Anda di halaman 1dari 432

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR

HARGA
NO. PERALATAN SATUAN MINIMUM
(Rp)

1 Dump Truck 3 ton jam 140,000


2 Dump Truck 5 ton jam 165,000
3 Truk Bak Terbuka Jam 110,000
4 Truk Tanki Air Jam 110,000
5 Bulldozer Jam 180,000
6 Motor Grader Jam 225,000
7 Wheel Loader Jam 200,000
8 Excavator Jam 200,000
9 Crane 30 ton hari 6,500,000
10 Flat Bed Truck jam 80,000
11 Baby Roller / Pedestrian Jam 100,000
12 P.Tire Roller 8 - 10 ton Jam 70,000
13 Baby Roller jam 150,000
14 Vibrator Roller self 7 ton Jam 50,000
15 Vibrator Roller Ped 1 ton jam 87,500
16 Water Pump 30m3/hari Jam 30,000
17 Asphalt Sprayer Jam 30,000
18 Pick Up hari 250,000
19 AM P Jam 60,000
20 Asphalt Finisher Jam 85,000
21 Concrete Vibrator Jam 30,000
22 Compressor Jam 30,000
23 Concrete Mixer 0,125m3 Jam 30,000
24 Concrete Mixer 0,5m3 jam 40,000
25 Stamper Jam 25,000
26 Genset Jam 30,000
27 Alat Pengecat Marka Jam 45,000
28 Mesin Las jam 45,000
29 Stone Crusher jam 60,000
AFTAR SEWA P E R A L A T AN

KOTA SEMARANG & SEKITAR


-

HARGA
MAKSIMUM KET.
(Rp)

150,000
180,000
125,000
120,000
200,000
250,000
225,000
220,000
7,000,000
100,000
120,000
100,000
175,000
60,000
90,000
35,000
40,000
300,000
70,000
90,000
40,000
40,000
40,000
50,000
30,000
30,000
55,000
55,000
70,000
DAFTAR UPAH PEKERJA
PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang

HARGA
NO. URAIAN PEKERJA SATUAN KET.
(Rp)

1 Pekerja Hr 57,000

2 Mandor Hr 78,000

3 Tukang listrik Hr 84,000

4 Tukang kayu Hr 84,000

5 Kep. tk. kayu Hr 87,000

6 Tukang batu Hr 84,000

7 Kep. tk. batu Hr 87,000

8 Tukang besi Hr 78,000

9 Kep. tk. besi Hr 87,000

10 T u k a n g c a t Hr 82,000

11 K e p . t k . c a t Hr 82,000

12 T u k a n g p l i t u r Hr 82,000

13 T u k a n g j a l a n Hr 61,000

14 T u k a n g g a l i Hr 64,000

15 Tukang masak aspal Hr 57,000

16 T k . l e i d e n g Hr 76,000

17 M a s i n i s Hr 162,000

18 P e m b . M a s i n i s Hr 102,000

19 P e n j a g a a p i Hr 57,000

20 P e n j a g a m a l a m Hr 58,000

21 Sopir Hr 162,000

22 Pembantu Sopir Hr 102,000

414275883.xlsx 432 daftar upah tenaga kerja


DAFTAR HARGA SATUAN BAHAN BANGUNAN

PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT


Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang

HARGA
NO. J E N I S B A H A N SAT
(Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 167,000
Bulat Belah m3 177,000
Pecah 10/15 m3 198,000
Pecah 5/7 m3 215,000
Pecah 3/5 m3 235,000
2 KERIKIL Timbun m3 122,000
Sawur / Koral m3 235,000
Beton 0,5/1 m3 252,000
Beton ,1/2 m3 280,000
Beton ,2/3 m3 270,000
Biasa m3 127,000
Tras Giling m3 220,000
3 BATU BATA ex lokal bh 520

4 PASIR Urug m3 130,000


Pasang m3 210,000
Beton m3 280,000
5 TANAH Padas m3 105,000
Liat m3 112,000
6 KAPUR Pasang m3 270,000
Semen Merah m3 177,000
7 PORTLAND CEMENT
Holcim 40 kg zak 53,000
Holcim 50 kg zak 68,000
Cibinong 40 kg zak 55,000
Cibinong 50 kg zak 69,000
Semen Putih 40 kg zak 67,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Semen Putih 50 kg zak 92,000


Semen warna kg 9,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 187,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000


Genteng Beton Warna Special bh 9,500
Genteng Beton Warna Khusus bh 14,500
Kerpus Beton Warna Standard bh 9,000
Kerpus Beton Warna Special bh 11,500
Kerpus Beton Warna Khusus bh 13,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

3 GENTENG TANAH LIAT


Vlaam bh 1,700
Kodok bh 1,800
Kodok Glasur bh 4,100
Nok kerpus Kodok bh 6,600
Nok kerpus Kodok Glasur bh 8,200
Plentong super besar 18 bh/m2 bh 5,200
Nok kerpus plentong super bh 9,000
4 GENTENG KACA
Vlaam tebal 2 mm bh 11,000
Vlaam tebal 3 mm bh 13,000
Kodok tebal 2 mm bh 11,000
Kodok tebal 3 mm bh 14,000

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 82,000
. 225 cm X 102 cm X 5 mm bh 95,000
. 250 cm X 102 cm X 5 mm bh 97,000
. 200 cm X 102 cm X 6 mm bh 85,000
. 225 cm X 102 cm X 6 mm bh 92,000
. 250 cm X 102 cm X 6 mm bh 106,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 43,000
. 180 cm X 105 cm X 4 mm bh 52,000
. 210 cm X 105 cm X 4 mm bh 62,000
. 240 cm X 105 cm X 4 mm bh 69,000
. 270 cm X 105 cm X 4 mm bh 80,000
. 300 cm X 105 cm X 4 mm bh 87,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 140,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 75,000
NOK Jabes nok
. Kerpus Genteng bh 30,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

. Stel Besar bh 47,000


. Paten Besar bh 44,000
Nokstel gelombang harflex
. Stel Besar bh 45,000
. Patent Besar bh 28,000
. Plat besar bh 52,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 100,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 16,000
. 100cm X 100 cm X 4 mm bh 18,000
. 50 cm X 200 cm X 3 mm bh 14,000
. 40 cm X 200 cm X 3 mm bh 13,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000


unt Plafond uk. 120cm x 240cm x 4mm lbr 66,000
uk. 122cm x 244cm x 4mm lbr 68,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000
uk.122cm x 244cm x 6mm lbr 125,000
uk.122cm x 244cm x 8mm lbr 185,000
uk.122cm x 244cm x 10mm lbr 245,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 50,000
200 X 92 cm bh 60,000
250 X 92 cm bh 65,000
180 X 105 cm bh 75,000
210 X 105 cm bh 75,000
250 X 105 cm bh 100,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 15,000
BJLS 0,20 lebar 55 cm m' 26,000
BJLS 0,28 lebar 55 cm m' 26,000
BJLS 0,30 lebar 55 cm m' 28,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 47,000
BJLS 0,20 panjang 180 cm lbr 50,000
BJLS 0,30 panjang 180 cm lbr 55,000
BJLS 0,40 panjang 180 cm lbr 73,000
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000
Balok/pesagen m3 20,000,000
2 KAMPER Papan m3 7,600,000
Balok/pesagen m3 7,000,000
3 KRUING Papan m3 6,000,000
Balok/pesagen m3 5,500,000
4 MERANTI Papan m3 4,900,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Balok/pesagen m3 4,500,000
5 LANAN Papan m3 2,100,000
Balok/pesagen m3 2,000,000
6 BENGKIRAI Papan m3 9,800,000
Balok/pesagen m3 9,500,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 18,000
Kecil 6 x 7 x 400 cm bt 16,000
Besar 10 x 12 x 400 cm bt 29,000
Kayu cetakan m3 1,900,000
Kayu bakar m3 155,000
Bambu bt 10,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

IV . BAHAN PENUTUP DINDING / LANTAI


1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 34,000
20 X 20 cm m2 32,000
PC warna 30 X 30 cm m2 45,000
20 X 20 cm m2 40,000
Teraso 30 X 30 cm m2 53,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,300
PC abu-abu 15 x 20 bh 5,200

3 POLIS UBIN Lantai/badan m'


Plint m'
Trap m'

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,500
11 X 11 warna dos 46,000
Lokal 15 X 15 putih dos 47,000
15 X 15 warna dos 49,000
5 MOZAIK PORSELIN
10 X 20 cm m2 49,000
15 X 15 cm m2 50,000
20 X 20 cm m2 50,000
20 X 25 cm m2 53,000

6 Keramik 30 X 30 cm m2 53,000
20 X 20 cm m2 54,000
33 x 33 cm m2 53,000
25 x 25 cm m2 52,000
15 x 20 cm m2 53,000
2,250
HARGA
NO. J E N I S B A H A N SAT
(Rp)

7 Parquet Jati m2 200,000


8 Batu Paros m2 95,000
9 Batu Tempel Hitam m2 98,000
10 GRANITO 40 x 40 cm m2 230,000
30 x 30 cm m2 270,000
11 Marmer m2 475,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 30,000
Ø 20 cm - 100 cm bh 35,000
Ø 30 cm - 100 cm bh 42,500
Ø 50 cm - 100 cm bh 80,000
Ø 60 cm - 100 cm bh 105,000
Ø 70 cm - 100 cm bh 130,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

U 10 cm - 100 cm bh 21,000
U 15 cm - 100 cm bh 27,000
U 20 cm - 100 cm bh 35,000
U 30 cm - 100 cm bh 40,000
U 50 cm - 100 cm bh
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 5,700
20 X 20 cm bh 6,500
25 X 25 cm bh 7,000
30 X 30 cm bh 7,500
15 X 25 cm bh 7,500
15 X 30 cm bh 7,700
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,000
besi beton prestress kg 16,500
besi beton ulir kg 12,500

2 BESI PLAT Besi Strip kg 12,500

3 BESI PROFIL Besi Profil kg 13,000


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 125,000
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 85,000
lebar : 7,5cm tebal : 0,65mm btg 80,000
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 45,000
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 40,000
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,4mm btg 25,000
tinggi 4 cm; tebal : 0,4 mm btg 30,000
4 JARING - JARING BAJA
Diameter 4 - 15 kg 15,000
Diameter 6 - 15 kg 15,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Kawat Bronjong kg 9,500


5 BESI SIKU L 40 X 40 X 4 btg 135,000
L 50 X 50 X 5 btg 210,000
L 60 X 60 X 6 btg 300,000

6 KAWAT - Ikat beton/bendrat kg 15,000


- Harmonika 12 X 45 mm m2 22,000
- Harmonika 12 X 24 mm m2 22,000
- Harmonika 14 X 30 mm m2 23,000
- Harmonika 14 X 35 mm m2 20,000
- Kawat Nyamuk Nylon m2 9,000
- Kawat Kasa m2 14,000
- Saringan pasir m2 14,000
- Kawat loket m2 15,000
- Kawat duri rol 115,000
- Kawat bronjong kg 20,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 27,000
Pipa PVC DN 25 ( ¾" ) AW JIS btg 33,000
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000
Pipa PVC DN 40 ( 1½" ) btg 65,000
Pipa PVC DN 63 ( 2" ) btg 110,000
Pipa PVC DN 90 ( 3" ) btg 200,000
Pipa PVC DN 110 ( 4" ) btg 300,000
Pipa PVC DN 160 ( 6" ) btg 625,000
Pipa PVC DN 200 ( 8" ) btg 1,000,000
Pipa PVC DN 250 ( 10" ) btg 1,400,000
Pipa PVC DN 315 ( 12" ) btg 2,050,000

3 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN ½" btg 67,000
Pipa Medium B Galvanis DN 25 ( ¾" ) btg 80,000
Pipa Medium B Galvanis DN 32 ( 1" ) btg 97,000
Pipa Medium B Galvanis DN 50 ( 1½" ) btg 140,000
Pipa Medium B Galvanis DN 63 ( 2" ) btg 170,000
Pipa Medium B Galvanis DN 2½" btg 250,000
Pipa Medium B Galvanis DN 90 ( 3" ) btg 470,000
Pipa Medium B Galvanis DN 110 ( 4" ) btg 560,000
Pipa Medium B Galvanis DN 160 ( 6" ) btg -
Pipa Medium B Galvanis DN 200 ( 8" ) btg -
Pipa Medium B Galvanis DN 250 ( 10") btg -

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,600
30 X 60 lbr 13,500
60 X 120 lbr 41,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

List Kayu Profil m' 4,800


2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 65,500
3 HARD BOARD-uk: 4'X 8' lbr 69,000
GYPROC uk.120cmx240cmx9mm lbr 57,500
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 52,000
. 120 X 240 X 3 mm lbr 87,000
. 90 X 210 X 4 mm lbr 66,000
. 90 X 210 X 9 mm lbr 117,000
. 90 X 210 X 12 mm lbr 165,000
. 90 X 210 X 15 mm lbr 230,000
. 90 X 210 X 18 mm lbr 300,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Tripleks
. 120 X 240 X 3 mm lbr 53,000
. 120 X 240 X 4 mm lbr 63,000
. 120 X 240 X 6 mm lbr 76,000
Multipleks
. 120 X 240 X 9 mm lbr 115,000
. 120 X 240 X 12 mm lbr 147,000
. 120 X 240 X 15 mm lbr 192,000
. 120 X 240 X 18 mm lbr 215,000
Formika ukuran pintu lbr 70,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 28,000
Dempul plamur kg 28,000
Ambril/amplas lbr 3,900
Batu Apung kg 29,000
Cat dasar kg 35,000
. Emco kg 52,000
. Yunior 66 (nippon paint) kg 52,000
- Koas bh 7,600
. Deculux kg 56,000
. Siralax ons 16,000
. Spiritus ltr 12,000
. Plitur jadi ltr 39,000

2 TEMBOK
Kalkarium kg 4,300
Kapur sirih kg 4,300
Plamur kg 21,000
Cat Tembok kg 20,000
Sintex 5 kg 100,000
Danabride 5 kg 102,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Catylac 5 kg 110,000
Mowilex 5 kg 280,000

3 BESI -
Menie kg 21,000
Cat mengkilat kg 56,000
Cat kg 37,000
Thinner A ltr 15,000
Minyak cat ltr 14,000
Thinner Super ltr 19,000
Residu (teer/aspal) drum 56,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 880,000
kapasitas 1100 liter. bh 1,655,000
Lem Aica Aibon kg 38,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

X.BAHAN KACA
1 POLOS 3 mm m2 61,000
5 mm m2 72,000
2 ES KABUR 3 mm m2 72,000
5 mm m2 81,000
3 RAY BAND 3 mm m2 71,000
5 mm m2 82,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
N YA : . 1 X 1 1/2 mm2 m' 3,100
SPLN LMK 1 X 2 1/2 mm2 m' 3,700
. 1X4 mm2 m' 5,800
1X6 mm2 m' 8,600
NYY :. 2 X 1 1/2 mm2 m' 9,250
PRIMA 2 X 2 1/2 mm2 m' 15,000
. 2X4 mm2 m' 27,000
2X6 mm2 m' 35,500
3 X 1 1/2 mm2 m' 13,200
3 X 2 1/2 mm2 m' 20,000
3X4 mm2 m' 34,500
3X6 mm2 m' 51,000
NYM :. 2 X 1 1/2 mm2 m' 7,000
PRIMA 2 X 2 1/2 mm2 m' 11,000
. 2X4 mm2 m' 21,500
3 X 1 1/2 mm2 m' 12,700
3 X 2 1/2 mm2 m' 19,500
3X4 mm2 m' 31,000
3X6 mm2 m' 44,000

2 SKAKELAR
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Out bauw . Seri bh 16,000


. Engkel bh 10,000
In bauw . Seri bh 14,000
. Engkel bh 11,000

3 FUSE BOX (SEKERING KASA)


1 group bh 120,000
2 group bh 225,000
3 group bh 340,000
-
4 STEKER - Biasa bh 11,000
Arde bh 15,500
T Biasa bh 12,500
T dengan Arde bh 17,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

5 FITING Flaon bh 9,000


Gantung bh 17,000
Kap bh 12,000
Kombinasi bh 315,000

6 STOP KONTAK - Arde Outbow putih bh 13,500


Arde Outbow hitam bh 5,500
Arde IB bh 13,000
Arde Putar bh 37,500

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 58,000
2 X slag bh 67,500
Yale : 1 X slag bh 88,000
2 X slag bh 150,000
Kuda : 1 X slag bh 58,000
2 X slag bh 73,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 15,500
Kupu-kupu biasa bh 4,500
Nylon kupu-kupu bh 8,000
Espagnoled - dalam negeri bh 42,500
Grendel Tanam luar negeri bh 9,000
Grendel biasa bh 16,000
Kait Angin bh 12,500
Door Stop bh 300,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,250,000
2 KLOSET JONGKOK bh 135,000
3 WASTAFEL PEDESTAL bh 1,100,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

4 WASTAFEL MEJA OVAL bh 870,000


5 WASTAFEL GANTUNG BULAT bh 380,000
6 WASTAFEL GANTUNG SUDUT bh 260,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 285,000
8 WASTAFEL BAK CUCI bh 165,000
9 TEMPAT SABUN GANTUNG bh 34,000
10 TEMPAT SABUN TANAM bh 23,000

11 SEPTIC TANK (ETERNIT GRESIK)


5 Pemakai 500 liter unit
10 Pemakai 1.000 liter unit -
HARGA
NO. J E N I S B A H A N SAT
(Rp)

12 LAIN - LAIN
Kran Air bh 28,000
Seal tape bh 4,000
Floor drain bh 18,000

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 14,000
2 PAKU - payung kg 26,000
3 PAKU - sekrup kg 7,500
4 PAKU - beton kg 28,000
5 MUR BAUT (kuda-kuda) kg 13,500
6 ANGKUR BAUT bh 13,500
7 LEM KAYU bh 19,500
8 Tali Ijuk kg 8,000

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 295,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 995,000
Fuji 250 watt bh 1,455,000
Shimizu . 100 watt bh 490,000
. 90 watt bh 375,000
Dab . 125 watt bh 390,000
. 175 watt bh 430,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 55,000
Merah/hitam m2 63,000
2 HOLLAND Abu-abu m2 58,000
Merah/hitam m2 65,000
3 UNIDECOR Abu-abu m2 50,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

Merah/hitam m2 63,000
4 UNI Abu-abu m2 63,000
Merah/hitam m2 67,000
5 TRIHEX Abu-abu m2 63,500
Merah/hitam m2 66,000
6 OLYMPIA HEXA Abu-abu m2 58,500
7 HEXAGONAL Abu-abu m2 65,000
Merah/hitam m2 57,500
8 CASTLE Abu-abu m2 64,000
9 TRAPEZ Abu-abu m2 58,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 62,000
11 STANDARD GRASS BLOCK ABU-ABU BH 8,000
12 BATACO BH 4,000
13 KANSTEEN m' 24,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

XVII. L A I N - L A I N
1 KREI 25 MM m2 48,000
2 Sliding Pintu J4 bh 210,000
3 Naco per Daun bh 12,500
4 Rolling door Besi m2 320,000
Rolling door Almunium m2 260,000
5 Awning Almunium m2 217,000
6 Kusen Almunium 4" Putih m' 83,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,548,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 1,690,000

Hotmix Tebal = 4 Cm m2 68,000


Hotmix Tebal = 5 Cm m2 83,000
Hotmix Tebal = 6 Cm m2 98,000
Hotmix Tebal = 7 Cm m2 115,000
Binder Course ton 1,325,000
Wearing Course ton 1,425,000
Hot Roller Sheet ton 1,200,000
Sand Sheet ton 1,550,000
Sand Sheet Emulsi ton 1,800,000
Cold Mix ton 1,820,000
Prime / Tack Coard RC liter 8,600
Prime Coat MC liter 8,500
Prime / Tack Coat Emulsi liter 8,600
10 K A C A
Cermin tebal 5 mm m2 265,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 185,000


Pagar BRC 120 A2 /lb 240,000
HARGA
NO. J E N I S B A H A N SAT
(Rp)

12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,700
Pintu Lipat Besi m2 410,000
Sunscreen Allumunim m2 335,000
Allumunium Foil m2 7,700
Soda api kg 12,500
Sabun kg 12,500
Air m3 18,000
Koas Alang-alang ikat 1,700
Solar (Industri) ltr 11,300
Premium (Industri) ltr 10,700
Pelumas ltr 42,500
Vynil 30x30 cm bh 6,400
UNAN

NGKAT

KET
KET
KET
KET
KET
KET
KET
KET
KET

panj : 6 m
panj : 6 m
panj : 6 m
panj : 6 m
panj : 6 m

panj : 4 m
panj : 4 m
KET
KET

panjang 4 m
panjang 4 m
panjang 4 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m

panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
KET
KET
KET
KET
KET
KET
KET
KET
KET
KET
KET
Perhitungan Human Resources

Mengambil Minggu ke 11 yang memiliki volume pekerjaan terbanyak dalam pelaksanaan proyek

Volume Volume/ Bobot Bobot/


No. Jenis Pekerjaan Durasi Satuan
Total Minggu Total Minggu
1 Air kerja dan listrik 20 ls 1.00 0.050 0.124 0.006
2 Administrasi dan Dokumentasi 20 ls 1.00 0.050 20.000 1.000
3 Pemasangan Dinding Bata Merah Uk
2 m2 280.00 140.000 1.675 0.838
(5x11x22)cm T 1/2 Bata Camp. 1pc : 6pp
4 Pemasangan Plesteran 1Pc : 3pp t=15 mm 1 m2 27.00 27.000 0.175 0.175
5 Pemasangan Plesteran 1Pc : 6pp t=15mm 2 m2 344.00 172.000 2.058 1.029
6 Pembuatan dan Pemasangan Kusen Pintu
2 m3 0.29 0.146 0.969 0.485
dan Jendela kelas I
7 Pelaburan Bidang Kayu dg Politur 2 m2 16.65 8.326 0.084 0.042
8 Pemasangan Dinding Bata Merah Uk
2 m2 260.00 130.000 1.556 0.778
(5x11x22)cm T 1/2 Bata Camp. 1pc : 6pp
9 Pemasangan Plesteran 1Pc : 6pp t=15mm 2 m2 290.25 145.125 1.273 0.636
10 Pembuatan dan Pemasangan Kusen Pintu
3 m3 0.82 0.274 2.734 0.911
dan Jendela kelas I
11 Membuat Kolom Beton Bertulang 2 m3 4.88 2.440 4.868 2.434
12 Pemasangan Pipa PVC tipe AW Ø ½" 1 m1 50 50 0.273 0.273396
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN BANGUNAN RUMAH TINGGAL
PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang

JENIS PEKERJAAN VOL. SAT. HARGA SAT.PEK JUMLAH


A. LANTAI 1
I PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 1.000 ls Rp 10,000,000 Rp 10,000,000
2 Pengukuran dan Pemasangan Bouwplank 70.000 m' Rp 136,004 Rp 9,520,280
3 Pembuatan Kantor Sementara dg Lantai Plesteran 9.000 m2 Rp 1,810,859 Rp 16,297,727
4 Pembuatan Gudang Semen dan Alat-alat 1.000 ls Rp 1,702,008 Rp 1,702,008
5 Membersihkan Lapangan dan Perataan 200.000 m2 Rp 10,560 Rp 2,112,000
6 Air kerja dan listrik 1.000 ls Rp 1,000,000 Rp 1,000,000
7 Papan Nama Proyek 1.000 ls Rp 300,000 Rp 300,000
8 Administrasi dan Dokumentasi 1.000 ls Rp 1,500,000 Rp 1,500,000
jumlah Rp 42,432,015
II PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 122.097 m3 Rp 49,170 Rp 6,003,509
2 Pengurugan Kembali 40.699 m3 Rp 49,170 Rp 2,001,170
3 Menggali Tanah Biasa Sedalam 2 m 44.064 m3 Rp 60,291 Rp 2,656,663
4 Pengurugan Kembali 14.688 m3 Rp 60,291 Rp 885,554
5 Urugan Pasir Bawah Pondasi 6.750 m3 Rp 191,268 Rp 1,291,059
6 Urugan Pasir Bawah Lantai lt 1 11.355 m3 Rp 191,268 Rp 2,171,848
jumlah Rp 15,009,803
III PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 42.590 m3 Rp 686,890 Rp 29,254,624
2 Pemasang Batu Kosong/Anstamping 18.360 m3 Rp 415,157 Rp 7,622,273
jumlah Rp 36,876,897
IV PEKERJAAN DINDING
Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata
1 Camp. 1SP : 3PP 20.250 m2 Rp 52,338 Rp 1,059,853

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata


2 Camp. 1SP : 6PP 280.000 m2 Rp 48,236 Rp 13,506,034

jumlah Rp 14,565,887
V PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 27.000 m2 Rp 52,338 Rp 1,413,137
2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 344.000 m2 Rp 48,236 Rp 16,593,128
3 Pemasangan Acian 371.000 m2 Rp 28,457 Rp 10,557,547
jumlah Rp 28,563,811
VI PEKERJAAN KUSEN KAYU
1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I 0.291 m3 Rp 26,851,000 Rp 7,814,285
2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 16.360 m3 Rp 708,373 Rp 11,588,974
jumlah Rp 19,403,260
VII PEKERJAAN BETON
1 Membuat Lantai Kerja Beton Mutu K(100) 0.450 m3 Rp 866,589 Rp 389,965
2 Membuat Beton Mutu K(250) 13.060 m3 Rp 4,659,540 Rp 60,851,722
3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 8.127 m3 Rp 3,769,209 Rp 30,632,836
4 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4.725 m3 Rp 4,608,610 Rp 21,775,680
5 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 9.805 m3 Rp 8,040,786 Rp 78,839,902
6 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 3.695 m3 Rp 6,321,926 Rp 23,359,515
7 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 1.643 m3 Rp 5,815,112 Rp 9,551,321
jumlah Rp 225,400,940
VIII PEKERJAAN LANGIT-LANGIT
1 Langit-langit Gypsum Board & Rangka Allumunium (Concealed) 51.100 m2 Rp 95,994 Rp 4,905,307
2 List Gypsum 113.000 m' Rp 20,485 Rp 2,314,805
jumlah Rp 7,220,112
IX PEKERJAAN SANITASI
1 Memasang Closet Duduk / Mono Blok 2.000 Unit Rp 1,779,874 Rp 3,559,747
2 Memasang Wastafel + Kran 1.000 Unit Rp 666,259 Rp 666,259
3 Pemasangan Floor Drain 2.000 bh Rp 31,053 Rp 62,106
4 Memasang Soap Holder 2.000 bh Rp 75,000 Rp 150,000
5 Memasang Paper Holder 1.000 bh Rp 80,000 Rp 80,000
6 Memasang Shower dan Kran 1.000 bh Rp 200,000 Rp 200,000
7 Memasang Kran Air 2.000 bh Rp 72,655 Rp 145,310
8 Memasang Pompa Air (Sanyo) 1.000 Unit Rp 995,000 Rp 995,000
jumlah Rp 5,858,422
X PEKERJAAN PLUMBING
1 Pemasangan Pipa PVC tipe AW Ø ½" 50.000 m' Rp 44,079 Rp 2,203,942
2 Pemasangan Pipa PVC tipe AW Ø 4" 50.000 m' Rp 44,079 Rp 2,203,942
3 Septictank + peresapan 1.000 Unit Rp 1,200,000 Rp 1,200,000
jumlah Rp 5,607,883
XI PEKERJAAN BESI DAN ALUMUNIUM
1 Memasang Railling Tangga 225.000 m' Rp 29,758 Rp 6,695,494
jumlah Rp 6,695,494
XII PEKERJAAN KUNCI DAN KACA
1 Memasang Kunci Tanam 4.000 bh Rp 176,152 Rp 704,606
2 Memasang Engsel Pintu dan Jendela 44.000 bh Rp 9,000 Rp 396,000
3 Pasang Kait Angin lt1 1.000 bh Rp 30,672 Rp 30,672
4 Pasang Grendel 27.000 bh Rp 3,000 Rp 81,000
5 Pasang Pull Handle 6.000 bh Rp 87,000 Rp 522,000
6 Pasang Handle Biasa 2.000 bh Rp 90,000 Rp 180,000
7 Pasang Kaca tebal 5 mm lt1 32.021 m2 Rp 90,110 Rp 2,885,424
jumlah Rp 4,799,702
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 100.500 m2 Rp 347,075 Rp 34,881,068
2 Pemasangan Lantai Keramik 20 x 20 cm 7.500 m2 Rp 57,815 Rp 433,615
3 Pemasangan Dinding Keramik 20 x 25cm 24.000 m2 Rp 200,654 Rp 4,815,703
4 Pemasangan dinding marmer 20x40 15.050 m2 Rp 350,000 Rp 5,267,500
jumlah Rp 45,397,886
XIV PEKERJAAN PENGECATAN
1 Pelaburan Bidang Kayu dg Politur 16.651 m2 Rp 40,814 Rp 679,602
2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 371.000 m2 Rp 17,286 Rp 6,412,924
3 Pengecatan Plafond 51.100 m2 Rp 17,286 Rp 883,290
jumlah Rp 7,975,815
XV PEKERJAAN INSTALASI LISTRIK
1 Lampu Spiral Kuning ( Teras ) 3.000 bh Rp 34,000 Rp 102,000
2 Lampu LED ( Dipasang Dalam Plafond ) 15.000 bh Rp 98,000 Rp 1,470,000
3 Saklar Tunggal 1.000 bh Rp 10,000 Rp 10,000
4 Saklar Ganda 7.000 bh Rp 16,000 Rp 112,000
5 Stop Kontak 4.000 bh Rp 13,500 Rp 54,000
6 Instalasi Titik Lampu 12.000 bh Rp 13,500 Rp 162,000
7 Kabel NYA 50.000 m1 Rp 3,700 Rp 185,000
jumlah Rp 2,095,000
B. LANTAI 2
XVI PEKERJAAN TANAH
1 Urugan pasir bawah lantai 2 10.883 m3 Rp 191,268 Rp 2,081,570
jumlah Rp 2,081,570
XVII PEKERJAAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata 20.250 m2 Rp 52,338 Rp 1,059,853
Camp. 1SP : 3PP
2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata 260.000 m2 Rp 48,236 Rp 12,541,317
Camp. 1SP : 6PP
jumlah Rp 13,601,170
XVIII PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 27.000 m2 Rp 48,236 Rp 1,302,368
2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 196.000 m2 Rp 52,338 Rp 10,258,326
3 Pemasangan Acian 409.000 m2 Rp 28,457 Rp 11,638,913
jumlah Rp 23,199,606
XIX PEKERJAAN KAYU
1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I m3
0.821 Rp 26,851,000 Rp 22,041,234
2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II m2
18.080 Rp 708,373 Rp 12,807,375
3 Pemasangan konstruksi Gording, Kayu Klas II m1
2.880 Rp 69,245 Rp 199,427
4 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II m2
169.000 Rp 183,986 Rp 31,093,634
5 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Klas I 0.87744 m3 Rp 29,190,920 Rp 25,613,281
6 Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II 36.900 m1 Rp 119,823 Rp 4,421,469
jumlah Rp 96,176,419
XX PEKERJAAN BETON
1 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 4.880 m3 Rp 8,040,786 Rp 39,239,033
2 Membuat Ring Balok Beton Bertulang 2.160 m3 Rp 6,321,926 Rp 13,655,359
jumlah Rp 52,894,392
XXI PEKERJAAN PENUTUP ATAP
1 Pemasangan Bubugan Genteng Beton 34.400 m1 Rp 93,291 Rp 3,209,210
2 Pemasangan Atap Genteng Beton 169.000 m2 Rp 104,606 Rp 17,678,346
3 Pemasangan Nok Genteng Beton 3.500 m1 Rp 106,159 Rp 371,556
4 Pasang Allumunium Foil / Sisalation 83.070 m2 Rp 24,083 Rp 2,000,608
jumlah Rp 23,259,721
XXII PEKERJAAN LANGIT-LANGIT
1 Langit-langit Gypsum Board & Rangka Allumunium (Concealed) 51.350 m2 Rp 95,994 Rp 4,929,306
4 List Gypsum 122.800 m1 Rp 20,485 Rp 2,515,558
jumlah Rp 7,444,864
XXIII PEKERJAAN SANITASI
1 Memasang Closet Duduk / Mono Blok 2.000 Unit Rp 1,779,874 Rp 3,559,747
2 Pemasangan Floor Drain 2.000 bh Rp 31,053 Rp 62,106
3 Memasang Soap Holder 2.000 bh Rp 80,000 Rp 160,000
5 Memasang Shower dan Kran 2.000 bh Rp 200,000 Rp 400,000
jumlah Rp 4,181,853
XXIV PEKERJAAN PLUMBING
1 Pemasangan Pipa PVC tipe AW Ø ½" 50.000 m' Rp 44,079 Rp 2,203,942
2 Pemasangan Pipa PVC tipe AW Ø 4" 60.000 m' Rp 44,079 Rp 2,644,730
3 Memasang rRoof Tank 1000 L 1.000 Unit Rp 1,600,000 Rp 1,600,000
jumlah Rp 6,448,672
XXV PEKERJAAN BESI DAN ALUMUNIUM
4 Pemasangan Ralling Balkon 5 x 5 10.000 m' Rp 112,641 Rp 1,126,410
6 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 27.200 m' Rp 172,717 Rp 4,697,889
jumlah Rp 5,824,299
XXVI PEKERJAAN KUNCI DAN KACA
1 Memasang Kunci Tanam 4.000 bh Rp 176,152 Rp 704,606
2 Memasang Engsel Pintu dan Jendela 27.000 bh Rp 9,000 Rp 243,000
3 Pasang Grendel 13.000 bh Rp 3,000 Rp 39,000
4 Pasang Pull Handle 2.000 bh Rp 87,000 Rp 174,000
5 Pasang Handle Biasa 5.000 bh Rp 90,000 Rp 450,000
6 Kaca tebal 3 mm 19.686 m2 Rp 90,110 Rp 1,773,912
jumlah Rp 3,384,518
XXVII PEKERJAAN PENUTUP LANTAI DAN DINDING LT2
1 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 76.500 m2 Rp 347,075 Rp 26,551,260
3 Pemasangan Lantai Keramik 20 x 20 cm 7.500 m2 Rp 57,815 Rp 433,615
4 Pemasangan Dinding Keramik 20 x 25cm 24.000 m2 Rp 200,654 Rp 4,815,703
5 Pemasangan dinding marmer 20x40 22.000 m2 Rp 350,000 Rp 7,700,000
jumlah Rp 39,500,579
XXVIII PEKERJAAN PENGECATAN LT2
1 Pelaburan Bidang Kayu dg Politur 18.901 m2 Rp 40,814 Rp 771,428
2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 409.000 m2 Rp 17,286 Rp 7,069,774
3 Pengecatan Plafond 51.350 m2 Rp 17,286 Rp 887,611
jumlah Rp 8,728,812
XXIX PEKERJAAN INSTALASI LISTRIK LT2
1 Lampu LED ( Dipasang Dalam Plafond ) 10.000 bh Rp 34,000 Rp 340,000
2 Lampu spiral kuning ( teras ) 1.000 bh Rp 98,000 Rp 98,000
3 Saklar Tunggal 3.000 bh Rp 10,000 Rp 30,000
4 Saklar Ganda 4.000 bh Rp 16,000 Rp 64,000
5 Stop Kontak 4.000 bh Rp 13,500 Rp 54,000
6 Instalasi Titik Lampu 11.000 bh Rp 13,500 Rp 148,500
7 Kabel NYA 50.000 m' Rp 3,700 Rp 185,000
jumlah Rp 919,500
XXX PEKERJAAN LAIN-LAIN
1 Penangkal Petir 2.000 ls Rp 250,000 Rp 500,000
2 Penyambungan daya ke PLN 2200 VA 1.000 ls Rp 1,000,000 Rp 1,000,000
3 Landscape 1.000 ls Rp 50,000,000 Rp 50,000,000
jumlah Rp 51,500,000
TOTAL Rp807,048,901
JUMLAH

