NO

A
I
1
2
3
4
II
A
1
2
B
1
2
C
1
E
1
2
3
4
5

III
A
1
2
B
1
2
D
1
E
1
2
3
4
5
6

IV
1
2
Jumlah
: 257/PMS-ALR/VIII/2018
: Penawaran Harga

Kepada Yth.

PT Satwiga Mustika Naga


Jl. Raya Geneng No. 100 Ngawi
Project DPRD Ngawi Tahap III
Telp. / Fax. : (0351) 749347 / 749350
Email : mustikanaga@yahoo.com
Att. Ibu Djuwariyah

Dengan hormat,

Bersama dengan ini kami sampaikan penawaran harga barang sebagai berikut :

DESCRIPTION

PEKERJAAN SISTEM FIRE ALARM


Peralatan Utama
Fire Alarm Control Panel 10 zone c/w Battery
Fire Alarm Annunciator Panel 10 zone
surge arester
Installasi dan setting FACP & Annunciator
LANTAI 1
CONVENTIONAL DETECTOR
Rate of Rise Heat Detector
Manual Call Point with base
Output Audible Visual
Alarm Bell
Indicating Lamp
Cable & Modul Management
TB - FA
INSTALASI
Material Instalasi Detector (Supreme NYA 2x1,5mm c/w pipe conduit 20mm (Boss HCI)) -
12 m Installasi Alarm Set (Supreme NYA 4x1,5mm c/w pipe conduit 20mm (Boss
Material
HCI)) - 36Installasi
Material m flow switch (Supreme NYA 2x1,5mm c/w pipe conduit 20mm (Boss
HCI)) - 36 m Feeder MCFA to zona (Supreme NYA 4x1,5mm c/w pipe conduit 20mm
Material Kabel
(Boss HCI)) - 36
Jasa instalasi : m
- Instalasi Detector
- Installasi Alarm Set
- Installasi flow switch
- Instalasi dan Connecting TBFA
- Kabel Feeder MCFA to zona
LANTAI 2
CONVENTIONAL DETECTOR
Rate of Rise Heat Detector
Manual Call Point with base
Output Audible Visual
Alarm Bell
Indicating Lamp
Cable & Modul Management
TB - FA
INSTALASI
Material Instalasi Detector (Supreme NYA 2x1,5mm c/w pipe conduit 20mm (Boss HCI)) -
12 m Installasi Alarm Set (Supreme NYA 4x1,5mm c/w pipe conduit 20mm (Boss
Material
HCI)) - 36Installasi
Material m flow switch (Supreme NYA 2x1,5mm c/wpipe conduit 20mm (Boss
HCI)) - 36 m Feeder TBFA to MCFA (Supreme NYA 4x1,5mm c/w pipe conduit 20mm
Material Kabel
Boss HCI))
Material - 36Feeder
Kabel m MCFA to ANN(POS SEC) (Supreme NYA 16x1,5mm c/w pipe
conduit
Jasa 20mm:(Boss HCI)) - 36 m
instalasi
- Instalasi Detector
- Installasi Alarm Set
- Installasi flow switch
- Instalasi dan Connecting TBFA
- Kabel Feeder TBFA to MCFA
- Kabel Feeder MCFA to ANN(POS SEC)
- Grounding Equipment Cw Ground stick & Installasi Kabel Ground, Supreme NYA 6mm
cw pipe conduit 20mm (Boss HCI) - 25 m
LAIN-LAIN
Testing & Commissioning Fire Alarm
Akomodasi dan Transportasi (Site Expenses)
Jumlah

Tidak Dikerjakan
Ada Di Rab
Perlangkapan 35 %

keterangan panjang pipa dan accesories harap disesuaikan gambar baru


Semarang, 13 Agustus 2018

BRAND & TYPE QTY UNIT PRICE TOTAL PRICE


(Rp) (Rp)

HS-10L Hooseki 1 unit 5,280,000


AN-10L Hooseki 1 unit 2,408,400 2,408,400
PF20 1P+N 1 unit 1,621,100 1,621,100
1 lot 4,740,000 4,740,000

HS-WS19L Hooseki 21 bh 69,500 1,459,500


HS-FP1 Hooseki 2 bh 166,700 333,400

HS-FB6 Hooseki 2 bh 189,900 379,800


HS-FL3 Hooseki 2 bh 52,800 105,600

TB 12 1 unit 361,300 361,300

21 ttk 196,000 4,116,000


2 set 905,100 1,810,200
1 zone 587,900 587,900
4 zone 858,700 3,434,800

21 ttk 323,800 6,799,800


2 set 1,588,000 3,176,000
1 zone 853,100 853,100
1 lot 357,900 357,900
4 zone 1,233,500 4,934,000

HS-WS19L Hooseki 23 bh 69,500 1,598,500


HS-FP1 Hooseki 2 bh 166,700 333,400

HS-FB6 Hooseki 2 bh 189,900 379,800


HS-FL3 Hooseki 2 bh 52,800 105,600

TB 12 1 unit 361,300 361,300


23 ttk 196,000 4,508,000
2 set 905,100 1,810,200
1 zone 587,900 587,900
4 zone 858,700 3,434,800
8 zone 2,484,700

2 ttk 323,800 647,600


2 set 1,588,000 3,176,000
1 zone 853,100 853,100
1 lot 357,900 357,900
4 zone 1,233,500
8 zone 4,936,800
1 Lot 4,736,800 4,736,800

1 ls 2,950,000 2,950,000
1 ls 16,525,000 16,525,000
79,844,700

Fap 79,844,700
Hydrant 145,614,200
Total 225,458,900
N o : 251/PMS-ENG/VIII/2018
Hal : Penawaran Harga

Kepada Yth.

