TIME SCHEDULE (CURVE - S) bedasarkan ES

durasi biaya bobot Hari ke-


No Kegiatan ES
(Hari) (xRp.1000) (%) 1 2 3 4 5 6 7 8 9 10
1 A 3 0 3,000 3 1.0 1.0 1.0

2 B 3 0 9,000 9 3.0 3.0 3.0

3 C 4 0 8,000 8 2.0 2.0 2.0 2.0

4 D 5 3 5,000 5 1.0 1.0 1.0 1.0 1.0

5 E 5 4 10,000 10 2.0 2.0 2.0 2.0 2.0

6 F 7 3 14,000 14 2.0 2.0 2.0 2.0 2.0 2.0 2.0

7 G 3 9 9,000 9 3.0

8 H 4 12 16,000 16

9 I 2 9 8,000 8 4.0

10 J 4 10 8,000 8

11 K 4 16 8,000 8

12 L 2 11 2,000 2

100,000 100 6 6 6 5 5 5 5 5 4 9

: Lintasan kritis 6 12 18 23 28 33 38 43 47 56

: Non kritis

TIME SCHEDULE (CURVE - S) bedasarkan LF


durasi biaya bobot Hari ke-
No Kegiatan LF
(Hari) (xRp.1000) (%) 1 2 3 4 5 6 7 8 9 10
1 A 3 7 3,000 3 1.0 1.0 1.0

2 B 3 9 9,000 9 3.0 3.0 3.0

3 C 4 4 8,000 8 2.0 2.0 2.0 2.0

4 D 5 12 5,000 5 1.0 1.0 1.0

5 E 5 9 10,000 10 2.0 2.0 2.0 2.0 2.0


6 F 7 16 14,000 14 2.0

7 G 3 12 9,000 9 3.0

8 H 4 16 16,000 16

9 I 2 18 8,000 8

10 J 4 20 8,000 8

11 K 4 20 8,000 8

12 L 2 20 2,000 2

100,000 2 2 2 2 3 3 6 6 6 6

: Lintasan kritis 2 4 6 8 11 14 20 26 32 38

: Non kritis
dasarkan ES
Hari ke-
11 12 13 14 15 16 17 18 19 20

100% Bobot

90%

80%

70%

60%

3.0 3.0 50%

4.0 4.0 4.0 4.0 40%

4.0 30%

2.0 2.0 2.0 2.0 20%

2.0 2.0 2.0 2.0 10%

1.0 1.0 0%

9 6 7 6 4 4 2 2 2 2 JUMLAH
ES
65 71 78 84 88 92 94 96 98 100 KOMULATIF

dasarkan LF
Hari ke-
11 12 13 14 15 16 17 18 19 20

100% Bobot

90%

1.0 1.0 80%

70%
2.0 2.0 2.0 2.0 2.0 2.0 60%

3.0 3.0 50%

4.0 4.0 4.0 4.0 40%

4.0 4.0 30%

2.0 2.0 2.0 2.0 20%

2.0 2.0 2.0 2.0 10%

1.0 1.0 0%

6 6 6 6 6 6 8 8 5 5 JUMLAH
LF
44 50 56 62 68 74 82 90 95 100 KOMULATIF
TIME SCHEDULE (CURVE - S) bedasarkan ES
durasi Pekerja biaya bobot Hari ke-
No Kegiatan ES
(Hari) (org/hari) (xRp.1000) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 A 3 0 10 3,000 3 10 10 10

2 B 3 0 15 9,000 9 15 15 15

3 C 4 0 25 8,000 8 25 25 25 25
20 20 20 20 20
4 D 5 3 20 5,000 5

5 E 5 4 25 10,000 10 25 25 25 25 25
40 40
6 F 7 3 40 14,000 14 40 40 40 40 40
30
7 G 3 9 30 9,000 9 30 30
45 45
8 H 4 12 45 16,000 16 45 45

9 I 2 9 25 8,000 8 25 25

10 J 4 10 20 8,000 8 20 20 20 20

11 K 4 16 10 8,000 8 10 10 10 10

12 L 2 11 5 2,000 2 5 5

Jumlah 100,000 100 50 50 50 85 85 85 85 85 65 95 75 55 70 65 45 45 10 10 10 10 ES


: Lintasan kritis

: Non kritis
: Kurva SDM

TIME SCHEDULE (CURVE - S) bedasarkan LF


durasi Pekerja biaya bobot Hari ke-
No Kegiatan LF
(Hari) (org/hari) (xRp.1000) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 A 3 7 10 3,000 3 10 10 10

2 B 3 9 15 9,000 9 15 15 15

3 C 4 4 25 8,000 8 25 25 25 25

4 D 5 12 20 5,000 5 20 20 20 20 20

5 E 5 9 25 10,000 10 25 25 25 25 25

6 F 7 16 40 14,000 14 40 40 40 40 40 40 40

7 G 3 12 30 9,000 9 30 30 30

8 H 4 16 45 16,000 16 45 45 45 45

9 I 2 18 25 8,000 8 25 25

10 J 4 20 20 8,000 8 20 20 20 20
10 J 4 20 20 8,000 8 20 20 20 20

11 K 4 20 10 8,000 8 10 10 10 10

12 L 2 20 5 2,000 2 5 5

Jumlah 100,000 100 25 25 25 25 35 35 50 60 60 90 90 90 85 85 85 85 55 55 35 35

: Lintasan kritis

: Non kritis
SDM

100

90

80 (org/hari)

70

60

50

40

30

20

10

0
JUMLAH
SDM

100

90

80 (org/hari)

70

60

50

40

30
20

10

0
LF
NAMA :
NIM :
TGL :

TIME SCHEDULE (CURVE - S) bedasarkan ……


durasi
No Kegiatan ES EF LS LF FF TF KETERANGAN
(Hari)
1

10

11

12

13

14

15

16
TIME SCHEDULE (CURVE - S) bedasarkan
durasi biaya bobot Hari ke-
No Kegiatan ES
(Hari) (xjuta Rp) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1

10

11

12

13

14

15

16
JUMLAH

KOMULATIF
JUMLAH
PEKERJAAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

PEKERJAAN BOBOT TOTAL


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

PEKERJAAN BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
PEKERJAAN BIAYA PREDESESOR DURASI BOBOT PEKERJAAN BIAYA
EV BOBOT PREDESESOR DURASI PEKERJAAN BIAYA AV BOBOT
PREDESESOR DURASI
JUMLAH

KOMULATIF

JUMLAH