Anda di halaman 1dari 63

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt mixing plant E01
2. Tenaga Pw 294.0 HP
3. Kapasitas Cp 150.0 T/Jam No.
4. Alat a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 2,730,900,000.00 Rupiah

1
5 Kapastas tangki aspal Ca 30,000.00 liter 1
2
B. BIAYA PASTI PER JAM KERJA 3
1. Nilai Sisa Alat = 10 % x B C 273,090,000.00 Rupiah 4
5
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.16275 - 6
(1 + i)^A - 1 7
3. Biaya Pasti per Jam : 8
a. Biaya Pengembalian Modal = (B-C)xD E 266,664.84 Rupiah 9
W 10
11
b. Asuransi, dll = 0.002 x B F 3,641.20 Rupiah 12
W 13
14
Biaya Pasti per Jam = (E+F) G 270,306.04 Rupiah 15
16
C. BIAYA OPERASI PER JAM KERJA 17
1. Bahan Bakar = (12%-15%) x Pw x Ms H1 330,750.00 Rupiah 18
Bahan Bakar Pemanasan Material = 12 ltr x 0.7 x Cp x Ms H2 9,450,000.00 Rupiah Khusus AMP 19
dan aspal (Oil Heater) 20
Bahan Bakar Pemanas Aspal =1/1000 *Ca*Ms H3 225,000.00 21
22
2. Pelumas = (2.5%-3%) x Pw x Mp I 264,600.00 Rupiah 23
24
3. Biaya bengkel (6.25% dan 8.75%) x B J 159,303 25
W 26
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 318,605.00 Rupiah 27
W 28
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah 29
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 51,426.00 Rupiah 30
31
Biaya Operasi per Jam = (H+I+J+K+L+M) P 10,820,397.50 Rupiah 32
33
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 11,090,703.54 Rupiah 34

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt finisher E02
2. Tenaga Pw 72.4 HP
3. Kapasitas Cp 10.0 Ton
4. Alat a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 1,700,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 170,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 234,199.53 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,266.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 236,466.19 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 81,450.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,160.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 99,167


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 198,333.33 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 481,966.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 718,432.19 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt sprayer E03
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 1,400.0 Liter
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 300,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 30,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 35,612.66 Rupiah
W

b. Asuransi, dll = 0.002 x B F 300.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 35,912.66 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 5,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,500.00 Rupiah


3. Biaya bengkel (6.25% dan 8.75%) x B J 13,125 Rupiah
W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 26,250.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 87,356.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 123,268.66 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Bulldozer E04
2. Tenaga Pw 155.0 HP
3. Kapasitas Cp 40.0 T/Jam
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,570,000,000.00 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 157,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 186,372.92 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,570.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 187,942.92 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 174,375.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 139,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 68,688


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 137,375.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 557,793.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 745,736.42 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Compressor E05
2. Tenaga Pw 65.0 HP
3. Kapasitas Cp 5,000.0 Liter
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 283,275,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 28,327,500.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 33,627.25 Rupiah
W

b. Asuransi, dll = 0.002 x B F 283.28 Rupiah


W

Biaya Pasti per Jam = (E+F) G 33,910.53 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 73,125.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 58,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 12,393


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 24,786.56 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 206,660.84 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 240,571.37 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Crane E06
2. Tenaga Pw 136.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 1,622,900,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 162,290,000.00 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.57619 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 561,059.71 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,163.87 Rupiah


W

Biaya Pasti per Jam = (E+F) G 563,223.58 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 153,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 122,400.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 94,669


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 189,338.33 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 597,263.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,160,487.08 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Motor Grader E07
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 10.8 T/Jam
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,631,250,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 163,125,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 193,643.84 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,631.25 Rupiah


W

Biaya Pasti per Jam = (E+F) G 195,275.09 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 140,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 112,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 71,367


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 142,734.38 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 505,082.56 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 700,357.65 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Excavator E08
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 2.0 M3
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 6,768,160,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 676,816,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 803,440.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 6,768.16 Rupiah


W

Biaya Pasti per Jam = (E+F) G 810,208.76 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 149,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 119,700.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 296,107


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 592,214.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,195,502.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 2,005,710.76 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.