Rp 10,000,000
Rp 9,520,280
Rp 16,297,727
Rp 1,702,008
Rp 2,112,000
Rp 1,000,000
Rp 300,000
Rp 1,500,000
Rp 42,432,015

Rp 6,003,509
Rp 2,001,170
Rp 2,656,663
Rp 885,554
Rp 1,291,059
Rp 2,171,848
Rp 15,009,803

Rp 29,254,624
Rp 7,622,273
Rp 36,876,897

Rp 1,059,853

Rp 13,506,034

Rp 14,565,887

Rp 1,413,137
Rp 16,593,128
Rp 10,557,547
Rp 28,563,811

Rp 7,814,285
Rp 11,588,974
Rp 19,403,260

Rp 389,965
Rp 60,851,722
Rp 30,632,836
Rp 21,775,680
Rp 78,839,902
Rp 23,359,515
Rp 9,551,321
Rp 225,400,940
Rp 4,905,307
Rp 2,314,805
Rp 7,220,112

Rp 3,559,747
Rp 666,259
Rp 62,106
Rp 150,000
Rp 80,000
Rp 200,000
Rp 145,310
Rp 995,000
Rp 5,858,422

Rp 2,203,942
Rp 2,203,942
Rp 1,200,000
Rp 5,607,883

Rp 6,695,494
Rp 6,695,494

Rp 704,606
Rp 396,000
Rp 30,672
Rp 81,000
Rp 522,000
Rp 180,000
Rp 2,885,424
Rp 4,799,702

Rp 34,881,068
Rp 433,615
Rp 4,815,703
Rp 5,267,500
Rp 45,397,886

Rp 679,602
Rp 6,412,924
Rp 883,290
Rp 7,975,815

Rp 102,000
Rp 1,470,000
Rp 10,000
Rp 112,000
Rp 54,000
Rp 162,000
Rp 185,000
Rp 2,095,000
Rp 2,081,570
Rp 2,081,570

Rp 1,059,853

Rp 12,541,317

Rp 13,601,170

Rp 1,302,368
Rp 10,258,326
Rp 11,638,913
Rp 23,199,606

Rp 22,041,234
Rp 12,807,375
Rp 199,427
Rp 31,093,634
Rp 25,613,281
Rp 4,421,469
Rp 96,176,419

Rp 39,239,033
Rp 13,655,359
Rp 52,894,392

Rp 3,209,210
Rp 17,678,346
Rp 371,556
Rp 2,000,608
Rp 23,259,721

Rp 4,929,306
Rp 2,515,558
Rp 7,444,864

Rp 3,559,747
Rp 62,106
Rp 160,000
Rp 400,000
Rp 4,181,853

Rp 2,203,942
Rp 2,644,730
Rp 1,600,000
Rp 6,448,672

Rp 1,126,410
Rp 4,697,889
Rp 5,824,299
Rp 704,606
Rp 243,000
Rp 39,000
Rp 174,000
Rp 450,000
Rp 1,773,912
Rp 3,384,518

Rp 26,551,260
Rp 433,615
Rp 4,815,703
Rp 7,700,000
Rp 39,500,579

Rp 771,428
Rp 7,069,774
Rp 887,611
Rp 8,728,812

Rp 340,000
Rp 98,000
Rp 30,000
Rp 64,000
Rp 54,000
Rp 148,500
Rp 185,000
Rp 919,500

Rp 500,000
Rp 1,000,000
Rp 50,000,000
Rp 51,500,000
Rp807,048,901
REKAPITULASI
KEGIATAN : PEMBANGUNAN BANGUNAN RUMAH TINGGAL
PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang

NO JENIS PEKERJAAN HARGA


A. LANTAI 1
I PEKERJAAN PERSIAPAN Rp 42,432,015
II PEKERJAAN TANAH Rp 15,009,803
III PEKERJAAN PONDASI Rp 36,876,897
IV PEKERJAAN DINDING Rp 14,565,887
V PEKERJAAN PLESTERAN Rp 28,563,811
VI PEKERJAAN KUSEN KAYU Rp 19,403,260
VII PEKERJAAN BETON Rp 225,400,940
VIII PEKERJAAN LANGIT-LANGIT Rp 7,220,112
IX PEKERJAAN SANITASI Rp 5,858,422
X PEKERJAAN PLUMBING Rp 5,607,883
XI PEKERJAAN BESI DAN ALUMUNIUM Rp 6,695,494
XII PEKERJAAN KUNCI DAN KACA Rp 4,799,702
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 45,397,886
XIV PEKERJAAN PENGECATAN Rp 7,975,815
XV PEKERJAAN INSTALASI LISTRIK Rp 2,095,000
JUMLAH Rp 467,902,927
B. LANTAI 2
XVI PEKERJAAN TANAH Rp 2,081,570
XVII PEKERJAAN DINDING Rp 13,601,170
XVIII PEKERJAAN PLESTERAN Rp 23,199,606
XIX PEKERJAAN KAYU Rp 96,176,419
XX PEKERJAAN BETON Rp 52,894,392
XXI PEKERJAAN PENUTUP ATAP Rp 23,259,721
XXII PEKERJAAN LANGIT-LANGIT Rp 7,444,864
XXIII PEKERJAAN SANITASI Rp 4,181,853
XXIV PEKERJAAN PLUMBING Rp 6,448,672
XXV PEKERJAAN BESI DAN ALUMUNIUM Rp 5,824,299
XXV PEKERJAAN KUNCI DAN KACA Rp 3,384,518
XXVII PEKERJAAN PENUTUP LANTAI DAN DINDING LT2 Rp 39,500,579
XXVIII
PEKERJAAN PENGECATAN LT2 Rp 8,728,812
XXIX PEKERJAAN INSTALASI LISTRIK LT2 Rp 919,500
XXX PEKERJAAN LAIN-LAIN Rp 51,500,000
JUMLAH Rp 339,145,974
JUMLAH TOTAL Rp 807,048,901

+ PPN 10% Rp 80,704,890.14


JUMLAH TOTAL Rp 887,753,791.55
DIBULATKAN RP Rp 887,750,000.00
TERBILANG: Delapan Ratus Delapan Puluh Tujuh Juta Tujuh Ratus Lima Puluh Ribu Rupiah

Semarang, Oktober 2015


Perencana
Muhammad Nur Azzam
BILL OF QUANTITY
KEGIATAN : PEMBANGUNAN BANGUNAN RUMAH & TOKO
PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang

NO KODE JENIS PEKERJAAN SATUAN VOLUME


A. LANTAI 1
I PEKERJAAN PERSIAPAN
1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m m' 30.000
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 70.000
3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 9.000
4 A.2.2.1.7 Pembuatan Gudang Semen dan Alat-alat ls 1.000
5 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 200.000
6 Taksir Air kerja dan listrik ls 1.000
7 Taksir Papan Nama Proyek ls 1.000

II PEKERJAAN TANAH
1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 122.097
2 A.2.3.1.9 Pengurugan Kembali m3 40.699
3 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 44.064
4 A.2.3.1.9 Pengurugan Kembali m3 14.688
5 A.2.3.1.11 Urugan Pasir Bawah Pondasi m3 6.750
6 A.2.3.1.11 Urugan Pasir Bawah Lantai lt 1 m3 11.355

III PEKERJAAN PONDASI


1 A.3.2.1.7 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP m3 42.590
2 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 18.360

IV PEKERJAAN DINDING
1 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : m2 20.250
3PP
2 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : m2 280.000
6PP

V PEKERJAAN PLESTERAN
1 A,4,4,2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 27.000
2 A,4,4,2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 344.000
3 A,4,4,2.27 Pemasangan Acian m2 371.000

VI PEKERJAAN KUSEN KAYU


1 A.4.6.1.1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I m3 0.291
2 A.4.6.1.5 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II m3 16.360

VII PEKERJAAN BETON


1 A.4.1.1.4 Membuat Lantai Kerja Beton Mutu K(100) m3 0.450
2 A.4.1.1.6 Membuat Beton Mutu K(250) m3 13.060
3 A.4.1.1.28 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) m3 8.127
4 A.4.1.1.29 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) m3 4.725
5 A.4.1.1.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 9.805
6 A.4.1.1.31 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) m3 3.695
7 A.4.1.1.34 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) m3 1.643
VIII PEKERJAAN LANGIT-LANGIT
1 Hitung Langit-langit Gypsum Board & Rangka Allumunium (Concealed) m2 51.100
2 Hitung List Gypsum m' 113.000

IX PEKERJAAN SANITASI
1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok Unit 2
2 A.5.1.1.5 Memasang Wastafel + Kran Unit 1
3 A.5.1.1.14 Pemasangan Floor Drain bh 2
4 Hitung Memasang Soap Holder bh 2
5 Hitung Memasang Paper Holder bh 1
6 Hitung Memasang Shower dan Kran bh 1
7 A.5.1.1.19 Memasang Kran Air bh 2
8 Hitung Memasang Pompa Air (Sanyo) Unit 1

X PEKERJAAN PLUMBING
1 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø ½" m' 50.000
2 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 4" m' 50.000
3 Hitung Septictank + peresapan Unit 1

XI PEKERJAAN BESI DAN ALUMUNIUM


1 Hitung Memasang Railling Tangga m' 225.000

XII PEKERJAAN KUNCI DAN KACA


1 A.4.6.2.2 Memasang Kunci Tanam bh 4
2 A.4.6.2.5 Memasang Engsel Pintu dan Jendela bh 44
3 A.4.6.2.9 Pasang Kait Angin lt1 bh 1
4 Hitung Pasang Grendel bh 27
5 Hitung Pasang Pull Handle bh 6
6 Hitung Pasang Handle Biasa bh 2
7 A.4.6.2.16 Pasang Kaca tebal 5 mm lt1 m2 32.021

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING


1 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 100.500
2 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 7.500
3 A.4.4.3.50 Pemasangan Dinding Keramik 20 x 25cm m2 24.000
4 Hitung Pemasangan dinding marmer 20x40 m2 15.050

XIV PEKERJAAN PENGECATAN


1 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 16.651
2 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar m2 371.000
3 A.4.7.1.10 Pengecatan Plafond m2 51.100

XV PEKERJAAN INSTALASI LISTRIK


1 Hitung Lampu Spiral Kuning ( Teras ) bh 3
2 Hitung Lampu LED ( Dipasang Dalam Plafond ) bh 15
3 Hitung Saklar Tunggal bh 1
4 Hitung Saklar Ganda bh 7
5 Hitung Stop Kontak bh 4
6 Hitung Instalasi Titik Lampu bh 12
7 Hitung Kabel NYA m1 50
B. LANTAI 2
XVI PEKERJAAN TANAH
1 A.2.3.1.11 Urugan pasir bawah lantai 2 m3 10.883

XVII PEKERJAAN DINDING


1 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP :
3PP m2 20.250
2 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP :
6PP m2 260.000

XVIII PEKERJAAN PLESTERAN


1 A,4,4,2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 27.000
2 A,4,4,2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 196.000
3 A,4,4,2.27 Pemasangan Acian m2 409.000

XIX PEKERJAAN KAYU


1 A.4.6.1.1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I m3 0.821
2 A.4.6.1.5 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II m2 18.080
3 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m1 2.880
4 A.4.6.1.17 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II m2 169.000
5 A.4.6.1.14 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Klas I m3 0.877
6 A.4.6.1.22 Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II m1 36.900

XX PEKERJAAN BETON
1 A.4.1.1.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 4.880
2 A.4.1.1.31 Membuat Ring Balok Beton Bertulang m3 2.160

XXI PEKERJAAN PENUTUP ATAP


1 A.4.5.2.6 Pemasangan Bubugan Genteng Beton m1 34.400
2 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 169.000
3 A.4.5.2.34 Pemasangan Nok Genteng Beton m1 3.500
4 A.4.5.2.42 Pasang Allumunium Foil / Sisalation m2 83.070

XXII PEKERJAAN LANGIT-LANGIT


1 Hitung Langit-langit Gypsum Board & Rangka Allumunium (Concealed) m2 51.350
4 Hitung List Gypsum m1 122.800

XXIII PEKERJAAN SANITASI


1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok Unit 2.000
2 A.5.1.1.14 Pemasangan Floor Drain bh 2.000
3 Hitung Memasang Soap Holder bh 2.000
5 Hitung Memasang Shower dan Kran bh 2.000

XXIV PEKERJAAN PLUMBING


1 A.4.7.1.12 Pemasangan Pipa PVC tipe AW Ø ½" m' 50.000
2 A.4.7.1.13 Pemasangan Pipa PVC tipe AW Ø 4" m' 60.000
3 Hitung Memasang Roof Tank Unit 1.000

XXV PEKERJAAN BESI DAN ALUMUNIUM


4 A.4.2.1.11 Pemasangan Ralling Balkon 5 x 5 m' 10.000
6 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm m' 27.200
XXVI PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.2 Memasang Kunci Tanam bh 4.000
2 A.4.6.2.5 Memasang Engsel Pintu dan Jendela bh 27.000
3 Hitung Pasang Grendel bh 13.000
4 Hitung Pasang Pull Handle bh 2.000
5 Hitung Pasang Handle Biasa bh 5.000
6 A.4.6.2.16 Kaca tebal 3 mm m2 19.686

XXVII PEKERJAAN PENUTUP LANTAI DAN DINDING LT2


1 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 76.500
2 A.4.4.3.36 Pemasangan lantai teras Uk. 40 x 40 cm m2 10.500
3 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 7.500
4 A.4.4.3.50 Pemasangan Dinding Keramik 20 x 25cm m2 24.000
5 Hitung Pemasangan dinding marmer 20x40 m2 22.000

XXVIII PEKERJAAN PENGECATAN LT2


1 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 18.901
2 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar m2 409.000
3 A.4.7.1.10 Pengecatan Plafond m2 51.350

XXIX PEKERJAAN INSTALASI LISTRIK LT2


1 Hitung Lampu LED ( Dipasang Dalam Plafond ) bh 10.000
2 Hitung Lampu spiral kuning ( teras ) bh 1.000
3 Hitung Saklar Tunggal bh 3.000
4 Hitung Saklar Ganda bh 4.000
5 Hitung Stop Kontak bh 4.000
6 Hitung Instalasi Titik Lampu bh 11.000
7 Hitung Kabel NYA m' 50.000

XXX PEKERJAAN LAIN-LAIN


1 Taksir Penangkal Petir ls 2.000
2 Taksir Penyambungan daya ke PLN 2200 VA ls 1.000
3 Taksir Landscape ls 1.000
VOLUME

30.000
70.000
9.000
1.000
200.000
1.000
1.000

122.097
40.699
44.064
14.688
6.750
11.355

42.590
18.360

20.250

280.000

27.000
344.000
371.000

0.291
16.360

0.450
13.060
8.127
4.725
9.805
3.695
1.643
51.100
113.000

2
1
2
2
1
1
2
1

50.000
50.000
1

225.000

4
44
1
27
6
2
32.021

100.500
7.500
24.000
15.050

16.651
371.000
51.100

3
15
1
7
4
12
50
10.883

20.250

260.000

27.000
196.000
409.000

0.821
18.080
2.880
169.000
0.877
36.900

4.880
2.160

34.400
169.000
3.500
83.070

51.350
122.800

2.000
2.000
2.000
2.000

50.000
60.000
1.000

10.000
27.200
4.000
27.000
13.000
2.000
5.000
19.686

76.500
10.500
7.500
24.000
22.000

18.901
409.000
51.350

10.000
1.000
3.000
4.000
4.000
11.000
50.000

2.000
1.000
1.000
PERHITUNGAN VOLUME PEKERJAAN

NO GAMBAR PERHITUNGAN
LANTAI 1
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan
Volume = Luas area
= 10 x 20
= 200 m2

2 Pemasangan pagar sementara Volume = Keliling area


= 30 m1

3 Pemasangan Bouwplank Volume = 35.000 x 2


= 70 m1

II PEKERJAAN TANAH
1 Galian Tanah Untuk Pondasi

Volume = 1.44 + 1
2
= 90.585 m3

Volume = 0.9 + 1.12


2
= 29.997 m3

Volume = p x l x
= 5.05 x 0.6
= 1.515 m3

Total = 90.585 + 29.997


= 122.097 m3

2 Galian Tanah Untuk Footplat


Volume = p x l x
= 1.2 x 1.2
= 44.064 m3

3 Urugan Tanah Kembali Untuk Pondasi


Volume = 122.097 /
= 40.699 m3
4 Urugan Tanah Kembali Untuk footplat
Volume = 44.064 /
= 14.688 m3

5 Urugan Pasir Bawah Pondasi


Volume = 1 x 0.1
= 6.75 m3

Volume = 0.9 x 0.1


= 2.43 m3

Volume = 0.6 x 0.1


= 0.303 m3

Total = 6.75 + 2.43


= 9.48 m3

6 Urugan Pasir Bawah Footplat


Volume = 1.2 x 1.2
= 0.45 m3

7 Urugan Pasir Bawah Lantai


Volume = Lbangunan x
= 113.55 x
= 11.355 m3

8 Urugan Pasir Carport


Volume = Lcarport x
= 92.0 x
= 9.2 m3
III PEKERJAAN PONDASI
1 Pekerjaan pondasi batu kosong ( Aanstamping)
Volume = 1.0 x 0.2
= 13.5 m3

Volume = 0.9 x 0.2


= 4.86 m3

Total = 13.5 + 4.86


= 18.36 m3
2 Pekerjaan pondasi batu belah

Volume = 0.8 + 0.3


2
= 29.7 m3

Volume = 0.8 + 0.3


2
= 11.88 m3

Volume = 0.4 x 0.5


= 1.01 m3

Total = 29.7 + 11.88


= 42.59 m3

IV PEKERJAAN BETON
1 Footplat
Volume = 0.25 + 1.2
2
x 1.2 x

= 3.77 m3

Volume = 0.25 + 1
2
x 1.2 x

= 2.82 m3

2 Pedestal
Volume = p x l x
= 0.25 x 0.25
= 1.541 m3

Total = 3.77 + 2.82


= 8.1 m3
3 Lantai Kerja
Volume = 1 x 0.05
= 0.45 m3

Volume = 1 x 0.05
= 0.4 m3

Total = 0.45 + 0.4


= 0.85 m3

5 Sloof
Sloof 20 x 25 Volume = b x h x
= 0.2 x 0.25
= 4.725 m3

6 Kolom
Kolom 25 x 25 Volume = p x l x
= 0.25 x 0.25
= 4.25 m3

Kolom 15 x 15 Volume = p x l x
= 0.15 x 0.15
= 0.54 m3
Kolom Pagar
Volume = 0.15 x 0.15
= 0.135 m3

Total = 8.5 + 1.17


= 9.805 m3
7 Balok
Balok 20 x 25 Volume = b x h x
= 0.2 x 0.25
= 3.695 m3

Balok 15 x 20 (anak) Volume = b x h x


= 0.2 x 0.25
3.375 m3

8 Tangga
Volume a x o
anak = x
tangga 2
= 0.3 x 0.25
2
= 0.563 m3
Volume
tebal = l x h x
tangga
= 1.00 x 0.12
= 1.08 m3

Total = 0.563 + 1.08


= 1.643 m3

PEKERJAAN DINDING
1 Pas. Dinding batu bata 1 : 6 ( 1/2 bata )
uk.5x11x22 Volume = Ptotal x t
= 70 x 4.00
= 280 m2

2 Pas. Dinding batu bata 1 : 3 ( 1/2 bata )


uk.5x11x22 (Trasram Kelliling) Volume = Ptotal x t
= 13.5 x 1.50
= 20.25 m2

Total = 280 + 20.25


= 300.25 m2

3 Plesteran dinding tebal 15 mm 1 : 6 Volume = 2 x 172


= 344 m2

4 Plesteran dinding tebal 15 mm 1 : 3 Volume = 2 x 13.5


= 27 m2

5 Acian Volume = 344 + 27.00


= 371 m2
PAGAR
1 Pas. Dinding batu bata 1 : 6 ( 1/2 bata ) Volume = 8 x 2.00
uk.5x11x22 = 16 m2

2 Plesteran dinding tebal 15 mm 1 : 6 Volume = 8 x 2.00


= 16 m2

3 Acian Volume = 8 x 2.00


16 m2
PEKERJAAN KUSEN
1 Kusen Pintu dan Jendela
a. Desain Pintu dan Jendela
Volume = ( 0.060 x
= 0.077 x jumlah
= 0.077 x 2
= 0.155 m3

b. Desain Pintu Garasi (P1)


Volume = ( 0.060 x
= 0.047 x jumlah
= 0.047 x 1
= 0.047 m3

c. Desain P2
Volume = ( 0.060 x
= 0.035 x jumlah
= 0.035 x 1
= 0.035 m3

d. Desain Jendela J1
Volume = ( 0.060 x
= 0.055 x jumlah
= 0.055 x 1
= 0.055 m3

Total = 0.155 + 0.047


= 0.291 m3
PEKERJAAN DAUN KUSEN
1 Kusen Pintu
a. Desain Pintu Jendela 1
Volume = 0.75 - 0.390
= 1.080 x jumlah
= 1.080 x 2
= 2.160 m 2

= 1.2 - 0.610
= 2.360 x jumlah
= 2.360 x 4
= 9.440 m 3

Total = 11.600 m3

b. Desain Pintu Garasi P1


Volume = 1 - 0.510
= 1.960 x jumlah
= 1.960 x 1
= 1.960 m 2

c. Desain Pintu P2
Volume = 1.6 - 0.900
= 2.800 x jumlah
= 2.800 x 1
= 2.800 m 2

TOTAL = 11.600 + 1.960


= 16.360 m2

PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Keramik Lantai Toko (Platinum) 50x50 Volume = 42.000 m2
2 Keramik Lantai Rumah (Platinum) 40x40 Volume = 58.5 m2
3 Keramik km/wc (Asia Tile) 20x20 Volume = 7.5 m2
4 Keramik Dinding km/wc (Asia Tile) 20x25 Volume = 24 m2
5 Keramik Dinding Marmer ( 20 x 40 ) Volume = 15.05 m2

PEKERJAAN LANGIT LANGIT


1 Plafond Gypsumboard Rangka Hollow Lantai 1 Volume = 51.1 m2
2 List Plafond Lantai 1 Volume = 2 x 56.500
= 113.000 m'
PEKERJAAN ELEKTRIKAL LISTRIK
1 Lampu Spiral Kuning ( Teras ) Volume = 3 bh
2 Lampu LED ( Dipasang Dalam Plafond ) Volume = 15 bh
3 Saklar Tunggal Volume = 1 bh
4 Saklar Ganda Volume = 7 bh
5 Stop Kontak Volume = 4 bh
6 Instalasi Titik Lampu Volume = 12 bh
7 Kabel NYA Volume = 50 m'
PEKERJAAN SANITASI
1 Memasang Kloset Duduk Volume = 2 bh
2 Memasang Westafel + Kran Volume = 1 bh
3 Memasang Floor Drain Volume = 2 bh
4 Memasang Soap Holder Volume = 2 bh
5 Memasang Paper Holder Volume = 1 bh
6 Memasang Shower dan Kran Volume = 1 bh
7 Memasang Kran Air Volume = 2 bh
8 Mesin pompa sanyo Volume = 1 bh

PEKERJAAN PLUMBING
1 Pemipaan Air Bersih
Pengadaan & pemasangan pemipaan air bersih
dari tandon air ke titik pelayanan, bahan PVC
AW klas 10 K lengkap terpasang termasuk
fitting galian, hanger, gantungan, dan bobokan.

- Pipa Air bersih PVC Ø 1/2'' bersih Volume = 50 m'

2 Pemipaan Air kotor


Pengadaan dan pemasangan pemipaan air bekas
Bahan PVC AW klas 10 K, lengkap terpasang,
termasuk fitting, galian, hanger, gantungan,
bobokan.
- Pipa Air kotor PVC Ø 4'' kotor Volume = 50 m'

3 Septictank + peresapan Volume = 1 unit

PEKERJAAN KUNCI DAN KACA


1 Handle Pintu
Pull Handle PJ = 2 x 2 =
P1 = 2 x 1 =
P2 =
Total = 6 buah

3 Engsel Pintu dan Jendela PJ = 12 x 2 =


P1 = 12 x 1 =
P2 = 3 x 1 =
P3 = 3 x 1 =
J3 = 2 x 1 =
Total = 44 buah
4 Kunci Tanam
Pull Handle PJ = 1 x 2 =
P1 = 1 x 1 =
Total = 3 buah

Biasa P2 = 1 x 1 =
P3 = 1 x 1 =
Total = 2 buah

5 Kaca tebal 5 mm Lantai 1 PJ = 0.390 x 2


P1 = 0.510 x 5
J1 = 3.270 x 3
Total = 13.14 m2
PEKERJAAN BESI DAN ALUMINIUM
1 Memasang Railling Tangga
Besi Stainless 5 x 5 Volume = 7.5 x 30
= 225.000 m1
PEKERJAAN FINISHING
1 Cat Dinding " Mowileks " Volume = 476 m2
2 Cat Plafond " Mowileks " Volume = 108 m2
3 Cat Kusen " Mowileks " Volume = 2 x 11.862
= 23.724 m2
PEKERJAAN LAIN-LAIN
1 Pekerjaan Lanscaping
Volume = 90 m1

LANTAI 2
1 Pekerjaan Urugan Pasir Bawah Lantai Volume = L x h
= 108.83 x 0.1
= 10.88 m3

PEKERJAAN BETON
1 Pelat Lantai
Volume = L x h
= 108.83 x 0.12
= 13.06 m3

2 Topi-Topi
Volume = 1 x 1.5
= 0.15 m3

3 Kolom
Kolom 25 x 25 Volume = p x l x
= 0.25 x 0.25
= 4.25 m3

4 Kolom 15 x 15 Volume = p x l x
= 0.15 x 0.15
= 0.63 m3
5 Ring Balok
Ring Balok 15 x 20 Volume = b x h x
= 0.15 x 0.2
2.16 m3

PEKERJAAN DINDING
1 Pas. Dinding batu bata 1 : 6 ( 1/2 bata )
uk.5x11x22 Volume = Ptotal x t
= 65 x 4.00
= 260 m2

2 Pas. Dinding batu bata 1 : 3 ( 1/2 bata )


uk.5x11x22 kamar mandi Volume = Ptotal x t
= 13.5 x 1.50
= 20.25 m2

3 Plesteran dinding tebal 15 mm 1 : 6 Volume = 2 x 98


= 196 m2

4 Plesteran dinding tebal 15 mm 1 : 3 Volume = 2 x 13.5


= 27 m2

5 Acian Volume = 364 + 45.000


= 409 m2

6 Sponengan Volume = 2 x 142.90


= 286 m2

PEKERJAAN KUSEN
1 Kusen Pintu dan Jendela
a. Desain Pintu dan Jendela
Volume = ( 0.060 x
= 0.071 x jumlah
= 0.071 x 1
= 0.071 m3
c. Desain P2
Volume = ( 0.060 x
= 0.035 x jumlah
= 0.035 x 4
= 0.141 m3
c. Desain Jendela J2
Volume = ( 0.060 x
= 0.057 x jumlah
= 0.057 x 2
= 0.115 m3

d. Desain Jendela J3

Volume = ( 0.060 x
= 0.156 x jumlah
= 0.156 x 3
= 0.468 m3

e. Desain Bouven (BV)


Volume = ( 0.060 x
= 0.026 x jumlah
= 0.026 x 1
= 0.026 m3

TOTAL = 0.071 + 0.141


+ 0.026
= 0.821 m3

PEKERJAAN DAUN KUSEN


1 Kusen Pintu dan Jendela
a. Desain Pintu Jendela 1 Volume = 0.75 - 0.390
= 1.080 x jumlah
= 1.080 x 2
= 2.160 m2

= 1.2 - 0.610
= 2.360 x jumlah
= 2.360 x 2
= 4.720 m3
Total = 6.880 m3

b. Desain Pintu P2
Volume = 1.6 - 0.900
= 2.800 x jumlah
= 2.800 x 2
= 5.600 m 2
b. Desain Jendela J2
Volume = 1.6 - 0.900
= 2.800 x jumlah
= 2.800 x 2
= 5.600 m 2

TOTAL = 6.880 + 5.600


= 18.080 m3

PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Keramik Lantai (Platinum) 40x40 Volume = 76.500 m2
2 Keramik Lantai Teras) 40x40 Volume = 10.500 m2
3 Keramik Dinding marmer 20x40 Volume = 22.000 m2
4 Keramik km/wc (Asia Tile)20x20 Volume = 7.5 m2
5 Keramik Dinding km/wc (Asia Tile) 20x25 Volume = 24 m2

PEKERJAAN LANGIT LANGIT


1 Plafond Gypsumboard Rangka Hollow Lantai 1 Volume = 51.1 m2
2 List Plafond Lantai 1 Volume = 2 x 56.500
= 113.000 m'

PEKERJAAN ELEKTRIKAL LISTRIK


1 Lampu LED ( Dipasang Dalam Plafond ) Volume = 10 bh
2 Lampu spiral kuning ( teras ) Volume = 1 bh
3 Saklar Tunggal Volume = 3 bh
4 Saklar Ganda Volume = 4 bh
5 Stop Kontak Volume = 4 bh
6 Instalasi Titik Lampu Volume = 11 bh
7 Kabel NYA Volume = 50 m'

PEKERJAAN SANITASI
1 Memasang Kloset Duduk Volume = 2 bh
2 Memasang Floor Drain Volume = 2 bh
3 Memasang Soap Holder Volume = 2 bh
5 Memasang Shower dan Kran Volume = 2 bh

PEKERJAAN PLUMBING
1 Pemipaan Air Bersih

Pengadaan & pemasangan pemipaan air bersih


dari tandon air ke titik pelayanan, bahan PVC
AW klas 10 K lengkap terpasang termasuk
fitting galian, hanger, gantungan, dan bobokan.
- Pipa Air bersih PVC Ø 2'' bersih Volume = 50 m'

2 Pemipaan Air kotor


Pengadaan dan pemasangan pemipaan air bekas
Bahan PVC AW klas 10 K, lengkap terpasang,
termasuk fitting, galian, hanger, gantungan,
bobokan.
- Pipa Air kotor PVC Ø 3'' kotor Volume = 60 m'

3 Memasang Roof Tank Volume = 1 unit


PEKERJAAN KUNCI DAN KACA
1 Handle Pintu
Pull Handle PJ = 2 x 1 =

Biasa P2 = 1 x 4 =
P3 = 1 x 1 =
Total = 5 buah

2 Engsel Pintu PJ = 12 x 1 =
P2 = 3 x 4 =
P3 = 3 x 1 =
Total = 27 buah

3 Kunci Tanam
Pull Handle PJ = 1 x 1 =

Biasa P2 = 1 x 4 =
P3 = 1 x 1 =
Total = 5 buah

4 Grendel
PJ = 8 x 1 =
P2 = 1 x 4 =
P3 = 1 x 1 =
Total = 13 buah

5 Kaca tebal 5 mm PJ1 = 4.968 x 1


P3 = 0.998 x 1
J2 = 7.193 x 1
J4 = 2.822 x 1
BV = 0.264 x 2
Total = 15.981 m2

PEKERJAAN KAYU
1 Lisplank 3/30 Volume = 36.900 m'

2 Rangka Atap Volume = 169.0 m2

3 Talang Datar Seng BJLS Volume = 24.000 m'

4 Nok 8/12 Volume = 8.000 m'

5 Reuter 2/20 Volume = 8.000 m'


KONSTRUKSI KUDA-KUDA
1 kuda-kuda bentang 7 meter balok tarik 8/12 = 0.0096 x
kaki kuda2 8/12 = 0.0096 x
makelar 8/12 0.0096 x
balok sokong 8/1 = 0.0096 x
balok 4/12gapit = 0.0096 x

Total = 0.219 x
= 0.219 x
= 0.877 kg

2 Gording Panjang = 30 m'


Volume = 30 x 0.096
= 2.880 m3

3 Kerpus Panjang = 32.6 m'


4 Mur Baut vol = 200 bh

PEKERJAAN PENUTUP ATAP


1 Pasang Bubugan Genteng Beton Volume = 34.400 m1
2 Pasang Atap Genteng Beton Volume = 169.00 m2
3 Alumunium Foil Volume = 27.20 m2

PEKERJAAN BESI DAN ALUMINIUM


1 Memasang Railling Balkon
Besi Stainless 5 x 5 Volume = 10.0 m1

PEKERJAAN FINISHING
1 Cat Dinding " Mowileks " Volume = 336.000 m2
2 Cat Plafond " Mowileks " Volume = 94.500 m2
3 Cat Kusen " Mowileks " Volume = 2 x 12.706
= 25.411 m2

PEKERJAAN LAIN-LAIN
1 Pekerjaan Penangkal Petir Volume = 2 titik
KERJAAN

PERHITUNGAN

1
x 1.1 x 67.5
2

1.12
x 1.1 x 27
2

t
0.6 x 0.5

29.997 + 1.515
t x jml
1.2 x 1.8 x 17

3
3

x 67.5

x 27

x 5.05

2.43 + 0.303

1.2 x 0.1 x 17

t
0.1

t
0.1

x 67.5

x 27
4.86
0.3
x 0.8 x 67.5
2

0.3
x 0.8 x 27
2

0.5 x 5.05

11.88 + 1.01

1.2
x 0.15 + 1.2 x 0.2
2
9

1
x 0.15 + 1.0 x 0.2
2
8
t x jml
0.25 x 1.45 x 17

2.82 + 1.541
0.05 x 1 x 9

0.05 x 1 x 8

0.4

p
0.25 x 94.5

t x jml
0.25 x 4 x 17

t x jml
0.15 x 4 x 6
0.15 x 1.5 x 4

1.17 + 0.135
p
0.25 x 73.9

p
0.25 x 67.5

p x jmlh
x 1 x 15

p
0.12 x 9

1.08

4.00

1.50
20.25

27.00
2.00

2.00

2.00

0.120 ) x 10.760
jumlah
2

0.120 ) x 6.500
jumlah
1

0.120 ) x 4.800
jumlah
1

0.120 ) x 7.600
jumlah
1

0.047 + 0.035 + 0.055


0.390 x 3
jumlah
2

0.610 x 4
jumlah
4

0.510 x 4
jumlah
1

0.900 x 4
jumlah
1

1.960 + 2.800
4 buah
2 buah

24 buah
12 buah
3 buah
3 buah
2 buah

2 buah
1 buah

1 buah
1 buah

= 0.78 m2
= 2.55 m2
= 9.81 m2
0.1

0.12

1.5 x 0.1
t x jml
0.25 x 4 x 17

t x jml
0.15 x 4 x 7
p
0.2 x 72

4.00

1.50

45.000

142.90

0.120 ) x 10.760
jumlah
0.120 ) x 4.800
jumlah
0.120 ) x 7.970
jumlah

0.120 ) x 21.670
jumlah

0.120 ) x 3.560
jumlah

0.141 + 0.115 + 0.468

0.390 x 3
jumlah
2

0.610 x 4
jumlah
2

0.900 x 4
jumlah
2
0.900 x 4
jumlah
2

5.600 + 5.600
2 buah

4 buah
1 buah

12 buah
12 buah
3 buah

1 buah

4 buah
1 buah

8 buah
4 buah
1 buah
buah

= 4.968 m2
= 0.998 m2
= 7.193 m2
= 2.822 m2
= 0.528 m2
7.03 = 0.067
7.50 = 0.072
2.00 = 0.019
3.12 = 0.030
3.20 = 0.031

jumlah
4

0.096
Contoh Perhitungan Human Resources

Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm


Volume = 105.60 m2
Durasi = 2.000 minggu
Volume/Minggu = 52.800 m2

Melihat tabel abk 5-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
1 Pekerja = 0.20 x 52.80 = 10.56
2 Tukang Batu = 0.10 x 52.80 = 5.28
3 Kepala Tukang = 0.01 x 52.80 = 0.53
4 Mandor = 0.01 x 52.80 = 0.53

