
465,000.00
525,000.00
95,000.00
80,000.00
95,000.00
235,000.00
1,015,000.00
425,000.00
525,000.00
32,400.00
120,000.00
345,000.00
80,000.00

55,000.00
58,000.00
555,000.00
8,000.00
8,000.00
12,000.00
8,000.00
30,000.00
40,000.00
50,000.00
3,320.00
80.00
80.00
750.00
822,000.00
250,000.00
300,000.00
540,000.00
450,000.00
17,850.00
112,000.00
47,000.00
66,000.00
87,000.00
48,000.00
200,000.00
1,200.00
205,000.00
332,000.00
520,000.00
755,000.00
535,000.00
962,000.00
754,000.00
996,000.00
924,000.00
1,234,000.00
1,949,000.00
2,576,000.00
12,000.00
12,000.00
24,000.00
29,000.00
32,000.00
24,000.00
28,000.00
30,000.00
31,000.00
37,000.00
84,000.00
32,000.00
40,000.00
1,500.00
20,000.00
23,000.00
185,000.00
240,000.00
35,000.00
37,000.00
39,000.00

85,000.00
63,000.00
63,000.00
81,000.00
24,000.00
132,000.00
24,000.00
1,500,000.00
34,000.00
59,000.00

63,000.00
98,000.00
20,000.00
25,000.00
64,000.00
25,000.00
34,000.00
84,000.00
75,000.00
75,000.00
234,000.00
15,000.00
188,000.00
212,000.00
303,000.00
514,100.00
1,050,000.00
275,000.00
275,000.00
1,250,000.00
205,000.00
55,000.00
286,000.00
55,000.00
90,000.00
211,000.00
90,000.00
348,000.00
125,000.00
32,000.00
950,000.00
1,050,000.00
1,300,000.00
1,800,000.00
2,100,000.00
890,000.00
1,520,000.00
2,540,000.00
DAFTAR HARGA SATUAN PEKERJAAN BIDANG KECIPTAKAR

KODE
NO.
ANALISA

I A.2.2.1

1 A. 2.2.1.1
2 A. 2.2.1.2
3 A. 2.2.1.3
4 A. 2.2.1.4
5 A. 2.2.1.9
6 A. 2.2.1.10

II A.2.3.1

1 A.2.3.1.1
2 A.2.3.1.2
3 A.2.3.1.9
4 A.2.3.1.10
5 A.2.3.1.11
6 A.2.3.1.13

III A.3.2.1

1 A.3.2.1.4
2 A.3.2.1.9

IV A.4.1.1

1 A.4.1.1.4
2 A.4.1.1.7
3 A.4.1.1.17.p
4 A.4.1.1.17.u
5 A.4.1.1.20
6 A.4.1.1.21
7 A.4.1.1.22
8 A.4.1.1.23
9 A.4.1.1.24
10 A.4.1.1.25
11 A.4.1.1.26

VI A.4.2.1

1 A.4.2.1.11
2 A.4.2.1.12
3 A.4.2.1.13
4 A.4.2.1.20
5 A.4.2.1.21
6 A.4.2.1.22.p
7 A.4.2.1.22.j

VII A.4.4.1
1 A.4.4.1.5
2 A.4.4.1.8
3 A.4.4.1.11

VIII A.4.4.2

3 A.4.4.2.3
1 A.4.4.2.6
17 A.4.4.2.17
3 A.4.4.2.20
4 A.4.4.2.27

IX A.4.4.3

1 A.4.4.3.36
2 A.4.4.3.39
3 A.4.4.3.54

X A.4.5.1

1 A.4.5.1.7
2 A.4.5.1.10

XI A.4.5.2

1 A.4.5.2.43

XII A.4.6.1

1 A.4.6.1.8
22 A.4.6.1.22

XIII A.4.6.2

1 A.4.6.2.2
2 A.4.6.2.5
3 A.4.6.2.6
4 A.4.6.2.17

XIV A.4.7.1

1 A.4.7.1.10

XV A.5.1.1

1 A.5.1.1.1
2 A.5.1.1 5
3 A.5.1.1 12
4 A.5.1.1 14
5 A.5.1.1 19
6 A.5.1.1 22
7 A.5.1.1 23
8 A.5.1.1 27
9 A.5.1.1 31
10 A.5.1.1 32

XXI A.8.4.6

1 A.8.4.6.1
2 A.8.4.6.2
DAFTAR HARGA SATUAN PEKERJAAN BIDANG KECIPTAKARYAAN

SATUA
URAIAN PEKERJAAN
N

HARGA SATUAN PEKERJAAN PERSIAPAN

(K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter m2


(K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter m2
(K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter m2
Pengukuran dan pemasangan 1 m Bouwplank m'
(K3) Pembersihan 1 m2 lapangan dan perataan m2
(K3) Pembuatan 1 m2 steger/perancah dari bambu m2

HARGA SATUAN PEKERJAAN TANAH

Penggalian 1 m3 tanah biasa sedalam 1 m m3


Penggalian 1 m3 tanah biasa sedalam 2 m m3
Pengurugan kembali 1 m3 galian tanah m3
(K3) Pemadatan tanah 1 m3 tanah (per 20 cm) m3
Pengurugan 1 m3 dengan pasir urug m3
Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan m2

HARGA SATUAN PEKERJAAN PONDASI

Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3


(K3) Pemasangan 1 m3 batu kosong (anstamping) m3

HARGA SATUAN PEKERJAAN BETON

Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa slump (3-6) cm, w/c = 0,87 (K 100) m3
Membuat 1 m3 beton mutu fc = 19,3 Mpa (Setara K 225) m3
Pembesian 10 kg dengan besi polos 10 kg
Pembesian 10 kg dengan besi ulir 10 kg
(K3) Pemasangan 1 m2 bekisting untuk pondasi m2
(K3) Pemasangan 1 m2 bekisting untuk sloof m2
(K3) Pemasangan 1 m2 bekisting untuk kolom m2
(K3) Pemasangan 1 m2 bekisting untuk balok m2
(K3) Pemasangan 1 m2 bekisting untuk lantai m2
(K3) Pemasangan 1 m2 bekisting untuk dinding m2
(K3) Pemasangan 1 m2 bekisting untuk tangga m2

HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Pemasangan 1 m kusen pintu alluminium 4" natural / silver m


Pemasangan 1 m2 pintu alluminium strip lebar 8 cm m2
Pemasangan 1 m2 pintu kaca rangka alluminium m2
Pemasangan 1 m2 rangka besi hollow 40x40 mm, modul 60 x120 cm, untuk partisi m2
Pemasangan 1 m2 rangka besi hollow 40x40 mm, modul 60 x 60 cm, untuk plafon m2
(K3) Pemasangan 1 m2 atap pelana rangka atap baja canal dingin profil C75 m2
(K3) Pemasangan 1 m2 atap jurai rangka atap baja canal dingin profil C75 m2

HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan 1 m2 Dinding Bata Merah tebal 1 batu campuran 1SP : 6PP m2
Pemasangan 1 m2 dinding bata merah tebal batu campuran 1SP : 3PP m2
Pemasangan 1 m2 dinding bata merah tebal batu campuran 1SP : 6PP m2

HARGA SATUAN PEKERJAAN PLESTERAN

Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15 mm m2


Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm m2
Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm m2
Pemasangan 1 m plesteran skoning 1SP : 3PP lebar 10 cm m'
Pemasangan 1 m2 acian m2

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

Pemasangan 1 m2 lantai keramik ukuran 20 cm x 20 cm m2


Pemasangan 1 m plint keramik ukuran 10 cm x 20 cm m'
Pemasangan 1 m2 dinding keramik 20 cm x 20 cm m2

SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240) cm, tebal 9 mm m2


Pemasangan 1 m2 rangka langit-langit besi hollow 40.40.1,1 mm (A.4.2.1.21) m2

HARGA SATUAN PEKERJAAN PENUTUP ATAP

Pemasangan 1 m2 alumunium foil/sisalation m2

HARGA SATUAN PEKERJAAN KAYU

Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm m2
Pemasangan 1 m lisplank ukuran (3 x 30) cm, kayu kelas kelas II (Bengkirai) m'

HARGA SATUAN PEKERJAAN KUNCI DAN KACA

Pemasangan 1 buah kunci tanam biasa buah


Pemasangan 1 buah engsel pintu buah
Pemasangan 1 buah engsel jendela kupu-kupu buah
Pemasangan 1 m2 kaca tebal 5 mm m2

HARGA SATUAN PEKERJAAN PENGECATAN

Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) m2

HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

(K3) Pemasangan 1 buah closet duduk/monoblock buah


(K3) Pemasangan 1 buah wastafel buah
Pemasangan 1 buah bak cuci piring stainless steel buah
Pemasangan 1 buah floor drain buah
Pemasangan 1 buah kran diameter atau buah
Pemasangan 1 m pipa galvanis diameter 1 m'
Pemasangan 1 m pipa galvanis diameter 3 m'
Pemasangan 1 m pipa PVC tipe AW diameter 1 m'
Pemasangan 1 m pipa PVC tipe AW diameter 3 m'
Pemasangan 1 m pipa PVC tipe AW diameter 4 m'

HARGA SATUAN PEKERJAAN ELEKTRIKAL

(K3) Pemasangan 1 buah titik lampu buah


(K3) Pemasangan 1 buah MCB buah
AAN

HARGA SATUAN
(Rp)

587,419.25
694,812.95
249,908.08
146,017.75
12,485.00
339,496.66

61,857.50
75,591.00
20,619.17
50,545.33
297,143.00
41,881.50

1,055,635.13
614,006.63

1,082,905.90
1,295,798.87
141,517.48
153,434.98
259,915.00
282,615.00
522,582.38
541,309.88
704,182.38
601,918.88
476,359.50

122,848.43
853,274.27
489,031.78
200,231.03
132,055.63
188,723.06
208,135.45
253,105.00
125,154.18
119,626.73

64,934.94
61,411.90
82,064.13
58,588.70
33,255.50

198,607.98
96,958.51
242,543.83

48,978.66
261,162.48

28,732.53

742,658.88
171,668.75

142,839.75
45,444.27
39,373.15
142,032.77

38,949.80

1,894,031.25
1,667,221.93
1,308,825.25
74,853.25
148,741.75
161,306.20
334,138.33
25,211.19
90,215.48
130,238.41

335,627.50
251,528.00
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A. 2.2.1.4 Pengukuran dan pemasangan 1 m Bouwplank


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 70,000.00
Tukang Kayu Kasar L.02 OH 0.1000 85,000.00
Kepala Tukang Kayu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kaso 5/7 Kruing m3 0.0120 5,500,000.00
Paku 2"- 3" Kg 0.0200 15,000.00
Papan Kayu Kruing m3 0.0070 6,500,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A. 2.2.1.9 (K3) Pembersihan 1 m2 lapangan dan perataan


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 70,000.00
Mandor L.04 OH 0.0500 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

7,000.00
8,500.00
950.00
400.00
16,850.00

66,000.00
300.00
45,500.00
111,800.00

128,650.00
17,367.75
146,017.75

Jumlah Harga (Rp)

7,000.00
4,000.00
11,000.00

11,000.00
1,485.00
12,485.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7500 70,000.00
Mandor L.04 OH 0.0250 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.2 Penggalian 1 m3 tanah biasa sedalam 2 m


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 70,000.00
Mandor L.04 OH 0.0450 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 70,000.00
Mandor L.04 OH 0.0083 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.10 (K3) Pemadatan tanah 1 m3 tanah (per 20 cm)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 70,000.00
Mandor L.04 OH 0.0500 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Stamper Jam 0.1667 33,200
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 70,000.00
Mandor L.04 OH 0.0100 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pasir urug 1.2000 200,000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.2.3.1.13 Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 70,000.00
Mandor L.04 OH 0.0150 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Ijuk Kg 6.0000 4,200.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

52,500.00
2,000.00
54,500.00

54,500.00
7,357.50
61,857.50

Jumlah Harga (Rp)

63,000.00
3,600.00
66,600.00

66,600.00
8,991.00
75,591.00

Jumlah Harga (Rp)

17,500.00
666.67
18,166.67
18,166.67
2,452.50
20,619.17

Jumlah Harga (Rp)

35,000.00
4,000.00
39,000.00

5,533.33
5,533.33
44,533.33
6,012.00
50,545.33

Jumlah Harga (Rp)

21,000.00
800.00
21,800.00

240,000.00
240,000.00

261,800.00
35,343.00
297,143.00
Jumlah Harga (Rp)

10,500.00
1,200.00
11,700.00

25,200.00
25,200.00

36,900.00
4,981.50
41,881.50
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.4 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 70,000.00
Tukang Batu Kasar L.02 OH 0.7500 85,000.00
Kepala Tukang L.03 OH 0.0750 95,000.00
Batu
Mandor L.04 OH 0.0750 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Batu belah m3 1.2000 300,000.00
Semen Portland Kg 117.0000 1,400.00
Pasir pasang m3 0.5610 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.3.2.1.9 (K3) Pemasangan 1 m3 batu kosong (anstamping)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7800 70,000.00
Tukang Batu Kasar L.02 OH 0.3900 85,000.00
Kepala Tukang L.03 OH 0.0390 95,000.00
Batu
Mandor L.04 OH 0.0390 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Batu belah m3 1.2000 300,000.00
Pasir urug m3 0.4320 200,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

105,000.00
63,750.00
7,125.00
6,000.00
181,875.00

360,000.00
163,800.00
224,400.00
748,200.00

930,075.00
125,560.13
1,055,635.13

Jumlah Harga (Rp)

54,600.00
33,150.00
3,705.00
3,120.00
94,575.00

360,000.00
86,400.00
446,400.00

540,975.00
73,031.63
614,006.63
A.4.1.1 HARGA SATUAN PEKERJAAN BETON

A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa slump (3-6) cm, w/c = 0,87 (K 1
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 70,000.00
Tukang batu kasar L.02 OH 0.2000 85,000.00
Kepala tukang batu L.03 OH 0.0200 95,000.00
Mandor L.04 OH 0.0600 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 230.0000 1,400.00
Pasir beton kg 893.0000 285.71
Kerikil (Maks 30 mm) kg 1,027.0000 259.26
Air Liter 200.0000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.7 Membuat 1 m3 beton mutu fc = 19,3 Mpa (Setara K 225)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 70,000.00
Tukang batu kasar L.02 OH 0.2750 85,000.00
Kepala tukang batu L.03 OH 0.0280 95,000.00
Mandor L.04 OH 0.0830 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 371.0000 1,400.00
Pasir beton kg 698.0000 285.71
Kerikil (Maks 30 mm) kg 1,047.0000 259.26
Air Liter 215.0000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.17.p Pembesian 10 kg dengan besi polos


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 70,000.00
Tukang besi L.02 OH 0.0700 90,000.00
Kepala Tukang Besi L.03 OH 0.0070 95,000.00
Mandor L.04 OH 0.0040 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Besi beton polos kg 10.5000 10,500.00
Kawat beton kg 0.1500 15,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.17.u Pembesian 10 kg dengan besi ulir


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 70,000.00
Tukang besi L.02 OH 0.0700 90,000.00
Kepala Tukang Besi L.03 OH 0.0070 95,000.00
Mandor L.04 OH 0.0040 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Besi beton ulir kg 10.5000 11,500.00
Kawat beton kg 0.1500 15,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 70,000.00
Tukang Kayu Kasar L.02 OH 0.2600 85,000.00
Kepala Tukang Kayu L.03 OH 0.0260 95,000.00
Mandor L.04 OH 0.0260 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0400 4,000,000.00
Paku 5 cm - 10 cm kg 0.3000 15,000.00
Minyak bekisting Liter 0.1000 14,500.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 70,000.00
Tukang Kayu Kasar L.02 OH 0.2600 85,000.00
Kepala Tukang Kayu L.03 OH 0.0260 95,000.00
Mandor L.04 OH 0.0260 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0450 4,000,000.00
Paku 5 cm - 10 cm kg 0.3000 15,000.00
Minyak bekisting Liter 0.1000 14,500.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0400 4,000,000.00
Paku 5 cm - 12 cm kg 0.4000 15,000.00
Minyak bekisting Liter 0.2000 14,500.00
Balok Kayu Kruing m3 0.0150 5,500,000.00
Plywood tebal 9 mm Lbr 0.3500 140,000.00
Dolken kayu 8-10/400 cm Batang 2.0000 40,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.4.1.1.23 (K3) Pemasangan 1 m2 bekisting untuk balok
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0400 4,000,000.00
Paku 5 cm - 12 cm kg 0.4000 15,000.00
Minyak bekisting Liter 0.2000 14,500.00
Balok Kayu Kruing m3 0.0180 5,500,000.00
Plywood tebal 9 mm Lbr 0.3500 140,000.00
Dolken kayu 8-10/400 cm Batang 2.0000 40,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk lantai


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0400 4,000,000.00
Paku 5 cm - 12 cm kg 0.4000 15,000.00
Minyak bekisting Liter 0.2000 14,500.00
Balok Kayu Kruing m3 0.0150 5,500,000.00
Plywood tebal 9 mm Lbr 0.3500 140,000.00
Dolken kayu 8-10/400 cm Batang 6.0000 40,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.25 (K3) Pemasangan 1 m2 bekisting untuk dinding


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0300 4,000,000.00
Paku 5 cm - 12 cm kg 0.4000 15,000.00
Minyak bekisting Liter 0.2000 14,500.00
Balok Kayu Kruing m3 0.0200 5,500,000.00
Plywood tebal 9 mm Lbr 0.3500 140,000.00
Dolken kayu 8-10/400 cm Batang 3.0000 40,000.00
Penjaga jarak bekisting/spacer Buah 4.0000 10,600.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.1.26 (K3) Pemasangan 1 m2 bekisting untuk tangga


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 70,000.00
Tukang Kayu Kasar L.02 OH 0.3300 85,000.00
Kepala Tukang Kayu L.03 OH 0.0330 95,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan Kayu Sengon m3 0.0300 4,000,000.00
Paku 5 cm - 12 cm kg 0.4000 15,000.00
Minyak bekisting Liter 0.1500 14,500.00
Balok Kayu Kruing m3 0.0150 5,500,000.00
Plywood tebal 9 mm Lbr 0.3500 140,000.00
Dolken kayu 8-10/400 cm Batang 2.0000 40,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
w/c = 0,87 (K 100)
Jumlah Harga
(Rp)

