RENCANA ANGGARAN BIAYA

PEMBANGUNAN MESJID AL IKHLAS


KAMULYAN MANONJAYA KAB. TASIKMALAYA

VOL KERJA SATUAN HARGA


No URAIAN PEKERJAAN HARGA TOTAL (Rp)
JML SAT (Rp)
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran / Uitzet Dan Bouwplank 225.00 m 34,575.00 7,779,375.00
2 Biaya Perijinan 450.00 m2 4,750.00 2,137,500.00
9,916,875.00
II PEKERJAAN TANAH
1 Pek.Galian tanah pondasi 136.80 m3 21,992.00 3,008,505.60
2 Pek.Urugan kembali Tanah Bekas Galian 34.20 m3 7,773.00 265,836.60
3 Pek.Urugan Pasir Bawah pondasi t = 5 cm 5.13 m3 99,500.00 509,937.50
4 Pek.Urugan dan pemadatan tanah peninggian Lantai 122.40 m3 70,603.00 8,641,807.20
12,426,086.90
III PEKERJAAN PONDASI
1 Pasangan Aanstamping Batu Kali 5.75 m3 157,252.50 904,201.88
2 Pasangan Pondasi Batu Kali 1 PC : 5 Ps 27.01 m3 402,228.00 10,864,005.08
3 Pasangan Pondasi Setempat 29.42 m3 402,229.00 11,832,389.51
23,600,596.47
IV PEKERJAAN STRUKTUR BETON
1 Pek. Sloof Beton 15/20 16.41 m3 2,437,900.00 39,998,353.67
2 Pek. Sloof Beton 15/30 10.17 m3 5,329,800.00 54,204,022.42
3 Pek. Kolom Strukrtur 40/40 35.18 m3 4,477,201.00 157,527,666.14
4 Pek. Kolom Strukrtur 15/25 5.68 m3 4,477,202.00 25,408,263.77
5 Pek. Kolom Praktis 5.54 m3 4,477,203.00 24,820,631.77
6 Pek. Ring Balk 25/60 24.55 m3 3,270,500.00 80,289,755.74
7 Pek. Ring Balk 15/30 10.71 m3 3,270,501.00 35,034,216.15
8 Pek. Tangga Beton 15.41 m3 3,270,501.00 50,395,350.53
9 Pek. Plat Lantai Beton t = 12 cm 24.24 m3 3,270,500.00 79,267,724.49
10 Pek. Plat Atap Beton t = 12 cm 20.64 m3 3,270,501.00 67,514,379.21
11 Pek. Lesplank Beton 187.50 m 59,217.95 11,103,365.63
12 Pek. Atap Kubah Enamel Ø 4,3 m 44.40 m2 2,400,000.00 106,560,755.74
13 Pek. Atap Kubah Enamel Ø 1,4 m 28.53 m2 2,400,000.00 68,460,755.74
800,585,240.98
V PEKERJAAN DINDING
1 Pek. Pas. Bata Merah 1 PC : 3 Ps 86.50 m2 140,473.00 12,150,914.50
2 Pek. Pas. Bata Merah 1 PC : 5 Ps 330.50 m2 128,961.00 42,621,593.18
3 Pek. Dinding Terawangan 110.87 m2 145,396.00 16,119,872.78
4 Pek. Plesteran Dinding 1 PC : 3 Ps 173.00 m2 30,850.00 5,337,050.00
5 Pek. Plesteran Dinding 1 PC : 5 Ps 661.00 m2 28,855.00 19,073,147.25
6 Pek. Plesteran Beton 1 PC : 3 Ps 351.05 m2 31,122.50 10,925,553.63
106,228,131.34
VI PEKERJAAN LANTAI
1 Pek. Urugan Pasir Bawah Lantai t = 5 cm 184.92 m2 99,500.00 18,399,105.26
2 Pek. Lantai Kerja 1 PC : 3 Ps : 5 Krt = 5 cm 367.71 m2 63,464.00 23,336,145.26
3 Pek. Pasangan Lantai Kramik 60 cm x 60 cm 360.00 m2 111,722.00 40,219,920.00
81,955,170.52
VII PEKERJAAN KAYU KUSEN PINTU & JENDELA
1 Pek. Kusen Pintu, Jendela & Bovenlicht Kayu Gunung Klas II 78.75 m2 219,054.00 17,250,502.50
2 Pek. Daun Pintu, Rangka kayu Kayu Gunung Klas II 25.50 m2 265,155.00 6,761,452.50
3 Pek. Rangka Daun Jendel Rangka Kayu Gunung Klas II 15.30 m2 306,849.31 4,694,794.44
4 Pek. Neut Kusen 15.00 bh 7,500.00 112,500.00
5 Pek. List 1/3 Penutup Daun pintu 90.21 m1 21,100.00 1,903,510.13
30,722,759.57
No. URAIAN PEKERJAAN VOL KERJA SATUAN HARGA HARGA TOTAL(Rp)
JML SAT (Rp)
VIII PEKERJAAN PLAFON
1 Pek. Rangka Plafond KayuGunung Klas II 360.00 m2 113,227.00 40,761,720.00
2 Pek. List Plafond Gypsum 407.50 m1 16,000.00 6,520,000.00
47,281,720.00
IX PEKERJAAN PENGGANTUNG KUNCI DAN KACA
1 Pek. Kunci Tanam 2 Slang Sek. Tessa 15.00 bh 125,000.00 1,875,000.00
2 Pek. Engsel kupu-kupu Pintu Sek. Unilon 45.00 bh 25,148.00 1,131,660.00
3 Pek. Engsel kupu-kupu jendela Sek. Unilon 30.00 bh 16,765.00 502,950.00
4 Sek. Sloot Tanam Pintu 2 Daun (atas bawah) 15.00 Ps 25,000.00 375,000.00
5 Pek. Sloot Jendela 23.00 Ps 17,031.00 391,713.00
6 Pek. Tarikan Jendela 23.00 bh 8,500.00 195,500.00
7 Pek. Tarikan Pintu 15.00 bh 86,579.00 1,298,685.00
8 Pek. Kait Angin 23.00 Ps 19,098.00 439,254.00
9 Pek. Kaca Polos 5 mm Sek. Asahi 123.84 m2 87,298.00 10,810,886.11
17,020,648.11
X PEKERJAAN PENGECATAN & LABURAN
1 Pek. Pengecatan Kayu dengan AVIAN 149.44 m2 25,699.00 3,840,394.31
2 Pek. Pengecatan Dinding dengan SANLEX 1,481.31 m2 18,000.00 26,663,618.96
3 Pek. Pengecatan Plafond Eternit 450.00 m2 21,650.00 9,742,500.00
40,246,513.27
XI PEKERJAAN INSTALASI LISTRIK
1 Pek. Intalasi Ttk Cahaya dan Saklar 50.00 ttk 45,000.00 2,250,000.00
2 Pek. Instalasi Daya dan Stop Sontak 18.75 ttk 50,000.00 937,500.00
3 Pasangan Lampu neon 1 x 36 Watt 15.00 bh 75,000.00 1,125,000.00
4 Pasang Lampu Pijar 25 Watt 30.00 bh 4,500.00 135,000.00
5 Feeder Cable NYY 4 x 6mm 1.25 ls 1,500,000.00 1,875,000.00
6,322,500.00
XII PEKEJAAN SALURAN AIR HUJAN
1 Pemasangan Saluran Air Hujan Kell. Bangunan 60.00 m 42,500.00 2,550,000.00

