Anda di halaman 1dari 30

ENGINEER ESTIMATE (EE)

PEKERJAAN :

PEMBANGUNAN GAZEBO KEDIAMAN SEKDA

LOKASI :

KEC. NAMLEA

TAHUN ANGGARAN 2015

KONSULTAN PERENCANA
CV. GRIYA HESANDE KONSULTAN
Jln. Dr. Malaiholo No.10 D Taman Makmur - Ambon
DAFTAR HARGA SATUAN UPAH dan BAHAN

NO. URAIAN SATUAN HARGA


(Rp)
1 2 3 4
UPAH
1 MANDOR OH 130,000.00
2 KEPALA TUKANG OH 115,000.00
3 TUKANG OH 105,000.00
4 PEKERJA OH 85,000.00

BAHAN LOKAL
1 PASIR URUG M3 256,000.00
2 PASIR PASANGAN ( SUNGAI KALI ) M3 355,600.00
3 TANAH URUG M3 196,200.00
4 SIRTU KALI M3 355,600.00
5 BATU KALI M3 483,400.00
6 BATU KARANG GUNUNG M3 421,600.00
7 BATU PECAH 2/3 M3 495,000.00
8 KERIKIL SARING SUNGAI M3 365,600.00
9 BATU BATA BH 1,250.00
10 BATAKO 25 X 15 X 13 CM BH 3,200.00
11 KAYU KLAS I M3 4,800,000.00
12 KAYU KLAS II M3 3,300,000.00
BAHAN NON LOKAL
1 SEMEN ZAK 90,000.00
2 SEMEN KG 1,800.00
3 SEMEN PUTIH ZAK 120,000.00
4 SEMEN PEREKAT INSTAN AM / SETARA KG 18,480.00
5 SEMEN NAT KG 67,400.00
6 SEMEN WARNA KG 15,400.00
7 BESI BETON KG 14,850.00
8 KAWAT BAJA / BENDRAT KG 26,000.00
9 PAKU BIASA KG 19,000.00
10 PAKU SENK KG 27,000.00
11 BAUT Dia. 1/2 INCH KG 21,200.00
12 PAKU BETON KG 23,500.00
13 PAKU TRIPLEKS KG 22,000.00
14 LEM KAYU Kg 45,000.00
15 BESI STRIP KG 14,850.00
16 KAWAT LAS KG 35,000.00
17 MULTIPLEKS 10 mm LBR 124,500.00
18 TEAK WOOD LBR 127,500.00
19 PLAYWOOD LBR 127,000.00
20 SENG GELOMBANG BJLS 0,20 LBR 47,400.00
21 SENG GELOMBANG BJLS 0,25 LBR 60,400.00
22 SENG DATAR BJLS 0.20 LBR 49,400.00
23 SENG DATAR BJLS 0.25 LBR 63,400.00
24 SENG DATAR BJLS 0.30 LBR 74,400.00
25 ATAP MULTIROOF BH 45,400.00
26 BUBUNGAN MULTIROOF M1 35,400.00
27 TRIPLEKS 3 MM M2 60,500.00
28 DINDING KERAMIK MOTIF BATU ALAM 20/40 M2 80,200.00
DINDING KERAMIK MOTIF BATU ALAM 20/40 BH 6,416.00
29 KERAMIK 40/40 M2 82,400.00
KERAMIK 40/40 Bh 12,428.36
NO. URAIAN SATUAN HARGA
(Rp)
1 2 3 4
30 PLAMIR KG 26,000.00
31 KAPUR API KG 12,200.00
32 CAT TEMBOK KG 27,500.00
33 CAT KAYU SETARA GLOTEK KG 56,000.00
34 CAT DASAR KG 21,000.00
35 CAT RESIDU KAYU KG 56,000.00
36 CAT MENI ZENK KG 56,000.00
37 CAT MENI KAYU LTR 56,000.00
38 MINYAK CAT KG 31,000.00
39 KUAS 3 BH 10,200.00
40 DEMPUL DINDING KG 26,000.00
41 KERTAS AMPLAS LBR 6,100.00
42 DEMPUL KAYU KG 26,000.00
43 KACA POLOS 3 MM M2 314,500.00
44 KACA POLOS 5 MM M2 336,500.00
45 LIST PLAFOND KAYU PROFIL Ky Klas II M' 25,500.00
46 HANDLE PINTU Bh 125,100.00
47 KUNCI PINTU Bh 200,200.00
48 ENGSEL PINTU Bh 50,100.00
49 ENGSEL JENDELA Bh 45,100.00
50 GRENDEL PINTU Bh 30,100.00
51 GRENDEL JENDELA Bh 30,100.00
52 DOOR CLOSER Bh 376,000.00
53 KAIT ANGIN Bh 25,100.00
54 CLOSET DUDUK BH 3,050,000.00
55 CLOSET JONGKOK BH 215,000.00
56 WASHTAFEL BH 376,000.00
57 KRAN TEMBOK BH 125,000.00
58 KRAN LEHER ANGSA BH 200,000.00
59 FLOOR DRAIN BH 27,200.00
60 DRAIN BAK AIR BH 35,100.00
61 KACA CERMIN BH 165,000.00
62 LAMPU TL 1x18 WATT PHILLIPS BH 55,200.00
63 LAMPU DOWN LIHGT 22 watt (Lengkap) BH 110,500.00
64 LAMPU PIJAR 60 WATT BH 30,200.00
65 SAKLAR GANDA BH 26,200.00
66 SAKLAR TUNGGAL BH 26,200.00
67 STOP KONTAK BH 23,200.00
68 Pipa GIV Dia. 1/2 Inch M' 29,500.00
69 Pipa GIV Dia. 3/4 Inch M' 43,000.00
70 Pipa GIV Dia. 1 Inch M' 53,000.00
71 Pipa GIV Dia. 1 1/2 Inch M' 84,000.00
72 Pipa GIV Dia. 2 Inch M' 134,000.00
73 Pipa GIV Dia. 3 Inch M' 152,500.00
74 Pipa GIV Dia. 4 Inch M' 160,800.00
75 Pipa GIV Dia. 6 Inch M 216,000.00
76 Pipa PVC Dia. 1/2 Inch STAF 23,200.00
77 Pipa PVC Dia. 3/4 Inch STAF 30,200.00
78 Pipa PVC Dia. 1 Inch STAF 41,500.00
79 Pipa PVC Dia. 1 1/2 Inch STAF 60,200.00
80 Pipa PVC Dia. 2 Inch STAF 85,500.00
81 Pipa PVC Dia. 3 Inch STAF 145,500.00
82 Pipa PVC Dia. 4 Inch STAF 150,500.00
NO. URAIAN SATUAN HARGA
(Rp)
1 2 3 4

83 Pipa PVC Dia. 6 Inch STAF 315,000.00


REKAPITULASI BIAYA
ENGINEER'S ESTIMATE (EE)
SATUAN KERJA : Badan Usaha Milik Desa - SIPATTON
PEKERJAAN : Pengembangan Lokasi Paralayang
LOKASI : Desa Latuhalat - Kota Ambon
TAHUN ANGGARAN : 2019