84,000.00
17,000.00
1,900.00
4,800.00
107,700.00

322,000.00
255,142.86
266,259.26
3,000.00
846,402.12

954,102.12
128,803.79
1,082,905.90

Jumlah Harga
(Rp)

115,500.00
23,375.00
2,660.00
6,640.00
148,175.00

519,400.00
199,428.57
271,444.44
3,225.00
993,498.02

1,141,673.02
154,125.86
1,295,798.87

Jumlah Harga
(Rp)

4,900.00
6,300.00
665.00
320.00
12,185.00

110,250.00
2,250.00
112,500.00
124,685.00
16,832.48
141,517.48

Jumlah Harga
(Rp)

4,900.00
6,300.00
665.00
320.00
12,185.00

120,750.00
2,250.00
123,000.00

135,185.00
18,249.98
153,434.98

Jumlah Harga
(Rp)

36,400.00
22,100.00
2,470.00
2,080.00
63,050.00

160,000.00
4,500.00
1,450.00
165,950.00

229,000.00
30,915.00
259,915.00
Jumlah Harga
(Rp)

36,400.00
22,100.00
2,470.00
2,080.00
63,050.00

180,000.00
4,500.00
1,450.00
185,950.00

249,000.00
33,615.00
282,615.00

Jumlah Harga
(Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

160,000.00
6,000.00
2,900.00
82,500.00
49,000.00
80,000.00
380,400.00

460,425.00
62,157.38
522,582.38
Jumlah Harga
(Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

160,000.00
6,000.00
2,900.00
99,000.00
49,000.00
80,000.00
396,900.00

476,925.00
64,384.88
541,309.88

Jumlah Harga
(Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

160,000.00
6,000.00
2,900.00
82,500.00
49,000.00
240,000.00
540,400.00

620,425.00
83,757.38
704,182.38

Jumlah Harga
(Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

120,000.00
6,000.00
2,900.00
110,000.00
49,000.00
120,000.00
42,400.00
450,300.00

530,325.00
71,593.88
601,918.88

Jumlah Harga
(Rp)

46,200.00
28,050.00
3,135.00
2,640.00
80,025.00

120,000.00
6,000.00
2,175.00
82,500.00
49,000.00
80,000.00
339,675.00

419,700.00
56,659.50
476,359.50
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Untuk produksi pracetak bisa dilakukan dipabrik (cor di plant) atau di lapangan (cast inplace). Inde
ada dalam pedoman
A.4.1.2.1 ini hanya1 m2
(K3) Pembuatan untuk pekerjaan
lahan produksiproduksi yang
tebal 8 cm dilakukan
beton di MPa,
fc 14,5 lapangan,
slumpterutama
(120 20
analisa cetakan (bekisting) pracetak baik untuk komponen kolom, balok dan pelat.
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1320 70,000.00
Tukang batu kasar L.02 OH 0.0220 85,000.00
Kepala tukang batu L.03 OH 0.0020 95,000.00
Mandor L.04 OH 0.0070 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 26.0800 1,400.00
Pasir beton Kg 60.8000 285.71
Kerikil (maks 30 mm) Kg 82.3200 259.26
Air L 17.2000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.2 (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton fc 14,5 MPa, slump (120 2
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1650 70,000.00
Tukang batu kasar L.02 OH 0.0280 85,000.00
Kepala tukang batu L.03 OH 0.0030 95,000.00
Mandor L.04 OH 0.0080 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 32.6000 1,400.00
Pasir beton Kg 76.0000 285.71
Kerikil (maks 30 mm) Kg 102.9000 259.26
Air L 21.5000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.3 (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton fc 14,5 MPa, slump (120 2
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1980 70,000.00
Tukang batu kasar L.02 OH 0.0330 85,000.00
Kepala tukang batu L.03 OH 0.0030 95,000.00
Mandor L.04 OH 0.0100 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 39.1200 1,400.00
Pasir beton Kg 91.2000 285.71
Kerikil (maks 30 mm) Kg 123.4800 259.26
Air L 25.8000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.4 (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton fc 14,5 MPa, slump (120 2
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2480 70,000.00
Tukang batu kasar L.02 OH 0.0410 85,000.00
Kepala tukang batu L.03 OH 0.0040 95,000.00
Mandor L.04 OH 0.0130 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 48.9000 1,400.00
Pasir beton Kg 114.0000 285.71
Kerikil (maks 30 mm) Kg 154.3500 259.26
Air L 32.2500 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.5 Pembuatan 1 m2 bekisting untuk pelat beton pracetak (5 kali pakai)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0070 70,000.00
Tukang batu kasar L.02 OH 0.0760 85,000.00
Kepala tukang batu L.03 OH 0.0080 95,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Lantai kerja t = 10 cm m3 0.0080 123,952.85
Besi hollow (50 x 50 x 3) mm Kg 9.3940 14,000.00
Kaso 5/7 Kruing m3 0.0050 5,500,000.00
Phenol film 12 mm Lbr 0.0800 160,000.00
Minyak cetakan (bekisting) Ltr 0.2000 14,500.00
Dinabolt 12 mm (10 cm - 15 cm) buah 3.8820 2,500.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.4.1.2.6 Pembuatan 1 m2 bekisting untuk balok beton pracetak (10-12 kali pakai)
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0040 70,000.00
Tukang kayu kasar L.02 OH 0.0380 85,000.00
Kepala tukang kayu L.03 OH 0.0040 95,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kaso 5/7 Kruing m3 0.0050 5,500,000.00
Phenol film 12 mm Lbr 0.0430 160,000.00
Minyak cetakan (bekisting) Ltr 0.2000 14,500.00
Paku 5 cm - 7 cm kg 0.0460 15,000.00
Dinabolt 12 mm (10 cm - 15 cm) buah 0.6930 2,500.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.7 Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai)
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0040 70,000.00
Tukang kayu kasar L.02 OH 0.0380 85,000.00
Kepala tukang kayu L.03 OH 0.0040 95,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kaso 5/7 Kruing m3 0.0040 5,500,000.00
Phenol film 12 mm Lbr 0.0480 160,000.00
Minyak cetakan (bekisting) ltr 0.2000 14,500.00
Paku 5 cm - 7 cm Kg 0.0460 15,000.00
Dinabolt 12 mm (10 cm - 15 cm) buah 0.6930 2,500.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.8 Pemasangan dan membuka bekisting 1 buah komponen pelat beton pracetak
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0530 70,000.00
Tukang kayu kasar L.02 OH 0.0180 85,000.00
Kepala tukang kayu L.04 OH 0.0050 95,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 13,5 %) 13,5% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.9 Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0890 70,000.00
Tukang kayu kasar L.02 OH 0.0300 85,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.10 Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0710 70,000.00
Tukang kayu kasar L.02 OH 0.0240 85,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.11 Penuangan/menebar beton 1 m3 komponen untuk pelat pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0640 70,000.00
Tukang batu kasar L.02 OH 0.2440 85,000.00
Tukang vibrator L.02 OH 0.1280 70,000.00
Kepala tukang batu L.03 OH 0.0340 95,000.00
Mandor L.04 OH 0.0730 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.12 Penuangan/menebar beton 1 m3 komponen untuk balok pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0690 70,000.00
Tukang batu kasar L.02 OH 0.2420 85,000.00
Tukang vibrator L.02 OH 0.1380 70,000.00
Kepala tukang batu L.03 OH 0.0370 95,000.00
Mandor L.04 OH 0.0730 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.13 Penuangan/menebar beton 1 m3 komponen kolom pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0610 70,000.00
Tukang batu kasar L.02 OH 0.2130 85,000.00
Tukang vibrator L.02 OH 0.1220 70,000.00
Kepala tukang batu L.03 OH 0.0330 95,000.00
Mandor/Supervisor/Penyelia L.04 OH 0.0730 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.14 Ereksi 1 buah komponen untuk pelat pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Operator crane L.08 OH 0.0670 150,000.00
Pembantu operator crane L.09 OH 0.0670 60,000.00
Pekerja L.01 OH 0.0670 70,000.00
Tukang batu kasar L.02 OH 0.0670 85,000.00
Tukang ereksi L.02 OH 0.1340 70,000.00
Kepala tukang batu L.03 OH 0.0670 95,000.00
Mandor L.04 OH 0.0670 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Solar Ltr 6.6760 13,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.0670 3,525,746.00
Sewa pipe support buah 1.1000 302.50
hari JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Indeks kenaikan lantai ereksi komponen untuk


Indekspelat pracetak
kenaikan
Lantai lantai ereksi Lantai
1 pelat
1.000 13.00
2 1.000 14.00
3 1.000 15.00
4 1.000 16.00
5 1.000 17.00
6 1.000 18.00
7 1.000 19.00
8 1.018 20.00
9 1.037 21.00
10 1.055 22.00
11 1.075 23.00
12 1.094 24.00

A.4.1.2.15 Ereksi 1 buah komponen untuk balok pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Operator crane L.08 OH 0.0610 150,000.00
Pembantu operator crane L.09 OH 0.0610 60,000.00
Pekerja L.01 OH 0.0610 70,000.00
Tukang batu kasar L.02 OH 0.0610 85,000.00
Tukang ereksi L.02 OH 0.1220 70,000.00
Kepala tukang batu L.03 OH 0.0610 95,000.00
Mandor L.04 OH 0.0610 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Solar Ltr 6.1100 13,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.0610 3,525,746.00
Sewa scaffolding unit hari 1.1000 3,000.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Indeks kenaikan lantai ereksi komponen untuk balok pracetak


Lantai Indeks kenaikan Lantai
1 lantai ereksi
1.000 13.00
2 balok
1.000 14.00
3 1.000 15.00
4 1.000 16.00
5 1.000 17.00
6 1.000 18.00
7 1.000 19.00
8 1.011 20.00
9 1.022 21.00
10 1.034 22.00
11 1.045 23.00
12 1.057 24.00

A.4.1.2.16 Ereksi 1 buah komponen untuk kolom pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Operator crane L.08 OH 0.0830 150,000.00
Pembantu operator crane L.09 OH 0.0830 60,000.00
Pekerja L.01 OH 0.0830 70,000.00
Tukang batu kasar L.02 OH 0.0830 85,000.00
Tukang ereksi L.02 OH 0.1660 70,000.00
Kepala tukang batu L.03 OH 0.0830 95,000.00
Mandor L.04 OH 0.0830 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Solar Ltr 8.2770 13,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.0830 3,525,746.00
Sewa scaffolding unit hari 2.2000 3,000.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Indeks kenaikan lantai ereksi komponen untuk kolom pracetak


Lantai Indeks kenaikan Lantai
1 lantai ereksi
1.000 13.00
2 kolom
1.000 14.00
3 1.000 15.00
4 1.000 16.00
5 1.000 17.00
6 1.000 18.00
7 1.000 19.00
8 1.025 20.00
9 1.051 21.00
10 1.078 22.00
11 1.105 23.00
12 1.133 24.00

A.4.1.2.17 Langsir 1 buah komponen untuk pelat pracetak ( 20 m)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Operator crane L.08 OH 0.0190 150,000.00
Pembantu operator crane L.09 OH 0.0190 60,000.00
Pekerja L.01 OH 0.0190 70,000.00
Tukang batu kasar L.02 OH 0.0380 85,000.00
JUMLAH TENAGA KERJA
B BAHAN
Solar Ltr 1.8970 13,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.0190 3,525,746.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.18 Langsir 1 buah komponen untuk balok pracetak ( 20 m)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Operator crane L.08 OH 0.0190 150,000.00
Pembantu operator crane L.09 OH 0.0190 60,000.00
Pekerja L.01 OH 0.0190 70,000.00
Tukang batu kasar L.02 OH 0.0380 85,000.00
JUMLAH TENAGA KERJA
B BAHAN
Solar Ltr 1.8970 13,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.0190 3,525,746.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.19 Langsir 1 buah komponen untuk kolom pracetak ( 20 m)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Operator crane L.08 OH 0.0190 150,000.00
Pembantu operator crane L.09 OH 0.0190 60,000.00
Pekerja L.01 OH 0.0190 70,000.00
Tukang batu kasar L.02 OH 0.0380 85,000.00
JUMLAH TENAGA KERJA
B BAHAN
Solar Ltr 1.8970 13,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.0190 3,525,746.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.20 Bahan 1 m3 grout campuran


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
JUMLAH TENAGA KERJA
B BAHAN
Semen grout Kg 1,200.0000 2,430.00
Screening Kg 650.0000 259.26
Air Ltr 350.0000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.21 Bahan 1 m3 grout (tidak campuran)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
JUMLAH TENAGA KERJA
B BAHAN
Semen grout Kg 1,850.0000 2,430.00
Air Ltr 400.0000 15.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.22 Upah 1 titik pekerjaan grout pada joint beton pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Tukang batu kasar L.02 OH 0.3670 85,000.00
Kepala tukang batu L.03 OH 0.0740 95,000.00
Mandor L.04 OH 0.0370 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.23 Pemasangan 1 titik bekisting joint pracetak


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1470 70,000.00
Tukang kayu kasar L.02 OH 0.1470 85,000.00
Kepala tukang kayu L.03 OH 0.0150 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kaso 5/7 Kruing m3 0.0120 5,500,000.00
Papan Kayu Sengon m3 0.0040 4,000,000.00
Paku 5 cm - 7 cm Kg 0.2640 15,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.1.2.24 Upah 1 titik joint dengan sling


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2200 70,000.00
Tukang kayu kasar L.02 OH 0.0220 85,000.00
Tukang besi L.02 OH 0.2200 90,000.00
Mandor L.04 OH 0.0110 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
st inplace). Indeks yang
ngan,
slumpterutama
(120 20)untuk
mm
Jumlah Harga
(Rp)

9,240.00
1,870.00
190.00
560.00
11,860.00

36,512.00
17,371.43
21,342.22
258.00
75,483.65

87,343.65
11,791.39
99,135.04

a, slump (120 20) mm


Jumlah Harga
(Rp)

11,550.00
2,380.00
285.00
640.00
14,855.00

45,640.00
21,714.29
26,677.78
322.50
94,354.56

109,209.56
14,743.29
123,952.85

a, slump (120 20) mm


Jumlah Harga
(Rp)

13,860.00
2,805.00
285.00
800.00
17,750.00
54,768.00
26,057.14
32,013.33
387.00
113,225.48

130,975.48
17,681.69
148,657.17

a, slump (120 20) mm


Jumlah Harga
(Rp)

17,360.00
3,485.00
380.00
1,040.00
22,265.00

68,460.00
32,571.43
40,016.67
483.75
141,531.85

163,796.85
22,112.57
185,909.42

Jumlah Harga
(Rp)

490.00
6,460.00
760.00
80.00
7,790.00

991.62
131,516.00
27,500.00
12,800.00
2,900.00
9,705.00
185,412.62

193,202.62
26,082.35
219,284.98
Jumlah Harga
(Rp)

280.00
3,230.00
380.00
80.00
3,970.00

27,500.00
6,880.00
2,900.00
690.00
1,732.50
39,702.50

43,672.50
5,895.79
49,568.29

Jumlah Harga
(Rp)

280.00
3,230.00
380.00
80.00
3,970.00

22,000.00
7,680.00
2,900.00
690.00
1,732.50
35,002.50

38,972.50
5,261.29
44,233.79

Jumlah Harga
(Rp)

3,710.00
1,530.00
475.00
5,715.00
5,715.00
771.53
6,486.53

Jumlah Harga
(Rp)

6,230.00
2,550.00
400.00
9,180.00

9,180.00
1,239.30
10,419.30

eton pracetak
Jumlah Harga
(Rp)

4,970.00
2,040.00
400.00
7,410.00

7,410.00
1,000.35
8,410.35

Jumlah Harga
(Rp)

4,480.00
20,740.00
8,960.00
3,230.00
5,840.00
43,250.00

43,250.00
5,838.75
49,088.75

Jumlah Harga
(Rp)

4,830.00
20,570.00
9,660.00
3,515.00
5,840.00
44,415.00

44,415.00
5,996.03
50,411.03

Jumlah Harga
(Rp)

4,270.00
18,105.00
8,540.00
3,135.00
5,840.00
39,890.00

39,890.00
5,385.15
45,275.15

Jumlah Harga
(Rp)

10,050.00
4,020.00
4,690.00
5,695.00
9,380.00
6,365.00
5,360.00
45,560.00

86,788.00
86,788.00
236,224.98
332.75
236,557.73

368,905.73
49,802.27
418,708.01

Indeks kenaikan
lantai ereksi pelat
1.11
1.13
1.16
1.18
1.20
1.22
1.24
1.26
1.29
1.31
1.33
1.36

Jumlah Harga
(Rp)

9,150.00
3,660.00
4,270.00
5,185.00
8,540.00
5,795.00
4,880.00
41,480.00

79,430.00
79,430.00

215,070.51
3,300.00
218,370.51

339,280.51
45,802.87
385,083.37

Indeks kenaikan
lantai ereksi balok
1.07
1.08
1.09
1.10
1.12
1.13
1.14
1.15
1.17
1.18
1.19
1.21

Jumlah Harga
(Rp)

12,450.00
4,980.00
5,810.00
7,055.00
11,620.00
7,885.00
6,640.00
56,440.00

107,601.00
107,601.00

292,636.92
6,600.00
299,236.92

463,277.92
62,542.52
525,820.44

Indeks kenaikan
lantai ereksi
1.16
kolom 1.19
1.22
1.25
1.28
1.32
1.35
1.38
1.42
1.46
1.49
1.53

Jumlah Harga
(Rp)

2,850.00
1,140.00
1,330.00
3,230.00
8,550.00

24,661.00
24,661.00
66,989.17
66,989.17

100,200.17
13,527.02
113,727.20

Jumlah Harga
(Rp)

2,850.00
1,140.00
1,330.00
3,230.00
8,550.00

24,661.00
24,661.00

66,989.17
66,989.17

100,200.17
13,527.02
113,727.20

Jumlah Harga
(Rp)

2,850.00
1,140.00
1,330.00
3,230.00
8,550.00

24,661.00
24,661.00

66,989.17
66,989.17

100,200.17
13,527.02
113,727.20

Jumlah Harga
(Rp)

2,916,000.00
168,518.52
5,250.00
3,089,768.52
3,089,768.52
417,118.75
3,506,887.27

Jumlah Harga
(Rp)

