PEKERJAAN :
LOKASI :
TAHUN :
HARGA
NO URAIAN PEKERJAAN SAT VOLUME KODE SATUAN
ANALISA
(Rp.)
I PEKERJAAN PERSIAPAN
1 Papan Nama Proyek bh 1.00 1.00 Ls 275,000.00
2 Uitzet dan Bouplank m' 124.00 124.00 A.2.2.1.4 141,733.13
3 Direksi Keet m2 24.00 24.00 Ls 200,000.00
4 Pembersihan dan Bongkaran ls 1.00 1.00 Ls 2,000,000.00
II PEKERJAAN TANAH
1 Galian Tanah 1 meter m3 66.08 66.08 A.2.3.1.1 44,179.88
2 Galian Tanah 2 Meter m3 28.48 28.48 A.2.3.1.2 53,986.28
3 Urugan Tanah Kembali m3 31.52 31.52 A.2.3.1.9 14,726.63
4 Urugan Pasir m3 9.39 9.39 A.2.3.1.11 283,261.95
5 Urugan Tanah Padas m3 94.50 94.50 Dihit 138,384.88
10 Tangga
Beton K-200 m3 - A.4.1.1.6 1,151,201.12
Besi Tulangan 10kg - A.4.1.1.17 156,292.91
Bekisting m2 - A.4.1.1.26 457,638.81
IX PEKERJAAN CAT
1 Cat Tembok m2 - A.4.7.1.10 16,506.87
2 Cat Plafond m2 - A.4.7.1.10 16,506.87
X PEKERJAAN LISTRIK
1 Sambungan PLN 1300 watt Baru unit - Ls 4,500,000.00
2 Instalasi Titik Lampu, Saklar dan Stop Kontak titik - Ls 200,000.00
3 Lampu SL 30 Watt buah - Ls 60,000.00
4 Lampu SL 5 Watt buah - Ls 40,000.00
5 Stop Kontak buah - Ls 35,000.00
6 Saklar Tunggal buah - Ls 30,000.00
7 Saklar Ganda buah - Ls 35,000.00
JUMLAH :
PPN 10% :
TOTAL :
DIBULATKAN :
JUMLAH
HARGA
(Rp.)
275,000.00
17,574,907.50
4,800,000.00
2,000,000.00
24,649,907.50
2,919,406.14
1,537,529.11
464,183.22
2,659,829.71
13,077,370.69
20,658,318.87
43,165,268.17
-
-
-
-
43,165,268.17
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
JUMLAH
HARGA
(Rp.)
-
-
-
-
-
-
JUMLAH
HARGA
(Rp.)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
88,473,494.54
8,847,349.45
97,320,844.00
97,320,000.00
L1 L2 T P J V
BACK UP VOLUME
PEKERJAAN :
LOKASI :
TAHUN :
I PEKERJAAN PERSIAPAN
1 Papan Nama Proyek = 1.00
2 Uitzet dan Bouplank = 124.00
3 Direksi Keet = 24.00
4 Pembersihan dan Bongkaran = 1.00
PANJANG BANGUNAN
PONDASI TYPE 1 PONDASI TYPE 2
V 12.00 H 22.00 VH 2.50
12.00 3.50 7.00
12.00 1.50 2.50
2.50 1.50
3.00 1.50
3.00 1.50
12.00 2.00
22.00
56.50 55.50 112.00 12.00
II PEKERJAAN TANAH
1 Galian Tanah 1 meter
Pondasi Type 1
V 0.70 x 0.80 x 112.00 = 62.72
Pondasi Type 2
V 0.70 x 0.40 x 12.00 = 3.36
Total = 66.08
Footplat Type 2
V 0.80 x 0.80 x 2.00 x 14.00 = 17.92
Footplat Type 2
V 0.80 x 0.80 x 2.00 x 2.00 = 2.56
Total = 28.48
3 Urugan Tanah Kembali
Galian Tanah 1 meter 66.08
Galian Tanah 2 meter 28.48
Total = 31.52
3.00
4 Urugan Pasir
Pondasi Type 1
V 0.70 x 0.10 x 112.00 = 7.84
Pondasi Type 2
V 0.70 x 0.10 x 12.00 = 0.84
Footplat Type 1
V 1.00 x 1.00 x 0.05 x 4.00 = 0.20
Footplat Type 2
V 0.80 x 0.80 x 0.05 x 14.00 = 0.45
Footplat Type 2
V 0.80 x 0.80 x 0.05 x 2.00 = 0.06
Total = 9.39
Ambal
V 7.00 x 2.50 x 0.60 = 10.50
Total = 94.50
Total = 46.40
Ornamen depan
V1 2.00 x 1.50 x 2.00 = 6.00
V2 3.00 x 3.00 x 2.00 = 6.00
V3 2.00 x 4.00 x 1.00 = 2.00
Gunungan
V1 12.00 / 2.00 x 2.45 = 14.70
V2 3.50 / 2.00 x 1.25 x 2.00 = 4.38
Total = 561.18
LUASAN LUBANG
3 Plesteran 1Pc : 5Psr. Muntilan
4 Acian Beton
5 Pas. Rooster