NO URAIAN PEKERJAAN JUMLAH HARGA

1 2 3

I PEKERJAAN PERSIAPAN Rp. 10,250,000.00


II PEKERJAAN TANAH Rp. 4,734,116.29
III PEKERJAAN PONDASI dan PASANGAN Rp. 23,579,640.39
IV PEKERJAAN BETON Rp. 12,987,339.07
V PEKERJAAN LANTAI KERAMIK Rp. 6,728,439.26
VI PEKERJAAN KAYU, ATAP dan PLAFOUND Rp. 39,303,261.63
VII PEKERJAAN PENGECATAN Rp. 4,711,162.92
VIII PEKERJAAN INSTALASI LISTRIK Rp. 6,277,965.00
IX PEKERJAAN LAIN - LAIN Rp. 6,238,263.05

A JUMLAH ( I s/d IX ) Rp. 114,810,187.61


B PPN 10 % Rp. 11,481,018.76
C JUMLAH TOTAL A + B Rp. 126,291,206.38
D JUMLAH DIBULATKAN Rp. 126,291,000.00

TERBILANG : Seratus Dua Puluh Enam Juta Dua Ratus Sembilan Puluh Satu Ribu Rupiah,-

Catatan : Harga tersebut diatas sudah termasuk Jasa, Over Head, IMB dan Pajak-pajak sesuai dengan
ketentuan yang berlaku.

Namlea, 13 Juli 2015

Dibuat Oleh,
KONSULTAN PERENCANA
CV. GRIYA HESANDE KONSULTAN

MADE A. LATUCONSINA, ST
Team Leader
REKAPITULASI
ENGINEER'S ESTIMATE (EE)

SATUAN KERJA : Badan Usaha Milik Desa - SIPATTON


PEKERJAAN : Pengembangan Lokasi Paralayang
LOKASI : Desa Latuhalat - Kota Ambon
TAHUN ANGGARAN : 2019

HARGA
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
(Rp)
1 2 3 4 5

A. PEMBANGUNAN 3 UNIT GAZEBO


I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Pekerjaan Ls 1.00 1.00 3,500,000.00
2 Pemasangan Bowplank Ls 1.00 1.00 2,500,000.00
3 Pembuatan Papan Nama Proyek Ls 1.00 1.00 750,000.00
4 Biaya K3 Ls 1.00 1.00 3,500,000.00

II PEKERJAAN TANAH
1 Galian Tanah Pondasi Batu Karang M3 11.26 17.32 73,700.00
2 Urugan Pasir Bawah Pondasi M3 1.35 2.08 367,400.00
3 Urugan Pasir Bawah Lantai M3 2.60 4.00 367,400.00
4 Urugan Tanah Kembali Bekas Galian M3 3.75 5.77 53,900.00
5 Urugan Tanah Bawah Lantai M3 7.80 12.00 288,464.00

III PEKERJAAN PONDASI dan PASANGAN


1 Pasangan Batu Kosong [Aanstamping] M3 2.03 3.12 806,648.70
2 Pasangan Pondasi Batu Karang ad, 1pc : 4ps M3 4.31 6.63 1,329,742.70
3 Pasangan Dinding Bt. Bata ad, 1pc : 5ps elv - 0.10 s/d + 2.70 M2 23.66 36.40 233,273.92
4 Pasangan Dinding Bt. Bata ad, 1pc : 5ps elv + 2.70 s/d + 3.80 M2 18.59 28.60 233,273.92
5 Plesteran Dinding Batu Bata ad, 1pc : 4ps elv + 1.00 s/d + 2.70 M2 20.33 31.28 71,160.54
6 Plesteran Dinding Batu Bata ad, 1pc : 4ps elv + 2.70 s/d + 3.80 M2 37.18 57.20 71,160.54
7 Acian Dinding Luar dan Dalam M2 57.51 88.48 39,380.00

IV PEKERJAAN BETON
1 Pek. Sloef 15/20 (150 kg/m3) elv - 0.25 M3 0.51 0.78 5,836,347.00
2 Pek. Kolom 20/20 (150 kg/m3) elv - 0.10 s/d + 3.80 M3 0.42 0.64 7,363,642.00
3 Pek. Kolom Praktis 12/12 (230 kg/m3) elv - 0.10 s/d + 3.80 M3 0.41 0.63 8,670,442.00
4 Pek. Ring Balok 15/20 (150 kg/m3) elv + 3.80 M3 0.51 0.78 6,694,677.00

V PEKERJAAN LANTAI KERAMIK


1 Pekerjaan Lantai Keramik 40 x 40 CM M2 26.00 40.00 190,984.20
2 Pekerjaan Keramik Dinding Motif Batu Alam 20/40 M2 5.98 9.20 294,790.98

VI PEKERJAAN KAYU, ATAP dan PLAFOUND


1 Pekerjaan Kusen Shading Sollar (tirai) Kayu Kls. I M3 0.27 0.41 9,241,512.50
2 Pekerjaan Shading Sollar (tirai) Kayu Kls. I M2 3.44 5.29 685,217.50
3 Pek. Kuda-Kuda 6/12 Kayu Kls. I M3 0.58 0.90 7,929,432.50
4 Pek. Gording 5/10 kayu kls. II M3 0.29 0.44 7,397,032.50
5 Pek. Rangka Atap Genteng Kayu kls. II M2 69.04 106.22 113,492.50
6 Pek. Atap Genteng Multiroof M2 69.04 106.22 85,566.80
7 Pek. Bubungan Atap Genteng Multiroof M1 14.56 22.40 87,626.00
8 Pek. Papan Listplank 3/20 [double] M1 24.31 37.40 94,985.00
9 Pek. Rangka Plafound kayu Kls. II M2 50.60 77.85 119,735.00
10 Pek. Pasangan Plafound Tripleks 3mm M2 50.60 77.85 39,380.00
11 Pek. Pasangan List Plafound Kayu diprofil M1 57.20 88.00 41,085.00
VII PEKERJAAN PENGECATAN
1 Cat Kusen dan Jalusi M2 8.90 13.69 38,556.10
2 Cat Dinding Luar dan Dalam M2 57.51 88.48 37,135.45
3 Cat Plafound tripleks M2 50.60 77.85 38,556.10
4 Cat Listplank M2 7.29 11.22 38,556.10

VIII PEKERJAAN INSTALASI LISTRIK


1 Pek. Instalasi Titik Lampu Titik 19.00 22.00 193,765.00
2 Lampu Down Light dia 6" PL 1x22 watt Bh 2.00 2.00 141,927.50
3 Lampu Down Light dia 5" PL 1x18 watt Bh 4.00 8.00 81,097.50
4 Lampu Hias bagian depan Bh 2.00 2.00 400,000.00
5 Saklar tunggal Bh 4.00 4.00 74,838.50
6 Saklar ganda Bh 2.00 2.00 74,838.50
7 Stop kontak Tanam Dinding Bh 4.00 4.00 71,538.50
8 Box panil komplit Bh 1.00 1.00 453,000.00