Bahan
1 sak portland semen 40 kg
1 Portland Cement (PC) = 3.25 x 52.80 = 172

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
1 Pekerja = 10.56 : 6 = 1.76
2 Tukang Batu = 5.28 : 6 = 0.88
3 Kepala Tukang = 0.53 : 6 = 0.09
4 Mandor = 0.53 : 6 = 0.09
3 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Volume = 280 m2
Durasi = 2 minggu
Volume/Minggu = 140 m2

Melihat tabel abk 4-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
1 Pekerja = 0.30 x 140.00 = 42.00
2 Tukang Batu = 0.1 x 140.00 = 14.00
3 Kepala Tukang = 0.01 x 140.00 = 1.40
4 Mandor = 0.015 x 140.00 = 2.10

Bahan
1 sak portland semen 40 kg
Bata Merah 5 x 11 x 22 = 70 x 140.00 = 9800
1 Portland Cement (PC) = 8.32 x 140.00 = 1,165
Pasir Pasang = 0.049 x 140.00 = 6.86

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
1 Pekerja = 42.00 : 6 = 7.00
2 Tukang Batu = 14.00 : 6 = 2.33
3 Kepala Tukang = 1.40 : 6 = 0.23
4 Mandor = 2.10 : 6 = 0.35

4 Pemasangan Plesteran 1Pc : 3pp t=15 mm

Volume = 27.00 m2
Durasi = 1 minggu
Volume/Minggu = 27 m2

Melihat tabel abk 5-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
1 Pekerja = 0.3 x 27.00 = 8.10
2 Tukang Batu = 0.15 x 27.00 = 4.05
3 Kepala Tukang = 0.015 x 27.00 = 0.41
4 Mandor = 0.015 x 27.00 = 0.41

Bahan
1 sak portland semen 40 kg
1 Portland Cement (PC) = 7.776 x 27.00 = 210.0
Pasir Pasang = 0.023 x 27.00 = 0.62

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
1 Pekerja = 8.10 : 6 = 1.35
2 Tukang Batu = 4.05 : 6 = 0.68
3 Kepala Tukang = 0.41 : 6 = 0.07
4 Mandor = 0.41 : 6 = 0.07
5 Pemasangan Plesteran 1Pc:6pp t=15mm

Volume = 344.0 m2
Durasi = 2 minggu
Volume/Minggu = 172 m2

Melihat tabel abk 5-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
1 Pekerja = 0.3 x 172.00 = 51.60
2 Tukang Batu = 0.15 x 172.00 = 25.80
3 Kepala Tukang = 0.015 x 172.00 = 2.58
4 Mandor = 0.015 x 172.00 = 2.58

Bahan
1 sak portland semen 40 kg
1 Portland Cement (PC) = 4.42 x 172.00 = 759.6
Pasir Pasang = 0.03 x 172.00 = 4.6

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
1 Pekerja = 51.6 : 6 = 8.60
2 Tukang Batu = 25.80 : 6 = 4.30
3 Kepala Tukang = 2.58 : 6 = 0.43
4 Mandor = 2.58 : 6 = 0.43

6 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I


Volume = 0.29 m3
Durasi = 2 minggu
Volume/Minggu = 0.145512 m3

Melihat tabel abk 6-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 7.00 x 0.146 = 1.02
Tukang Kayu = 21.00 x 0.146 = 3.06
Kepala Tukang = 2.10 x 0.146 = 0.31
Mandor = 0.35 x 0.146 = 0.05
Bahan
Kayu Klas I (Jati) , Balok = 1.1 x 0.146 = 0.16
Paku Biasa 2" - 5 " = 1.25 x 0.146 = 0.18
Lem Kayu = 1 x 0.146 = 0.15

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 1.02 : 6 = 0.17
Tukang Kayu = 3.06 : 6 = 0.51
Kepala Tukang = 0.31 : 6 = 0.05
Mandor = 0.05 : 6 = 0.01
7 Pelaburan Bidang Kayu dg Politur

Volume = 16.65 m2
Durasi = 2 minggu
Volume/Minggu = 8.33 m2

Melihat tabel abk 14-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 0.04 x 8.33 = 0.33
Tukang kayu = 0.06 x 8.33 = 0.50
Kepala Tukang = 0.016 x 8.33 = 0.13
Mandor = 0.003 x 8.33 = 0.02

Bahan
Politur = 0.15 x 8.33 = 1
Politur Jadi = 0.37 x 8.33 = 3
Ampelas = 2.00 x 8.33 = 16.65

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 0.33 : 6 = 0.06
Tukang kayu = 0.50 : 6 = 0.08
Kepala Tukang = 0.13 : 6 = 0.02
Mandor = 0.02 : 6 = 0.00

8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Volume = 260.00
Durasi = 2 minggu
Volume/Minggu = 130.00 m2

Melihat tabel abk 4-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 0.3 x 130.00 = 39.00
Tukang Batu = 0.1 x 130.00 = 13.00
Kepala Tukang = 0.01 x 130.00 = 1.30
Mandor = 0.015 x 130.00 = 1.95

Bahan
Bata Merah 5 x 11 x 22 = 70 x 130.00 = 9100
Portland Semen = 8.32 x 130.00 = 1,082
Pasir Pasang = 0.049 x 130.00 = 6.4

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 39.00 : 6 = 6.50
Tukang Batu = 13.00 : 6 = 2.17
Kepala Tukang = 1.30 : 6 = 0.22
Mandor = 1.95 : 6 = 0.33
9 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm
Volume = 196.00
Durasi = 2 minggu
Volume/Minggu = 98.00 m2

Melihat tabel abk 5-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 0.3 x 98.00 = 29.40
Tukang batu = 0.15 x 98.00 = 14.70
Kepala Tukang = 0.015 x 98.00 = 1.47
Mandor = 0.015 x 98.00 = 1.47

Bahan
Portland Semen = 7.78 x 98.00 = 762.0
Pasir Pasang = 0.023 x 98.00 = 2.25

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 29.4 : 6 = 4.90
Tukang batu = 14.70 : 6 = 2.45
Kepala Tukang = 1.47 : 6 = 0.25
Mandor = 1.47 : 6 = 0.25

10 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I


Volume = 0.82 m3
Durasi = 3 minggu
Volume/Minggu = 0.274 m3

Melihat tabel abk 6-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 7.00 x 0.274 = 1.92
Tukang Kayu = 21.00 x 0.274 = 5.75
Kepala Tukang = 2.10 x 0.274 = 0.57
Mandor = 0.35 x 0.274 = 0.10

Bahan
Kayu Klas I (Jati) , Balok = 1.1 x 0.274 = 0.30
Paku Biasa 2" - 5 " = 1.25 x 0.274 = 0.34
Lem Kayu = 1 x 0.274 = 0.27

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 1.92 : 6 = 0.32
Tukang Kayu = 5.75 : 6 = 0.96
Kepala Tukang = 0.57 : 6 = 0.10
Mandor = 0.10 : 6 = 0.02
11 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting)
Volume = 4.88 m3
Durasi = 2 minggu
Volume/Minggu = 2.44 m3

Melihat tabel abk 7-14


Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 7.05 x 2.44 = 17.20
Tukang batu = 0.275 x 2.44 = 0.67
Tukang Kayu = 1.65 x 2.44 = 4.03
Tukang Besi = 2.1 x 2.44 = 5.12
Kepala Tukang = 0.403 x 2.44 = 0.98
Mandor = 0.353 x 2.44 = 0.86

Bahan
Kayu Klas III (Terentang) = 0.4 x 2.44 = 0.976
Paku Biasa 2" - 5" = 4 x 2.44 = 9.760
Minyak Bekisting = 2 x 2.44 = 4.880
Besi Beton Polos = 315 x 2.44 = 768.6
Kawat Beton = 4.5 x 2.44 = 10.980
Portland Semen = 336 x 2.44 = 819.84
Pasir Beton = 0.54 x 2.44 = 1.318
Kerikil Beton = 0.81 x 2.44 = 1.976
Kayu Klas II Balok = 0.15 x 2.44 = 0.366
Plywood 9 mm = 3.5 x 2.44 = 8.540
Dolken diameter 8 / 4rm = 20 x 2.44 = 48.800

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 17.20 : 6 = 2.87
Tukang batu = 0.67 : 6 = 0.112
Tukang Kayu = 4.03 : 6 = 0.671
Tukang Besi = 5.12 : 6 = 0.854
Kepala Tukang = 0.98 : 6 = 0.164
Mandor = 0.86 : 6 = 0.14355333

12 Pemasangan Pipa PVC tipe AW Ø ½"


Volume = 50.00 m1
Durasi = 1 minggu
Volume/Minggu = 50.00 m1
Melihat tabel abk 10-14
Jumlah Kebutuhan Tenaga dan Bahan dalam 1 Minggu
Tenaga
Pekerja = 0.81 x 50.00 = 40.50
Tukang Batu = 0.140 x 50.00 = 7.00
Kepala Tukang = 2.80 x 50.00 = 140.00
Mandor = 16.0 x 50.00 = 800.00

Bahan
Pipa PVC Ø ½" = 1.2 x 50.00 = 60
Perlengkapan 35% x pipa = 0.35 x 50.00 = 17.5

Jumlah Kebutuhan Tenaga dan Bahan dalam 1 hari


Tenaga
Pekerja = 40.50 : 6 = 6.75
Tukang Batu = 7.00 : 6 = 1.17
Kepala Tukang = 140.00 : 6 = 23.33
Mandor = 800.00 : 6 = 133.33
orang
orang
orang
orang

kg

= 2 orang
= 1 orang
= 1 orang
= 1 orang
Bata Camp. 1SP : 6PP

orang
orang
orang
orang

kg
m3

= 7 orang
= 3 orang
= 1 orang
= 1 orang

orang
orang
orang
orang

kg
m3

= 2 orang
= 1 orang
= 1 orang
= 1 orang
orang
orang
orang
orang

kg = 18.99
m3 sak

= 9 orang
= 5 orang
= 1 orang
= 1 orang

orang
orang
orang
orang
m3
kg
kg

= 1 orang
= 1 orang
= 1 orang
= 1 orang
orang
orang
orang
orang

Ltr
Ltr
Lbr

= 1 orang
= 1 orang
= 1 orang
= 1 orang

Bata Camp. 1SP : 6PP

orang
orang
orang
orang

Buah
Kg
m3

= 7 orang
= 3 orang
= 1 orang
= 1 orang
orang
orang
orang
orang

kg
kg

= 5 orang
= 3 orang
= 1 orang
= 1 orang

orang
orang
orang
orang

m3
kg
kg

= 1 orang
= 1 orang
= 1 orang
= 1 orang
orang
orang
orang
orang
orang
orang

m3
Kg
Ltr
kg
kg
Kg
m3
m3
m3
Lbr
Btg

= 3 orang
= 1 orang
= 1 orang
= 1 orang
= 1 orang
= 1 orang
orang
orang
orang
orang

m'
Ls

orang
orang
orang
orang
Tabel Kebutuhan Tenaga Kerja di Minggu ke 11 dengan 6 hari kerja
Anggaran Tenaga
No. Tenaga Kerja Jumlah Jumlah Pekerja
Kerja
1 Pekerja 39 40 orang Rp2,280,000
2 Tukang Batu 13.20 14 orang Rp1,176,000
3 Tukang Kayu 1.55 2 orang Rp168,000
4 Tukang Besi 0.85 1 orang Rp78,000
5 Kepala Tukang 1.57 2 orang Rp174,000
6 Mandor 1.57 2 orang Rp156,000
Total ( 1 Hari Kerja ) 61 Rp4,032,000

Maka total anggaran untuk tenaga kerja selama 1 minggu = Rp24,192,000

Tabel Kebutuhan Bahan Bangunan di Minggu ke 11

Anggaran Untuk
No. Bahan Jumlah
Bahan Bangunan
4,797.79 kg /
1 Portland Cement ( PC ) Rp 6,360,000
120 sak
2 Bata Merah 5 x 11 x 22 18,900 buah Rp 9,828,000
3 Pasir Pasang 18.495 m3 Rp 3,883,950
4 Pasir Beton 1.318 m3 Rp 368,928
5 Kerikil Beton 1.976 kg Rp 553,392
6 Kayu Klas I (Jati) , Balok 0.461 m3 Rp 9,220,992
7 Kayu Klas III (Terentang) 0.98 kg Rp 172,752
8 Pipa PVC Ø ½" 60 m' Rp 405,000
9 Dolken diameter 8 / 4rm 48.80 btg Rp 878,400
10 Plywood 9 mm 8.540 lbr Rp 999,180
11 Minyak Bekisting 4.88 ltr Rp 47,336
12 Besi Beton Polos 768.60 kg Rp 7,686,000
13 Kawat Beton 10.98 kg Rp 164,700
14 Politur 4.35 ltr Rp 169,491
15 Lem Kayu 0.42 kg Rp 8,173
16 Paku Biasa 2" - 5 " 10.28 kg Rp 143,975
17 Air kerja dan listrik 0.006 ls Rp 6,202
Total Rp 40,896,471

Total Anggaran yang dikeluarkan di minggu ke 11 Rp 24,192,000


Rp 40,896,471
Rp 65,088,471
Anggaran Biaya Minggu ke-11 = bobot x
= 7.62% x
= Rp 65,088,471
6 hari kerja
Anggaran Tenaga
Kerja
Rp2,280,000
Rp1,176,000
Rp168,000
Rp78,000
Rp174,000
Rp156,000
Rp4,032,000

Rp24,192,000

Anggaran Untuk
Bahan Bangunan

Rp 6,360,000
Rp 9,828,000
Rp 3,883,950
Rp 368,928
Rp 553,392
Rp 9,220,992
Rp 172,752
Rp 405,000
Rp 878,400
Rp 999,180
Rp 47,336
Rp 7,686,000
Rp 164,700
Rp 169,491
Rp 8,173
Rp 143,975
Rp 6,202
Rp 40,896,471

Rp 24,192,000
Rp 40,896,471
Rp 65,088,471
Anggaran Biaya (+PPN)
Rp887,750,000
KE
P

HARGA BOBOT
NO JENIS PEKERJAAN VOL. SAT. SATUAN HARGA
(%)
A. LANTAI 1
I PEKERJAAN PERSIAPAN
100.000
1 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 1.000 ls Rp 10,000,000 Rp 10,000,000 1.240
2 Pengukuran dan Pemasangan Bouwplank 70.000 m' Rp 136,004 Rp 9,520,280 1.181
3 Pembuatan Kantor Sementara dg Lantai Plesteran 9.000 m2 Rp 1,810,859 Rp 16,297,727 2.022
4 Pembuatan Gudang Semen dan Alat-alat 1.000 ls Rp 1,702,008 Rp 1,702,008 0.211
5 Membersihkan Lapangan dan Perataan 200.000 m2 Rp 10,560 Rp1,198,560 0.149
6 Air kerja dan listrik 1.000 ls Rp 1,000,000 Rp 1,000,000 0.124
7 Papan Nama Proyek 1.000 ls Rp 300,000 Rp 300,000 0.037
8 Administrasi dan Dokumentasi 1.000 ls Rp 1,500,000 Rp 1,500,000 0.186
II PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 122.097 m3 Rp 49,170 Rp 6,003,509 0.745
2 Pengurugan Kembali 40.699 m3 Rp 49,170 Rp 2,001,170 0.248
3 Menggali Tanah Biasa Sedalam 2 m 44.064 m3 Rp 60,291 Rp 2,656,663 0.330
4 Pengurugan Kembali 14.688 m3 Rp 60,291 Rp 885,554 0.110
5 Urugan Pasir Bawah Pondasi 6.750 m3 Rp 191,268 Rp 1,291,059 0.160
6 Urugan Pasir Bawah Lantai lt 1 11.355 m3 Rp 191,268 Rp 2,171,848 0.269
III PEKERJAAN PONDASI
1 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 42.590 m3 Rp 686,890 Rp 29,254,624 3.629
2 Pemasang Batu Kosong/Anstamping 18.360 m3 Rp 415,157 Rp 7,622,273 0.946
IV PEKERJAAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP 20.250 m2 Rp 52,338 Rp 1,059,853 0.131
2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP 280.000 m2 Rp 48,236 Rp 13,506,034 1.675
V PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 27.000 m2 Rp 52,338 Rp 1,413,137 0.175
2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 344.000 m2 Rp 48,236 Rp 16,593,128 2.058
3 Pemasangan Acian 371.000 m2 Rp 28,457 Rp 10,557,547 1.310
VI PEKERJAAN KUSEN KAYU
1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I 0.291 m3 Rp 26,851,000 Rp 7,814,285 0.969
2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 16.360 m3 Rp 708,373 Rp 11,588,974 1.438
VII PEKERJAAN BETON
1 Membuat Lantai Kerja Beton Mutu K(100) 0.450 m3 Rp 866,589 Rp 389,965 0.048
80.000
2 Membuat Pelat Lantai K-250 (200 kg Besi + Bekisting) 13.060 m3 Rp 4,659,540 Rp 60,851,722 7.549
3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 8.127 m3 Rp 3,769,209 Rp 30,632,836 3.800
4 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4.725 m3 Rp 4,608,610 Rp 21,775,680 2.701
5 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 9.805 m3 Rp 8,040,786 Rp 78,839,902 9.780
6 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 3.695 m3 Rp 6,321,926 Rp 23,359,515 2.898
7 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 1.643 m3 Rp 5,815,112 Rp 9,551,321 1.185
VIII PEKERJAAN LANGIT-LANGIT
1 Langit-langit Gypsum Board & Rangka Allumunium (Concealed) 51.100 m2 Rp 95,994 Rp 4,905,307 0.608
2 List Gypsum 113.000 m' Rp 20,485 Rp 2,314,805 0.287
IX PEKERJAAN SANITASI
1 Memasang Closet Duduk / Mono Blok 2.000 Unit Rp 1,779,874 Rp 3,559,747 0.442
2 Memasang Wastafel + Kran 1.000 Unit Rp 666,259 Rp 666,259 0.083
3 Pemasangan Floor Drain 2.000 bh Rp 31,053 Rp 62,106 0.008
4 Memasang Soap Holder 2.000 bh Rp 75,000 Rp 150,000 0.019
5 Memasang Paper Holder 1.000 bh Rp 80,000 Rp 80,000 0.010
6 Memasang Shower dan Kran 1.000 bh Rp 200,000 Rp 200,000 0.025
7 Memasang Kran Air 2.000 bh Rp 72,655 Rp 145,310 0.018
8 Memasang Pompa Air (Sanyo) 1.000 Unit Rp 995,000 Rp 995,000 0.123
X PEKERJAAN PLUMBING
1 Pemasangan Pipa PVC tipe AW Ø ½" 50.000 m' Rp 44,079 Rp 2,203,942 0.273
2 Pemasangan Pipa PVC tipe AW Ø 4" 50.000 m' Rp 44,079 Rp 2,203,942 0.273
3 Septictank + peresapan 1.000 Unit Rp 1,200,000 Rp 1,200,000 0.149
XI PEKERJAAN BESI DAN ALUMUNIUM
1 Memasang Railling Tangga 225.000 m' Rp 29,758 Rp 6,695,494 0.831
XII PEKERJAAN KUNCI DAN KACA
1 Memasang Kunci Tanam 4.000 bh Rp 176,152 Rp 704,606 0.087
2 Memasang Engsel Pintu dan Jendela 44.000 bh Rp 9,000 Rp 396,000 0.049

60.000
3 Pasang Kait Angin lt1 1.000 bh Rp 30,672 Rp 30,672 0.004
4 Pasang Grendel 27.000 bh Rp 3,000 Rp 81,000 0.010
Pasang Pull Handle 60.000
5 6.000 bh Rp 87,000 Rp 522,000 0.065
6 Pasang Handle Biasa 2.000 bh Rp 90,000 Rp 180,000 0.022
7 Pasang Kaca tebal 5 mm lt1 32.021 m2 Rp 90,110 Rp 2,885,424 0.358
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 100.500 m2 Rp 347,075 Rp 34,881,068 4.327
2 Pemasangan Lantai Keramik 20 x 20 cm 7.500 m2 Rp 57,815 Rp 433,615 0.054
3 Pemasangan Dinding Keramik 20 x 25cm 24.000 m2 Rp 200,654 Rp 4,815,703 0.597
4 Pemasangan dinding marmer 20x40 15.050 m2 Rp 350,000 Rp 5,267,500 0.653
XIV PEKERJAAN PENGECATAN
1 Pelaburan Bidang Kayu dg Politur 16.651 m2 Rp 40,814 Rp 679,602 0.084
2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 371.000 m2 Rp 17,286 Rp 6,412,924 0.796
3 Pengecatan Plafond 51.100 m2 Rp 17,286 Rp 883,290 0.110
XV PEKERJAAN INSTALASI LISTRIK
1 Lampu Spiral Kuning ( Teras ) 3.000 bh Rp 34,000 Rp 102,000 0.013
2 Lampu LED ( Dipasang Dalam Plafond ) 15.000 bh Rp 98,000 Rp 1,470,000 0.182
3 Saklar Tunggal 1.000 bh Rp 10,000 Rp 10,000 0.001
4 Saklar Ganda 7.000 bh Rp 16,000 Rp 112,000 0.014
5 Stop Kontak 4.000 bh Rp 13,500 Rp 54,000 0.007
6 Instalasi Titik Lampu 12.000 bh Rp 13,500 Rp 162,000 0.020
7 Kabel NYA 50.000 m1 Rp 3,700 Rp 185,000 0.023
B. LANTAI 2
XVI PEKERJAAN TANAH
1 Urugan pasir bawah lantai 2 10.883 m3 Rp 191,268 Rp 2,081,570 0.258
XVII PEKERJAAN DINDING
1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP 20.250 m2 Rp 52,338 Rp 1,059,853 0.131
2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP 260.000 m2 Rp 48,236 Rp 12,541,317 1.556
XVIII PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 27.000 m2 Rp 48,236 Rp 1,302,368 0.162
2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 196.000 m2 Rp 52,338 Rp 10,258,326 1.273
3 Pemasangan Acian 409.000 m2 Rp 28,457 Rp 11,638,913 1.444
40.000
XIX PEKERJAAN KAYU
1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I 0.821 m3 Rp 26,851,000 Rp 22,041,234 2.734
2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 18.080 m3 Rp 708,373 Rp 12,807,375 1.589
3 Pemasangan konstruksi Gording, Kayu Klas II 2.880 m1 Rp 69,245 Rp 199,427 0.025
4 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Klas I 0.877 m3 Rp 29,190,920 Rp 25,613,281 3.177
5 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II 169.000 m2 Rp 183,986 Rp 31,093,634 3.857
6 Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II 36.900 m1 Rp 119,823 Rp 4,421,469 0.548
XX PEKERJAAN BETON
1 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 4.880 m3 Rp 8,040,786 Rp 39,239,033 4.868
2 Membuat Ring Balok Beton Bertulang 2.160 m3 Rp 6,321,926 Rp 13,655,359 1.694
XXI PEKERJAAN PENUTUP ATAP
1 Pemasangan Bubugan Genteng Beton 34.400 m1 Rp 93,291 Rp 3,209,210 0.398
2 Pemasangan Atap Genteng Beton 169.000 m2 Rp 104,606 Rp 17,678,346 2.193
3 Pemasangan Nok Genteng Beton 3.500 m1 Rp 106,159 Rp 371,556 0.046
4 Pasang Allumunium Foil / Sisalation 83.070 m2 Rp 24,083 Rp 2,000,608 0.248
XXII PEKERJAAN LANGIT-LANGIT
1 Langit-langit Gypsum Board & Rangka Allumunium (Concealed) 51.350 m2 Rp 95,994 Rp 4,929,306 0.611
2 List Gypsum 122.800 m1 Rp 20,485 Rp 2,515,558 0.312
XXIII PEKERJAAN SANITASI
1 Memasang Closet Duduk / Mono Blok 2.000 Unit Rp 1,779,874 Rp 3,559,747 0.442
2 Pemasangan Floor Drain 2.000 bh Rp 31,053 Rp 62,106 0.008
3 Memasang Soap Holder 2.000 bh Rp 80,000 Rp 160,000 0.020
4 Memasang Shower dan Kran 2.000 bh Rp 200,000 Rp 400,000 0.050
XXIV PEKERJAAN PLUMBING
1 Pemasangan Pipa PVC tipe AW Ø ½" 50.000 m' Rp 44,079 Rp 2,203,942 0.273
2 Pemasangan Pipa PVC tipe AW Ø 4" 60.000 m' Rp 44,079 Rp 2,644,730 0.328
3 Memasang Roof Tank 1000 L 1.000 Unit Rp 1,600,000 Rp 1,600,000 0.198
XXV PEKERJAAN BESI DAN ALUMUNIUM
1 Pemasangan Ralling Balkon 5 x 5 10.000 m' Rp 112,641 Rp 1,126,410 0.140
2 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 27.200 m' Rp 172,717 Rp 4,697,889 0.583
20.000
XXVI PEKERJAAN KUNCI DAN KACA
1 Memasang Kunci Tanam 4.000 bh Rp 176,152 Rp 704,606 0.087
2 Memasang Engsel Pintu dan Jendela 27.000 bh Rp 9,000 Rp 243,000 0.030
3 Pasang Grendel 13.000 bh Rp 3,000 Rp 39,000 0.005
4 Pasang Pull Handle 2.000 bh Rp 87,000 Rp 174,000 0.022
5 Pasang Handle Biasa 5.000 bh Rp 90,000 Rp 450,000 0.056
6 Kaca tebal 3 mm 19.686 m2 Rp 90,110 Rp 1,773,912 0.220
XXVII PEKERJAAN PENUTUP LANTAI DAN DINDING LT2
1 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 76.500 m2 Rp 347,075 Rp 26,551,260 3.294
2 Pemasangan Lantai Keramik 20 x 20 cm 7.500 m2 Rp 57,815 Rp 433,615 0.054
3 Pemasangan Dinding Keramik 20 x 25cm 24.000 m2 Rp 200,654 Rp 4,815,703 0.597
4 Pemasangan dinding marmer 20x40 22.000 m2 Rp 350,000 Rp 7,700,000 0.955
XXVIII PEKERJAAN PENGECATAN LT2
1 Pelaburan Bidang Kayu dg Politur 18.901 m2 Rp 40,814 Rp 771,428 0.096
2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 409.000 m2 Rp 17,286 Rp 7,069,774 0.877
3 Pengecatan Plafond 51.350 m2 Rp 17,286 Rp 887,611 0.110
XXIX PEKERJAAN INSTALASI LISTRIK LT2
1 Lampu LED ( Dipasang Dalam Plafond ) 10.000 bh Rp 34,000 Rp 340,000 0.042
2 Lampu spiral kuning ( teras ) 1.000 bh Rp 98,000 Rp 98,000 0.012
3 Saklar Tunggal 3.000 bh Rp 10,000 Rp 30,000 0.004
4 Saklar Ganda 4.000 bh Rp 16,000 Rp 64,000 0.008
5 Stop Kontak 4.000 bh Rp 13,500 Rp 54,000 0.007
6 Instalasi Titik Lampu 11.000 bh Rp 13,500 Rp 148,500 0.018
7 Kabel NYA 50.000 m' Rp 3,700 Rp 185,000 0.023
XXX PEKERJAAN LAIN-LAIN
1 Penangkal Petir 2.000 ls Rp 250,000 Rp 500,000 0.062
2 Penyambungan daya ke PLN 2200 VA 1.000 ls Rp 1,000,000 Rp 1,000,000 0.124
3 Landscape 1.000 ls Rp 50,000,000 Rp 50,000,000 6.202
PROSENTASE
Rp 806,135,461.41 1000.000
JUMLAH KOMULATIF 1
TIME SCHEDULE
KEGIATAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang
DURASI BULAN 1 BULAN 2 BULAN 3
minggu minggu 1 minggu 2 minggu 3 minggu 4 minggu 5 minggu 6 minggu 7 minggu 8 minggu 9 minggu 10 minggu 11

100.000
1 1.240
2 0.590 0.590
3 0.674 0.674 0.674
2 0.106 0.106
1 0.149
20 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006
1 0.037
20 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

2 0.372 0.372
1 0.248
2 0.165 0.165
1 0.110
1 0.160
1 0.269

2 1.814 1.814
1 0.946

1 0.131
2 0.838 0.838

1 0.175
2 1.029
2

2 0.485 0.485
3 0.479 0.479

80.000 1 0.048
2 3.774 3.774
2 1.900 1.900
2 1.351 1.351
2 4.890 4.890
2 1.449 1.449
1 1.185

2
1

1
1
1
1
1
1
1
1 0.123

1 0.273
1 0.273
1 0.149

1
1

60.000
1
1
60.000
1
1
1

2
1
1
2

2 0.042 0.042
2
2

1
1
1
1
1
1
1

1 0.131
2 0.778 0.778

1
2 0.636
40.000 2

3 0.911 0.911
3 0.530 0.530
1
3 1.059 1.059
2
1

2 2.434 2.434
2

1
2
1
1

2
1

1
1
1
1

1 0.273
1 0.328
1

2
20.000 1

1
1
1
1
1
1

2
1
1
2

2 0.048
3
1

1
1
1
1
1
1
1

1
1
5
1.256 1.534 3.066 4.989 5.081 6.256 6.288 7.147 7.312 7.544 7.617
0.000
1 1.256
2 2.790
3 5.856
4 10.8455 15.926 6 22.182 7 28.470 8 35.617 9 42.929 50.474
10 58.091
11 12 13
N3 BULAN 4 BULAN 5
BOBOT PRESENTASE
minggu 12 minggu 13 minggu 14 minggu 15 minggu 16 minggu 17 minggu 18 minggu 19 minggu 20

100%

0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006

0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

1.029
0.655 0.655

0.479

0.304 0.304
0.287

0.442
0.083
0.008
0.019
0.010
0.025
0.018

0.831

0.087
0.049

Row 189
0.004
0.010
0.065 Row 189
0.022
0.358

2.163 2.163
0.054
0.597
0.327 0.327 50%

0.398 0.398
0.055 0.055

0.013
0.182
0.001
0.014
0.007
0.020
0.023

0.258

0.162
0.636
0.722 0.722

0.911
0.530
0.025
1.059
1.929 1.929
0.548

0.847 0.847

0.398
1.096 1.096
0.046
0.248

0.306 0.306 25%


0.312

0.442
0.008
0.020
0.050

0.198

0.070 0.070
0.583

0.087
0.030
0.005
0.022
0.056
0.220

1.647 1.647
0.054
0.597
0.478 0.478

0.048
0.292 0.292 0.292
0.110

0.042
0.012
0.004
0.008
0.007
0.018
0.023

0.062
0.124
1.240 1.240 1.240 1.240 1.240 0%
7.196 6.661 6.493 5.935 5.038 4.546 3.077 1.583 1.380
11 65.287
12 71.948
13 78.441
14 84.37715 89.414 16 93.960 17 97.037 18 98.620 100.000
19 20
DAF TAR HAR GA SAT UAN PE K E R JAAN
PEKERJAAN : PEMBANGUNAN RUMAH DAN TOKO BERTINGKAT
Lokasi : Jalan Estetika Raya No.1 Tembalang, Semarang

URAIAN PEKERJAAN
NO. KODE

I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m

2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank


3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran

4 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan


5 A.2.2.1.9 Membersihkan Lapangan dan Perataan
6 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu

7 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm


8 A.2.2.1.13 Bongkaran Beton Bertulang

9 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m


3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m


5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m
6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m


8 A.2.3.1.8 MembuangTanah sejauh 30 m'

9 A.2.3.1.9 Pengurugan Kembali


10 A.2.3.1.10 Pemadatan Tanah (per 20 cm)
11 A.2.3.1.11 Urugan Pasir

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL


13 A.2.3.1.13 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat

414275883.xlsx 157/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI

1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP


2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP
3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP


5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP


7 A.3.2.1.7 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP
8 A.3.2.1.8 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping
10 A.3.2.1.10 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm

IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

1 A.4.4.1.1 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP

2 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP

3 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP

4 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP

5 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP

414275883.xlsx 158/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

6 A.4.4.1.6 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

7 A.4.4.1.7 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

8 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

9 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

10 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

11 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

12 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP

13 A.4.4.1.13 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP

14 A.4.4.1.14 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP

15 A.4.4.1.15 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP

16 A.4.4.1.20 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP

17 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP


18 A.4.4.1.22 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP
19 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP

V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A,4,4,2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm

2 A,4,4,2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm


3 A,4,4,2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm
4 A,4,4,2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm

5 A,4,4,2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm


6 A,4,4,2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm

7 A,4,4,2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm


8 A,4,4,2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm
9 A.4.4.2.9 Pemasangan Plesteran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm

10 A,4,4,2.10 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm


11 A,4,4,2.11 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm

12 A,4,4,2.12 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm


13 A,4,4,2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm
14 A,4,4,2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm

414275883.xlsx 159/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

15 A,4,4,2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm

16 A,4,4,2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm


17 A,4,4,2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm
0 A,4,4,2.18 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm

0 A,4,4,2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm


0 A,4,4,2.20 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm

0 A,4,4,2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp


0 A,4,4,2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m')
0 A,4,4,2.25 Pemasangan Finishing Siar Pasangan Dinding Conblock ekspose (=8 m')
0 A,4,4,2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp
0 A,4,4,2.27 Pemasangan Acian

VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U


1 A.4.6.1.1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I
2 A.4.6.1.2 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III

3 A.4.6.1.3 Pembuatan & Pemasangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer)
4 A.4.6.1.4 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III

5 A.4.6.1.5 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II
6 A.4.6.1.6 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II
7 A.4.6.1.7 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati)

414275883.xlsx 160/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

8 A.4.6.1.8 Pembuatan&Pemasangan Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

9 A.4.6.1.9 Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu klas I atau II
10 A.4.6.1.10 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Klas I atau II
11 A.4.6.1.11 Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I

12 A.4.6.1.12 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II
13 A.4.6.1.13 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter

14 A.4.6.1.14 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Klas I


15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II
16 A.4.6.1.16 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas II
17 A.4.6.1.17 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II
18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II

