R E K A P I T U L A S I

DAFTAR KUANTITAS DAN HARGA

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

NO URAIAN PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PENDAHULUAN 7,544,440.00

II. PEKERJAAN TANAH DAN PASIR 47,882,592.96

III. PEKERJAAN BETON DAN PASANGAN 1,230,677,618.06

IV. PEK. KAYU DAN KUNSEN 119,477,525.00

V. PEK. RANGKA KAP DAN ATAP 120,008,133.38

VI. PEKERJAAN INSTALASI LISTRIK 18,269,975.00

VII. PEKERJAAN GANTUNGAN DAN KUNCI 5,174,020.00

VIII. PEKERJAAN PENGECATAN 30,758,975.00

IX. PEKERJAAN PEMBUATAN KM/WC 147,179,411.38

JUMLAH 1,726,972,690.78
PPn 10 % 172,697,269.08
JUMLAH TOTAL 1,899,669,959.85
DIBULATKAN 1,899,669,000.00

Terbilang
xxxxxxxxxxxxxxxxxxxx
:

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur
DAFTAR HARGA SATUAN JADI
### #REF!
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
HARGA SATUAN

NO URAIAN PEKERJAAN SATUAN

(Rp.)
1. #REF! #REF! #REF!
2. #REF! #REF! #REF!
3. #REF! #REF! #REF!
4. #REF! #REF! #REF!
5. #REF! #REF! #REF!
6. #REF! #REF! #REF!
7. #REF! #REF! #REF!
8. #REF! #REF! #REF!
9. #REF! #REF! #REF!
10. #REF! #REF! #REF!
11. #REF! #REF! #REF!
12. #REF! #REF! #REF!
13. #REF! #REF! #REF!
14. #REF! #REF! #REF!
15. #REF! #REF! #REF!
16. #REF! #REF! #REF!

xxxxxxxxxxx, 29 Juli 2013

0 Dibuat Oleh,
0

0 xxxxxxxxxxxxxxxxxxx
0 Direktur
DAFTAR KUANTITAS DAN HARGA

HARGA SATUAN

NO URAIAN PEKERJAAN VOLUME SAT

1 2 3 4 5

I. PEKERJAAN PENDAHULUAN (Rp.)


1 Pek. Persiapan, Pembersihan Awal Dan Akhir Pekerjaan 1.00 Ls 1,000,000.00
2 Pek. Pasangan Bowplank 58.00 M' 48,180.00
3 Pek. Papan Nama Proyek 1.00 Ls 250,000.00
4 Pek. Dokumentasi 1.00 Ls 1,000,000.00
5 Pek. Barak Kerja Sementara 1.00 Ls 2,000,000.00
6 Air Kerja 1.00 Ls 500,000.00
JUMLAH I
II. PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi 135.952 M3 22,400.00
2 Pek. Urugan Kembali Tanah Pondasi 50.984 M3 10,740.00
3 Pek. Pasir Urug Dibawah Lantai Dan Pondasi 300.750 M3 111,600.00
4 Pek. Timbunan Tanah Didatangkan ( Bawah lantai ) 86.500 M3 124,000.00
JUMLAH II
III. PEKERJAAN BETON DAN PASANGAN
1
2 Pek. Pasangan Pondasi Tapak Beton 97.200 M3 3,268,395.00
3 Pek. Balok Sloof 9.600 M3 4,362,505.00
4 Pek. Tiang Kolom 1.264 M3 4,264,555.00
5
6
7 Pek. Tiang Kolom baja ### kg 14,500.00
8 Pek. Balok lantai 2 dan 3 8,458.000 kg 14,500.00
9 Pek. Pasangan Dinding 756.000 M2 92,220.00
10 Pek. Plesteran Dinding 1,512.021 M2 44,335.00
11 Pek. Cor Lantai 115.600 M3 591,450.00
12 Pek. Pasangan Lantai Keramik 720.000 M2 118,900.00
13 Pek. Pasangan Dinding saluran 334.500 M2 98,755.00
14 Pek. Plesteran 670.000 M2 56,572.00
JUMLAH III
IV. PEK. KAYU DAN KUSEN
1 Pek. Konsen Pintu, Jendela, 54.000 buah 1,500,000.00
2 Pek. Pas. Konsen Ventilasi Silang 40.000 Unit 43,280.63
3 Pek. Daun Pintu 63.000 M2 390,500.00
4 Pek. Daun Jendela Kaca 38.000 M2 319,600.00

JUMLAH IV
V. PEK. RANGKA KAP DAN ATAP
1 Pek. Pasangan Rangka Atap Baja Ringan 245.000 M2 183,759.50
2 Pek. Pasangan Atap zincalum 245.000 M2 70,000.00
3 Pek. Bumbungan Genteng 32.000 M' 70,000.00
4 Pek. Listplang 76.000 M' 62,850.00
5 Pek. Rangka Plapond 630.876 M2 64,650.00
6 Pek. Plapond 190.876 M2 34,980.00
7 Pek. List Plapond 196.000 M' 17,130.00
JUMLAH V
VI. PEKERJAAN INSTALASI LISTRIK
1 Pek. Instalasi Listrik dan Cahaya 58.000 Ttk 155,250.00
2 Pek. Lampu XL 20 Watt ( Lampu Hemat Energi ) 40.000 Bh 50,600.00
3 Pek. Stop Kontak 48.000 Bh 37,450.00
4 Pek. Saklar Ganda 64.000 Bh 37,450.00
5 Pek. Saklar Tunggal 46.000 Bh 32,450.00
6 Pek. MCB 15.000 Bh 103,625.00
JUMLAH VI
VII. PEKERJAAN GANTUNGAN DAN KUNCI
1 Pek. Kunci Pintu 2 Slaag 4.000 Bh 119,475.00
2 Pek. Engsel Pintu 4 " 54.000 Bh 31,248.00
3 Pek. Engsel Jendela 3 " 34.000 Bh 28,248.00
4 Hak Angin 34.000 Bh 20,748.00
5 Pek. Grendel Jendela 34.000 Bh 21,248.00
6 Tarikan Jendela 34.000 Bh 18,248.00
JUMLAH VII
VIII. PEKERJAAN PENGECATAN
1 Pek. Cat Tembok 1,512.000 M2 13,975.00
2 Pek. Cat Plapond 689.000 M2 13,975.00

JUMLAH VIII
HARGA SATUAN

NO URAIAN PEKERJAAN VOLUME SAT

1 2 3 4 5

IX. PEKERJAAN ARSITEKTUR DAN LAIN LAIN (Rp.)


1 Pek. Galian Tanah Pondasi 2.800 M3 22,400.00
2 Pek. Urugan Kembali Tanah Pondasi 1.440 M3 10,740.00
3 Pek. Pasangan Pondasi Beton Cor 1 : 2 : 3 0.960 M3 814,305.00
4 Pek. Tiang Kolom Praktis 11 x 11 cm 480.000 M' 83,355.59
5 Pek. Pasangan Dinding Bata 22.900 M2 92,220.00
6 Pek. Plesteran dinding toilet 486.000 M2 44,335.00
7 Pek. Konsen Pintu 0.072 M3 5,770,750.00
8 Pek. Daun Pintu Panil 2.800 M2 390,500.00
9 Pek. Pas. Kunci Pintu 2.000 Unit 119,475.00
10 Pek. Pas. Engsel Pintu 6.000 Unit 31,248.00
11 Pek. Pas. Rangka Atap Baja Ringan 15.600 M2 183,759.50
12 Pek. Pasangan Atap Genteng Metal 15.600 M2 54,860.00
13 Pek. Bumbungan Genteng Metal 4.000 M' 30,250.00
14 Pek. Listplang 15.000 M' 62,850.00
15 Pek. Rangka Plapond 8.750 M2 64,650.00
16 Pek. Plapond 18.250 M2 34,980.00
17 Pek. Kaca Es T = 5 mm Utk. Ventilasi 0.490 M2 123,245.00
18 Pek. Pas. Lantai Beton Cor 1 : 3 : 5 Diaci Tebal 10 cm 0.650 M3 591,450.00
19 Pek. Pas. Dinding Keramik 20 x 20 cm T = 120 cm 7.637 M2 113,900.00
20 Pek. Pasangan Lantai Keramik WC 30x30 cm 48.000 M2 138,370.00
21 Pek. Pas. Bak Air Fibber 2.000 Unit 666,800.00
22 Pek. Pas. Closet Jongkok 30.000 Unit 1,500,000.00
23 Pek. Pas. Kran Air 48.000 Unit 44,162.50
24 Pas. Floor Drain 63.000 Unit 24,100.00
25 Pek. Pas. Pipa Paralon, Sambungan, Lem + Upah 54.000 Ls 150,000.00
26 Pek. Pembuatan Septic tank 1.000 Ls 1,591,017.14
27 Pek. Pembutan Sumur Gali Dalam 6 M + ( Beton Gorong Dia + 80 1.000 Ls 1,250,000.00
28 Pek. Pas. Pompa Air ( Upah Pasang ) 1.000 Ls 2,500,000.00
29 Pek. Cat Tembok 216.600 M2 13,975.00
30 Pek. Cat Kilat 8.720 M2 37,660.00
JUMLAH IX

TOTAL PEKERJAAN 1,726,972,690.78

-
AR KUANTITAS DAN HARGA

JUMLAH HARGA

(Rp.)

1,000,000.00
2,794,440.00
250,000.00
1,000,000.00
2,000,000.00
500,000.00
7,544,440.00

3,045,324.80
547,568.16
33,563,700.00
10,726,000.00
47,882,592.96

-
317,687,994.00
41,880,048.00
5,390,397.52
-
-
381,408,000.00
122,641,000.00
69,718,320.00
67,035,451.04
68,371,620.00
85,608,000.00
33,033,547.50
37,903,240.00
1,230,677,618.06

81,000,000.00
1,731,225.00
24,601,500.00
12,144,800.00

119,477,525.00

45,021,077.50
17,150,000.00
2,240,000.00
4,776,600.00
40,786,133.40
6,676,842.48
3,357,480.00
120,008,133.38

9,004,500.00
2,024,000.00
1,797,600.00
2,396,800.00
1,492,700.00
1,554,375.00
18,269,975.00

477,900.00
1,687,392.00
960,432.00
705,432.00
722,432.00
620,432.00
5,174,020.00

21,130,200.00
9,628,775.00

30,758,975.00
JUMLAH HARGA

(Rp.)

62,720.00
15,465.60
781,732.80
40,010,682.09
2,111,838.00
21,546,810.00
415,494.00
1,093,400.00
238,950.00
187,488.00
2,866,648.20
855,816.00
121,000.00
942,750.00
565,687.50
638,385.00
60,390.05
384,442.50
869,854.30
6,641,760.00
1,333,600.00
45,000,000.00
2,119,800.00
1,518,300.00
8,100,000.00
1,591,017.14
1,250,000.00
2,500,000.00
3,026,985.00
328,395.20
147,179,411.38
R E K A P I T U L A S I

KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS


PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANG
LOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARA
SUMBER DANA : DAK/DAU
TAHUN ANGGARAN : 2009

NO JENIS PEKERJAAN HARGA (Rp)

A. PEKERJAAN PERSIAPAN 14,850,000.00


B. PEMBANGUNAN GEDUNG RAWAT JALAN #REF!
C. PEMBANGUNAN GEDUNG RAWAT INAP #REF!
D. PEKERJAAN KORIDOR PENGHUBUNG 12,000,000.00
E. PEKERJAAN LAIN - LAIN 4,500,000.00

A. SUB TOTAL #REF!


B. PPN 10 % #REF!
C. IMB 13,410,000.00
( A + B + C) TOTAL #REF!
DIBULATKAN #REF!

Terbilang : " Satu Milyar Enam Ratus Satu Juta Enam Ratus Ribu Rupiah "

Kwandang, 23 Maret 2009


Mengetahui
PT. PERDANA PUTRA BAJATAMA Dibuat Oleh

ABDUL RASYID ABAS xxxxxxxxxxxxx


Direktur Pimpinan Teknik
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS
PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANG
LOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARA
SUMBER DANA : DAK/DAU
TAHUN ANGGARA
: 2009

HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOL SATUAN HARGA
( Rp.) ( Rp. )

A. PEKERJAAN PERSIAPAN 14,850,000.00


1 Pekerjaan Pembuatan Papan Nama Proyek Ls 1.00 500,000.00 500,000.00
2 Pembersihan awal Ls 1.00 1,000,000.00 1,000,000.00
3 Pembongkaran Bangunan Lama Ls 1.00 6,000,000.00 6,000,000.00
4 Biaya administrasi / dokumentasi Ls 1.00 1,500,000.00 1,500,000.00
5 Pekerjaan Penyediaan Air Kerja Ls 1.00 2,000,000.00 2,000,000.00
6 Biaya Pemindahan/Pasang Meteran PLN Lama Ls 1.00 350,000.00 350,000.00
7 Direksi Keet Ls 1.00 3,000,000.00 3,500,000.00

B. PEMBANGUNAN GEDUNG RAWAT JALAN #REF!


I PEKERJAAN TANAH DAN URUGAN
1 Galian tanah untuk pondasi M³ 103.68 22,400.00 2,322,432.00
2 Urugan tanah kembali M³ 34.56 - -
3 Pekerjaan Timbunan lantai M³ 79.65 #REF! #REF!
4 Urugan pasir dibawah Pondasi dan lantai M³ 23.90 #REF! #REF!

II PEKERJAAN PONDASI
1 Pasangan batu kosong / aanstamping M³ 13.30 #REF! #REF!
2 Pas. pondasi batu kali camp 1 : 4 M³ 61.66 #REF! #REF!
=
=
III PEKERJAAN BETON =
1 Pekerjaan Cor Lantai Kerja 1 : 3 : 5 M³ 12.39 - -
2 Pekerjaan Beton Pondasi Tapak M³ 7.88 #REF! #REF!
3 Pek. Lantai Beton Bertulang 1:2:3 M³ 18.72 #REF! #REF!
4 Pek. Beton Sloof 20/25 M³ 6.20 #REF! #REF!
5 Pek. Beton Kolom K1 30/30 M³ 5.26 #REF! #REF!
6 Pek. Beton Kolom K2 20/30 M³ 0.46 #REF! #REF!
7 Pek. Beton Kolom K3 20/20 M³ 2.34 #REF! #REF!
8 Pek. Beton Kolom K4 11/20 M³ 0.10 #REF! #REF!
9 Pek. Beton Kolom Praktis 12/12 M³ 3.57 #REF! #REF!
10 Pek. Beton Balok B1 25/40 M³ 10.80 #REF! #REF!
11 Pek. Beton Balok B2 20/30 M³ 0.24 #REF! #REF!
12 Pek. Beton Balok B3 15/20 M³ 2.55 #REF! #REF!
13 Pek. Beton Balok Ring 15/20 M³ 5.58 #REF! #REF!
14 Pek. Beton Balok Bordes 25/20 M³ 0.25 #REF! #REF!
15 Pek. Beton Balok Latei 12/15 M³ 2.84 #REF! #REF!
16 Pek. Lisplank Beton M³ 31.53 #REF! #REF!
17 Pek. Tangga/Bordes Beton M³ 1.33 #REF! #REF!
18 Pekerjaan Beton Plat Level M³ 1.72 #REF! #REF!
19 Pekerjaan Beton Plat Meja M³ 0.12 #REF! #REF!
=
=
IV PEKERJAAN PAS. DINDING DAN PLESTERAN =
1 Pas. Tembok bt. Bata trasram camp. 1Pc : 3Ps M² 67.89 #REF! #REF!
2 Pas. Tembok bt. Bata camp. 1Pc : 5Ps M² 583.69 #REF! #REF!
3 Plesteran tembok trasram camp. 1Pc : 3Ps M² 135.78 #REF! #REF!
4 Plesteran tembok biasa camp. 1Pc : 5Ps M² 1,109.01 #REF! #REF!
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOL SATUAN HARGA
( Rp.) ( Rp. )