IX PEKERJAAN LAIN - LAIN


Rabat Keliling Bangunan
1 Pek. Galian Tanah M3 2.11 3.24 73,700.00
2 Urugan Tanah Kembali Bekas Galian M3 0.70 1.08 53,900.00
3 Pek. Rolaag Pasangan Batu Bata ad, 1pc : 3ps M2 12.87 19.80 233,273.92
4 Pek. Urugan Tanah M3 3.08 4.74 288,464.00
5 Pek. Urugan Pasir M3 2.05 3.16 367,400.00
6 Pek. Hamparan Batu Putih Ls 0.65 1.00 1,000,000.00
7 Pek. Plesteran 1 : 3 M2 10.53 16.20 71,160.54
JUMLAH
HARGA
(Rp)
6

3,500,000.00
2,500,000.00
750,000.00
3,500,000.00
10,250,000.00

829,834.36
496,724.80
955,240.00
202,297.93
2,250,019.20
4,734,116.29

1,635,883.56
5,730,526.17
5,519,260.95
4,336,562.17
1,446,836.10
2,645,748.88
2,264,822.56
23,579,640.39

2,959,027.93
3,063,275.07
3,570,834.83
3,394,201.24
12,987,339.07

4,965,589.20
1,762,850.06
6,728,439.26

2,467,428.39
2,355,006.90
4,623,874.11
2,127,090.67
7,835,493.83
5,907,510.48
1,275,834.56
2,309,085.35
6,059,084.91
1,992,790.44
2,350,062.00
39,303,261.63
343,141.58
2,135,734.00
1,951,097.70
281,189.64
4,711,162.92

3,681,535.00
283,855.00
324,390.00
800,000.00
299,354.00
149,677.00
286,154.00
453,000.00
6,277,965.00

155,212.20
37,837.80
3,002,235.35
888,898.21
754,759.01
650,000.00
749,320.49
6,238,263.05
ANALISA HARGA SATUAN UPAH DAN BAHAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.1. Pengukuran dan pemasangan 1 m’ Bouwplank

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang Kayu L.02 OH 0.100 105,000.00 10,500.00
Kepala Tukang L.03 OH 0.010 115,000.00 1,150.00
Mandor L.04 OH 0.005 130,000.00 650.00
JUMLAH TENAGA KERJA 20,800.000
B BAHAN
Kayu balok 5/7 kls. II. m3 0.120 3,300,000.00 396,000.00
Paku 2”-3” Kg 0.020 19,000.00 380.00
Kayu papan 3/20 Kls. II m3 0.007 3,300,000.00 23,100.00
JUMLAH HARGA BAHAN 419,480.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 440,280.00
E Overhead & Profit 10% x D 44,028.00
F Harga Satuan Pekerjaan (D+E) 484,308.00

A. 2.2.1.3. Pembuatan 1 m2 Gudang semen & Peralatan

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.00 85,000.00 85,000.00
Tukang Kayu L.02 OH 2.00 105,000.00 210,000.00
Kepala Tukang L.03 OH 0.20 115,000.00 23,000.00
Mandor L.04 OH 0.25 130,000.00 32,500.00
JUMLAH TENAGA KERJA 350,500.00
B BAHAN
Dolken kayu dia. 8-10/400 cm Batang 1.700 60,000.00 102,000.00
Kayu m3 0.210 3,300,000.00 693,000.00
Paku Biasa Kg 0.300 19,000.00 5,700.00
Semen portland Kg 10.500 1,800.00 18,900.00
Pasir Pasang m3 0.030 355,600.00 10,668.00
koral beton m3 0.050 365,600.00 18,280.00
Sen Gelombang Lbr 0.250 47,400.00 11,850.00
Sen Plat Lbr 0.200 49,400.00 9,880.00
JUMLAH HARGA BAHAN 870,278.00

C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,220,778.00
E Overhead & Profit 10% x D 122,077.80
F Harga Satuan Pekerjaan (D+E) 1,342,855.80

A.2.3.1.4. Pembersihan 1 m2 Lapangan & Perataan Tanah

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
JUMLAH TENAGA KERJA 15,000.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 15,000.00
E Overhead & Profit 10% x D 1,500.00
F Harga Satuan Pekerjaan (D+E) 16,500.00

A.2.3.1. PEKERJAAN TANAH


A.2.3.1.7. Pengalian 1 m3 Tanah Biasa sedalam 1 m

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.750 85,000.00 63,750.00
Mandor L.04 OH 0.025 130,000.00 3,250.00
JUMLAH TENAGA KERJA 67,000.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 67,000.00
E Overhead & Profit 10% x D 6,700.00
F Harga Satuan Pekerjaan (D+E) 73,700.00

A.2.3.1.8. Pengurugan Kembali 1 m3 Galian Tanah


A.2.3.1.8. Pengurugan Kembali 1 m3 Galian dihitung dari 1/3 kali Dari Koefisien Pekerjaan Galian

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 85,000.00 42,500.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
JUMLAH TENAGA KERJA 49,000.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 49,000.00
E Overhead & Profit 10% x D 4,900.00
F Harga Satuan Pekerjaan (D+E) 53,900.00

A.2.3.1.9. Pengurugan 1 m3 Dengan Pasir Urug

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Mandor L.04 OH 0.010 130,000.00 1,300.00
JUMLAH TENAGA KERJA 26,800.00
B BAHAN
Pasir urug 1.200 256,000.00 307,200.00
JUMLAH HARGA BAHAN 307,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 334,000.00
E Overhead & Profit 10% x D 33,400.00
F Harga Satuan Pekerjaan (D+E) 367,400.00

A.2.3.1.10. Pengurugan 1 m3 Dengan Tanah

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Mandor L.04 OH 0.010 130,000.00 1,300.00
JUMLAH TENAGA KERJA 26,800.00
B BAHAN
Tanah Urug 1.200 196,200.00 235,440.00
JUMLAH HARGA BAHAN 235,440.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 262,240.00
E Overhead & Profit 10% x D 26,224.00
F Harga Satuan Pekerjaan (D+E) 288,464.00
A.3.2.2 HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1 Pemasangan 1 m3 Pondasi Pasangan Batu Karang Gunung Campuran 1SP : 3PP

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 85,000.00 127,500.00
Tukang Batu L.02 OH 0.750 105,000.00 78,750.00
Kepala Tukang L.03 OH 0.075 115,000.00 8,625.00
Mandor L.04 OH 0.075 130,000.00 9,750.00
JUMLAH TENAGA KERJA 224,625.00
B BAHAN
1. Semen Portland kg 202.00 1,800.00 363,600.00
2. Pasir pasangan m3 0.485 355,600.00 172,466.00
3. Batu karang gunung m3 1.200 421,600.00 505,920.00
JUMLAH HARGA BAHAN 1,041,986.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,266,611.00


E Overhead & Profit 10% x D 126,661.10
F Harga Satuan Pekerjaan (D+E) 1,393,272.10

