Laporan Praktik Kerja Lapangan

Star Energy Geothermal (Wayang Windu) Ltd.


Pangalengan-Bandung

LEMBAR PENGESAHAN

Nama : Faesal Fajar


NIM : 131711041
Departemen / Program Studi : Teknik Konversi Energi / D3-Teknik
Konversi Energi
Judul Laporan : Studi Prosedur Start-Up Vacuum Up
Operation Star Energy Geothermal
(Wayang Windu) Limited
Tempat Kerja Praktik : Star Energy Geothermal (Wayang Windu)
Limited
Waktu Kerja Praktik : 03 Agustus-03 September 2015

Telah diperiksa dan disetujui oleh

Pembimbing Lapangan Dosen Pembimbing

Hariyanto Ir. Sapto Prajogo, M.Si


NIP. 11081255 NIP. 196211221995121001

Mengetahui,
Ketua Departemen Teknik Konversi Energi
Politeknik Negeri Bandung

Ahmad Deni Mulyadi, S.T, M.T


NIP. 196306231992031002

Departemen Teknik Konversi Energi i


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

KATA PENGANTAR

Alhamdulillah, segala puji dan syukur senantiasi saya penjatkan kehadirat Allah
SWT, atas berkat rahmat dan hidayah-Nya penulis dapat melaksanakan kerja praktik dan
menyelesaikan laporan kerja praktik di Star Energy Geothermal (Wayang Windu) Limited,
Pangalengan dengan lancar.
Laporan Kerja Praktik yang berjudul STUDI PROSEDUR START-UP VACUUM
UP OPERATION STAR ENERGY GEOTHERMAL (WAYANG WINDU) LIMITED
yang merupakan laporan kerja praktik di Star Energy Geothermal (Wayang Windu)
Limited, Pangalengan. Selain itu, laporan kerja praktik ini disusun untuk memenuhi salah
satu tugas mata kuliah kerja praktik di semester lima, Program Studi Teknik Konversi
Energi Jurusan Teknik Konversi Energi Politeknik Negeri Bandung.
Dengan selesainya laporan ini, penulis berharap laporan ini dapat memberikan
manfaat berupa pengetahuan kepada semua orang yang membacanya. Selain itu, penulis
telah berusaha semaksimal mungkin dalam penulisan laporan ini. Namun, penulis
menyadari masih terdapat banyak kekurangan dalam penulisan laporan ini. Untuk itu,
penulis mengharapkan saran dan kritik yang sifatnya konstruktif demi perbaikan dan
kesempurnaan laporan ini. Amin.

Bandung, Oktober 2015

Penulis

Departemen Teknik Konversi Energi ii


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

UCAPAN TERIMA KASIH

Penulis menyadari bahwa dalam pembuatan laporan kerja praktik ini tidak akan
berjalan dengan baik tanpa adanya bantuan dan bimbingan dari berbagai pihak yang terkait
dalam perbuatan laporan kerja praktik ini, dalam kesempatan ini penulis ingin
mengucapkan banyak terima kasih kepada :
1. Allah SWT atas segala rahmat dan hidayah-Nya kepada penulis.
2. Ahmad Deni Mulyadi, S.T, M.T, sebagai Ketua Departemen Teknik Konversi
Energi Politeknik Negeri Bandung.
3. Ika Yuliani, S.T, M.T, sebagai Ketua Program Studi Teknik Konversi Energi
Departemen Teknik Konversi Energi Politeknik Negeri Bandung
4. Ir. Sapto Prajogo, M.Si, sebagai Dosen Pembimbing Praktik Kerja Lapangan.
5. Siti Saodah, MT., sebagai Koordinator Praktik Kerja Lapangan Departemen Teknik
Konversi Energi.
6. Ir. Teguh Sasono, M.T, sebagai Wali Kelas B Teknik Konversi Energi 2013.
7. Seluruh dosen dan staf Departemen Teknik Konversi Energi.
8. Ibu Nayla, sebagai Koordinator Praktik Kerja Lapangan di Star Energy Geothermal
(Wayang Windu) Ltd.
9. Bapak Ismail, sebagai Superintendent di Production Departemen Star Energy
Geothermal (Wayang Windu) Ltd.
10. Bapak Hariyanto, sebagai Supervisor Production di Production Department Star
Energy Geothermal (Wayang Windu) Ltd. dan Pembimbing Lapangan.
11. Bapak Aceng, Bapak Iman, dan Bapak Hari Firmansyah, sebagai lead group 1, lead
group 2, dan lead group 3 di Production Department Star Energy Geothermal
(Wayang Windu) Ltd.
12. Para Pemateri dari Production Departement yang telah memberikan ilmunya
kepada penulis: Bapak Burhan, Bapak Yadi, Bapak Jalit, Bapak Alvin, Bapak Edi,
Bapak Panca, Bapak Dadan, dan Bapak Anton. Semoga Allah SWT dapat
membalas semua kebaikan mereka.
13. Seluruh jajaran karyawan Star Energy Geothermal (Wayang Windu) Ltd. yang
telah membantu kelancaran praktik kerja lapangan.

