A. MATERIAL/BAHAN
1 Kabel NYY 4x25 mm mtr 30.00 Rp 480,000.00
2 Kabel NYY 4x10 mm mtr 20.00 Rp 236,000.00
3 Kabel NYM 3x4 mm Roll 2.00 Rp 2,772,000.00
4 Kabel NYM 3x2,5mm Roll 6.00 Rp 1,954,000.00
5 Kabel NYM 2x2,5mm Roll 9.00 Rp 1,818,000.00
6 Kabel NYYHY 2x1,5mm Roll 5.00 Rp 2,045,000.00
7 Kabel Duck 45x45 mm Btg 10.00 Rp 75,000.00
8 Kabel Ground BC 35 mm Mtr 50.00 Rp 95,000.00
9 Isolasi Scoot Buah 50.00 Rp 54,000.00
10 Klem Kabel 10 mm Dos 35.00 Rp 45,000.00
11 Klem Kabel 12 mm Dos 10.00 Rp 59,000.00
12 Klem Kabel 17 mm Dos 4.00 Rp 72,000.00
13 Double Tape 3 m Buah 10.00 Rp 136,000.00
14 Terminal Nol Buah 1.00 Rp 227,000.00
15 Terminal Ground Buah 1.00 Rp 227,000.00
16 Stick Grounding Buah 1.00 Rp 734,000.00
17 Pipa Pelindung 1/2 Inc Btg 5.00 Rp 81,000.00
18 Pipa Pelindung kabel lampu taman Buah 25.00 Rp 63,000.00
19 Vitting Lampu Down Ligth Zetalux Buah 166.00 Rp 140,000.00
20 Lampu Philips Tornado 12 Watt Buah 166.00 Rp 145,000.00
21 Lampu TL 40 Watt Buah 9.00 Rp 245,000.00
22 Lampu Taman 1 Box Buah 16.00 Rp 713,000.00
23 Saklar Ganda Panasonic Buah 45.00 Rp 81,000.00
24 Salar Tunggal Panasonic Buah 10.00 Rp 68,000.00
25 Stop Kontak Panasonic Buah 65.00 Rp 72,000.00
26 Stop Kontak AC + Saklar Slipsal Buah 15.00 Rp 163,000.00
27 IB.Doz Clipsal Tempel Buah 15.00 Rp 36,000.00
28 Main Breaker 3 Phase 100 A Buah 1.00 Rp 3,363,000.00
29 MCB 3 Phase 50 A Buah 4.00 Rp 738,000.00
30 MCB 1 Phase 20 A Buah 8.00 Rp 175,000.00
31 MCB 1 Phase 50 A Buah 2.00 Rp 272,000.00
32 MCB 1 Phase 16 A Buah 2.00 Rp 154,000.00
33 MCB 1 Phase 10 A Buah 2.00 Rp 136,000.00
B. JASA PEMASANGAN
1 Titik Nyala Titik 340.00 Rp 228,634.22
REKAPITULASI TOTAL
QUANTITAS DAN HARGA
KEGIATAN : PEMELIHARAAN/RUTIN BERKALA RUMAH JABATAN
PEKERJAAN : INSTALASI PENGATURAN PUSAT LISTRIK RUMAH JABATAN KETUA DPRD
NO. DPA SKPD : 1.20.1.20.04.02.42
LOKASI : Jl.Cenderawasih SP-III Timika
TAHUN ANGGARAN : 2017
NO JENIS PEKERJAAN
A. MATERIAL/BAHAN
B. JASA PEMASANGAN
Terbilang : Dua Ratus Enam Puluh Satu Juta Empat Ratus Delapan Ribu Rupiah
Timika,
Diajukan Oleh
CV.FURWAGI INDAH
ISMAIL RUMADAUL
Direktur
RINCIAN
TITAS DAN HARGA
JUMLAH
Rp 159,908,000.00
Rp 14,400,000.00
Rp 4,720,000.00
Rp 5,544,000.00
Rp 11,724,000.00
Rp 16,362,000.00
Rp 10,225,000.00
Rp 750,000.00
Rp 4,750,000.00
Rp 2,700,000.00
Rp 1,575,000.00
Rp 590,000.00
Rp 288,000.00
Rp 1,360,000.00
Rp 227,000.00
Rp 227,000.00
Rp 734,000.00
Rp 405,000.00
Rp 1,575,000.00
Rp 23,240,000.00
Rp 24,070,000.00
Rp 2,205,000.00
Rp 11,408,000.00
Rp 3,645,000.00
Rp 680,000.00
Rp 4,680,000.00
Rp 2,445,000.00
Rp 540,000.00
Rp 3,363,000.00
Rp 2,952,000.00
Rp 1,400,000.00
Rp 544,000.00
Rp 308,000.00
Rp 272,000.00
Rp 77,735,636.36
Rp 77,735,636.36
PITULASI TOTAL
NTITAS DAN HARGA
JUMLAH
Rp 159,908,000.00
Rp 77,735,636.36
Rp 237,643,636.36
Rp 23,764,363.64
Rp 261,408,000.00
Rp 261,408,000.00
###
Diajukan Oleh
CV.FURWAGI INDAH
ISMAIL RUMADAUL
Direktur
A. MATERIAL/BAHAN
1 Kabel NYY 4x25 mm
2 Kabel NYY 4x10 mm
3 Kabel NYM 3x4 mm
4 Kabel NYM 3x2,5mm
5 Kabel NYM 2x2,5mm
6 Kabel NYYHY 2x1,5mm
7 Kabel Duck 45x45 mm
8 Kabel Ground BC 35 mm
9 Isolasi Scoot
10 Klem Kabel 10 mm
11 Klem Kabel 12 mm
12 Klem Kabel 17 mm
13 Double Tape 3 m
14 Terminal Nol
15 Terminal Ground
16 Stick Grounding
17 Pipa Pelindung 1/2 Inc
18 Pipa Pelindung kabel lampu taman
19 Vitting Lampu Down Ligth Zetalux
20 Lampu Philips Tornado 12 Watt
21 Lampu TL 40 Watt
22 Lampu Taman 1 Box
23 Saklar Ganda Panasonic
24 Salar Tunggal Panasonic
25 Stop Kontak Panasonic
26 Stop Kontak AC + Saklar Slipsal
27 IB.Doz Clipsal Tempel
28 Main Breaker 3 Phase 100 A
29 MCB 3 Phase 50 A
30 MCB 1 Phase 20 A
31 MCB 1 Phase 50 A
32 MCB 1 Phase 16 A
33 MCB 1 Phase 10 A
B. JASA PEMASANGAN
1. Titik Nyala
2