A.3.2.1.2 Pemasangan 1 m3 Fondasi pasangan batu karang gunung campuran 1SP : 4PP

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 85,000.00 127,500.00
Tukang Batu L.02 OH 0.750 105,000.00 78,750.00
Kepala Tukang L.03 OH 0.075 115,000.00 8,625.00
Mandor L.04 OH 0.075 130,000.00 9,750.00
JUMLAH TENAGA KERJA 224,625.00
B BAHAN
1. Semen Portland kg 163.00 1,800.00 293,400.00
2. Pasir pasangan m3 0.520 355,600.00 184,912.00
3. Batu karang gunung m3 1.200 421,600.00 505,920.00
JUMLAH HARGA BAHAN 984,232.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,208,857.00


E Overhead & Profit 10% x D 120,885.70
F Harga Satuan Pekerjaan (D+E) 1,329,742.70

A.3.2.1.3 Pemasangan 1 m3 Pondasi Pasangan Batu Karang Gunung Campuran 1SP : 5PP

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 85,000.00 127,500.00
Tukang Batu L.02 OH 0.750 105,000.00 78,750.00
Kepala Tukang L.03 OH 0.075 115,000.00 8,625.00
Mandor L.04 OH 0.075 130,000.00 9,750.00
JUMLAH TENAGA KERJA 224,625.00
B BAHAN
1. Semen Portland kg 136.00 1,800.00 244,800.00
2. Pasir pasangan m3 0.544 355,600.00 193,446.40
3. Batu karang gunung m3 1.200 421,600.00 505,920.00
JUMLAH HARGA BAHAN 944,166.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,168,791.40


E Overhead & Profit 10% x D 116,879.14
F Harga Satuan Pekerjaan (D+E) 1,285,670.54

A.3.2.1.4 Pemasangan 1 m3 Pondasi Pasangan Batu Kosong (Aanstamping)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.780 85,000.00 66,300.00
Tukang Batu L.02 OH 0.390 105,000.00 40,950.00
Kepala Tukang L.03 OH 0.039 115,000.00 4,485.00
Mandor L.04 OH 0.039 130,000.00 5,070.00
JUMLAH TENAGA KERJA 116,805.00
B BAHAN
2. Pasir uruk m3 0.432 256,000.00 110,592.00
3. Batu karang gunung m3 1.200 421,600.00 505,920.00
JUMLAH HARGA BAHAN 616,512.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 733,317.00


E Overhead & Profit 10% x D 73,331.70
F Harga Satuan Pekerjaan (D+E) 806,648.70

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),slump (3-6) cm,w/c = 0,87
Harga Satuan Jumlah harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 85,000.00 102,000.00
Tukang Batu L.02 OH 0.200 105,000.00 21,000.00
Kepala Tukang L.03 OH 0.020 115,000.00 2,300.00
Mandor L.04 OH 0.060 130,000.00 7,800.00
JUMLAH TENAGA KERJA 133,100.00
B BAHAN
Semen Portland kg 230.00 1,800.00 414,000.00
Pasir Beton kg 893.00 284.43 254,000.00
Batu Pecah 2x3 cm kg 1,027.00 481.99 495,000.00
Air Liter 200.00 50.00 10,000.00
JUMLAH HARGA BAHAN 1,173,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,306,100.00
E Overhead & Profit 10% x D 130,610.00
F Harga Satuan Pekerjaan (D+E) 1,436,710.00

A.4.1.1.29 Membuat 1 m3 Sloof beton bertulang (150 kg besi + bekisting)


Harga Satuan Jumlah harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 5.650 85,000.00 480,250.00
Tukang batu L.02 OH 0.275 105,000.00 28,875.00
Tukang kayu L.02 OH 1.560 105,000.00 163,800.00
Tukang besi L.02 OH 1.400 105,000.00 147,000.00
Kepala tukang L.03 OH 0.323 115,000.00 37,145.00
Mandor L.04 OH 0.283 130,000.00 36,790.00
JUMLAH TENAGA KERJA 893,860.00
B BAHAN
Kayu kelas II m3 0.270 3,300,000.00 891,000.00
Paku 5 cm – 12cm kg 2.000 19,000.00 38,000.00
Minyak bekesting Ltr 0.600 30,500.00 18,300.00
Besi beton polos kg 155.000 14,850.00 2,301,750.00
Kawat beton kg 3.000 26,000.00 78,000.00
Semen Portland kg 336.000 1,800.00 604,800.00
Pasir Beton m3 0.540 355,600.00 192,024.00
Kerikil m3 0.810 355,600.00 288,036.00
JUMLAH HARGA BAHAN 4,411,910.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 5,305,770.00
E Overhead & Profit 10% x D 530,577.00
F Harga Satuan Pekerjaan (D+E) 5,836,347.00

A.4.1.1.30 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.050 85,000.00 599,250.00
Tukang batu L.02 OH 0.275 105,000.00 28,875.00
Tukang kayu L.02 OH 1.650 105,000.00 173,250.00
Tukang besi L.02 OH 2.100 105,000.00 220,500.00
Kepala tukang L.03 OH 0.403 115,000.00 46,345.00
Mandor L.04 OH 0.353 130,000.00 45,890.00
JUMLAH TENAGA KERJA 1,114,110.00
B BAHAN
Kayu kelas III m3 0.400 2,500,000.00 1,000,000.00
Paku 5 cm – 12cm kg 4.000 19,000.00 76,000.00
Minyak bekesting Ltr 2.000 30,500.00 61,000.00
Besi beton polos kg 155.000 14,850.00 2,301,750.00
Kawat beton kg 4.500 26,000.00 117,000.00
Semen Portland kg 336.000 1,800.00 604,800.00
Pasir Beton m3 0.540 355,600.00 192,024.00
Kerikil m3 0.810 355,600.00 288,036.00
Kayu kelas II balok m3 0.150 3,300,000.00 495,000.00
Plywood 9 mm Lbr 3.500 127,000.00 444,500.00
JUMLAH HARGA BAHAN 5,580,110.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 6,694,220.00
E Overhead & Profit 10% x D 669,422.00
F Harga Satuan Pekerjaan (D+E) 7,363,642.00

A.4.1.1.30 Membuat 1 m3 kolom beton bertulang (230 kg besi + bekisting)