19 A.4.6.1.19 Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III


20 A.4.6.1.20 Pemasangan Rangka Langit-langit (60x60) cm, kayu Klas II atau III
21 A.4.6.1.21 Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II

22 A.4.6.1.22 Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II


23 A.4.6.1.23 Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III

24 A.4.6.1.24 Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II


25 A.4.6.1.25 Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II
26 A.4.6.1.26 Pemasangan Dinding Lambriziring dari Papan klas I

27 A.4.6.1.27 Pemasangan Dinding Lambriziring dari Plywood ukuran (120x240) cm


28 A.4.6.1.28 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87
2 A.4.1.1.2 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78

3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
4 A.4.1.1.4 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87

5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58

414275883.xlsx 161/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56

9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
11 A.4.1.1.11 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49

12 A.4.1.1.12 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir

14 A.4.1.1.18 Kabel Presstresed Polos/strand


15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh
16 A.4.1.1.20 Memasang Bekisting untuk Pondasi
17 A.4.1.1.21 Memasang Bekisting untuk Sloof
18 A.4.1.1.22 Memasang Bekisting untuk Kolom

19 A.4.1.1.23 Memasang Bekisting untuk Balok


20 A.4.1.1.24 Memasang Bekisting untuk Lantai
21 A.4.1.1.25 Memasang Bekisting untuk Dinding

22 A.4.1.1.26 Memasang Bekisting untuk Tangga


23 A.4.1.1.27 Memasang Jembatan Cor

24 A.4.1.1.28 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting)


25 A.4.1.1.29 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting)
26 A.4.1.1.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting)

414275883.xlsx 162/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

27 A.4.1.1.31 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting)

28 A.4.1.1.32 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting)


29 A.4.1.1.33 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting)
30 A.4.1.1.34 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting)

31 A.4.1.1.35 Membuat Kolom Penguat Beton Bertulang (11 x 11) cm


32 A.4.1.1.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil
2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur
3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar
4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur


6 A.4.5.2.6 Pemasangan Bubugan Genteng Beton
7 A.4.5.2.9 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 mm

8 A.4.5.2.10 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 mm


9 A.4.5.2.12 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 mm

10 A.4.5.2.15 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 mm


11 A.4.5.2.30 Pemasangan Atap Genteng Beton
12 A.4.5.2.32 Pemasangan Atap Genteng Metal

13 A.4.5.2.33 Pemasangan Atap Sirap


14 A.4.5.2.34 Pemasangan Nok Genteng Beton

15 A.4.5.2.36 Pemasangan Nok Genteng Metal


16 A.4.5.2.37 Pemasangan Nok Sirap
17 A.4.5.2.38 Pemasangan Atap Seng Gelombang

18 A.4.5.2.39 Pemasangan Atap Nok Seng


19 A.4.5.2.42 Pasang Allumunium Foil / Sisalation

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm

414275883.xlsx 163/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

2 A.4.5.1.2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm

3 A.4.5.1.3 Pemasangan Langit-langit Akustik Ukuran (30x60) cm


4 A.4.5.1.4 Pemasangan Langit-langit Akustik Ukuran (60x120) cm
5 A.4.5.1.5 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm

6 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm


7 A.4.5.1.7 Memasang Langit-langit Gypsu Board, Uk (120x240) tebal 9 mm

8 A.4.5.1.9 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium


9 A.4.5.1.10 List Langit-Langit Kayu Profil

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok
2 A.5.1.1.2 Memasang Closet Jongkok Porselen

3 A.5.1.1.4 Memasang Urinoir


4 A.5.1.1.5 Memasang Wastafel + Kran
5 A.5.1.1.6 Pemasangan Bathcuip porselen

6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3


7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3

8 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell


9 A.5.1.1.14 Pemasangan Floor Drain
10 A.5.1.1.15 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm

414275883.xlsx 164/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

11 A.5.1.1.16 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm

12 A.5.1.1.17 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm


13 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½"
14 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾"

15 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾"


16 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1"

17 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ "


18 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3"
19 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4"
20 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½"
21 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾"

22 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1"


23 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½"
24 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2"

25 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3"


26 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4"

27 A.5.1.1.33 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm


28 A.5.1.1.34 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm
29 A.5.1.1.35 Pemasangan Pipa Beton Ø 20 cm

30 A.5.1.1.36 Pemasangan Pipa Beton Ø 100 cm

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 Pemasangan Besi Profil

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF


3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja)

4 A.4.2.1.4 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku
5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik
6 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi

7 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door)


8 A.4.2.1.9 Pemasangan Sunscreen Allumunium

414275883.xlsx 165/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

9 A.4.2.1.10 Pemasangan Rolling Door Allumunium

10 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium


11 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm
12 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium

13 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds


14 A.4.2.1.15 Pemasangan Terali Besi Strip (2x3) cm

15 A.4.2.1.16 Pemasangan Kawat Nyamuk


16 A.4.2.1.17 Pemasangan Jendela Nako & Tralis
17 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm
18 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm
19 A.4.2.1.20 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x120 cm dinding partisi

20 A.4.2.1.21 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x60 cm dinding plafond

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa


2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi

3 A.4.6.2.4 Pemasangan Kunci Selinder


4 A.4.6.2.5 Pemasangan Engsel Pintu
5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu

414275883.xlsx 166/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

6 A.4.6.2.7 Pemasangan Engsel Angin

7 A.4.6.2.9 Pemasangan Kait Angin


8 A.4.6.2.10 Pasang Door Closer
9 A.4.6.2.11 Pemasangan Kunci Selot

10 A.4.6.2.13 Pemasangan Door Stop


11 A.4.6.2.14 Pemasangan Rel Pintu Dorong

12 A.4.6.2.15 Pemasangan Kunci Lemari


13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm
14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm
15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm
2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm


4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm


6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm
7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm


9 A.4.4.3.33 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm


11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm
12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm

13 A.4.4.3.37 Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi / border


14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm


16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm
17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm

18 A.4.4.3.44 Pemasangan Lantai Karpet

414275883.xlsx 167/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm


21 A.4.4.3.49 Pemasangan Dinding Keramik 10x20 cm,
22 A.4.4.3.50 Pemasangan Dinding Keramik 20 x 25cm

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm,


24 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm

25 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam


26 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm
27 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


1 A.4.7.1.1 Pengikisan / pengerokan Permukaan Cat Tembok Lama
2 A.4.7.1.2 Pencucian Bidang Permukaan Tembok yang Pernah dicat

3 A.4.7.1.3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual


4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)

5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup)
6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil
7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur

414275883.xlsx 168/432 sat.pekerjaan


URAIAN PEKERJAAN
NO. KODE

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis


10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar
11 A.4.7.1.11 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium


13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih

14 A.4.7.1.14 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaan)


15 A.4.7.1.15 Pemasangan Wallpaper
16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi
17 A.4.7.1.17 Pengecatan Permukaan Baja dg Meni Besi & Perancah

414275883.xlsx 169/432 sat.pekerjaan


A SAT UAN PE K E R JAAN
AN RUMAH DAN TOKO BERTINGKAT
aya No.1 Tembalang, Semarang

HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m' 598,752.00

m' 136,004.00
m2 1,810,858.50

m2 1,702,008.00
m2 10,560.00
m2 286,316.80

bh 487,223.00
m3 893,184.60

m3 420,852.30

m3 49,170.00

m3 60,291.00
m3 71,583.60

m3 65,445.60
m3 99,198.00
m3 79,101.00

m2 3,564.00
m3 3,564.00

m3 1/3 x Gal.tanah
m3 35,640.00
m3 191,268.00

m3 257,653.00
m2 63,492.00

m3 178,860.00

414275883.xlsx 170/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m3 852,549.50
m3 802,290.50
m3 767,442.50

m3 742,945.50
m3 709,362.50

m3 600,451.50
m3 686,889.50
m3 652,217.50
m3 415,156.50
m3 2,284,668.10

m3 791,975.80

m2 224,224.00

m2 210,982.20
m2 201,869.80
m2 197,441.20
m2 196,526.00

414275883.xlsx 171/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 185,282.68

m2 107,461.20
m2 101,071.52
m2 97,471.00

m2 95,210.28
m2 94,099.72

m2 91,608.00
m2 93,071.00
m2 83,342.60
m2 88,214.50
m2 195,137.36

m2 196,148.48
m2 246,730.00
m2 242,935.00

m2 62,282.48

m2 55,307.60
m2 52,338.40
m2 50,271.54

m2 49,153.76
m2 48,235.84

m2 47,748.76
m2 47,261.68
m2 48,863.76

m2 46,945.80
m2 42,857.10

m2 43,259.70
m2 73,992.07
m2 54,984.48

414275883.xlsx 172/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 67,200.32

m2 65,786.95
m2 64,486.05
m2 60,492.30

m2 31,548.26
m' 49,898.20

m2 38,142.72
m2 22,436.57
m2 10,742.60
m2 47,649.14
m2 28,457.00

m3 26,851,000.00
m3 11,518,100.00

m2 465,727.90
m2 465,727.90

m2 708,372.50
m2 505,395.00
m2 1,932,425.00

414275883.xlsx 173/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 553,817.00

m2 596,123.00
m2 1,729,002.00
m2 982,817.00

m2 639,285.90
m3 10,254,090.00

m3 29,190,920.00
m3 69,245.35
m2 156,266.00
m2 183,986.00
m2 131,155.20

m2 168,091.00
m2 173,349.00
m' 289,993.00

m' 119,823.00
m2 273,887.90

m2 348,335.90
m2 355,652.00
m2 395,917.50

m2 37,838.90
m2 120,458.14

m3 923,395.00
m3 960,619.00

m3 989,747.00
m3 866,588.80

m3 1,024,199.00
m3 1,057,155.00
m3 1,081,839.00

414275883.xlsx 174/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m3 1,098,207.00

m3 1,126,499.00
m3 1,135,211.00
m3 1,206,089.50

m3 1,217,573.50
10 kg 158,720.10

10 kg 125,640.90
10 kg 229,379.70
m2 155,034.00
m2 166,034.00
m2 348,782.50

m2 366,932.50
m2 427,982.50
m2 398,832.50

m2 326,249.00
m2 92,409.90

m3 3,769,209.40
m3 4,608,609.50
m3 8,040,785.50

414275883.xlsx 175/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m3 6,321,925.50

m3 5,786,280.50
m3 5,693,593.40
m3 5,815,111.50

m' 66,977.90
m' 92,801.50

m2 64,489.15
m2 130,537.00
m2 120,747.00
m' 114,505.60

m' 101,305.60
m' 104,605.60
m2 66,396.00

m2 60,472.50
m2 52,057.50

m2 53,344.50
m2 96,657.00
m2 82,775.00

m2 101,377.10
m' 106,158.80

m' 57,055.90
m' 46,978.80
m2 34,485.00

m' 26,253.70
m2 24,083.40

m2 28,876.10

414275883.xlsx 176/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 94,965.20

m2 103,796.00

m2 85,316.00
m2 43,345.50

m2 498,322.00
m2 39,838.70

m2 191,895.00
m1 14,188.90

Unit 1,779,873.70
Unit 518,364.00

Unit 685,036.00
Unit 666,259.00
Unit 1,071,437.40

Unit 1,024,705.00
Unit 1,283,947.90

buah 336,259.00
buah 31,053.00
bh 360,527.20

414275883.xlsx 177/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

bh 542,701.50

bh 662,843.50
m' 33,918.87
bh 72,655.00

m' 37,613.03
m' 42,443.87

m' 65,338.53
m' 165,614.53
m' 270,756.20
m' 20,055.75
m' 22,613.25

m' 27,728.25
m' 31,291.33
m' 44,078.83

m' 76,021.18
m' 93,797.00

m' 84,634.00
m' 35,907.30
m' 92,681.82

m' 528,080.30

Kg 27,968.60

kg 26,582.60
kg 72,739.70

m2 845,725.10
cm 15,981.90
m2 550,118.80

m2 525,342.40
m2 455,435.20

414275883.xlsx 178/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 454,960.00

m' 112,640.99
m2 488,347.31
m2 455,793.80

m2 163,678.90
m2 338,220.56

m2 49,676.98
m2 64,204.80
m' 172,716.50
m' 65,036.40
m2 157,782.90

m2 191,178.90

Buah 213,213.00
Buah 144,006.50

Buah 212,206.50
Buah 25,679.50
Buah 16,203.00

414275883.xlsx 179/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

Buah 43,756.90

Buah 30,672.40
Buah 384,334.50
Buah 39,333.80

Buah 340,866.90
Buah 296,201.40

Buah 32,671.54
m2 90,110.35
m2 103,420.35
m2 336,950.35

m2 95,297.50
m2 95,209.40

m2 124,293.50
m2 120,575.40

m2 347,075.30
m' 57,815.34
m' 34,087.24

m2 189,588.74
m2 194,043.74

m2 186,045.52
m2 185,698.50
m2 187,537.90

m2 372,238.90
m' 32,470.24

m' 78,774.74
m' 76,442.74
m2 665,514.74

m2 187,771.10

414275883.xlsx 180/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 338,662.50

m2 212,301.29
m2 208,607.30
m2 200,654.30

m2 208,607.30
m2 738,153.36

m2 223,195.50
m2 133,928.30
m' 40,900.20

m2 10,349.90
m2 10,349.90

m2 10,778.90
m2 39,652.80

m2 53,479.80
m2 30,851.70
m2 40,814.40

414275883.xlsx 181/432 sat.pekerjaan


HARGA SATUAN
PEKERJAAN
SAT
(Rp)

m2 7,862.80

m2 32,698.60
m2 17,285.51
m2 11,839.74

m2 6,768.74
m2 11,855.47

m2 5,976.85
m2 76,422.50
m2 22,867.90
m2 46,389.75

414275883.xlsx 182/432 sat.pekerjaan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A.2.2.1.2 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m
A TENAGA
L.01 0.2 OH Pekerja
L.02 0.4 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.02 OH Mandor
B BAHAN
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm
2.5 Kg Portalnd Semen
1.2 Lbr Seng Gelombang 3" - 5"
0.005 m3 Pasir Beton
0.009 m3 Koral Beton
0.072 m3 Kayu 5/7X4m Kayu Kruing
0.06 Kg Paku Biasa 2" - 5"
0.45 Kg Meni Besi
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank
A Tenaga
L.01 0.1 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
0.012 m3 Kayu 5/7x 4m Kayu Kruing
0.02 Kg Paku Biasa 2" - 5"
0.007 m3 Kayu Papan 3/20 Kruing
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)

3 A.2.2.1.5 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran


A Tenaga
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

L.01 2 OH Pekerja
L.02 2 OH Tukang Kayu
L.02 1 OH Tukang Batu
L.03 0.3 OH Kepala Tukang
L.04 0.05 OH Mandor
B Bahan
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m
0.18 m3 Kayu
0.85 Kg Paku Biasa 2" - 5"
1.1 Kg Besi Strip
35 Kg Portland Sement
0.15 m3 Pasir pasang
0.1 m3 Pasir Beton
0.15 m3 Koral Beton
30 buah Batu bata Merah
0.25 Lbr Seng Plat
2 buah Jendela Naco
0.08 m2 Kaca Polos
0.15 buah Kunci Tanam
0.3 buah Engsel
0.06 Lbr Plywood 4 mm
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)

4 A.2.2.1.7 1 m2 Pembuatan Gudang Semen dan Peralatan


A Tenaga
L.01 1 OH Pekerja
L.02 2 OH Tukang Kayu
L.03 0.2 OH Kepala Tukang
L.04 0.05 OH Mandor
B Bahan
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm
0.21 m3 Kayu
0.3 Kg Paku Biasa 2" - 5"
10.5 Kg Portland Semen
0.03 m3 Pasir Beton
0.05 m3 Koral Beton
1.5 Lbr Seng Gelombang BJLS 32
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)

5 A.2.2.1.9 1 m2 Membersihkan Lapangan dan Perataan


A Tenaga
L.01 0.1 OH Pekerja
L.04 0.05 OH Mandor
B Bahan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)

6 A.2.2.1.10 1 m2 Pembuatan Steger/Perancah dari Bambu


A Tenaga
L.01 1.00 OH Pekerja
L.02 2.00 OH Tukang Kayu
L.03 0.200 OH Kepala Tukang
L.04 0.0500 OH Mandor
B Bahan
1.250 Btg Bambu diameter 6 - 8 / 600 cm
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.186 Kg Tali Ijuk


C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)

7 A.2.2.1.11 1 bh Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm


A Tenaga
L.02 0.300 OH Tukang Kayu
L.03 0.030 OH Kepala Tukang
B Bahan
0.036 m3 Kayu Papan Kelas III
0.036 m3 Kayu Balok Kelas III
0.080 kg Paku Biasa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)

8 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang


A Tenaga
L.02 13.334 OH Pekerja
L.04 0.666 OH Mandor
B Bahan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

9 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah


B Tenaga
L.02 6.667 OH Pekerja
L.04 0.033 OH Mandor
B Bahan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%) 10%
F Harga Satuan Pekerjaan (D+E)
HARGA
BAHAN/UPAH JUMLAH

Rp Rp

dari Seng Gelombang Tinggi 2,00 m 598,752.00


` 48,300.00
57,000.00 11,400.00
84,000.00 33,600.00
87,000.00 1,740.00
78,000.00 1,560.00
496,020.00
18,000.00 22,500.00
1,360.00 3,400.00
50,000.00 60,000.00
280,000.00 1,400.00
270,000.00 2,430.00
5,500,000.00 396,000.00
14,000.00 840.00
21,000.00 9,450.00

544,320.00
54,432.00
598,752.00

136,004.00
15,360.00
57,000.00 5,700.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 390.00
108,280.00
5,500,000.00 66,000.00
14,000.00 280.00
6,000,000.00 42,000.00

123,640.00
12,364.00
136,004.00

1,810,858.50
396,000.00
HARGA
BAHAN/UPAH JUMLAH

Rp Rp

57,000.00 114,000.00
84,000.00 168,000.00
84,000.00 84,000.00
87,000.00 26,100.00
78,000.00 3,900.00
1,250,235.00
18,000.00 22,500.00
5,500,000.00 990,000.00
14,000.00 11,900.00
12,500.00 13,750.00
1,360.00 47,600.00
210,000.00 31,500.00
280,000.00 28,000.00
270,000.00 40,500.00
520.00 15,600.00
15,000.00 3,750.00
12,500.00 25,000.00
61,000.00 4,880.00
67,500.00 10,125.00
4,500.00 1,350.00
63,000.00 3,780.00
HARGA
BAHAN/UPAH JUMLAH

Rp Rp

1,646,235.00
164,623.50
1,810,858.50

1,702,008.00
246,300.00
57,000.00 57,000.00
84,000.00 168,000.00
87,000.00 17,400.00
78,000.00 3,900.00
1,300,980.00
18,000.00 30,600.00
5,500,000.00 1,155,000.00
14,000.00 4,200.00
1,360.00 14,280.00
280,000.00 8,400.00
270,000.00 13,500.00
50,000.00 75,000.00

1,547,280.00
154,728.00
1,702,008.00

10,560.00
9,600.00
57,000.00 5,700.00
78,000.00 3,900.00

9,600.00
960.00
10,560.00

286,316.80
246,300.00
57,000.00 57,000.00
84,000.00 168,000.00
87,000.00 17,400.00
78,000.00 3,900.00
13,988.00
10,000.00 12,500.00
HARGA
BAHAN/UPAH JUMLAH

Rp Rp

8,000.00 1,488.00

260,288.00
26,028.80
286,316.80

487,223.00
27,810.00
84,000.00 25,200.00
87,000.00 2,610.00
415,120.00
6,000,000.00 216,000.00
5,500,000.00 198,000.00
14,000.00 1,120.00

442,930.00
44,293.00
487,223.00

893,184.60
811,986.00
57,000.00 760,038.00
78,000.00 51,948.00

811,986.00
81,198.60
893,184.60
HARGA
BAHAN/UPAH JUMLAH

Rp Rp

420,852.30
382,593.00
57,000.00 380,019.00
78,000.00 2,574.00

382,593.00
38,259.30
420,852.30
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m


A TENAGA
L.01 0.75 OH Pekerja
L.04 0.025 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m
A TENAGA
L.01 0.90 OH Pekerja
L.04 0.045 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m


A TENAGA
L.01 1.05 OH Pekerja
L.04 0.067 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m


TENAGA
L.01 1.000 OH Pekerja
L.04 0.032 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m

414275883.xlsx 432/193 abk 2-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

A TENAGA
L.01 1.50 OH Pekerja
L.04 0.060 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m


A TENAGA
L.01 1.200 OH Pekerja
L.04 0.045 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m


A TENAGA
L.01 0.05 OH Pekerja
L.04 0.005 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m'


A TENAGA
L.01 0.330 OH Pekerja
L.04 0.010 OH Mandor

414275883.xlsx 432/194 abk 2-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.2.3.1.9 1 m3 Pengurugan Kembali


Pengurugan Kembali di hitung dari 1/3 kali koefisien Peke
A TENAGA
L.01 0.50 OH Pekerja
L.04 0.050 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm)


A TENAGA
L.01 0.5 OH Pekerja
L.04 0.05 OH Mandor
B BAHAN
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.2.3.1.11 1 m3 Urugan Pasir


A TENAGA
L.01 0.30 OH Pekerja
L.04 0.01 OH Mandor
B BAHAN
1.2 m3 Pasir Urug
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL


A TENAGA
L.01 0.800 OH Pekerja
L.02 0.400 OH Tukang Batu
L.03 0.04 OH Kepala Tukang

414275883.xlsx 432/195 abk 2-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.080 OH Mandor


B BAHAN
0.135 m3 Pasir Pasang
0.400 m3 Kapur Padam
0.080 m3 Tanah Liat
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

13 A.2.3.1.13 1 m2 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapa


A TENAGA
0.15 OH Pekerja
0.015 OH Mandor
B BAHAN
6.00 kg Ijuk
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat


A TENAGA
0.25 OH Pekerja
0.025 OH Mandor
B BAHAN
1.2 m3 Sirtu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contah 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/196 abk 2-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN Rp Rp

49,170.00
44,700.00
57,000.00 42,750.00
78,000.00 1,950.00

44,700.00
10% 4,470.00
49,170.00

60,291.00
54,810.00
57,000.00 51,300.00
78,000.00 3,510.00

54,810.00
10% 5,481.00
60,291.00

71,583.60
65,076.00
57,000.00 59,850.00
78,000.00 5,226.00

65,076.00
10% 6,507.60
71,583.60

65,445.60
59,496.00
57,000.00 57,000.00
78,000.00 2,496.00

59,496.00
10% 5,949.60
65,445.60

99,198.00

414275883.xlsx 432/197 abk 2-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN Rp Rp

90,180.00
57,000.00 85,500.00
78,000.00 4,680.00

90,180.00
10% 9,018.00
99,198.00

79,101.00
71,910.00
57,000.00 68,400.00
78,000.00 3,510.00

71,910.00
10% 7,191.00
79,101.00

3,564.00
3,240.00
57,000.00 2,850.00
78,000.00 390.00

3,240.00
10% 324.00
3,564.00

21,549.00
19,590.00
57,000.00 18,810.00
78,000.00 780.00

414275883.xlsx 432/198 abk 2-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN Rp Rp

19,590.00
10% 1,959.00
21,549.00

11,880.00
bali di hitung dari 1/3 kali koefisien Pekerjaan galian
32,400.00
57,000.00 28,500.00
78,000.00 3,900.00

32,400.00
10% 3,240.00
35,640.00

35,640.00
32,400.00
57,000.00 28,500.00
78,000.00 3,900.00

32,400.00
10% 3,240.00
35,640.00

191,268.00
17,880.00
57,000.00 17,100.00
78,000.00 780.00
156,000.00
130,000.00 156,000.00

173,880.00
10% 17,388.00
191,268.00

257,653.00
88,920.00
57,000.00 45,600.00
84,000.00 33,600.00
87,000.00 3,480.00

414275883.xlsx 432/199 abk 2-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN Rp Rp

78,000.00 6,240.00
145,310.00
210,000.00 28,350.00
270,000.00 108,000.00
112,000.00 8,960.00

234,230.00
10% 23,423.00
257,653.00

san Ijuk tebal 10 cm unt Bidang Resapan 63,492.00


9,720.00
57,000.00 8,550.00
78,000.00 1,170.00
48,000.00
8,000.00 48,000.00

57,720.00
10% 5,772.00
63,492.00

178,860.00
16,200.00
57,000.00 14,250.00
78,000.00 1,950.00
146,400.00
122,000.00 146,400.00

162,600.00
10% 16,260.00
178,860.00

414275883.xlsx 432/200 abk 2-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP
A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B BAHAN
1.2 m3 Batu Belah 15/20
202 Kg Portland Sement
0.485 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP
A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B BAHAN
1.2 m3 Batu Belah 15/20
163 Kg Portland Sement
0.52 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP


A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B BAHAN
1.2 m3 Batu Belah 15/20
414275883.xlsx 432/201 abk 3-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

136 Kg Portland Sement


0.544 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP


A TENAGA
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B BAHAN
1.2 m3 Batu Belah 15/20
117 Kg Portland Sement
0.561 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP


A Tenaga
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor

414275883.xlsx 432/202 abk 3-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
1.2 m3 Batu Belah 15/20
91 Kg Portland Sement
0.584 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP


A Tenaga
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B Bahan
1.2 m3 Batu Belah 15/20
0.17 m3 Kapur Pasang (KP)
0.17 Kg Semen Merah (SM)
0.340 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP


A Tenaga
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B Bahan
1.2 m3 Batu Belah 15/20
61 kg Portland Sement
0.147 m3 Kapur Pasang
0.492 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
414275883.xlsx 432/203 abk 3-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

F Harga Satuan Pekerjaan (D+E)

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP


A Tenaga
L.01 1.5 OH Pekerja
L.02 0.750 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.075 OH Mandor
B Bahan
1.2 m3 Batu Belah 15/20
41 kg Portland Sement
0.131 m3 Kapur Pasang
0.492 m3 Pasir
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping


A Tenaga
L.01 0.78 OH Pekerja
L.02 0.39 OH Tukang Batu
L.03 0.039 OH Kepala Tukang
L.04 0.039 OH Mandor
B Bahan
1.2 m3 Batu Belah 15/20
0.432 m3 Pasir Urug
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/204 abk 3-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

10 A.3.2.1.10 1 m3 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR
A Tenaga
L.01 3.4 OH Pekerja
L.02 0.85 OH Tukang Batu
L.03 0.085 OH Kepala Tukang
L.04 0.15 OH Mandor
B Bahan
0.480 m3 Batu Belah 15/20 cm
126 Kg Besi Beton
194 Kg Portland Semen
0.312 m3 Pasir Beton
0.468 m3 Koral Beton
1.8 Kg Kawat Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm


A Tenaga
L.01 2.40 OH Pekerja
L.02 0.8 OH Tukang Batu
L.03 0.08 OH Kepala Tukang
L.04 0.119 OH Mandor
B Bahan
0.45 m3 Batu Belah 15/20 cm
194 Kg Portland Semen
0.312 m3 Pasir Beton
0.468 m3 Koral Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/205 abk 3-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

N PEKERJAAN PONDASI
852,549.50
160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
614,170.00
198,000.00 237,600.00
1,360.00 274,720.00
210,000.00 101,850.00

775,045.00
10% 77,504.50
852,549.50

802,290.50
160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
568,480.00
198,000.00 237,600.00
1,360.00 221,680.00
210,000.00 109,200.00

729,355.00
10% 72,935.50
802,290.50

767,442.50
160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
536,800.00
198,000.00 237,600.00
414275883.xlsx 432/206 abk 3-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

1,360.00 184,960.00
210,000.00 114,240.00

697,675.00
10% 69,767.50
767,442.50

742,945.50
160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
514,530.00
198,000.00 237,600.00
1,360.00 159,120.00
210,000.00 117,810.00

675,405.00
10% 67,540.50
742,945.50

709,362.50
160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00

414275883.xlsx 432/207 abk 3-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

484,000.00
198,000.00 237,600.00
1,360.00 123,760.00
210,000.00 122,640.00

644,875.00
10% 64,487.50
709,362.50

dasi Batu Belah 1SP : 1KP : 2PP 600,451.50


160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
384,990.00
198,000.00 237,600.00
270,000.00 45,900.00
177,000.00 30,090.00
210,000.00 71,400.00

545,865.00
10% 54,586.50
600,451.50

dasi Batu Belah, 1 SP : 3 KP : 10 PP 686,889.50


160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
463,570.00
198,000.00 237,600.00
1,360.00 82,960.00
270,000.00 39,690.00
210,000.00 103,320.00

624,445.00
10% 62,444.50
414275883.xlsx 432/208 abk 3-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

686,889.50

dasi Batu Belah, ¼ SP : 1KP : 4 PP 652,217.50


160,875.00
57,000.00 85,500.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 5,850.00
432,050.00
198,000.00 237,600.00
1,360.00 55,760.00
270,000.00 35,370.00
210,000.00 103,320.00

592,925.00
10% 59,292.50
652,217.50

415,156.50
83,655.00
57,000.00 44,460.00
84,000.00 32,760.00
87,000.00 3,393.00
78,000.00 3,042.00
293,760.00
198,000.00 237,600.00
130,000.00 56,160.00

377,415.00
10% 37,741.50
415,156.50

414275883.xlsx 432/209 abk 3-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah 2,284,668.10
284,295.00
57,000.00 193,800.00
84,000.00 71,400.00
87,000.00 7,395.00
78,000.00 11,700.00
1,792,676.00
198,000.00 95,040.00
10,000.00 1,260,000.00
1,360.00 263,840.00
280,000.00 87,360.00
127,000.00 59,436.00
15,000.00 27,000.00

2,076,971.00
10% 207,697.10
2,284,668.10

791,975.80
220,242.00
57,000.00 136,800.00
84,000.00 67,200.00
87,000.00 6,960.00
78,000.00 9,282.00
499,736.00
198,000.00 89,100.00
1,360.00 263,840.00
280,000.00 87,360.00
127,000.00 59,436.00

719,978.00
10% 71,997.80
791,975.80

414275883.xlsx 432/210 abk 3-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.1 1 m2 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Teba
A Tenaga
L.01 0.6 OH Pekerja
L.02 0.2 OH Tukang Batu
L.03 0.02 OH Kepala Tukang Batu
L.04 0.03 OH Mandor
B Bahan
140 Buah Bata Merah
43.5 Kg Portland Semen (PC)
0.08 m3 Pasir Pasang (PP)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
2 A.4.4.1.2 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Teba
A Tenaga
L.01 0.6 OH Pekerja
L.02 0.2 OH Tukang Batu
L.03 0.02 OH Kepala Tukang Batu
L.04 0.03 OH Mandor
B Bahan
140 Buah Bata Merah
32.95 Kg Portland Semen (PC)
0.091 m3 Pasir Pasang (PP)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.4.4.1.3 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Teba


A Tenaga
L.01 0.6 OH Pekerja
L.02 0.2 OH Tukang Batu

414275883.xlsx 432/211 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.02 OH Kepala Tukang Batu


L.04 0.03 OH Mandor
B Bahan
140 Buah Bata Merah
26.55 Kg Portland Semen (PC)
0.093 m3 Pasir Pasang (PP)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

4 A.4.4.1.4 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Teba


A Tenaga
L.01 0.6 OH Pekerja
L.02 0.2 OH Tukang Batu
L.03 0.02 OH Kepala Tukang Batu
L.04 0.03 OH Mandor
B Bahan
140 Buah Bata Merah
22.2 Kg Portland Semen (PC)
0.102 m3 Pasir Pasang (PP)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/212 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

5 A.4.4.1.5 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Teba


A Tenaga
L.01 0.6 OH Pekerja
L.02 0.2 OH Tukang Batu
L.03 0.02 OH Kepala Tukang Batu
L.04 0.03 OH Mandor
B Bahan
140 Buah Bata Merah
18.5 Kg Portland Semen (PC)
0.122 m3 Pasir Pasang (PP)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

6 A.4.4.1.6 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Teba


A Tenaga
L.01 0.6 OH Pekerja
L.02 0.2 OH Tukang Batu
L.03 0.02 OH Kepala Tukang Batu
L.04 0.03 OH Mandor
B Bahan
140 Buah Bata Merah
10.08 Kg Portland Semen (PC)
0.0925 m3 Pasir Pasang (PP)
0.0275 m3 Kapur Pasang (KP)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.4.4.1.7 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu

414275883.xlsx 432/213 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.01 OH Kepala Tukang


L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
18.95 Kg Portland Semen
0.038 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 A.4.4.1.8 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
14.37 Kg Portland Semen
0.04 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/214 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

9 A.4.4.1.9 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
11.50 Kg Portland Semen
0.043 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

10 A.4.4.1.10 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
9.68 Kg Portland Semen
0.045 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.4.4.1.11 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang

414275883.xlsx 432/215 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.015 OH Mandor


B Bahan
70 Buah Bata Merah 5 x 11 x 22
8.32 Kg Portland Semen
0.049 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

12 A.4.4.1.12 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
6.50 Kg Portland Semen
0.05 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/216 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

13 A.4.4.1.13 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
4.5 Kg Portland Semen
0.05 m3 Pasir Pasang
0.015 m3 Kapur Padam
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

14 A.4.4.1.14 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
0.018 m3 Semen Merah
0.018 m3 Pasir Pasang
0.018 m3 Kapur Padam
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

15 A.4.4.1.15 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal


A Tenaga
L.01 0.30 OH Pekerja

414275883.xlsx 432/217 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.02 0.1 OH Tukang Batu


L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
70 Buah Bata Merah 5 x 11 x 22
0.014 m3 Semen Merah
0.028 m3 Pasir Pasang
0.014 m3 Kapur Padam
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

16 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.100 OH Tukang Batu
L.03 0.010 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
12.500 buah Batako
15.160 kg PC
0.364 m3 Pasir Pasang
0.280 kg Besi Angkur Ø 8 mm

414275883.xlsx 432/218 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

17 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.100 OH Tukang Batu
L.03 0.010 OH Kepala Tukang
L.04 0.015 OH Mandor

B Bahan
12.500 buah Batako
12.130 kg PC
0.388 m3 Pasir Pasang
0.280 kg Besi Angkur Ø 8 mm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

18 A.4.4.1.22 1 m2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
30 Buah Terawang / Roster
14 kg Portland Semen
0.032 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

414275883.xlsx 432/219 abk 4-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

F Harga Satuan Pekerjaan (D+E)

19 A.4.4.1.23 1 m2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang Batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
30 Buah Terawang / Roster
11 kg Portland Semen
0.035 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/220 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

ERJAAN PASANGAN DINDING


ta Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP 224,224.00
55,080.00
57,000.00 34,200.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 2,340.00
148,760.00
520.00 72,800.00
1,360.00 59,160.00
210,000.00 16,800.00

203,840.00
10% 20,384.00
224,224.00

ta Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP 210,982.20


55,080.00
57,000.00 34,200.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 2,340.00
136,722.00
520.00 72,800.00
1,360.00 44,812.00
210,000.00 19,110.00

191,802.00
10% 19,180.20
210,982.20

ta Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP 201,869.80


55,080.00
57,000.00 34,200.00
84,000.00 16,800.00

414275883.xlsx 432/221 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

87,000.00 1,740.00
78,000.00 2,340.00
128,438.00
520.00 72,800.00
1,360.00 36,108.00
210,000.00 19,530.00