5 Pekerjaan Acian M² 1,244.79 #REF! #REF!


6 Pek. Papan Nama Stainless Steel Ls 1.00 1,000,000.00 1,000,000.00
=

V PEKERJAAN PINTU JENDELA DAN VENTILASI =


1 Pek. Kusen pintu dan jendela Aluminium M' 741.64 #REF! #REF!
2 Pek. Bingkai Jendela Aluminium M' 582.88 #REF! #REF!
3 Pas. Pintu Panel Aluminium/Kaca M² 31.74 #REF! #REF!
4 Pas. Sekat Multipleks 5 mm M² 31.50 #REF! #REF!
5 Pas. Pintu PVC Set 5.00 #REF! #REF!
6 Pas. Kaca polos t = 4,5 mm M² 73.15 #REF! #REF!
7 Pas. Railling Stainless Balkon M' 22.00 375,000.00 8,250,000.00
=
###
VI PEKERJAAN ATAP =
1 Pekerjaan Kuda-Kuda Kayu Kelas II M³ 6.79 #REF! #REF!
2 Pekerjaan Rangka Atap Kayu Kelas II M² 172.90 #REF! #REF!
3 Pekerjaan Atap Genteng Sakura Roof M² 172.90 #REF! #REF!
4 Pekerjaan Nok Genteng Sakura Roof M' 64.74 #REF! #REF!
5 Pekerjaan Lisplank Kayu M' 9.00 #REF! #REF!
=
=
VII PEKERJAAN PLAFOND =
1 Pekerjaan Pasangan rangka Plafond M² 409.94 #REF! #REF!
2 Pekerjaan Plafond Tripleks 3 mm M² 409.94 #REF! #REF!
3 Pekerjaan Lis Plafon Sp. 3 M' 388.00 - -
=
=
VIII PEKERJAAN KERAMIK =
1 Pas. Keramik 40 x 40 cm polos M² 324.20 #REF! #REF!
2 Pas. Keramik 20 x 20 cm KM/WC M² 9.50 #REF! #REF!
3 Pas. Keramik Dinding 20 x 25 cm KM/WC/Meja Beton M² 27.90 #REF! #REF!
=
IX PEKERJAAN GANTUNGAN DAN KUNCI =
1 Pas. Engsel Pintu Psg 22.00 #REF! #REF!
2 Pas. Engsel Jendela Psg 150.00 #REF! #REF!
3 Pas. Kunci 3 Lever Bh 22.00 #REF! #REF!
4 Pas. Grendel Tanam Bh 150.00 #REF! #REF!
5 Pas. Hak Angin Psg 150.00 #REF! #REF!
6 Pas. Ekspagnyolet Stainless Psg 10.00 #REF! #REF!
7 Pas. Door Closer Psg 22.00 #REF! #REF!
=
=
X PEKERJAAN PERLENGKAPAN DALAM =
Pekerjaan Instalasi Listrik =
1 Pasang MCB 6 grup Bh 6.00 #REF! #REF!
2 Penyambungan Kabel Listrik Ls 1.00 350,000.00 350,000.00
3 Pasangan Lampu Pijar 25 Watt Unit 6.00 #REF! #REF!
4 Pasangan Lampu SL Philips 18 Watt + Downlight Unit 18.00 #REF! #REF!
5 Pasangan Lampu SL Philips 18 Watt Unit 25.00 #REF! #REF!
6 Lampu TL Armateur 2 x 36 Watt Unit 26.00 #REF! #REF!
7 Pasangan Saklar Doubel Unit 24.00 #REF! #REF!
8 Pasangan Saklar Tunggal Unit 10.00 #REF! #REF!
9 Pasangan Stop Kontak Unit 38.00 #REF! #REF!
10 Pasangan Instalasi Titik Lampu Ttk 75.00 #REF! #REF!
Pekerjaan Sanitasi Dan Instalasi Air =
1 Pasangan Floor Drain Bh 5.00 #REF! #REF!
2 Pasangan Pipa VE 0,5" (Air Bersih) M1 102.00 #REF! #REF!
3 Pasangan Pipa VE 2" (Air Kotor) M1 94.00 #REF! #REF!
4 Pasangan Pipa VE 3" (Air Hujan) M1 211.50 #REF! #REF!
5 Pasangan Pipa VE 4" (Air Kotor) M1 40.00 #REF! #REF!
6 Pasangan Kran Air Bh 11.00 #REF! #REF!
7 Pasangan Kloset Duduk Bh 5.00 #REF! #REF!
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOL SATUAN HARGA
( Rp.) ( Rp. )

8 Pasangan Wastafel Bh 6.00 #REF! #REF!


9 Pasang Septic tank dan peresapan Unit 1.00 #REF! #REF!
10 Pasang Saluran Air Hujan M' 58.00 #REF! #REF!
=
XI PEKERJAAN PENGECATAN =
1 Pek. Pengecatan Tembok Dan Plafond M² 1,654.73 #REF! #REF!
2 Pek. Pengecatan Lisplank Kayu M² 4.50 #REF! #REF!
3 Pek. Pengecatan Waterproofing Lisplank Beton M² 192.20 #REF! #REF!
=

C. PEMBANGUNAN GEDUNG RAWAT INAP #REF!

I PEKERJAAN TANAH DAN URUGAN


1 Galian tanah untuk pondasi M³ 120.62 22,400.00 2,701,888.00
2 Urugan tanah kembali M³ 40.21 - -
3 Pekerjaan Timbunan lantai M³ 135.90 #REF! #REF!
4 Urugan pasir dibawah Pondasi dan lantai M³ 36.36 #REF! #REF!

II PEKERJAAN PONDASI
1 Pasangan batu kosong / aanstamping M³ 20.27 #REF! #REF!
2 Pas. pondasi batu kali camp 1 : 4 M³ 94.85 #REF! #REF!
=
=
III PEKERJAAN BETON
1 Pekerjaan Cor Lantai Kerja 1 : 3 : 5 M³ 21.14 - -
2 Pekerjaan Beton Pondasi Tapak M³ 2.63 #REF! #REF!
3 Pekerjaan Sloef Beton 15/20 M³ 5.91 #REF! #REF!
4 Pekerjaan Sloef Beton 20/30 M³ 0.96 #REF! #REF!
5 Pekerjaan Kolom K1 40/40 M³ 2.78 #REF! #REF!
6 Pekerjaan Kolom K3 25/25 M³ 2.74 #REF! #REF!
7 Pekerjaan Kolom K2 30/30 M³ 0.66 #REF! #REF!
8 Pekerjaan Kolom Praktis 12/12 M³ 2.05 #REF! #REF!
9 Pekerjaan Balok Latei 12/15 M³ 2.21 #REF! #REF!
10 Pekerjaan Ring Balok 15/20 M³ 5.37 #REF! #REF!
11 Pekerjaan Ring Balok 20/30 M³ 1.08 #REF! #REF!
12 Pekerjaan Beton Plat Level M³ 1.19 #REF! #REF!
13 Pekerjaan Beton Plat Meja M³ 0.21 #REF! #REF!
14 Pekerjaan Lisplank Beton M³ 21.39 #REF! #REF!
=
=
IV PEKERJAAN PAS. DINDING DAN PLESTERAN =
1 Pas. Tembok bt. Bata trasram camp. 1Pc : 3Ps M² 118.77 #REF! #REF!
2 Pas. Tembok bt. Bata camp. 1Pc : 5Ps M² 454.67 #REF! #REF!
3 Plesteran tembok trasram camp. 1Pc : 3Ps M² 237.54 #REF! #REF!
4 Plesteran tembok biasa camp. 1Pc : 5Ps M² 863.86 #REF! #REF!
5 Pekerjaan Acian M² 1,101.40 #REF! #REF!
6 Pekerjaan Profil Semen M' 86.92 #REF! #REF!
=

V PEKERJAAN PINTU JENDELA DAN VENTILASI =


1 Pek. Kusen pintu dan jendela Aluminium M' 293.08 #REF! #REF!
2 Pek. Bingkai Jendela Aluminium M' 202.70 #REF! #REF!
3 Pas. Pintu Panel Aluminium/Kaca M² 31.74 #REF! #REF!
4 Pas. Pintu PVC Set 6.00 #REF! #REF!
5 Pas. Kaca polos t = 4,5 mm M² 28.24 #REF! #REF!
=
###
VI PEKERJAAN ATAP =
1 Pekerjaan Kuda-Kuda Kayu Kelas II M³ 8.15 #REF! #REF!
2 Pekerjaan Rangka Atap Kayu Kelas II M² 421.78 #REF! #REF!
3 Pekerjaan Atap Genteng Sakura Roof M² 421.78 #REF! #REF!
4 Pekerjaan Nok Genteng Sakura Roof M' 60.47 #REF! #REF!
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOL SATUAN HARGA
( Rp.) ( Rp. )

=
=
VII PEKERJAAN PLAFOND =
1 Pekerjaan Pasangan rangka Plafond M² 384.00 #REF! #REF!
2 Pekerjaan Plafond Tripleks 3 mm M² 384.00 #REF! #REF!
3 Pekerjaan Lis Plafon Sp. 3 M' 361.00 - -
=
=
VIII PEKERJAAN KERAMIK =
1 Pas. Keramik 40 x 40 cm polos M² 253.00 #REF! #REF!
2 Pas. Keramik 20 x 20 cm KM/WC M² 16.50 #REF! #REF!
3 Pas. Keramik Dinding 20 x 25 cm KM/WC/Meja Beton M² 15.00 #REF! #REF!
=
IX PEKERJAAN GANTUNGAN DAN KUNCI =
1 Pas. Engsel Pintu Psg 18.00 #REF! #REF!
2 Pas. Engsel Jendela Psg 80.00 #REF! #REF!
3 Pas. Kunci 3 Lever Bh 4.00 #REF! #REF!
4 Pas. Kunci 2 Lever Bh 10.00 #REF! #REF!
5 Pas. Grendel Tanam Bh 80.00 #REF! #REF!
6 Pas. Hak Angin Psg 80.00 #REF! #REF!
7 Pas. Ekspagnyolet Stainless Psg 8.00 #REF! #REF!
8 Pas. Door Closer Psg 17.00 #REF! #REF!
=
=
X PEKERJAAN PERLENGKAPAN DALAM =
Pekerjaan Instalasi Listrik =
1 Pasang MCB 5 grup Bh 5.00 #REF! #REF!
2 Pasangan Lampu Pijar 25 Watt Unit 8.00 #REF! #REF!
3 Pasangan Lampu SL Philips 18 Watt Unit 17.00 #REF! #REF!
4 Lampu TL Armateur 2 x 36 Watt Unit 26.00 #REF! #REF!
5 Pasangan Saklar Doubel Unit 16.00 #REF! #REF!
6 Pasangan Saklar Tunggal Unit 7.00 #REF! #REF!
7 Pasangan Stop Kontak Unit 29.00 #REF! #REF!
8 Pasangan Instalasi Titik Lampu Ttk 51.00 #REF! #REF!
Pekerjaan Sanitasi Dan Instalasi Air =
1 Pasangan Floor Drain Bh 6.00 #REF! #REF!
2 Pasangan Pipa VE 0,5" (Air Bersih) M1 65.00 #REF! #REF!
3 Pasangan Pipa VE 2" (Air Kotor) M1 40.00 #REF! #REF!
4 Pasangan Pipa VE 4" (Air Kotor) M1 23.00 #REF! #REF!
5 Pasangan Pipa VE 3" (Air Hujan) M1 122.85 #REF! #REF!
6 Pasangan Kran Air Bh 9.00 #REF! #REF!
7 Pasangan Shower Bh 2.00 #REF! #REF!
8 Pasangan Kran Shower Bh 2.00 #REF! #REF!
9 Pasangan Kloset Jongkok Bh 4.00 #REF! #REF!
10 Pasangan Kloset Duduk Bh 2.00 #REF! #REF!
11 Pasangan Wastafel Bh 4.00 #REF! #REF!
12 Pasangan Kitchen Zink Bh 1.00 #REF! #REF!
13 Pasangan Bak Fiberglass Bh 4.00 #REF! #REF!
14 Pasang Septic tank dan peresapan Unit 3.00 #REF! #REF!
15 Pasang Saluran Air Hujan M' 66.00 #REF! #REF!
=
XI PEKERJAAN PENGECATAN =
1 Pek. Pengecatan Tembok Dan Plafond M² 1,485.40 #REF! #REF!
2 Pek. Pengecatan Waterproofing Lisplank Beton M² 130.38 #REF! #REF!

D. PEKERJAAN KORIDOR PENGHUBUNG 12,000,000.00


1 Selasar Rangka Stainless Steel Atap Polykarbonat Ls 1.00 12,000,000.00 12,000,000.00

E. PEKERJAAN LAIN - LAIN 4,500,000.00


1 Pembersihan Akhir Ls 1.00 1,000,000.00 1,000,000.00
2 Asbuilt Drawing Ls 1.00 3,500,000.00 3,500,000.00
=
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOL SATUAN HARGA
( Rp.) ( Rp. )

xxxxxxxxxxx, 29 Juli 2013


0 #REF!
0

0 xxxxxxxxxxxxx
0 Pimpinan Teknik
ANALISA TEKNIK
I. PEKERJAAN PENDAHULUAN
* Pek. Persiapan, Pembersihan Awal Dan Akhir Pekerjaan 12.0000 Hari
* Pek. Pasangan Bowplank 4.0000 Hari
* Pek. Papan Nama Proyek 1.0000 Hari
* Pek. Dokumentasi Selama Pelaksanaan
* Pek. Barak Kerja Sementara 4.0000 Hari
* Air Kerja 2.0000 Hari

II. PEKERJAAN TANAH DAN PASIR


* Pek. Galian Tanah Pondasi
- Volume Pekerjaan = 135.9520 M3
- Koefisien Pekerja
- Pekerja = 0.4000 O/H
- Mandor = 0.0400 O/H
0.4400

- Jumlah Pekerja
- Pekerja = 4.0000 Org
- Mandor = 0.0200 Org
4.0200 Org

- Waktu yang diperlukan ### x 0.4400 = 14.8803 Hari


4.0200
- Peralatan
- Mesin Air
- Waterpass
- Alat Bantu

* Pek. Urugan Kembali Tanah Pondasi


- Volume Pekerjaan = 50.9840 M3
- Koefisien Pekerja
- Pekerja = 0.1920 O/H
- Mandor = 0.0190 O/H
0.2110

- Jumlah Pekerja
- Pekerja = 4.0000 Org
- Mandor = 0.0200 Org
4.0200 Org

- Waktu yang diperlukan 50.9840 x 0.2110 = 2.6760 Hari


4.0200
- Peralatan
- Mesin Air
- Waterpass
- Alat Bantu
* Pek. Pasir Urug Dibawah Lantai Dan Pondasi
- Volume Pekerjaan = 300.7500 M3
- Koefisien Pekerja
- Pekerja = 0.3000 O/H
- Mandor = 0.0100 O/H
0.3100

- Jumlah Pekerja
- Pekerja = 4.0000 Org
- Mandor = 0.0200 Org
4.0200 Org

- Waktu yang diperlukan ### x 0.3100 = 23.1922 Hari


4.0200
- Bahan yang diperlukan
- Pasir Urug ### x 1.2000 = 360.9000 M3

- Peralatan
- Mesin Air
- Waterpass
- Dump Truck
- Alat Bantu

* Pek. Timbunan Tanah Didatangkan ( Bawah lantai )


- Volume Pekerjaan = 86.5000 M3
- Koefisien Pekerja
- Pekerja = 0.5000 O/H
- Mandor = 0.0500 O/H
0.5500

- Jumlah Pekerja
- Pekerja = 4.0000 Org
- Mandor = 0.0200 Org
4.0200 Org

- Waktu yang diperlukan 86.5000 x 0.5500 = 11.8346 Hari


4.0200
- Bahan yang diperlukan
- Tanah Timbunan 86.5000 x 1.2000 = 103.8000 M3

- Peralatan
- Mesin Air
- Waterpass
- Dump Truck
- Alat Bantu

Jumlah Hari Kerja = 52.5831 Hari


Dalam Mingguan 7.5119 Minggu
III. PEKERJAAN BETON DAN PASANGAN
###*
- Volume Pekerjaan = - M3
- Koefisien Pekerja
- Tukang = 0.2500 O/H
- Kepala Tukang = 0.0250 O/H
- Pekerja = 1.6500 O/H
- Mandor = 0.0800 O/H
2.0050
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.2000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.2400

- Waktu yang diperlukan - x 2.0050 = - Hari


12.2400
- Bahan yang diperlukan
- Kerikil - x 0.8700 = - M3
Pasir Pasang - x 0.5200 = - M3
Semen - x ### = - Kg

- Peralatan
- Mesin Air
- Dump Truk
- Concrete Mixer
- Concrete Vibrator
- Alat Bantu

* Beton Bertulang 1 : 2 : 3
- Volume Pekerjaan = 1.0000 M3
- Koefisien Pekerja
- Tukang = 0.2750 O/H
- Kepala Tukang = 0.0280 O/H
- Pekerja = 1.6500 O/H
- Mandor = 0.0830 O/H
2.0360
- Jumlah Pekerja
- Tukang = 0.5000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 1.0000 Org
- Mandor = 0.5000 Org
2.0500

- Waktu yang diperlukan 1.0000 x 2.0360 = 0.9932 Hari


2.0500
- Bahan yang diperlukan
- Kerikil 1.0000 x 0.7530 = 0.7530 M3
Pasir Pasang 1.0000 x 0.5710 = 0.5710 M3
Semen 1.0000 x ### = 371.0000 Kg

- Peralatan
- Sekop
- Cangkul
- Dump Truck
- Concrete Mixer
- Dll
* Pembesian
- Volume Pekerjaan = 1.0000 M3
- Koefisien Pekerja
- Tukang = 0.0070 O/H
- Kepala Tukang = 0.0007 O/H
- Pekerja = 0.0070 O/H
- Mandor = 0.0003 O/H
0.0150
- Jumlah Pekerja
- Tukang = 0.5000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 1.0000 Org
- Mandor = 0.5000 Org
2.0500

- Waktu yang diperlukan 1.0000 x 0.0150 = 0.0073 Hari


2.0500
- Bahan yang diperlukan
- Besi beton 1.0000 x 1.0500 = 1.0500 Kg
Kawat Beton 1.0000 x 0.0150 = 0.0150 Kg

- Peralatan
- Alat Bantu

* Bekisting
- Volume Pekerjaan = 1.0000 M3
- Koefisien Pekerja
- Tukang = 0.2600 O/H
- Kepala Tukang = 0.0260 O/H
- Pekerja = 0.5200 O/H
- Mandor = 0.0260 O/H
0.8320
- Jumlah Pekerja
- Tukang = 0.5000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 1.0000 Org
- Mandor = 0.5000 Org
2.0500

- Waktu yang diperlukan 1.0000 x 0.8320 = 0.4059 Hari


2.0500
- Bahan yang diperlukan
- Kayu Bekisting 1.0000 x 0.0450 = 0.0450 M3
Paku campuran 1.0000 x 0.3000 = 0.3000 Kg

- Peralatan
- Alat Bantu
* Membongkar / Menyiram Beton
- Volume Pekerjaan = 1.0000 M3
- Koefisien Pekerja
- Pekerja = 2.0000 O/H
- = O/H
- = O/H
- = O/H
2.0000
- Jumlah Pekerja
- Pekerja = 1.0000 Org
- = Org
- = Org
- = Org
1.0000