Harga Satuan Jumlah harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.050 85,000.00 599,250.00
Tukang batu L.02 OH 0.275 105,000.00 28,875.00
Tukang kayu L.02 OH 1.650 105,000.00 173,250.00
Tukang besi L.02 OH 2.100 105,000.00 220,500.00
Kepala tukang L.03 OH 0.403 115,000.00 46,345.00
Mandor L.04 OH 0.353 130,000.00 45,890.00
JUMLAH TENAGA KERJA 1,114,110.00
B BAHAN
Kayu kelas III m3 0.400 2,500,000.00 1,000,000.00
Paku 5 cm – 12cm kg 4.000 19,000.00 76,000.00
Minyak bekesting Ltr 2.000 30,500.00 61,000.00
Besi beton polos kg 235.000 14,850.00 3,489,750.00
Kawat beton kg 4.500 26,000.00 117,000.00
Semen Portland kg 336.000 1,800.00 604,800.00
Pasir Beton m3 0.540 355,600.00 192,024.00
Kerikil m3 0.810 355,600.00 288,036.00
Kayu kelas II balok m3 0.150 3,300,000.00 495,000.00
Plywood 9 mm Lbr 3.500 127,000.00 444,500.00
JUMLAH HARGA BAHAN 6,768,110.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 7,882,220.00
E Overhead & Profit 10% x D 788,222.00
F Harga Satuan Pekerjaan (D+E) 8,670,442.00
A.4.1.1.31 Membuat 1 m3 Balok Beton Bertulang (135 kg besi + bekisting)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.350 85,000.00 539,750.00
Tukang batu L.02 OH 0.275 105,000.00 28,875.00
Tukang kayu L.02 OH 1.650 105,000.00 173,250.00
Tukang besi L.02 OH 1.400 105,000.00 147,000.00
Kepala tukang L.03 OH 0.333 115,000.00 38,295.00
Mandor L.04 OH 0.318 130,000.00 41,340.00
JUMLAH TENAGA KERJA 968,510.00
B BAHAN
Kayu kelas III m3 0.320 2,500,000.00 800,000.00
Paku 5 cm – 12 cm kg 3.200 19,000.00 60,800.00
Minyak bekesting Ltr 1.600 30,500.00 48,800.00
Besi beton polos kg 135.000 14,850.00 2,004,750.00
Kawat beton kg 3.000 26,000.00 78,000.00
Semen Portland kg 336.000 1,800.00 604,800.00
Pasir Beton m3 0.540 355,600.00 192,024.00
Batu Pecah 2x3 cm m3 0.810 355,600.00 288,036.00
Kayu kelas II balok m3 0.140 3,300,000.00 462,000.00
Plywood 9 mm Lbr 2.800 127,000.00 355,600.00
JUMLAH HARGA BAHAN 4,894,810.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 5,863,320.00


E Overhead & Profit 10% x D 586,332.00
F Harga Satuan Pekerjaan (D+E) 6,449,652.00

A.4.1.1.31 Membuat 1 m3 Balok Beton Bertulang (150 kg besi + bekisting)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.350 85,000.00 539,750.00
Tukang batu L.02 OH 0.275 105,000.00 28,875.00
Tukang kayu L.02 OH 1.650 105,000.00 173,250.00
Tukang besi L.02 OH 1.400 105,000.00 147,000.00
Kepala tukang L.03 OH 0.333 115,000.00 38,295.00
Mandor L.04 OH 0.318 130,000.00 41,340.00
JUMLAH TENAGA KERJA 968,510.00
B BAHAN
Kayu kelas III m3 0.320 2,500,000.00 800,000.00
Paku 5 cm – 12 cm kg 3.200 19,000.00 60,800.00
Minyak bekesting Ltr 1.600 30,500.00 48,800.00
Besi beton polos kg 150.000 14,850.00 2,227,500.00
Kawat beton kg 3.000 26,000.00 78,000.00
Semen Portland kg 336.000 1,800.00 604,800.00
Pasir Beton m3 0.540 355,600.00 192,024.00
Batu Pecah 2x3 cm m3 0.810 355,600.00 288,036.00
Kayu kelas II balok m3 0.140 3,300,000.00 462,000.00
Plywood 9 mm Lbr 2.800 127,000.00 355,600.00
JUMLAH HARGA BAHAN 5,117,560.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 6,086,070.00


E Overhead & Profit 10% x D 608,607.00
F Harga Satuan Pekerjaan (D+E) 6,694,677.00

A.4.1.1.33 Membuat 1 m3 Plat beton bertulang (150 kg besi + bekisting)

Harga Satuan (Rp) Jumlah harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 7.050 85,000.00 599,250.00
Tukang batu L.02 OH 0.275 105,000.00 28,875.00
Tukang kayu L.02 OH 1.650 105,000.00 173,250.00
Tukang besi L.02 OH 2.100 105,000.00 220,500.00
Kepala tukang L.03 OH 0.403 115,000.00 46,345.00
Mandor L.04 OH 0.353 130,000.00 45,890.00
JUMLAH TENAGA KERJA 1,114,110.00
B BAHAN
Kayu kelas II m3 0.400 3,300,000.00 1,320,000.00
Paku 5 cm – 12cm kg 4.000 19,000.00 76,000.00
Minyak bekesting Ltr 1.600 30,500.00 48,800.00
Besi beton polos kg 160.000 14,850.00 2,376,000.00
Kawat beton kg 4.500 26,000.00 117,000.00
Semen Portland kg 336.000 1,800.00 604,800.00
Pasir Beton m3 0.540 355,600.00 192,024.00
Batu Pecah 2x3 cm m3 0.810 355,600.00 288,036.00
Kayu kelas II balok M3 0.150 2,500,000.00 375,000.00
Multipleks 10 mm Lbr 3.500 124,500.00 435,750.00
JUMLAH HARGA BAHAN 5,833,410.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 6,947,520.00
E Overhead & Profit 10% x D 694,752.00
F Harga Satuan Pekerjaan (D+E) 7,642,272.00

A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.2 Pemasangan 1 m2 Dinding Batako (8x15x30) cm tebal 1 batu campuran 1SP : 3PP

Harga Satuan (Rp) Jumlah harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang batu L.02 OH 0.200 105,000.00 21,000.00
Kepala tukang L.03 OH 0.020 115,000.00 2,300.00
Mandor L.04 OH 0.030 130,000.00 3,900.00
JUMLAH TENAGA KERJA 78,200.00
B BAHAN
Batako bh 18.00 3,200.00 57,600.00
Semen Portland kg 32.95 1,800.00 59,310.00
Pasir pasang m3 0.09 355,600.00 32,395.16
JUMLAH HARGA BAHAN 149,305.16
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 227,505.16
E Overhead & Profit 10% x D 22,750.52
F Harga Satuan Pekerjaan (D+E) 250,255.68

A.4.4.1.4 Pemasangan 1 m2 Dinding batako (8x15x30) cm tebal 1 batu campuran 1SP : 5PP

Harga Satuan (Rp) Jumlah harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.600 85,000.00 51,000.00
Tukang batu L.02 OH 0.200 105,000.00 21,000.00
Kepala tukang L.03 OH 0.020 115,000.00 2,300.00
Mandor L.04 OH 0.030 130,000.00 3,900.00
JUMLAH TENAGA KERJA 78,200.00
B BAHAN
Batako Bh 18.00 3,200.00 57,600.00
Semen Portland kg 22.220 1,800.00 39,996.00
Pasir pasang m3 0.1020 355,600.00 36,271.20
JUMLAH HARGA BAHAN 133,867.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 212,067.20
E Overhead & Profit 10% x D 21,206.72
F Harga Satuan Pekerjaan (D+E) 233,273.92

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Batu L.03 OH 0.150 105,000.00 15,750.00
Kepala Tukang L.03 OH 0.015 115,000.00 1,725.00
Mandor L.04 OH 0.015 130,000.00 1,950.00
JUMLAH TENAGA KERJA 44,925.00
B BAHAN
1. PC Kg 7.776 1,800.00 13,996.80
2. PP m3 0.023 355,600.00 8,178.80
JUMLAH HARGA BAHAN 22,175.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 67,100.60


E Overhead & Profit 10% x D 6,710.06
F Harga Satuan Pekerjaan (D+E) 73,810.66
A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4 PP. Tebal 15 mm.

