UJIAN AKHIR SEMESTER GENAP


TAHUN AKADEMIK 2016/2017
Mata Kuliah : REKAYASA PERENCANAAN DAN PENGENDALIAN PROYEK
KELAS A2
Program Studi : Teknik Sipil
Hari/ tgl : Rabu, 7 Juni 2017
Waktu : 90 menit
Sifat : Buka Buku
Dosen : Arif Kurniawan S, ST, MT

RENCANA ANGGARAN BIAYA (RAB)


PEKERJAAN PEMBANGUNAN GUDANG SEMBAKO

HARGA SAT JML HARGA JML TOTAL


NO URAIAN PEKERJAAN VOLUME SAT
(Rp) (Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 100.00 m2 Rp 9,000.00 Rp 900,000.00
2 Pasangan bouplang 46.00 m1 Rp 40,000.00 Rp 1,840,000.00
Rp 2,740,000.00 Rp 2,740,000.00

II PEKERJAAN TANAH DAN PASIR


1 Galian tnh Pondasi 64.00 m3 Rp 30,000.00 Rp 1,920,000.00
2 Urug tanah kembali 16.00 m3 Rp 15,000.00 Rp 240,000.00
3 Urug tanah peninggian level bang. 90.00 m3 Rp 100,000.00 Rp 9,000,000.00
4 Urug pasir bwh lantai 4.50 m3 Rp 150,000.00 Rp 675,000.00
Rp 11,835,000.00 Rp 11,835,000.00

III PEKERJAAN PASANGAN


1 Pas Pondasi bt kali 1:5 35.00 m3 Rp 700,000.00 Rp 24,500,000.00
2 Pas Rollag Bata 1:5 8.40 m' Rp 30,000.00 Rp 252,000.00
3 Pas Dinding 1/2 bata 1:5 142.59 m2 Rp 95,000.00 Rp 13,546,050.00
4 Pek Plesteran dan Acian dinding 285.18 m2 Rp 55,000.00 Rp 15,684,900.00
5 Pek Sponengan 196.00 m1 Rp 15,000.00 Rp 2,940,000.00
Rp 56,922,950.00 Rp 56,922,950.00

IV PEKERJAAN BETON
1 Pek Sloof Beton 15/20 1:2:3 1.44 m3 Rp 4,000,000.00 Rp 5,760,000.00
2 Pek Kolom Beton 15/15 1:2:3 1.10 m3 Rp 4,000,000.00 Rp 4,410,000.00
3 Pek Balok Beton 15/20 1 : 2 : 3 1.94 m3 Rp 4,000,000.00 Rp 7,740,000.00
4 Pek Rabat Beton 1:3:5 90.00 m2 Rp 50,000.00 Rp 4,500,000.00
Rp 22,410,000.00 Rp 22,410,000.00
V PEKERJAAN KERAMIK
1 Pas Lantai keramik 40x40 kw I 54.00 m2 Rp 160,000.00 Rp 8,640,000.00
2 Pas Lantai keramik KM Anti Slip 40x4 36.00 m2 Rp 160,000.00 Rp 5,760,000.00
Rp 14,400,000.00 Rp 14,400,000.00

VI PEKERJAAN KUSEN PINTU DAN JENDELA


1 Pas PintuUtama 3.00 unit
Pas Kusen kayu bangkire 6/12 27.00 m1 Rp 120,000.00 Rp 3,240,000.00
Pas Daun Pintu 6.00 bh Rp 900,000.00 Rp 5,400,000.00
Pas Handel Pintu Utama 6.00 psg Rp 200,000.00 Rp 1,200,000.00
Pas Spanolet 3.00 bh Rp 250,000.00 Rp 750,000.00
Pas Engsel 4" 12.00 psg Rp 20,000.00 Rp 240,000.00
Pas Daun jendela kecil 6.00 bh Rp 400,000.00 Rp 2,400,000.00
Pas Engsel 3" 3.00 psg Rp 20,000.00 Rp 60,000.00
Pas gerendel jago 6.00 bh Rp 20,000.00 Rp 120,000.00
Pas kait angin 6.00 bh Rp 20,000.00 Rp 120,000.00

2 Pas Jendela Boven 3.00 unit


Pas Kusen kayu bangkire 6/12 19.80 m1 Rp 120,000.00 Rp 2,376,000.00
Pas Daun jendela 9.00 bh Rp 400,000.00 Rp 3,600,000.00
Pas Engsel 3" 9.00 psg Rp 20,000.00 Rp 180,000.00
Pas gerendel jago 9.00 bh Rp 20,000.00 Rp 180,000.00
Pas kait angin 9.00 bh Rp 20,000.00 Rp 180,000.00