- Waktu yang diperlukan 1.0000 x 2.0000 = 2.0000 Hari


1.0000
- Bahan yang diperlukan
-

- Peralatan
- Alat Bantu

* Pek. Pasangan Pondasi Tapak Beton


- Volume Pekerjaan = 97.2000 M3
- Waktu Pelaksanaan
- Beton Bertulang 0.9932 x 97.2000 = 96.5362 Hari
- Pembesian 0.0073 x 97.2000 = 0.7112 Hari
- Bekisting 0.4059 x 97.2000 = 39.4490 Hari
- Membongkar / Menyiram Beton 2.0000 x 97.2000 = 194.4000 Hari
331.0964
- Bahan yang diperlukan
- Beton Bertulang 97.2000 x 1.0000 = 97.2000 M3
- Pembesian 97.2000 x ### = 14,580.0000 Kg
- Bekisting 97.2000 x 2.6667 = 259.2000 M2
- Membongkar / Menyiram Beton 97.2000 x 1.0000 = 97.2000 M3

* Pek. Balok Sloof


- Volume Pekerjaan = 9.6000 M3
- Koefisien
- Beton Bertulang 0.9932 x 9.6000 = 9.5344 O/H
- Pembesian 0.0073 x 9.6000 = 0.0702 O/H
- Bekisting 0.4059 x 9.6000 = 3.8962 O/H
- Membongkar / Menyiram Beton 2.0000 x 9.6000 = 19.2000 O/H
32.7009
- Bahan yang diperlukan
- Beton Bertulang 9.6000 x 1.0000 = 9.6000 M3
- Pembesian 9.6000 x ### = 1,920.0000 Kg
- Bekisting 9.6000 x 5.8333 = 56.0000 M2
- Membongkar / Menyiram Beton 9.6000 x 1.0000 = 9.6000 M3
* Pek. Tiang Kolom
- Volume Pekerjaan = 1.2640 M'
- Koefisien
- Beton Bertulang 0.9932 x 1.2640 = 1.2554 O/H
- Pembesian 0.0073 x 1.2640 = 0.0092 O/H
- Bekisting 0.4059 x 1.2640 = 0.5130 O/H
- Membongkar / Menyiram Beton 2.0000 x 1.2640 = 2.5280 O/H
4.3056
- Bahan yang diperlukan
- Beton Bertulang 1.2640 x 1.0000 = 1.2640 M3
- Pembesian 1.2640 x ### = 189.6000 Kg
- Bekisting 1.2640 x 10.0000 = 12.6400 M2
- Membongkar / Menyiram Beton 1.2640 x 1.0000 = 1.2640 M3

* Pek. Tiang Kolom baja


- Volume Pekerjaan = 26,304.0000 M'
- Koefisien
- Beton Bertulang 0.9932 x ### = 26,124.3629 O/H
- Pembesian 0.0073 x ### = 192.4683 O/H
- Bekisting 0.4059 x ### = 10,675.5746 O/H
- Membongkar / Menyiram Beton 2.0000 x ### = 52,608.0000 O/H
89,600.4059
Dalam M'= 0.0121 x ### = 1,084.1649

- Bahan yang diperlukan dalam M'


- Beton Bertulang ### x 0.0121 = 318.2784 M3
- Pembesian ### x 4.3189 = ### Kg
- Bekisting ### x 0.1100 = 2,893.4400 M2
- Membongkar / Menyiram Beton ### x 0.0121 = 318.2784 M3

* Pek. Balok lantai 2 dan 3


- Volume Pekerjaan = 8,458.0000 M'
- Koefisien
- Beton Bertulang 0.9932 x ### = 8,400.2380 O/H
- Pembesian 0.0073 x ### = 61.8878 O/H
- Bekisting 0.4059 x ### = 3,432.7102 O/H
- Membongkar / Menyiram Beton 2.0000 x ### = 16,916.0000 O/H
28,810.8361
Dalam M'= 0.0150 x ### = 432.1625

- Bahan yang diperlukan dalam M'


- Beton Bertulang ### x 0.0150 = 126.8700 M3
- Pembesian ### x 4.3197 = 36,535.6927 Kg
- Bekisting ### x 0.1250 = 1,057.2500 M2
- Membongkar / Menyiram Beton ### x 0.0150 = 126.8700 M3
* Pek. Pasangan Dinding
- Volume Pekerjaan = 756.0000 M2
- Koefisien Pekerja
- Tukang = 0.1000 O/H
- Kepala Tukang = 0.0100 O/H
- Pekerja = 0.3000 O/H
- Mandor = 0.0150 O/H
0.4250
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.4250 = 25.8280 Hari


12.4400
- Bahan yang diperlukan
- Batu Bata ### x 70.0000 = 52,920.0000 Bh
Pasir Pasangan ### x 0.0450 = 34.0200 M3
Semen ### x 9.6800 = 7,318.0800 Kg

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu

* Pek. Pasangan Dinding saluran


- Volume Pekerjaan = 334.5000 M2
- Koefisien Pekerja
- Tukang = 0.1000 O/H
- Kepala Tukang = 0.0100 O/H
- Pekerja = 0.3000 O/H
- Mandor = 0.0150 O/H
0.4250
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.4250 = 11.4279 Hari


12.4400
- Bahan yang diperlukan
- Batu Bata ### x 70.0000 = 23,415.0000 Bh
Pasir Pasang ### x 0.0400 = 13.3800 M3
Semen ### x 14.3700 = 4,806.7650 Kg

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu
* Pek. Plesteran Dinding
- Volume Pekerjaan = 1,512.0210 M2
- Koefisien Pekerja
- Tukang = 0.2000 O/H
- Kepala Tukang = 0.0200 O/H
- Pekerja = 0.2500 O/H
- Mandor = 0.0250 O/H
0.4950
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.4950 = 60.1648 Hari


12.4400
- Bahan yang diperlukan
- Pasir Pasangan ### x 0.0280 = 42.3366 M3
Semen ### x 7.2900 = 11,022.6331 Kg

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu

* Pek. Plesteran
- Volume Pekerjaan = 670.0000 M2
- Koefisien Pekerja
- Tukang = 0.2000 O/H
- Kepala Tukang = 0.0200 O/H
- Pekerja = 0.4000 O/H
- Mandor = 0.0220 O/H
0.6420
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.6420 = 34.5772 Hari


12.4400
- Bahan yang diperlukan
- Pasir Pasangan ### x 0.0310 = 20.7700 M3
Semen ### x 10.3680 = 6,946.5600 Kg

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu
* Pek. Cor Lantai
- Volume Pekerjaan = 115.6000 M3
- Koefisien Pekerja
- Tukang = 0.2500 O/H
- Kepala Tukang = 0.0250 O/H
- Pekerja = 1.6500 O/H
- Mandor = 0.0800 O/H
2.0050
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 2.0050 = 18.6317 Hari


12.4400
- Bahan yang diperlukan
- Kerikil ### x 0.8700 = 100.5720 M3
Pasir Pasang ### x 0.5200 = 60.1120 M3
Semen ### x ### = 25,200.8000 Kg

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu

* Pek. Pasangan Lantai Keramik


- Volume Pekerjaan = 720.0000 M2
- Koefisien Pekerja
- Tukang = 0.1000 O/H
- Kepala Tukang = 0.0450 O/H
- Pekerja = 0.6000 O/H
- Mandor = 0.0300 O/H
0.7750
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.7750 = 44.8553 Hari


12.4400
- Bahan yang diperlukan
- Keramik Lantai 30 x 30 ### x 1.0000 = 720.0000 M2
Semen ### x 9.3000 = 6,696.0000 Kg
Pasir Pasang ### x 0.0180 = 12.9600 M3
Semen Warna ### x 1.5000 = 1,080.0000 Kg

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu
###
*
- Volume Pekerjaan = - M2
- Koefisien Pekerja
- Tukang = 0.1100 O/H
- Kepala Tukang = 0.0110 O/H
- Pekerja = 0.6600 O/H
- Mandor = 0.0330 O/H
0.8140
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan - x 0.8140 = - Hari


12.4400
- Bahan yang diperlukan
- Batu alam - x 1.1000 = - M2
Semen Portland - x 9.3000 = - Kg
Pasir pasang - x 0.0180 = - M3

- Peralatan
- Mesin Air
- Dump Truck
- Concrete Mixer
- Waterpass
- Alat Bantu

Jumlah Hari Kerja = 2,079.9151 Hari


Dalam Mingguan 297.1307 Minggu

V. PEK. KAYU DAN KUSEN


* Pek. Konsen Pintu, Jendela,
- Volume Pekerjaan = 54.0000 M3
- Koefisien Pekerja
- Tukang = 18.0000 O/H
- Kepala Tukang = 1.8000 O/H
- Pekerja = 6.0000 O/H
- Mandor = 0.3000 O/H
26.1000
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan 54.0000 x 26.1000 = 113.2958 Hari


12.4400
- Bahan yang diperlukan
- Kayu Kulim 54.0000 x 1.2000 = 64.8000 M3
Lem Kayu 54.0000 x 1.0000 = 54.0000 Kg
Paku 54.0000 x 1.2500 = 67.5000 Kg

- Peralatan
- Alat Bantu
* Pek. Pas. Konsen Ventilasi Silang
- Volume Pekerjaan = 40.0000 Unit
- Koefisien Pekerja
- Tukang = 18.0000 O/H
- Kepala Tukang = 1.8000 O/H
- Pekerja = 6.0000 O/H
- Mandor = 0.3000 O/H
26.1000
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan 40.0000 x 26.1000 = 83.9228 Hari


12.4400

Dalam Unit = 0.0075 x ### = 0.6294 Hari

- Bahan yang diperlukan


- Kayu Kulim 40.0000 x 1.2000 = 48.0000 M3
Lem Kayu 40.0000 x 1.0000 = 40.0000 Kg
Paku 40.0000 x 1.2500 = 50.0000 Kg

- Peralatan
- Alat Bantu

* Pek. Daun Pintu


- Volume Pekerjaan = 63.0000 M2
- Koefisien Pekerja
- Tukang = 2.5000 O/H
- Kepala Tukang = 0.2500 O/H
- Pekerja = 1.0000 O/H
- Mandor = 0.0500 O/H
3.8000
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan 63.0000 x 3.8000 = 19.2444 Hari


12.4400
- Bahan yang diperlukan
- Kayu Kulim 63.0000 x 0.0400 = 2.5200 M3

- Peralatan
- Alat Bantu
* Pek. Daun Jendela Kaca
- Volume Pekerjaan = 38.0000 M2
- Koefisien Pekerja
- Tukang = 2.4000 O/H
- Kepala Tukang = 0.2400 O/H
- Pekerja = 0.8000 O/H
- Mandor = 0.0400 O/H
3.4800
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan 38.0000 x 3.4800 = 10.6302 Hari


12.4400
- Bahan yang diperlukan
- Kayu Kulim 38.0000 x 0.0240 = 0.9120 M3

- Peralatan
- Alat Bantu

###
*
- Volume Pekerjaan = - M2
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.0150 O/H
- Mandor = 0.0008 O/H
0.1808
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan - x 0.1808 = - Hari


12.4400
- Bahan yang diperlukan
- Kaca 5 mm - x 1.1000 = - M2

- Peralatan
- Alat Bantu

Jumlah Hari Kerja = 143.7998 Hari


Dalam Mingguan 20.5428 Minggu
V. PEK. RANGKA KAP DAN ATAP
Pek. Pasangan Rangka Atap Baja Ringan
- Volume Pekerjaan = 245.0000 M2
- Koefisien Pekerja
- Tukang = 0.8000 O/H
- Kepala Tukang = 0.0800 O/H
- Pekerja = 0.0800 O/H
- Mandor = 0.1000 O/H
1.0600
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 1.0600 = 20.8762 Hari


12.4400
- Bahan yang diperlukan
- Smar Truss C75.100 ### x 2.8510 = 698.4950 M
Web C75.75 ### x 1.7290 = 423.6050 M
Top Span 40 ### x 1.1220 = 274.8900 M
ZA, G550 ### x 4.8890 = 1,197.8050 M
Main Truss 1.05 TCT ### x 8.8650 = 2,171.9250 M
Web 0,8 TCT ### x 12.2070 = 2,990.7150 M
Ancor / Seng Pelapis Genteng ### x 0.0400 = 9.8000 Rol

- Peralatan
- Alat Bantu

Pek. Pasangan Atap zincalum


- Volume Pekerjaan = 245.0000 M2
- Koefisien Pekerja
- Tukang = 0.1000 O/H
- Kepala Tukang = 0.0100 O/H
- Pekerja = 0.2000 O/H
- Mandor = 0.0010 O/H
0.3110
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.3110 = 6.1250 Hari


12.4400
- Bahan yang diperlukan
- Atap Genteng Metal ### x 1.2000 = 294.0000 Lbr
Paku Genteng ### x 0.0200 = 4.9000 Kg

- Peralatan
- Alat Bantu
Pek. Bumbungan Genteng
- Volume Pekerjaan = 32.0000 M'
- Koefisien Pekerja
- Tukang = 0.0700 O/H
- Kepala Tukang = 0.0080 O/H
- Pekerja = 0.1500 O/H
- Mandor = 0.0060 O/H
0.2340
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan 32.0000 x 0.2340 = 0.6019 Hari


12.4400
- Bahan yang diperlukan
- Bubungan Genteng Metal 32.0000 x 1.1000 = 35.2000 M'

- Peralatan
- Alat Bantu

Pek. Listplang
- Volume Pekerjaan = 76.0000 M'
- Koefisien Pekerja
- Tukang = 0.2000 O/H
- Kepala Tukang = 0.0200 O/H
- Pekerja = 0.1000 O/H
- Mandor = 0.0050 O/H
0.3250
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan 76.0000 x 0.3250 = 1.9855 Hari


12.4400
- Bahan yang diperlukan
- Kayu Kelas II 76.0000 x 0.0160 = 1.2160 M3
Paku Campuran 76.0000 x 0.0500 = 3.8000 Kg

- Peralatan
- Alat Bantu
Pek. Rangka Plapond
- Volume Pekerjaan = 630.8760 M2
- Koefisien Pekerja
- Tukang = 0.2500 O/H
- Kepala Tukang = 0.0250 O/H
- Pekerja = 0.1500 O/H
- Mandor = 0.0750 O/H
0.5000
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.5000 = 25.3568 Hari


12.4400
- Bahan yang diperlukan
- Kayu Kls. II ### x 0.0120 = 7.5705 M3
Paku Campuran ### x 0.1000 = 63.0876 Kg

- Peralatan
- Alat Bantu

Pek. Plapond
- Volume Pekerjaan = 190.8760 M2
- Koefisien Pekerja
- Tukang = 0.0500 O/H
- Kepala Tukang = 0.0050 O/H
- Pekerja = 0.1000 O/H
- Mandor = 0.0050 O/H
0.1600
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.1600 = 2.4550 Hari


12.4400
- Bahan yang diperlukan
- GRC ### x 0.3640 = 69.4789 Lbr
Paku Sekrup ### x 0.1100 = 20.9964 Kg

- Peralatan
- Alat Bantu
Pek. List Plapond
- Volume Pekerjaan = 196.0000 M'
- Koefisien Pekerja
- Tukang = 0.0500 O/H
- Kepala Tukang = 0.0050 O/H
- Pekerja = 0.0500 O/H
- Mandor = 0.0030 O/H
0.1080
- Jumlah Pekerja
- Tukang = 4.0000 Org
- Kepala Tukang = 0.4000 Org
- Pekerja = 8.0000 Org
- Mandor = 0.0400 Org
12.4400

- Waktu yang diperlukan ### x 0.1080 = 1.7016 Hari


12.4400
- Bahan yang diperlukan
- List Profil Sp. 3 ### x 1.0500 = 205.8000 M'
Paku Campuran ### x 0.1000 = 19.6000 Kg

- Peralatan
- Alat Bantu

Jumlah Hari Kerja = 59.1020 Hari


Dalam Mingguan 8.4431 Minggu

VI. PEKERJAAN INSTALASI LISTRIK


Pek. Instalasi Listrik dan Cahaya
- Volume Pekerjaan = 58.0000 Ttk
- Koefisien Pekerja
- Tukang = 0.7500 O/H
- Kepala Tukang = 0.0750 O/H
- Pekerja = 0.4000 O/H
- Mandor = - O/H
1.2250
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.1000 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.1100

- Waktu yang diperlukan 58.0000 x 1.2250 = 22.8457 Hari


3.1100
- Bahan yang diperlukan
- Kawat NYYM 2 x 2.5 mm 58.0000 x 6.0000 = 348.0000 M'
Klem PVC 1/2" 58.0000 x 0.5000 = 29.0000 Lot
T.Dos PVC 58.0000 x 4.0000 = 232.0000 Bh
Bok PVC 58.0000 x 2.0000 = 116.0000 Bh
Isolatip 58.0000 x 2.0000 116.0000 Bh

- Peralatan
- Alat Bantu
* Pek. Lampu XL 20 Watt ( Lampu Hemat Energi )
- Volume Pekerjaan = 40.0000 Bh
- Koefisien Pekerja
- Tukang = - O/H
- Kepala Tukang = - O/H
- Pekerja = 0.1000 O/H
- Mandor = 0.0100 O/H
0.1100
- Jumlah Pekerja
- Tukang = - Org
- Kepala Tukang = - Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
2.0100