Rp. 1,178,856,242.15
Dibulatkan Rp. 1,178,856,000.00
Terbilang : (Satu Miliar Seratus Tujuh Puluh Delapan Juta Delapan Ratus Lima Puluh Enam Ribu Rupiah ).

Tasikmalaya, 18 Maret 2019


REKAPITULASI ANGGARAN BIAYA
PEMBANGUNAN MESJID AL IKHLAS
KAMULYAN MANONJAYA KAB. TASIKMALAYA

NO PEKERJAAN
I PEKERJAAN PERSIAPAN Rp 9,916,875.00
II PEKERJAAN TANAH Rp 12,426,086.90
III PEKERJAAN PONDASI Rp 23,600,596.47
IV PEKERJAAN STRUKTUR BETON Rp 800,585,240.98
V PEKERJAAN DINDING Rp 106,228,131.34
VI PEKERJAAN LANTAI Rp 81,955,170.52
VII PEKERJAAN KAYU KUSEN PINTU & JENDELA Rp 30,722,759.57
VIII PEKERJAAN PLAFON Rp 47,281,720.00
IX PEKERJAAN PENGGANTUNG KUNCI DAN KACA Rp 17,020,648.11
X PEKERJAAN PENGECATAN & LABURAN Rp 40,246,513.27
XI PEKERJAAN INSTALASI LISTRIK Rp 6,322,500.00
XII PEKERJAAN INSTALASI AIR HUJAN Rp 2,550,000.00
TOTAL Rp 1,178,856,242.15

Terbilang : (Satu Miliar Seratus Tujuh Puluh Delapan Juta Delapan Ratus Lima Puluh Enam Ribu Rupiah ).