183,518.00
10% 18,351.80
201,869.80

ta Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP 197,441.20


55,080.00
57,000.00 34,200.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 2,340.00
124,412.00
520.00 72,800.00
1,360.00 30,192.00
210,000.00 21,420.00

179,492.00
10% 17,949.20
197,441.20

414275883.xlsx 432/222 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

ta Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP 196,526.00


55,080.00
57,000.00 34,200.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 2,340.00
123,580.00
520.00 72,800.00
1,360.00 25,160.00
210,000.00 25,620.00

178,660.00
10% 17,866.00
196,526.00

ta Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP 185,282.68


55,080.00
57,000.00 34,200.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 2,340.00
113,358.80
520.00 72,800.00
1,360.00 13,708.80
210,000.00 19,425.00
270,000.00 7,425.00

168,438.80
10% 16,843.88
185,282.68

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP 107,461.20
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00

414275883.xlsx 432/223 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

87,000.00 870.00
78,000.00 1,170.00
70,152.00
520.00 36,400.00
1,360.00 25,772.00
210,000.00 7,980.00

97,692.00
10% 9,769.20
107,461.20

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP 101,071.52
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
64,343.20
520.00 36,400.00
1,360.00 19,543.20
210,000.00 8,400.00

91,883.20
10% 9,188.32
101,071.52

414275883.xlsx 432/224 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP 97,471.00
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
61,070.00
520.00 36,400.00
1,360.00 15,640.00
210,000.00 9,030.00

88,610.00
10% 8,861.00
97,471.00

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP 95,210.28
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
59,014.80
520.00 36,400.00
1,360.00 13,164.80
210,000.00 9,450.00

86,554.80
10% 8,655.48
95,210.28

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP 94,099.72
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00

414275883.xlsx 432/225 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

78,000.00 1,170.00
58,005.20
520.00 36,400.00
1,360.00 11,315.20
210,000.00 10,290.00

85,545.20
10% 8,554.52
94,099.72

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP 91,608.00
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
55,740.00
520.00 36,400.00
1,360.00 8,840.00
210,000.00 10,500.00

83,280.00
10% 8,328.00
91,608.00

414275883.xlsx 432/226 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP 93,071.00
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
57,070.00
520.00 36,400.00
1,360.00 6,120.00
210,000.00 10,500.00
270,000.00 4,050.00

84,610.00
10% 8,461.00
93,071.00

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP 83,342.60
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
48,226.00
520.00 36,400.00
177,000.00 3,186.00
210,000.00 3,780.00
270,000.00 4,860.00

75,766.00
10% 7,576.60
83,342.60

ta Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP 83,685.80
27,540.00
57,000.00 17,100.00

414275883.xlsx 432/227 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
48,538.00
520.00 36,400.00
177,000.00 2,478.00
210,000.00 5,880.00
270,000.00 3,780.00

76,078.00
10% 7,607.80
83,685.80

/CB 10, speci camp. 1SP : 3PP 195,137.36


27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
149,857.60
4,000.00 50,000.00
1,360.00 20,617.60
210,000.00 76,440.00
10,000.00 2,800.00

414275883.xlsx 432/228 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

177,397.60
10% 17,739.76
195,137.36

/CB 10, speci camp. 1SP : 4PP 196,148.48


27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
150,776.80
4,000.00 50,000.00
1,360.00 16,496.80
210,000.00 81,480.00
10,000.00 2,800.00

178,316.80
10% 17,831.68
196,148.48

awang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP 246,730.00


27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
196,760.00
5,700.00 171,000.00
1,360.00 19,040.00
210,000.00 6,720.00

224,300.00
10% 22,430.00

414275883.xlsx 432/229 abk 4-14


HARGA BAHAN/UPAH JUMLAH
RAIAN PEKERJAAN
Rp Rp

246,730.00

awang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP 242,935.00


27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
193,310.00
5,700.00 171,000.00
1,360.00 14,960.00
210,000.00 7,350.00

220,850.00
10% 22,085.00
242,935.00

414275883.xlsx 432/230 abk 4-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A,4,4,2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm
A Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
15.504 Kg Portland Semen
0.016 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
2 A,4,4,2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm
A Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
10.224 Kg Portland Semen
0.020 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A,4,4,2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm


A Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
7.776 Kg Portland Semen
0.023 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

4 A,4,4,2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm


A Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
414275883.xlsx 432/231 abk 5-14
file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.015 OH Kepala Tukang


L.04 0.015 OH Mandor
B Bahan
6.240 Kg Portland Semen
0.024 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

5 A,4,4,2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm


A Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
5.184 Kg Portland Semen
0.026 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

6 A,4,4,2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm


Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
Bahan
4.416 Kg Portland Semen
0.027 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/232 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

7 A,4,4,2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm


A Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
3.936 Kg Portland Semen
0.028 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 A,4,4,2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm


A Tenaga
L.01 0.30 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
3.456 Kg Portland Semen
0.029 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm


A Tenaga
L.01 0.36 OH Pekerja
L.02 0.12 OH Tukang batu
L.03 0.012 OH Kepala Tukang
L.04 0.018 OH Mandor
B Bahan
5.760 Kg Portland Semen
0.003 m3 Kapur Pasang
0.013 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

10 A,4,4,2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm


A Tenaga
L.01 0.36 OH Pekerja
L.02 0.12 OH Tukang batu

414275883.xlsx 432/233 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.012 OH Kepala Tukang


L.04 0.018 OH Mandor
B Bahan
3 kg Portland Semen
0.005 m3 Kapur Padam
0.020 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A,4,4,2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm


A Tenaga
L.01 0.36 OH Pekerja
L.02 0.12 OH Tukang batu
L.03 0.012 OH Kepala Tukang
L.04 0.018 OH Mandor
B Bahan
0.009 m3 Semen Merah
0.009 m3 Kapur Padam
0.009 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

12 A,4,4,2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm


A Tenaga
L.01 0.36 OH Pekerja
L.02 0.12 OH Tukang batu
L.03 0.012 OH Kepala Tukang
L.04 0.018 OH Mandor
B Bahan
0.007 m3 Semen Merah
0.007 m3 Kapur Padam
0.015 m3 Pasir Pasang

414275883.xlsx 432/234 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

13 A,4,4,2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm


A Tenaga
L.01 0.40 OH Pekerja
L.02 0.20 OH Tukang batu
L.03 0.020 OH Kepala Tukang
L.04 0.022 OH Mandor
B Bahan
13.632 kg Portland Semen
0.027 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

14 A,4,4,2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm


A Tenaga
L.01 0.26 OH Pekerja
L.02 0.2 OH Tukang batu
L.03 0.02 OH Kepala Tukang
L.04 0.013 OH Mandor
B Bahan
10.368 Kg Portland Semen
0.031 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
15 A,4,4,2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm
A Tenaga
L.01 0.40 OH Pekerja
L.02 0.20 OH Tukang batu
L.03 0.020 OH Kepala Tukang
L.04 0.022 OH Mandor
B Bahan
8.320 kg Portland Semen
0.032 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

16 A,4,4,2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm

414275883.xlsx 432/235 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

A Tenaga
L.01 0.400 OH Pekerja
L.02 0.200 OH Tukang batu
L.03 0.020 OH Kepala Tukang
L.04 0.022 OH Mandor
B Bahan
6.912 Kg Portland Semen
0.035 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

17 A,4,4,2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm


A Tenaga
L.01 0.40 OH Pekerja
L.02 0.2 OH Tukang batu
L.03 0.02 OH Kepala Tukang
L.04 0.022 OH Mandor
B Bahan
5.888 Kg Portland Semen
0.036 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

18 A,4,4,2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm


A Tenaga
L.01 0.440 OH Pekerja
L.02 0.22 OH Tukang batu
L.03 0.022 OH Kepala Tukang
L.04 0.022 OH Mandor

414275883.xlsx 432/236 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
0.009 m3 Semen Merah
0.009 m3 Kapur Padam
0.018 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

19 A,4,4,2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.075 OH Tukang batu
L.03 0.008 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
5.184 Kg Portland Semen
0.026 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

20 A,4,4,2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm


A Tenaga
L.01 0.080 OH Pekerja
L.02 0.40 OH Tukang batu
L.03 0.040 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan
0.5 Kg Portland Semen
0.013 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

21 A,4,4,2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp


Tenaga
L.01 0.30 OH Pekerja
L.02 0.1 OH Tukang batu
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
Bahan
4.32 Kg Portland Semen
0.006 m3 Pasir Pasang
C PERALATAN

414275883.xlsx 432/237 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

22 A,4,4,2.24 1 m2 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.075 OH Tukang batu
L.03 0.008 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
3.108 Kg Portland Semen
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

23 A,4,4,2.25 1 m2 Pemasangan Finishing Siar Pasangan Dinding Conblock ek


A Tenaga
L.01 0.070 OH Pekerja
L.02 0.035 OH Tukang batu
L.03 0.004 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan
1.600 Kg Portland Semen
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

24 A,4,4,2.26 1 m2 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp


Tenaga
L.01 0.3 OH Pekerja
L.02 0.15 OH Tukang batu
L.03 0.015 OH Kepala Tukang
L.04 0.015 OH Mandor

414275883.xlsx 432/238 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

Bahan
6.34 Kg Pc
0.012 m3 PP
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

25 A,4,4,2.27 1 m2 Pemasangan Acian


Tenaga
L.01 0.20 OH Pekerja
L.02 0.10 OH Tukang batu
L.03 0.010 OH Kepala Tukang
L.04 0.010 OH Mandor
Bahan
3.25 Kg Portland Semen
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/239 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

eran 1 Pc : 1 Pp Tebal 15 mm 62,282.48


32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
24,445.44
1,360.00 21,085.44
210,000.00 3,360.00

56,620.44
10% 5,662.04
62,282.48

eran 1 Pc : 2 Pp Tebal 15 mm 55,307.60


32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
18,104.64
1,360.00 13,904.64
210,000.00 4,200.00

50,279.64
10% 5,027.96
55,307.60
eran 1 Pc : 3 Pp Tebal 15 mm 52,338.40
32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
15,405.36
1,360.00 10,575.36
210,000.00 4,830.00

47,580.36
10% 4,758.04
52,338.40
eran 1 Pc : 4 Pp Tebal 15 mm 50,271.54
32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
414275883.xlsx 432/240 abk 5-14
file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

87,000.00 1,305.00
78,000.00 1,170.00
13,526.40
1,360.00 8,486.40
210,000.00 5,040.00

45,701.40
10% 4,570.14
50,271.54
eran 1 Pc : 5 Pp Tebal 15 mm 49,153.76
32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
12,510.24
1,360.00 7,050.24
210,000.00 5,460.00

44,685.24
10% 4,468.52
49,153.76
eran 1 Pc : 6 Pp Tebal 15 mm 48,235.84
32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
11,675.76
1,360.00 6,005.76
210,000.00 5,670.00

43,850.76
10% 4,385.08
48,235.84

414275883.xlsx 432/241 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

eran 1 Pc : 7 Pp Tebal 15 mm 47,748.76


32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
11,232.96
1,360.00 5,352.96
210,000.00 5,880.00

43,407.96
10% 4,340.80
47,748.76
eran 1 Pc : 8 Pp Tebal 15 mm 47,261.68
32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00
10,790.16
1,360.00 4,700.16
210,000.00 6,090.00

42,965.16
10% 4,296.52
47,261.68
eran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm 48,863.76
33,048.00
57,000.00 20,520.00
84,000.00 10,080.00
87,000.00 1,044.00
78,000.00 1,404.00
11,373.60
1,360.00 7,833.60
270,000.00 810.00
210,000.00 2,730.00

44,421.60
10% 4,442.16
48,863.76
eran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 46,945.80
33,048.00
57,000.00 20,520.00
84,000.00 10,080.00

414275883.xlsx 432/242 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

87,000.00 1,044.00
78,000.00 1,404.00
9,630.00
1,360.00 4,080.00
270,000.00 1,350.00
210,000.00 4,200.00

42,678.00
10% 4,267.80
46,945.80
eran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 42,857.10
33,048.00
57,000.00 20,520.00
84,000.00 10,080.00
87,000.00 1,044.00
78,000.00 1,404.00
5,913.00
177,000.00 1,593.00
270,000.00 2,430.00
210,000.00 1,890.00

38,961.00
10% 3,896.10
42,857.10
eran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 43,259.70
33,048.00
57,000.00 20,520.00
84,000.00 10,080.00
87,000.00 1,044.00
78,000.00 1,404.00
6,279.00
177,000.00 1,239.00
270,000.00 1,890.00
210,000.00 3,150.00

414275883.xlsx 432/243 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

39,327.00
10% 3,932.70
43,259.70
eran 1 Pc : 2 Pp Tebal 20 mm 73,992.07
43,056.00
57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 1,716.00
24,209.52
1,360.00 18,539.52
210,000.00 5,670.00

67,265.52
10% 6,726.55
73,992.07
eran 1Pc : 3Pp Tebal 20 mm 54,984.48
34,374.00
57,000.00 14,820.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 1,014.00
20,610.48
1,360.00 14,100.48
210,000.00 6,510.00

55,998.48
10% 5,599.85
61,598.33
eran 1 Pc : 4 Pp Tebal 20 mm 67,200.32
43,056.00
57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 1,716.00
18,035.20
1,360.00 11,315.20
210,000.00 6,720.00

61,091.20
10% 6,109.12
67,200.32
eran 1Pc : 5Pp Tebal 20 mm 65,786.95

414275883.xlsx 432/244 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

43,056.00
57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 1,716.00
16,750.32
1,360.00 9,400.32
210,000.00 7,350.00

59,806.32
10% 5,980.63
65,786.95
eran 1Pc : 6Pp Tebal 20 mm 64,486.05
43,056.00
57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 1,716.00
15,567.68
1,360.00 8,007.68
210,000.00 7,560.00

58,623.68
10% 5,862.37
64,486.05
eran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 60,492.30
47,190.00
57,000.00 25,080.00
84,000.00 18,480.00
87,000.00 1,914.00
78,000.00 1,716.00

414275883.xlsx 432/245 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

7,803.00
177,000.00 1,593.00
270,000.00 2,430.00
210,000.00 3,780.00

54,993.00
10% 5,499.30
60,492.30
en 1 Pc : 5Pp Tebal 15 mm 31,548.26
16,170.00
57,000.00 8,550.00
84,000.00 6,300.00
87,000.00 696.00
78,000.00 624.00
12,510.24
1,360.00 7,050.24
210,000.00 5,460.00

28,680.24
10% 2,868.02
31,548.26
eran Skoning 1 Pc : 2Pp, lebar 10 mm 49,898.20
41,952.00
57,000.00 4,560.00
84,000.00 33,600.00
87,000.00 3,480.00
78,000.00 312.00
3,410.00
1,360.00 680.00
210,000.00 2,730.00

45,362.00
10% 4,536.20
49,898.20
38,142.72
27,540.00
57,000.00 17,100.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 1,170.00
7,135.20
1,360.00 5,875.20
210,000.00 1,260.00

414275883.xlsx 432/246 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

34,675.20
10% 3,467.52
38,142.72
hing Siar Pasangan Dinding Bata Merah (=20 m') 22,436.57
16,170.00
57,000.00 8,550.00
84,000.00 6,300.00
87,000.00 696.00
78,000.00 624.00
4,226.88
1,360.00 4,226.88

20,396.88
10% 2,039.69
22,436.57
hing Siar Pasangan Dinding Conblock ekspose (=8 m') 10,742.60
7,590.00
57,000.00 3,990.00
84,000.00 2,940.00
87,000.00 348.00
78,000.00 312.00
2,176.00
1,360.00 2,176.00

9,766.00
10% 976.60
10,742.60
hing Siar Pas.Batu Kali Adukan 1Pc : 2Pp 47,649.14
32,175.00
57,000.00 17,100.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 1,170.00

414275883.xlsx 432/247 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

11,142.40
1,360.00 8,622.40
210,000.00 2,520.00

43,317.40
10% 4,331.74
47,649.14

28,457.00
21,450.00
57,000.00 11,400.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 780.00
4,420.00
1,360.00 4,420.00

25,870.00
10% 2,587.00
28,457.00

414275883.xlsx 432/248 abk 5-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U


1 A.4.6.1.1 1 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Ka
A Tenaga
L.01 7 OH Pekerja
L.02 21 OH Tukang Kayu
L.03 2.10 OH Kepala Tukang
L.04 0.35 OH Mandor
B Bahan
1.1 m3 Kayu Klas I (Jati) , Balok
1.25 kg Paku Biasa 2" - 5 "
1 kg Lem Kayu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

2 A.4.6.1.2 1 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Ka


Tenaga
L.01 6.00 OH Pekerja
L.02 18.00 OH Tukang Kayu
L.03 1.80 OH Kepala Tukang
L.04 0.30 OH Mandor
Bahan
1.2 m3 Kayu Klas II (Kamfer) , Balok
1.25 kg Paku Biasa 2" - 5 "
1 kg Lem Kayu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.4.6.1.3 1 m2 Pembuatan & Pemasangan Pintu KlampStandard Kayu


A Tenaga
L.01 0.35 OH Pekerja
L.02 1.05 OH Tukang Kayu
L.03 0.105 OH Kepala Tukang
L.04 0.018 OH Mandor
B Bahan
0.040 m3 Kayu Klas II (Kamfer), papan

414275883.xlsx 432/249 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.05 Kg Paku Biasa 2" - 5 "


C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

4 A.4.6.1.4 1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederha


Tenaga
L.01 0.35 OH Pekerja
L.02 1.05 OH Tukang Kayu
L.03 0.105 OH Kepala Tukang
L.04 0.018 OH Mandor
Bahan
0.040 m3 Kayu Klas II (Kamfer), papan
0.05 Kg Paku Biasa 2" - 5 "
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

5 A.4.6.1.5 1 m2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Kl


A Tenaga
L.01 1.00 OH Pekerja
L.02 3.00 OH Tukang Kayu
L.03 0.30 OH Kepala Tukang
L.04 0.05 OH Mandor
B Bahan
0.04 m3 Kayu Klas II (Kamfer), papan
0.050 kg Lem Kayu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/250 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

6 A.4.6.1.6 1 m2 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu


A Tenaga
L.01 0.800 OH Pekerja
L.02 2.400 OH Tukang Kayu
L.03 0.240 OH Kepala Tukang
L.04 0.040 OH Mandor
B Bahan
0.024 m3 Kayu Klas II (Kamfer), papan
0.300 kg Lem Kayu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.4.6.1.7 1 m2 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kay


A Tenaga
L.01 1 OH Pekerja
L.02 3 OH Tukang Kayu
L.03 0.3 OH Kepala Tukang
L.04 0.05 OH Mandor
B Bahan
0.064 m3 Kayu Klas I (Jati), papan
0.5 kg Lem Kayu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 A.4.6.1.8 1 m2 Pembuatan&Pemasangan Pintu kayu lapis (Plywood) Rangk


A Tenaga
L.01 0.700 OH Pekerja
L.02 2.100 OH Tukang Kayu
L.03 0.210 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
0.025 m3 Kayu Klas II (Kamfer), papan
0.030 Kg Paku Biasa 1/2" - 1"
0.500 Ltr Lem Kayu
1.000 Lbr Plywood tebal 4 mm uk.90x220cm

414275883.xlsx 432/251 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.4.6.1.9 1 m2 Pembuatan&Pemasangan Pintu Plywood rangkap, ran


A Tenaga
L.01 0.800 OH Pekerja
L.02 2.400 OH Tukang Kayu
L.03 0.240 OH Kepala Tukang
L.04 0.040 OH Mandor
B Bahan
0.0256 m3 Kayu Klas II (Kamfer), papan
0.03 Kg Paku Biasa 1/2" - 1"
0.5 Ltr Lem Kayu
1 Lbr Plywood tebal 4 mm uk.90x220cm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

10 A.4.6.1.10 1 m2 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Kl


A Tenaga
L.01 0.670 OH Pekerja
L.02 2.000 OH Tukang Kayu
L.03 0.200 OH Kepala Tukang
L.04 0.335 OH Mandor
B Bahan
0.06 m3 Kayu Klas I (Jati), papan
0.15 Kg Paku Biasa 1/2" - 1"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/252 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

11 A.4.6.1.11 1 m2 Pembuatan & Pemasangan Pintu Teakwood Rangkap,


A Tenaga
L.01 0.80 OH Pekerja
L.02 2.40 OH Tukang Kayu
L.03 0.24 OH Kepala Tukang
L.04 0.04 OH Mandor
B Bahan
0.025 m3 Kayu Klas I (Jati), papan
0.03 Kg Paku Biasa 1/2" - 1"
0.3 kg Lem Kayu
1 Lbr Teakwood (90 x 220) cm x 4 mm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

12 A.4.6.1.12 1 m2 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis F


A Tenaga
L.01 0.850 OH Pekerja
L.02 2.550 OH Tukang Kayu
L.03 0.255 OH Kepala Tukang
L.04 0.043 OH Mandor
B Bahan
0.025 m3 Kayu Klas II (Kamfer), papan
0.03 Kg Paku Biasa 1/2" - 1"
0.08 kg Lem Kayu
1 Lbr Teakwood (90 x 220) cm x 4 mm
0.5 Lbr Formika
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

13 A.4.6.1.13 1 m3 Pembuatan&Memasang Konstruksi Kuda-kuda Konven


A Tenaga
L.01 4 OH Pekerja
L.02 12 OH Tukang Kayu
L.03 1.2 OH Kepala Tukang
L.04 0.2 OH Mandor

414275883.xlsx 432/253 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
1.1 m3 Kayu Kamfer, balok
15 Kg Besi Strip
5.6 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

14 A.4.6.1.14 1 m3 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expo


A Tenaga
L.01 6.7 OH Pekerja
L.02 20.1 OH Tukang Kayu
L.03 2.01 OH Kepala Tukang
L.04 0.335 OH Mandor
B Bahan
1.2 m3 Kayu Klas I (jati), balok
15 Kg Besi Strip
5.6 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II


A Tenaga
L.01 2.4 OH Pekerja
L.02 7.2 OH Tukang Kayu
L.03 0.72 OH Kepala Tukang
L.04 0.12 OH Mandor
B Bahan
1.1 m3 Kayu Klas I (Kamfer), balok
15 Kg Besi Strip
3 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/254 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

16 A.4.6.1.16 1 m2 Pemasangan Rangka Atap Genteng Keramik, Kayu Kla


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm
0.0036 m3 Reng (2x3) cm
0.25 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

17 A.4.6.1.17 1 m2 Pemasangan Rangka Atap Genteng Beton, Kayu Klas


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm
0.0072 m3 Reng (2x3) cm
0.25 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II


A Tenaga
L.01 0.12 OH Pekerja
L.02 0.12 OH Tukang Kayu
L.03 0.012 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan
0.014 m3 Kayu Klas II (Kamfer), balok

414275883.xlsx 432/255 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.2 Kg Paku Biasa 2" - 5"


C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

19 A.4.6.1.19 1 m2 Pemasangan Rangka Langit-langit (50x1,00) m, kayu K


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.30 OH Tukang Kayu
L.03 0.030 OH Kepala Tukang
L.04 0.075 OH Mandor
B Bahan
0.0154 m3 Kayu Klas II (Kamfer), balok
0.2 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

20 A.4.6.1.20 1 m2 Pemasangan Rangka Langit-langit (60x60) cm, kayu K


A Tenaga
L.01 0.2 OH Pekerja
L.02 0.3 OH Tukang Kayu
L.03 0.03 OH Kepala Tukang
L.04 0.01 OH Mandor
B Bahan
0.0163 m3 Kayu Klas II (Kamfer), balok
0.25 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/256 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

21 A.4.6.1.21 1 m' Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau I


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.020 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
0.0108 m3 Kayu klas I (Jati), papan
0.10 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

22 A.4.6.1.22 1 m' Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau k


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
0.011 m3 Kayu klas II (Kamfer), papan
0.05 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

23 A.4.6.1.23 1 m2 Pemasangan Rangka Dinding Pemisah (60x120) cm K


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.45 OH Tukang Kayu
L.03 0.045 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
0.028 m3 Kayu klas II (Kamfer), balok
0.15 Kg Paku Biasa 2" - 5"
C PERALATAN
D Jumlah A + B + C

414275883.xlsx 432/257 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

24 A.4.6.1.24 1 m2 Pemasangan Dinding Pemisah Teakwood Rangkap Ra


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.45 OH Tukang Kayu
L.03 0.045 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
0.028 m3 Kayu klas II (Kamfer), balok
0.15 Kg Paku Biasa 2" - 5"
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm
0.56 Ltr Lem
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

25 A.4.6.1.25 1 m2 Pemasangan Dinding Pemisah Plywood Rangkap Ran


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.600 OH Tukang Kayu
L.03 0.060 OH Kepala Tukang
L.04 0.010 OH Mandor
B Bahan
0.028 m3 Kayu klas II (Kamfer), balok
0.15 Kg Paku Biasa 2" - 5"
0.86 Lbr Plywood 120 x 240 cm tebal 4mm
0.56 Ltr Lem
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/258 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan klas I


A Tenaga
L.01 0.6 OH Pekerja
L.02 1.8 OH Tukang Kayu
L.03 0.18 OH Kepala Tukang
L.04 0.03 OH Mandor
B Bahan
0.007 m3 Kayu klas I (Jati), papan
0.1 Kg Paku Biasa 2" - 5"
0.15 Kg Paku Sekrup 3,5"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

27 A.4.6.1.27 1 m2 Pemasangan Dinding Lambriziring dari Plywood ukur


A Tenaga
L.01 0.025 OH Pekerja
L.02 0.075 OH Tukang Kayu
L.03 0.0080 OH Kepala Tukang
L.04 0.0010 OH Mandor
B Bahan
0.4 Lbr Plywood (120 X 240) cm x 4mm
0.05 Kg Paku Biasa 1/2" - 1"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

28 A.4.6.1.28 1 m2 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau I


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.05 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1.500 m2 Bilik Bambu
0.014 m3 Kayu Klas III (Meranti)
0.012 Kg Paku Biasa 1/2" - 1"

414275883.xlsx 432/259 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.003 m' List Kayu 2/4


C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/260 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

masangan Kosen Pintu & Jendela Kayu klas I 26,851,000.00


2,373,000.00
57,000.00 399,000.00
84,000.00 1,764,000.00
87,000.00 182,700.00
78,000.00 27,300.00
22,037,000.00
20,000,000.00 22,000,000.00
14,000.00 17,500.00
19,500.00 19,500.00

24,410,000.00
10% 2,441,000.00
26,851,000.00

masangan Kosen Pintu & Jendela Kayu klas II atau III 11,518,100.00
2,034,000.00
57,000.00 342,000.00
84,000.00 1,512,000.00
87,000.00 156,600.00
78,000.00 23,400.00
8,437,000.00
7,000,000.00 8,400,000.00
14,000.00 17,500.00
19,500.00 19,500.00

10,471,000.00
10% 1,047,100.00
11,518,100.00

masangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer) 465,727.90


118,689.00
57,000.00 19,950.00
84,000.00 88,200.00
87,000.00 9,135.00
78,000.00 1,404.00
304,700.00
7,600,000.00 304,000.00

414275883.xlsx 432/261 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

14,000.00 700.00

423,389.00
10% 42,338.90
465,727.90

masangan Daun Pintu Klamp Sederhana Kayu Klas III 465,727.90


118,689.00
57,000.00 19,950.00
84,000.00 88,200.00
87,000.00 9,135.00
78,000.00 1,404.00
304,700.00
7,600,000.00 304,000.00
14,000.00 700.00

423,389.00
10% 42,338.90
465,727.90

masangan Daun Pintu Panel, Kayu Klas I atau II 708,372.50


339,000.00
57,000.00 57,000.00
84,000.00 252,000.00
87,000.00 26,100.00
78,000.00 3,900.00
304,975.00
7,600,000.00 304,000.00
19,500.00 975.00

643,975.00
10% 64,397.50
708,372.50

414275883.xlsx 432/262 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

masangan Pintu & Jendela Kaca Kayu Klas I atau II 505,395.00


271,200.00
57,000.00 45,600.00
84,000.00 201,600.00
87,000.00 20,880.00
78,000.00 3,120.00
188,250.00
7,600,000.00 182,400.00
19,500.00 5,850.00

459,450.00
10% 45,945.00
505,395.00

masangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) 1,932,425.00
339,000.00
57,000.00 57,000.00
84,000.00 252,000.00
87,000.00 26,100.00
78,000.00 3,900.00
1,417,750.00
22,000,000.00 1,408,000.00
19,500.00 9,750.00

1,756,750.00
10% 175,675.00
1,932,425.00

angan Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 c 553,817.00
237,300.00
57,000.00 39,900.00
84,000.00 176,400.00
87,000.00 18,270.00
78,000.00 2,730.00
266,170.00
7,600,000.00 190,000.00
14,000.00 420.00
19,500.00 9,750.00
66,000.00 66,000.00

414275883.xlsx 432/263 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

503,470.00
10% 50,347.00
553,817.00

asangan Pintu Plywood rangkap, rangka expose kayu klas I atau II 596,123.00
271,200.00
57,000.00 45,600.00
84,000.00 201,600.00
87,000.00 20,880.00
78,000.00 3,120.00
270,730.00
7,600,000.00 194,560.00
14,000.00 420.00
19,500.00 9,750.00
66,000.00 66,000.00

541,930.00
10% 54,193.00
596,123.00

masangan Jalusi mati Kosen Kayu Klas I atau II 1,729,002.00


249,720.00
57,000.00 38,190.00
84,000.00 168,000.00
87,000.00 17,400.00
78,000.00 26,130.00
1,322,100.00
22,000,000.00 1,320,000.00
14,000.00 2,100.00

1,571,820.00
10% 157,182.00
1,729,002.00

414275883.xlsx 432/264 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

masangan Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I 982,817.00


271,200.00
57,000.00 45,600.00
84,000.00 201,600.00
87,000.00 20,880.00
78,000.00 3,120.00
622,270.00
22,000,000.00 550,000.00
14,000.00 420.00
19,500.00 5,850.00
66,000.00 66,000.00

893,470.00
10% 89,347.00
982,817.00

angan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II 639,285.90
288,189.00
57,000.00 48,450.00
84,000.00 214,200.00
87,000.00 22,185.00
78,000.00 3,354.00
292,980.00
7,600,000.00 190,000.00
14,000.00 420.00
19,500.00 1,560.00
66,000.00 66,000.00
70,000.00 35,000.00

581,169.00
10% 58,116.90
639,285.90

asang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 10,254,090.00


1,356,000.00
57,000.00 228,000.00
84,000.00 1,008,000.00
87,000.00 104,400.00
78,000.00 15,600.00

414275883.xlsx 432/265 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

7,965,900.00
7,000,000.00 7,700,000.00
12,500.00 187,500.00
14,000.00 78,400.00

9,321,900.00
10% 932,190.00
10,254,090.00

asangan Konstruksi Kuda-kuda Expose, Kayu Klas I 29,190,920.00


2,271,300.00
57,000.00 381,900.00
84,000.00 1,688,400.00
87,000.00 174,870.00
78,000.00 26,130.00
24,265,900.00
20,000,000.00 24,000,000.00
12,500.00 187,500.00
14,000.00 78,400.00

26,537,200.00
10% 2,653,720.00
29,190,920.00

struksi Gording, Kayu Klas II 9,617,410.00


813,600.00
57,000.00 136,800.00
84,000.00 604,800.00
87,000.00 62,640.00
78,000.00 9,360.00
7,929,500.00
7,000,000.00 7,700,000.00
12,500.00 187,500.00
14,000.00 42,000.00

8,743,100.00
10% 874,310.00
9,617,410.00

414275883.xlsx 432/266 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

gka Atap Genteng Keramik, Kayu Klas II 156,266.00


15,360.00
57,000.00 5,700.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 390.00
126,700.00
7,000,000.00 98,000.00
7,000,000.00 25,200.00
14,000.00 3,500.00

142,060.00
10% 14,206.00
156,266.00

gka Atap Genteng Beton, Kayu Klas II 183,986.00


15,360.00
57,000.00 5,700.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 390.00
151,900.00
7,000,000.00 98,000.00
7,000,000.00 50,400.00
14,000.00 3,500.00

167,260.00
10% 16,726.00
183,986.00

gka Atap Sirap, Kayu Klas II 131,155.20


18,432.00
57,000.00 6,840.00
84,000.00 10,080.00
87,000.00 1,044.00
78,000.00 468.00
100,800.00
7,000,000.00 98,000.00

414275883.xlsx 432/267 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

14,000.00 2,800.00

119,232.00
10% 11,923.20
131,155.20

gka Langit-langit (50x1,00) m, kayu Klas II atau III 168,091.00


42,210.00
57,000.00 8,550.00
84,000.00 25,200.00
87,000.00 2,610.00
78,000.00 5,850.00
110,600.00
7,000,000.00 107,800.00
14,000.00 2,800.00

152,810.00
10% 15,281.00
168,091.00

gka Langit-langit (60x60) cm, kayu Klas II atau III 173,349.00


39,990.00
57,000.00 11,400.00
84,000.00 25,200.00
87,000.00 2,610.00
78,000.00 780.00
117,600.00
7,000,000.00 114,100.00
14,000.00 3,500.00

157,590.00
10% 15,759.00
173,349.00

414275883.xlsx 432/268 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

plank Uk. (3x20)cm Kayu klas I atau II 289,993.00


24,630.00
57,000.00 5,700.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 390.00
239,000.00
22,000,000.00 237,600.00
14,000.00 1,400.00

263,630.00
10% 26,363.00
289,993.00

plank Uk. (3x30)cm Kayu klas I atau klas II 119,823.00


24,630.00
57,000.00 5,700.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 390.00
84,300.00
7,600,000.00 83,600.00
14,000.00 700.00

108,930.00
10% 10,893.00
119,823.00

gka Dinding Pemisah (60x120) cm Kayu klas II atau III 273,887.90


50,889.00
57,000.00 8,550.00
84,000.00 37,800.00
87,000.00 3,915.00
78,000.00 624.00
198,100.00
7,000,000.00 196,000.00
14,000.00 2,100.00

248,989.00

414275883.xlsx 432/269 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

10% 24,898.90
273,887.90

ding Pemisah Teakwood Rangkap Rangka Kayu Klas II 348,335.90


50,889.00
57,000.00 8,550.00
84,000.00 37,800.00
87,000.00 3,915.00
78,000.00 624.00
265,780.00
7,000,000.00 196,000.00
14,000.00 2,100.00
66,000.00 56,760.00
19,500.00 10,920.00

316,669.00
10% 31,666.90
348,335.90

ding Pemisah Plywood Rangkap Rangka Kayu Klas II 355,652.00


57,540.00
57,000.00 1,140.00
84,000.00 50,400.00
87,000.00 5,220.00
78,000.00 780.00
265,780.00
7,000,000.00 196,000.00
14,000.00 2,100.00
66,000.00 56,760.00
19,500.00 10,920.00

323,320.00
10% 32,332.00
355,652.00

414275883.xlsx 432/270 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

ding Lambriziring dari Papan klas I 395,917.50


203,400.00
57,000.00 34,200.00
84,000.00 151,200.00
87,000.00 15,660.00
78,000.00 2,340.00
156,525.00
22,000,000.00 154,000.00
14,000.00 1,400.00
7,500.00 1,125.00