- Waktu yang diperlukan 40.0000 x 0.1100 = 2.1891 Hari


2.0100
- Bahan yang diperlukan
- Lampu XL 20 Watt 40.0000 x 1.0000 = 40.0000 Bh

- Peralatan
- Alat Bantu

* Pek. Stop Kontak


- Volume Pekerjaan = 48.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.1000 O/H
- Mandor = - O/H
0.2650
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.1000 Org
- Pekerja = 2.0000 Org
- Mandor = - Org
3.1000

- Waktu yang diperlukan 48.0000 x 0.2650 = 4.1032 Hari


3.1000
- Bahan yang diperlukan
- Stop Kontak 48.0000 x 1.0000 = 48.0000 Bh

- Peralatan
- Alat Bantu
* Pek. Saklar Ganda
- Volume Pekerjaan = 64.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.1000 O/H
- Mandor = - O/H
0.2650
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.1000 Org
- Pekerja = 2.0000 Org
- Mandor = - Org
3.1000

- Waktu yang diperlukan 64.0000 x 0.2650 = 5.4710 Hari


3.1000
- Bahan yang diperlukan
- Saklar Ganda 64.0000 x 1.0000 = 64.0000 Bh

- Peralatan
- Alat Bantu

* Pek. MCB
- Volume Pekerjaan = 15.0000 Bh
- Koefisien Pekerja
- Tukang = 0.3750 O/H
- Kepala Tukang = 0.0375 O/H
- Pekerja = 0.2500 O/H
- Mandor = - O/H
0.6625
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.1000 Org
- Pekerja = 2.0000 Org
- Mandor = - Org
3.1000

- Waktu yang diperlukan 15.0000 x 0.6625 = 3.2056 Hari


3.1000
- Bahan yang diperlukan
- MCB 15.0000 x 1.0000 = 15.0000 Bh

- Peralatan
- Alat Bantu

Jumlah Hari Kerja = 37.8146 Hari


Dalam Mingguan 5.4021 Minggu
VII. PEKERJAAN GANTUNGAN DAN KUNCI
* Pek. Kunci Pintu 2 Slaag
- Volume Pekerjaan = 4.0000 Bh
- Koefisien Pekerja
- Tukang = 0.2250 O/H
- Kepala Tukang = 0.0225 O/H
- Pekerja = 0.0100 O/H
- Mandor = 0.0050 O/H
0.2625
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan 4.0000 x 0.2625 = 0.3431 Hari


3.0600
- Bahan yang diperlukan
- Kunci Tanam 2 Slaag 4.0000 x 1.0000 = 4.0000 Bh

- Peralatan
- Alat Bantu

* Pek. Engsel Pintu 4 "


- Volume Pekerjaan = 54.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.0150 O/H
- Mandor = 0.0008 O/H
0.1808
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan 54.0000 x 0.1808 = 3.1906 Hari


3.0600
- Bahan yang diperlukan
- Engsel Pintu Lengkap 4" 54.0000 x 1.0000 = 54.0000 M2

- Peralatan
- Alat Bantu
* Pek. Engsel Jendela 3 "
- Volume Pekerjaan = 34.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.0150 O/H
- Mandor = 0.0008 O/H
0.1808
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan 34.0000 x 0.1808 = 2.0089 Hari


3.0600
- Bahan yang diperlukan
- Engsel Jendela Lengkap 3" 34.0000 x 1.0000 = 34.0000 Bh

- Peralatan
- Alat Bantu

* Hak Angin
- Volume Pekerjaan = 34.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.0150 O/H
- Mandor = 0.0008 O/H
0.1808
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan 34.0000 x 0.1808 = 2.0089 Hari


3.0600
- Bahan yang diperlukan
- Hak Angin 34.0000 x 1.0000 = 34.0000 Bh

- Peralatan
- Alat Bantu
* Pek. Grendel Jendela
- Volume Pekerjaan = 34.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.0150 O/H
- Mandor = 0.0008 O/H
0.1808
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan 34.0000 x 0.1808 = 2.0089 Hari


3.0600
- Bahan yang diperlukan
- Grendel Jendela 34.0000 x 1.0000 = 34.0000 Bh

- Peralatan
- Alat Bantu

* Tarikan Jendela
- Volume Pekerjaan = 34.0000 Bh
- Koefisien Pekerja
- Tukang = 0.1500 O/H
- Kepala Tukang = 0.0150 O/H
- Pekerja = 0.0150 O/H
- Mandor = 0.0008 O/H
0.1808
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan 34.0000 x 0.1808 = 2.0089 Hari


3.0600
- Bahan yang diperlukan
- Tarikan Jendela 34.0000 x 1.0000 = 34.0000 Bh

- Peralatan
- Alat Bantu

Jumlah Hari Kerja = 11.5693 Hari


Dalam Mingguan 1.6528 Minggu
VIII. PEKERJAAN PENGECATAN
* Pengecatan Dinding & Plafond
- Volume Pekerjaan = 2,201.0000 M2
- Koefisien Pekerja
- Tukang = 0.0630 O/H
- Kepala Tukang = 0.0060 O/H
- Pekerja = 0.0200 O/H
- Mandor = 0.0020 O/H
0.0910
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan ### x 0.0910 = 65.4546 Hari


3.0600
- Bahan yang diperlukan
- Plamir Dinding ### x 0.1000 = 220.1000 Kg
- Cat Dasar ### x 0.1000 = 220.1000 Kg
- Cat Penutup 2x ### x 0.2600 = 572.2600 Kg

- Peralatan
- Alat Bantu

* Mengecat Mengkilap
- Volume Pekerjaan = - M2
- Koefisien Pekerja
- Tukang = 0.0090 O/H
- Kepala Tukang = 0.0060 O/H
- Pekerja = 0.0700 O/H
- Mandor = 0.0030 O/H
0.0880
- Jumlah Pekerja
- Tukang = 1.0000 Org
- Kepala Tukang = 0.0500 Org
- Pekerja = 2.0000 Org
- Mandor = 0.0100 Org
3.0600

- Waktu yang diperlukan - x 0.0880 = - Hari


3.0600
- Bahan yang diperlukan
- Plamir kayu - x 0.1500 = - Kg
- Cat Dasar - x 0.2600 = - Kg
- Cat Mengkilap - x 0.1700 = - Kg
Menie - x 0.2000 = - Kg

- Peralatan
- Alat Bantu

Jumlah Hari Kerja = 65.4546 Hari


Dalam Mingguan 9.3507 Minggu
IX. PEKERJAAN ARSITEKTUR DAN LAIN LAIN
* Pek. Galian Tanah Pondasi = 1.0000 Hari
Pek. Urugan Kembali Tanah Pondasi = 1.0000 Hari
Pek. Pasangan Pondasi Beton Cor 1 : 2 : 3 = 1.0000 Hari
Pek. Tiang Kolom Praktis 11 x 11 cm = 1.0000 Hari
Pek. Pasangan Dinding Bata = 1.0000 Hari
Pek. Plesteran dinding toilet = 2.0000 Hari
Pek. Konsen Pintu = 2.0000 Hari
Pek. Daun Pintu Panil = 2.0000 Hari
Pek. Pas. Kunci Pintu = 2.0000 Hari
Pek. Pas. Engsel Pintu = 2.0000 Hari
Pek. Pas. Rangka Atap Baja Ringan = 2.0000 Hari
Pek. Pasangan Atap Genteng Metal = 2.0000 Hari
Pek. Bumbungan Genteng Metal = 2.0000 Hari

Jumlah Hari Kerja = 21.0000 Hari


Dalam Mingguan 3.0000 Minggu

Demikian tahapan-tahapan pelaksanaan pekerjaan Pemb. RKB MDT Nurul Ikhlas Desa
xxxxxxxxxxx Kec. xxxxxxxxx kami buat untuk menjadi acuan dalam pelaksanaan
pekerjaan.

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur
BOBOT

JADWAL WAKTU PELAKSANAAN (KURVA "S")

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

WAKTU PELAKSANAAN MINGGU KE -


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 17.14
NO. U R A I A N Keterangan
WAKTU PELAKSANAAN HARI KE -
1-7 8-14 15-21 22-28 29-35 36-42 43-49 50-56 57-63 64-70 71-77 78-84 85-91 92-98 99-105 106-112 113-119 120
100
I PEKERJAAN PENDAHULUAN 0.437 0.022 0.044 0.044 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022

90
II PEKERJAAN TANAH DAN PASIR 2.773 1.386 1.386
80
III PEKERJAAN BETON DAN PASANGAN ### 3.563 ### ### ### ### ### 3.563 3.563
70
IV PEK. KAYU DAN KUNSEN 6.918 1.384 5.535 Jangka Waktu
60
Pelaksanaan
V PEK. RANGKA KAP DAN ATAP 6.949 0.347 1.390 2.085 2.085 0.695 0.347 120 (Seratus
50
Dua Puluh)
VI PEKERJAAN INSTALASI LISTRIK 1.058 0.529 0.529 40
Hari Kalender

VII PEKERJAAN GANTUNGAN DAN KUNCI 0.300 0.300 30


(%)
VIII PEKERJAAN PENGECATAN 1.781 1.069 0.534 0.178 20

10
IX PEKERJAAN PEMBUATAN KM/WC 8.522 3.835 3.835 0.852

JUMAH ### 0

I RENCANA KEMAJUAN MINGGUAN 0.022 1.430 4.993 ### ### ### ### ### 9.120 4.232 1.941 2.636 5.942 4.552 1.222 1.090 0.556 0.200

II RENCANA KOMULATIF MINGGUAN - 0.022 1.452 6.445 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

III REALISASI

IV DEVIASI

xxxxxxxxxxx, 29 Juli 2013

#REF! Dibuat Oleh,


### Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur
ANALISA HARGA SATUAN

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

JENIS PEKERJAAN : PENGUKURAN DAN PEMASANGAN BOWPLANK


SATUAN : M1
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN - - -
Papan Bouwplank M3 0.0070 1,800,000 12,600.00
Balok Bouwplank M3 0.0120 1,800,000 21,600.00
Paku Kg 0.0200 19,000 380.00
Sub Total A 34,580.00

B. UPAH
Tukang O/H 0.1000 75,000.00 7,500.00
Kepala Tukang O/H 0.0100 80,000.00 800.00
Pekerja O/H 0.1000 50,000.00 5,000.00
Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 13,600.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 48,180.00

JENIS PEKERJAAN : GALIAN TANAH BIASA


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN - - -

Sub Total A

B. UPAH
Pekerja O/H 0.4000 50,000.00 20,000.00
Mandor O/H 0.0400 60,000.00 2,400.00
Sub Total B 22,400.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 22,400.00

39
JENIS PEKERJAAN : URUGAN TANAH KEMBALI
SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN - - -
- - -
Sub Total A

B. UPAH
Pekerja O/H 0.1920 50,000.00 9,600.00
Mandor O/H 0.0190 60,000.00 1,140.00
Sub Total B 10,740.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 10,740.00

JENIS PEKERJAAN : URUGAN PASIR DIBAWAH LANTAI & PONDASI


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Pasir Urug M3 1.2000 80,000.00 96,000.00

Sub Total A 96,000

B. UPAH
Pekerja O/H 0.3000 50,000.00 15,000.00
Mandor O/H 0.0100 60,000.00 600.00
Sub Total B 15,600.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 111,600.00

JENIS PEKERJAAN : TIMBUNAN TANAH


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Tanah Timbunan M3 1.2000 80,000.00 96,000.00

Sub Total A 96,000

B. UPAH
Pekerja O/H 0.5000 50,000.00 25,000.00
Mandor O/H 0.0500 60,000.00 3,000.00
Sub Total B 28,000.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 124,000.00

40
JENIS PEKERJAAN : BETON TUMBUK 1 : 3 : 5
SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Kerikil M3 0.8700 120,000.00 104,400.00
Pasir Pasang M3 0.5200 100,000.00 52,000.00
Semen Kg 218.0000 1,500.00 327,000.00
Sub Total A 483,400.00

B. UPAH
Tukang O/H 0.2500 75,000.00 18,750.00
Kepala Tukang O/H 0.0250 80,000.00 2,000.00
Pekerja O/H 1.6500 50,000.00 82,500.00
Mandor O/H 0.0800 60,000.00 4,800.00
Sub Total B 108,050.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 591,450.00

JENIS PEKERJAAN : COR BETON BERTULANG 1 : 2 : 3


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)
A. BAHAN
Kerikil M3 0.7530 120,000.00 90,360.00
Pasir Pasang M3 0.5710 100,000.00 57,100.00
Semen Kg 371.0000 1,500.00 556,500.00
Sub Total A 703,960.00

UPAH
Tukang O/H 0.2750 75,000.00 20,625.00
Kepala Tukang O/H 0.0280 80,000.00 2,240.00
Pekerja O/H 1.6500 50,000.00 82,500.00
Mandor O/H 0.0830 60,000.00 4,980.00
Sub Total B 110,345.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 814,305.00

41
JENIS PEKERJAAN : PEMBESIAN
SATUAN : Kg
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Besi beton Kg 1.0500 11,500.00 12,075.00
Kawat Beton Kg 0.0150 17,000.00 255.00
Sub Total A 12,330.00

B. UPAH
Tukang O/H 0.0070 75,000.00 525.00
Kepala Tukang O/H 0.0007 80,000.00 56.00
Pekerja O/H 0.0070 50,000.00 350.00
Mandor O/H 0.0003 60,000.00 18.00
Sub Total B 949.00

C. PERALATAN

Sub Total C -
D Jumlah Harga ( A + B + C ) 13,279.00

JENIS PEKERJAAN : CETAKAN BETON / BEKISTING


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Kayu Bekisting M3 0.0450 1,800,000.00 81,000.00
Paku campuran Kg 0.3000 19,000.00 5,700.00
Sub Total A 86,700.00

B. UPAH
Tukang O/H 0.2600 75,000.00 19,500.00
Kepala Tukang O/H 0.0260 80,000.00 2,080.00
Pekerja O/H 0.5200 50,000.00 26,000.00
Mandor O/H 0.0260 60,000.00 1,560.00
Sub Total B 49,140.00
C. PERALATAN
-
Sub Total C -
D Jumlah Harga ( A + B + C ) 135,840.00

JENIS PEKERJAAN : MEMBONGKAR & MENYIRAM BETON


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
Pekerja O/H 2.0000 50,000.00 100,000.00

Sub Total B 100,000.00


C. PERALATAN
-
Sub Total C -
D Jumlah Harga ( A + B + C ) 100,000.00

42
JENIS PEKERJAAN : Pek. Balok Sloof 15 / 20 Beton Btl. 1 : 2 : 3 ( Besi 200 Kg )
SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00


B. Pembesian Kg 200.0000 13,279.00 2,655,800.00
C. Cetakan Bekisting M² 5.8333 135,840.00 792,400.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 4,362,505.00

JENIS PEKERJAAN : Pek. Tiang Kolom 20 X 20 cm Beton Btl. 1 : 2 : 3 ( Besi 150 Kg )


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00


B. Pembesian Kg 150.0000 13,279.00 1,991,850.00
C. Cetakan Bekisting M² 10.0000 135,840.00 1,358,400.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 4,264,555.00

JENIS PEKERJAAN : Pek. Tiang Kolom Praktis Beton Bertulang Uk. 11 x 11 cm


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00


B. Pembesian Kg 356.9303 13,279.00 4,739,677.45
C. Cetakan Bekisting M² 9.0909 135,840.00 1,234,909.09
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 6,888,891.54
F. Jumlah Harga Kolom Praktis / M' ### x 0.0121 83,355.59

JENIS PEKERJAAN : Pek. Ring Balok Beton Beton Bertulang Uk. 10 x 15 cm


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00


B. Pembesian Kg 287.9774 13,279.00 3,824,051.89
C. Cetakan Bekisting M² 8.3333 135,840.00 1,132,000.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 5,870,356.89
F. Jumlah Harga Ring Balok / M' ### x 0.0121 71,031.32

JENIS PEKERJAAN : Pek. Pasangan Pondasi Tapak Beton Btl. 1 : 2 : 3 ( Besi 150 Kg )
SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00


B. Pembesian Kg 150.0000 13,279.00 1,991,850.00
C. Cetakan Bekisting M² 2.6667 135,840.00 362,240.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 3,268,395.00

43
JENIS PEKERJAAN : PAS. DINDING BATA 1/2 BT. SP. 1 : 3
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Batu Bata Bh 70.0000 700.00 49,000.00
2 Pasir Pasang M3 0.0400 100,000.00 4,000.00
3 Semen Kg 14.3700 1,500.00 21,555.00
Sub Total A 74,555.00

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.3000 50,000.00 15,000.00
4 Mandor O/H 0.0150 60,000.00 900.00
Sub Total B 24,200.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 98,755.00

JENIS PEKERJAAN : PAS. DINDING BATA 1/2 BT. SP. 1 : 4


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Batu Bata Bh 70.0000 700.00 49,000.00
2 Pasir Pasangan M3 0.0450 100,000.00 4,500.00
3 Semen Kg 9.6800 1,500.00 14,520.00
Sub Total A 68,020.00

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.3000 50,000.00 15,000.00
4 Mandor O/H 0.0150 60,000.00 900.00
Sub Total B 24,200.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 92,220.00

44
JENIS PEKERJAAN : PLESTERAN Sp. 1 : 3
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Pasir Pasangan M3 0.0310 100,000.00 3,100.00
2 Semen Kg 10.3680 1,500.00 15,552.00
Sub Total A 18,652.00

B. UPAH
1 Tukang O/H 0.2000 75,000.00 15,000.00
2 Kepala Tukang O/H 0.0200 80,000.00 1,600.00
3 Pekerja O/H 0.4000 50,000.00 20,000.00
4 Mandor O/H 0.0220 60,000.00 1,320.00
Sub Total B 37,920.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 56,572.00