4,495,500.00
6,000.00
4,501,500.00

4,501,500.00
607,702.50
5,109,202.50

Jumlah Harga
(Rp)

31,195.00
7,030.00
2,960.00
41,185.00

41,185.00
5,559.98
46,744.98

Jumlah Harga
(Rp)

10,290.00
12,495.00
1,425.00
400.00
24,610.00

66,000.00
16,000.00
3,960.00
85,960.00
110,570.00
14,926.95
125,496.95

Jumlah Harga
(Rp)

15,400.00
1,870.00
19,800.00
880.00
37,950.00

37,950.00
5,123.25
43,073.25
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.12 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 70,000.00
Tukang Allumunium L.03 OH 0.0850 90,000.00
Kepala Tukang Alumunium L.03 OH 0.0085 95,000.00
Mandor L.04 OH 0.0042 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Profil Alluminium m 4.4000 60,000.00
Alluminium strip m 14.6000 32,400.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alluminium


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 70,000.00
Tukang Allumunium L.03 OH 0.0850 90,000.00
Kepala Tukang Alumunium L.03 OH 0.0090 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pintu alluminium m 4.4000 60,000.00
Profil kaca m 4.5000 32,400.00
Sealant Tube 0.2700 23,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 40x40 mm, modul 60 x120 cm, untuk partis
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 70,000.00
Tukang Las Biasa L.02 OH 0.2500 70,000.00
Kepala Tukang Las Biasa L.03 OH 0.0250 95,000.00
Mandor L.04 OH 0.0130 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Hollow Meni 40 x 40 x 1,1 mm M1 5.0000 23,000.00
100% x
Assesoris (perkuatan, las dll) Ls 23,000.00
rangka
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 40x40 mm, modul 60 x 60 cm, untuk plafon
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 70,000.00
Tukang Besi L.02 OH 0.3500 90,000.00
Kepala Tukang Besi L.03 OH 0.0350 95,000.00
Mandor L.04 OH 0.0180 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Hollow Galvanis 40 x 40 x 0,35 mm M1 6.6667 7,250.00
Assesoris (perkuatan, las dll) Ls 100% x rangka 7,250.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.22.p (K3) Pemasangan 1 m2 atap pelana rangka atap baja canal dingin profil C75
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7340 70,000.00
Tukang Besi L.02 OH 0.7340 90,000.00
Kepala Tukang Besi L.03 OH 0.0730 95,000.00
Mandor L.04 OH 0.0370 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canal dingin C75 M1 3.0650 11,550.00
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10.0000 35,400.75
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.22.j (K3) Pemasangan 1 m2 atap jurai rangka atap baja canal dingin profil C75
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7604 70,000.00
Tukang besi L.02 OH 0.7604 90,000.00
Kepala Tukang Besi L.03 OH 0.0760 95,000.00
Mandor L.04 OH 0.0380 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canal dingin C75 M1 4.0500 11,550.00
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10.0000 46,777.50
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

5,950.00
7,650.00
807.50
336.00
14,743.50

264,000.00
473,040.00
737,040.00

751,783.50
101,490.77
853,274.27

Jumlah Harga
(Rp)

5,950.00
7,650.00
855.00
400.00
14,855.00

264,000.00
145,800.00
6,210.00
416,010.00

430,865.00
58,166.78
489,031.78

cm, untuk partisi


Jumlah Harga
(Rp)

17,500.00
17,500.00
2,375.00
1,040.00
38,415.00

115,000.00
23,000.00
138,000.00
176,415.00
23,816.03
200,231.03

cm, untuk plafon


Jumlah Harga
(Rp)

24,500.00
31,500.00
3,325.00
1,440.00
60,765.00

48,333.58
7,250.00

55,583.58

116,348.58
15,707.06
132,055.63

profil C75
Jumlah Harga
(Rp)

51,380.00
66,060.00
6,935.00
2,960.00
127,335.00

35,400.75
35,400.75

3,540.08
3,540.08

166,275.83
22,447.24
188,723.06

rofil C75
Jumlah Harga
(Rp)

53,228.00
68,436.00
7,220.00
3,040.00
131,924.00

46,777.50
46,777.50

4,677.75
4,677.75

183,379.25
24,756.20
208,135.45
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.8 Pemasangan 1 m2 dinding bata merah tebal batu campuran 1SP : 3PP
Uraian Kode Satuan Koefisien Harga Satuan
No (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 70,000.00
Tukang Batu Halus L.02 OH 0.1000 90,000.00
Kepala Tukang Batu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0150 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bata merah buah 70.0000 600.00
Semen Portland Kg 14.3700 1,400.00
Pasir pasang m3 0.0400 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.1.11 Pemasangan 1 m2 dinding bata merah tebal batu campuran 1SP : 6PP
Uraian Kode Satuan Koefisien Harga Satuan
No (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 70,000.00
Tukang Batu Halus L.02 OH 0.1000 90,000.00
Kepala Tukang Batu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0150 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bata merah buah 70.0000 600.00
Semen Portland Kg 8.3200 1,400.00
Pasir pasang m3 0.0490 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
1SP : 3PP
Jumlah Harga
(Rp)

21,000.00
9,000.00
950.00
1,200.00
32,150.00

42,000.00
20,118.00
16,000.00
78,118.00

110,268.00
14,886.18
125,154.18

1SP : 6PP
Jumlah Harga
(Rp)

21,000.00
9,000.00
950.00
1,200.00
32,150.00

42,000.00
11,648.00
19,600.00
73,248.00

105,398.00
14,228.73
119,626.73
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A.4.4.2.6 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 70,000.00
Tukang Batu Halus L.03 OH 0.1500 90,000.00
Kepala Tukang Batu L.03 OH 0.0150 95,000.00
Mandor L.04 OH 0.0150 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 4.4160 1,400.00
Pasir Pasang m3 0.0270 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.2.14 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 70,000.00
Tukang Batu Halus L.03 OH 0.2000 90,000.00
Kepala Tukang Batu L.03 OH 0.0200 95,000.00
Mandor L.04 OH 0.0130 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 10.3680 1,400.00
Pasir Pasang m3 0.0310 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.2.20 Pemasangan 1 m plesteran skoning 1SP : 3PP lebar 10 cm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 70,000.00
Tukang Batu Halus L.03 OH 0.4000 90,000.00
Kepala Tukang Batu L.03 OH 0.0400 95,000.00
Mandor L.04 OH 0.0040 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 0.5000 1,400.00
Pasir pasang m3 0.0130 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.2.27 Pemasangan 1 m2 acian


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 70,000.00
Tukang Batu Halus L.03 OH 0.1000 90,000.00
Kepala Tukang Batu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0100 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen PC Kg 3.2500 1,400.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 13,5 %) 13,5% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

21,000.00
13,500.00
1,425.00
1,200.00
37,125.00

6,182.40
10,800.00
16,982.40

54,107.40
7,304.50
61,411.90

Jumlah Harga (Rp)

18,200.00
18,000.00
1,900.00
1,040.00
39,140.00

14,515.20
12,400.00
26,915.20

66,055.20
8,917.45
74,972.65

Jumlah Harga (Rp)

5,600.00
36,000.00
3,800.00
320.00
45,720.00

700.00
5,200.00
5,900.00

51,620.00
6,968.70
58,588.70

Jumlah Harga (Rp)

14,000.00
9,000.00
950.00
800.00
24,750.00

4,550.00
4,550.00

29,300.00
3,955.50
33,255.50
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
A.4.4.3.36 Pemasangan 1 m2 lantai keramik ukuran 20 cm x 20 cm
No Uraian Kode Satuan Koefisien

A TENAGA
Pekerja L.01 OH 0.7000
Tukang batu halus L.02 OH 0.3500
Kepala tukang batu L.03 OH 0.0350
Mandor L.04 OH 0.0350
JUMLAH TENAGA KERJA
B BAHAN
Ubin keramik 20 cm x 20 cm Doos 1.0500
Semen Portland Kg 10.4000
Pasir pasang m3 0.0450
Semen warna Kg 0.5000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.39 Pemasangan 1 m plint keramik ukuran 10 cm x 20 cm


No Uraian Kode Satuan Koefisien

A TENAGA
Pekerja L.01 OH 0.0900
Tukang batu halus L.02 OH 0.0900
Kepala tukang batu L.03 OH 0.0350
Mandor L.04 OH 0.0050
JUMLAH TENAGA KERJA
B BAHAN
Plint keramik 10 cm x 20 cm Bh 5.3000
Semen Portland Kg 1.1400
Pasir pasang m3 0.0030
Semen warna Kg 0.0250
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.4.3.54 Pemasangan 1 m2 dinding keramik 20 cm x 20 cm


No Uraian Kode Satuan Koefisien

A TENAGA
Pekerja L.01 OH 0.9000
Tukang batu halus L.02 OH 0.4500
Kepala tukang batu L.03 OH 0.0450
Mandor L.04 OH 0.0450
JUMLAH TENAGA KERJA
B BAHAN
Keramik artistik 20 cm x 20 cm buah 26.5000
Semen Portland Kg 9.3000
Pasir pasang m3 0.0180
Semen warna Kg 1.9400
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
AN PENUTUP DINDING

Harga Satuan Jumlah Harga


(Rp) (Rp)

70,000.00 49,000.00
90,000.00 31,500.00
95,000.00 3,325.00
80,000.00 2,800.00
UMLAH TENAGA KERJA 86,625.00

46,000.00 48,300.00
1,400.00 14,560.00
400,000.00 18,000.00
15,000.00 7,500.00
UMLAH HARGA BAHAN 88,360.00

UMLAH HARGA ALAT

174,985.00
3,5% x D 23,622.98
198,607.98

Harga Satuan Jumlah Harga


(Rp) (Rp)

70,000.00 6,300.00
90,000.00 8,100.00
95,000.00 3,325.00
80,000.00 400.00
UMLAH TENAGA KERJA 18,125.00

12,100.00 64,130.00
1,400.00 1,596.00
400,000.00 1,200.00
15,000.00 375.00
UMLAH HARGA BAHAN 67,301.00

UMLAH HARGA ALAT

85,426.00
3,5% x D 11,532.51
96,958.51

Harga Satuan Jumlah Harga


(Rp) (Rp)

70,000.00 63,000.00
90,000.00 40,500.00
95,000.00 4,275.00
80,000.00 3,600.00
UMLAH TENAGA KERJA 111,375.00

2,000.00 53,000.00
1,400.00 13,020.00
400,000.00 7,200.00
15,000.00 29,100.00
UMLAH HARGA BAHAN 102,320.00

UMLAH HARGA ALAT

213,695.00
3,5% x D 28,848.83
242,543.83
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240) cm, tebal 9 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 70,000.00
Tukang kayu halus L.02 OH 0.0500 90,000.00
Kepala tukang kayu L.03 OH 0.0050 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Gypsum board Lembar 0.3640 77,000.00
Paku sekrup kg 0.1100 25,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.5.1.10 Pemasangan 1 m2 rangka langit-langit besi hollow 40.40.1,1 mm (A.4.2.1.21)


Lihat pada kelompok Pekerjaan Besi dan Alumunium (A.4.2.1)
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 70,000.00
Tukang Las Biasa L.02 OH 0.3500 70,000.00
Kepala Tukang Las Biasa L.03 OH 0.0350 95,000.00
Mandor L.04 OH 0.0180 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Hollow Meni 40 x 40 x 1,1 mm M' 6.6667 23,000.00
Assesoris (perkuatan, las dll) Ls 100% x rangka 23,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
m, tebal 9 mm

Jumlah Harga (Rp)

7,000.00
4,500.00
475.00
400.00
12,375.00

28,028.00
2,750.00
30,778.00

43,153.00
5,825.66
48,978.66

A.4.2.1.21)

Jumlah Harga (Rp)

24,500.00
24,500.00
3,325.00
1,440.00
53,765.00

153,334.10
23,000.00

176,334.10

230,099.10
31,063.38
261,162.48
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.43 Pemasangan 1 m2 alumunium foil/sisalation


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 70,000.00
Tukang Kayu Kasar L.03 OH 0.0500 85,000.00
Kepala tukang kayu L.11 OH 0.0050 95,000.00
Mandor L.15 OH 0.0080 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Aluminium foil m2 1.0500 9,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

10,500.00
4,250.00
475.00
640.00
15,865.00

9,450.00
9,450.00

25,315.00
3,417.53
28,732.53
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

A.4.6.1.8 Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sa
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 70,000.00
Tukang kayu halus L.03 OH 2.1000 90,000.00
Kepala tukang kayu L.03 OH 0.2100 95,000.00
Mandor L.04 OH 0.0350 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan kayu bengkirai m3 0.0250 11,200,000.00
Paku 1 cm - 2,5 cm kg 0.0300 15,000.00
Lem kayu kg 0.5000 16,250.00
Plywood tebal 4 mm Ukuran (90 x 220) cm Lembar 1.0000 105,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
tutup (lebar sampai 90 cm)
Jumlah Harga
(Rp)

49,000.00
189,000.00
19,950.00
2,800.00
260,750.00

280,000.00
450.00
8,125.00
105,000.00
393,575.00

654,325.00
88,333.88
742,658.88
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.2 Pemasangan 1 buah kunci tanam biasa


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.0100 70,000.00
Tukang kayu halus L.02 OH 0.5000 90,000.00
Kepala tukang kayu L.03 OH 0.0500 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kunci tanam biasa buah 1.0000 75,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.3 Pemasangan 1 buah kunci kamar mandi


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.0050 70,000.00
Tukang kayu halus L.02 OH 0.5000 90,000.00
Kepala tukang kayu L.03 OH 0.0500 95,000.00
Mandor L.04 OH 0.0030 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kunci tanam KM buah 1.0000 75,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.5 Pemasangan 1 buah engsel pintu


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 70,000.00
Tukang kayu halus L.02 OH 0.1500 90,000.00
Kepala tukang kayu L.03 OH 0.0150 95,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Engsel pintu buah 1.0000 24,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 70,000.00
Tukang kayu halus L.02 OH 0.1000 90,000.00
Kepala tukang kayu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0005 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Engsel kupu-kupu buah 1.0000 24,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.7 Pemasangan 1 buah engsel angin


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 70,000.00
Tukang kayu halus L.02 OH 0.2000 90,000.00
Kepala tukang kayu L.03 OH 0.0200 95,000.00
Mandor L.04 OH 0.0005 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Engsel angin buah 1.0000 63,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.9 Pemasangan 1 buah kait angin


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 70,000.00
Tukang kayu halus L.02 OH 0.1500 90,000.00
Kepala tukang kayu L.03 OH 0.0150 95,000.00
Mandor L.04 OH 0.0080 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kait angin buah 1.0000 25,000.00
JUMLAH HARGA ALAT
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.11 Pemasangan 1 buah kunci slot


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 70,000.00
Tukang kayu halus L.02 OH 0.2000 90,000.00
Kepala tukang kayu L.03 OH 0.0200 95,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kunci slot buah 1.0000 34,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.13 Pemasangan 1 buah door stop


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 70,000.00
Tukang kayu halus L.02 OH 0.1000 90,000.00
Kepala tukang kayu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Door stop buah 1.0000 85,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 70,000.00
Tukang kayu halus L.02 OH 0.1500 90,000.00
Kepala tukang kayu L.03 OH 0.0150 95,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kaca tebal 5 mm m2 1.1000 95,000.00
Sealant kaca Kg 0.0500 92,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

700.00
45,000.00
4,750.00
400.00
50,850.00

75,000.00
75,000.00

125,850.00
16,989.75
142,839.75

Jumlah Harga
(Rp)

350.00
45,000.00
4,750.00
240.00
50,340.00

75,000.00
75,000.00

125,340.00
16,920.90
142,260.90

Jumlah Harga
(Rp)

1,050.00
13,500.00
1,425.00
64.00
16,039.00

24,000.00
24,000.00

40,039.00
5,405.27
45,444.27

Jumlah Harga
(Rp)

700.00
9,000.00
950.00
40.00
10,690.00

24,000.00
24,000.00

34,690.00
4,683.15
39,373.15

Jumlah Harga
(Rp)

7,000.00
18,000.00
1,900.00
40.00
26,940.00

63,000.00
63,000.00

89,940.00
12,141.90
102,081.90

Jumlah Harga
(Rp)
1,050.00
13,500.00
1,425.00
640.00
16,615.00

25,000.00
25,000.00

41,615.00
5,618.03
47,233.03

Jumlah Harga
(Rp)

1,400.00
18,000.00
1,900.00
80.00
21,380.00

34,000.00
34,000.00

55,380.00
7,476.30
62,856.30

Jumlah Harga
(Rp)

700.00
9,000.00
950.00
400.00
11,050.00

85,000.00
85,000.00

96,050.00
12,966.75
109,016.75

Jumlah Harga
(Rp)
1,050.00
13,500.00
1,425.00
64.00
16,039.00

104,500.00
4,600.00
109,100.00

125,139.00
16,893.77
142,032.77
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 70,000.00
Tukang cat L.02 OH 0.0630 70,000.00
Kepala tukang cat L.03 OH 0.0063 90,000.00
Mandor L.04 OH 0.0030 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Plamur tembok Kg 0.1000 35,000.00
Cat dasar Kg 0.1000 34,000.00
Cat Penutup Tembok Kg 0.2600 80,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
t dasar, 2 lapis cat penutup
Jumlah Harga
(Rp)

1,400.00
4,410.00
567.00
240.00
6,617.00

3,500.00
3,400.00
20,800.00
27,700.00

34,317.00
4,632.80
38,949.80
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 (K3) Pemasangan 1 buah closet duduk/monoblock


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 3.3000 70,000.00
Tukang batu halus L.02 OH 1.1000 90,000.00
Kepala tukang batu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.1600 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Closet duduk Biasa (Standar) Unit 1.0000 1,250,000.00
Perlengkapan Ls 6% x closet 1,250,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 5 (K3) Pemasangan 1 buah wastafel


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 70,000.00
Tukang batu halus L.02 OH 1.4500 90,000.00
Kepala tukang batu L.03 OH 0.1500 95,000.00
Mandor L.04 OH 0.0600 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Wastafel Biasa Unit 1.2000 890,000.00
Semen Portland Kg 6.0000 1,400.00
Pasir pasang m3 0.0100 400,000.00
Perlengkapan % 12.0000 1,291,400.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 12 Pemasangan 1 buah bak cuci piring stainless steel


