KOMPONEN UTAMA
No Nama Peralatan
1 Bendungan
- Spilway gate
- Intake gate
- Trast Rack
- Bottom Outlet
2 Tunnel
- Pintu Inspeksi
3 Surge Tank
- Kondisi Fisik
- Kebocoran
4 Penstock Valve
- Instalasi hydraulic
- Kondisi Valve
5 Inlet Valve
- Valve
- By pass Valve
- Instalasi hydraulic
- Instalasi air
6 Water Turbin
- Guide Vane
- Runner
- Sudu tetap
- Turbin Bearing
- Getaran
- Draft tube
7 Generator
- Radiator ( system pendingin )
- Stator
- Rotor
- Sistem break
- Thrust bearing
- Upper bearing
- PMG
- Lifter
- Bus duct
- Sistem Grounding
- CB & DS
- Sistem Pengukuran
8 Transformer
- Sistem Pemadam kebakaran
- Sistem Pendingin
- Sistem Proteksi
- Bushing
- Arrester
- System Grounding
- Peralatan Kontrol
9 Sistem Eksitasi
- Trafo eksitasi
- Thyristor dan panel control
- Sistem pendinginan
- Sistem Proteksi
10 AVR
- Sistem pendingin
- Pengaturan tegangan
- Pengecekan modul-modul
3 Central AC
- Sistem Grounding
- Sistem Pengukuran
- Sistem proteksi
5 Genset
- Sistem Grounding
- Sistem Pengukuran
- Sistem proteksi
6 Sistem pemakaian Sendiri 20 KV dan 380 Volt
- Sistem proteksi
- Sistem grounding
- Sistem Interlock
- Sistem Pengukuran
- CT & PT
- Trafo tegangan Menengah dan rendah
-
2 Dewatering pump
- instalasi air
- aligment
- getaran
3 Water treatmen
- Pompa pompa
- Instalasi kimia
6 Governor
- Presure tank
- Tangki minyak dan pompa
- Sistem pengaman
- Sistem pengukuran
- Sistem kontrol