REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN REHABILITASI GEDUNG MADRASAH


TAHUN ANGGARAN 2012

Nama Madrasah : MTsN TERATE PANDIAN SUMENEP


Alamat Lengkap : Jalan Pesantren (PP.Terate) ( 0328-662193 Pandian Sumenep 69414

NO. URAIAN PEKERJAAN JUMLAH ( Rp )

I PEKERJAAN PERSIAPAN 4,027,823.75

II PEKERJAAN PASANGAN 20,106,246.09

III PEKERJAAN BETON 4,830,843.68

IV PEKERJAAN ATAP 24,728,564.34

V PEKERJAAN PINTU DAN JENDELA 14,073,415.64

VI PEKERJAAN PLAFOND 8,211,496.09

VII PEKERJAAN LANTAI 11,352,838.86

VIII PEKERJAAN PENGECATAN 3,782,987.45

IX PEKERJAAN INSTALASI LISTRIK 1,886,000.00

JUMLAH SELURUHNYA 93,000,215.90

PEMBULATAN 93,000,000.00

Terbilang : SEMBILAN PULUH TIGA JUTA RUPIAH


KEMENTERIAN AGAMA
MADRASAH TSABAWIYAH NEGERI
TERATE PANDIAN SUMENEP
Alamat : Jalan Pesantren (PP. Terate) ( 0328-662193 Pandian Sumenep 69414

RENCANA ANGGARAN BIAYA PEKERJAAN


REHABILITASI GEDUNG MADRASAH
TAHUN ANGGARAN 2012

HARGA SAT. JUMLAH


NO URAIAN PEKERJAAN SAT. VOLUME
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi ls 1.00 150,000.00 150,000.00
2 Penurunan Genteng m2 19.95 85,750.00 1,710,712.50
3 Pembongkaran usuk reng m2 104.19 5,675.00 591,278.25
4 Pembongkaran Plafond m3 104.19 1,375.00 143,261.25
5 Pembongkaran Kuda-kuda m3 86.82 7,587.50 658,746.75
6 Pembongkaran Kusen ls 6.00 100,000.00 600,000.00
7 Pembongkaran Tembok m3 0.85 204,500.00 173,825.00
JUMLAH 4,027,823.75

II PEKERJAAN PASANGAN
1 Pasang Batu Putih 1 Pc : 8 Ps m2 133.02 63,411.50 8,434,997.73
2 Plesteran 1 Pc : 7 Ps m2 266.04 34,615.63 9,209,142.21
3 Benangan m2 79.81 7,119.00 568,167.39
4 Acian m2 266.04 7,119.00 1,893,938.76
JUMLAH 20,106,246.09

III PEKERJAAN BETON


1 Kolom 15/ 15 m3 0.32 2,805,517.50 897,765.60
2 Kolom 25/25 m3 0.00 3,087,990.00 0.00
3 Ring Balk/Ring Gewel 15/15 m3 0.89 2,805,717.50 2,497,088.58
4 Bekising Kolom m2 3.38 96,280.56 325,428.29
5 Bekising Ring Balk 15/15 m2 11.10 100,050.56 1,110,561.22
JUMLAH 4,830,843.68

IV PEKERJAAN ATAP
1 Kuda-kuda6/12 Kayu Gelam m3 0.85 5,681,680.00 4,829,428.00
2 Gording/Nok Ikatan Angin 8/12 kayu Gelam m3 1.09 5,681,680.00 6,193,031.20
3 Usuk Reng Kayu Gelam m2 104.19 62,302.10 6,491,255.80
4 Genteng Kodok/Flam 2 sayap m2 104.19 43,150.00 4,495,798.50
5 Genteng Bubung m1 9.00 58,985.00 530,865.00
6 ListplangKayu Gelam 3/25 m1 18.00 121,565.88 2,188,185.84
JUMLAH 24,728,564.34

V PEKERJAAN PINTU DAN JENDELA


1 Kusen Benuas m2 0.39 13,447,610.00 5,244,567.90
2 Pas Daun Pintu Panil Benuas m2 5.17 613,625.00 3,172,441.25
3 Daun Jendela Kaca m2 8.18 523,300.00 4,280,594.00
4 Pegangan Pintu Kuku Tarung set 2.00 150,000.00 300,000.00
5 Engsel Pintu Kuningan set 3.00 54,368.13 163,104.40
6 Engsel Jendela Kuningan set 10.00 26,478.75 264,787.50
7 Grendel Jendela bh 10.00 24,268.13 242,681.30
8 Hag Angin bh 10.00 38,268.13 382,681.30
9 Kaca Mati Biasa 5 mm m2 0.27 83,548.13 22,558.00
JUMLAH 14,073,415.64
VI PEKERJAAN PLAFOND
1 Rangka Plafond Kayu Gelam m2 85.40 75,727.10 6,467,094.34
2 Plafond Eternit m2 85.40 20,426.25 1,744,401.75
JUMLAH 8,211,496.09

VII PEKERJAAN LANTAI


1 Keramik Lantai 40 X 40 m2 79.20 111,105.05 8,799,519.96
2 Rabatan Beton 1 : 4 : 6 m3 3.96 644,777.50 2,553,318.90
JUMLAH 11,352,838.86

VIII PEKERJAAN PENGECATAN


1 Cat Kayu m2 23.57 14,468.75 341,028.44
2 Cat Dinding m2 266.04 12,937.75 3,441,959.01
JUMLAH 3,782,987.45

IX PEKERJAAN INSTALASI LISTRIK


1 Instalasi titik lampu + titik stop kontak ttk 9.00 150,000.00 1,350,000.00
2 Stop Kontak bh 1.00 14,000.00 14,000.00
3 Sakelar Ganda bh 4.00 27,500.00 110,000.00
4 Lampu SI, 25 watt bh 8.00 48,000.00 384,000.00
5 Fitting Plafond bh 8.00 3,500.00 28,000.00
JUMLAH 1,886,000.00
JUMLAH SELURUHNYA 93,000,215.90
PEMBULATAN 93,000,000.00

Sumenep, 10 September 2012


Kepala MTsN Terate
Pandian Sumenep Ketua Panitia

H. MUH. RIFA'I HASYIM, S.Pd, MMPd SULISTIANA, S.Pd

Mengetahui,
Dinas PU / Kimpraswil
Kabupaten Sumenep

........................................................