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 85,000.00 25,500.00
Tukang batu L.03 OH 0.1500 105,000.00 15,750.00
Kepala tukang L.03 OH 0.0150 115,000.00 1,725.00
Mandor L.04 OH 0.0150 130,000.00 1,950.00
JUMLAH TENAGA KERJA 44,925.00
B BAHAN
1. PC Kg 6.240 1,800.00 11,232.00
2. PP mᶟ 0.024 355,600.00 8,534.40
JUMLAH HARGA BAHAN 19,766.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 64,691.40


E Overhead & Profit 10% x D 6,469.14
F Harga Satuan Pekerjaan (D+E) 71,160.54

A.4.4.2.27. Pemasangan 1 m2 acian.

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang Batu L.03 OH 0.100 105,000.00 10,500.00
Kepala Tukang L.03 OH 0.010 115,000.00 1,150.00
Mandor L.04 OH 0.010 130,000.00 1,300.00
JUMLAH TENAGA KERJA 29,950.00
B BAHAN
Semen PC Kg 3.250 1,800.00 5,850.00
JUMLAH HARGA BAHAN 5,850.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,800.00


E Overhead & Profit 10% x D 3,580.00
F Harga Satuan Pekerjaan (D+E) 39,380.00

A.4.4.3.10.Pemasangan 1 m2 Lantai Keramik Ukuran 40 x 40 cm Anti Slip

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang Batu L.02 OH 0.125 105,000.00 13,125.00
Kepala tukang L.03 OH 0.013 115,000.00 1,495.00
Mandor L.04 OH 0.013 130,000.00 1,690.00
JUMLAH TENAGA KERJA 37,560.00
B BAHAN
Lantaik Keramik 40/40 bh 6.630 12,428.36 82,400.00
Semen Portlan Kg 9.800 1,800.00 17,640.00
pasir Pasang m3 0.045 355,600.00 16,002.00
Semen warna Kg 1.300 15,400.00 20,020.00
JUMLAH HARGA BAHAN 136,062.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 173,622.00


E Overhead & Profit 10% x D 17,362.20
F Harga Satuan Pekerjaan (D+E) 190,984.20

A.4.4.3.58.Pemasangan 1 m2 Dinding Keramik Ukuran 20 cm x 25 cm

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 85,000.00 76,500.00
Tukang Batu L.02 OH 0.450 105,000.00 47,250.00
Kepala tukang L.03 OH 0.045 115,000.00 5,175.00
Mandor L.04 OH 0.045 130,000.00 5,850.00
JUMLAH TENAGA KERJA 134,775.00
B BAHAN
Keramik Bh 20.000 4,010.00 80,200.00
Semen Portlan Kg 9.300 1,800.00 16,740.00
pasir Pasang m3 0.0180 355,600.00 6,400.80
Semen warna Kg 1.940 15,400.00 29,876.00
JUMLAH HARGA BAHAN 133,216.80
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 267,991.80


E Overhead & Profit 10% x D 26,799.18
F Harga Satuan Pekerjaan (D+E) 294,790.98

A.4.6.1 HARGA SATUAN PEKERJAAN KAYU


A.4.6 .1.2. Pembuatan dan Pemasangan 1 M3 Kusen Pintu / Jendela Kayu Kls I

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.000 85,000.00 595,000.00
Tukang Kayu L.03 OH 21.000 105,000.00 2,205,000.00
Kepala tukang L.03 OH 2.100 115,000.00 241,500.00
Mandor L.04 OH 0.350 130,000.00 45,500.00
JUMLAH TENAGA KERJA 3,087,000.00
B BAHAN
Balok Kayu M3 1.100 4,800,000.00 5,280,000.00
Paku Biasa 10 cm Kg 1.250 19,000.00 23,750.00
Lem Kayu Kg 1.000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 5,280,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 8,401,375.00


E Overhead & Profit 10% x D 840,137.50
F Harga Satuan Pekerjaan (D+E) 9,241,512.50

A.4.6 .1.5. Pembuatan dan Pemasangan 1 M2 Daun Pintu Panel Kayu Kls I

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 85,000.00 68,000.00
Tukang Kayu L.03 OH 2.400 105,000.00 252,000.00
Kepala tukang L.03 OH 0.240 115,000.00 27,600.00
Mandor L.04 OH 0.040 130,000.00 5,200.00
JUMLAH TENAGA KERJA 352,800.00
B BAHAN
Papan Kayu Kls I M3 0.024 4,800,000.00 115,200.00
Lem Kayu Kg 0.300 45,000.00 13,500.00
JUMLAH HARGA BAHAN 115,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 474,750.00


E Overhead & Profit 10% x D 47,475.00
F Harga Satuan Pekerjaan (D+E) 522,225.00

A.4.6 .1.6. Pembuatan dan Pemasangan 1 M2 Pintu dan Jendela Kaca Kayu Kls I

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang Kayu L.03 OH 3.000 105,000.00 315,000.00
Kepala tukang L.03 OH 0.300 115,000.00 34,500.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
JUMLAH TENAGA KERJA 441,000.00
B BAHAN
Papan Kayu Kls I M3 0.040 4,800,000.00 192,000.00
Lem Kayu Kg 0.500 45,000.00 22,500.00
JUMLAH HARGA BAHAN 192,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 644,250.00


E Overhead & Profit 10% x D 64,425.00
F Harga Satuan Pekerjaan (D+E) 708,675.00
A.4.6 .1.7. Pembuatan dan Pemasangan 1 M2 Pintu dan Jendela Jalusi Kayu Kls I

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang Kayu L.03 OH 3.000 105,000.00 315,000.00
Kepala tukang L.03 OH 0.300 115,000.00 34,500.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
JUMLAH TENAGA KERJA 441,000.00
B BAHAN
Papan Kayu Kls I M3 0.064 4,800,000.00 307,200.00
Lem Kayu Kg 0.500 45,000.00 22,500.00
JUMLAH HARGA BAHAN 307,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 759,450.00


E Overhead & Profit 10% x D 75,945.00
F Harga Satuan Pekerjaan (D+E) 835,395.00

A.4.6 .1.10. Pemasangan 1 M2 Jalusi Kusen Kayu Kls I

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.670 85,000.00 56,950.00
Tukang Kayu L.03 OH 2.000 105,000.00 210,000.00
Kepala tukang L.03 OH 0.200 115,000.00 23,000.00
Mandor L.04 OH 0.335 130,000.00 43,550.00
JUMLAH TENAGA KERJA 333,500.00
B BAHAN
Papan Kayu Kls I M3 0.060 4,800,000.00 288,000.00
Paku 1 - 2,5 cm Kg 0.150 19,000.00 2,850.00
JUMLAH HARGA BAHAN 288,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 622,925.00