Departemen Teknik Konversi Energi iii


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

14. Kedua orang tua yang ikhlas dan penuh kesabaran dalam mendidik dan
memberikan dukungan moril serta materil kepada penulis selama ini. Semoga
rahmat Allah SWT selalu menyertai mereka.
15. Seluruh teman-teman seperjuangan kerja praktik : Banu Luthfan, Riky, Rizky,
Tony, Noviandri, Agung, Gilang, Gisel, Aknan, Mas Waldi, dan Mas Andika.
Semoga kita semua menjadi orang yang sukses.
16. Suci Susilawati yang selalu memberikan semangat dan motivasinya kepada penulis.
17. Sahabat-sahabat kelas B Teknik Konersi Energi 2013 yang selalu memberikan
warna di kehidupan penulis.
18. Seluruh teman-teman Himpunan Mahasiswa Teknik Energi Politeknik Negeri
Bandung. Jayalah HMTE.
19. Seluruh teman-teman Unit Kegiatan Mahasiswa Bulutangkis Politeknik Negeri
Bandung. Tetap solid dan Jayalah UKM Bulutangkis.
20. Dan semua pihak terkait baik secara langsung maupun tidak langsung dalam
membantu penulis selama kerja praktik dan penyusunan laporan ini.

Semoga apa yang telah kalian berikan kepada penulis dalam melaksanakan kerja
praktik ini bernilai ibadah dan mendapatkan balasan dari Allah SWT. Amiin.

Departemen Teknik Konversi Energi iv


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

DAFTAR ISI

LEMBAR PENGESAHAN .................................................................................................... i

KATA PENGANTAR ........................................................................................................... ii

UCAPAN TERIMA KASIH ................................................................................................ iii

DAFTAR ISI ......................................................................................................................... v

DAFTAR GAMBAR .......................................................................................................... viii

DAFTAR TABEL ................................................................................................................ ix

BAB I PENDAHULUAN .................................................................................................. 1

1. 1. Latar Belakang ............................................................................................... 1

1. 2. Rumusan Masalah .......................................................................................... 2

1. 3. Tujuan Praktik Kerja Lapangan ..................................................................... 2

1. 4. Batasan Masalah ............................................................................................ 2

1. 5. Metode Penelitian .......................................................................................... 2

1. 6. Waktu dan Tempat Pelaksanaan .................................................................... 3

1. 7. Sistematika Penulisan Laporan ...................................................................... 3

BAB II LANDASAN TEORI .............................................................................................. 5

2. 1. Tekanan Mutlak (Absolute Pressure) ............................................................ 5

2. 2. Kondisi Vakum ............................................................................................ 10

2. 3. Klasifikasi Tekanan Vakum ......................................................................... 10