359,925.00
10% 35,992.50
395,917.50

ding Lambriziring dari Plywood ukuran (120x240) cm 37,838.90


8,499.00
57,000.00 1,425.00
84,000.00 6,300.00
87,000.00 696.00
78,000.00 78.00
25,900.00
63,000.00 25,200.00
14,000.00 700.00

34,399.00
10% 3,439.90
37,838.90

ding Bilik, Rangka Kayu Klas III atau IV 120,458.14


10,725.00
57,000.00 5,700.00
84,000.00 4,200.00
87,000.00 435.00
78,000.00 390.00
98,782.40
20,000.00 30,000.00
4,900,000.00 68,600.00
14,000.00 168.00

414275883.xlsx 432/271 abk 6-14


file:///conversion/tmp/scratch/414275883.xlsx

HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

4,800.00 14.40

109,507.40
10% 10,950.74
120,458.14

414275883.xlsx 432/272 abk 6-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.1 1 m3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87
A Tenaga
L.01 1.65 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
247 Kg Portland Semen
869 Kg Pasir Beton
999 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
2 A.4.1.1.2 1 m3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78
A Tenaga
L.01 1.65 OH Pekerja
L.02 0.28 OH Tukang Batu
L.03 0.03 OH Kepala Tukang
L.04 0.08 OH Mandor
B Bahan
276 Kg Portland Semen
828 kg Pasir Beton
1,012 kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

3 A.4.1.1.3 1.00 m3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
A Tenaga
L.01 1.65 OH Pekerja
L.02 0.28 OH Tukang Batu
L.03 0.03 OH Kepala Tukang
L.04 0.08 OH Mandor
B Bahan
299 Kg Portland Semen
799 kg Pasir Beton
414275883.xlsx 432/273 abk 7-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

1,017 kg Kerikil (maksimum 30 mm)


215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

4 A.4.1.1.4 1.00 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm,
A Tenaga
L.01 1.200 OH Pekerja
L.02 0.200 OH Tukang Batu
L.03 0.020 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan
230 Kg Portland Semen
893 kg Pasir Beton
1,027 kg Kerikil (maksimum 30 mm)
200 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

5 A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A Tenaga
L.01 1.65 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
326 Kg Portland Semen
760 Kg Pasir Beton
1,029 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/274 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

6 A.4.1.1.6 1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A Tenaga
L.01 1.650 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
352 Kg Portland Semen
731 Kg Pasir Beton
1,031 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

7 A.4.1.1.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A Tenaga
L.01 1.650 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
371 Kg Portland Semen
698 Kg Pasir Beton
1,047 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

8 A.4.1.1.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A Tenaga
L.01 1.650 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
384 Kg Portland Semen

414275883.xlsx 432/275 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

692 Kg Pasir Beton


1,039 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

9 A.4.1.1.9 1 m3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)c
A Tenaga
L.01 1.650 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
406 Kg Portland Semen
684 kg Pasir Beton
1,026 kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
10 A.4.1.1.10 1 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A Tenaga
L.01 1.650 OH Pekerja
L.02 0.275 OH Tukang Batu
L.03 0.028 OH Kepala Tukang
L.04 0.083 OH Mandor
B Bahan
413 Kg Portland Semen
681 Kg Pasir Beton
1,021 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/276 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

11 A.4.1.1.11 1 m3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49
A Tenaga
L.01 2.1 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.105 OH Mandor
B Bahan
439 Kg Portland Semen
670 Kg Pasir Beton
1,006 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

12 A.4.1.1.12 1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48
A Tenaga
L.01 2.10 OH Pekerja
L.02 0.350 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.105 OH Mandor
B Bahan
448 Kg Portland Semen
667 Kg Pasir Beton
1,000 Kg Kerikil (maksimum 30 mm)
215 ltr Air
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir


A Tenaga
L.01 0.07 OH Pekerja
L.02 0.07 OH Tukang Besi
L.03 0.007 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan
10.50 Kg Besi Beton (polos/ulir)

414275883.xlsx 432/277 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.150 Kg Kawat Beton


C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand


A Tenaga
L.01 0.05 OH Pekerja
L.02 0.05 OH Tukang Besi
L.03 0.005 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
10.5 Kg Besi presstred polos
0.1 Kg Kawat Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh


A Tenaga
L.01 0.025 OH Pekerja
L.02 0.025 OH Tukang Besi
L.03 0.002 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
10.20 Kg Jaring Kawat Baja dilas
0.05 Kg Kawat Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi


A Tenaga
L.01 0.52 OH Pekerja
L.02 0.26 OH Tukang Kayu

414275883.xlsx 432/278 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.026 OH Kepala Tukang


L.04 0.026 OH Mandor
B Bahan
0.04 m3 Kayu Klas III (Terentang)
0.3 Kg Paku Biasa 2" - 5"
0.1 Ltr Minyak Bekisting
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof


A Tenaga
L.01 0.52 OH Pekerja
L.02 0.26 OH Tukang Kayu
L.03 0.026 OH Kepala Tukang
L.04 0.026 OH Mandor
B Bahan
0.045 m3 Kayu Klas III (Terentang)
0.3 Kg Paku Biasa 2" - 5"
0.1 Ltr Minyak Bekisting
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom


A Tenaga
L.01 0.66 OH Pekerja
L.02 0.33 OH Tukang Kayu
L.03 0.033 OH Kepala Tukang
L.04 0.033 OH Mandor
B Bahan
0.04 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m
C PERALATAN

414275883.xlsx 432/279 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok


A Tenaga
L.01 0.66 OH Pekerja
L.02 0.33 OH Tukang Kayu
L.03 0.033 OH Kepala Tukang
L.04 0.033 OH Mandor
B Bahan
0.04 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.018 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai


A Tenaga
L.01 0.66 OH Pekerja
L.02 0.33 OH Tukang Kayu
L.03 0.033 OH Kepala Tukang
L.04 0.033 OH Mandor
B Bahan
0.04 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas II (Borneo)
0.35 Lbr Plywood tebal 9mm
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

414275883.xlsx 432/280 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

F Harga Satuan Pekerjaan (D+E)

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding


A Tenaga
L.01 0.66 OH Pekerja
L.02 0.33 OH Tukang Kayu
L.03 0.033 OH Kepala Tukang
L.04 0.033 OH Mandor
B Bahan
0.03 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.02 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m
4 Buah Formite/Penjaga jarak / Spacer (alat bantu)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga


A Tenaga
L.01 0.66 OH Pekerja
L.02 0.33 OH Tukang Kayu
L.03 0.033 OH Kepala Tukang
L.04 0.033 OH Mandor
B Bahan
0.03 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.15 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor

414275883.xlsx 432/281 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

A Tenaga
L.01 0.15 OH Pekerja
L.02 0.05 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
0.0264 m3 Kayu Terentang
0.6 kg Paku Biasa 2" - 5"
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

24 A.4.1.1.28 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting)


A Tenaga
L.01 5.3 OH Pekerja
L.02 0.275 OH Tukang batu
L.02 1.30 OH Tukang Kayu
L.02 1.05 OH Tukang Besi
L.03 0.262 OH Kepala Tukang
L.04 0.265 OH Mandor
B Bahan
0.2 m3 Kayu Klas III (Terentang)
1.5 Kg Paku Biasa 2" - 5"
0.4 Ltr Minyak Bekisting
157.5 Kg Besi Beton Polos
2.25 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

25 A.4.1.1.29 1 m3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting)


A Tenaga

414275883.xlsx 432/282 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.01 5.65 OH Pekerja


L.02 0.275 OH Tukang batu
L.02 1.56 OH Tukang Kayu
L.02 1.4 OH Tukang Besi
L.03 0.323 OH Kepala Tukang
L.04 0.283 OH Mandor
B Bahan
0.27 m3 Kayu Klas III (Terentang)
2 Kg Paku Biasa 2" - 5"
0.6 Ltr Minyak Bekisting
210 Kg Besi Beton Polos
3 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

26 A.4.1.1.30 1 m3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting)


A Tenaga
L.01 7.05 OH Pekerja
L.02 0.275 OH Tukang batu
L.02 1.65 OH Tukang Kayu
L.02 2.1 OH Tukang Besi
L.03 0.403 OH Kepala Tukang
L.04 0.353 OH Mandor
B Bahan
0.4 m3 Kayu Klas III (Terentang)
4 Kg Paku Biasa 2" - 5"
2 Ltr Minyak Bekisting
315 kg Besi Beton Polos
4.5 kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.15 m3 Kayu Klas II Balok
3.5 Lbr Plywood 9 mm
20 Btg Dolken diameter 8 / 4rm

414275883.xlsx 432/283 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

27 A.4.1.1.31 1 m3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting)


A Tenaga
L.01 6.35 OH Pekerja
L.02 0.275 OH Tukang batu
L.02 1.65 OH Tukang Kayu
L.02 1.4 OH Tukang Besi
L.03 0.333 OH Kepala Tukang
L.04 0.318 OH Mandor
B Bahan
0.32 m3 Kayu Klas III (Terentang)
3.2 Kg Paku Biasa 2" - 5"
1.6 Ltr Minyak Bekisting
210 Kg Besi Beton Polos
3 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.14 m3 Kayu Klas II Balok
2.8 Lbr Plywood 9 mm
16 Btg Dolken diameter 8 / 4rm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

28 A.4.1.1.32 1 m3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting)


A Tenaga
L.01 5.3 OH Pekerja
L.02 0.275 OH Tukang batu
L.02 1.3 OH Tukang Kayu
L.02 1.05 OH Tukang Besi
L.03 0.265 OH Kepala Tukang
L.04 0.265 OH Mandor

414275883.xlsx 432/284 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
0.32 m3 Kayu Klas III (Terentang)
3.2 Kg Paku Biasa 2" - 5"
1.6 Ltr Minyak Bekisting
157.5 Kg Besi Beton Polos
2.25 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.12 m3 Kayu Klas II Balok
2.8 Lbr Plywood 9 mm
32 Btg Dolken diameter 8 / 4rm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

29 A.4.1.1.33 1 m3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting)


A Tenaga
L.01 5.3 OH Pekerja
L.02 0.275 OH Tukang batu
L.02 1.3 OH Tukang Kayu
L.02 1.05 OH Tukang Besi
L.03 0.262 OH Kepala Tukang
L.04 0.265 OH Mandor
B Bahan
0.24 m3 Kayu Klas III (Terentang)
3.2 Kg Paku Biasa 2" - 5"
1.6 Ltr Minyak Bekisting
157.5 Kg Besi Beton Polos
2.25 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.16 m3 Kayu Klas II Balok
2.8 Lbr Plywood 9 mm
24 Btg Dolken diameter 8 / 4rm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

414275883.xlsx 432/285 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

F Harga Satuan Pekerjaan (D+E)

30 A.4.1.1.34 1 m3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting)


A Tenaga
L.01 5.65 OH Pekerja
L.02 0.275 OH Tukang batu
L.02 1.56 OH Tukang Kayu
L.02 1.4 OH Tukang Besi
L.03 0.323 OH Kepala Tukang
L.04 0.283 OH Mandor
B Bahan
0.25 m3 Kayu Klas III (Terentang)
3 Kg Paku Biasa 2" - 5"
1.2 Ltr Minyak Bekisting
210 Kg Besi Beton Polos
3 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.105 m3 Kayu Klas II Balok
2.5 Lbr Plywood 9 mm
14 Btg Dolken diameter 8 / 4rm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

31 A.4.1.1.35 1 m' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm


A Tenaga
L.01 0.18 OH Pekerja
L.02 0.02 OH Tukang batu
L.02 0.02 OH Tukang Kayu
L.02 0.02 OH Tukang Besi
L.03 0.006 OH Kepala Tukang
L.04 0.009 OH Mandor
B Bahan
0.002 m3 Kayu Klas III (Terentang)
0.01 Kg Paku Biasa 2" - 5"
3 Kg Besi Beton Polos
0.045 Kg Kawat Beton

414275883.xlsx 432/286 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

4 Kg Portland Semen
0.006 m3 Pasir Beton
0.009 m3 Kerikil Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

32 A.4.1.1.36 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm


A Tenaga
L.01 0.297 OH Pekerja
L.02 0.033 OH Tukang batu
L.02 0.033 OH Tukang Kayu
L.02 0.033 OH Tukang Besi
L.03 0.01 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
0.003 m3 Kayu Klas III (Terentang)
0.02 Kg Paku Biasa 2" - 5"
3.6 Kg Besi Beton Polos
0.05 Kg Kawat Beton
5.5 Kg Portland Semen
0.009 m3 Pasir Beton
0.015 m3 Kerikil Beton
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/287 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

923,395.00
126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
713,390.00
1,360.00 335,920.00
200.00 173,800.00
200.00 199,800.00
18.00 3,870.00

839,450.00
83,945.00
923,395.00
960,619.00
126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
747,230.00
1,360.00 375,360.00
200.00 165,600.00
200.00 202,400.00
18.00 3,870.00

873,290.00
87,329.00
960,619.00

2 Mpa (K150), slum (12±2)cm, w/c = 0,72 989,747.00


126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
773,710.00
1,360.00 406,640.00
200.00 159,800.00
414275883.xlsx 432/288 abk 7-14
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

200.00 203,400.00
18.00 3,870.00

899,770.00
89,977.00
989,747.00

mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 866,588.80


87,408.00
57,000.00 68,400.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 468.00
700,400.00
1,360.00 312,800.00
200.00 178,600.00
200.00 205,400.00
18.00 3,600.00

787,808.00
78,780.80
866,588.80
5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,024,199.00
126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
805,030.00
1,360.00 443,360.00
200.00 152,000.00
200.00 205,800.00
18.00 3,870.00

931,090.00
93,109.00
1,024,199.00

414275883.xlsx 432/289 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

9 MPa (K200), slum (12±2)cm, w/c = 0,61 1,057,155.00


126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
834,990.00
1,360.00 478,720.00
200.00 146,200.00
200.00 206,200.00
18.00 3,870.00

961,050.00
96,105.00
1,057,155.00

3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,081,839.00


126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
857,430.00
1,360.00 504,560.00
200.00 139,600.00
200.00 209,400.00
18.00 3,870.00

983,490.00
98,349.00
1,081,839.00

7 MPa (K250), slum (12±2)cm, w/c = 0,56 1,098,207.00


126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
872,310.00
1,360.00 522,240.00

414275883.xlsx 432/290 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

200.00 138,400.00
200.00 207,800.00
18.00 3,870.00

998,370.00
99,837.00
1,098,207.00

mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 1,126,499.00


126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
898,030.00
1,360.00 552,160.00
200.00 136,800.00
200.00 205,200.00
18.00 3,870.00

1,024,090.00
102,409.00
1,126,499.00
4 MPa (K300), slum (12±2)cm, w/c = 0,52 1,135,211.00
126,060.00
57,000.00 94,050.00
84,000.00 23,100.00
87,000.00 2,436.00
78,000.00 6,474.00
905,950.00
1,360.00 561,680.00
200.00 136,200.00
200.00 204,200.00
18.00 3,870.00

1,032,010.00
103,201.00
1,135,211.00

414275883.xlsx 432/291 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

8 MPa (K325), slum (12±2)cm, w/c = 0,49 1,206,089.50


160,335.00
57,000.00 119,700.00
84,000.00 29,400.00
87,000.00 3,045.00
78,000.00 8,190.00
936,110.00
1,360.00 597,040.00
200.00 134,000.00
200.00 201,200.00
18.00 3,870.00

1,096,445.00
109,644.50
1,206,089.50

2 MPa (K350), slum (12±2)cm, w/c = 0,48 1,217,573.50


160,335.00
57,000.00 119,700.00
84,000.00 29,400.00
87,000.00 3,045.00
78,000.00 8,190.00
946,550.00
1,360.00 609,280.00
200.00 133,400.00
200.00 200,000.00
18.00 3,870.00

1,106,885.00
110,688.50
1,217,573.50

158,720.10
10,791.00
57,000.00 3,990.00
84,000.00 5,880.00
87,000.00 609.00
78,000.00 312.00
133,500.00
12,500.00 131,250.00

414275883.xlsx 432/292 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

15,000.00 2,250.00

144,291.00
14,429.10
158,720.10

125,640.90
7,719.00
57,000.00 2,850.00
84,000.00 4,200.00
87,000.00 435.00
78,000.00 234.00
106,500.00
10,000.00 105,000.00
15,000.00 1,500.00

114,219.00
11,421.90
125,640.90

229,379.70
3,777.00
57,000.00 1,425.00
84,000.00 2,100.00
87,000.00 174.00
78,000.00 78.00
204,750.00
20,000.00 204,000.00
15,000.00 750.00

208,527.00
20,852.70
229,379.70

155,034.00
55,770.00
57,000.00 29,640.00
84,000.00 21,840.00

414275883.xlsx 432/293 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

87,000.00 2,262.00
78,000.00 2,028.00
85,170.00
2,000,000.00 80,000.00
14,000.00 4,200.00
9,700.00 970.00

140,940.00
14,094.00
155,034.00

166,034.00
55,770.00
57,000.00 29,640.00
84,000.00 21,840.00
87,000.00 2,262.00
78,000.00 2,028.00
95,170.00
2,000,000.00 90,000.00
14,000.00 4,200.00
9,700.00 970.00

150,940.00
15,094.00
166,034.00

348,782.50
70,785.00
57,000.00 37,620.00
84,000.00 27,720.00
87,000.00 2,871.00
78,000.00 2,574.00
246,290.00
2,000,000.00 80,000.00
14,000.00 5,600.00
9,700.00 1,940.00
5,500,000.00 82,500.00
115,000.00 40,250.00
18,000.00 36,000.00

414275883.xlsx 432/294 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

317,075.00
31,707.50
348,782.50

366,932.50
70,785.00
57,000.00 37,620.00
84,000.00 27,720.00
87,000.00 2,871.00
78,000.00 2,574.00
262,790.00
2,000,000.00 80,000.00
14,000.00 5,600.00
9,700.00 1,940.00
5,500,000.00 99,000.00
115,000.00 40,250.00
18,000.00 36,000.00

333,575.00
33,357.50
366,932.50

427,982.50
70,785.00
57,000.00 37,620.00
84,000.00 27,720.00
87,000.00 2,871.00
78,000.00 2,574.00
318,290.00
2,000,000.00 80,000.00
14,000.00 5,600.00
9,700.00 1,940.00
5,500,000.00 82,500.00
115,000.00 40,250.00
18,000.00 108,000.00

389,075.00
38,907.50

414275883.xlsx 432/295 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

427,982.50

398,832.50
70,785.00
57,000.00 37,620.00
84,000.00 27,720.00
87,000.00 2,871.00
78,000.00 2,574.00
291,790.00
2,000,000.00 60,000.00
14,000.00 5,600.00
9,700.00 1,940.00
5,500,000.00 110,000.00
115,000.00 40,250.00
18,000.00 54,000.00
5,000.00 20,000.00

362,575.00
36,257.50
398,832.50

326,249.00
70,785.00
57,000.00 37,620.00
84,000.00 27,720.00
87,000.00 2,871.00
78,000.00 2,574.00
225,805.00
2,000,000.00 60,000.00
14,000.00 5,600.00
9,700.00 1,455.00
5,500,000.00 82,500.00
115,000.00 40,250.00
18,000.00 36,000.00

296,590.00
29,659.00
326,249.00

92,409.90

414275883.xlsx 432/296 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

13,809.00
57,000.00 8,550.00
84,000.00 4,200.00
87,000.00 435.00
78,000.00 624.00
70,200.00
2,000,000.00 52,800.00
14,000.00 8,400.00
18,000.00 9,000.00

84,009.00
8,400.90
92,409.90

3,769,209.40
566,064.00
57,000.00 302,100.00
84,000.00 23,100.00
84,000.00 109,200.00
84,000.00 88,200.00
87,000.00 22,794.00
78,000.00 20,670.00
2,860,490.00
2,000,000.00 400,000.00
14,000.00 21,000.00
9,700.00 3,880.00
10,000.00 1,575,000.00
15,000.00 33,750.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00

3,426,554.00
342,655.40
3,769,209.40

4,608,609.50
643,965.00

414275883.xlsx 432/297 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

57,000.00 322,050.00
84,000.00 23,100.00
84,000.00 131,040.00
84,000.00 117,600.00
87,000.00 28,101.00
78,000.00 22,074.00
3,545,680.00
2,000,000.00 540,000.00
14,000.00 28,000.00
9,700.00 5,820.00
10,000.00 2,100,000.00
15,000.00 45,000.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00

4,189,645.00
418,964.50
4,608,609.50

8,040,785.50
802,545.00
57,000.00 401,850.00
84,000.00 23,100.00
84,000.00 138,600.00
84,000.00 176,400.00
87,000.00 35,061.00
78,000.00 27,534.00
6,507,260.00
2,000,000.00 800,000.00
14,000.00 56,000.00
9,700.00 19,400.00
10,000.00 3,150,000.00
15,000.00 67,500.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00
5,500,000.00 825,000.00
115,000.00 402,500.00
18,000.00 360,000.00

414275883.xlsx 432/298 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

7,309,805.00
730,980.50
8,040,785.50

6,321,925.50
695,025.00
57,000.00 361,950.00
84,000.00 23,100.00
84,000.00 138,600.00
84,000.00 117,600.00
87,000.00 28,971.00
78,000.00 24,804.00
5,052,180.00
2,000,000.00 640,000.00
14,000.00 44,800.00
9,700.00 15,520.00
10,000.00 2,100,000.00
15,000.00 45,000.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00
5,500,000.00 770,000.00
115,000.00 322,000.00
18,000.00 288,000.00

5,747,205.00
574,720.50
6,321,925.50

5,786,280.50
566,325.00
57,000.00 302,100.00
84,000.00 23,100.00
84,000.00 109,200.00
84,000.00 88,200.00
87,000.00 23,055.00
78,000.00 20,670.00

414275883.xlsx 432/299 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

4,693,930.00
2,000,000.00 640,000.00
14,000.00 44,800.00
9,700.00 15,520.00
10,000.00 1,575,000.00
15,000.00 33,750.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00
5,500,000.00 660,000.00
115,000.00 322,000.00
18,000.00 576,000.00

5,260,255.00
526,025.50
5,786,280.50

5,693,593.40
566,064.00
57,000.00 302,100.00
84,000.00 23,100.00
84,000.00 109,200.00
84,000.00 88,200.00
87,000.00 22,794.00
78,000.00 20,670.00
4,609,930.00
2,000,000.00 480,000.00
14,000.00 44,800.00
9,700.00 15,520.00
10,000.00 1,575,000.00
15,000.00 33,750.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00
5,500,000.00 880,000.00
115,000.00 322,000.00
18,000.00 432,000.00

5,175,994.00
517,599.40

414275883.xlsx 432/300 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

5,693,593.40

5,815,111.50
643,965.00
57,000.00 322,050.00
84,000.00 23,100.00
84,000.00 131,040.00
84,000.00 117,600.00
87,000.00 28,101.00
78,000.00 22,074.00
4,642,500.00
2,000,000.00 500,000.00
14,000.00 42,000.00
9,700.00 11,640.00
10,000.00 2,100,000.00
15,000.00 45,000.00
1,360.00 456,960.00
280,000.00 151,200.00
270,000.00 218,700.00
5,500,000.00 577,500.00
115,000.00 287,500.00
18,000.00 252,000.00

5,286,465.00
528,646.50
5,815,111.50

66,977.90
16,524.00
57,000.00 10,260.00
84,000.00 1,680.00
84,000.00 1,680.00
84,000.00 1,680.00
87,000.00 522.00
78,000.00 702.00
44,365.00
2,000,000.00 4,000.00
14,000.00 140.00
10,000.00 30,000.00
15,000.00 675.00

414275883.xlsx 432/301 abk 7-14


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

1,360.00 5,440.00
280,000.00 1,680.00
270,000.00 2,430.00

60,889.00
6,088.90
66,977.90

92,801.50
27,285.00
57,000.00 16,929.00
84,000.00 2,772.00
84,000.00 2,772.00
84,000.00 2,772.00
87,000.00 870.00
78,000.00 1,170.00
57,080.00
2,000,000.00 6,000.00
14,000.00 280.00
10,000.00 36,000.00
15,000.00 750.00
1,360.00 7,480.00
280,000.00 2,520.00
270,000.00 4,050.00

84,365.00
8,436.50
92,801.50

414275883.xlsx 432/302 abk 7-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil

A Tenaga
L.01 0.15 OH Pekerja
L.02 0.075 OH Tukang Kayu
L.03 0.0075 OH Kepala Tukang
L.04 0.008 OH Mandor

B Bahan
25 Buah Genteng Plentong

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

Overhead & Profit (contoh 10%)


2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur
A Tenaga
L.01 0.15 OH Pekerja
L.02 0.075 OH Tukang Kayu
L.03 0.008 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
25 Buah Genteng Kodok / Glasur

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.075 OH Tukang Kayu
L.03 0.008 OH Kepala Tukang

414275883.xlsx 432/303 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.008 OH Mandor


B Bahan

18 Buah Genteng Plentong Super / Besar


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong


A Tenaga
L.01 0.4 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan

5 Buah Genteng Bubung Plentong


8 Kg Portland Semen

0.032 m3 Pasir Pasang


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/304 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur


A Tenaga
L.01 0.4 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan

5 Buah Genteng Bubung Kodok / Glasur


8 Kg Portland Semen
0.032 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar


A Tenaga
L.01 0.4 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan

4 Buah Genteng Bubung Plentong Besar


8 Kg Portland Semen
0.032 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

7 A.4.5.2.9 1 m2 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 m


A Tenaga
L.01 0.14 OH Pekerja
414275883.xlsx 432/305 abk 8-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.02 0.075 OH Tukang Kayu


L.03 0.008 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
0.6 Lbr Asbes Gelombang

0.12 Kg Paku Pancing 60 x 230


C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 A.4.5.2.10 1 m2 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 m

A Tenaga
L.01 0.14 OH Pekerja
L.02 0.07 OH Tukang Kayu
L.03 0.007 OH Kepala Tukang
L.04 0.007 OH Mandor

B Bahan
0.6 Lbr Asbes Gelombang
0.12 Kg Paku Pancing 60 x 230

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/306 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

9 A.4.5.2.12 1 m2 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 m


A Tenaga
L.01 0.14 OH Pekerja
L.02 0.07 OH Tukang Kayu
L.03 0.007 OH Kepala Tukang
L.04 0.007 OH Mandor
B Bahan

0.35 Lbr Asbes Gelombang


0.12 Kg Paku Pancing 60 x 230
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

10 A.4.5.2.15 1 m2 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 m


A Tenaga
L.01 0.14 OH Pekerja
L.02 0.070 OH Tukang Kayu
L.03 0.007 OH Kepala Tukang
L.04 0.007 OH Mandor
B Bahan

0.51 Lbr Asbes Gelombang


0.12 Kg Paku Pancing 60 x 230

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

11 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton


A Tenaga
L.01 0.2 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang

414275883.xlsx 432/307 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.01 OH Mandor


B Bahan

11 Lbr Genteng Beton Standrad


0.03 Kg Paku Biasa 2" - 5"
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

12 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal

A Tenaga
L.01 0.2 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.01 OH Mandor

B Bahan
1.02 m2 Genteng Metal

0.20 Kg Paku Biasa Ø ½" - 1"

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

13 A.4.5.2.33 1 m2 Pemasangan Atap Sirap

A Tenaga
L.01 0.166 OH Pekerja
L.02 0.25 OH Tukang Kayu
L.03 0.025 OH Kepala Tukang
L.04 0.008 OH Mandor

B Bahan
30 Lbr Genteng Sirap

0.2 Kg Paku Biasa 1/2" - 1"

414275883.xlsx 432/308 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

14 A.4.5.2.34 1 m' Pemasangan Nok Genteng Beton


A Tenaga
L.01 0.4 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.02 OH Mandor
B Bahan

3.5 Buah Nok Genteng Beton


0.05 Kg Paku Biasa 2" - 5"
10.8 Kg Portland Semen

0.032 m3 Pasir Pasang


1 Kg Semen Warna

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

15 A.4.5.2.36 1 m' Pemasangan Nok Genteng Metal


A Tenaga
L.01 0.250 OH Pekerja
L.02 0.150 OH Tukang Kayu
L.03 0.015 OH Kepala Tukang
L.04 0.013 OH Mandor
B Bahan
1.1 Buah Nok Genteng
0.05 Kg Paku Biasa 1/2" - 1"

C PERALATAN

414275883.xlsx 432/309 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

16 A.4.5.2.37 1 m' Pemasangan Nok Sirap


A Tenaga
L.01 0.125 OH Pekerja
L.02 0.25 OH Tukang Kayu
L.03 0.025 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan
0.4 Lbr Seng Plaat 3" x 6" BJLS 28
0.06 Kg Paku Biasa 1/2" - 1"
0.05 Kg Paku Biasa 2" - 5"

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

17 A.4.5.2.38 1 m2 Pemasangan Atap Seng Gelombang


A Tenaga
L.01 0.12 OH Pekerja
L.02 0.06 OH Tukang Kayu
L.03 0.006 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28
0.02 Kg Paku Biasa 1/2" - 1"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/310 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

18 A.4.5.2.39 1 m' Pemasangan Atap Nok Seng


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.07 OH Tukang Kayu
L.03 0.007 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan
0.3 Lbr Seng Plaat 3" x 6" BJLS 28
0.04 Kg Paku Biasa 1/2" - 1"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

19 A.4.5.2.42 1 m2 Pasang Allumunium Foil / Sisalation


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.05 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
1.05 m2 Sisalation / Allumunium Foil
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/311 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

PEKERJAAN PENUTUP ATAP


64,489.15

16,126.50
57,000.00 8,550.00

84,000.00 6,300.00
87,000.00 652.50
78,000.00 624.00

42,500.00
1,700.00 42,500.00

58,626.50
10% 5,862.65

64,489.15

130,537.00
16,170.00
57,000.00 8,550.00

84,000.00 6,300.00
87,000.00 696.00

78,000.00 624.00
102,500.00
4,100.00 102,500.00

118,670.00
10% 11,867.00
130,537.00

Genteng Plentong Super / Besar 120,747.00


16,170.00

57,000.00 8,550.00
84,000.00 6,300.00

87,000.00 696.00

414275883.xlsx 432/312 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

78,000.00 624.00
93,600.00

5,200.00 93,600.00

109,770.00
10% 10,977.00
120,747.00

114,505.60
41,496.00

57,000.00 22,800.00
84,000.00 16,800.00

87,000.00 1,740.00
78,000.00 156.00
62,600.00

9,000.00 45,000.00
1,360.00 10,880.00

210,000.00 6,720.00

104,096.00
10% 10,409.60
114,505.60

414275883.xlsx 432/313 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

eng Bubung Kodok / Glasur 101,305.60


41,496.00

57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00

78,000.00 156.00
50,600.00

6,600.00 33,000.00
1,360.00 10,880.00
210,000.00 6,720.00

92,096.00
10% 9,209.60
101,305.60

eng Bubung Plentong Besar 104,605.60


41,496.00

57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00

78,000.00 156.00
53,600.00

9,000.00 36,000.00
1,360.00 10,880.00
210,000.00 6,720.00

95,096.00
10% 9,509.60
104,605.60

Asbes Gelombang (2,25x0,92 m) x 5 mm 66,396.00


15,600.00

57,000.00 7,980.00
414275883.xlsx 432/314 abk 8-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

84,000.00 6,300.00
87,000.00 696.00

78,000.00 624.00
44,760.00
71,500.00 42,900.00

15,500.00 1,860.00

60,360.00
10% 6,036.00
66,396.00

Asbes Gelombang (2,00x0,92 m) x 5 mm 60,472.50

15,015.00
57,000.00 7,980.00
84,000.00 5,880.00

87,000.00 609.00
78,000.00 546.00

39,960.00
63,500.00 38,100.00
15,500.00 1,860.00

54,975.00
10% 5,497.50
60,472.50

414275883.xlsx 432/315 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

Asbes Gelombang (3,00x1,05 m) x 4 mm 52,057.50


15,015.00

57,000.00 7,980.00
84,000.00 5,880.00
87,000.00 609.00

78,000.00 546.00
32,310.00

87,000.00 30,450.00
15,500.00 1,860.00

47,325.00
10% 4,732.50

52,057.50

Asbes Gelombang (2,10x1,05 m) x 4 mm 53,344.50


15,015.00

57,000.00 7,980.00
84,000.00 5,880.00

87,000.00 609.00
78,000.00 546.00
33,480.00

62,000.00 31,620.00
15,500.00 1,860.00

48,495.00
10% 4,849.50

53,344.50

96,657.00
21,450.00
57,000.00 11,400.00

84,000.00 8,400.00
87,000.00 870.00

414275883.xlsx 432/316 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

78,000.00 780.00
66,420.00

6,000.00 66,000.00
14,000.00 420.00

87,870.00
10% 8,787.00

96,657.00

82,775.00

21,450.00
57,000.00 11,400.00

84,000.00 8,400.00
87,000.00 870.00
78,000.00 780.00

53,800.00
50,000.00 51,000.00

14,000.00 2,800.00

75,250.00
10% 7,525.00
82,775.00

101,377.10

33,261.00
57,000.00 9,462.00

84,000.00 21,000.00
87,000.00 2,175.00
78,000.00 624.00

58,900.00
1,870.00 56,100.00

14,000.00 2,800.00

414275883.xlsx 432/317 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

92,161.00
10% 9,216.10
101,377.10

106,158.80
42,900.00

57,000.00 22,800.00
84,000.00 16,800.00
87,000.00 1,740.00

78,000.00 1,560.00
53,608.00

9,000.00 31,500.00
14,000.00 700.00
1,360.00 14,688.00

210,000.00 6,720.00
9,000.00 9,000.00

96,508.00
10% 9,650.80

106,158.80

57,055.90
29,169.00
57,000.00 14,250.00

84,000.00 12,600.00
87,000.00 1,305.00

78,000.00 1,014.00
22,700.00
20,000.00 22,000.00
14,000.00 700.00

414275883.xlsx 432/318 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

51,869.00
10% 5,186.90
57,055.90

46,978.80
30,768.00
57,000.00 7,125.00
84,000.00 21,000.00
87,000.00 2,175.00
78,000.00 468.00
11,940.00
26,000.00 10,400.00
14,000.00 840.00
14,000.00 700.00

42,708.00
10% 4,270.80
46,978.80

34,485.00
12,870.00
57,000.00 6,840.00
84,000.00 5,040.00
87,000.00 522.00
78,000.00 468.00
18,480.00
26,000.00 18,200.00
14,000.00 280.00

31,350.00
10% 3,135.00
34,485.00

414275883.xlsx 432/319 abk 8-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

26,253.70
15,507.00
57,000.00 8,550.00
84,000.00 5,880.00
87,000.00 609.00
78,000.00 468.00
8,360.00
26,000.00 7,800.00
14,000.00 560.00

23,867.00
10% 2,386.70
26,253.70

24,083.40
13,809.00
57,000.00 8,550.00
84,000.00 4,200.00
87,000.00 435.00
78,000.00 624.00
8,085.00
7,700.00 8,085.00

21,894.00
10% 2,189.40
24,083.40

414275883.xlsx 432/320 abk 8-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 1 m2 Pemasangan Langit-langit Asbes (1,00x1,00) m, teba