E Overhead & Profit 10% x D 62,292.50
F Harga Satuan Pekerjaan (D+E) 685,217.50

A.4.6 .1.13. Pemasangan 1 M3 Konstruksi Kuda-kuda Konvensional Kayu Kls I Bentangan 6 meter

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.000 85,000.00 340,000.00
Tukang Kayu L.03 OH 12.000 105,000.00 1,260,000.00
Kepala tukang L.03 OH 1.200 115,000.00 138,000.00
Mandor L.04 OH 0.200 130,000.00 26,000.00
JUMLAH TENAGA KERJA 1,764,000.00
B BAHAN
Balok Kayu Kayu Kls I M3 1.100 4,800,000.00 5,280,000.00
Besi Strip T 5 mm Kg 15.000 14,850.00 222,750.00
Paku 12 cm Kg 5.600 19,000.00 106,400.00
JUMLAH HARGA BAHAN 5,280,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 7,208,575.00


E Overhead & Profit 10% x D 720,857.50
F Harga Satuan Pekerjaan (D+E) 7,929,432.50

A.4.6 .1.15. Pemasangan 1 M3 Konstruksi Gorden Kayu Kls II

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.700 85,000.00 569,500.00
Tukang Kayu L.03 OH 20.100 105,000.00 2,110,500.00
Kepala tukang L.03 OH 2.010 115,000.00 231,150.00
Mandor L.04 OH 0.335 130,000.00 43,550.00
JUMLAH TENAGA KERJA 2,954,700.00
B BAHAN
Balok Kayu Kayu Kls II M3 1.100 3,300,000.00 3,630,000.00
Besi Strip T 5 mm Kg 15.000 14,850.00 222,750.00
Paku 12 cm Kg 3.000 19,000.00 57,000.00
JUMLAH HARGA BAHAN 3,630,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 6,724,575.00


E Overhead & Profit 10% x D 672,457.50
F Harga Satuan Pekerjaan (D+E) 7,397,032.50

A.4.6 .1.16. Pemasangan 1 M2 Rangka Atap genteng Keramik, Kayu Kls II

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang Kayu L.03 OH 0.100 105,000.00 10,500.00
Kepala tukang L.03 OH 0.010 115,000.00 1,150.00
Mandor L.04 OH 0.005 130,000.00 650.00
JUMLAH TENAGA KERJA 20,800.00
B BAHAN
Kaso-kaso 5/7 cm M3 0.014 2,500,000.00 35,000.00
Reng 2/3 cm M4 0.036 2,500,000.00 90,000.00
Paku 12 cm Kg 0.250 19,000.00 4,750.00
JUMLAH HARGA BAHAN 35,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 103,175.00


E Overhead & Profit 10% x D 10,317.50
F Harga Satuan Pekerjaan (D+E) 113,492.50
A.4.5 .2.32. Pemasangan 1 M2 Atap Metal roof

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang Kayu L.03 OH 0.100 105,000.00 10,500.00
Kepala tukang L.03 OH 0.010 115,000.00 1,150.00
Mandor L.04 OH 0.001 130,000.00 130.00
JUMLAH TENAGA KERJA 28,780.00
B BAHAN
Atap Metal roof lbr 1.020 45,400.00 46,308.00
Paku Biasa 2" - 5" Kg 0.200 27,000.00 5,400.00
JUMLAH HARGA BAHAN 46,308.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,788.00


E Overhead & Profit 10% x D 7,778.80
F Harga Satuan Pekerjaan (D+E) 85,566.80

A.4.5 .2.32. Pemasangan 1 M' Pasang Bubungan Metal roof

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang Kayu L.03 OH 0.150 105,000.00 15,750.00
Kepala tukang L.03 OH 0.015 115,000.00 1,725.00
Mandor L.04 OH 0.013 130,000.00 1,690.00
JUMLAH TENAGA KERJA 40,415.00
B BAHAN
Bubungan Metal roof lbr 1.100 35,400.00 38,940.00
Paku Biasa ½" - 1" Kg 0.050 12,200.00 610.00
JUMLAH HARGA BAHAN 38,940.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 79,660.00


E Overhead & Profit 10% x D 7,966.00
F Harga Satuan Pekerjaan (D+E) 87,626.00

A.4.6 .1.19. Pemasangan 1 M2 Rangka Langit-Langit ( 50x100) cm Kayu Kls II

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang Kayu L.03 OH 0.300 105,000.00 31,500.00
Kepala tukang L.03 OH 0.030 115,000.00 3,450.00
Mandor L.04 OH 0.075 130,000.00 9,750.00
JUMLAH TENAGA KERJA 57,450.00
B BAHAN
Kaso 5 - 7 cm M3 0.015 3,300,000.00 49,500.00
Paku 7 - 10 cm Kg 0.200 19,000.00 3,800.00
JUMLAH HARGA BAHAN 49,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 108,850.00


E Overhead & Profit 10% x D 10,885.00
F Harga Satuan Pekerjaan (D+E) 119,735.00

A.4.6 .1.19. Pemasangan 1 M2 Langit-Langit Tripleks 3 mm

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang Kayu L.03 OH 0.075 105,000.00 7,875.00
Kepala tukang L.03 OH 0.008 115,000.00 920.00
Mandor L.04 OH 0.001 130,000.00 130.00
JUMLAH TENAGA KERJA 11,050.00
B BAHAN
Tripleks 3 mm M3 0.400 60,500.00 24,200.00
Paku Tripleks Kg 0.050 22,000.00 1,100.00
JUMLAH HARGA BAHAN 24,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,800.00


E Overhead & Profit 10% x D 3,580.00
F Harga Satuan Pekerjaan (D+E) 39,380.00

A.4.5 .1.9. Pemasangan 1 M1 List Langit-langit Kayu Profil Kls II

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 85,000.00 4,250.00
Tukang Kayu L.03 OH 0.050 105,000.00 5,250.00
Kepala tukang L.03 OH 0.005 115,000.00 575.00
Mandor L.04 OH 0.003 130,000.00 390.00
JUMLAH TENAGA KERJA 10,465.00
B BAHAN
List Kayu Profil M1 1.050 25,500.00 26,775.00
Paku Kg 0.010 22,000.00 220.00
JUMLAH HARGA BAHAN 26,775.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 37,350.00
E Overhead & Profit 10% x D 3,735.00
F Harga Satuan Pekerjaan (D+E) 41,085.00

A.4.5 .1.9. Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang Kayu L.03 OH 0.200 105,000.00 21,000.00
Kepala tukang L.03 OH 0.020 115,000.00 2,300.00
Mandor L.04 OH 0.005 130,000.00 650.00
JUMLAH TENAGA KERJA 32,450.00
B BAHAN
Papan kayu kls I M1 0.011 4,800,000.00 52,800.00
Paku 5 cm dan 7 cm Kg 0.100 22,000.00 2,200.00
JUMLAH HARGA BAHAN 52,800.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 86,350.00