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 70,000.00
Tukang batu halus L.02 OH 0.3000 90,000.00
Kepala tukang batu L.03 OH 0.0300 95,000.00
Mandor L.04 OH 0.0150 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bak cuci piring Unit 1.0000 1,050,000.00
Waterdrain buah 1.0000 70,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 13 Pemasangan 1 buah bak cuci piring teraso


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 70,000.00
Tukang batu halus L.02 OH 0.5000 90,000.00
Kepala tukang batu L.03 OH 0.0500 95,000.00
Mandor L.04 OH 0.0250 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bak cuci piring Unit 1.0000 1,050,000.00
Waterdrain buah 1.0000 70,000.00
Semen portland Kg 20.0000 1,400.00
Pasir pasang m3 0.0500 400,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 14 Pemasangan 1 buah floor drain


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 70,000.00
Tukang batu halus L.02 OH 0.1000 90,000.00
Kepala tukang batu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0050 60,000.00
JUMLAH TENAGA KERJA
B BAHAN
Floor drain Unit 1.0000 55,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 15 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.1600 70,000.00
Tukang batu halus L.02 OH 0.7200 90,000.00
Kepala tukang batu L.03 OH 0.0720 95,000.00
Mandor L.04 OH 0.0110 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bata merah buah 40.0000 600.00
Semen portland Kg 44.0000 1,400.00
Pasir pasang m3 0.0700 400,000.00
Pasir beton m3 0.0600 400,000.00
Kerikil beton / split m3 0.0700 350,000.00
Baja tulangan Kg 1.6000 10,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 19 Pemasangan 1 buah kran diameter atau


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 70,000.00
Tukang Pipa L.02 OH 0.4000 90,000.00
Kepala tukang Pipa L.03 OH 0.0400 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kran Air Biasa Stainlees Buah 1.0000 90,000.00
Sealtape Buah 0.0250 6,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 22 Pemasangan 1 m pipa galvanis diameter 1


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1080 70,000.00
Tukang Pipa L.02 OH 0.1800 90,000.00
Kepala tukang Pipa L.03 OH 0.0180 95,000.00
Mandor L.04 OH 0.0050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa galvanis 1" M 1.2000 75,000.00
Perlengkapan % 35.0000 75,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 23 Pemasangan 1 m pipa galvanis diameter 3


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1350 70,000.00
Tukang Pipa L.02 OH 0.2250 90,000.00
Kepala tukang Pipa L.03 OH 0.0230 95,000.00
Mandor L.04 OH 0.0070 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa galvanis 3" M 1.2000 169,000.00
Perlengkapan % 35.0000 169,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 27 Pemasangan 1 m pipa PVC tipe AW diameter 1


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0360 70,000.00
Tukang Pipa L.02 OH 0.0600 90,000.00
Kepala tukang Pipa L.03 OH 0.0060 95,000.00
Mandor L.04 OH 0.0020 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC 1" M 1.2000 8,750.00
Perlengkapan % 35.0000 8,750.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 31 Pemasangan 1 m pipa PVC tipe AW diameter 3


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 70,000.00
Tukang Pipa L.02 OH 0.1350 90,000.00
Kepala tukang Pipa L.03 OH 0.0135 95,000.00
Mandor L.04 OH 0.0040 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC 3" M 1.2000 38,750.00
Perlengkapan % 35.0000 38,750.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.5.1.1 32 Pemasangan 1 m pipa PVC tipe AW diameter 4


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 70,000.00
Tukang Pipa L.02 OH 0.1350 90,000.00
Kepala tukang Pipa L.03 OH 0.0135 95,000.00
Mandor L.04 OH 0.0040 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC 4" M 1.2000 61,500.00
Perlengkapan % 35.0000 61,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

231,000.00
99,000.00
950.00
12,800.00
343,750.00

1,250,000.00
75,000.00
1,325,000.00

1,668,750.00
225,281.25
1,894,031.25

Jumlah Harga
(Rp)

84,000.00
130,500.00
14,250.00
4,800.00
233,550.00

1,068,000.00
8,400.00
4,000.00
154,968.00
1,235,368.00

1,468,918.00
198,303.93
1,667,221.93

Jumlah Harga
(Rp)

2,100.00
27,000.00
2,850.00
1,200.00
33,150.00
1,050,000.00
70,000.00
1,120,000.00

1,153,150.00
155,675.25
1,308,825.25

Jumlah Harga
(Rp)

3,500.00
45,000.00
4,750.00
2,000.00
55,250.00

1,050,000.00
70,000.00
28,000.00
20,000.00
1,168,000.00

1,223,250.00
165,138.75
1,388,388.75

Jumlah Harga
(Rp)

700.00
9,000.00
950.00
300.00
10,950.00

55,000.00
55,000.00
65,950.00
8,903.25
74,853.25

Jumlah Harga
(Rp)

151,200.00
64,800.00
6,840.00
880.00
223,720.00

24,000.00
61,600.00
28,000.00
24,000.00
24,500.00
16,800.00
178,900.00

402,620.00
54,353.70
456,973.70

Jumlah Harga
(Rp)

700.00
36,000.00
3,800.00
400.00
40,900.00

90,000.00
150.00
90,150.00

131,050.00
17,691.75
148,741.75
Jumlah Harga
(Rp)

7,560.00
16,200.00
1,710.00
400.00
25,870.00

90,000.00
26,250.00
116,250.00

142,120.00
19,186.20
161,306.20

Jumlah Harga
(Rp)

9,450.00
20,250.00
2,185.00
560.00
32,445.00

202,800.00
59,150.00
261,950.00

294,395.00
39,743.33
334,138.33

Jumlah Harga
(Rp)

2,520.00
5,400.00
570.00
160.00
8,650.00

10,500.00
3,062.50
13,562.50

22,212.50
2,998.69
25,211.19

Jumlah Harga
(Rp)

5,670.00
12,150.00
1,282.50
320.00
19,422.50

46,500.00
13,562.50
60,062.50

79,485.00
10,730.48
90,215.48

Jumlah Harga
(Rp)

5,670.00
12,150.00
1,282.50
320.00
19,422.50
73,800.00
21,525.00
95,325.00

114,747.50
15,490.91
130,238.41
A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG

A.8.4.1.1 (K3) Pemasangan 1 m pipa PVC 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 70,000.00
Tukang Pipa L.02 OH 0.0410 90,000.00
Mandor L.04 OH 0.0080 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 63 mm m 1.0000 19,500.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0060 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Catatan:
Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang tercantum pada tabel. Apabila
tambahan peralatan yang digunakan,harus disesuaikan dengan spesifikasi dan gambar kerja.
A.8.4.1.2 (K3) Pemasangan 1 m pipa PVC 90 mm
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0940 70,000.00
Tukang Pipa L.02 OH 0.0470 90,000.00
Mandor L.04 OH 0.0090 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 90 mm m 1.0000 38,750.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0080 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.3 (K3) Pemasangan 1 m pipa PVC 110 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1050 70,000.00
Tukang Pipa L.02 OH 0.0530 90,000.00
Mandor L.04 OH 0.0110 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 110 mm m 1.0000 61,500.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0100 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.4 (K3) Pemasangan 1 m pipa PVC 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1180 70,000.00
Tukang Pipa L.02 OH 0.0590 90,000.00
Mandor L.04 OH 0.0120 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 150 mm m 1.0000 98,750.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0120 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1890 70,000.00
Tukang Pipa L.02 OH 0.0950 90,000.00
Mandor L.04 OH 0.0190 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 200 mm m 1.0000 165,375.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0240 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.6 (K3) Pemasangan 1 m pipa PVC 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2560 70,000.00
Tukang Pipa L.02 OH 0.1280 90,000.00
Mandor L.04 OH 0.0260 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC 250 mm m 1.0000 186,925.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0340 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.7 (K3) Pemasangan 1 m pipa PVC 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2940 70,000.00
Tukang Pipa L.02 OH 0.1470 90,000.00
Mandor L.04 OH 0.0290 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 300 mm m 1.0000 237,075.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0400 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.8 (K3) Pemasangan 1 m pipa PVC 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5440 70,000.00
Tukang Pipa L.02 OH 0.2720 90,000.00
Mandor L.04 OH 0.0540 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa PVC 400 mm m 1.0000 389,300.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0800 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.17 (K3) Pemasangan 1 m pipa HDPE 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0350 70,000.00
Tukang Pipa L.02 OH 0.0170 90,000.00
Mandor L.04 OH 0.0030 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 63 mm m 1.0000 39,900.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.18 (K3) Pemasangan 1 m pipa HDPE 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 70,000.00
Tukang Pipa L.02 OH 0.0200 90,000.00
Mandor L.04 OH 0.0040 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 100 mm m 1.0000 98,300.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.19 (K3) Pemasangan 1 m pipa HDPE 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0450 70,000.00
Tukang Pipa L.02 OH 0.0230 90,000.00
Mandor L.04 OH 0.0050 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 125 mm m 1.0000 109,810.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.8.4.1.20 (K3) Pemasangan 1 m pipa HDPE 150 mm
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0620 70,000.00
Tukang Pipa L.02 OH 0.0310 90,000.00
Mandor L.04 OH 0.0060 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 150 mm m 1.0000 207,700.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.21 (K3) Pemasangan 1 m pipa HDPE 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1020 70,000.00
Tukang Pipa L.02 OH 0.0510 90,000.00
Mandor L.04 OH 0.0100 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 200 mm m 1.0000 320,500.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.22 (K3) Pemasangan 1 m pipa HDPE 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1330 70,000.00
Tukang Pipa L.02 OH 0.0670 90,000.00
Mandor L.04 OH 0.0130 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 250 mm m 1.0000 502,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0420 300,000.00
crane 2 T
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.23 (K3) Pemasangan 1 m pipa HDPE 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1700 70,000.00
Tukang Pipa L.02 OH 0.0850 90,000.00
Mandor L.04 OH 0.0170 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 300 mm m 1.0000 797,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0650 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.24 (K3) Pemasangan 1 m pipa HDPE 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2900 70,000.00
Tukang Pipa L.02 OH 0.1450 90,000.00
Mandor L.04 OH 0.0290 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa HDPE 400 mm m 1.0000 1,289,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.1520 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.33 (K3) Pemasangan 1 m pipa GIP 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3450 70,000.00
Tukang Pipa L.02 OH 0.1720 90,000.00
Mandor L.04 OH 0.0340 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa GIP 63 mm m 1.0000 158,633.33
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.34 (K3) Pemasangan 1 m pipa GIP 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 70,000.00
Tukang Pipa L.02 OH 0.2000 90,000.00
Mandor L.04 OH 0.0400 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa GIP 100 mm m 1.0000 296,633.33
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.35 (K3) Pemasangan 1 m pipa GIP 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4480 70,000.00
Tukang Pipa L.02 OH 0.2240 90,000.00
Mandor L.04 OH 0.0450 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa GIP 125 mm m 1.0000 399,133.33
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.36 (K3) Pemasangan 1 m pipa GIP 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5060 70,000.00
Tukang Pipa L.02 OH 0.2530 90,000.00
Mandor L.04 OH 0.0510 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa GIP 150 mm m 1.0000 475,300.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.37 (K3) Pemasangan 1 m pipa GIP 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7960 70,000.00
Tukang Pipa L.02 OH 0.3980 90,000.00
Mandor L.04 OH 0.0800 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa GIP 200 mm m 1.0000 682,633.33
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.49 (K3) Pemasangan 1 m pipa DCI 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4890 70,000.00
Tukang Pipa L.02 OH 0.0980 90,000.00
Mandor L.04 OH 0.0490 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa DCI 100 mm m 1.0000 97,600.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.50 (K3) Pemasangan 1 m pipa DCI 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5470 70,000.00
Tukang Pipa L.02 OH 0.1090 90,000.00
Mandor L.04 OH 0.0550 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa DCI 125 mm m 1.0000 200,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.3800 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.51 (K3) Pemasangan 1 m pipa DCI 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6130 70,000.00
Tukang Pipa L.02 OH 0.1230 90,000.00
Mandor L.04 OH 0.0610 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa DCI 150 mm m 1.0000 219,500.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.52 (K3) Pemasangan 1 m pipa DCI 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.8550 70,000.00
Tukang Pipa L.02 OH 0.1710 90,000.00
Mandor L.04 OH 0.0850 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa DCI 200 mm m 1.0000 390,600.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0190 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.53 (K3) Pemasangan 1 m pipa DCI 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9510 70,000.00
Tukang Pipa L.02 OH 0.1900 90,000.00
Mandor L.04 OH 0.0950 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa DCI 250 mm M 1.0000 550,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0500 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.54 (K3) Pemasangan 1 m pipa DCI 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9730 70,000.00
Tukang Pipa L.02 OH 0.1950 90,000.00
Mandor L.04 OH 0.0970 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa DCI 300 mm m 1.0000 732,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0710 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.55 (K3) Pemasangan 1 m pipa DCI 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.5450 70,000.00
Tukang Pipa L.02 OH 0.3090 90,000.00
Operator alat berat L.08 OH 0.0930 150,000.00
Mandor L.04 OH 0.1540 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 400 mm m 1.0000 2,076,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.0230 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.0310 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.56 (K3) Pemasangan 1 m pipa DCI 450 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.8130 70,000.00
Tukang Pipa L.02 OH 0.3630 90,000.00
Operator alat berat L.08 OH 0.1430 150,000.00
Mandor L.04 OH 0.1810 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 450 mm m 1.0000 2,350,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.0290 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.0390 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.57 (K3) Pemasangan 1 m pipa DCI 500 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.0470 70,000.00
Tukang Pipa L.02 OH 0.4090 90,000.00
Operator alat berat L.08 OH 0.1930 150,000.00
Mandor L.04 OH 0.2050 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 500 mm m 1.0000 2,750,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.0340 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.0450 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.58 (K3) Pemasangan pipa 1 m DCI 600 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.0110 70,000.00
Tukang Pipa L.02 OH 0.4020 90,000.00
Operator alat berat L.08 OH 0.2930 150,000.00
Mandor L.04 OH 0.2010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 600 mm m 1.0000 3,102,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.0580 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.0770 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.59 (K3) Pemasangan 1 m pipa DCI 800 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 3.8590 70,000.00
Tukang Pipa L.02 OH 0.7720 90,000.00
Operator alat berat L.08 OH 0.4930 150,000.00
Mandor L.04 OH 0.3860 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 800 mm m 1.0000 4,152,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.0840 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.2250 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.61 (K3) Pemasangan 1 m pipa DCI 1000 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 5.9310 70,000.00
Tukang Pipa L.02 OH 1.1860 90,000.00
Operator alat berat L.08 OH 0.7930 150,000.00
Mandor L.04 OH 0.6930 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 1000 mm m 1.0000 5,184,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.1120 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.2980 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.62 (K3) Pemasangan 1 m pipa DCI 1100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 6.9490 70,000.00
Tukang Pipa L.02 OH 1.3900 90,000.00
Operator alat berat L.08 OH 0.7930 150,000.00
Mandor L.04 OH 0.6950 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 1100 mm m 1.0000 5,600,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.1520 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.3040
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.63 (K3) Pemasangan 1 m pipa DCI 1200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 8.0560 70,000.00
Tukang Pipa L.02 OH 1.6110 90,000.00
Operator alat berat L.08 OH 0.8930 150,000.00
Mandor L.04 OH 0.8060 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa DCI 1200 mm m 1.0000 6,228,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa excavator type 225 hari 0.1800 569,012.00
kapasitas 0,5 - 1,0 m
Sewa Tripot/Tackel
3
& handle hari 0.3600
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.64 (K3) Pemasangan 1 m Pipa baja 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4990 70,000.00
Tukang Pipa L.02 OH 0.1000 90,000.00
Mandor L.04 OH 0.0500 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa baja 63 mm m 1.0000 153,750.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0040 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.65 (K3) Pemasangan 1 m pipa baja 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5790 70,000.00
Tukang Pipa L.02 OH 0.1160 90,000.00
Mandor L.04 OH 0.0580 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa baja 100 mm m 1.0000 244,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0040 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.66 (K3) Pemasangan 1 m pipa baja 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6480 70,000.00
Tukang Pipa L.02 OH 0.1300 90,000.00
Mandor L.04 OH 0.0650 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa baja 125 mm m 1.0000 335,833.33
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0040 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.67 (K3) Pemasangan 1 m pipa baja 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7080 70,000.00
Tukang Pipa L.02 OH 0.1420 90,000.00
Mandor L.04 OH 0.0710 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa baja 150 mm m 1.0000 399,166.67
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0040 300,000.00
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.1.68 (K3) Pemasangan 1 m pipa baja 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.1130 70,000.00
Tukang Pipa L.02 OH 0.2230 90,000.00
Mandor L.04 OH 0.1110 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa baja 200 mm m 1.0000 565,833.33
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & handle hari 0.0040 300,000
crane 2 T JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

5,670.00
3,690.00
640.00

10,000.00

19,500.00
19,500.00

1,800.00
1,800.00
31,300.00
4,225.50
35,525.50

ada tabel. Apabila ada


ar kerja.