2. 4. Kondisi Operasi pada Pembangkit ............................................................... 10

2. 5. Operasi Start-up ........................................................................................... 11

2. 6. Operasi Normal ............................................................................................ 11

2. 7. Operasi Abnormal ........................................................................................ 12

2. 8. Operasi Shut-down ....................................................................................... 12

Departemen Teknik Konversi Energi v


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

BAB III DESKRIPSI OBJEK PRAKTIK KERJA LAPANGAN ...................................... 13

3. 1. Profil Perusahaan ......................................................................................... 13

3. 1. 1. Sejarah Singkat Perusahaan ........................................................... 13

3. 1. 2. Visi dan Misi Perusahaan .............................................................. 14

3. 1. 3. Lokasi Perusahaan ......................................................................... 15

3. 1. 4. Struktur Organisasi Perusahaan ..................................................... 16

3. 1. 5. Fasilitas Perusahaan ....................................................................... 17

3. 1. 6. Kegiatan Perusahaan ...................................................................... 18

3. 2. Daerah Operasi dan Komponen Utama ....................................................... 19

3. 2. 1. Sumur Produksi ............................................................................. 19

3. 2. 2. Sumur Injeksi ................................................................................. 20

3. 2. 3. Separator ....................................................................................... 21

3. 2. 4. Scrubber ......................................................................................... 22

3. 2. 5. Turbin Uap ..................................................................................... 23

3. 2. 6. Generator ....................................................................................... 24

3. 2. 7. Transformator ................................................................................ 24

3. 2. 8. Kondensor Utama .......................................................................... 25

3. 2. 9. Gas Removal System ...................................................................... 26

3. 2. 10. Menara Pendingin .......................................................................... 27

3. 3. Proses Pembangkitan Listrik........................................................................ 28

3. 4. Peralatan Utama Vacuum Up Operation...................................................... 30

3. 5. Gas Removal System .................................................................................... 30

3. 5. 1. Sistem Desain ................................................................................ 31

3. 5. 2. Kriteria dan Klasifikasi Gas Removal System ............................... 31

3. 5. 3. Bagian Gas Removal System ......................................................... 32

3. 5. 3. 1. Steam Jet Ejector ............................................................. 32

Departemen Teknik Konversi Energi vi


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

3. 5. 3. 2. Liquid Ring Vacuum Pump .............................................. 33

3. 5. 3. 3. Intercondenser dan Aftercondenser ................................. 35

3. 5. 4. Spesifikasi Gas Removal System ................................................... 35

3. 5. 4. 1. First Stage Ejector ........................................................... 35

3. 5. 4. 2. Second Stage Ejector ....................................................... 36

3. 5. 4. 3. Vacuum Pump .................................................................. 36

3. 5. 4. 4. First Stage Ejector (Buck-up) .......................................... 36

3. 5. 4. 5. Second Stage Ejector (Buck-up) ...................................... 36

3. 5. 4. 6. First Inter Condenser ...................................................... 37

3. 5. 4. 7. After Condenser ............................................................... 37

3. 5. 4. 8. First Inter Condenser (Buck-up) ..................................... 37

3. 5. 4. 9. After Condenser (Buck-up) .............................................. 38

3. 6. Kondensor Utama ........................................................................................ 38

3. 6. 1. Fungsi Kondensor Utama .............................................................. 39

3. 6. 2. Spesifikasi Kondensor Utama........................................................ 39

3. 7. Auxiliary Cooling Water Pump .................................................................... 39

3. 7. 1. Fungsi Auxiliary Cooling Water Pump ......................................... 41

3. 7. 2. Spesifikasi Auxiliary Cooling Water Pump .................................. 42

3. 8. Hot Well Pump ............................................................................................. 43

3. 9. Gland Sealing............................................................................................... 44

BAB IV PEMBAHASAN ................................................................................................... 45

4. 1. Vacuum Up Operation ................................................................................. 45

4. 2. Tahapan Start-up Vacuum Up Operation .................................................... 45