JENIS PEKERJAAN : PLESTERAN Sp. 1 : 4


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Pasir Pasangan M3 0.0280 100,000.00 2,800.00
2 Semen Kg 7.2900 1,500.00 10,935.00
Sub Total A 13,735.00

B. UPAH
1 Tukang O/H 0.2000 75,000.00 15,000.00
2 Kepala Tukang O/H 0.0200 80,000.00 1,600.00
3 Pekerja O/H 0.2500 50,000.00 12,500.00
4 Mandor O/H 0.0250 60,000.00 1,500.00
Sub Total B 30,600.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 44,335.00

45
JENIS PEKERJAAN : PAS. BATU ALAM
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Batu alam M2 1.1000 150,000.00 165,000.00
2 Semen Portland Kg 9.3000 1,500.00 13,950.00
3 Pasir pasang M3 0.0180 100,000.00 1,800.00
Sub Total A 180,750.00

B. UPAH
1 Tukang O/H 0.1100 75,000.00 8,250.00
2 Kepala Tukang O/H 0.0110 80,000.00 880.00
3 Pekerja O/H 0.6600 50,000.00 33,000.00
4 Mandor O/H 0.0330 60,000.00 1,980.00
Sub Total B 44,110.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 224,860.00

JENIS PEKERJAAN : KUSEN PINTU KAYU KULIM


SATUAN : M3
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Kayu Kulim M3 1.2000 3,250,000.00 3,900,000.00
Lem Kayu Kg 1.0000 35,000.00 35,000.00
Paku Kg 1.2500 19,000.00 23,750.00
Sub Total A 3,958,750.00

B. UPAH
Tukang O/H 18.0000 75,000.00 1,350,000.00
Kepala Tukang O/H 1.8000 80,000.00 144,000.00
Pekerja O/H 6.0000 50,000.00 300,000.00
Mandor O/H 0.3000 60,000.00 18,000.00
Sub Total B 1,812,000.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 5,770,750.00
E. I Unit Kusen Ventilasi Silang = ### x 0.0075 43,280.63

46
JENIS PEKERJAAN : DAUN PINTU PANEL KAYU KULIM
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kulim M3 0.0400 3,250,000.00 130,000.00
Sub Total A 130,000.00

B. UPAH
1 Tukang O/H 2.5000 75,000.00 187,500.00
2 Kepala Tukang O/H 0.2500 80,000.00 20,000.00
3 Pekerja O/H 1.0000 50,000.00 50,000.00
4 Mandor O/H 0.0500 60,000.00 3,000.00
Sub Total B 260,500.00

C. ALAT

Sub Total C -
D. Jumlah Harga ( A + B + C ) 390,500.00

JENIS PEKERJAAN : PAS. BINGKAI DAUN JENDELA


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kulim M3 0.0240 3,250,000.00 78,000.00

Sub Total A 78,000.00

B. UPAH
1 Tukang O/H 2.4000 75,000.00 180,000.00
2 Kepala Tukang O/H 0.2400 80,000.00 19,200.00
3 Pekerja O/H 0.8000 50,000.00 40,000.00
4 Mandor O/H 0.0400 60,000.00 2,400.00
Sub Total B 241,600.00

C. ALAT

Sub Total C -
D. Jumlah Harga ( A + B + C ) 319,600.00

JENIS PEKERJAAN : PAS. JALUSI VENTILASI


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls. II M3 0.0240 2,500,000.00 60,000.00
2 Paku Campuran Kg 0.1500 19,000.00 2,850.00
Sub Total A 62,850.00

B. UPAH
1 Tukang O/H 1.8000 75,000.00 135,000.00
2 Kepala Tukang O/H 0.1800 80,000.00 14,400.00
3 Pekerja O/H 0.6000 50,000.00 30,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 181,200.00

C. ALAT

Sub Total C -
D. Jumlah Harga ( A + B + C ) 244,050.00

47
JENIS PEKERJAAN : PAS. KACA POLOS
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kaca 5 mm M3 1.1000 100,000.00 110,000.00
Sub Total A 110,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.00075 60,000.00 45.00
Sub Total B 13,245.00

C. ALAT

Sub Total C -
D. Jumlah Harga ( A + B + C ) 123,245.00

JENIS PEKERJAAN : PAS. ENGSEL PINTU LENGKAP 4"


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Engsel Pintu Lengkap 4" Bh 1.0000 18,000.00 18,000.00

Sub Total A 18,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 31,248.00

JENIS PEKERJAAN : PAS. ENGSEL JENDELA LENGKAP 3"


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Engsel Jendela Lengkap 3" Bh 1.0000 15,000.00 15,000.00

Sub Total A 15,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 28,248.00

48
JENIS PEKERJAAN : PAS. KUNCI TANAM 2 SLAAG
SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Kunci Tanam 2 Slaag Bh 1.0000 100,000.00 100,000.00

Sub Total A 100,000.00

B. UPAH
Tukang O/H 0.2250 75,000.00 16,875.00
Kepala Tukang O/H 0.0225 80,000.00 1,800.00
Pekerja O/H 0.0100 50,000.00 500.00
Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 19,475.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 119,475.00

JENIS PEKERJAAN : PAS. GRENDEL JENDELA


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Grendel Jendela Bh 1.0000 8,000.00 8,000.00

Sub Total A 8,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00

C. ALAT

Sub Total C -
D. Jumlah Harga ( A + B + C ) 21,248.00

JENIS PEKERJAAN : PAS. HAK ANGIN


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Hak Angin Bh 1.0000 7,500.00 7,500.00

Sub Total A 7,500.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 20,748.00

49
JENIS PEKERJAAN : PAS. TARIKAN JENDELA
SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Tarikan Jendela Bh 1.0000 5,000.00 5,000.00

Sub Total A 5,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 18,248.00

JENIS PEKERJAAN : MEMBUAT RANGKA ATAP BAJA RINGAN


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
Smar Truss C75.100 M 2.8510 10,000.00 28,510.00
Web C75.75 M 1.7290 10,000.00 17,290.00
Top Span 40 M 1.1220 2,000.00 2,244.00
ZA, G550 M 4.8890 3,500.00 17,111.50
Main Truss 1.05 TCT M 8.8650 2,000.00 17,730.00
Web 0,8 TCT M 12.2070 2,000.00 24,414.00
Ancor / Seng Pelapis Genteng Rol 0.0400 1,500.00 60.00

Sub Total A 107,359.50

B UPAH
Tukang O/H 0.8000 75,000.00 60,000.00
Kepala Tukang O/H 0.0800 80,000.00 6,400.00
Pekerja O/H 0.0800 50,000.00 4,000.00
Mandor O/H 0.1000 60,000.00 6,000.00
Sub Total B 76,400.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 183,759.50

50
JENIS PEKERJAAN : PAS. ATAP GENTENG METAL
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Atap Genteng Metal Lbr 1.2000 30,000.00 36,000.00
2 Paku Genteng Kg 0.0200 25,000.00 500.00
Sub Total A 36,500.00

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.2000 50,000.00 10,000.00
4 Mandor O/H 0.0010 60,000.00 60.00
Sub Total B 18,360.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 54,860.00

JENIS PEKERJAAN : PAS. BUBUNGAN GENTENG METAL


SATUAN : M'
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Bubungan Genteng Metal M' 1.1000 15,000.00 16,500.00

Sub Total A 16,500.00

B. UPAH
1 Tukang O/H 0.0700 75,000.00 5,250.00
2 Kepala Tukang O/H 0.0080 80,000.00 640.00
3 Pekerja O/H 0.1500 50,000.00 7,500.00
4 Mandor O/H 0.0060 60,000.00 360.00
Sub Total B 13,750.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 30,250.00

JENIS PEKERJAAN : RANGKA PLAFOND KAYU KLS. II


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls. II M3 0.0120 2,500,000.00 30,000.00
Paku Campuran Kg 0.1000 19,000.00 1,900.00
Sub Total A 31,900.00

B UPAH
1 Tukang O/H 0.2500 75,000.00 18,750.00
2 Kepala Tukang O/H 0.0250 80,000.00 2,000.00
3 Pekerja O/H 0.1500 50,000.00 7,500.00
4 Mandor O/H 0.0750 60,000.00 4,500.00
Sub Total B 32,750.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 64,650.00

51
JENIS PEKERJAAN : PLAFOND GRC
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 GRC Lbr 0.3640 65,000.00 23,660.00
2 Paku Sekrup Kg 0.1100 17,000.00 1,870.00
Sub Total A 25,530.00

B UPAH
1 Tukang O/H 0.0500 75,000.00 3,750.00
2 Kepala Tukang O/H 0.0050 80,000.00 400.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 9,450.00

C. ALAT

Sub Total C -
D. Jumlah Harga ( A + B + C ) 34,980.00

JENIS PEKERJAAN : LIST PROFIL SP. 3


SATUAN : M'
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 List Profil Sp. 3 M' 1.0500 8,000.00 8,400.00
2 Paku Campuran Kg 0.1000 19,000.00 1,900.00
Sub Total A 10,300.00

B UPAH
1 Tukang O/H 0.0500 75,000.00 3,750.00
2 Kepala Tukang O/H 0.0050 80,000.00 400.00
3 Pekerja O/H 0.0500 50,000.00 2,500.00
4 Mandor O/H 0.0030 60,000.00 180.00
Sub Total B 6,830.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 17,130.00

JENIS PEKERJAAN : PAS. LIST PLANK PAPAN


SATUAN : M'
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kelas II M3 0.0160 2,500,000.00 40,000.00
2 Paku Campuran Kg 0.0500 19,000.00 950.00
Sub Total A 40,950.00

B. UPAH
1 Tukang O/H 0.2000 75,000.00 15,000.00
2 Kepala Tukang O/H 0.0200 80,000.00 1,600.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 21,900.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 62,850.00

52
JENIS PEKERJAAN : MEMASANG KERAMIK LANTAI 20 x 20 CM
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Keramik Lantai 20 x 20 M2 1.0000 50,000.00 50,000.00
2 Semen Kg 11.3800 1,500.00 17,070.00
3 Pasir Pasang M3 0.0420 100,000.00 4,200.00
4 Semen Warna Kg 1.5000 3,500.00 5,250.00
Sub Total A 76,520.00

B. UPAH
1 Tukang O/H 0.3500 75,000.00 26,250.00
2 Kepala Tukang O/H 0.0350 80,000.00 2,800.00
3 Pekerja O/H 0.6200 50,000.00 31,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 61,850.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 138,370.00

JENIS PEKERJAAN : MEMASANG KERAMIK DINDING 20 x 20 CM


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Keramik Dinding 20 x 20 M2 1.0000 50,000.00 50,000.00
2 Semen Kg 9.3000 1,500.00 13,950.00
3 Pasir Pasang M3 0.0180 100,000.00 1,800.00
4 Semen Warna Kg 1.5000 3,500.00 5,250.00
Sub Total A 71,000.00

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0450 80,000.00 3,600.00
3 Pekerja O/H 0.6000 50,000.00 30,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 42,900.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 113,900.00

53
JENIS PEKERJAAN : MEMASANG LANTAI KERAMIK 30 x 30 CM
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Keramik Lantai 30 x 30 M2 1.0000 55,000.00 55,000.00
2 Semen Kg 9.3000 1,500.00 13,950.00
3 Pasir Pasang M3 0.0180 100,000.00 1,800.00
4 Semen Warna Kg 1.5000 3,500.00 5,250.00
Sub Total A 76,000.00

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0450 80,000.00 3,600.00
3 Pekerja O/H 0.6000 50,000.00 30,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 42,900.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 118,900.00

JENIS PEKERJAAN : PAS. MATA KRAN AIR


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Mata Kran 1/2" Bh 1.0000 35,000.00 35,000.00
2 Seal Tape Bh 0.0250 2,500.00 62.50
Sub Total A 35,062.50

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.0100 50,000.00 500.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 9,100.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 44,162.50

JENIS PEKERJAAN : PAS. FLOOR DRAIN


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Floor Drain Besi Bh 1.0000 15,000.00 15,000.00

Sub Total A 15,000.00

B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.0100 50,000.00 500.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 9,100.00

C. PERALATAN

Sub Total C -

54
D. Jumlah Harga ( A + B + C ) 24,100.00

55
JENIS PEKERJAAN : PAS. KLOSET JONGKOK
SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kloset Jongkok Bh 1.0000 175,000.00 175,000.00
2 Semen Kg 6.0000 1,500.00 9,000.00
3 Pasir Pasang M3 0.0100 100,000.00 1,000.00
Sub Total A 185,000.00

B. UPAH
1 Tukang O/H 1.5000 75,000.00 112,500.00
2 Kepala Tukang O/H 0.1500 80,000.00 12,000.00
3 Pekerja O/H 1.0000 50,000.00 50,000.00
4 Mandor O/H 0.1600 60,000.00 9,600.00
Sub Total B 184,100.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 369,100.00

JENIS PEKERJAAN : PAS. BAK AIR FIBBER


SATUAN : Unit
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Bak Air Fibber Unit 1.0000 275,000.00 275,000.00
2 Perlengkapan (18% x Harga Fibbe Ls 0.1800 275,000.00 49,500.00
Sub Total A 324,500.00

B. UPAH
1 Tukang O/H 2.7000 75,000.00 202,500.00
2 Kepala Tukang O/H 0.5400 80,000.00 43,200.00
3 Pekerja O/H 1.8000 50,000.00 90,000.00
4 Mandor O/H 0.1100 60,000.00 6,600.00
Sub Total B 342,300.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 666,800.00

JENIS PEKERJAAN : SEPTICTANK + PERESAPAN


SATUAN : UNIT
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

1 Pek. Galian Tanah M3 2.7500 22,400.00 61,600.00


2 Pek. Urugan Pasir Alas M3 0.1500 111,600.00 16,740.00
3 Ijuk M2 3.6000 25,000.00 90,000.00
4 Batu Karang M3 0.9000 160,000.00 144,000.00
5 Pas. Batu Bata 1/2 ad. 1:3 M2 5.5000 98,755.00 543,152.50
6 Pas. Plester ad. 1:3 M2 6.6000 56,572.00 373,375.20
7 Cor Beton Bertulang 1 : 2 : 3 M3 0.1080 814,305.00 87,944.94
8 Cor Beton ad. 1:3:5 M3 0.2100 591,450.00 124,204.50
9 Pipa PVC 4" + Accessories M' 4.0000 35,000.00 140,000.00
10 Pipa Penguapan Galv. 2 " M' 0.2500 40,000.00 10,000.00

Jumlah Harga 1,591,017.14

56
JENIS PEKERJAAN : MEMASANG INSTALASI LISTRIK
SATUAN : TTK
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Kawat NYYM 2 x 2.5 mm M' 6.0000 7,500.00 45,000.00
2 Klem PVC 1/2" Lot 0.5000 4,000.00 2,000.00
3 T.Dos PVC Bh 4.0000 3,000.00 12,000.00
4 Bok PVC Bh 2.0000 3,000.00 6,000.00
5 Isolatip Bh 2.0000 4,000.00 8,000.00

Sub Total A 73,000.00

B. UPAH
1 Tukang O/H 0.7500 75,000.00 56,250.00
2 Kepala Tukang O/H 0.0750 80,000.00 6,000.00
3 Pekerja O/H 0.4000 50,000.00 20,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 82,250.00
C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 155,250.00

JENIS PEKERJAAN : MEMASANG SAKLAR GANDA


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Saklar Ganda Bh 1.0000 20,000.00 20,000.00

Sub Total A 20,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 17,450.00
C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 37,450.00

JENIS PEKERJAAN : MEMASANG SAKLAR TUNGGAL


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Saklar Tunggal Bh 1.0000 15,000.00 15,000.00

Sub Total A 15,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 17,450.00
C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 32,450.00

57
JENIS PEKERJAAN : MEMASANG MCB
SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 MCB Unit 1.0000 60,000.00 60,000.00

Sub Total A 60,000.00

B. UPAH
1 Tukang O/H 0.3750 75,000.00 28,125.00
2 Kepala Tukang O/H 0.0375 80,000.00 3,000.00
3 Pekerja O/H 0.2500 50,000.00 12,500.00
4 Mandor O/H - 60,000.00 -
Sub Total B 43,625.00
C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 103,625.00

JENIS PEKERJAAN : MEMASANG STOP KONTAK


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Stop Kontak Bh 1.0000 20,000.00 20,000.00

Sub Total A 20,000.00

B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 17,450.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 37,450.00

JENIS PEKERJAAN : MEMASANG LAMPU XL 20 WATT


SATUAN : Bh
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)

A. BAHAN
1 Lampu XL 20 Watt Bh 1.0000 45,000.00 45,000.00

Sub Total A 45,000.00

B. UPAH
1 Tukang O/H
2 Kepala Tukang O/H
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H 0.0100 60,000.00 600.00
Sub Total B 5,600.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 50,600.00

58
JENIS PEKERJAAN : PENGECATAN DINDING & PLAFOND
SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)
A. BAHAN
Plamir Dinding Kg 0.1000 12,000.00 1,200.00
Cat Dasar Kg 0.1000 12,500.00 1,250.00
Cat Penutup 2x Kg 0.2600 20,000.00 5,200.00
Sub Total A 7,650.00
B. Upah
Tukang O/H 0.0630 75,000.00 4,725.00
Kepala Tukang O/H 0.0060 80,000.00 480.00
Pekerja O/H 0.0200 50,000.00 1,000.00
Mandor O/H 0.0020 60,000.00 120.00
Sub Total B 6,325.00

C. PERALATAN

Sub Total C -
D. Jumlah Harga ( A + B + C ) 13,975.00

JENIS PEKERJAAN : MENGECAT KAYU + PLAMIR


SATUAN : M2
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN SATUAN KUANTITAS
(Rp.) (Rp.)
A. BAHAN
Plamir kayu Kg 0.1500 17,500.00 2,625.00
Cat Dasar Kg 0.2600 45,000.00 11,700.00
Cat Mengkilap Kg 0.1700 50,000.00 8,500.00
Menie Kg 0.2000 50,000.00 10,000.00
Sub Total A 32,825.00
B. UPAH
Tukang O/H 0.0090 75,000.00 675.00
Kepala Tukang O/H 0.0060 80,000.00 480.00
Pekerja O/H 0.0700 50,000.00 3,500.00
Mandor O/H 0.0030 60,000.00 180.00
Sub Total B 4,835.00

C. PERALATAN

Sub Total C -
Jumlah Harga ( A + B + C ) 37,660.00

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur

59
DAFTAR HARGA SATUAN BAHAN

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

HARGA SATUAN
NO. U R A I A N SATUAN
(Rp.)