A Tenaga
L.01 0.03 OH Pekerja
L.02 0.07 OH Tukang Kayu
L.03 0.007 OH Kepala Tukang
L.04 0.004 OH Mandor

B Bahan
1.1 Lbr Plat Asbes
0.01 Kg Paku

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)

2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm


A Tenaga
L.01 0.12 OH Pekerja
L.02 0.12 OH Tukang Kayu
L.03 0.012 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan

12.0 Lbr Akustik Uk.30 x 30 cm


0.05 Kg Paku
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) c

A Tenaga
L.01 0.10 OH Pekerja

414275883.xlsx 432/321 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.02 0.10 OH Tukang Kayu


L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor

B Bahan
5.80 Lbr Akustik
0.05 Kg Paku

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120)


A Tenaga
L.01 0.10 OH Pekerja
L.02 0.10 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan

1.50 Lbr Akustik


0.05 Kg Paku
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

5 A.4.5.1.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, T

A Tenaga
L.01 0.10 OH Pekerja
L.02 0.10 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor

414275883.xlsx 432/322 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan

0.375 Lbr Tripleks (4 mm)


0.03 Kg Paku Tripleks

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, teba


A Tenaga
L.01 0.8 OH Pekerja
L.02 0.8 OH Tukang Kayu
L.03 0.08 OH Kepala Tukang
L.04 0.04 OH Mandor
B Bahan
0.015 m3 Kayu Jati,Papan

0.01 Kg Paku
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.4.5.1.7 1 m2 Memasang Langit-langit Gypsu Board, Uk (120x240)

A Tenaga
L.01 0.1 OH Pekerja
L.02 0.05 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.005 OH Mandor

B Bahan
0.364 Lbr Gypsum Board
0.11 Kg Paku Sekrup

C PERALATAN
D Jumlah A + B + C

414275883.xlsx 432/323 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

8 A.4.5.1.9 1 m2 Memasang Langit-langit Akuatik Uk (60x120) cm & R


A Tenaga
L.01 0.5 OH Pekerja
L.02 0.5 OH Tukang Kayu
L.03 0.05 OH Kepala Tukang
L.04 0.025 OH Mandor
B Bahan
3.6 m' Profil Allumunium "T"
0.15 kg Kawat Ø 4 mm
1.05 bh Ramset
1.5 lmb Akuatik 60 x 120 cm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.4.5.1.10 1 m1 List Langit-Langit Kayu Profil


A Tenaga
L.01 0.05 OH Pekerja
L.02 0.05 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
1.05 m1 List Kayu Profil
0.01 Kg Paku
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/324 abk 9-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

PEKERJAAN LANGIT-LANGIT
ngit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm 28,876.10

8,511.00
57,000.00 1,710.00
84,000.00 5,880.00

87,000.00 609.00
78,000.00 312.00

17,740.00
16,000.00 17,600.00
14,000.00 140.00

26,251.00
10% 2,625.10
28,876.10

ngit-langit Akustik Ukuran (30x30) cm 94,965.20


18,432.00

57,000.00 6,840.00
84,000.00 10,080.00
87,000.00 1,044.00

78,000.00 468.00
67,900.00

5,600.00 67,200.00
14,000.00 700.00

86,332.00
10% 8,633.20

94,965.20

ngit-langit Akustik Ukuran (30x60) cm 103,796.00

15,360.00
57,000.00 5,700.00

414275883.xlsx 432/325 abk 9-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

84,000.00 8,400.00

87,000.00 870.00
78,000.00 390.00

79,000.00
13,500.00 78,300.00
14,000.00 700.00

94,360.00
10% 9,436.00
103,796.00

ngit-langit Akustik Ukuran (60x120) cm 85,316.00


15,360.00

57,000.00 5,700.00
84,000.00 8,400.00
87,000.00 870.00

78,000.00 390.00
62,200.00

41,000.00 61,500.00
14,000.00 700.00

77,560.00
10% 7,756.00

85,316.00

it-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm 43,345.50

15,360.00
57,000.00 5,700.00

84,000.00 8,400.00
87,000.00 870.00
78,000.00 390.00

414275883.xlsx 432/326 abk 9-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

24,045.00

63,000.00 23,625.00
14,000.00 420.00

39,405.00
10% 3,940.50

43,345.50

it-langit Lambriziring Kayu Jati, tebal 6 mm 498,322.00


122,880.00
57,000.00 45,600.00

84,000.00 67,200.00
87,000.00 6,960.00

78,000.00 3,120.00
330,140.00
22,000,000.00 330,000.00

14,000.00 140.00

453,020.00
10% 45,302.00
498,322.00

it-langit Gypsu Board, Uk (120x240) tebal 9 mm 39,838.70

10,725.00
57,000.00 5,700.00
84,000.00 4,200.00

87,000.00 435.00
78,000.00 390.00

25,492.00
65,500.00 23,842.00
15,000.00 1,650.00

36,217.00

414275883.xlsx 432/327 abk 9-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

10% 3,621.70

39,838.70

it-langit Akuatik Uk (60x120) cm & Rangka Allumunium 191,895.00


76,800.00
57,000.00 28,500.00

84,000.00 42,000.00
87,000.00 4,350.00

78,000.00 1,950.00
97,650.00
3,500.00 12,600.00
6,500.00 975.00
21,500.00 22,575.00
41,000.00 61,500.00

174,450.00
10% 17,445.00
191,895.00

14,188.90
7,719.00
57,000.00 2,850.00
84,000.00 4,200.00
87,000.00 435.00
78,000.00 234.00
5,180.00
4,800.00 5,040.00
14,000.00 140.00

12,899.00
10% 1,289.90
14,188.90

414275883.xlsx 432/328 abk 9-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUN


1 A.5.1.1.1 1 Unit Memasang Closet Duduk / Mono Blok
A Tenaga
L.01 3.3 OH Pekerja
L.02 1.1 OH Tukang Batu
L.03 0.001 OH Kepala Tukang
L.04 0.16 OH Mandor
Buah Bahan
1 Buah Kloset Duduk / Monoblok
0.06 Kelengkapan 6% dari harga Kloset
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Memasang Closet Jongkok Porselen
A Tenaga
L.01 1 OH Pekerja
L.02 1.5 OH Tukang Batu
L.03 1.5 OH Kepala Tukang
L.04 0.16 OH Mandor
B Bahan
1 Buah Kloset Jongkok
6 Kg Portland Semen
0.01 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.5.1.1.4 1 Unit Memasang Urinoir


A Tenaga
L.01 1 OH Pekerja
L.02 1 OH Tukang Batu
L.03 0.1 OH Kepala Tukang

414275883.xlsx432/329 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.1 OH Mandor


B Bahan
1 Buah Urinoir
0.3 - Perlengkapan 30% Harga Urinoir
6 Kg Portland Semen
0.01 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

4 A.5.1.1.5 1 Unit Memasang Wastafel


A Tenaga
L.01 1.2 OH Pekerja
L.02 0.145 OH Tukang Batu
L.03 0.15 OH Kepala Tukang
L.04 0.1 OH Mandor
B Bahan
1 Buah Wastafel
0.3 - Perlengkapan 30% Harga Wastafel
6 Kg Portland Semen
0.01 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen


A Tenaga
L.01 0.075 OH Pekerja
L.02 0.75 OH Tukang Batu
L.03 0.075 OH Kepala Tukang
L.04 0.003 OH Mandor

414275883.xlsx432/330 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
1 Buah Batchuip
0.2 - Perlengkapan 20% Harga Bathcuip
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3


A Tenaga
L.01 3 OH Pekerja
L.02 4.5 OH Tukang Batu
L.03 0.05 OH Kepala Tukang
L.04 0.9 OH Mandor
B Tukang Batu
1 Buah Bak Fibreglass
0.12 - Perlengkapan 12% Bak Fibreglass
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3


A Tenaga
L.01 6.00 OH Pekerja
L.02 3.00 OH Tukang Batu
L.03 0.30 OH Kepala Tukang
L.04 0.03 OH Mandor
B Bahan
150.0 bh Batu Bata
120 Kg Portland Semen
0.3 m3 Pasir Pasang
360 buah Porselen 11 x 11 cm
6 Kg Semen Nat
C PERALATAN
D Jumlah A + B + C
414275883.xlsx432/331 abk 10-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

8 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell


A Tenaga
L.01 0.030 OH Pekerja
L.02 0.300 OH Tukang Batu
L.03 0.030 OH Kepala Tukang
L.04 0.015 OH Mandor
B Bahan
1 unit Bak Cuci Piring
1 bh Water drain
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.5.1.1.14 1 buah Pemasangan Floor Drain


A Tenaga
L.01 0.010 OH Pekerja
L.02 0.100 OH Tukang Batu
L.03 0.010 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1 bh Floor Drain

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx432/332 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

10 A.5.1.1.15 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 c


A Tenaga
L.01 2.160 OH Pekerja
L.02 0.720 OH Tukang Batu
L.03 0.072 OH Kepala Tukang
L.04 0.011 OH Mandor
B Bahan
40.00 bh Batu Bata
44.00 kg Semen Portland
0.07 m3 Pasir Pasang
0.06 m3 Pasir Beton
0.07 m3 Kerikil
1.60 kg Baja Tulangan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.5.1.1.16 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50


A Tenaga
L.01 3.200 OH Pekerja
L.02 1.150 OH Tukang Batu
L.03 0.011 OH Kepala Tukang
L.04 0.016 OH Mandor
B Bahan
70.00 bh Batu Bata
77.00 kg Semen Portland
0.13 m3 Pasir Pasang
0.09 m3 Pasir Beton
0.02 m3 Kerikil
1.60 kg Baja Tulangan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx432/333 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

12 A.5.1.1.17 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 c


A Tenaga
L.01 3.200 OH Pekerja
L.02 1.150 OH Tukang Batu
L.03 0.011 OH Kepala Tukang
L.04 0.016 OH Mandor
B Bahan
123.00 bh Batu Bata
114.00 kg Semen Portland
0.18 m3 Pasir Pasang
0.12 m3 Pasir Beton
4.85 kg Baja Tulangan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

13 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½"


A Tenaga
L.01 0.054 OH Pekerja
L.02 0.090 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.027 OH Mandor
B Bahan
1.20 m' Pipa Galvanis Ø ½"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx432/334 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

14 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾"


A Tenaga
L.01 0.010 OH Pekerja
L.02 0.400 OH Tukang Batu
L.03 0.040 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1.00 bh Kran Air
0.0025 bh Sealtape
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

15 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾"


A Tenaga
L.01 0.054 OH Pekerja
L.02 0.090 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.027 OH Mandor
B Bahan
1.20 m' Pipa Galvanis Ø ¾"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

16 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1"


A Tenaga
L.01 0.054 OH Pekerja
L.02 0.090 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.027 OH Mandor
B Bahan
1.20 m' Pipa Galvanis Ø 1"
414275883.xlsx432/335 abk 10-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.35 Ls Perlengkapan 35% x pipa


C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

17 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ "


A Tenaga
L.01 0.108 OH Pekerja
L.02 0.180 OH Tukang Batu
L.03 0.018 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1.20 m' Pipa Galvanis Ø 1½"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

18 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3"


A Tenaga
L.01 0.135 OH Pekerja
L.02 0.225 OH Tukang Batu
L.03 0.023 OH Kepala Tukang
L.04 0.007 OH Mandor
B Bahan
1.20 m' Pipa Galvanis Ø 3"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx432/336 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

19 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4"


A Tenaga
L.01 0.135 OH Pekerja
L.02 0.225 OH Tukang Batu
L.03 0.023 OH Kepala Tukang
L.04 0.007 OH Mandor
B Bahan
1.20 m' Pipa Galvanis Ø 4"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

20 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½"


A Tenaga
L.01 0.036 OH Pekerja
L.02 0.060 OH Tukang Batu
L.03 0.006 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan
1.20 m' Pipa PVC Ø ½"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

21 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾"


A Tenaga
L.01 0.036 OH Pekerja
L.02 0.060 OH Tukang Batu
L.03 0.006 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan
414275883.xlsx432/337 abk 10-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

1.20 m' Pipa PVC Ø ¾"


0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

22 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1"


A Tenaga
L.01 0.036 OH Pekerja
L.02 0.060 OH Tukang Batu
L.03 0.006 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan
1.20 m' Pipa PVC Ø 1"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

23 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½"


A Tenaga
L.01 0.054 OH Pekerja
L.02 0.090 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
1.20 m' Pipa PVC Ø 1½"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx432/338 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

24 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2"


A Tenaga
L.01 0.054 OH Pekerja
L.02 0.090 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
1.20 m' Pipa PVC Ø 2"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

25 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3"


A Tenaga
L.01 0.081 OH Pekerja
L.02 0.135 OH Tukang Batu
L.03 0.0135 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan
1.20 m' Pipa PVC Ø 3"
0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

26 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4"


A Tenaga
L.01 0.036 OH Pekerja
L.02 0.060 OH Tukang Batu
L.03 0.006 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan
414275883.xlsx432/339 abk 10-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

1.20 m' Pipa PVC Ø 4"


0.35 Ls Perlengkapan 35% x pipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

27 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm


A Tenaga
L.01 0.080 OH Pekerja
L.02 0.040 OH Tukang Batu
L.03 0.004 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan
1.60 bh pipa tanah
35.00 kg Semen Portlan
0.014 m3 Pasir Pasang
0.014 m3 Pasir Urug

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

28 A.5.1.1.34 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm


A Tenaga
L.01 0.060 OH Pekerja
L.02 0.030 OH Tukang Batu
L.03 0.003 OH Kepala Tukang
L.04 0.003 OH Mandor

414275883.xlsx432/340 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
1.60 bh pipa tanah
6.80 kg Semen Portlan
0.013 m3 Pasir Pasang
0.011 m3 Pasir Urug

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

29 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 20 cm


A Tenaga
L.01 0.140 OH Pekerja
L.02 0.070 OH Tukang Batu
L.03 0.007 OH Kepala Tukang
L.04 0.007 OH Mandor
B Bahan
1.10 bh pipa beton
0.03 m3 Batu Bata
3.920 kg Semen Portlan
0.056 m3 Pasir Pasang
0.024 m3 Pasir Urug
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

30 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 100 cm


A Tenaga
L.01 0.380 OH Pekerja
L.02 0.190 OH Tukang Batu
L.03 0.019 OH Kepala Tukang
L.04 0.019 OH Mandor
B Bahan
1.10 bh pipa beton
414275883.xlsx432/341 abk 10-14
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.55 m3 Batu Bata


10.300 kg Semen Portlan
0.061 m3 Pasir Pasang
0.069 m3 Pasir Urug
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx432/342 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

PEKERJAAN SANITASI DALAM GEDUNG


1,779,873.70
293,067.00
57,000.00 188,100.00
84,000.00 92,400.00
87,000.00 87.00
78,000.00 12,480.00
1,325,000.00
1,250,000.00 1,250,000.00
1,250,000.00 75,000.00

1,618,067.00
10% 161,806.70
1,779,873.70

518,364.00
325,980.00
57,000.00 57,000.00
84,000.00 126,000.00
87,000.00 130,500.00
78,000.00 12,480.00
145,260.00
135,000.00 135,000.00
1,360.00 8,160.00
210,000.00 2,100.00

471,240.00
10% 47,124.00
518,364.00

685,036.00
157,500.00
57,000.00 57,000.00
84,000.00 84,000.00
87,000.00 8,700.00

414275883.xlsx432/343 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

78,000.00 7,800.00
465,260.00
350,000.00 350,000.00
350,000.00 105,000.00
1,360.00 8,160.00
210,000.00 2,100.00

622,760.00
10% 62,276.00
685,036.00

666,259.00
101,430.00
57,000.00 68,400.00
84,000.00 12,180.00
87,000.00 13,050.00
78,000.00 7,800.00
504,260.00
380,000.00 380,000.00
380,000.00 114,000.00
1,360.00 8,160.00
210,000.00 2,100.00

605,690.00
10% 60,569.00
666,259.00

1,071,437.40

74,034.00
57,000.00 4,275.00
84,000.00 63,000.00
87,000.00 6,525.00
78,000.00 234.00

414275883.xlsx432/344 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

900,000.00

750,000.00 750,000.00
750,000.00 150,000.00

974,034.00
10% 97,403.40
1,071,437.40

1,024,705.00
623,550.00

57,000.00 171,000.00
84,000.00 378,000.00
87,000.00 4,350.00
78,000.00 70,200.00
308,000.00

275,000.00 275,000.00
275,000.00 33,000.00

931,550.00
10% 93,155.00
1,024,705.00

1,283,947.90
622,440.00
57,000.00 342,000.00
84,000.00 252,000.00
87,000.00 26,100.00
78,000.00 2,340.00
544,785.37
520.00 78,000.00
0.11 1,360.00 163,200.00
0.0121 210,000.00 63,000.00
82.6446280992 518.29 186,585.37
9,000.00 54,000.00

1,167,225.37
414275883.xlsx432/345 abk 10-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

10% 116,722.54
1,283,947.90

336,259.00
30,690.00
57,000.00 1,710.00
84,000.00 25,200.00
87,000.00 2,610.00
78,000.00 1,170.00
275,000.00
225,000.00 225,000.00
50,000.00 50,000.00

305,690.00
10% 30,569.00
336,259.00

31,053.00
10,230.00

57,000.00 570.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 390.00
18,000.00
18,000.00 18,000.00

28,230.00
10% 2,823.00
31,053.00

414275883.xlsx432/346 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

Kontrol Pas.Batu Bata 30x30 tinggi 35 cm 360,527.20


190,722.00
57,000.00 123,120.00
84,000.00 60,480.00
87,000.00 6,264.00
78,000.00 858.00
137,030.00
520.00 20,800.00
1,360.00 59,840.00
210,000.00 14,700.00
280,000.00 16,800.00
127,000.00 8,890.00
10,000.00 16,000.00

327,752.00
10% 32,775.20
360,527.20

Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm 542,701.50


281,205.00
57,000.00 182,400.00
84,000.00 96,600.00
87,000.00 957.00
78,000.00 1,248.00
212,160.00
520.00 36,400.00
1,360.00 104,720.00
210,000.00 27,300.00
280,000.00 25,200.00
127,000.00 2,540.00
10,000.00 16,000.00

493,365.00
10% 49,336.50
542,701.50

414275883.xlsx432/347 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

Kontrol Pas.Batu Bata 60x60 tinggi 60 cm 662,843.50


281,205.00
57,000.00 182,400.00
84,000.00 96,600.00
87,000.00 957.00
78,000.00 1,248.00
321,380.00
520.00 63,960.00
1,360.00 155,040.00
210,000.00 38,640.00
127,000.00 15,240.00
10,000.00 48,500.00

602,585.00
10% 60,258.50
662,843.50

33,918.87
13,527.00
57,000.00 3,078.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 2,106.00
17,308.33
11,166.67 13,400.00
11,166.67 3,908.33

30,835.33
10% 3,083.53
33,918.87

414275883.xlsx432/348 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

72,655.00
38,040.00
57,000.00 570.00
84,000.00 33,600.00
87,000.00 3,480.00
78,000.00 390.00
28,010.00
28,000.00 28,000.00
4,000.00 10.00

66,050.00
10% 6,605.00
72,655.00

37,613.03
13,527.00
57,000.00 3,078.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 2,106.00
20,666.67
13,333.33 16,000.00
13,333.33 4,666.67

34,193.67
10% 3,419.37
37,613.03

42,443.87
13,527.00
57,000.00 3,078.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 2,106.00
25,058.33
16,166.67 19,400.00
414275883.xlsx432/349 abk 10-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

16,166.67 5,658.33

38,585.33
10% 3,858.53
42,443.87

65,338.53
23,232.00
57,000.00 6,156.00
84,000.00 15,120.00
87,000.00 1,566.00
78,000.00 390.00
36,166.67
23,333.33 28,000.00
23,333.33 8,166.67

59,398.67
10% 5,939.87
65,338.53

165,614.53
29,142.00
57,000.00 7,695.00
84,000.00 18,900.00
87,000.00 2,001.00
78,000.00 546.00
121,416.67
78,333.33 94,000.00
78,333.33 27,416.67

150,558.67
10% 15,055.87
165,614.53

414275883.xlsx432/350 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

270,756.20
29,142.00
57,000.00 7,695.00
84,000.00 18,900.00
87,000.00 2,001.00
78,000.00 546.00
217,000.00
140,000.00 168,000.00
140,000.00 49,000.00

246,142.00
10% 24,614.20
270,756.20

20,055.75
7,770.00
57,000.00 2,052.00
84,000.00 5,040.00
87,000.00 522.00
78,000.00 156.00
10,462.50
6,750.00 8,100.00
6,750.00 2,362.50

18,232.50
10% 1,823.25
20,055.75

22,613.25
7,770.00
57,000.00 2,052.00
84,000.00 5,040.00
87,000.00 522.00
78,000.00 156.00
12,787.50
414275883.xlsx432/351 abk 10-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

8,250.00 9,900.00
8,250.00 2,887.50

20,557.50
10% 2,055.75
22,613.25

27,728.25
7,770.00
57,000.00 2,052.00
84,000.00 5,040.00
87,000.00 522.00
78,000.00 156.00
17,437.50
11,250.00 13,500.00
11,250.00 3,937.50

25,207.50
10% 2,520.75
27,728.25

31,291.33
11,655.00
57,000.00 3,078.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 234.00
16,791.67
10,833.33 13,000.00
10,833.33 3,791.67

28,446.67
10% 2,844.67
31,291.33

414275883.xlsx432/352 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

44,078.83
11,655.00
57,000.00 3,078.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 234.00
28,416.67
18,333.33 22,000.00
18,333.33 6,416.67

40,071.67
10% 4,007.17
44,078.83

76,021.18
17,443.50
57,000.00 4,617.00
84,000.00 11,340.00
87,000.00 1,174.50
78,000.00 312.00
51,666.67
33,333.33 40,000.00
33,333.33 11,666.67

69,110.17
10% 6,911.02
76,021.18

93,797.00
7,770.00
57,000.00 2,052.00
84,000.00 5,040.00
87,000.00 522.00
78,000.00 156.00
77,500.00
414275883.xlsx432/353 abk 10-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

50,000.00 60,000.00
50,000.00 17,500.00

85,270.00
10% 8,527.00
93,797.00

a Air Limbah Jenis Pipa Tanah Ø 20 cm 84,634.00


8,580.00
57,000.00 4,560.00
84,000.00 3,360.00
87,000.00 348.00
78,000.00 312.00
68,360.00
10,000.00 16,000.00
1,360.00 47,600.00
210,000.00 2,940.00
130,000.00 1,820.00
-

76,940.00
10% 7,694.00
84,634.00

a Air Limbah Jenis Pipa Tanah Ø 15 cm 35,907.30


6,435.00
57,000.00 3,420.00
84,000.00 2,520.00
87,000.00 261.00
78,000.00 234.00

414275883.xlsx432/354 abk 10-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

26,208.00
8,000.00 12,800.00
1,360.00 9,248.00
210,000.00 2,730.00
130,000.00 1,430.00
,

32,643.00
10% 3,264.30
35,907.30

92,681.82
15,015.00
57,000.00 7,980.00
84,000.00 5,880.00
87,000.00 609.00
78,000.00 546.00
69,241.20
35,000.00 38,500.00
390,000.00 10,530.00
1,360.00 5,331.20
210,000.00 11,760.00
130,000.00 3,120.00

84,256.20
10% 8,425.62
92,681.82

528,080.30
40,755.00
57,000.00 21,660.00
84,000.00 15,960.00
87,000.00 1,653.00
78,000.00 1,482.00
439,318.00
180,000.00 198,000.00
414275883.xlsx432/355 abk 10-14
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

390,000.00 214,500.00
1,360.00 14,008.00
210,000.00 12,810.00
130,000.00 8,970.00

480,073.00
10% 48,007.30
528,080.30

414275883.xlsx432/356 abk 10-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil
A Tenaga
L.01 0.06 OH Pekerja
L.02 0.06 OH Tukang Besi
L.03 0.006 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan

1.15 Kg Besi Profil


0.06 Kg Meni Besi

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)


Overhead & Profit (contoh 10%)

2 A.4.2.1.2 1 kg Pemasangan Rangka Kuda-kuda Baja IWF


A Tenaga
L.01 0.06 OH Pekerja
L.02 0.06 OH Tukang Besi
L.03 0.006 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
1.15 kg Besi Baja IWF

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja)


A Tenaga
L.01 0.100 OH Pekerja
L.02 0.100 OH Tukang Besi

414275883.xlsx 432/357 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.001 OH Kepala Tukang


L.04 0.005 OH Mandor
B Bahan

1 ltr Solar
0.1 ltr Minyak Pelumas
C PERALATAN

0.800 jam Sewa Alat


D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

4 A.4.2.1.4 1 m2 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rang


A Tenaga
L.01 1.05 OH Pekerja
L.02 1.05 OH Tukang Besi
L.03 0.105 OH Kepala Tukang
L.04 0.052 OH Mandor
B Bahan
15 Kg Besi Siku L.30.30.3
32.8 Kg Besi Plat Baja
0.05 Kg Kawat Las

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/358 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik

A Tenaga
L.01 0.04 OH Pekerja
L.02 0.02 OH Tukang Besi
L.03 0.002 OH Kepala Tukang
L.04 0.002 OH Mandor

B Bahan
0.04 kg Kawat Las

0.03 ltr Solar


0.004 ltr Minyak Pelumas
C PERALATAN

0.170 jam Sewa Alat


D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

6 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi


A Tenaga
L.01 1.2 OH Pekerja
L.02 1.2 OH Tukang Besi
L.03 0.12 OH Kepala Tukang
L.04 0.006 OH Mandor
B Bahan

1 m2 Pintu Gulung Besi


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

7 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door)


A Tenaga
L.01 0.44 OH Pekerja
L.02 0.44 OH Tukang Besi

414275883.xlsx 432/359 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.03 0.044 OH Kepala Tukang


L.04 0.022 OH Mandor
B Bahan

1 m2 Pintu Lipat
C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

8 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium


A Tenaga
L.01 0.08 OH Pekerja
L.02 0.8 OH Tukang Besi
L.03 0.08 OH Kepala Tukang
L.04 0.004 OH Mandor
B Bahan

1 m2 Sunscreen Allumunium
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium

A Tenaga
L.01 1 OH Pekerja
L.02 1 OH Tukang Besi
L.03 0.1 OH Kepala Tukang
L.04 0.05 OH Mandor

414275883.xlsx 432/360 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan

1 m2 Rolling Allumunium
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium

A Tenaga
L.01 0.043 OH Pekerja
L.02 0.043 OH Tukang Besi
L.03 0.0043 OH Kepala Tukang
L.04 0.0021 OH Mandor

B Bahan
1.1 m' Profil Allumunium
2 buah Skrup Fixer

0.06 Tube Sealant


C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm

A Tenaga
L.01 0.085 OH Pekerja
L.02 0.085 OH Tukang Besi
L.03 0.0085 OH Kepala Tukang
L.04 0.0042 OH Mandor

B Bahan
4.4 m' Profil Allumunium
14.6 m' Allumunium Strip

C PERALATAN
D Jumlah A + B + C

414275883.xlsx 432/361 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

12 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium


A Tenaga
L.01 0.085 OH Pekerja
L.02 0.085 OH Tukang Besi
L.03 0.009 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
4.4 m' Pintu Allumunium

4.5 m' Profil Kaca


0.27 tube Sealant

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

13 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds


A Tenaga
L.01 0.35 OH Pekerja
L.02 0.35 OH Tukang Besi
L.03 0.035 OH Kepala Tukang
L.04 0.018 OH Mandor

414275883.xlsx 432/362 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan

1 m2 Venetions Blinds atau Vertical Blinds (tirai)


C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

14 A.4.2.1.15 1 m2 Pemasangan Terali Besi Strip (2x3) cm

A Tenaga
L.01 1.67 OH Pekerja
L.02 1.67 OH Tukang Las
L.03 0.167 OH Kepala Tukang
L.04 0.083 OH Mandor

B Bahan
6.177 m' Besi Strip 2x3
27.08 cm Pengelasan

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

15 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk


A Tenaga
L.01 0.1 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.0050 OH Mandor
B Bahan

1.1 m2 Kawat Nyamuk nylon


11.11 cm Pengelasan
1.716 kg Baja Strip (0,2x2) cm

C PERALATAN
D Jumlah A + B + C

414275883.xlsx 432/363 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

16 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis


A Tenaga
L.01 0.2 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1.1 m2 Jendela Nako

10 buah Paku Skrup 1 - 2,5 cm


7 m' Besi Strip
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

17 A.4.2.1.18 1 m' Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 c

A Tenaga
L.01 0.20 OH Pekerja
L.02 0.4 OH Tukang Kayu
L.03 0.025 OH Kepala Tukang
L.04 0.01 OH Mandor

414275883.xlsx 432/364 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan

1.05 Lbr Seng Plaat


0.015 Kg Paku Biasa 1 - 2,5 cm

0.019 m3 Kayu Papan Klas II atau III


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

18 A.4.2.1.19 1 m' Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJ


A Tenaga
L.01 0.15 OH Pekerja
L.02 0.3 OH Tukang Kayu
L.03 0.03 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan

1.05 Lbr Seng Plaat


0.01 Kg Paku Biasa 1 - 2,5 cm

0.5 Kg Besi strip


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

19 A.4.2.1.20 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 6


A Tenaga
L.01 0.250 OH Pekerja
L.02 0.250 OH Tukang Besi
L.03 0.025 OH Kepala Tukang
L.04 0.013 OH Mandor
B Bahan

3.50 m' Rangka metal hollow 40.40.2 mm


1.00 Assesoris (perkuatan; las dll)

414275883.xlsx 432/365 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

20 A.4.2.1.21 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 6


A Tenaga
L.01 0.350 OH Pekerja
L.02 0.350 OH Tukang Besi
L.03 0.035 OH Kepala Tukang
L.04 0.018 OH Mandor
B Bahan
4.00 m' Rangka metal hollow 40.40.2 mm
1.00 Assesoris (perkuatan; las dll)

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

414275883.xlsx 432/366 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

PEKERJAAN BESI & ALLUMUNIUM


27,968.60
9,216.00

57,000.00 3,420.00
84,000.00 5,040.00

87,000.00 522.00
78,000.00 234.00
16,210.00

13,000.00 14,950.00
21,000.00 1,260.00

25,426.00
10% 2,542.60

27,968.60

26,582.60
9,216.00
57,000.00 3,420.00
84,000.00 5,040.00
87,000.00 522.00

78,000.00 234.00
14,950.00
13,000.00 14,950.00

24,166.00
10% 2,416.60
26,582.60

aan Perakitan (Kuda-kuda Baja) 72,739.70


14,577.00

57,000.00 5,700.00
84,000.00 8,400.00

414275883.xlsx 432/367 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

87,000.00 87.00

78,000.00 390.00
15,550.00

11,300.00 11,300.00
42,500.00 4,250.00
36,000

45,000 36,000
66,127.00
10% 6,612.70
72,739.70

Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku 845,725.10


161,241.00

57,000.00 59,850.00
84,000.00 88,200.00
87,000.00 9,135.00

78,000.00 4,056.00
607,600.00

13,000.00 195,000.00
12,500.00 410,000.00
52,000.00 2,600.00

768,841.00
10% 76,884.10
845,725.10

414275883.xlsx 432/368 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

15,981.90

4,290.00
57,000.00 2,280.00

84,000.00 1,680.00
87,000.00 174.00
78,000.00 156.00

2,589.00
52,000.00 2,080.00

11,300.00 339.00
42,500.00 170.00
7,650

45,000 7,650
14,529.00
10% 1,452.90
15,981.90

550,118.80
180,108.00

57,000.00 68,400.00
84,000.00 100,800.00
87,000.00 10,440.00

78,000.00 468.00
320,000.00

320,000.00 320,000.00

500,108.00
10% 50,010.80
550,118.80

525,342.40
67,584.00

57,000.00 25,080.00
84,000.00 36,960.00

414275883.xlsx 432/369 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

87,000.00 3,828.00

78,000.00 1,716.00
410,000.00

410,000.00 410,000.00

477,584.00
10% 47,758.40
525,342.40

455,435.20
79,032.00

57,000.00 4,560.00
84,000.00 67,200.00

87,000.00 6,960.00
78,000.00 312.00
335,000.00

335,000.00 335,000.00

414,032.00
10% 41,403.20
455,435.20

454,960.00

153,600.00
57,000.00 57,000.00
84,000.00 84,000.00

87,000.00 8,700.00
78,000.00 3,900.00

414275883.xlsx 432/370 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

260,000.00

260,000.00 260,000.00

413,600.00
10% 41,360.00
454,960.00

112,640.99

6,600.90
57,000.00 2,451.00
84,000.00 3,612.00

87,000.00 374.10
78,000.00 163.80

95,800.00
83,000.00 91,300.00
750.00 1,500.00

50,000.00 3,000.00

102,400.90
10% 10,240.09
112,640.99

u Allumunium Strip Lebar 8 cm 488,347.31

13,052.10
57,000.00 4,845.00
84,000.00 7,140.00

87,000.00 739.50
78,000.00 327.60

430,900.00
83,000.00 365,200.00
4,500.00 65,700.00

443,952.10

414275883.xlsx 432/371 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

10% 44,395.21

488,347.31

u Kaca Rangka Allumunium 455,793.80


13,158.00
57,000.00 4,845.00

84,000.00 7,140.00
87,000.00 783.00

78,000.00 390.00
401,200.00
83,000.00 365,200.00

5,000.00 22,500.00
50,000.00 13,500.00

414,358.00
10% 41,435.80

455,793.80

etions Blinds & Vertical Blinds 163,678.90


53,799.00
57,000.00 19,950.00

84,000.00 29,400.00
87,000.00 3,045.00

78,000.00 1,404.00

414275883.xlsx 432/372 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

95,000.00

95,000.00 95,000.00

148,799.00
10% 14,879.90
163,678.90

338,220.56

256,473.00
57,000.00 95,190.00
84,000.00 140,280.00

87,000.00 14,529.00
78,000.00 6,474.00

51,000.24
1,250.00 7,721.25
1,598.19 43,278.99

307,473.24
10% 30,747.32
338,220.56

49,676.98
15,360.00

57,000.00 5,700.00
84,000.00 8,400.00
87,000.00 870.00

78,000.00 390.00
29,800.89

9,000.00 9,900.00
1,598.19 17,755.89
1,250.00 2,145.00

45,160.89

414275883.xlsx 432/373 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

10% 4,516.09

49,676.98

64,204.80
30,018.00
57,000.00 11,400.00

84,000.00 16,800.00
87,000.00 1,740.00

78,000.00 78.00
28,350.00
12,500.00 13,750.00

200.00 2,000.00
1,800.00 12,600.00

58,368.00
10% 5,836.80
64,204.80

ng Datar/Jurai , Seng BJLS 28 Lebar 90 cm 172,716.50

47,955.00
57,000.00 11,400.00
84,000.00 33,600.00

87,000.00 2,175.00
78,000.00 780.00

414275883.xlsx 432/374 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

109,060.00

15,000.00 15,750.00
14,000.00 210.00

4,900,000.00 93,100.00

157,015.00
10% 15,701.50
172,716.50

ng 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm 65,036.40


36,984.00

57,000.00 8,550.00
84,000.00 25,200.00

87,000.00 2,610.00
78,000.00 624.00
22,140.00

15,000.00 15,750.00
14,000.00 140.00

12,500.00 6,250.00

59,124.00
10% 5,912.40
65,036.40

gka Besi Hollow 1 x 40.40.2mm; Modul 60x120 cm dinding partisi 157,782.90


38,439.00

57,000.00 14,250.00
84,000.00 21,000.00

87,000.00 2,175.00
78,000.00 1,014.00
105,000.00

15,000.00 52,500.00
52,500.00 52,500.00

414275883.xlsx 432/375 abk 11-14


HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

143,439.00
10% 14,343.90
157,782.90

gka Besi Hollow 1 x 40.40.2mm; Modul 60x60 cm dinding plafond 191,178.90


53,799.00

57,000.00 19,950.00
84,000.00 29,400.00
87,000.00 3,045.00
78,000.00 1,404.00
120,000.00
15,000.00 60,000.00
60,000.00 60,000.00