Rp 20,046,000.00 Rp 20,046,000.00

VII PEKERJAAN PLAFOND


1 Pas Plafond Kalsiboard dicoumpon 100.00 m2 Rp 140,000.00 Rp 14,000,000.00
Rp 14,000,000.00 Rp 14,000,000.00

X PEKERJAAN PENGECATAN
1 Pek Cat Dinding Catylac 285.18 m2 Rp 35,000.00 Rp 9,981,300.00
2 Pek Cat Plafon Catylac 100.00 m2 Rp 35,000.00 Rp 3,500,000.00
3 Pek Cat Lisplang 34.00 m1 Rp 20,000.00 Rp 680,000.00
4 Pek Cat Kusen 46.80 m1 Rp 35,000.00 Rp 1,638,000.00
5 Pek Cat Daun Pintu 7.20 m2 Rp 60,000.00 Rp 432,000.00
6 Pek Cat Daun Jendela 36.00 m1 Rp 35,000.00 Rp 1,260,000.00
Rp 13,481,300.00 Rp 13,481,300.00

XI PEKERJAAN ATAP DEPAN


1 Pas Rangka Atap Glugu, 8/12, reng, 7.20 m3 Rp 3,500,000.00 Rp 25,200,000.00
Pas murplat, Gording 8/12 100.00 m1 Rp 40,000.00 Rp 4,000,000.00
2 Pas Asbes 110.00 m2 Rp 40,000.00 Rp 4,400,000.00
3 Pas talang U 20.00 m1 Rp 50,000.00 Rp 1,000,000.00
4 Pas Lisplang Kayu Kruing 2/20 34.00 m1 Rp 60,000.00 Rp 2,040,000.00
Rp 36,640,000.00 Rp 36,640,000.00

JUMLAH TOTAL PEKERJAAN GUDANG Rp 192,475,250.00

JUMLAH : Rp 192,475,250.00
Dibulatkan :

BUATLAH TIME SCHEDULLE PROYEK DIATAS


DENGAN WAKTU PROYEK 15 MINGGU
JAWABAN DISIMPAN DI FOLDER D, RPP, KELAS, NAMA, NO MHS
dan dikirim email ke arifkurniawan2537@yahoo.com

Anda mungkin juga menyukai

  • Tugas Ts
    Tugas Ts
    Dokumen39 halaman
    Tugas Ts
    muhammad bachtiar abdillah
    Belum ada peringkat
  • Tugas Ts
    Tugas Ts
    Dokumen39 halaman
    Tugas Ts
    muhammad bachtiar abdillah
    Belum ada peringkat
  • Kelas A2
    Kelas A2
    Dokumen4 halaman
    Kelas A2
    Gilank Mahardika
    Belum ada peringkat
  • Halaman Persetujuan
    Halaman Persetujuan
    Dokumen1 halaman
    Halaman Persetujuan
    Gilank Mahardika
    Belum ada peringkat
  • Tugas Ts
    Tugas Ts
    Dokumen39 halaman
    Tugas Ts
    muhammad bachtiar abdillah
    Belum ada peringkat
  • BAB II Ok
    BAB II Ok
    Dokumen13 halaman
    BAB II Ok
    Gilank Mahardika
    Belum ada peringkat
  • Kelas A2
    Kelas A2
    Dokumen4 halaman
    Kelas A2
    Gilank Mahardika
    Belum ada peringkat
  • Awal
    Awal
    Dokumen13 halaman
    Awal
    Gilank Mahardika
    Belum ada peringkat
  • Halaman Persetujuan
    Halaman Persetujuan
    Dokumen1 halaman
    Halaman Persetujuan
    Gilank Mahardika
    Belum ada peringkat
  • Lembar Persyaratan
    Lembar Persyaratan
    Dokumen1 halaman
    Lembar Persyaratan
    Gilank Mahardika
    Belum ada peringkat
  • BAB III Revisi
    BAB III Revisi
    Dokumen11 halaman
    BAB III Revisi
    Gilank Mahardika
    Belum ada peringkat
  • Daftar Isi
    Daftar Isi
    Dokumen3 halaman
    Daftar Isi
    Gilank Mahardika
    Belum ada peringkat
  • Lembar Pengesahan
    Lembar Pengesahan
    Dokumen1 halaman
    Lembar Pengesahan
    Gilank Mahardika
    Belum ada peringkat
  • Halaman Judul
    Halaman Judul
    Dokumen1 halaman
    Halaman Judul
    Gilank Mahardika
    Belum ada peringkat