1. Kayu Kulim M3 3,250,000.00


2. Kayu Kls. II M3 2,500,000.00
3. Kayu Kls. III M3 1,800,000.00
4. Batu Bata Bh 700.00
5. Batu Alam M2 150,000.00
6. Kerikil M3 120,000.00
7. Pasir Pasang M3 100,000.00
8. Pasir Urug M3 80,000.00
9. Tanah Timbunan M3 80,000.00
10. Semen Kg 1,500.00
11. Semen Warna Kg 3,500.00
12. Lem Kayu Kg 35,000.00
13. Keramik Lantai 20 x 20 Cm M2 50,000.00
14. Keramik Dinding 20 x 20 Cm M2 50,000.00
15. Keramik Lantai 30 x 30 Cm M2 55,000.00
16. Besi Beton Polos Kg 11,500.00
17. Kawat Beton Kg 17,000.00
18. Smar Truss C75.100 M 10,000.00
19. Web C75.75 M 10,000.00
20. Top Span 40 M 2,000.00
21. ZA, G550 M 3,500.00
22. Main Truss 1.05 TCT M 2,000.00
23. Web 0,8 TCT M 2,000.00
24. Ancor / Seng Pelapis Genteng Rol 1,500.00
25. Genteng Metal M2 30,000.00
26. Bubungan Genteng Metal M' 15,000.00
27. Baut Scrup Kg 17,000.00
28. GRC Lbr 65,000.00
29. List Profil Sp. 3 M' 8,000.00
30. Kaca 5 mm (Bening) M2 100,000.00
31. Paku Campuran Kg 19,000.00
32. Paku Ulir Kg 25,000.00
33. Plamir Tembok Kg 12,000.00
HARGA SATUAN
NO. U R A I A N SATUAN
(Rp.)

34. Kunci Tanam 2 Levers Bh 100,000.00


35. Engsel Pintu 4 Inchi Bh 18,000.00
36. Engsel Jendela 3 Inchi Bh 15,000.00
37. Grendel Jendela Bh 8,000.00
38. Hak Angin Bh 7,500.00
39. Tarikan Jendela Bh 5,000.00
40. Pipa PVC Dia. 4" M' 35,000.00
41. Pipa Galvanis 2" M' 40,000.00
42. Mata Kran Air 1/2" Bh 35,000.00
43. Seal Tape Bh 2,500.00
44. Fluor drain (Avour) Bh 15,000.00
45. Kloset Jongkok Bh 175,000.00
46. Bak Air Fibber Unit 275,000.00
47. Ijuk M2 25,000.00
48. Batu Karang M3 160,000.00
49. Cat tembok Penutup Kg 20,000.00
50. Cat Dasar Tembok Kg 12,500.00
51. Plamur Kayu Kg 17,500.00
52. Cat Dasar Minyak Kg 45,000.00
53. Cat Kayu Kg 50,000.00
54. Saklar Ganda Bh 20,000.00
55. Saklar Tunggal Bh 15,000.00
56. MCB Unit 60,000.00
57. Stop Kontak Bh 20,000.00
58. Lampu XL 20 Watt Bh 45,000.00
59. Kawat NYYM 2 x 2.5 mm M' 7,500.00
60. Klem PVC 1/2" Lot 4,000.00
61. T.Dos PVC Bh 3,000.00
62. Bok PVC Bh 3,000.00
63. Isolatip Bh 4,000.00

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur
DAFTAR HARGA SATUAN UPAH

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

HARGA
NO. U R A I A N SATUAN
(Rp.)

1. Tukang Hari 75,000.00

2. Kepala Tukang Hari 80,000.00

3. Pekerja Hari 50,000.00

4. Mandor Hari 60,000.00

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur
DAFTAR HARGA SATUAN PERALATAN

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

HARGA
NO. U R A I A N SATUAN
(Rp.)

1 Dump Truck Hari 500,000.00

2 Mesin Air Hari 150,000.00

3 Waterpass Hari 200,000.00

4 Concrete Mixer/Concrete Vibrator Hari 250,000.00

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur
ASLI

DOKUMEN PENAWARAN

PEKERJAAN
PEMBANGUNAN BALAI NIKAH 2 (DUA) UNIT
KANTOR KEMENTRIAN AGAMA KABUPATEN BONE BOLANGO

LOKASI
KABUPATEN BONE BOLANGO

TAHUN ANGGARAN 2011


DOKUMEN KUALIFIKASI

#REF! #REF!

#REF! #REF!

#REF! #REF!

LOKASI 0

0 0
ASLI

KUMEN PENAWARAN

PEKERJAAN
BANGUNAN BALAI NIKAH 2 (DUA) UNIT
MENTRIAN AGAMA KABUPATEN BONE BOLANGO

LOKASI
KABUPATEN BONE BOLANGO

TAHUN ANGGARAN 2011


KUMEN KUALIFIKASI

0
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA & VENTILASI
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS
PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANG
LOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARA
SUMBER DANA : DAK/DAU
TAHUN ANGGARAN : 2009

HARGA SATUAN
NO TYPE PINTU & JENDELA VOLUME SAT (Rp)

1 pj1
Bahan + upah
- Kusen 18.7000 m1 #REF!
- Bingkai 23.9000 m1 #REF!
- Kaca 3.8880 M2 #REF!
- Pintu 3.6800 M2 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

1 pj2
Bahan + upah
- Kusen 20.1600 m1 #REF!
- Bingkai 19.8200 m1 #REF!
- Kaca 2.4960 M2 #REF!
- Pintu 2.0700 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

2 pj3
Bahan + upah
- Kusen 16.4200 m1 #REF!
- Bingkai 6.7000 m1 #REF!
- Kaca 2.3540 M2 #REF!
- Pintu 2.0700 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

3 p3
Bahan + upah
- Kusen m1 #REF!
- Bingkai m1 #REF!
- Kaca M2 #REF!
- 1,500.00
- #REF!
- #REF!
4 p1
Bahan + upah
- Kusen 11.3000 m1 #REF!
- Bingkai m1 #REF!
- Kaca 0.3900 M2 #REF!
- Pintu 3.6800 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
5 p2
Bahan + upah
- Kusen 8.7000 m1 #REF!
- Bingkai m1 #REF!
- Kaca 0.1976 M2 #REF!
- Pintu 2.0700 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =

6 j1
Bahan + upah
- Kusen 15.2800 m1 #REF!
- Bingkai 16.9200 m1 #REF!
- Kaca 1.8492 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
7 j2
Bahan + upah
- Kusen 10.8600 m1 #REF!
- Bingkai 11.2800 m1 #REF!
- Kaca 1.2328 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
7 j3
Bahan + upah
- Kusen 6.3400 m1 #REF!
- Bingkai 5.6400 m1 #REF!
- Kaca 0.6164 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
7 v1
Bahan + upah
- Kusen 2.1200 m1 #REF!
- Bingkai m1 #REF!
- Kaca 0.2500 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =

xxxxxxxxxxx, 29 Juli 2013

0 #REF!
0
0 xxxxxxxxxxxxx
#REF! Pimpinan Teknik
NDELA & VENTILASI

JUMLAH
(Rp)

#REF!
#REF!
#REF!
5,520.00
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
3,105.00
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
3,105.00
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
5,520.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
3,105.00
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

xxxxxxxxxxx, 29 Juli 2013

#REF!
xxxxxxxxxxxxx
Pimpinan Teknik
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA & VENTILASI
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS
PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANG
LOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARA
SUMBER DANA : DAK/DAU
TAHUN ANGGARAN : 2009

HARGA SATUAN
NO TYPE PINTU & JENDELA VOLUME SAT (Rp)

1 pj1
Bahan + upah
- Kusen 18.7000 m1 #REF!
- Bingkai 23.9000 m1 #REF!
- Kaca 3.8880 M2 #REF!
- Pintu 3.6800 M2 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

1 pj2
Bahan + upah
- Kusen 11.3000 m1 #REF!
- Bingkai 4.7000 m1 #REF!
- Kaca 0.3276 M2 #REF!
- Pintu 3.6800 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

2 pj3
Bahan + upah
- Kusen 19.6600 m1 #REF!
- Bingkai 11.9000 m1 #REF!
- Kaca 1.9220 M2 #REF!
- Pintu 4.6575 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

3 p3
Bahan + upah
- Kusen m1 #REF!
- Bingkai m1 #REF!
- Kaca M2 #REF!
- 1,500.00
- #REF!
- #REF!
4 p1
Bahan + upah
- Kusen m1 #REF!
- Bingkai m1 #REF!
- Kaca M2 #REF!
- Pintu 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
5 p2
Bahan + upah
- Kusen m1 #REF!
- Bingkai m1 #REF!
- Kaca M2 #REF!
- Pintu 1,500.00
- #REF!
- #REF!
Jumlah harga sat. bahan + upah =

6 j1
Bahan + upah
- Kusen 15.2800 m1 #REF!
- Bingkai 16.9200 m1 #REF!
- Kaca 1.8492 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
7 j2
Bahan + upah
- Kusen 10.8600 m1 #REF!
- Bingkai 11.2800 m1 #REF!
- Kaca 1.2328 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
7 j3
Bahan + upah
- Kusen 6.3400 m1 #REF!
- Bingkai 5.6400 m1 #REF!
- Kaca 0.6164 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =
7 v1
Bahan + upah
- Kusen 2.1200 m1 #REF!
- Bingkai m1 #REF!
- Kaca 0.2500 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =

7 v2
Bahan + upah
- Kusen 4.2000 m1 #REF!
- Bingkai 4.0000 m1 #REF!
- Kaca 0.2392 M2 #REF!
- 1,500.00
- #REF!
- - #REF!
Jumlah harga sat. bahan + upah =

xxxxxxxxxxx, 29 Juli 2013

0 #REF!
0

0 xxxxxxxxxxxxx
#REF! Pimpinan Teknik
NDELA & VENTILASI

JUMLAH
(Rp)

#REF!
#REF!
#REF!
5,520.00
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
5,520.00
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
6,986.25
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!

xxxxxxxxxxx, 29 Juli 2013

#REF!

xxxxxxxxxxxxx
Pimpinan Teknik
SPESIFIKASI TEKNIS
### #REF!
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx

Spesifikasi Terknis ditetapkan dalam dokumen pelalangan berdasarkan jenis pekerjaan yang akan
dilelangkan, dengan ketentuan :
1. Tidak mengarah kepada merk/produk tertentu, tidak menutup kemungkinan digunakannya
produksi dalam negeri;
2. Semaksimal mungkin diupayakan menggunakan standar nasional (SNI);
3. Metode Pelaksanaan harus logis, realistik dan dapat dilaksanakan;
4. Jadwal waktu pelaksanaan harus sesuai dengan metoda pelaksanaan;
5. Mencantumkan macam, jenis, kapasitas dan jumlah peralatan utama minimal yang
diperlukan dalam pelaksanaan pekerjaan;
6. Mencantumkan syarat-syarat bahan yang dipergunakan dalam pelaksanaan pekerjaan;
7. Mencantumkan syarat-syarat pengujian bahan dan hasil produk;
8. Mencantumkan kriteria kinerja produk yang diinginkan;
9. Mencantumkan tatacara pengukuran dan tata cara pemabayaran;
10. Spesifikasi Teknis Bahan Bangunan Konstruksi :
a. Mengidentifikasi setiap jenis bahan bangunan konstruksi yang akan digunakan untuk
pekerjaan permanen maupun untuk pekerjaan sementara atau penunjang, dan
menetapkan spesifikasi teknis setiap jenis bahan yang boleh digunakan;
b. Setiap bahan bangunan konstruksi yang digunakan sedaspat mungkin dipilih yang paling
kecil bahay dan resikonya, dan diberi penjelasan cara penggunaan yang benar dan
selamat;
c. Memberi penjelasan atas bahan bangunan yang berbahaya atau beracun dan
menjelaskan cara pengangkutan dan pembuangan limbahnya sesuai dengan prosedur
perundang-undangan yang berlaku;
d. Informasi tentang bahan bangunan dan beracun yang diterbitkan oleh pabrik
pembuatnya atau dari sumber-sumber yang berkompeten.
11. Spesifikasi Teknis Peralatan Konstruksi dan Peralatan Bangunan;
a. Mengindentifikasi bahaya setiap jenis alat yang digunakan;
b. Memilih setiap jenis alat yang paling kecil bahaya dan resikonya serta lebih mudah
penggunaan dan perawatnnya dan memberi penjelasan singkat cara penggunaan dan
perawatnnya.
c. Memastikan setiap jenis alat yang digunakan telah diberi perlindungan atau kelengkapan
pengaman untuk mencegah bahaya secara langsung terhadap tubuh pekerja;

12. Spesifikasi Teknis Proses / Kegiatan


a. Mengidentifikasi setiap bahay dari jenis proses ataua tahapan kegiatan pekerjaan
konstruksi
b. Setiap jenis proses/kegiatan sedapat mungkin dipilih yang paling kecil bahay dan
resikonya
c. Melengkapi dengan prosedur kerja, sistem perlindungan terhadap pekerja, perlengkapan
pengaman dan rambu-rambu peringatan dan kewajiban pekerja.
13. Spesifikasi Teknis Metode Konstruksi/Metode Pelaksanaan/Metode Kerja
a. Identifikasi bahaya harus dilakukan terhadap setiap metode konstruksi/metode
pelaksanaan pekerjaan, dan persyaratan teknis yang ditetapkan
b. Melaksanakan pekerjaan dengan menggunakan peralatan, material dan konstruksi
semnetara sesuai dengan kondisi lokasi/tanah/cuaca dan dapat dikerjakan oleh pekerja
dan operator terlatih

14. Spesifikasi Jabatan Kerja Konstruksi


a. Penetapan Spesifikasi teknis serta metode pelaksanaan/konstruksi/kerja harus dilakukan
oleh tenaga ahli yang mempunyai kompetensi yang dipersyaratkan.
b. Memastikan bahwa semua potensi bahaya dan resiko yang terkait pada bentuk
rancangan, spesifikasi teknis dan metode kerja/konstruksi.

LINGKUP PEKERJAAN
A. PEKERJAAN PERSIAPAN
Sebelum memulai pelaksanaan pekerjaan lokasi harus dibersihkan dari sisa-sisa bangunan,
rumput, semak, akar, pohon, tanah humus dan segala sesuatu yang tidak diperlukan

Mengadakan pengukuran kembali dengan teliti dengan disaksikan oleh pengawas lapangan
untyuk mengetahui batas-batas, ketinggian bangunan dengan menggunakan alat ukur

Mengadakan sumber air bersih untuk keperluan pelaksanaan pekerjaan


Membuat Direksi Keet atau barak kerja yang dilengkapi dengan fasilitas untuk direksi dan
tamu-tamu antara lain :
- Meja / Kursi Kerja
- Lemari Arsip
- Meja Rapat
- Kursi Rapat
- Papan White Board
- Dispenser
- KM/WC sementara
- Komputer dan Printer
Memperhitungkan biaya dokumentasi berupa foto-foto yang diambil secara berkala dari
seluruh pelaksanaan pekerjaan
Menyediakan obat-obatan untuk pertolongan pertama pada kecelakaan.
Memperhitunkan biaya untuk keamanan.

B PEKERJAAN KONSTRUKSI
Pekerjaan Galian Tanah
Mengupas seluruh daerah yang akan terletak di bawah lantai bangunan dari lapisan
humusnya. Hasil kupasan dibuang ketempat yang akan jauh dari lokasi pekerjaan agar tidak
mengganggu kelancaran pekerjaan.
Mengukur Elevasi permukaan tanah asli dibeberapa tempat sesuai petunjuk direksi
Galian harus mencapai kedalaman dan lubang galian harus cukup lebar sehingga waktu
mengerjakan pasangan atau pengecoran tidak akan terganggu dan dasar lubang pondasi
rata.
Menyingkirkan dan membuang hasil galian yang tidak dipergunanakan sebagai urugan tanah
kemabli agar tidak terjadi penumpukan tanah disekitar lokasi
Jika terdapat genangan air dalam galian maka air tersebut harus dipompa keluar dengan
menggunakan Pompa Air.
d. Jika terdapat tempat yang gembur pada dasar galian, maka harus digali dan ditimbun
kembali dengan pasir urug kemudian disiram air dan dipadatkan.
Pekerjaan Urugan Tanah Kembali Bekas Galian
Tanah bekas galian setelah dibersihkan dari kotoran-kotoran dan apabila dipandang cukup
baik dapat dipergunakan untuk menimbun kembali pondasi dan membuang tanah hasil
galian yang tidak dapat dipergunakan keluar dari lokasi pekerjaan.