4. 3. Tahap Persiapan Vacuum Up Operation...................................................... 45

4. 4. Tahap Pelaksanaan Vacuum Up Operation ................................................. 46

4. 5. Tahap Konfirmasi Vacuum Up Operation ................................................... 49

Departemen Teknik Konversi Energi vii


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

4. 6. Kondisi Peralatan pada Vacuum Up Operation ........................................... 50

4. 7. Pengaruh Vacuum Up Operation ................................................................. 52

BAB V PENUTUP ............................................................................................................ 53

5. 1. Kesimpulan .................................................................................................. 53

5. 2. Saran ............................................................................................................ 54

DAFTAR PUSTAKA ......................................................................................................... 55

LAMPIRAN ....................................................................................................................... 56

Departemen Teknik Konversi Energi viii


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

DAFTAR GAMBAR

Gambar 2.1 Pengukur tekanan (Bourdon) ............................................................................ 6


Gambar 2.2 Pengukur tekanan mutlak (Bourdon) ................................................................ 6
Gambar 2.3 Tekanan mutlak (absolut) dan tekanan ukur (gauge) ....................................... 9
Gambar 3.1 Peta lokasi dan letak sumur Star Energy Geothermal (Wayang Windu) Ltd . 16
Gambar 3.2 Struktur organisasi Star Energy Geothermal (Wayang Windu) Ltd ............... 17
Gambar 3.3 Sumur produksi............................................................................................... 19
Gambar 3.4 Sumur injeksi .................................................................................................. 20
Gambar 3.5 Peta sumur Star Energy Geothermal (Wayang Windu) Ltd ........................... 21
Gambar 3.6 Separator ........................................................................................................ 22
Gambar 3.7 Scrubber .......................................................................................................... 23
Gambar 3.8 Turbin uap ....................................................................................................... 24
Gambar 3.9 Generator ........................................................................................................ 24
Gambar 3.10 Main transformator dan unit transformator ................................................... 25
Gambar 3.11 Kondensor utama ............................................................................................ 26
Gambar 3.12 Gas removal system ........................................................................................ 27
Gambar 3.13 Menara pendingin ........................................................................................... 27
Gambar 3.14 Skema pembangkitan Star Energy Geothermal (Wayang Windu) Ltd .......... 28
Gambar 3.15 Prinsip dasar operasi steam jet ........................................................................ 32
Gambar 3.16 Pompa liquid ring vacuum pump (LRVP)....................................................... 41
Gambar 3.18 (a) Lube oil cooler .......................................................................................... 42
(b) Generator air cooler ................................................................................. 42
(c) Inter/After condenser GRS ........................................................................ 42
(d) Liquid ring vacuum pump ......................................................................... 42
(e) Liquid ring shaft seal vacuum pump ......................................................... 42
Gambar 3.19 Pompa hot well pump ..................................................................................... 43
Gambar 3.20 (a) Water sealed glands and labyrinth seal ................................................... 44
(b) Labyrinth type ........................................................................................... 44
Gambar 4.1 Tahapan sequence pada vacuum up operation ............................................... 50

Departemen Teknik Konversi Energi ix


Politeknik Negeri Bandung
Laporan Praktik Kerja Lapangan
Star Energy Geothermal (Wayang Windu) Ltd.
Pangalengan-Bandung

DAFTAR TABEL

Tabel 2.1 Properti-properti atmosfer standar .......................................................................... 8


Tabel 2.2 Properti-properti atmosfer dalam satuan British .................................................... 9
Tabel 3.1 Spesifikasi separator ............................................................................................ 22
Tabel 3.2 Spesifikasi scrubber ............................................................................................. 23
Tabel 3.3 Spesifikasi kondensor utama ................................................................................ 26
Tabel 4.1 Kondisi peralatan pada vacuum up operation ...................................................... 46

Departemen Teknik Konversi Energi x


Politeknik Negeri Bandung