PT Satwiga Mustika Naga


Jl. Raya Geneng No. 100 Ngawi
Project DPRD Ngawi Tahap III
Telp. / Fax. : (0351) 749347 / 749350
Email : mustikanaga@yahoo.com
Att. Ibu Djuwariyah

Dengan hormat,

Bersama dengan ini kami sampaikan penawaran harga barang sebagai berikut :

No Uraian

IFIRE HYDRANT & FIRE SPRINKLER INSTALLATION


A FIRE HYDRANT INSTALLATION
Peralatan Hydrant Lengkap terpasang komplit dengan aksesorisnya :
a Hydrant Equipments Luar Gedung :
1 Out Door Hydrant Box , type C ( uk. 95x66x20cm ), berkaca & berkunci GuardALL
2 Fire Hose Epdm ,2,5" x 30m c/w machino coupling GuardALL
3 Straight Nozzle 2,5" , machino coupling GuardALL
4 Hose Rack 2,5" , GuardALL
5 Hydrant Pillar Two Way 4" x 2,5" x 2,5" , machino coupling GuardALL
6 Siamese Connection , 4" x 2,5" x2,5" , machino coupling GuardALL
7 Check Valve-100m dia, type swing, Flanged JIS 10K Kitz
b Hydrant Equipments Dalam Gedung Lt.1 - Lt.2 :
1 InDoor Hydrant Box , type B GuardALL , w/o Glass&Lock
2 Fire Hose Epdm 1,5" x 30m c/w machino coupling GuardALL
3 Straight Nozzle 1,5" , machino coupling GuardALL
4 Hose Rack 1 1/2", GuardALL
5 Hydrant Valve 1 1/2" , machino coupling GuardALL
6 Landing Valve 2 1/2" , machino coupling GuardALL
7 Gate Valve 65mm dia, CI body, Flanged JIS 10K Kitz
8 Automatic Air vent Samyang c/w Gate Valve 1" dia Kitz
9 Pressure Gauge Wipro, dia 100mm, 1/2 NPT, 16 kg/cm2 c/w Gate Valve dia 1/2" Kitz
c Installation Risser Fire Hydrant :
1 Pipe dia 100mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Hydrant )
2 Fitting,Support,Painting,Consumable
d Installation Fire Hydrant Existing Connect To Insttalation New Building :
1 Pipe dia 100mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Hydrant )
2 Gate Valve 100mm dia, CI body, Flanged JIS 10K Kitz
3 Fitting,Support,Painting,Consumable
e Installation Fire Hydrant Indoor & Installation Hydrant Outdoor :
1 Pipe dia 100mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Hydrant Outdoor )
2 Pipe dia 65mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Hydrant Indoor )
3 Pipe dia 40mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Hydrant )
4 Galian dan Urugan kembali include pembungkus pipe polyken
5 Fitting (Elbow, Tee, Reducer, etc)
6 Support (Hanger Clam, U Bolt, bolt nut, etc)
7 Painting (Zincromate, finishing, thiner)
8 Consumable (Resibon, kawat las, sealtape)
B FIRE SPRINKLER INSTALLATION
a Installation Risser Fire Sprinkler :
1 Pipe dia 80mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Sprinkler )
2 Pipe dia 50mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Risser Draint Sprinkler)
3 Pressure Gauge Wipro, dia 100mm, 1/2 NPT, 16 kg/cm2 c/w Gate Valve dia 1/2" Kitz
4 Automatic Air vent Samyang c/w Gate Valve 1" dia Kitz
5 Fitting,Support,Painting,Consumable
b Installation Draint Fire Sprinkler :
1 Pipe dia 25mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo
2 Gate Valve 25mm dia, Bronze, Screw connection Kitz
3 Fitting,Support,Painting,Consumable
c Installation Fire Sprinkler Existing Connect To Insttalation Fire Sprinkler New Building :
1 Pipe dia 80mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo ( Sprinkler )
2 Gate Valve 80mm dia, CI body, Flanged JIS 10K Kitz
3 Fitting (Elbow, Tee, Reducer, etc)
4 Support (Hanger Clam, U Bolt, bolt nut, etc)
5 Painting (Zincromate, finishing, thiner)
6 Consumable (Resibon, kawat las, sealtape)
d Installation Fire Sprinkler Lantai 1:
1 Sprinkler head Viking Pendant 68 C, 1/2" Inlet
2 Branch Control Valve dia 65mm (butterfly valve,flow switch,test and draint) Viking
3 Pressure Gauge Wipro, dia 100mm, 1/2 NPT, 16 kg/cm2 c/w Get Valve dia 15mm Kitz
4 Pipe dia 65mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo (Main Line Sprinkler )
5 Pipe dia 50mm,Black Steel Pipe SCH 40 ,ASTM A53 Spindo (Branch Line Sprinkler)
6 Pipe dia 40m, Black Steel Pipe SCH 40 ,ASTM A53 Spindo
7 Pipe dia 25mm,Black Steel Pipe SCH 40 ,ASTM A53 Spindo
8 Fitting (Elbow, Tee, Reducer, etc)
9 Support (Hanger Clam, U Bolt, bolt nut, etc)
10 Painting (Zincromate, finishing, thiner)
11 Consumable (Resibon, kawat las, sealtape)
e Installation Fire Sprinkler Lantai 2:
1 Sprinkler head Viking Pendant 68 C, 1/2" Inlet
2 Branch Control Valve dia 65mm (butterfly valve,flow switch,test and draint) Viking
3 Pressure Gauge Wipro, dia 100mm, 1/2 NPT, 16 kg/cm2 c/w Get Valve dia 15mm Kitz
4 Pipe dia 65mm, Black Steel Pipe SCH 40 ,ASTM A53 Spindo (Main Line Sprinkler )
5 Pipe dia 50mm,Black Steel Pipe SCH 40 ,ASTM A53 Spindo (Branch Line Sprinkler)
6 Pipe dia 40m, Black Steel Pipe SCH 40 ,ASTM A53 Spindo
7 Pipe dia 25mm,Black Steel Pipe SCH 40 ,ASTM A53 Spindo
8 Fitting (Elbow, Tee, Reducer, etc)
9 Support (Hanger Clam, U Bolt, bolt nut, etc)
10 Painting (Zincromate, finishing, thiner)
11 Consumable (Resibon, kawat las, sealtape)
II LAIN - LAIN
a Commissioning Testing
b Site Expenses (Peralatan Kerja, Akomodasi dan Transportasi)
c Labor / Jasa Pemasangan
Jumlah