Pekerjaan Urugan Pasir Dibawah Lantai dan Pondasi


Urugan pasir harus dilaksanakan di bawah lantai pada bangunan minimal setebal 10 cm
padat dan di bawah rabat minimal setebal 10 cm.
Lapisan pasir urug harus ditimbun / dipadatkan dengan diairi sebelum lantai ubin atau
pondasi dipasang, pasir urug harus bersih dari akar-akar dan kotoran lain.

Pekerjaan Urugan Tanah


Urugan tanah dilaksanakan lapis demi lapis, dan harus ditumbuk serta diairi sampai padat
sebelum lapisan berikutnya dikerjakan.

Pekerjaan Timbrisan Batu Kali / Belah


Batu kali yang digunakan harus batu yang keras dan baik.
Pasir urug untuk lapisan dasar pondasi harus memenuhi ketentuan

Pekerjaan Pasangan Batu Kali / Belah


Pekerjaan pasangan batu harus didasarkan sesuai ukuran minimal pada gambar kerja.
Pasangan batu kali/batu belah dilaksanakan dengan campuran 1 pc : 4 pasir
Batu kali/batu belah yang dipakai adalah jenis keras, batu karang tidak boleh dipakai.
Pasir Pasang untuk adukan harus terdiri dari butir-butir yang bersih dari segala kotoran
Semen yang digunakan adalah Portland Cemen (PC) produk dalam negeri yang memnuhi
persyaratan

Pekerjaan Beton Bertulang, pembesian dan bekisting


Semua tahapan pembuatan beton harus mengikuti standar dan memenuhi persyaratan yang
berlaku di Indonesia dengan perbandingan 1Semen : 2 Pasir : 3 Kerikil
Pekerjaan pengecoran beton harus dilakukan sekaligus dan harus dihindarkan adanya
penghentian pengecoran dan segera setelah adukan dituangkan ke dalam bekisting, adukan
harus dipadatkan
Kubus beton yang dipakai selama pengecoran harus diuji kekuatan tekan karakteristiknya
dilaboratorium yang dapat disetujui Direksi dan hasilnya dilaporkan secara tertulis kepada
Direksi untuk dievaluasi. Apabila hasil pemeriksaan menunjukkan bahwa mutu beton kurang
dari nilai yang disyaratkan, pemborong harus mengambil core sample dari bagian – bagian
Konstruksi yang diragukan. Jumlah core sample untuk tiap pemeriksaan adalah tiga buah,
dan selanjutnya akan diperiksa di laboratorium dengan persetujuan Direksi. Hasilnya akan
dievaluasi Direksi dan bila nilai yang diperoleh membahayakan konstruksi, harus dilakukan
perbaikan konstruksi tersebut atas biaya pemborong.

Semen yang digunakan adalah Portland Cemen (PC) produk dalam negeri yang memnuhi
persyaratn
Pasir Pasang untuk adukan harus terdiri dari butir-butir yang bersih dari segala kotoran
Kerikil harus kuat, padat tahan lama dan bersih dari segala bentuk kotoran yang dapat
menurunkan mutu beton
Air harus bersih dan tidak boleh mengandung endapan lumpur, minyak dan garam, asam,

Menggunakan alat pengaduk yang disetujui direksi


Menganyam besi beton sesuai dengan dimensi dan ukuran yang ditentukan dalam gambar.
Semua pembengkokan tulangan harus dilakukan sebelum penyetelan/penempatan dan
diperkenankan membengkokkan tulangan bila sudah ditempatkan kecuali apabila hal itu
terpaksa dan sudah mendapat persetujuan direksi.
Tulangan harus ditempatkan secara teliti pada poisi sesuai rencan dan harus dijaga jarak
antara tulangan dengan bekisting untuk mendapatkan tebal selimut beton minimal sesuai
dengan gambar rencana. Sebelum melakukan pengecoran, semua tulangan harus terlebih
dahulu diperiksa untuk memastikan ketelitian penempatannya, kebersihannya, dan untuk
mendapatkan perbaikan bila diperlukan. Tulangan yang berkarat harus segera dibersihakan
atau diganti bilamana dianggap dapat melemahkan konstruksi. Pengecoran tidak dapat
dilakukan apabila belum mendapatkan persetujuan direksi.

Membuat cetakan (bekisting) dari bahan yang bagus yang mempunyai permukaan yang rata
dan kedap air.
Untuk mendapatkan bentuk penampang dan ukuran dari beton seperti dalam gambar kerja
(konstruksi), maka bekisting harus dikerjakan dengan baik, lurus, rata, teliti dan kokoh.

Pekerjaan bekisting harus sedemikian rupa sehingga hubungan-hubungan antara papan


bekisting terjamin rapat dan adukan tidak akan merembes keluar.
Melindungi beton selama proses pengeringan dari cuaca dengan cara menyiram, menutup
dengan karung, atau dengan cara lain yang dibenarkan

Pembongkaran bekisting beton tidak boleh dilakukan sebelum waktu pengerasan menurut
PBI 1991 dipenuhi dan pembongkarannya dilakukan hati-hati dan tidak merusak beton yang
sudah mengeras.

Pekerjaan Beton Tidak Bertulang


Beton Tidak bertulang dengan campuran 1 semen : 3 pasir : 5 kerikil, dilaksanakan untuk
pekerjaan lain-lain dimana dianggap perlu menurut syarat-syarat pelaksanaan yang baik dan
sempurna

Pekerjaan Pasangan Dinding Batu Bata


Sebelum dipasang batu bata harus direndam lebih dahulu dengan air. Dalam hari yang sama
setelah pemasangan batu bata selesai dikerjakan, siar – siar dikeruk sedalam 1 cm agar
plesteran dapat melekat dengan baik.
Sebelum melakukan pekerjaan pasangan dinding, harus dipastikan bahwa pekerjaan pondasi
telah benar-benar selesai dan balok sloof telah mencapai umur kering dan kekuatan yang
diharpkan, dan semua tembok harus dipasang tegak lurus dan rata,
Pada bagian + 1,00 m dari permukaan balok sloof digunakan campuran spesi pengikat
dengan perbandingan 1 pc : 3 pasir untuk lapisan kedap air atau dikenal dengan lapisan
transram
Perbandingan campuran pada kegiatan adalah campran 1 semen : 3 pasir (trasram) dan
campuran 1 semen : 5 pasir.

Pekerjaan Plesteran dan Acian


Semua permukaan dinding sebelah luar dan dalam harus diplester dengan adukan yang
sesuai dengan perekat yang dipergunakan oleh pasangan dinding.
Pada pasangan batu bata, sebelum diplester bidang tembok harus dibasahi dahulu sampai
jenuh. Begitu selesai memasang batu bata siar – siar dikeruk sedalam 1 cm untuk tujuan
supaya plesteran dapat lebih kokoh menempel pada pasangan bata. Permukaan beton yang
akan di plester sebelumnya harus diberap dahulu dengan air semen, kemudian dilakukan
pemelesteran.

Tebal plesteran tembok bata diambil maksimum 2 cm dengan perbandingan 1 semen : 3


pasir dan 1 semen : 5 pasir. Plesteran tembok boleh dilakukan apabila selesai dengan
pemasangan pipa – pipa saluran air dan listrik, Pembobokan plesteran untuk instalasi
Pekerjaan Pintu dan Jendela Aluminium
Pekerjaan ini meliputi pengadaan tenaga kerja, bahan-bahan dan peralatan yang
dipergunakan untuk melaksanakan pekerjaan pembuatan dan pemasangan Kusen Pintu dan
Jendela Aluminium pada seluruh bangunan seperti yang ditunjukkan dalam gambar dan
berdasarkan spesifikasi yang ada.

Pekerjaan Atap
Rangka atap menggunakan kuda-kuda kayu kelas II dengan dimensi dan ukuran sesuai
dengan gambar kerja/bestek dengan memperhatikan sambungan ataupun pertemuan kayu
yang lain dengan kayu lainnya.
Penutup atap dipsersyaratkan menggunakan bahan aluminium gelombang dan bubungan
aluminium.
Kemiringan atap dibuat sedemikian sehingga air hujan yang jatuh dapat segera mengalir
turun tanpa terjadi rembesan di sela-sela sambungan atau susunan penutup atap.

Pekerjaan Plafond
Rangka plafond menggunakan kuda-kuda kayu kelas II dengan dimensi dan ukuran sesuai
dengan gambar kerja/bestek dengan memperhatikan sambungan ataupun pertemuan kayu
yang lain dengan kayu lainnya.
Dipergunakan triplex tebal minimum 3 mm, ukuran sesuai gambar rencana untuk semua
ruangan dalam/luar gedung, bagian lain disesuaikan dan langit-langit dari triplex dipasang
tepat waterpass.
List plafond kayu profil Sp.4 di pasang pada bagian pertemuan antara plafond dengan
dinding dicat minyak, warna akan ditentukan kemudian oleh pemberi tugas.

Pekerjaan Lantai
Sebelum memulai pekerjaan, harus dipastikan bahwa permukaan timbunan telah benar-
benar padat dan kuat serta siap untuk dikerjakan.
Lantai dicor dengan campuran cor beton 1 pc : 3 pasir : 5 kerikil dengan ketebalan sesuai
dengan gambar kerja/bestek.
Pekerjaan lantai ruangan-ruangan (selain kamar mandi) menggunakan bahan keramik
ukuran 30 x 30 cm dan plint keramik 10 x 30
Lantai toilet (kamar mandi / wc) dengan kemiringan cukup + 5 % kearah lubang
pembuangan (floor drain). Siar-siar harus membentuk satu garis lurus dan diisi dengan
semen kental sampai penuh, kemudian dibersihkan sampai noda-nodanya hilang.
Keramik lantai toilet (km / wc) ukuran 20 x 20 cm (anti slip) dan Keramik ukuran 20 x 25 cm
dipergunakan untuk pelapis dinding km / wc (toilet) setinggi 1,50 cm, dan tempat-tempat
lainnya sesuai gambar bestek/detail.
Semua keramik yang digunakan berkualitas KW. 1 mempunyai ukuran yang tepat dan
pinggiran-pinggiran yang tajam dan utuh dan tidak retak.

Pekerjaan Instalasi Listrik


Kabel, Stop Kontak, Saklar dan lampu harus disesuaikan dengan persyaratan dan Setiap
sambungan kabel harus dibungkus dengan isolatip
Kabel yang digunakan dalam kegiatan ini adalah kabel 2,5 mm digunakan untuk semua
pekerjaan jaringan instalasi listrik gedung, baik untuk instalasi penerang maupun instalasi
stop kontak / saklar.
Jenis lampu (baik lampu TL maupun lampu pijar) harus berspesifikasi hemat energi.

Sesuai dengan persyaratan dalam gambar, untuk lampu pijar harus memakai lampu holder,
floursent harus dari jenis daylight dilengkapi dengan kapasitas lampu TL 1 x 40 watt dan TL
1 x 20 watt dengan armateur. Semua komponen didalam rumahan/housing (built in) lengkap.
Pekerjaan Sanitair
Meliputi pelaksanaan pengadaan dan pemasangan Kloset, Kran Air, Floor Drain, serta
perlengkapan-perlengkapan sanitair lainnya.
Semua kran yang dipakai adalah dengan chromed finish. Kran-kran tembok dipakai yang
berleher panjang dan mempunyai ring kedudukan yang harus dipasang menempel pada
dinding. Kran-kran yang dipasang dihalaman harus mempunyai ulir sink dan dapat
disambung dengan pipa leher angsa (extension).
Floor drain dan clean out dengan bahan dasar kuningan finishing verchroom type bulat
ukuran 3" dan atau ∅ 4” dilengkapi dengan siphon.
Pada tempat-tempat yang akan dipasang floor drain penutup lantai harus dilobangi dengan
rapi, menggunakan pahat kecil dengan bentuk dan ukuran sesuai ukuran floor drain
tersebut.
Pelaksanaan lnstalasi Air Bersih, Air Kotor, Air Buangan harus dilaksanakan dengan Pedoman
Plumbing Indonesia 1979 dan Peraturan standar air buangan.
Penyediaan instalasi air bersih, pengelolaan air kotor dan drainase air hujan, termasuk
pemilihan dan pengadaan material, pemasangan, pembangunan, pengujian material dan
sistem, trial run, untuk seluruh sistem sehingga dapat berjalan dengan baik sesuai gambar
rencana dan persyaratan ini. Sistem dan unit-unitnya meliputi :
- Menggunakan Pipa-pipa PVC ydengan diameter yang ditentukan.
- Sedapat menugkin menghindari keboran pada sambungan pipa.
- Jaringan pipa air bersih untuk diluar dan didalam bangunan.
- Jaringan pipa-pipa dan saluran, talang tegak, talang datar untuk pembuangan air hujan
dari atap serta halaman dan menyalurkan menuju drainase utama.
- Jaringan pipa-pipa vent untuk sistem pembuangan air kotor/air hujan.
- Jaringan pipa-pipa air kotor didalam bangunan.
- Penyambungan pipa air bersih dari jalur pipa air bersih utama.
- Unit pengolahan air kotor, berupa tangki septic yang dilengkapi dengan resapan.

13. PEKERJAAN LAIN-LAIN


Membuat gambar-gambar persyaratan revisi pada gambar bestek/gambar detail yang telah
dilaksanakan. Gambar tersebut dibuat dalam 3 (tiga) rangkap dan diserahkan kepada Direksi
/ PTP dan Pengguna Jasa pada saat penyerahan pertama pekerjaan, satu copy gambar
tersebut diserahkan pada perencana pada waktu yang sama.

Membersihkan seluruh lapangan pekerjaan dari bekas bongkaran pekerjaan, bekas galian
dan sisa-sisa material yang tidak digunakan lagi.

xxxxxxxxxxx, 29 Juli 2013

0 Dibuat Oleh,
0 0
0 xxxxxxxxxxxxxxxxxxx
0 Direktur
DAFTAR PERSONIL INTI

### #REF!
### #REF!
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx

No. Nama POSISI DI PROYEK INI UMUR PENDIDIKAN TERAKHIR


1 2 3 4 5

1. Pimpinan Teknik 46 Tahun Sarjana Teknik Mesin

2. Pelaksana Lapangan 28 Tahun Sarjana Teknik Elektro

3. Logistik 27 Tahun Sarjana TekniK Sipil

4. Administrasi 35 Tahun SMA

xxxxxxxxxxx, 29 Juli 2013


0
0 Dibuat Oleh,

0 xxxxxxxxxxxxxxxxxxx
0 Direktur
DAFTAR PERSONIL INTI

PENGALAMAN
6

19 Tahun

3 Tahun

2 Tahun

20 Tahun

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,

xxxxxxxxxxxxxxxxxxx
Direktur
DAFTAR PERALATAN UTAMA

### #REF!
### #REF!
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx

Jumlah Merk Tahun Ukuran / Milik Lokasi Alat


No. Nama Alat Daya Sewa
Alat dan Type Pembuatan Kapasitas Sendiri Sekarang
1 2 3 4 5 6 7 8 9

1 Genset Jiandiong 2002 15 KVA Sewa Gorontalo

2 Dump Truck Mitsubishi 2008 6 Ton Sewa Gorontalo

3 Molen (Concert Mixer) Goliath 2008 7,5 HP Sewa Gorontalo

4 Water Pump Honda 2008 5 HP Sewa Gorontalo

xxxxxxxxxxx, 29 Juli 2013


0
0 Dibuat Oleh,

0 xxxxxxxxxxxxxxxxxxx
0 Direktur
PAKTA INTEGRITAS

Saya yang bertanda tangan dibawah ini :

1. N a m a : MUCHSIN BREKAT

Jabatan : Direktur

Bertindak untuk : CV. MARGA MULYA


Dan atas nama

2. N a m a : xxxxxxxxxxxxxxxxxx

Jabatan : xxxxxxxxxxxxxxx

Bertindak untuk : xxxxxxxxxxxx


Dan atas nama

Dalam rangka Pengadaan Pekerjaan Pembangunan Pabrik Es Kapasitas 15 Ton


pada Pokja Pekerjaan Konstruksi ULP pada Dinas Perikanan dan Kelautan Provinsi
Gorontalo Tahun Anggaran 2011, dengan ini menyatakan bahwa :

1. Tidak akan melakukan praktek Korupsi, Kolusi dan Nepotisme (KKN)

2. Akan melaporkan kepada pihak APIP Inspektorat Jenderal Kementrian Kelautan


dan Perikanan yang bersangkutan dan/atau LKPP apabila mengetahui ada
indikasi KKN di dalam proses pengadaan ini;

3. Akan mengikuti proses pengadaan secara bersih, transparan dan profesional


untuk memberikan hasil kerja terbaik sesuai ketentuan peraturan perundang-
undangan.