Jumlah Harga
(Rp)

6,580.00
4,230.00
720.00

11,530.00

38,750.00
38,750.00

2,400.00
2,400.00
52,680.00
7,111.80
59,791.80

Jumlah Harga
(Rp)

7,350.00
4,770.00
880.00

13,000.00

61,500.00
61,500.00
3,000.00
3,000.00
77,500.00
10,462.50
87,962.50

Jumlah Harga
(Rp)

8,260.00
5,310.00
960.00

14,530.00

98,750.00
98,750.00

3,600.00
3,600.00
116,880.00
15,778.80
132,658.80

Jumlah Harga
(Rp)

13,230.00
8,550.00
1,520.00

23,300.00

165,375.00
165,375.00

7,200.00
7,200.00
195,875.00
26,443.13
222,318.13

Jumlah Harga
(Rp)

17,920.00
11,520.00
2,080.00
31,520.00

186,925.00
186,925.00

10,200.00
10,200.00
228,645.00
30,867.08
259,512.08

Jumlah Harga
(Rp)

20,580.00
13,230.00
2,320.00

36,130.00

237,075.00
237,075.00

12,000.00
12,000.00
285,205.00
38,502.68
323,707.68

Jumlah Harga
(Rp)

38,080.00
24,480.00
4,320.00

66,880.00

389,300.00
389,300.00

24,000.00
24,000.00
480,180.00
64,824.30
545,004.30

Jumlah Harga
(Rp)
2,450.00
1,530.00
240.00

4,220.00

39,900.00
39,900.00

5,700.00
5,700.00
49,820.00
7,473.00
57,293.00

Jumlah Harga
(Rp)

2,800.00
1,800.00
320.00

4,920.00

98,300.00
98,300.00

5,700.00
5,700.00
108,920.00
14,704.20
123,624.20

Jumlah Harga
(Rp)

3,150.00
2,070.00
400.00

5,620.00

109,810.00
109,810.00

5,700.00
5,700.00
121,130.00
16,352.55
137,482.55
Jumlah Harga
(Rp)

4,340.00
2,790.00
480.00

7,610.00

207,700.00
207,700.00

5,700.00
5,700.00
221,010.00
29,836.35
250,846.35

Jumlah Harga
(Rp)

7,140.00
4,590.00
800.00

12,530.00

320,500.00
320,500.00

5,700.00
5,700.00
338,730.00
45,728.55
384,458.55

Jumlah Harga
(Rp)

9,310.00
6,030.00
1,040.00

16,380.00

502,000.00
502,000.00

12,600.00
12,600.00
530,980.00
71,682.30
602,662.30

Jumlah Harga
(Rp)

11,900.00
7,650.00
1,360.00

20,910.00

797,000.00
797,000.00

19,500.00
19,500.00
837,410.00
113,050.35
950,460.35

Jumlah Harga
(Rp)

20,300.00
13,050.00
2,320.00

35,670.00

1,289,000.00
1,289,000.00

45,600.00
45,600.00
1,370,270.00
184,986.45
1,555,256.45

Jumlah Harga
(Rp)

24,150.00
15,480.00
2,720.00

42,350.00
158,633.33
158,633.33

5,700.00
5,700.00
206,683.33
27,902.25
234,585.58

Jumlah Harga
(Rp)

28,000.00
18,000.00
3,200.00

49,200.00

296,633.33
296,633.33

5,700.00
5,700.00
351,533.33
47,457.00
398,990.33

Jumlah Harga
(Rp)

31,360.00
20,160.00
3,600.00

55,120.00

399,133.33
399,133.33

5,700.00
5,700.00
459,953.33
62,093.70
522,047.03

Jumlah Harga
(Rp)

35,420.00
22,770.00
4,080.00

62,270.00

475,300.00
475,300.00

5,700.00
5,700.00
543,270.00
73,341.45
616,611.45

Jumlah Harga
(Rp)

55,720.00
35,820.00
6,400.00

97,940.00

682,633.33
682,633.33

5,700.00
5,700.00
786,273.33
106,146.90
892,420.23

Jumlah Harga
(Rp)

34,230.00
8,820.00
3,920.00

46,970.00

97,600.00
97,600.00

5,700.00
5,700.00
150,270.00
20,286.45
170,556.45
Jumlah Harga
(Rp)

38,290.00
9,810.00
4,400.00

52,500.00

200,000.00
200,000.00

114,000.00
114,000.00
366,500.00
49,477.50
415,977.50

Jumlah Harga
(Rp)

42,910.00
11,070.00
4,880.00

58,860.00

219,500.00
219,500.00

5,700.00
5,700.00
284,060.00
38,348.10
322,408.10

Jumlah Harga
(Rp)

59,850.00
15,390.00
6,800.00

82,040.00

390,600.00
390,600.00

5,700.00
5,700.00
478,340.00
64,575.90
542,915.90

Jumlah Harga
(Rp)

66,570.00
17,100.00
7,600.00

91,270.00

550,000.00
550,000.00

15,000.00
15,000.00
656,270.00
88,596.45
744,866.45

Jumlah Harga
(Rp)

68,110.00
17,550.00
7,760.00

93,420.00

732,000.00
732,000.00

21,300.00
21,300.00
846,720.00
114,307.20
961,027.20

Jumlah Harga
(Rp)

108,150.00
27,810.00
13,950.00
12,320.00
162,230.00

2,076,000.00
2,076,000.00
13,087.28
13,087.28
26,174.55
2,264,404.55
305,694.61
2,570,099.17

Jumlah Harga
(Rp)

126,910.00
32,670.00
21,450.00
14,480.00
195,510.00

2,350,000.00
2,350,000.00

16,501.35
16,501.35
33,002.70
2,578,512.70
348,099.21
2,926,611.91

Jumlah Harga
(Rp)

143,290.00
36,810.00
28,950.00

209,050.00

2,750,000.00
2,750,000.00

19,346.41
19,346.41
38,692.82
2,997,742.82
404,695.28
3,402,438.10

Jumlah Harga
(Rp)

140,770.00
36,180.00
43,950.00
16,080.00
236,980.00

3,102,000.00
3,102,000.00

33,002.70
33,002.70
66,005.39
3,404,985.39
459,673.03
3,864,658.42

Jumlah Harga
(Rp)

270,130.00
69,480.00
73,950.00
30,880.00
444,440.00

4,152,000.00
4,152,000.00

47,797.01
47,797.01
95,594.02
4,692,034.02
633,424.59
5,325,458.61

Jumlah Harga
(Rp)

415,170.00
106,740.00
118,950.00
55,440.00
696,300.00

5,184,000.00
5,184,000.00

63,729.34
63,729.34
127,458.69
6,007,758.69
811,047.42
6,818,806.11

Jumlah Harga
(Rp)

486,430.00
125,100.00
118,950.00
55,600.00
786,080.00

5,600,000.00
5,600,000.00

86,489.82
86,489.82
172,979.65
6,559,059.65
885,473.05
7,444,532.70

Jumlah Harga
(Rp)

563,920.00
144,990.00
133,950.00
64,480.00
907,340.00

6,228,000.00
6,228,000.00

102,422.16
102,422.16
204,844.32
7,340,184.32
990,924.88
8,331,109.20

Jumlah Harga
(Rp)

34,930.00
9,000.00
4,000.00
47,930.00

153,750.00
153,750.00

1,200.00
1,200.00
202,880.00
27,388.80
230,268.80

Jumlah Harga
(Rp)

40,530.00
10,440.00
4,640.00
55,610.00

244,000.00
244,000.00

1,200.00
1,200.00
300,810.00
40,609.35
341,419.35

Jumlah Harga
(Rp)

45,360.00
11,700.00
5,200.00
62,260.00

335,833.33
335,833.33

1,200.00
1,200.00
399,293.33
53,904.60
453,197.93

Jumlah Harga
(Rp)

49,560.00
12,780.00
5,680.00
68,020.00
399,166.67
399,166.67

1,200.00
1,200.00
468,386.67
63,232.20
531,618.87

Jumlah Harga
(Rp)

77,910.00
20,070.00
8,880.00
106,860.00

565,833.33
565,833.33

1,200.00
1,200.00
673,893.33
90,975.60
764,868.93
A.8.4.2 HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA

A.8.4.2.1 (K3) Pemotongan 1 buah pipa PVC 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0050 70,000.00
Tukang Pipa L.02 OH 0.0020 90,000.00
Mandor L.04 OH 0.0005 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0030 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.2 (K3) Pemotongan 1 buah pipa PVC 90 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0140 70,000.00
Tukang Pipa L.02 OH 0.0070 90,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0030 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.3 (K3) Pemotongan 1 buah pipa PVC 110 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0220 70,000.00
Tukang Pipa L.02 OH 0.0110 90,000.00
Mandor L.04 OH 0.0020 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0030 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.4 (K3) Pemotongan 1 buah pipa PVC 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0310 70,000.00
Tukang Pipa L.02 OH 0.0150 90,000.00
Mandor L.04 OH 0.0030 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0030 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.5 (K3) Pemotongan 1 buah pipa PVC 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 70,000.00
Tukang Pipa L.02 OH 0.0400 90,000.00
Mandor L.04 OH 0.0080 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0170 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.6 (K3) Pemotongan 1 buah pipa PVC 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1280 70,000.00
Tukang Pipa L.02 OH 0.0640 90,000.00
Mandor L.04 OH 0.0130 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0300 3,500.00
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.7 (K3) Pemotongan 1 buah pipa PVC 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1550 70,000.00
Tukang Pipa L.02 OH 0.0770 90,000.00
Mandor L.04 OH 0.0150 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0370 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.8 (K3) Pemotongan 1 buah pipa PVC 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3310 70,000.00
Tukang Pipa L.02 OH 0.1660 90,000.00
Mandor L.04 OH 0.0330 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0860 3,500.00
T1/manual (gergaji) /saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.9 (K3) Pemotongan 1 buah pipa PVC 450 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4200 70,000.00
Tukang Pipa L.02 OH 0.2100 90,000.00
Mandor L.04 OH 0.0420 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0540 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.10 (K3) Pemotongan 1 buah pipa PVC 500 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5180 70,000.00
Tukang Pipa L.02 OH 0.2590 90,000.00
Mandor L.04 OH 0.0520 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0690 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.11 (K3) Pemotongan 1 buah pipa PVC 600 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6230 70,000.00
Tukang Pipa L.02 OH 0.3110 90,000.00
Mandor L.04 OH 0.0620 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0860 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.12 (K3) Pemotongan 1 buah pipa PVC 800 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.0890 70,000.00
Tukang Pipa L.02 OH 0.5450 90,000.00
Mandor L.04 OH 0.1090 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan potong pipa hari 0.1600 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.13 (K3) Pemotongan 1 buah pipa PVC 900 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.1410 70,000.00
Tukang Pipa L.02 OH 0.5710 90,000.00
Mandor L.04 OH 0.1140 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1680 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.14 (K3) Pemotongan 1 buah pipa PVC 1000 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.2850 70,000.00
Tukang Pipa L.02 OH 0.6430 90,000.00
Mandor L.04 OH 0.1290 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1910 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.15 (K3) Pemotongan 1 buah pipa PVC 1100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.4290 70,000.00
Tukang Pipa L.02 OH 0.7150 90,000.00
Mandor L.04 OH 0.1430 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2130 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.16 (K3) Pemotongan 1 buah pipa PVC 1200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.5730 70,000.00
Tukang Pipa L.02 OH 0.7870 90,000.00
Mandor L.04 OH 0.1570 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2360 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.17 (K3) Pemotongan 1 buah pipa HDPE 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0020 70,000.00
Tukang Pipa L.02 OH 0.0010 90,000.00
Mandor L.04 OH 0.0002 80,000.00
Operator (alat potong T2) L.08 OH 0.0340 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0040 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.18 (K3) Pemotongan 1 buah pipa HDPE 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0060 70,000.00
Tukang Pipa L.02 OH 0.0030 90,000.00
Mandor L.04 OH 0.0010 80,000.00
Operator (alat potong T2) L.08 OH 0.0710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0050 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.19 (K3) Pemotongan 1 buah pipa HDPE 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0090 70,000.00
Tukang Pipa L.02 OH 0.0050 90,000.00
Mandor L.04 OH 0.0010 80,000.00
Operator (alat potong T2) L.08 OH 0.0960 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0060 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.20 (K3) Pemotongan 1 buah pipa HDPE 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0160 70,000.00
Tukang Pipa L.02 OH 0.0080 90,000.00
Mandor L.04 OH 0.0020 80,000.00
Operator (alat potong T2) L.08 OH 0.1210 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0090 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.21 (K3) Pemotongan 1 buah pipa HDPE 200 mm
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0440 70,000.00
Tukang Pipa L.02 OH 0.0220 90,000.00
Mandor L.04 OH 0.0040 80,000.00
Operator (alat potong T2) L.08 OH 0.1710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0170 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.22 (K3) Pemotongan 1 buah pipaHDPE 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0670 70,000.00
Tukang Pipa L.02 OH 0.0330 90,000.00
Mandor L.04 OH 0.0070 80,000.00
Operator (alat potong T2) L.08 OH 0.2210 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0230 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.23 (K3) Pemotongan 1 buah pipa HDPE 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 70,000.00
Tukang Pipa L.02 OH 0.0450 90,000.00
Mandor L.04 OH 0.0090 80,000.00
Operator (alat potong T2) L.08 OH 0.2710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0300 3,500.00
T2/mekanik/cilinder saw
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.24 (K3) Pemotongan 1 buah pipa HDPE 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1770 70,000.00
Tukang Pipa L.02 OH 0.0880 90,000.00
Mandor L.04 OH 0.0180 80,000.00
Operator (alat potong T2) L.08 OH 0.3710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0550 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.25 (K3) Pemotongan 1 buah pipa HDPE 450 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2250 70,000.00
Tukang Pipa L.02 OH 0.1130 90,000.00
Mandor L.04 OH 0.0230 80,000.00
Operator (alat potong T2) L.08 OH 0.4210 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0700 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.26 (K3) Pemotongan 1 buah pipa HDPE 500 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2770 70,000.00
Tukang Pipa L.02 OH 0.1390 90,000.00
Mandor L.04 OH 0.0280 80,000.00
Operator (alat potong T2) L.08 OH 0.4710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0850 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.27 (K3) Pemotongan 1 buah pipa HDPE 600 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3330 70,000.00
Tukang Pipa L.02 OH 0.1670 90,000.00
Mandor L.04 OH 0.0330 80,000.00
Operator (alat potong T2) L.08 OH 0.5710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1010 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.28 (K3) Pemotongan 1 buah pipa HDPE 800 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6010 70,000.00
Tukang Pipa L.02 OH 0.3010 90,000.00
Mandor L.04 OH 0.0600 80,000.00
Operator (alat potong T2) L.08 OH 0.7710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1790 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.29 (K3) Pemotongan 1 buah pipa HDPE 900 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9130 70,000.00
Tukang Pipa L.02 OH 0.4560 90,000.00
Mandor L.04 OH 0.0910 80,000.00
Operator (alat potong T2) L.08 OH 0.8710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2700 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.30 (K3) Pemotongan 1 buah pipa HDPE 1000 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.1250 70,000.00
Tukang Pipa L.02 OH 0.5620 90,000.00
Mandor L.04 OH 0.1120 80,000.00
Operator (alat potong T2) L.08 OH 0.9710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.3320 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.31 (K3) Pemotongan 1 buah pipa HDPE 1100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.2380 70,000.00
Tukang Pipa L.02 OH 0.6190 90,000.00
Mandor L.04 OH 0.1240 80,000.00
Operator (alat potong T2) L.08 OH 1.0710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.3650 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.32 (K3) Pemotongan 1 buah pipa HDPE 1200 mm
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.6190 70,000.00
Tukang Pipa L.02 OH 0.8090 90,000.00
Mandor L.04 OH 0.1620 80,000.00
Operator (alat potong T2) L.08 OH 1.1710 75,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.4770 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.33 (K3) Pemotongan 1 buah pipa GIP 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1900 70,000.00
Tukang Pipa L.02 OH 0.0100 90,000.00
Mandor L.04 OH 0.0020 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0040 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.34 (K3) Pemotongan 1 buah pipa GIP 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 70,000.00
Tukang Pipa L.02 OH 0.0290 90,000.00
Mandor L.04 OH 0.0060 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0040 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.35 (K3) Pemotongan 1 buah pipa GIP 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9200 70,000.00
Tukang Pipa L.02 OH 0.0460 90,000.00
Mandor L.04 OH 0.0090 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0060 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.36 (K3) Pemotongan 1 buah pipa GIP 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.3100 70,000.00
Tukang Pipa L.02 OH 0.0660 90,000.00
Mandor L.04 OH 0.0130 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0090 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.37 (K3) Pemotongan 1 buah pipa GIP 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.7000 70,000.00
Tukang Pipa L.02 OH 0.1700 90,000.00
Mandor L.04 OH 0.0340 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0170 3,500.00
T2/mekanik/cilinder saw
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.38 (K3) Pemotongan 1 buah pipa GIP 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.3700 70,000.00
Tukang Pipa L.02 OH 0.2370 90,000.00
Mandor L.04 OH 0.0470 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0230 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.39 (K3) Pemotongan 1 buah pipa GIP 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.5200 70,000.00
Tukang Pipa L.02 OH 0.2520 90,000.00
Mandor L.04 OH 0.0500 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0300 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.40 (K3) Pemotongan 1 buah pipa GIP 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7380 70,000.00
Tukang Pipa L.02 OH 0.3690 90,000.00
Mandor L.04 OH 0.0740 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0550 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.41 (K3) Pemotongan 1 buah pipa GIP 450 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.8480 70,000.00
Tukang Pipa L.02 OH 0.4240 90,000.00
Mandor L.04 OH 0.0850 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0700 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.42 (K3) Pemotongan 1 buah pipa GIP 500 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9410 70,000.00
Tukang Pipa L.02 OH 0.4710 90,000.00
Mandor L.04 OH 0.0940 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0850 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.43 (K3) Pemotongan1 buah pipa GIP 600 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.8640 70,000.00
Tukang Pipa L.02 OH 0.4320 90,000.00
Mandor L.04 OH 0.0860 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan potong pipa hari 0.1010 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.44 (K3) Pemotongan 1 buah pipa GIP 800 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.5670 70,000.00
Tukang Pipa L.02 OH 0.7830 90,000.00
Mandor L.04 OH 0.1570 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1790 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.45 (K3) Pemotongan 1 buah pipa GIP 900 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.7700 70,000.00
Tukang Pipa L.02 OH 0.8850 90,000.00
Mandor L.04 OH 0.1770 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2700 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.46 (K3) Pemotongan 1 buah pipa GIP 1000 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.9740 70,000.00
Tukang Pipa L.02 OH 0.9870 90,000.00
Mandor L.04 OH 0.1970 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.3320 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.47 (K3) Pemotongan 1 buah pipa GIP 1100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.1780 70,000.00
Tukang Pipa L.02 OH 1.0890 90,000.00
Mandor L.04 OH 0.2180 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.3650 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.48 (K3) Pemotongan 1 buah pipa GIP 1200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.3820 70,000.00
Tukang Pipa L.02 OH 1.1910 90,000.00
Mandor L.04 OH 0.2380 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.4770 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.49 (K3) Pemotongan 1 buah pipa DCI 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0710 70,000.00
Tukang Pipa L.02 OH 0.0140 90,000.00
Mandor L.04 OH 0.0070 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel & hari 0.0030 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.50 (K3) Pemotongan 1 buah pipa DCI 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1120 70,000.00
Tukang Pipa L.02 OH 0.0220 90,000.00
Mandor L.04 OH 0.0110 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel & hari 0.0100 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.51 (K3) Pemotongan 1 buah pipa DCI 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1590 70,000.00
Tukang Pipa L.02 OH 0.0320 90,000.00
Mandor L.04 OH 0.0160 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel & hari 0.0180 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.52 (K3) Pemotongan 1 buah pipa DCI 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3660 70,000.00
Tukang Pipa L.02 OH 0.0730 90,000.00
Mandor L.04 OH 0.0370 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel & hari 0.0540 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.53 (K3) Pemotongan 1 buah pipa DCI 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4760 70,000.00
Tukang Pipa L.02 OH 0.0950 90,000.00
Mandor L.04 OH 0.0480 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel & hari 0.0730 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.54 (K3) Pemotongan 1 buah pipa DCI 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.5120 70,000.00
Tukang Pipa L.02 OH 0.1020 90,000.00
Mandor L.04 OH 0.0510 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Tripot/Tackel & hari 0.0790 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.55 (K3) Pemotongan 1 buah pipa DCI 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.9410 70,000.00
Tukang Pipa L.02 OH 0.1880 90,000.00
Mandor L.04 OH 0.0940 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1580 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.56 (K3) Pemotongan 1 buah pipa DCI 450 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.1370 70,000.00
Tukang Pipa L.02 OH 0.2270 90,000.00
Mandor L.04 OH 0.1140 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1760 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.57 (K3) Pemotongan 1 buah pipa DCI 500 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.3120 70,000.00
Tukang Pipa L.02 OH 0.2620 90,000.00
Mandor L.04 OH 0.1310 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1920 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
A.8.4.2.58 (K3) Pemotongan 1 buah pipa DCI 600 mm
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.3090 70,000.00
Tukang Pipa L.02 OH 0.2620 90,000.00
Mandor L.04 OH 0.1310 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1920 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.59 (K3) Pemotongan 1 buah pipa DCI 800 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.5980 70,000.00
Tukang Pipa L.02 OH 0.5200 90,000.00
Mandor L.04 OH 0.2600 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.3100 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.60 (K3) Pemotongan 1 buah pipa DCI 900 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 3.3700 70,000.00
Tukang Pipa L.02 OH 0.6740 90,000.00
Mandor L.04 OH 0.3370 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.3810 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.61 (K3) Pemotongan 1 buah pipa DCI 1000 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 4.0210 70,000.00
Tukang Pipa L.02 OH 0.8040 90,000.00
Mandor L.04 OH 0.4020 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.4410 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.62 (K3) Pemotongan 1 buah pipa DCI 1100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 4.7310 70,000.00
Tukang Pipa L.02 OH 0.9460 90,000.00
Mandor L.04 OH 0.4730 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.5060 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.63 (K3) Pemotongan 1 buah pipa DCI 1200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 5.5020 70,000.00
Tukang Pipa L.02 OH 1.1000 90,000.00
Mandor L.04 OH 0.5500 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.5760 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.64 (K3) Pemotongan 1 buah pipa baja 63 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0280 70,000.00
Tukang Pipa L.02 OH 0.0060 90,000.00
Mandor L.04 OH 0.0030 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0370 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.65 (K3) Pemotongan 1 buah pipa baja 100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 70,000.00
Tukang Pipa L.02 OH 0.0170 90,000.00
Mandor L.04 OH 0.0080 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0400 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.66 (K3) Pemotongan 1 buah pipa baja 125 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1330 70,000.00
Tukang Pipa L.02 OH 0.0270 90,000.00
Mandor L.04 OH 0.0130 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0420 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.67 (K3) Pemotongan 1 buah pipa baja 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1840 70,000.00
Tukang Pipa L.02 OH 0.0370 90,000.00
Mandor L.04 OH 0.0180 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0450 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.68 (K3) Pemotongan 1 buah pipa baja 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4760 70,000.00
Tukang Pipa L.02 OH 0.0950 90,000.00
Mandor L.04 OH 0.0480 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa baja 200 mm buah - -
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan potong pipa hari 0.0600 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.69 (K3) Pemotongan 1 buah pipa baja 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.6630 70,000.00
Tukang Pipa L.02 OH 0.1330 90,000.00
Mandor L.04 OH 0.0660 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan potong pipa hari 0.0680 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.70 (K3) Pemotongan 1 buah pipa baja 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.7450 70,000.00
Tukang Pipa L.02 OH 0.1490 90,000.00
Mandor L.04 OH 0.0740 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.0720 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.71 (K3) Pemotongan 1 buah pipa baja 400 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.4400 70,000.00
Tukang Pipa L.02 OH 0.2880 90,000.00
Mandor L.04 OH 0.1440 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1050 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.72 (K3) Pemotongan 1 buah pipa baja 450 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.3990 70,000.00
Tukang Pipa L.02 OH 0.2800 90,000.00
Mandor L.04 OH 0.1400 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1070 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.73 (K3) Pemotongan 1 buah pipa baja 500 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.5580 70,000.00
Tukang Pipa L.02 OH 0.3120 90,000.00
Mandor L.04 OH 0.1560 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1070 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.74 (K3) Pemotongan 1 buah pipa baja 600 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.4370 70,000.00
Tukang Pipa L.02 OH 0.2870 90,000.00
Mandor L.04 OH 0.1440 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1130 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.75 (K3) Pemotongan 1 buah pipa baja 800 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.6240 70,000.00
Tukang Pipa L.02 OH 0.5250 90,000.00
Mandor L.04 OH 0.2620 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1660 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.76 (K3) Pemotongan 1 buah pipa baja 900 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.9710 70,000.00
Tukang Pipa L.02 OH 0.5940 90,000.00
Mandor L.04 OH 0.2970 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.1830 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.77 (K3) Pemotongan 1 buah pipa baja 1000 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 3.3190 70,000.00
Tukang Pipa L.02 OH 0.6640 90,000.00
Mandor L.04 OH 0.3320 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2010 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.78 (K3) Pemotongan 1 buah pipa baja 1100 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 3.6670 70,000.00
Tukang Pipa L.02 OH 0.7330 90,000.00
Mandor L.04 OH 0.3670 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2180 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.2.79 (K3) Pemotongan 1 buah pipa baja 1200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 4.0150 70,000.00
Tukang Pipa L.02 OH 0.8030 90,000.00
Mandor L.04 OH 0.4020 80,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Peralatan potong pipa hari 0.2360 3,500.00
T2/mekanik/cilinder saw JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