E Overhead & Profit 10% x D 8,635.00
F Harga Satuan Pekerjaan (D+E) 94,985.00
A.4.7.2. HARGA SATUAN PEKERJAAN PENGECETAN
A.4.7.1.4. 1 M2 Pengecatan Bidang Kayu Baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.07 85,000.00 5,950.00
Tukang cat L.02 OH 0.009 105,000.00 945.00
Kepala tukang L.03 OH 0.006 115,000.00 690.00
Mandor L.04 OH 0.003 130,000.00 390.00
JUMLAH TENAGA KERJA 7,975.00
B BAHAN
Cat Meni Kg 0.200 56,000.00 11,200.00
Plamuur Kg 0.150 26,000.00 3,900.00
Cat Dasar Kg 0.170 21,000.00 3,570.00
Cat Penutup Kg 0.260 56,000.00 14,560.00
Kuas Bh 0.010 10,200.00 102.00
Minyak Cat Kg 0.030 31,000.00 930.00
Amplas Lbr 0.200 6,100.00 1,220.00
JUMLAH HARGA BAHAN 18,670.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,051.00


E Overhead & Profit 10% x D 3,505.10
F Harga Satuan Pekerjaan (D+E) 38,556.10
A.4.7.1.10a. Pengecatan 1 m2 Watterproof ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.02 85,000.00 1,700.00
Tukang cat L.02 OH 0.063 105,000.00 6,615.00
Kepala tukang L.03 OH 0.0063 115,000.00 724.50
Mandor L.04 OH 0.003 130,000.00 390.00
JUMLAH TENAGA KERJA 9,429.50
B BAHAN
Plamir Kg 0.100 26,000.00 2,600.00
Cat dasar Kg 0.100 21,000.00 2,100.00
Cat Watter proof Kg 0.260 75,500.00 19,630.00
JUMLAH HARGA BAHAN 24,330.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 33,759.50


E Overhead & Profit 10% x D 3,375.95
F Harga Satuan Pekerjaan (D+E) 37,135.45

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.02 85,000.00 1,700.00
Tukang cat L.02 OH 0.063 105,000.00 6,615.00
Kepala tukang L.03 OH 0.0063 115,000.00 724.50
Mandor L.04 OH 0.003 130,000.00 390.00
JUMLAH TENAGA KERJA 9,429.50
B BAHAN
Plamir Kg 0.100 26,000.00 2,600.00
Cat dasar Kg 0.100 21,000.00 2,100.00
Cat penutup Metrolitte Kg 0.260 27,500.00 7,150.00
JUMLAH HARGA BAHAN 11,850.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 21,279.50


E Overhead & Profit 10% x D 2,127.95
F Harga Satuan Pekerjaan (D+E) 23,407.45

HARGA SATUAN PEKERJAAN INSTALASI LISTRIK


An. 1 Titik Lampu Lampu/Instalasi Penerang

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 85,000.00 25,500.00
Tukang Listrik L.02 OH 0.500 105,000.00 52,500.00
Kepala tukang (Listrik) L.03 OH 0.050 115,000.00 5,750.00
JUMLAH TENAGA KERJA 83,750.00
B BAHAN
Isolator Bh 1.000 10,000.00 10,000.00
Kabel NYM 3 x 2,5 mm M' 6.000 7,500.00 45,000.00
Las Doof Bh 4.000 2,500.00 10,000.00
Pipa PVC 3/4"-5/8" M' 1.000 12,400.00 12,400.00
Aksesoris & Alat Bantu Ls 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 92,400.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 176,150.00


E Overhead & Profit 10% x D 17,615.00
F Harga Satuan Pekerjaan (D+E) 193,765.00

An. Memasang Lampu Down Light dia 6" PL 1x22 watt

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 85,000.00 850.00
Tukang Listrik L.02 OH 0.020 105,000.00 2,100.00
Kepala tukang (Listrik) L.03 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 3,525.00
B BAHAN
Lampu Down light 22 watt Bh 1.000 110,500.00 110,500.00
Perlengkapan Ls 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 125,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 129,025.00


E Overhead & Profit 10% x D 12,902.50
F Harga Satuan Pekerjaan (D+E) 141,927.50
An. Memasang Lampu TL 18 watt Phillips

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 85,000.00 850.00
Tukang Listrik L.02 OH 0.020 105,000.00 2,100.00
Kepala tukang (Listrik) L.03 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 3,525.00
B BAHAN
Lampu TL 18 watt Phillips Bh 1.000 55,200.00 55,200.00
Perlengkapan Ls 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 70,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 73,725.00


E Overhead & Profit 10% x D 7,372.50
F Harga Satuan Pekerjaan (D+E) 81,097.50

An. Memasang Saklar Tunggal


Harga Satuan Jumlah harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.001 85,000.00 85.00
Tukang Listrik L.02 OH 0.200 105,000.00 21,000.00
Kepala tukang (Listrik) L.03 OH 0.050 115,000.00 5,750.00
JUMLAH TENAGA KERJA 26,835.00
B BAHAN
Saklar Tunggal Bh 1.000 26,200.00 26,200.00
Perlengkapan Ls 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 41,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 68,035.00


E Overhead & Profit 10% x D 6,803.50
F Harga Satuan Pekerjaan (D+E) 74,838.50

An. Memasang Saklar Ganda


Harga Satuan Jumlah harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.001 85,000.00 85.00
Tukang Listrik L.02 OH 0.200 105,000.00 21,000.00
Kepala tukang (Listrik) L.03 OH 0.050 115,000.00 5,750.00
JUMLAH TENAGA KERJA 26,835.00
B BAHAN
Saklar Tunggal Bh 1.000 26,200.00 26,200.00
Perlengkapan Ls 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 41,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 68,035.00


E Overhead & Profit 10% x D 6,803.50
F Harga Satuan Pekerjaan (D+E) 74,838.50

An. Memasang Stop Kontak

Harga Satuan Jumlah harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.001 85,000.00 85.00
Tukang Listrik L.02 OH 0.200 105,000.00 21,000.00
Kepala tukang (Listrik) L.03 OH 0.050 115,000.00 5,750.00
JUMLAH TENAGA KERJA 26,835.00
B BAHAN
Stop Kontak Bh 1.000 23,200.00 23,200.00
Perlengkapan Ls 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 38,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 65,035.00


E Overhead & Profit 10% x D 6,503.50
F Harga Satuan Pekerjaan (D+E) 71,538.50
PEKERJAAN :
BELANJA ATAP PENGHUBUNG II
KANTOR BUPATI

DOKUMEN PERENCANAAN :
■ DESAIN GAMBAR KERJA
■ ENGINEER ESTIMATE [EE]
■ BILL OF QUANTITY [BOQ]

LOKASI :

KEC. NAMLEA

TAHUN ANGGARAN 2015

KONSULTAN PERENCANA
CV. GRIYA HESANDE KONSULTAN
Jln. Dr. Malaiholo No.10 D Taman Makmur - Ambon

Anda mungkin juga menyukai