4. Apabila melanggar hal-hal yang dinyatakan dalam Pakta Integritas ini bersedia
menerima sanksi administratif, menerima sanksi pencantuman dalam daftar
hitam, digugat secara perdata dan atau dilaporkan secara pidana.

xxxxxxxxxxx, 29 Juli 2013

CV. MARGA MULYA xxxxxxxxxxxx


xxxxxxxxxxxxxxxxxx
MUCHSIN BREKAT xxxxxxxxxxxxxxx
Direktur
PRA RENCANA K3 KONTRAK

KEGIATAN : PEMBANGUNAN RKB


PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013

1. Kebijakan xxxxxxxxxxxxxxxxxxxx

1.1 Visi dan Misi


- Memenuhi kebutuhan pelanggan dengan layanan yang baik dan produk yang
berkualitas
- Menyediakan lingkungan kerja yang aman
- Meningkatkan dan mengembangkan kemampuan sumberdaya manusia, terutama
dibidang keteknikan, manajemen perusahaan dan proyek
- Memperkokoh posisi perusahaan di pasar global dengan pelayanan yang baik,
produk berkualitas dan tenaga kerja yang terampil

1.2 Kebijakan Mutu dan K3L


- Meningkatkan mutu cara kerja dan hasil kerja
- Melaksanakan kegiatan sesuai dengan ketentuan dan mencegah ketidaksesuaian
pada semua tahapan kerja
- Melaksanakan norma-norma perlindungan kerja dan lingkungan kerja serta
menciptakan tempat kerja yang aman, sehat dan bebas resiko kecelakaan
- Melakukan perbaikan kinerja mutu dan K3L secara berkelanjutan, untuk
memenuhi kepuasan pelanggan dan stakeholder lainnya

2. Manajemen Resiko K3

2.1 Prosedur Manajemen Resiko


- Mengidentifikasi tempat kerja dan proses tahapan pekerjaan yang akan
- Mengidentifikasi potensi bahaya pada setiap proses tahapan pekerjaan baik yang
berjalan normal, abnormal, emergensi serta kondisi peralatan yang berjalan.
- Mengidentifikasi tingkat resiko bahaya, yang mungkin terjadi pada setiap ahapan
pekerjaan
- Mengevaluasi besar kecilnya tingkat resiko bahaya untuk menentukan prioritas
pengendalian terhadap resiko yang terjadi

2.2 Resiko Bahaya


Resiko bahaya lingkungan/manusia yang mungkin terjadi dari kegiatan pekerjaan
dapat berupa kerugian, cidera/cacat/kematian dan pencemaran lingkungan.
Contoh resiko bahaya yang mungkin terjadi pada setiap tahapan pekerjaan adalah
terpeleset, jatuh dari ketinggian, tersengat listrik, tertimpa peralatan/bahan,
penurunan pendengaran, kebakaran, pencemaran air, kontaninasi tanah dan
pencemaran udara.
2.3 Identifikasi Potensi Bahaya
Identifikasi potensi bahaya dapat menggunakan pendekatan-pendekatan sebagai
berikut :
- Pendekatan data/dokumen masa lalu
- Penggunaan check list
- Pendekatan sistem proses kerja

2.4 Penilaian Tingkat Resiko


- Kemungkinan (tingkat keseringan) adalah variable yang mereflesikan seberapa
sering suatu dampak terjadi dan berapa besar peluang terjadinya
- Konsekwensi (tingkat keparahan) adalah memprosentasikan besarnya dampak
kerugian yang dialami akibat terjadinya resiko, aspek legal menjadi point tertinggi
dalam penilaian aspek keparahan.
- Resikonya dibagi dalam sistem peringkat, yaitu resiko rendah, resiko sedang dan
resiko tinggi

2.5 Pengendalian Resiko


- Eliminasi (modifikasi proses, metoda/materi untuk mengurangi dampak K3)
- Subsitusi (mengganti materi zat atau proses dengan yang tidak/kurang berdampak)
- Pemisahan (menyingkirkan atau memisahkan agar dampak yang mungkin terjadi
minim dengan cara perlingdungan, penyimpanan ditempat, ruang tau waktu
terpisah)
- Administrasi (menyesuaikan waktu dan kondisi dengan proses administrasi
misalnya dengan membuat standar prosedur)
- Pelatihan (meningkatkanpengetahuan dan keterampilan untuk mengurangi resiko
terkena dampak K3)
- Alat pelindung diri (yang sesuai dan memadai guna menghindari dampak yang
mungkin terjadi)
xxxxxxxxxxxxxxxxxxxx LEMBAR PENGESAHAN

RENCANA K3 KONTRAK

PEKERJAAN : PEMBANGUNAN RKB


LOKASI : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx

KLASIFIKASI DOKUMEN
xxxxxxxxxxxxxxxxxxxx

Tanggal Terbit Pertama Tanggal Terbit Edisi Ini

Pihak Penyedia Jasa Pihak Pengguna Jasa

CV……………………… Disetujui Oleh

…………………………………. ………………………..
Direktur Nip :
xxxxxxxxxxxxxxxxxxxx KEBIJAKAN K3

KEBIJAKAN MUTU DAN K3L

- Meningkatkan mutu cara kerja dan hasil kerja

- Melaksanakan norma-norma perlindungan kerja dan lingkungan kerja serta


menciptakan tempat kerja yang aman, sehat dan bebas resiko kecelakaan

- Melaksanakan norma-norma perlindungan kerja dan lingkungan kerja serta


menciptakan tempat kerja yang aman, sehat dan bebas resiko kecelakaan

- Melakukan perbaikan kinerja mutu dan K3L secara berkelanjutan, untuk memenuhi
kepuasan pelanggan dan stakeholder lainnya

xxxxxxxxxxxxxxxxxxxx PEMENUHAN PERUNDANG-UNDANGAN DAN


PERSYARATAN LAINNYA

Nomor Dokumen Peraturan Perundang-undangan'


UU No. 1/1970 Tentang Keselamatan Kerja
UU No. 20/1992 Tentang Kelistrikan
UU No. 23/1992 Tentang Kesehatan
UU. No. 18/1999 Tentang Jasa Konstruksi
UU No. 13/2003 Tentang Ketenagakerjaan
Permenaker No. 01/MEN/1980 Tentang K3 Konstruksi Bangunan
SKB Menaker & PU 1986 Tentang K3 Konstruksi
Permenaker No. 5/1996 Tentang SMK3
Ins. Menaker N0. 01/1992 Tentang Pemeriksaan Unit Organisasi K3
SK. Dirjen PPK No. 20/DJPPK/VI/2004 Tentang Ahli Keselamatan dan Kesehatan Kerja
xxxxxxxxxxxxxxxxxxxx SASARAN DAN PROGRAM

1. Sasaran
Sasaran Mutu dan K3
Memberikan produk dan layanan kepada pelanggan dan stakeholder lainnya, sesuai
dengan ketentuan dan spesifikasi yang diperjanjikan serta mencapai sasaran
perusahaan tanpa kecelakaan atau zero accident

2. Program Dalam Mencapai Sasaran


* Adanya Program Kerja K3
* Persyaratan Program Kerja K3
- Dibuat untuk mencapai sasaran K3
- Uraian, wewenang dan tanggung jawab, sasaran, waktu
- Indikator pencapaian program
- Ditinjau secara regular
* Program kerja diuraikan secara jelas
xxxxxxxxxxxxxxxxxxxx ORGANISASI KEGIATAN

PENYEDIA JASA PENGGUNA JASA

KEPALA SATUAN KERJA

PEJABAT PEMBUAT
DIREKTUR KOMITMEN

ADMINISTRASI ASS. TEKNIK

PIMPINAN TEKNIK DIREKSI

PELAKSANA LAPANGAN PENGAWAS LAPANGAN

LOGISTIK
xxxxxxxxxxxxxxxxxxxx ORGANISASI PENYEDIA JASA

Direktur

Pimpinan
Pimpinan Teknik Administrasi
Administrasi

Juru
Juru Ukur
Ukur Logistik
Logistik
xxxxxxxxxxxxxxxxxxxx URAIAN TUGAS, WEWENANG DAN TANGGUNG JAWAB

NO NAMA JABATAN TUGAS WEWENANG TANGGUNG JAWAB

1 Direktur Membuat Menetapkan harga Bertanggung


Perjanjian Kontrak satuan upah dan jawab langsung
dengan Pengguna BTL maksimum atas terlaksananya
Melakukan
Jasa sama-sama pekerjaan yang
Monitoring Proyek
dengan RAPK diberikan.
selama Mensahkan bukti-
pelaksanaan
bukti pembayaran.
pekerjaan
Melaksanakan Mewakili
rapat mingguan perusahaan
atau rapat bulananberhubungan
internal dan dengan pihak I
eksternal. sesuai tugas yang
diatur dalam pasal-
2 Pimpinan Membuat kegiatan pasal kontrak.
Mewakili Bertanggung
Teknik perencanaan yang perusahaan jawab langsung
lain (Review Doc. berhubungan kepada Direktur
Spec Hitung dengan pihak I atas terlaksananya
kembali dan sesuai tugas yang dengan baik tugas
Metode diatur dalam pasal- yang diberikan.
Pelaksanaan). pasal kontrak.
Membuat rencana
tidak lanjut /
corrective action
terhadap
penyimpangan
yang terjadi.

3 Pelaksana Melaksanakan Mewakili Bertanggung


Lapangan Pekerjaan sesuai perusahaan jawab langsung
dengan mutu yang berhubungan kepada pelaksana
direncanakan. dengan pihak I utama atas
sesuai tugas yang terlaksananya
Mengadakan diatur dalam pasal- dengan baik tugas
Pengecekan yang diberikan
transaksi-transaksi
pelaksanaan
proyek,
mengkompilasikan
dan
membandingkan
dengan rencana
semula.
NO NAMA JABATAN TUGAS WEWENANG TANGGUNG JAWAB

4 Administrasi Mengatur dan Mewakili Bertanggung


menyiapkan perusahaan jawab langsung
kebutuhan berhubungan kepada pelaksana
material yang dengan pihak I utama atas
dibutuhkan sesuai tugas yang terlaksananya
Melakukan
diatur dalam pasal- dengan baik tugas
penilitian kembali
yang diberikan
untuk meyakinkan
kebenaran/ketepat
an yang dilakukan.
Melakukan Penanggung jawab Bertanggung
pencatatan berkas- masalah-masalah jawab langung
berkas transaksi ke keuangan,Akuntan kepada pelaksana
dalam media si/Pembukuan dan utma atas
pembukuan unsur-unsur Umum terlaksananya
(jurnal,dll) secara dan SDM Proyek. dengan baik tugas
benar dan tepat yang diberikan
waktu.
Melakukan
penilitian kembali
untuk meyakinkan
kebenaran/ketepat
an yang dilakukan.
Secara periodic
membuat laporan-
laporan yang telah
ditetapkan,
dimintakan
pengesahannya
kepada pejabat
yang berwenang
dan
mengirimkannya
kepada pihak-
pihak yang
memerlukan
sesuai prosedur
yang berlaku.
Melaksanakan
pengadministrasia
n keuangan dan
melaksanakan
pencatatan mutasi
keuangan secara
khusus.
Mengurus masalah
kepegawaian
seperti :
kebutuhan tenaga
kerja proyek,
asuransi-asuransi
lain yang diper-
syratkan dalam
proyek dan lain-
lain.
NO NAMA JABATAN TUGAS WEWENANG TANGGUNG JAWAB

6 Teknisi Material Mengatur dan Penanggung jawab Bertanggung


menyiapkan masalah-masalah jawab langung
kebutuhan pengadaan bahan. kepada pelaksana
material yang utama atas
dibutuhkan terlaksananya
Melakukan dengan baik tugas
penilitian kembali yang diberikan
untuk meyakinkan
kebenaran/ketepat
an yang dilakukan.
Secara periodic
membuat laporan-
laporan yang telah
ditetapkan,
dimintakan
pengesahannya
kepada pejabat
yang berwenang
dan
mengirimkannya
kepada pihak-
pihak yang
memerlukan
sesuai prosedur
yang berlaku.
Sebagai anggota
tim yang
melaksanakan
opname kas dan
sediaan secara
periodic.
Melakukan
Verifiaksi seluruh
dokumen transaksi
pembayaran
xxxxxxxxxxxxxxxxxxxx PRA - RENCANA KESELAMATAN DAN KESEHATAN
KERJA KONTRAK ( PRA - RK3K)

IDENTIFIKASI JENIS
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
BAHAYA & RESIKO K3

Pekerjaan Tanah Jenis Bahaya dan Resiko Pengendalian resiko K3


1 Galian Tanah Biasa Terjadi Insiden Berupa Akan disediakan sepatu
Kaki Pekerja Terkena boat pelindung kaki
2 Urugan Tanah Peralatan Seperti Sekop
dan Pacul Sehingga Terjadi
Luka
3 Urugan Pasir Terkena Material Hasil Akan disediakan helm
Galian sehingga terjadi pelindung kepala
luka dibagian kepala
pekerja baik luka ringan
maupun luka berat.
Resiko bahaya Mengindentifikasi potensi
lingkungan / manusia bahaya yang akan terjadi
yang mungkin terjadi dari dengan menggunakan
kegiatan pekerjaan dapat pendekatan data,
erupa kerugian, cidera, penggunaan chek list dan
cacat/kematian dan pendekatan sistem proses
pencemaran lingkungan kerja

Pekerjaan Pasangan Jenis Bahaya dan Resiko Pengendalian resiko K3


1 Pek. Pondasi Batu Kali/Belah Terjadi Insiden Berupa Akan disediakan sepatu
Kaki Pekerja Terkena boat pelindung kaki
2 Pek. Pas. Dinding Batu Bata Peralatan Seperti Sekop Akan disediakan helm
dan Pacul Sehingga Terjadi pelindung kepala
Luka
3 Pek. Plesteran Terkena Material batu
kali/belah & batu bata Akan disediakan masker
sehingga terjadi luka pelindung muka dan mata
dibagian kepala pekerja Akan disediakan sarung
sehingga terjadi luka baik tangan pelindung tangan
luka ringan maupun luka
Mengindentifikasi potensi
berat.
bahaya yang akan terjadi
Terjadi Insiden berupa dengan menggunakan
mata Pekerja Terkena pendekatan
material semen, pasir, data,penggunaan chek list
pecahan batu dibagian dan pendekatan sistem
muka dan mata sehingga proses kerja
mengakibatkan luka
ringan maupun luka berat.
IDENTIFIKASI JENIS
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
BAHAYA & RESIKO K3

Pekerjaan Kayu Jenis Bahaya dan Resiko Pengendalian resiko K3


1 Pek. Kusen Kayu Terjadi Insiden berupa kaki Akan disediakan sepatu
pekerja kejatuhan boat pelindung kaki
2 Pek. Daun Pintu Panel perlatan seperti gergaji, Akan disediakan helm
palu dll sehingga terjadi pelindung kepala
luka.
3 Pek. Rangka Plafond Terkena sisa potongan
kayu, paku, dan bahan Akan disediakan masker
lainnya sehingga terjadi pelindung muka dan mata
Pek. Rangka Atap luka dibagian kepala Akan disediakan sarung
pekerja sehingga terjadi tangan pelindung tangan
luka baik luka ringan
Akan disediakan tali
maupun luka berat.
pelindung sehingga tidak
Terjadi Insiden berupa langsung terjatuh dari
mata Pekerja Terkena ketinggian
material kayu, paku, baut Mengindentifikasi potensi
dan bahan lainnya bahaya yang akan terjadi
dibagian muka dan mata dengan menggunakan
sehingga mengakibatkan pendekatan
luka ringan maupun luka data,penggunaan chek list
berat. dan pendekatan sistem
Terjadi Insiden berupa proses kerja
terjatuh dari ketinggian
sehingga mengakibatkan
luka ringan maupun luka
berat.
Pekerjaan Kusen Jenis Bahaya dan Resiko Pengendalian resiko K3
1 Pek. Kusen Pintu & Jendela Terjadi Insiden berupa kaki Akan disediakan sepatu
pekerja kejatuhan boat pelindung kaki
perlatan seperti sehingga Akan disediakan helm
terjadi luka. pelindung kepala
Terkena sisa potongan
aluminium, dan bahan Akan disediakan masker
lainnya sehingga terjadi pelindung muka dan mata
luka dibagian kepala Akan disediakan sarung
pekerja sehingga terjadi tangan pelindung tangan
luka baik luka ringan
Akan disediakan tali
maupun luka berat.
pelindung sehingga tidak
langsung terjatuh dari
ketinggian
Mengindentifikasi potensi
bahaya yang akan terjadi
dengan menggunakan
pendekatan
data,penggunaan chek list
dan pendekatan sistem
proses kerja
IDENTIFIKASI JENIS
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
BAHAYA & RESIKO K3

Pekerjaan Kaca Jenis Bahaya dan Resiko Pengendalian resiko K3


1 Pas. Kaca Terjadi Insiden berupa Akan disediakan sepatu
kaki, tangan, mata dan boat pelindung kaki
badan pekerja terkena Akan disediakan helm
pecahan kaca sehingga pelindung kepala
menimbulkan luka baik
luka ringan maupun luka
berat. Akan disediakan masker
pelindung muka dan mata
Akan disediakan sarung
tangan pelindung tangan
Akan disediakan tali
pelindung sehingga tidak
langsung terjatuh dari
ketinggian
Mengindentifikasi potensi
bahaya yang akan terjadi
dengan menggunakan
pendekatan
data,penggunaan chek list
dan pendekatan sistem
proses kerja

Akan disediakan kotak P3K


IDENTIFIKASI JENIS
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
BAHAYA & RESIKO K3

Pekerjaan Lainnya Jenis Bahaya dan Resiko Pengendalian resiko K3


1 Pek. Finishing Terjadi Insiden berupa Akan disediakan sepatu
kaki, tangan, mata dan boat pelindung kaki
badan pekerja terkena Akan disediakan helm
bahan/material sehingga pelindung kepala
menimbulkan luka baik
luka ringan maupun luka
berat. Akan disediakan masker
pelindung muka dan mata
Akan disediakan sarung
tangan pelindung tangan
Akan disediakan tali
pelindung sehingga tidak
langsung terjatuh dari
ketinggian
Mengindentifikasi potensi
bahaya yang akan terjadi
dengan menggunakan
pendekatan
data,penggunaan chek list
dan pendekatan sistem
proses kerja

Akan disediakan kotak P3K

xxxxxxxxxxx, 29 Juli 2013

Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxx
Direktur