350.00
180.00
40.00
570.00

10.50
10.50

580.50
78.37
658.87

Jumlah Harga
(Rp)

980.00
630.00
80.00
1,690.00

10.50
10.50

1,700.50
229.57
1,930.07

Jumlah Harga
(Rp)

1,540.00
990.00
160.00
2,690.00

10.50
10.50
2,700.50
364.57
3,065.07

Jumlah Harga
(Rp)

2,170.00
1,350.00
240.00
3,760.00

10.50
10.50

3,770.50
509.02
4,279.52

Jumlah Harga
(Rp)

5,670.00
3,600.00
640.00
9,910.00

59.50
59.50

9,969.50
1,345.88
11,315.38

Jumlah Harga
(Rp)

8,960.00
5,760.00
1,040.00
15,760.00

105.00
105.00

15,865.00
2,141.78
18,006.78

Jumlah Harga
(Rp)

10,850.00
6,930.00
1,200.00
18,980.00

129.50
129.50

19,109.50
2,579.78
21,689.28

Jumlah Harga
(Rp)

23,170.00
14,940.00
2,640.00
40,750.00

301.00
301.00

41,051.00
5,541.89
46,592.89

Jumlah Harga
(Rp)

29,400.00
18,900.00
3,360.00
51,660.00

-
189.00
189.00

51,849.00
6,999.62
58,848.62

Jumlah Harga
(Rp)

36,260.00
23,310.00
4,160.00
63,730.00

241.50
241.50

63,971.50
8,636.15
72,607.65

Jumlah Harga
(Rp)

43,610.00
27,990.00
4,960.00
76,560.00

301.00
301.00

76,861.00
10,376.24
87,237.24

Jumlah Harga
(Rp)

76,230.00
49,050.00
8,720.00
134,000.00
-

560.00
560.00

134,560.00
18,165.60
152,725.60

Jumlah Harga
(Rp)

79,870.00
51,390.00
9,120.00
140,380.00

588.00
588.00

140,968.00
19,030.68
159,998.68

Jumlah Harga
(Rp)

89,950.00
57,870.00
10,320.00
158,140.00

668.50
668.50

158,808.50
21,439.15
180,247.65

Jumlah Harga
(Rp)

100,030.00
64,350.00
11,440.00
175,820.00

745.50
745.50

176,565.50
23,836.34
200,401.84

Jumlah Harga
(Rp)

110,110.00
70,830.00
12,560.00
193,500.00

826.00
826.00

194,326.00
26,234.01
220,560.01

Jumlah Harga
(Rp)

140.00
90.00
16.00
2,550.00
2,796.00

14.00
14.00

2,810.00
379.35
3,189.35

Jumlah Harga
(Rp)
420.00
270.00
80.00
5,325.00
6,095.00

17.50
17.50

6,112.50
825.19
6,937.69

Jumlah Harga
(Rp)

630.00
450.00
80.00
7,200.00
8,360.00

21.00
21.00

8,381.00
1,131.44
9,512.44

Jumlah Harga
(Rp)

1,120.00
720.00
160.00
9,075.00
11,075.00

31.50
31.50

11,106.50
1,499.38
12,605.88
Jumlah Harga
(Rp)

3,080.00
1,980.00
320.00
12,825.00
18,205.00

59.50
59.50

18,264.50
2,465.71
20,730.21

Jumlah Harga
(Rp)

4,690.00
2,970.00
560.00
16,575.00
24,795.00

80.50
80.50

24,875.50
3,358.19
28,233.69

Jumlah Harga
(Rp)

6,300.00
4,050.00
720.00
20,325.00
31,395.00

105.00
105.00

31,500.00
4,252.50
35,752.50

Jumlah Harga
(Rp)

12,390.00
7,920.00
1,440.00
27,825.00
49,575.00

192.50
192.50

49,767.50
6,718.61
56,486.11

Jumlah Harga
(Rp)

15,750.00
10,170.00
1,840.00
31,575.00
59,335.00

245.00
245.00

59,580.00
8,043.30
67,623.30

Jumlah Harga
(Rp)

19,390.00
12,510.00
2,240.00
35,325.00
69,465.00
-

297.50
297.50

69,762.50
9,417.94
79,180.44

Jumlah Harga
(Rp)

23,310.00
15,030.00
2,640.00
42,825.00
83,805.00

353.50
353.50

84,158.50
11,361.40
95,519.90

Jumlah Harga
(Rp)

42,070.00
27,090.00
4,800.00
57,825.00
131,785.00

626.50
626.50

132,411.50
17,875.55
150,287.05

Jumlah Harga
(Rp)
63,910.00
41,040.00
7,280.00
65,325.00
177,555.00

945.00
945.00

178,500.00
24,097.50
202,597.50

Jumlah Harga
(Rp)

78,750.00
50,580.00
8,960.00
72,825.00
211,115.00

1,162.00
1,162.00

212,277.00
28,657.40
240,934.40

Jumlah Harga
(Rp)

86,660.00
55,710.00
9,920.00
80,325.00
232,615.00

1,277.50
1,277.50

233,892.50
31,575.49
265,467.99
Jumlah Harga
(Rp)

113,330.00
72,810.00
12,960.00
87,825.00
286,925.00

1,669.50
1,669.50

288,594.50
38,960.26
327,554.76

Jumlah Harga
(Rp)

13,300.00
900.00
160.00
14,360.00

14.00
14.00

14,374.00
1,940.49
16,314.49

Jumlah Harga
(Rp)

40,600.00
2,610.00
480.00
43,690.00

14.00
14.00
43,704.00
5,900.04
49,604.04

Jumlah Harga
(Rp)

64,400.00
4,140.00
720.00
69,260.00

21.00
21.00

69,281.00
9,352.94
78,633.94

Jumlah Harga
(Rp)

91,700.00
5,940.00
1,040.00
98,680.00

31.50
31.50

98,711.50
13,326.05
112,037.55

Jumlah Harga
(Rp)

119,000.00
15,300.00
2,720.00
137,020.00

59.50
59.50

137,079.50
18,505.73
155,585.23

Jumlah Harga
(Rp)

165,900.00
21,330.00
3,760.00
190,990.00

80.50
80.50

191,070.50
25,794.52
216,865.02

Jumlah Harga
(Rp)

176,400.00
22,680.00
4,000.00
203,080.00

105.00
105.00

203,185.00
27,429.98
230,614.98

Jumlah Harga
(Rp)

51,660.00
33,210.00
5,920.00
90,790.00

-
192.50
192.50

90,982.50
12,282.64
103,265.14

Jumlah Harga
(Rp)

59,360.00
38,160.00
6,800.00
104,320.00

245.00
245.00

104,565.00
14,116.28
118,681.28

Jumlah Harga
(Rp)

65,870.00
42,390.00
7,520.00
115,780.00

297.50
297.50

116,077.50
15,670.46
131,747.96

Jumlah Harga
(Rp)

60,480.00
38,880.00
6,880.00
106,240.00
-

353.50
353.50

106,593.50
14,390.12
120,983.62

Jumlah Harga
(Rp)

109,690.00
70,470.00
12,560.00
192,720.00

626.50
626.50

193,346.50
26,101.78
219,448.28

Jumlah Harga
(Rp)

123,900.00
79,650.00
14,160.00
217,710.00

945.00
945.00

218,655.00
29,518.43
248,173.43

Jumlah Harga
(Rp)

138,180.00
88,830.00
15,760.00
242,770.00

1,162.00
1,162.00

243,932.00
32,930.82
276,862.82

Jumlah Harga
(Rp)

152,460.00
98,010.00
17,440.00
267,910.00

1,277.50
1,277.50

269,187.50
36,340.31
305,527.81

Jumlah Harga
(Rp)

166,740.00
107,190.00
19,040.00
292,970.00

1,669.50
1,669.50

294,639.50
39,776.33
334,415.83

Jumlah Harga
(Rp)

4,970.00
1,260.00
560.00
6,790.00

900.00
900.00

7,690.00
1,038.15
8,728.15

Jumlah Harga
(Rp)

7,840.00
1,980.00
880.00
10,700.00

3,000.00
3,000.00

13,700.00
1,849.50
15,549.50

Jumlah Harga
(Rp)

11,130.00
2,880.00
1,280.00
15,290.00

5,400.00
5,400.00

20,690.00
2,793.15
23,483.15

Jumlah Harga
(Rp)
25,620.00
6,570.00
2,960.00
35,150.00

16,200.00
16,200.00

51,350.00
6,932.25
58,282.25

Jumlah Harga
(Rp)

33,320.00
8,550.00
3,840.00
45,710.00

21,900.00
21,900.00

67,610.00
9,127.35
76,737.35

Jumlah Harga
(Rp)

35,840.00
9,180.00
4,080.00
49,100.00

23,700.00
23,700.00

72,800.00
9,828.00
82,628.00
Jumlah Harga
(Rp)

65,870.00
16,920.00
7,520.00
90,310.00

553.00
553.00

90,863.00
12,266.51
103,129.51

Jumlah Harga
(Rp)

79,590.00
20,430.00
9,120.00
109,140.00

616.00
616.00

109,756.00
14,817.06
124,573.06

Jumlah Harga
(Rp)

91,840.00
23,580.00
10,480.00
125,900.00

672.00
672.00

126,572.00
17,087.22
143,659.22
Jumlah Harga
(Rp)

91,630.00
23,580.00
10,480.00
125,690.00

672.00
672.00

126,362.00
17,058.87
143,420.87

Jumlah Harga
(Rp)

181,860.00
46,800.00
20,800.00
249,460.00

1,085.00
1,085.00

250,545.00
33,823.58
284,368.58

Jumlah Harga
(Rp)

235,900.00
60,660.00
26,960.00
323,520.00

1,333.50
1,333.50

324,853.50
43,855.22
368,708.72

Jumlah Harga
(Rp)

281,470.00
72,360.00
32,160.00
385,990.00

1,543.50
1,543.50

387,533.50
52,317.02
439,850.52

Jumlah Harga
(Rp)

331,170.00
85,140.00
37,840.00
454,150.00

1,771.00
1,771.00

455,921.00
61,549.34
517,470.34

Jumlah Harga
(Rp)

385,140.00
99,000.00
44,000.00
528,140.00

2,016.00
2,016.00
530,156.00
71,571.06
601,727.06

Jumlah Harga
(Rp)

1,960.00
540.00
240.00
2,740.00

129.50
129.50

2,869.50
387.38
3,256.88

Jumlah Harga
(Rp)

5,950.00
1,530.00
640.00
8,120.00

140.00
140.00

8,260.00
1,115.10
9,375.10

Jumlah Harga
(Rp)

9,310.00
2,430.00
1,040.00
12,780.00

-
147.00
147.00

12,927.00
1,745.15
14,672.15

Jumlah Harga
(Rp)

12,880.00
3,330.00
1,440.00
17,650.00

157.50
157.50

17,807.50
2,404.01
20,211.51

Jumlah Harga
(Rp)

33,320.00
8,550.00
3,840.00
45,710.00

-
-

210.00
210.00

45,920.00
6,199.20
52,119.20

Jumlah Harga
(Rp)

46,410.00
11,970.00
5,280.00
63,660.00
-

238.00
238.00

63,898.00
8,626.23
72,524.23

Jumlah Harga
(Rp)

52,150.00
13,410.00
5,920.00
71,480.00

252.00
252.00

71,732.00
9,683.82
81,415.82

Jumlah Harga
(Rp)

100,800.00
25,920.00
11,520.00
138,240.00

367.50
367.50

138,607.50
18,712.01
157,319.51

Jumlah Harga
(Rp)

97,930.00
25,200.00
11,200.00
134,330.00
-

374.50
374.50

134,704.50
18,185.11
152,889.61

Jumlah Harga
(Rp)

109,060.00
28,080.00
12,480.00
149,620.00

374.50
374.50

149,994.50
20,249.26
170,243.76

Jumlah Harga
(Rp)

100,590.00
25,830.00
11,520.00
137,940.00

395.50
395.50

138,335.50
18,675.29
157,010.79

Jumlah Harga
(Rp)

183,680.00
47,250.00
20,960.00
251,890.00

581.00
581.00

252,471.00
34,083.59
286,554.59

Jumlah Harga
(Rp)