173,799.00
10% 17,379.90
191,178.90

414275883.xlsx 432/376 abk 11-14


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa
A Tenaga
L.01 0.01 OH Pekerja
L.02 0.5 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1 Buah Kunci Tanam Biasa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)

2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi


A Tenaga
L.01 0.005 OH Pekerja
L.02 0.5 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.0025 OH Mandor
B Bahan
1 Buah Kunci Tanam Kamar Mandi
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder


A Tenaga
L.01 0.005 OH Pekerja
L.02 0.5 OH Tukang Kayu
L.03 0.005 OH Kepala Tukang
L.04 0.0025 OH Mandor
B Bahan
1 Buah Kunci Selinder
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu


A Tenaga
L.01 0.015 OH Pekerja
L.02 0.15 OH Tukang Kayu
L.03 0.015 OH Kepala Tukang
L.04 0.0075 OH Mandor
B Bahan
1 Buah Engsel pintu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu


A Tenaga
L.01 0.01 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1 Buah Engsel Jendela
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin


A Tenaga
L.01 0.10 OH Pekerja
L.02 0.20 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.0005 OH Mandor
B Bahan
1 Buah Engsel Angin
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin


A Tenaga
L.01 0.015 OH Pekerja
L.02 0.15 OH Tukang Kayu
L.03 0.015 OH Kepala Tukang
L.04 0.008 OH Mandor
B Bahan
1 Buah Kait Angin
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 A.4.6.2.10 1 Buah Pasang Door Closer


A Tenaga
L.01 0.05 OH Pekerja
L.02 0.5 OH Tukang Kayu
L.03 0.05 OH Kepala Tukang
L.04 0.0025 OH Mandor
B Bahan
1 Buah Door Closer
C PERALATAN
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot


A Tenaga
L.01 0.02 OH Pekerja
L.02 0.2 OH Tukang Kayu
L.03 0.02 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1 Buah Kunci Selot
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

10 A.4.6.2.13 1 Buah Pemasangan Door Stop


A Tenaga
L.01 0.01 OH Pekerja
L.02 0.1 OH Tukang Kayu
L.03 0.01 OH Kepala Tukang
L.04 0.0005 OH Mandor
B Bahan
1 Buah Door Stop
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong


A Tenaga
L.01 0.06 OH Pekerja
L.02 0.6 OH Tukang Kayu
L.03 0.06 OH Kepala Tukang
L.04 0.003 OH Mandor
B Bahan
1 Buah Rel Pintu Dorong
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari


A Tenaga
L.01 0.025 OH Pekerja
L.02 0.25 OH Tukang Kayu
L.03 0.025 OH Kepala Tukang
L.04 0.00130 OH Mandor
B Bahan
1 Buah Kunci Lemari
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm


A Tenaga
L.01 0.015 OH Pekerja
L.02 0.15 OH Tukang Kayu
L.03 0.015 OH Kepala Tukang
L.04 0.00075 OH Mandor
B Bahan
1.1 m2 Kaca tebal 3mm
C PERALATAN
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm


A Tenaga
L.01 0.015 OH Pekerja
L.02 0.15 OH Tukang Kayu
L.03 0.015 OH Kepala Tukang
L.04 0.00075 OH Mandor
B Bahan
1.1 m2 Kaca tebal 5mm
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm


A Tenaga
L.01 0.015 OH Pekerja
L.02 0.15 OH Tukang Kayu
L.03 0.015 OH Kepala Tukang
L.04 0.00075 OH Mandor
B Bahan
1.1 m2 Kaca Cermin
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

N PEKERJAAN KUNCI dan KACA


213,213.00
43,830.00
57,000.00 570.00
84,000.00 42,000.00
87,000.00 870.00
78,000.00 390.00
150,000.00
150,000.00 150,000.00

193,830.00
10% 19,383.00
213,213.00

144,006.50
42,915.00
57,000.00 285.00
84,000.00 42,000.00
87,000.00 435.00
78,000.00 195.00
88,000.00
88,000.00 88,000.00

130,915.00
10% 13,091.50
144,006.50

212,206.50
42,915.00
57,000.00 285.00
84,000.00 42,000.00
87,000.00 435.00
78,000.00 195.00
150,000.00
150,000.00 150,000.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

192,915.00
10% 19,291.50
212,206.50

25,679.50
15,345.00
57,000.00 855.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 585.00
8,000.00
8,000.00 8,000.00

23,345.00
10% 2,334.50
25,679.50

16,203.00
10,230.00
57,000.00 570.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 390.00
4,500.00
4,500.00 4,500.00

14,730.00
10% 1,473.00
16,203.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

43,756.90
24,279.00
57,000.00 5,700.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 39.00
15,500.00
15,500.00 15,500.00

39,779.00
10% 3,977.90
43,756.90

30,672.40
15,384.00
57,000.00 855.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 624.00
12,500.00
12,500.00 12,500.00

27,884.00
10% 2,788.40
30,672.40

384,334.50
49,395.00
57,000.00 2,850.00
84,000.00 42,000.00
87,000.00 4,350.00
78,000.00 195.00
300,000.00
300,000.00 300,000.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

349,395.00
10% 34,939.50
384,334.50

39,333.80
19,758.00
57,000.00 1,140.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 78.00
16,000.00
16,000.00 16,000.00

35,758.00
10% 3,575.80
39,333.80

340,866.90
9,879.00
57,000.00 570.00
84,000.00 8,400.00
87,000.00 870.00
78,000.00 39.00
300,000.00
300,000.00 300,000.00

309,879.00
10% 30,987.90
340,866.90
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

296,201.40
59,274.00
57,000.00 3,420.00
84,000.00 50,400.00
87,000.00 5,220.00
78,000.00 234.00
210,000.00
210,000.00 210,000.00

269,274.00
10% 26,927.40
296,201.40

32,671.54
24,701.40
57,000.00 1,425.00
84,000.00 21,000.00
87,000.00 2,175.00
78,000.00 101.40
5,000.00
5,000.00 5,000.00

29,701.40
10% 2,970.14
32,671.54

90,110.35
14,818.50
57,000.00 855.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 58.50
67,100.00
61,000.00 67,100.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

81,918.50
10% 8,191.85
90,110.35

103,420.35
14,818.50
57,000.00 855.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 58.50
79,200.00
72,000.00 79,200.00

94,018.50
10% 9,401.85
103,420.35

336,950.35
14,818.50
57,000.00 855.00
84,000.00 12,600.00
87,000.00 1,305.00
78,000.00 58.50
291,500.00
265,000.00 291,500.00

306,318.50
10% 30,631.85
336,950.35
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan D

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm


A Tenaga
L.01 0.25 OH Pekerja
L.02 0.125 OH Tukang Batu
L.03 0.013 OH Kepala Tukang
L.04 0.013 OH Mandor
B Bahan
11.87 Buah Ubin Abu-abu 30x30 cm

10.0 Kg Portland Semen


0.0450 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm


A Tenaga
L.01 0.27 OH Pekerja
L.02 0.135 OH Tukang Batu
L.03 0.014 OH Kepala Tukang
L.04 0.014 OH Mandor
B Bahan
26.5 Buah Ubin Abu-abu 20x20 cm

10.4 Kg Portland Semen


0.0450 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm


A Tenaga
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.01 0.26 OH Pekerja


L.02 0.130 OH Tukang Batu
L.03 0.013 OH Kepala Tukang
L.04 0.013 OH Mandor
B Bahan
11.87 Buah Ubin Warna 30x30 cm
10.0 Kg Portland Semen
1.50 Kg Semen warna
0.0450 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm


A Tenaga
L.01 0.27 OH Pekerja
L.02 0.135 OH Tukang Batu
L.03 0.014 OH Kepala Tukang
L.04 0.014 OH Mandor
B Bahan
26.5 Buah Ubin Warna 20x20 cm
10.4 Kg Portland Semen
1.62 Kg Semen warna
0.0450 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm

A Tenaga
L.01 0.250 OH Pekerja
L.02 0.125 OH Tukang Batu
L.03 0.013 OH Kepala Tukang
L.04 0.013 OH Mandor
B Bahan
6.63 Buah Ubin Granito 40x40 cm

9.8 Kg Portland Semen


1.300 Kg Semen warna

0.045 m3 Pasir Pasang


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm

A Tenaga
L.01 0.090 OH Pekerja
L.02 0.090 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.005 OH Mandor

B Bahan
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm
1.2 Kg Portland Semen

0.045 m3 Pasir Pasang


C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm

A Tenaga
L.01 0.090 OH Pekerja
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.02 0.090 OH Tukang Batu


L.03 0.009 OH Kepala Tukang
L.04 0.005 OH Mandor

B Bahan
2.65 Buah Ubin Plin Pc SWarna 15x20 cm
1.14 Kg Portland Semen

0.100 Kg Semen Warna


0.003 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)

F Harga Satuan Pekerjaan (D+E)

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm


A Tenaga
L.01 0.70 OH Pekerja
L.02 0.350 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
53.00 Buah Keramik 10 x 20 cm

8.2 Kg Portland Semen


2.75 Kg Semen Warna

0.0450 m3 Pasir Pasang


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm

A Tenaga
L.01 0.70 OH Pekerja
L.02 0.350 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor

B Bahan
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm

8.19 Kg Portland Semen


3.20 Kg Semen Warna
0.0450 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm


A Tenaga
L.01 0.70 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan

10 Buah Ubin Keramik 33 x 33 cm


8.19 Kg Portland Semen
0.045 m3 Pasir Pasang

1.62 Kg Semen Warna


C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm

A Tenaga
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.01 0.70 OH Pekerja


L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
11.87 Buah Ubin Keramik 30 x 30 cm

10.00 Kg Portland Semen


0.045 m3 Pasir Pasang

1.50 Kg Semen Warna


C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%)


F Harga Satuan Pekerjaan (D+E)

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm


A Tenaga
L.01 0.70 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
26.5 Buah Ubin Keramik 20 x 20 cm
10.40 Kg Portland Semen
1.62 Kg Semen Warna
0.045 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

13 A.4.4.3.37 1 m2 Pemasangan Lantai Keramik uk.10 x 33 cm, untuk varias


A Tenaga
L.01 1.05 OH Pekerja
L.02 0.525 OH Tukang Batu
L.03 0.053 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
33.0 Buah Ubin Keramik
9.80 Kg Portland Semen
4.37 Kg Semen Warna
0.045 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm


A Tenaga
L.01 0.09 OH Pekerja
L.02 0.09 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
5.3 Buah Ubin Keramik
1.14 Kg Portland Semen
0.003 m3 Pasir Pasang
0.025 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm


A Tenaga
L.01 0.09 OH Pekerja
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.02 0.09 OH Tukang Batu


L.03 0.009 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
10.6 Buah Ubin Keramik
1.14 Kg Portland Semen
0.003 m3 Pasir Pasang
0.05 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm


A Tenaga
L.01 0.09 OH Pekerja
L.02 0.09 OH Tukang Batu
L.03 0.009 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
10.6 Buah Ubin Keramik
1.14 Kg Portland Semen
0.003 m3 Pasir Pasang
0.05 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm


A Tenaga
L.01 0.7 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
1.06 buah Marmer
8.19 kg Portland Semen
0.045 m3 Pasir Pasang
0.65 kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet


A Tenaga
L.01 0.17 OH Pekerja
L.02 0.17 OH Tukang Batu
L.03 0.017 OH Kepala Tukang
L.04 0.009 OH Mandor
B Bahan
1.05 m2 Karpet
0.35 kg Lem
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati


A Tenaga
L.01 0.70 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.035 OH Mandor


B Bahan
1.05 m2 Parquet Jati
0.6 Kg Lem Vynil
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm


A Tenaga
L.01 1.00 OH Pekerja
L.02 0.50 OH Tukang Batu
L.03 0.050 OH Kepala Tukang
L.04 0.050 OH Mandor
B Bahan
86 bh Porselen
9.30 Kg Portland Semen

2.750 Kg Semen Warna

0.018 m3 Pasir Pasang

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

21 A.4.4.3.49 1 m2 Pemasangan Dinding Keramik 10x20 cm,


A Tenaga
L.01 0.9 OH Pekerja
L.02 0.45 OH Tukang Batu
L.03 0.045 OH Kepala Tukang
L.04 0.045 OH Mandor
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
53 Buah Keramik
9.3 Kg Portland Semen
0.018 m3 Pasir Pasang
2.75 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

22 A.4.4.3.50 1 m2 Pemasangan Dinding Keramik 20x20 cm,


A Tenaga
L.01 0.9 OH Pekerja
L.02 0.45 OH Tukang Batu
L.03 0.045 OH Kepala Tukang
L.04 0.045 OH Mandor
B Bahan
26.0 Buah Keramik
9.3 Kg Portland Semen
0.018 m3 Pasir Pasang
1.94 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm,


A Tenaga
L.01 0.9 OH Pekerja
L.02 0.45 OH Tukang Batu
L.03 0.045 OH Kepala Tukang
L.04 0.045 OH Mandor
B Bahan
53.0 Buah Keramik
9.3 Kg Portland Semen
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

0.018 m3 Pasir Pasang


2.75 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

23 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm,


A Tenaga
L.01 0.9 OH Pekerja
L.02 0.45 OH Tukang Batu
L.03 0.045 OH Kepala Tukang
L.04 0.045 OH Mandor
B Bahan
26.5 Buah Keramik
9.3 Kg Portland Semen
0.018 m3 Pasir Pasang
1.94 Kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

24 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm


A Tenaga
L.01 1.3 OH Pekerja
L.02 0.65 OH Tukang Batu
L.03 0.065 OH Kepala Tukang
L.04 0.065 OH Mandor
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
1.06 buah Marmer
3.003 buah Paku 12 cm
12.44 kg Portlan Semen
0.025 m3 Pasir Pasang
0.65 kg Semen Warna
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

25 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam


A Tenaga
L.01 0.70 OH Pekerja
L.02 0.35 OH Tukang Batu
L.03 0.035 OH Kepala Tukang
L.04 0.035 OH Mandor
B Bahan
1.10 m2 Batu Paros
11.75 Kg Portland Semen
0.035 m3 Pasir Pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

26 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm


A Tenaga
L.01 0.35 OH Pekerja
L.02 0.175 OH Tukang Batu
L.03 0.017 OH Kepala Tukang
L.04 0.002 OH Mandor
B Bahan
11.87 bh Vynil 30x30cm
0.25 kg Lem
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

27 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm


Tenaga
L.01 0.12 OH Pekerja
L.02 0.12 OH Tukang Batu
L.03 0.012 OH Kepala Tukang
L.04 0.006 OH Mandor
Bahan
0.003 m3 Papan Kayu Klas II
0.05 kg Paku Sekrup 5 cm

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

N PEKERJAAN PENUTUP LANTAI dan DINDING

tai Ubin PC Abu-abu Uk. 30 x 30 cm 95,297.50


26,895.00
57,000.00 14,250.00

84,000.00 10,500.00
87,000.00 1,131.00

78,000.00 1,014.00
59,739.09
11.1111111111 3,090.91 36,689.09

0.3 1,360.00 13,600.00


0.09 210,000.00 9,450.00

86,634.09
10% 8,663.41

95,297.50

tai Ubin PC Abu-abu Uk. 20 x 20 cm 95,209.40


29,040.00
57,000.00 15,390.00

84,000.00 11,340.00
87,000.00 1,218.00

78,000.00 1,092.00
57,514.00
1,280.00 33,920.00

1,360.00 14,144.00
210,000.00 9,450.00

86,554.00
10% 8,655.40

95,209.40

tai Ubin PC Warna Uk. 30 x 30 cm 124,293.50


27,885.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

57,000.00 14,820.00

84,000.00 10,920.00
87,000.00 1,131.00

78,000.00 1,014.00
85,109.09
4,090.91 48,559.09
1,360.00 13,600.00
9,000 13,500.00
210,000.00 9,450.00

112,994.09
10% 11,299.41

124,293.50

tai Ubin PC Warna Uk. 20 x 20 cm 120,575.40


29,040.00

57,000.00 15,390.00
84,000.00 11,340.00
87,000.00 1,218.00
78,000.00 1,092.00
80,574.00
1,600.00 42,400.00
1,360.00 14,144.00
9,000.00 14,580.00
210,000.00 9,450.00

109,614.00
10% 10,961.40

120,575.40
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

tai Ubin Granito Uk. 40 x 40 cm 347,075.30

26,895.00
57,000.00 14,250.00
84,000.00 10,500.00
87,000.00 1,131.00

78,000.00 1,014.00
288,628.00
0.4 38,333.33 254,150.00

0.16 1,360.00 13,328.00


6.25 9,000.00 11,700.00

210,000.00 9,450.00

315,523.00
10% 31,552.30
347,075.30

n Plin Pc.Abu-abu Uk. 15 x 20 cm 57,815.34

13,863.00
57,000.00 5,130.00
84,000.00 7,560.00

87,000.00 783.00
78,000.00 390.00

38,696.40
5,200.00 27,560.00
1,360.00 1,686.40

210,000.00 9,450.00

52,559.40
10% 5,255.94
57,815.34

n Plin Pc.Warna Uk. 10 x 20 cm 34,087.24

13,863.00
57,000.00 5,130.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

84,000.00 7,560.00

87,000.00 783.00
78,000.00 390.00

17,125.40
5,300.00 14,045.00
1,360.00 1,550.40

9,000.00 900.00
210,000.00 630.00

30,988.40
10% 3,098.84

34,087.24

189,588.74
75,075.00
57,000.00 39,900.00

84,000.00 29,400.00
87,000.00 3,045.00

78,000.00 2,730.00
97,278.40
980.00 51,940.00

1,360.00 11,138.40
9,000.00 24,750.00

210,000.00 9,450.00

172,353.40
10% 17,235.34
189,588.74
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

tai Keramik Uk. 10 x 10 cm / 5 x 20 cm 194,043.74

75,075.00
57,000.00 39,900.00

84,000.00 29,400.00
87,000.00 3,045.00
78,000.00 2,730.00

101,328.40
490.00 51,940.00

1,360.00 11,138.40
9,000.00 28,800.00
210,000.00 9,450.00

176,403.40
10% 17,640.34
194,043.74

186,045.52
75,075.00

57,000.00 39,900.00
84,000.00 29,400.00
87,000.00 3,045.00

78,000.00 2,730.00
94,057.29

5,888.89 58,888.89
1,360.00 11,138.40
210,000.00 9,450.00

9,000.00 14,580.00

169,132.29
10% 16,913.23
186,045.52

185,698.50

75,075.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

57,000.00 39,900.00

84,000.00 29,400.00
87,000.00 3,045.00

78,000.00 2,730.00
93,741.82
4,818.18 57,191.82

1,360.00 13,600.00
210,000.00 9,450.00

9,000.00 13,500.00

168,816.82
10% 16,881.68
185,698.50

187,537.90
75,075.00

57,000.00 39,900.00
84,000.00 29,400.00

87,000.00 3,045.00
78,000.00 2,730.00
95,414.00
2,160.00 57,240.00
1,360.00 14,144.00
9,000.00 14,580.00
210,000.00 9,450.00

170,489.00
10% 17,048.90
187,537.90
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

ntai Keramik uk.10 x 33 cm, untuk variasi / border 372,238.90


111,291.00
57,000.00 59,850.00
84,000.00 44,100.00
87,000.00 4,611.00
78,000.00 2,730.00
227,108.00
5,000.00 165,000.00
1,360.00 13,328.00
9,000.00 39,330.00
210,000.00 9,450.00

338,399.00
10% 33,839.90
372,238.90

32,470.24
13,863.00
57,000.00 5,130.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 390.00
15,655.40
2,500.00 13,250.00
1,360.00 1,550.40
210,000.00 630.00
9,000.00 225.00

29,518.40
10% 2,951.84
32,470.24

78,774.74
13,863.00
57,000.00 5,130.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

84,000.00 7,560.00
87,000.00 783.00
78,000.00 390.00
57,750.40
5,200.00 55,120.00
1,360.00 1,550.40
210,000.00 630.00
9,000.00 450.00

71,613.40
10% 7,161.34
78,774.74

76,442.74
13,863.00
57,000.00 5,130.00
84,000.00 7,560.00
87,000.00 783.00
78,000.00 390.00
55,630.40
5,000.00 53,000.00
1,360.00 1,550.40
210,000.00 630.00
9,000.00 450.00

69,493.40
10% 6,949.34
76,442.74
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

ntai Marmer Ukuran 1.00x1.00 cm 665,514.74


75,075.00
57,000.00 39,900.00
84,000.00 29,400.00
87,000.00 3,045.00
78,000.00 2,730.00
529,938.40
475,000.00 503,500.00
1,360.00 11,138.40
210,000.00 9,450.00
9,000.00 5,850.00

605,013.40
10% 60,501.34
665,514.74

187,771.10
26,151.00
57,000.00 9,690.00
84,000.00 14,280.00
87,000.00 1,479.00
78,000.00 702.00
144,550.00
125,000.00 131,250.00
38,000.00 13,300.00

170,701.00
10% 17,070.10
187,771.10

338,662.50
75,075.00
57,000.00 39,900.00
84,000.00 29,400.00
87,000.00 3,045.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

78,000.00 2,730.00
232,800.00
200,000.00 210,000.00
38,000.00 22,800.00

307,875.00
10% 30,787.50
338,662.50

212,301.29
107,250.00
57,000.00 57,000.00
84,000.00 42,000.00
87,000.00 4,350.00
78,000.00 3,900.00
85,751.17
518.29 44,573.17
82.6446280992 1,360.00 12,648.00

0.0121 9,000.00 24,750.00

0.11 210,000.00 3,780.00

193,001.17
10% 19,300.12
212,301.29

208,607.30
96,525.00
57,000.00 51,300.00
84,000.00 37,800.00
87,000.00 3,915.00
78,000.00 3,510.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

93,118.00
980.00 51,940.00
1,360.00 12,648.00
210,000.00 3,780.00
9,000.00 24,750.00

189,643.00
10% 18,964.30
208,607.30

200,654.30
96,525.00
57,000.00 51,300.00
84,000.00 37,800.00
87,000.00 3,915.00
78,000.00 3,510.00
85,888.00
2,000.00 52,000.00
1,360.00 12,648.00
210,000.00 3,780.00
9,000.00 17,460.00

182,413.00
10% 18,241.30
200,654.30

208,607.30
96,525.00
57,000.00 51,300.00
84,000.00 37,800.00
87,000.00 3,915.00
78,000.00 3,510.00
93,118.00
980.00 51,940.00
1,360.00 12,648.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

210,000.00 3,780.00
9,000.00 24,750.00

189,643.00
10% 18,964.30
208,607.30

201,754.30
96,525.00
57,000.00 51,300.00
84,000.00 37,800.00
87,000.00 3,915.00
78,000.00 3,510.00
86,888.00
2,000.00 53,000.00
1,360.00 12,648.00
210,000.00 3,780.00
9,000.00 17,460.00

183,413.00
10% 18,341.30
201,754.30

ding Marmer Ukuran 1.00x1.00 cm 738,153.36


139,425.00
57,000.00 74,100.00
84,000.00 54,600.00
87,000.00 5,655.00
78,000.00 5,070.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

531,623.51
475,000.00 503,500.00
35.00 105.11
1,360.00 16,918.40
210,000.00 5,250.00
9,000.00 5,850.00

671,048.51
10% 67,104.85
738,153.36

ding Batu Paros / Batu Tempel Hitam 223,195.50


75,075.00
57,000.00 39,900.00
84,000.00 29,400.00
87,000.00 3,045.00
78,000.00 2,730.00
127,830.00
95,000.00 104,500.00
1,360.00 15,980.00
210,000.00 7,350.00

202,905.00
10% 20,290.50
223,195.50

133,928.30
36,285.00
57,000.00 19,950.00
84,000.00 14,700.00
87,000.00 1,479.00
78,000.00 156.00
85,468.00
6,400.00 75,968.00
38,000.00 9,500.00
HARGA
BAHAN/UPAH JUMLAH
URAIAN PEKERJAAN
Rp Rp

121,753.00
10% 12,175.30
133,928.30

nt Kayu Klas II Ukuran 2x10 cm 40,900.20


18,432.00
57,000.00 6,840.00
84,000.00 10,080.00
87,000.00 1,044.00
78,000.00 468.00
18,750.00
6,000,000.00 18,000.00
15,000.00 750.00

37,182.00
10% 3,718.20
40,900.20
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 1 m2 Pengikisan / pengerokan Permukaan Cat Tembok Lama


A Tenaga

L.01 0.15 OH Pekerja


L.04 0.0030 OH Mandor

B Bahan
0.05 Kg Soda Api
C PERALATAN

D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

2 A.4.7.1.2 1 m2 Pencucian Bidang Permukaan Tembok yang Pernah dicat

A Tenaga
L.01 0.15 OH Pekerja

L.04 0.0030 OH Mandor


B Bahan
0.05 Kg Sabun
C PERALATAN
D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

3 A.4.7.1.3 1 m2 Pengerokan Karat Cat Lama permukaan Baja dg cara man


A Tenaga
L.01 0.15 OH Pekerja
L.04 0.0080 OH Mandor
B Bahan
0.05 Kg Sabun
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

4 A.4.7.1.4 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat das


A Tenaga

L.01 0.070 OH Pekerja

L.02 0.009 OH Tukang Cat

L.03 0.006 OH Kepala Tukang

L.04 0.003 OH Mandor

B Bahan
0.2000 kg Cat Menie

0.1500 kg Plamuur

0.1700 kg Cat Dasar

0.2600 kg Cat Penutup

0.0100 bh Kuas

0.0300 kg Pengencer

0.2000 lbr Amplas

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

5 A.4.7.1.5 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat das


A Tenaga

L.01 0.070 OH Pekerja

L.02 0.105 OH Tukang Cat

L.03 0.004 OH Kepala Tukang

L.04 0.003 OH Mandor


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
0.2000 kg Cat Menie

0.1500 kg Plamuur

0.1700 kg Cat Dasar

0.3500 kg Cat Penutup

0.0100 bh Kuas

0.0300 kg Pengencer

0.2000 lbr Amplas

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil


A Tenaga
L.01 0.04 OH Pekerja
L.02 0.063 OH Tukang Cat
L.03 0.063 OH Kepala Tukang
L.04 0.0030 OH Mandor
B Bahan
0.36 Ltr Teak Oil
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur


A Tenaga
L.01 0.04 OH Pekerja
L.02 0.06 OH Tukang Cat
L.03 0.016 OH Kepala Tukang
L.04 0.0030 OH Mandor
B Bahan
0.15 Ltr Politur
0.372 Ltr Politur Jadi
2 Lbr Ampelas
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter


A Tenaga
L.01 0.1 OH Pekerja
L.04 0.006 OH Mandor
B Bahan
0.35 Ltr Residu atau Ter
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis


A Tenaga
L.01 0.16 OH Pekerja
L.02 0.16 OH Tukang Cat
L.03 0.016 OH Kepala Tukang
L.04 0.0030 OH Mandor
B Bahan
0.15 Ltr Vernis
0.05 Ltr Dempul
0.1 Lbr Ampelas

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

10 A.4.7.1.10 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


2 lap. Cat Penutup)
A Tenaga
L.01 0.02 OH Pekerja
L.02 0.063 OH Tukang Cat
L.03 0.0063 OH Kepala Tukang
L.04 0.0030 OH Mandor
B Bahan
0.1 Kg Plamir
0.1 Kg Cat Dasar
0.26 Kg Cat Penutup 2 kali
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

11 A.4.7.1.11 1 m2 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup


A Tenaga
L.01 0.028 OH Pekerja
L.02 0.042 OH Tukang Cat
L.03 0.0042 OH Kepala Tukang
L.04 0.0030 OH Mandor
B Bahan
0.12 Kg Cat Dasar
0.18 Kg Cat Penutup 2 kali
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium


A Tenaga
L.01 0.028 OH Pekerja
L.02 0.042 OH Tukang Cat
L.03 0.0042 OH Kepala Tukang
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

L.04 0.0030 OH Mandor


B Bahan
0.1 Kg Kalkarium

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih


A Tenaga
L.01 0.150 OH Pekerja
L.02 0.001 OH Tukang Cat
L.03 0.0001 OH Kepala Tukang
L.04 0.0025 OH Mandor
B Bahan
0.15 Kg Kapur Sirih
0.1 lbr Amplas
0.25 ikat Alang-alang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

14 A.4.7.1.14 1 m2 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaa


A Tenaga
L.01 0.040 OH Pekerja
L.02 0.005 OH Tukang Cat
L.03 0.0005 OH Kepala Tukang
L.04 0.0025 OH Mandor
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

B Bahan
0.30 Kg Kapur Sirih
0.2 lbr Amplas
0.25 ikat Alang-alang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.200 OH Tukang Cat
L.03 0.0200 OH Kepala Tukang
L.04 0.0025 OH Mandor
B Bahan
1.20 lbr Wall Paper
0.2 kg Lem

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi


A Tenaga
L.01 0.02 OH Pekerja
L.02 0.2 OH Tukang Cat
L.03 0.002 OH Kepala Tukang
L.04 0.0025 OH Mandor
B Bahan
0.1 Kg Meni Besi
0.01 Kg Perekat / Lem
C PERALATAN
D Jumlah A + B + C
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

17 A.4.7.1.17 1 m2 Pengecatan Permukaan Baja dg Meni Besi & Perancah


A Tenaga
L.01 0.25 OH Pekerja
L.02 0.225 OH Tukang Cat
L.03 0.0225 OH Kepala Tukang
L.04 0.0075 OH Mandor
B Bahan
0.1 Kg Meni Besi
0.01 Kg Perekat / Lem
0.002 m3 Perancah Kayu
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


HARGA
BAHAN/UPAH JUMLAH
Rp Rp

engerokan Permukaan Cat Tembok Lama 10,349.90


8,784.00

57,000.00 8,550.00
78,000.00 234.00

625.00
12,500.00 625.00

9,409.00
940.90

10,349.90

dang Permukaan Tembok yang Pernah dicat 10,349.90

8,784.00
57,000.00 8,550.00

78,000.00 234.00
625.00
12,500.00 625.00

9,409.00

940.90
10,349.90

arat Cat Lama permukaan Baja dg cara manual 10,778.90


9,174.00
57,000.00 8,550.00
78,000.00 624.00
625.00
12,500.00 625.00

9,799.00
979.90
10,778.90
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

idang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penut 39,652.80


5,502.00

57,000.00 3,990.00

84,000.00 756.00

87,000.00 522.00

78,000.00 234.00

30,546.00
28,000.00 5,600.00

28,000.00 4,200.00

35,000.00 5,950.00

52,000.00 13,520.00

7,600.00 76.00

14,000.00 420.00

3,900.00 780.00

36,048.00
3,604.80
39,652.80

idang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penut 53,479.80


13,392.00

57,000.00 3,990.00

84,000.00 8,820.00

87,000.00 348.00

78,000.00 234.00
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

35,226.00
28,000.00 5,600.00

28,000.00 4,200.00

35,000.00 5,950.00

52,000.00 18,200.00

7,600.00 76.00

14,000.00 420.00

3,900.00 780.00

48,618.00
4,861.80
53,479.80

30,851.70
13,287.00
57,000.00 2,280.00
84,000.00 5,292.00
87,000.00 5,481.00
78,000.00 234.00
14,760.00
41,000.00 14,760.00

28,047.00
2,804.70
30,851.70

40,814.40
8,946.00
57,000.00 2,280.00
84,000.00 5,040.00
87,000.00 1,392.00
78,000.00 234.00
28,158.00
39,000.00 5,850.00
39,000.00 14,508.00
3,900.00 7,800.00
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

37,104.00
3,710.40
40,814.40

7,862.80
6,168.00
57,000.00 5,700.00
78,000.00 468.00
980.00
2,800.00 980.00

7,148.00
714.80
7,862.80

32,698.60
24,186.00
57,000.00 9,120.00
84,000.00 13,440.00
87,000.00 1,392.00
78,000.00 234.00
5,540.00
25,000.00 3,750.00
28,000.00 1,400.00
3,900.00 390.00
-

29,726.00
2,972.60
32,698.60
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

17,285.51

7,214.10
57,000.00 1,140.00
84,000.00 5,292.00
87,000.00 548.10
78,000.00 234.00
8,500.00
21,000.00 2,100.00
12,000.00 1,200.00
20,000.00 5,200.00

15,714.10
1,571.41
17,285.51

embok Lama (1lap.Plamir, 2lap Cat Penutup) 11,839.74


5,723.40
57,000.00 1,596.00
84,000.00 3,528.00
87,000.00 365.40
78,000.00 234.00
5,040.00
12,000.00 1,440.00
20,000.00 3,600.00

10,763.40
1,076.34
11,839.74

6,768.74
5,723.40
57,000.00 1,596.00
84,000.00 3,528.00
87,000.00 365.40
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

78,000.00 234.00
430.00
4,300.00 430.00
-

6,153.40
615.34
6,768.74

11,855.47
8,837.70
57,000.00 8,550.00
84,000.00 84.00
87,000.00 8.70
78,000.00 195.00
1,940.00
7,500.00 1,125.00
3,900.00 390.00
1,700.00 425.00

10,777.70
1,077.77
11,855.47

mbok lama dengan Kapur Sirih (pemeliharaan) 5,976.85


2,938.50
57,000.00 2,280.00
84,000.00 420.00
87,000.00 43.50
78,000.00 195.00
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

2,495.00
4,300.00 1,290.00
3,900.00 780.00
1,700.00 425.00

5,433.50
543.35
5,976.85

76,422.50
19,875.00
57,000.00 1,140.00
84,000.00 16,800.00
87,000.00 1,740.00
78,000.00 195.00
49,600.00
35,000.00 42,000.00
38,000.00 7,600.00

69,475.00
6,947.50
76,422.50

22,867.90
18,309.00
57,000.00 1,140.00
84,000.00 16,800.00
87,000.00 174.00
78,000.00 195.00
2,480.00
21,000.00 2,100.00
38,000.00 380.00

20,789.00
HARGA
BAHAN/UPAH JUMLAH
Rp Rp

2,078.90
22,867.90

46,389.75
35,692.50
57,000.00 14,250.00
84,000.00 18,900.00
87,000.00 1,957.50
78,000.00 585.00
6,480.00
21,000.00 2,100.00
38,000.00 380.00
2,000,000.00 4,000.00

42,172.50
4,217.25
46,389.75

Anda mungkin juga menyukai