1.1 Data curah hujan yang digunakan yaitu data curah hujan Koya Barat tahun 2009 – 2018
Curah hujan rencana dan curah hujan berdasarkan periode ulang tertentu diperoleh dari
perhitungan analisis frekuensi. Perhitungan analisis frekuensi yang dilakukan menggunakan
empat distribusi berbeda. Keempat jenis distribusi tersebut yaitu distribusi normal,distribusi log normal,
distribusi Log Pearson III dan distribusi Gumbel.
No Xi Xi-ẍ ( Xi - ẍ )² ( Xi - ẍ )³ ( Xi -ẍ )⁴
1 34,03 -8,923 79,625 -710,511 6340,072
2 34,58 -8,374 70,117 -587,125 4916,325
3 40,3 -2,657 7,057 -18,748 49,806
4 40,75 -2,207 4,869 -10,744 23,706
5 40,78 -2,174 4,724 -10,269 22,320
6 45,7 2,743 7,526 20,648 56,648
7 45,96 3,001 9,009 27,039 81,156
8 46,68 3,718 13,827 51,414 191,180
9 47,65 4,693 22,028 103,389 485,249
10 53,13 10,177 103,566 1053,965 10725,924
Jumlah 429,5656 0,000 322,348 -80,941 22892,385
ẍ= 42,95656
a) Rata – Rata
1
𝑋̅ = 𝑛 ∑𝑛𝑖=1 𝑋𝑖
1
𝑋̅ = 10
. 429,56
𝑋̅ = 42,956
b) Setandar Deviasi
1 1/2
𝑆 = [𝑛−1 ∑𝑛𝑖−1(𝑋𝑖 − 𝑋̅)2 ]
1 1/2
𝑆 = [10−1 322,348]
𝑆 = 5,98468
c) Koefisien Skewness
𝑛 ∑𝑛
𝑖=1 (𝑋𝑖−𝑋)
3
𝐶𝑠 = (𝑛−1)(𝑛−2)𝑠3
10 𝑥 −80,941
𝐶𝑠 = (10−1)(10−2)(𝟓,𝟗𝟖𝟒𝟔𝟖)3
𝐶𝑠 = -0,0524
d) Koefisien Kurtosis
𝑛2 ∑𝑛
𝑖=1(𝑋𝑖−𝑋)
4
𝐶𝑘 = (𝑛−1)(𝑛−2)(𝑛−3)𝑠4
102 x 22892,385
𝐶𝑘 = (10−1)(10−2)(10−3)(𝟓,𝟗𝟖𝟒𝟔𝟖)4
𝐶𝑘 = 𝟑, 𝟓𝟒𝟎𝟖
e) Koefisien Varians
𝑆
𝐶𝑣 =
𝑥̅
𝟓,𝟗𝟖𝟒𝟔𝟖
𝐶𝑣 =
42,956
𝐶𝑣 = 𝟎, 𝟏𝟑𝟗𝟑
Rumus untuk menghitung hujan rencana dengan probabilitas normal adalah sebagai
berikut :
__
XT = X + KTS
Keterangan rumus :
XT = hujan rencana dengan periode ulang T tahun
X = nilai rata-rata dari data hujan (X) mm.
S = Standar deviasi dari data hujan (X) mm.
KT = faktor frekuensi, nilainya tergantung dari T (lampiran tabel Variabel Reduksi Gauss)
Tabel Variabel Distribusi Gauss
Nilai KT berdasarkan nilai T yang diambil dari lampiran tabel Variabel Reduksi Gauss, nilai T untuk
XT = X + KTS
XT = 42.956 + (0.84 x 5,98468)
5
XT = 47.983 mm
XT = X + KTS
XT = 42.956 + (1.64 x 5,98468)
20
XT = 52.771 mm
XT = X + KTS
XT = 42.956 + (2.05 x 5,98468)
50
XT = 55.224 mm
XT = X + KTS
XT = 42.956 + (2.33 x 5,98468)
100
XT = 56.900 mm
No Xi Max Log Xi Log xi - Log X (Log xi - Log X)² (Log xi - Log X)³
1 34.0 1.5319 -0.0973 0.0095 -0.0009
2 34.58 1.5388 -0.0903 0.0082 -0.0007
3 40.3 1.6053 -0.0238 0.0006 0.0000
4 40.75 1.6101 -0.0190 0.0004 0.0000
5 40.78 1.6104 -0.0187 0.0003 0.0000
6 45.70 1.6599 0.0308 0.0009 0.0000
7 45.96 1.6624 0.0332 0.0011 0.0000
8 46.68 1.6691 0.0400 0.0016 0.0001
9 47.65 1.6781 0.0489 0.0024 0.0001
10 53.13 1.7253 0.0962 0.0093 0.0009
429.5600 16.2914 0.0000 0.0342 -0.0005
X 42.9560 1.6291
f) Rata – Rata
1
Log 𝑋̅ = 𝑛 ∑𝑛𝑖=1 𝐿𝑜𝑔 𝑋𝑖
1
Log 𝑋̅= 10
. 16,2914
Log 𝑋̅ = 1,6291
g) Setandar Deviasi
1 1/2
𝑆 = [𝑛−1 ∑𝑛𝑖−1(𝐿𝑜𝑔𝑋𝑖 − ̅̅̅̅̅̅̅̅
𝐿𝑜𝑔 𝑋)2 ]
1 1/2
𝑆= [ (0,0342) ]
10−1
𝑆 = 0,0616
h) Koefisien Skewness
𝑛 ∑𝑛
𝑖=1 (𝐿𝑜𝑔 𝑋𝑖−Log 𝑋)
3
𝐶𝑠 = (𝑛−1)(𝑛−2)𝑠3
10 (−0,0002)
𝐶𝑠 = (10−1)(10−2)(𝟎,𝟎𝟒𝟎𝟖)3
𝐶𝑠 = -0,3243
i) Koefisien Varians
𝑆
𝐶𝑣 = ̅̅̅̅̅̅̅̅
𝐿𝑜𝑔 𝑥
𝟎,𝟎𝟔𝟏𝟔
𝐶𝑣 = 1,6291
𝐶𝑣 = 0,0378
Rumus untuk menghitung hujan rencana dengan Distribusi Log normal adalah sebagai
berikut :
__
XT = Log X + KTS
Keterangan rumus :
XT = hujan rencana dengan periode ulang T tahun
Log X = nilai rata-rata dari data hujan (X) mm.
S = Standar deviasi dari data hujan (X) mm.
KT = faktor frekuensi, nilainya tergantung dari T (lampiran tabel Variabel Reduksi Gauss)
Tabel Variabel Distribusi Gauss
Nilai KT berdasarkan nilai T yang diambil dari lampiran tabel Variabel Reduksi Gauss, nilai T untuk
XT = Log X + KTS
XT = 1,6291 + (0.84 x 0,0616)
5 XT = 1,6808
X = 47,9513
XT = Log X + KTS
XT = 1,6291 + (1.64 x 0,0616)
20 XT = 1,730
X = 53,7032
XT = Log X + KTS
XT = 1,6291 + (2.05 x 0,0616)
50 XT = 1,7554
X = 56,9377
XT = Log X + KTS
XT = 1,6291 + (2.33 x 0,0616)
100 XT = 1,7726