207,970.00
53,460.00
23,760.00
285,190.00

640.50
640.50

285,830.50
38,587.12
324,417.62

Jumlah Harga
(Rp)

232,330.00
59,760.00
26,560.00
318,650.00

703.50
703.50

319,353.50
43,112.72
362,466.22

Jumlah Harga
(Rp)
256,690.00
65,970.00
29,360.00
352,020.00

763.00
763.00

352,783.00
47,625.71
400,408.71

Jumlah Harga
(Rp)

281,050.00
72,270.00
32,160.00
385,480.00

826.00
826.00

386,306.00
52,151.31
438,457.31
A.8.4.3 HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA

A.8.4.3.1 (K3) Pemasangan 1 buah Valve 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.4290 70,000.00
Tukang Pipa L.02 OH 0.7150 90,000.00
Mandor L.04 OH 0.1430 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Valve 150 mm buah 1.0000 11,501,600.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.1000 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.2 (K3) Pemasangan 1 buah Valve 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.7140 70,000.00
Tukang Pipa L.02 OH 0.8570 90,000.00
Mandor L.04 OH 0.1710 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Valve 200 mm buah 1.0000 18,370,000.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.3000 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.3 (K3) Pemasangan 1 buah Valve 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 1.7140 70,000
Tukang Pipa L.02 OH 0.8570 90,000
Mandor L.04 OH 0.1710 80,000

JUMLAH TENAGA KERJA


B BAHAN
Valve 250 mm buah 1.0000 30,897,900
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.4000 300,000
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.4 (K3) Pemasangan 1 buah Valve 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 2.0000 70,000
Tukang Pipa L.02 OH 1.0000 90,000
Mandor L.04 OH 0.2000 80,000

JUMLAH TENAGA KERJA


B BAHAN
Valve 300 mm buah 1.0000 40,675,800
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.5000 300,000
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.15 (K3) Pemasangan 1 buah Tee 150 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.1060 70,000.00
Tukang Pipa L.02 OH 0.0530 90,000.00
Mandor L.04 OH 0.0110 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Tee 150 mm buah 1.0000 203,560.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.0280 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.16 (K3) Pemasangan 1 buah Tee 200 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.2160 70,000.00
Tukang Pipa L.02 OH 0.1080 90,000.00
Mandor L.04 OH 0.0220 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Tee 200 mm buah 1.0000 367,690.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.0290 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.17 (K3) Pemasangan 1 buah Tee 250 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.3260 70,000.00
Tukang Pipa L.02 OH 0.1630 90,000.00
Mandor L.04 OH 0.0330 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Tee 250 mm buah 1.0000 639,630.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.0390 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.3.18 (K3) Pemasangan 1 buah Tee 300 mm


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Pekerja L.01 OH 0.4360 70,000.00
Tukang Pipa L.02 OH 0.2180 90,000.00
Mandor L.04 OH 0.0440 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Tee 300 mm buah 1.0000 960,260.00
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Tripot/Tackel & hari 0.5000 300,000.00
handle crane 2 T JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

100,030.00
64,350.00
11,440.00

175,820.00

11,501,600.00
11,501,600.00

30,000.00
30,000.00

11,707,420.00
1,580,501.70
13,287,921.70

Jumlah Harga (Rp)

119,980.00
77,130.00
13,680.00

210,790.00

18,370,000.00
18,370,000.00

90,000.00
90,000.00

18,670,790.00
2,520,556.65
21,191,346.65

Jumlah Harga (Rp)

119,980.00
77,130.00
13,680.00

210,790.00

30,897,900.00
30,897,900.00

120,000.00
120,000.00

31,228,690.00
4,215,873.15
35,444,563.15

Jumlah Harga (Rp)

140,000.00
90,000.00
16,000.00

246,000.00

40,675,800.00
40,675,800.00

150,000.00
150,000.00

41,071,800.00
5,544,693.00
46,616,493.00

Jumlah Harga (Rp)

7,420.00
4,770.00
880.00

13,070.00

203,560.00
203,560.00

8,400.00
8,400.00

225,030.00
30,379.05
255,409.05

Jumlah Harga (Rp)

15,120.00
9,720.00
1,760.00

26,600.00

367,690.00
367,690.00

8,700.00
8,700.00

402,990.00
54,403.65
457,393.65

Jumlah Harga (Rp)

22,820.00
14,670.00
2,640.00

40,130.00

639,630.00
639,630.00

11,700.00
11,700.00

691,460.00
93,347.10
784,807.10

Jumlah Harga (Rp)

30,520.00
19,620.00
3,520.00

53,660.00

960,260.00
960,260.00

150,000.00
150,000.00

1,163,920.00
157,129.20
1,321,049.20
A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN PIPA

A.8.4.5.1 (K3) Pengetesan 1 m pipa 50 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0020 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.2 (K3) Pengetesan 1 m pipa 75 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0040 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.3 (K3) Pengetesan 1 m pipa 100 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0080 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.4 (K3) Pengetesan 1 m pipa 150 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0180 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.5 (K3) Pengetesan 1 m pipa 200 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0310 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.6 (K3) Pengetesan 1 m pipa 250 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0490 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.7 (K3) Pengetesan 1 m pipa 300 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.0710 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.8 (K3) Pengetesan 1 m pipa 400 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.1260 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.9 (K3) Pengetesan 1 m pipa 500 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.1580 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.5.10 (K3) Pengetesan 1 m pipa 600 mm


No Uraian Kode Satuan Koefisien Harga Satuan
A TENAGA
Pekerja L.01 OH 0.0080 70,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Air test (air
m3 0.2830 15,000.00
bersih)
Bahan bakar liter 0.0600 7,600.00
Oli liter 0.0020 35,000.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga

560.00
64.00
624.00

30.00
456.00
70.00

556.00

1,180.00
159.30
1,339.30

Jumlah Harga

560.00
64.00
624.00

60.00
456.00
70.00

586.00

1,210.00
163.35
1,373.35

Jumlah Harga

560.00
64.00
624.00

120.00
456.00
70.00

646.00
1,270.00
171.45
1,441.45

Jumlah Harga

560.00
64.00
624.00

270.00
456.00
70.00

796.00

1,420.00
191.70
1,611.70

Jumlah Harga

560.00
64.00
624.00

465.00
456.00
70.00

991.00

1,615.00
218.03
1,833.03

Jumlah Harga

560.00
64.00
624.00

735.00
456.00
70.00

1,261.00

1,885.00
282.75
2,167.75

Jumlah Harga

560.00
64.00
624.00

1,065.00
456.00
70.00

1,591.00

2,215.00
332.25
2,547.25

Jumlah Harga

560.00
64.00
624.00

1,890.00
456.00
70.00

2,416.00

3,040.00
456.00
3,496.00

Jumlah Harga
560.00
64.00
624.00

2,370.00
456.00
70.00

2,896.00

3,520.00
528.00
4,048.00

Jumlah Harga

560.00
64.00
624.00

4,245.00
456.00
70.00

4,771.00

5,395.00
809.25
6,204.25
A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Tukang Listrik % 100.0000 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa listrik 5/8" btg 3.0000 12,000.00
Kabel m 24.0000 3,320.00
T Dus buah 3.0000 1,500.00
L Bow buah 4.0000 750.00
Las Dop buah 3.0000 17,850.00
Klem buah 24.0000 80.00
Mangkok buah 1.0000 1,200.00
Saklar buah 1.0000 24,000.00
Fitting buah 1.0000 8,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

A.8.4.6.2 (K3) Pemasangan 1 buah MCB


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
Tukang Listrik % 100.0000 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa listrik 5/8" btg 3.0000 12,000.00
Kabel m 15.0000 3,320.00
T Dus buah 1.0000 1,500.00
L Bow buah 2.0000 750.00
Klem biasa buah 24.0000 80.00
MCB buah 1.0000 48,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

80,000.00
80,000.00

36,000.00
79,680.00
4,500.00
3,000.00
53,550.00
1,920.00
1,200.00
24,000.00
8,000.00
211,850.00

291,850.00
43,777.50
335,627.50

Jumlah Harga
(Rp)

80,000.00
80,000.00

36,000.00
49,800.00
1,500.00
1,500.00
1,920.00
48,000.00
138,720.00

218,720.00
32,808.00
251,528.00
DAFTAR HARGA SATUAN DIHIT

NO. KODE ANALISA

I A.2.3.1
1 Dihit. UTP 1
A.4.4.3
1 Dihit. A.4.4.3.G.40/40. P
2 Dihit. A.4.4.3. W 20/40
3 Dihit. A.4.4.3. ACP PVDF
A.4.5.1
1 Dihit. A.4.5.1. Calsi
2 Dihit. Progips 10
Dihit. A.4.6.1 . GRC Uk
20
A.4.5.2
1 Dihit. A.4.5.2.3 Glaz
2 Dihit. A.4.5.2.6 Glaz
3 Dihit. A.4.5.2 Galva
A.4.6.2
1 Dihit. TF 12
2 Dihit. Grend 4
3 Dihit. HP 30
4 Dihit. Rambuncis
A.4.7.1
1 Dihit. A.4.7.1. RMP
L.1.2
1 Dihit. L.1.2.11
1.5.2
1 dihit 15.2.

1 Dihit. A.4.1.1.a
2 Dihit. A.4.1.1.b
DAFTAR HARGA SATUAN DIHIT

URAIAN PEKERJAAN SATUAN

PEKERJAAN TANAH
Pemasangan 1 m3 Urugan Tanah Padas ( dipadatkan dengan alat pemadat tangan ) M3
PEKERJAAN PENUTUP DINDING DAN LANTAI
Pemasangan 1 m2 Lantai Keramik 40x40 cm (putih/polos) m2
Pemasangan 1 m2 Dinding Keramik 20 x 40 cm m2
Pemasangan 1 m2 Penutup Dinding Luar dg ACP Rangka hollow Galvanis m2
PEKERJAAN LANGIT- LANGIT
Pemasangan 1 m2 Langit - Langit Calsiboard, Uk. (120 x 240) cm Tebal 3,5 mm m2
Pemasangan 1 m List Langit - Langit Profil Gipsum Lebar 10 cm m2
Pemasangan 1 m Lisplank Urat Kayu 20 cm m'
PEKERJAAN PENUTUP ATAP
Pemasangan 1 m2 Atap Genteng Press Jatiwangi Besar Glazur m2
Pemasangan 1 m Bubung Genteng Jatiwangi Besar Glazur M'
Pemasangan 1 m2 Atap Galvalum M2
PEKERJAAN KUNCI DAN KACA
Pemasangan 1 m2 Kaca Tempered Frameless 12 mm m2
Pemasangan 1 Buah Grendel Panjang 4" BH
Pemasangan 1 Pasang Tarikan Pintu Panjang 30 cm PS
Pemasangan 1 Buah Rambuncis Jendela Allumunium 12" PS
PEKERJAAN PENGECATAN
Pelapisan 1 m2 Plat Atap/Talang Dengan Lapisan Membran Waterproofing M2
PEKERJAAN LISTRIK
Pemasangan 1 m Titik Stop Kontak Dengan Kabel NYM 3 x 2,5 mm2 M

Pasang got type U 20 cm termasuk pasangan dinding M'


PEKERJAAN BEKISTING
Pemasangan 1 m2 bekisting kolom praktis m2
Pemasangan 1 m2 bekisting untuk ringbalok m2
HARGA SATUAN
(Rp)

213,071.28

229,571.91
297,307.58
815,667.75

38,552.55
30,335.71
43,670.94

112,677.13
123,783.10
109,215.38

1,574,459.52
91,231.30
237,646.30
29,158.15

89,403.38

231,199.50

135,305.00

313,742.38
282,529.88
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

Dihit. UTP 1 Pemasangan 1 m3 Urugan Tanah Padas ( dipadatkan dengan alat pem
Satua Harga
No Uraian Kode Koefisien
n Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.1368 70,000.00
Mandor L.04 OH 0.0274 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Tanah Padas Quarry - Lokasi Pekerjaan m3 1.2000 132,800.00
JUMLAH HARGA BAHAN
C PERALATAN
Stamper Jam 0.5000 33,200.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
engan alat pemadat tangan )
Jumlah Harga
(Rp)

9,576.00
2,192.00
11,768.00

159,360.00
159,360.00

16,600.00
16,600.00

187,728.00
25,343.28
213,071.28
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP

Dihit. A.4.4.3.G.40/40.Pemasangan 1 m2 Lantai Keramik 40x40 cm (putih/polos)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.7000
Tukang batu halus L.02 OH 0.3500
Kepala tukang batu L.03 OH 0.0350
Mandor L.04 OH 0.0350
JUMLAH TENAGA KERJA
B BAHAN
Keramik Lantai 40 x 40
Bh 6.8750
cm (putih/polos)
Semen Portland kg 8.1900
Semen warna Kg 1.6200
Pasir pasang (muntilan) m3 0.0450
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Dihit. A.4.4.3. ACP P Pemasangan 1 m2 Penutup Dinding Luar dg ACP Rangka hol
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.8000
Tukang allumunium L.02 OH 0.8000
Kepala tukang L.03 OH 0.1600
alumunium
Mandor L.04 OH 0.0400
JUMLAH TENAGA KERJA
B BAHAN
ACP Coating PVDF
Lbr 0.2500
(Outdoor)
Hollow Galvanis 20 x 40 x
m3 3.6000
0,35 mm
Hollow Galvanis 40 x 40 x m3 3.6000
0,35
ACP Bracing Buah 1.0000
Sealant Liter 0.5000
Paku Sekrup 3,5" Buah 10.0000
ACP Bracket Buah 8.0000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Dihit. A.4.4.3. W 20/4 Pemasangan 1 m2 Dinding Keramik 20 x 40 cm
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.9000
Tukang batu halus L.02 OH 0.4500
Kepala tukang batu L.03 OH 0.0450
Mandor L.04 OH 0.0450
JUMLAH TENAGA KERJA
B BAHAN
Keramik Dinding 20 x 40 Buah 13.5000
cm
Semen Portland Kg 9.3000
Semen warna Kg 1.9400
Pasir pasang (muntilan) m3 0.0180
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
LANTAI DAN PENUTUP DINDING

x40 cm (putih/polos)
Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 49,000.00
90,000.00 31,500.00
95,000.00 3,325.00
80,000.00 2,800.00
UMLAH TENAGA KERJA 86,625.00

9,000.00 61,875.00
1,400.00 11,466.00
15,000.00 24,300.00
400,000.00 18,000.00
UMLAH HARGA BAHAN 115,641.00

UMLAH HARGA ALAT

202,266.00
3,5% x D 27,305.91
229,571.91

ar dg ACP Rangka hollow Galvanis


Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 56,000.00
90,000.00 72,000.00
95,000.00 15,200.00
80,000.00 3,200.00
UMLAH TENAGA KERJA 146,400.00

985,000.00 246,250.00
8,000.00 28,800.00
12,500.00 45,000.00
45,000.00 45,000.00
92,000.00 46,000.00
120.00 1,200.00
20,000.00 160,000.00
UMLAH HARGA BAHAN 572,250.00

UMLAH HARGA ALAT

718,650.00
3,5% x D 97,017.75
815,667.75
0 x 40 cm
Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 63,000.00
90,000.00 40,500.00
95,000.00 4,275.00
80,000.00 3,600.00
UMLAH TENAGA KERJA 111,375.00

7,500.00 101,250.00
1,400.00 13,020.00
15,000.00 29,100.00
400,000.00 7,200.00
UMLAH HARGA BAHAN 150,570.00

UMLAH HARGA ALAT

261,945.00
3,5% x D 35,362.58
297,307.58
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

Dihit. A.4.5.1. Cals Pemasangan 1 m2 Langit - Langit Calsiboard, Uk. (120 x 240) cm
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.0300
Tukang kayu halus L.02 OH 0.0700
Kepala tukang kayu L.03 OH 0.0070
Mandor L.04 OH 0.0040
JUMLAH TENAGA KERJA
B BAHAN
Calsiboard 122 x 244 cm tebal Lembar 0.3640
3,5 mm
Paku Plafon kg 0.1100
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Dihit. Progips 10 Pemasangan 1 m List Langit - Langit Profil Gipsum Lebar 10 c


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.0500
Tukang Kayu halus L.02 OH 0.0500
Kepala tukang kayu L.03 OH 0.0050
Mandor L.04 OH 0.0030
JUMLAH TENAGA KERJA
B BAHAN
List Profil Gipsum lebar 10 cm m 1.0500
Lem Gipsum Kg 0.0100
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
d, Uk. (120 x 240) cm Tebal 3,5 mm
Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 2,100.00
90,000.00 6,300.00
95,000.00 665.00
80,000.00 320.00
UMLAH TENAGA KERJA 9,385.00

63,000.00 22,932.00
15,000.00 1,650.00
UMLAH HARGA BAHAN 24,582.00

UMLAH HARGA ALAT

33,967.00
3,5% x D 4,585.55
38,552.55

Gipsum Lebar 10 cm
Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 3,500.00
90,000.00 4,500.00
95,000.00 475.00
80,000.00 240.00
UMLAH TENAGA KERJA 8,715.00

17,000.00 17,850.00
16,250.00 162.50
UMLAH HARGA BAHAN 18,012.50

UMLAH HARGA ALAT

26,727.50
3,5% x D 3,608.21
30,335.71
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

Dihit. A.4.5.2.3 Pemasangan 1 m2 Atap Genteng Press Jatiwangi Besar Glazur


Satua
No Uraian Kode Koefisien
n
A TENAGA
Pekerja L.01 OH 0.1500
Tukang kayu kasar L.03 OH 0.0750
Kepala tukang kayu L.11 OH 0.0080
Mandor L.15 OH 0.0080
JUMLAH TENAGA KERJA
B BAHAN
Genteng Press Jatiwangi Besar
buah 18.0000
Glazur Transparan/Coklat/Hitam
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Dihit. A.4.5.2.6 Pemasangan 1 m Bubung Genteng Jatiwangi Besar Glazur


Satua
No Uraian Kode Koefisien
n
A TENAGA
Pekerja L.01 OH 0.4000
Tukang kayu kasar L.03 OH 0.2000
Kepala tukang kayu L.11 OH 0.0200
Mandor L.15 OH 0.0020
JUMLAH TENAGA KERJA
B BAHAN
Bubungan Press Jatiwangi Glazur
Buah 4.0000
Transparan/Coklat/Hitam
Semen Portland Kg 8.0000
Pasir pasang (muntilan) m3 0.0320
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
angi Besar Glazur
Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 10,500.00
85,000.00 6,375.00
95,000.00 760.00
80,000.00 640.00
UMLAH TENAGA KERJA 18,275.00

