PEMBULATAN 93,000,000.00
II PEKERJAAN PASANGAN
1 Pasang Batu Putih 1 Pc : 8 Ps m2 133.02 63,411.50 8,434,997.73
2 Plesteran 1 Pc : 7 Ps m2 266.04 34,615.63 9,209,142.21
3 Benangan m2 79.81 7,119.00 568,167.39
4 Acian m2 266.04 7,119.00 1,893,938.76
JUMLAH 20,106,246.09
IV PEKERJAAN ATAP
1 Kuda-kuda6/12 Kayu Gelam m3 0.85 5,681,680.00 4,829,428.00
2 Gording/Nok Ikatan Angin 8/12 kayu Gelam m3 1.09 5,681,680.00 6,193,031.20
3 Usuk Reng Kayu Gelam m2 104.19 62,302.10 6,491,255.80
4 Genteng Kodok/Flam 2 sayap m2 104.19 43,150.00 4,495,798.50
5 Genteng Bubung m1 9.00 58,985.00 530,865.00
6 ListplangKayu Gelam 3/25 m1 18.00 121,565.88 2,188,185.84
JUMLAH 24,728,564.34