Tidak Dikerjakan
Ada Di Rab
Perlangkapan 35 %

keterangan panjang pipa dan accesories harap disesuaikan gambar baru


Semarang, 13 Agustus 2018

Unit Q'ty Harga /unit Jumlah


(Rp) (Rp)

ea 2 1,684,200
ea 2 1,931,600
ea 2 552,400
ea 2 378,900
ea 2 3,031,600
ea 1 2,947,400
ea 1 5,271,600

ea 2 1,431,600 2,863,200
ea 2 1,710,500 3,421,000
ea 2 320,000 640,000
ea 2 178,500 357,000
ea 4 325,100 1,300,400
ea 4 729,300 2,917,200
ea 2 2,850,500 5,701,000
ea 1 1,747,400 1,747,400
ea 1 530,100 530,100

m 12 246,800 2,961,600
ls 1 1,925,400 1,925,400

m 24 246,800 5,923,200
ea 1 4,842,100 4,842,100
ls 1 3,850,700 3,850,700

m 142 246,800
m 147 133,200
m 6 62,600
m 87 289,500
ls 1 8,250,200
ls 1 11,000,300
ls 1 4,400,100
ls 1 6,600,200

m 12 173,500 2,082,000
m 12 83,700 1,004,400
ea 1 530,100 530,100
ea 1 1,747,400 1,747,400
ls 1 2,005,800 2,005,800

m 18 38,600 694,800
ea 2 231,600 463,200
ls 1 452,000 452,000

m 78 173,500 13,533,000
ea 1 3,418,900 3,418,900
ls 1 2,029,700 2,029,700
ls 1 2,706,200 2,706,200
ls 1 1,082,500 1,082,500
ls 1 1,623,700 1,623,700
ea 11 52,800 580,800
set 1 6,669,500 6,669,500
ea 1 530,100 530,100
m 54 133,200 7,192,800
m 22 83,700 1,841,400
m 18 62,600 1,126,800
m 168 38,600 6,484,800
ls 1 2,497,400 2,497,400
ls 1 3,329,800 3,329,800
ls 1 1,331,900 1,331,900
ls 1 1,997,900 1,997,900

ea 23 52,800 1,214,400
set 1 6,669,500 6,669,500
ea 1 530,100 530,100
m 60 133,200 7,992,000
m 12 83,700 1,004,400
m 12 62,600 751,200
m 182 38,600 7,025,200
ls 1 2,516,400 2,516,400
ls 1 3,355,300 3,355,300
ls 1 1,342,100 1,342,100
ls 1 2,013,200 2,013,200

lot 1 5,263,200 5,263,200


ls 1 24,210,500 Nunggu
ls 1 161,360,500 Nunggu