4,500.00 81,000.00
UMLAH HARGA BAHAN 81,000.00

UMLAH HARGA ALAT

99,275.00
3,5% x D 13,402.13
112,677.13

Besar Glazur
Harga Jumlah
Satuan (Rp) Harga (Rp)

70,000.00 28,000.00
85,000.00 17,000.00
95,000.00 1,900.00
80,000.00 160.00
UMLAH TENAGA KERJA 47,060.00

9,500.00 38,000.00
1,400.00 11,200.00
400,000.00 12,800.00
UMLAH HARGA BAHAN 62,000.00

UMLAH HARGA ALAT

109,060.00
3,5% x D 14,723.10
123,783.10
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

Dihit. TF 12 Pemasangan 1 m2 Kaca Tempered Frameless 12 mm


Satua Harga
No Uraian Kode Koefisien
n Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.0150 70,000.00
Tukang kayu halus L.02 OH 0.1500 90,000.00
Kepala tukang kayu L.03 OH 0.0150 95,000.00
Mandor L.04 OH 0.0008 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kaca Flat Tempered 12 mm m2 1.1000 525,000.00
Floor Hinges (Engsel Lantai) Buah 0.5291 1,500,000.00
JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Dihit. Grend
4 Pemasangan 1 Buah Grendel Panjang 4"
Satua Harga
No Uraian Kode Koefisien
n Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.0200 70,000.00
Tukang kayu halus L.02 OH 0.2000 90,000.00
Kepala tukang kayu L.03 OH 0.0200 95,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Grendel 4" kuning/silver Buah 1.0000 59,000.00
JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Dihit. HP 30 Pemasangan 1 Pasang Tarikan Pintu Panjang 30 cm


Satua Harga
No Uraian Kode Koefisien
n Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.0200 70,000.00
Tukang kayu halus L.02 OH 0.2000 90,000.00
Kepala tukang kayu L.03 OH 0.0200 95,000.00
Mandor L.04 OH 0.0010 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Tarikan Pintu Panjang 30 cm Pasang 1.0000 188,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)

Dihit. Rambu Pemasangan 1 Buah Rambuncis Jendela Allumunium 12"


Satua Harga
No Uraian Kode Koefisien
n Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.0100 70,000.00
Tukang kayu halus L.02 OH 0.1000 90,000.00
Kepala tukang kayu L.03 OH 0.0100 95,000.00
Mandor L.04 OH 0.0005 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Rambuncis (Handle jendela Buah 1.0000 15,000.00
alumunium) JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(Rp)

1,050.00
13,500.00
1,425.00
64.00
16,039.00

577,500.00
793,650.00
1,371,150.00

1,387,189.00
187,270.52
###

Jumlah Harga
(Rp)

1,400.00
18,000.00
1,900.00
80.00
21,380.00

59,000.00
59,000.00

80,380.00
10,851.30
91,231.30

Jumlah Harga
(Rp)

1,400.00
18,000.00
1,900.00
80.00
21,380.00

188,000.00
188,000.00
209,380.00
28,266.30
237,646.30

Jumlah Harga
(Rp)

700.00
9,000.00
950.00
40.00
10,690.00

15,000.00
15,000.00

25,690.00
3,468.15
29,158.15
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
Dihit. A.4.7.1.
Pelapisan 1 m2 Plat Atap/Talang Dengan Lapisan Membran Waterproofi
RMP
Harga
No Uraian Kode Satuan Koefisien
Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.0200 70,000.00
Tukang cat L.02 OH 0.0630 70,000.00
Kepala tukang cat L.03 OH 0.0063 90,000.00
Mandor L.04 OH 0.0030 80,000.00
JUMLAH TENAGA KERJA
B BAHAN
Serat Fiberglass m2 1.1000 15,000.00
Semen Waterproofer Kg 1.6250 22,500.00
Cat Pelapis Kg 0.2300 83,000.00
Waterproofer JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Membran Waterproofing
Jumlah
Harga (Rp)

1,400.00
4,410.00
567.00
240.00
6,617.00

16,500.00
36,562.50
19,090.00
72,152.50

78,769.50
10,633.88
89,403.38
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

Dihit. TU PVC Pemasangan 1 m Talang Air Hujan PVC Persegi

No Uraian Kode

A TENAGA
Pekerja L.01
Tukang kayu halus L.02
Kepala tukang kayu L.03
Mandor L.04

B BAHAN
Talang PVC Persegi Abu-abu 4"
Perlengkapan 35% x talang PVC

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Dihit. T 1/2 Pemasangan 1 m Talang Air Hujan 1/2 PVC


PVC

No Uraian Kode

A TENAGA
Pekerja L.01
Tukang kayu halus L.02
Kepala tukang kayu L.03
Mandor L.04

B BAHAN
Talang PVC 1/2 Lingkaran
Perlengkapan 35% x talang PVC

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Dihit. T 1/2 Pemasangan 1 m Talang Air Hujan 1/2 Lingkaran 6"
Galva

No Uraian Kode

A TENAGA
Pekerja L.01
Tukang kayu halus L.02
Kepala tukang kayu L.03
Mandor L.04

B BAHAN
Talang Metal Setengah Lingkaran 6"
Perlengkapan 35% x talang PVC

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Dihit. ST. Pemasangan 1 Unit Septictank Dinding Bata Trassram 2x1, 5x1,5 m
Tipe A
No Uraian Kode

A+B TENAGA DAN BAHAN


Galian Tanah
Urugan Kembali
Urugan Pasir
Pondasi Batu Kosong ( anstamping)
Pas. Bata Tebal 1 Bata 1Pc : 3PP
Pas. Bata Tebal 1/2 Bata 1Pc : 3PP
Plesteran 1PC : 3PP, tebal 15mm
Beton Mutu f' c=14,5 Mpa (K200)
Pembesian
Bekisting
Pasang Pipa Galvanis 1 1/2"

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Dihit. ST. Pemasangan 1 Unit Septictank Dinding Bata Trassram 1,5x1, 2x1,7
Tipe B
No Uraian Kode

A+B TENAGA DAN BAHAN


Galian Tanah
Urugan Kembali
Urugan Pasir
Pondasi Batu Kosong ( anstamping)
Pas. Bata Tebal 1 Bata 1Pc : 3PP
Pas. Bata Tebal 1/2 Bata 1Pc : 3PP
Plesteran 1PC : 3PP, tebal 15mm
Beton Mutu f' c=14,5 Mpa (K200)
Pembesian
Bekisting
Pasang Pipa Galvanis 1 1/2"

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Dihit. BF 06 Pembuatan 1 Unit Septictank Bio Filter Kapasitas 6 orang

No Uraian Kode

A+B TENAGA DAN BAHAN


Galian Tanah
Urugan Kembali
Urugan Pasir
Septic Tank Bio Filter Volume 1850 Liter Kapastas 4-6 Ora

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Dihit. BF 08 Pembuatan 1 Unit Septictank Bio Filter Kapasitas 8 orang


No Uraian Kode

A+B TENAGA DAN BAHAN


Galian Tanah
Urugan Kembali
Urugan Pasir
Septic Tank Bio Filter Volume 2145 Liter Kapastas 6-8 Ora

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

Dihit. BF 12 Pembuatan 1 Unit Septictank Bio Filter Kapasitas 12 orang

No Uraian Kode

A+B TENAGA DAN BAHAN


Galian Tanah
Urugan Kembali
Urugan Pasir
Septic Tank Bio Filter Volume 3000 Liter Kapastas 8-12 O

C PERALATAN

D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
DALAM GEDUNG

Harga Jumlah Harga


Satuan Koefisien
Satuan (Rp) (Rp)

OH 0.0360 70,000.00 2,520.00


OH 0.0600 90,000.00 5,400.00
OH 0.0060 95,000.00 570.00
OH 0.0020 80,000.00 160.00
JUMLAH TENAGA KERJA 8,650.00

m 1.2000 43,000.00 51,600.00


Ls 0.3500 43,000.00 15,050.00
JUMLAH HARGA BAHAN 66,650.00

JUMLAH HARGA ALAT

75,300.00
13,5% x D 10,165.50
85,465.50

Harga Jumlah Harga


Satuan Koefisien
Satuan (Rp) (Rp)

OH 0.0360 70,000.00 2,520.00


OH 0.0600 90,000.00 5,400.00
OH 0.0060 95,000.00 570.00
OH 0.0020 80,000.00 160.00
JUMLAH TENAGA KERJA 8,650.00

m 1.2000 39,000.00 46,800.00


Ls 0.3500 39,000.00 13,650.00
JUMLAH HARGA BAHAN 60,450.00

JUMLAH HARGA ALAT

69,100.00
13,5% x D 9,328.50
78,428.50
gkaran 6"

Harga Jumlah Harga


Satuan Koefisien
Satuan (Rp) (Rp)

OH 0.0360 70,000.00 2,520.00


OH 0.0600 90,000.00 5,400.00
OH 0.0060 95,000.00 570.00
OH 0.0020 80,000.00 160.00
JUMLAH TENAGA KERJA 8,650.00

m 1.2000 56,000.00 67,200.00


Ls 6.0000 56,000.00 19,600.00
JUMLAH HARGA BAHAN 86,800.00

JUMLAH HARGA ALAT

95,450.00
13,5% x D 12,885.75
108,335.75

ta Trassram 2x1, 5x1,5 m


Harga Jumlah Harga
Satuan Koefisien
Satuan (Rp) (Rp)

m3 14.1178 75,591.00 1,067,175.60 dilihat A.2.3.1.2 Penggalian 1 m3 tan


m3 0.3309 14,755.00 4,882.21 dilihat A.2.3.1.9 Pengurugan kembali
m3 0.5941 297,143.00 176,539.31 dilihat A.2.3.1.11 Pengurugan 1 m3 de
m3 1.2177 616,219.88 750,344.32 dilihat A.3.2.1.9 (K3) Pemasangan 1
m2 16.6869 261,992.05 4,371,834.67 dilihat A. 4.4.1.2 Pemasangan 1m2 di
m2 8.6868 125,154.18 1,087,193.61 dilihat A. 4.4.1.8 campuran 1SP
Pemasangan 1m2: 3PP
di
m2 21.6241 64,934.94 1,404,162.44 dilihat A.4.4.2.3 campuran
Pemasangan 1SP : 3PP
1 m2 p
m3 0.6920 ### 881,031.55 dilihat A.4.1.1.6 Membuat 1 m3 beto
Kg 161.1051 14,151.75 2,279,918.87 dilihat A.4.1.1.17 Pembesian 10 kg den
m2 6.1971 706,055.13 4,375,500.15 dilihat A.4.1.1.24 (K3) Pemasangan 1 m
m 1.8000 161,306.20 2,903.51 dilihat A.5.1.1 22 Pemasangan 1 m pi
JUMLAH HARGA BAHAN 16,401,486.24

JUMLAH HARGA ALAT

16,401,486.24
-
###

ta Trassram 1,5x1, 2x1,7 m


Harga Jumlah Harga
Satuan Koefisien
Satuan (Rp) (Rp)

m3 9.6000 75,591.00 725,673.60


m3 0.2250 14,755.00 3,319.88
m3 0.4040 297,143.00 120,045.77
m3 0.8280 616,219.88 510,230.06
m2 11.3470 261,992.05 2,972,823.79
m2 5.9070 125,154.18 739,285.74
m2 14.7043 64,934.94 954,822.82
m3 0.4674 ### 595,075.82
Kg 109.5506 14,151.75 1,550,332.43
m2 4.2140 706,055.13 2,975,316.30
m 1.8000 161,306.20 2,903.51
JUMLAH HARGA BAHAN 11,149,829.71

JUMLAH HARGA ALAT

11,149,829.71
-
###

pasitas 6 orang
Harga Jumlah Harga
Satuan Koefisien
Satuan (Rp) (Rp)

m3 9.6000 75,591.00 725,673.60


m3 0.2250 14,755.00 3,319.88
m3 0.4040 297,143.00 120,045.77
Buah 1.0000 ### 5,300,000.00
JUMLAH HARGA BAHAN 6,149,039.25

JUMLAH HARGA ALAT

6,149,039.25
13,5% x D 830,120.30
###

pasitas 8 orang
Harga Jumlah Harga
Satuan Koefisien
Satuan (Rp) (Rp)

m3 9.6000 75,591.00 725,673.60


m3 0.2250 14,755.00 3,319.88
m3 0.4040 297,143.00 120,045.77
Buah 1.0000 ### 6,400,000.00
JUMLAH HARGA BAHAN 7,249,039.25

JUMLAH HARGA ALAT

7,249,039.25
13,5% x D 978,620.30
###

pasitas 12 orang
Harga Jumlah Harga
Satuan Koefisien
Satuan (Rp) (Rp)

m3 9.6000 75,591.00 725,673.60


m3 0.2250 14,755.00 3,319.88
m3 0.4040 297,143.00 120,045.77
Buah 1.0000 ### 8,600,000.00
JUMLAH HARGA BAHAN 9,449,039.25

JUMLAH HARGA ALAT

9,449,039.25
13,5% x D 1,275,620.30
###
Penggalian 1 m3 tanah biasa sedalam 2 m
Pengurugan kembali 1 m3 galian tanah
Pengurugan 1 m3 dengan pasir urug
(K3) Pemasangan 1 m3 batu kosong (anstamping)
Pemasangan 1m2 dinding bata merah tebal 1 batu
campuran 1SP
Pemasangan 1m2: 3PP
dinding bata merah tebal batu
campuran
Pemasangan 1SP : 3PP
1 m2 plesteran 1SP : 3PP tebal 15mm
Membuat 1 m3 beton mutu fc = 16,9 Mpa
Pembesian 10 kg dengan besi polos
K3) Pemasangan 1 m2 bekisting untuk lantai
Pemasangan 1 m pipa galvanis diameter 1
Dihit.
Pemasangan 1 m Titik Stop Kontak Dengan Kabel NYM 3 x 2,5 mm2
L.1.2.11
Harga Satuan
No Kode Satuan Koefisien
(Rp)
A TENAGA

Tukang listrik L.02 OH 0.3750 80,000.00

JUMLAH TENAGA KERJA


B BAHAN
Pipa Conduit 5/8" btg 3.0000 12,000.00
Kabel NYM 3 x 2 1/2 mm2 m 10.0000 9,620.00
T Dus buah 3.0000 1,500.00
L Bow buah 4.0000 750.00
Klem buah 10.0000 80.00
Mangkok buah 1.0000 1,200.00
Stop Kontak buah 1.0000 32,000.00
JUMLAH BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
mm2

Jumlah Harga
(Rp)

30,000.00

30,000.00

36,000.00
96,200.00
4,500.00
3,000.00
800.00
1,200.00
32,000.00
173,700.00

203,700.00
27,499.50
231,199.50
XVIII KODE ANALISA
HARGA SATUAN PEKERJAAN DINDING PEMISAH (PARTISI)

1 Dihit.Holo Gips 9Pasang Partisi Dobel Gipsum Board 9 mm Rangka Hollow M


2 Dihit.Holo Ply 6 Pasang Partisi Dobel Plywood 6 mm Rangka Hollow Meni 4x
3 Dihit.Holo Grc Pasang Partisi Dobel GRC Board 9 mm Rangka Hollow Meni
4 Dihit.Stud Gips Pasang Partisi Dobel Gipsum Board 9 mm Rangka Metal St
5 Dihit.Stud Ply 6 Pasang Partisi Dobel Plywood 6 mm Rangka Metal Stud / A
6 Dihit.Stud Grc Pasang Partisi Dobel GRC Board 9 mm Rangka Metal Stud
AN DINDING PEMISAH (PARTISI)
SATUANHARGA SATUAN

um Board 9 mm Rangka Hollow M m 345,000.00


ood 6 mm Rangka Hollow Meni 4x m 365,000.00
Board 9 mm Rangka Hollow Meni m 385,000.00
um Board 9 mm Rangka Metal St m 445,000.00
ood 6 mm Rangka Metal Stud / A m 480,000.00
Board 9 mm Rangka Metal Stud m 500,000.00
dihit 15.2. Pasang got type U 20 cm termasuk pasangan dinding

No Uraian Kode Satuan Koefisien Harga Satuan


(Rp)
A TENAGA KERJA

JUMLAH HARGA TENAGA KERJA


B BAHAN
1 Got normal U-20 M.271 buah 1.000 65,000.00

JUMLAH HARGA BAHAN


C SUB PEKERJAAN
1 Siar 1 pc : 2 ps M2 0.016 45,470.82
2 Mengurug pasir M3 0.010 241,527.00
3 Menggali tanah M3 0.200 42,817.00
4 Pasangan bata 1 : 6 M3 0.120 105,000.00
5 Plester 1 : 3 M2 0.500 59,812.00
JUMLAH HARGA SUB PEKERJAAN

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah
Harga
(Rp)

65,000.00

65,000.00

727.53
2,415.27
8,563.40
12,600.00
29,906.00
54,212.20

119,212.20
16,093.65
135,305.00
Dihit. A.4.6.1 . GRC Pemasangan 1 m Lisplank Urat Kayu 20 cm
Koefisi
No Uraian Kode Satuan
en
A TENAGA
Pekerja L.01 OH ###
Tukang kayu kasar L.03 OH ###
Kepala tukang kayu L.11 OH ###
Mandor L.15 OH ###
JUMLAH TENAGA KERJA
B BAHAN
Lisplank GRC Urat Kayu 20 cm (200x Lbr ###
Paku Plafon Kg ###
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 13,5% x D
F Harga Satuan Pekerjaan (D+E)
Harga Satuan Jumlah Harga
(Rp) (Rp)

Mohon Cek ! 9,800.00


Mohon Cek ! 5,950.00
Mohon Cek ! 665.00
Mohon Cek ! 560.00
JUMLAH TENAGA KERJA 16,975.00
-
Mohon Cek ! 20,001.60
15,000.00 1,500.00
JUMLAH HARGA BAHAN 21,501.60

JUMLAH HARGA ALAT

38,476.60
13,5% x D 5,194.34
43,670.94

Anda mungkin juga menyukai