A. URAIAN PERALATAN
1. Jenis Peralatan Wheel loader E09
2. Tenaga Pw 96.0 HP
3. Kapasitas Cp 9.31 M3
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,043,600,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 104,360,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 123,884.57 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,043.60 Rupiah


W

Biaya Pasti per Jam = (E+F) G 124,928.17 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 108,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 86,400.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 45,658


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 91,315.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 369,228.50 Rupiah


D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 494,156.67 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Jack Hammer E10
2. Tenaga Pw 3.0 HP
3. Kapasitas Cp 1,330.0 -
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 34,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 3,400,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 4,036.10 Rupiah
W

b. Asuransi, dll = 0.002 x B F 34.00 Rupiah


W
Biaya Pasti per Jam = (E+F) G 4,070.10 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 3,375.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 2,700.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 1,488


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 2,975.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 48,393.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 52,463.60 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Three whells roller E11
2. Tenaga Pw 55.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 372,985,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 37,298,500.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 44,276.63 Rupiah
W

b. Asuransi, dll = 0.002 x B F 372.99 Rupiah


W

Biaya Pasti per Jam = (E+F) G 44,649.61 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 61,875.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 49,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 16,318


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 32,636.19 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 198,185.28 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 242,834.89 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Vibrator roller E12
2. Tenaga Pw 82.0 HP
3. Kapasitas Cp 7.1 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 740,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 74,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 87,844.56 Rupiah
W

b. Asuransi, dll = 0.002 x B F 740.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 88,584.56 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 92,250.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 73,800.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 32,375


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 64,750.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 301,031.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 389,615.56 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Tire Roller E13
2. Tenaga Pw 100.5 HP
3. Kapasitas Cp 9.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 953,360,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 95,336,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 113,172.28 Rupiah
W

b. Asuransi, dll = 0.002 x B F 953.36 Rupiah


W

Biaya Pasti per Jam = (E+F) G 114,125.64 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 113,062.50 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 90,450.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 41,710


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 83,419.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 366,497.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 480,622.64 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Generator E14
2. Tenaga Pw 180.0 HP
3. Kapasitas Cp 130.0 KVA
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,230,654,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 123,065,400.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 146,089.54 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,230.65 Rupiah


W

Biaya Pasti per Jam = (E+F) G 147,320.20 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 202,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 162,000.00 Rupiah


3. Biaya bengkel (6.25% dan 8.75%) x B J 53,841
W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 107,682.23 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 563,879.34 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 711,199.53 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Drump truck 10 Ton E15
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 674,681,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 67,468,100.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 80,090.62 Rupiah
W

b. Asuransi, dll = 0.002 x B F 674.68 Rupiah


W

Biaya Pasti per Jam = (E+F) G 80,765.30 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 213,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 171,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 29,517


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 59,034.59 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 511,157.88 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 591,923.18 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Dump truck 3.5 Ton E16
2. Tenaga Pw 62.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 111,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,100,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 13,176.68 Rupiah
W

b. Asuransi, dll = 0.002 x B F 111.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 13,287.68 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 69,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 55,800.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 4,856


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 9,712.50 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 177,974.75 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 191,262.43 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Truck trailer E17
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 20.0 T/Jam
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 300,500,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 30,050,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 35,672.01 Rupiah
W

b. Asuransi, dll = 0.002 x B F 300.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 35,972.51 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 196,875.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 157,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 13,147


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 26,293.75 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 431,671.63 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 467,644.14 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Concrete mixer E18
2. Tenaga Pw 20.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 201,600,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 20,160,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 23,931.71 Rupiah
W

b. Asuransi, dll = 0.002 x B F 201.60 Rupiah


W

Biaya Pasti per Jam = (E+F) G 24,133.31 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 22,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 18,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 8,820


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 17,640.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah
Biaya Operasi per Jam = (H+I+J+K+L+M) P 104,816.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 128,949.31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Stone crusher E19
2. Tenaga Pw 120.0 HP
3. Kapasitas Cp 3.0 T/Jam
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 566,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 56,600,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 67,189.22 Rupiah
W
b. Asuransi, dll = 0.002 x B F 566.00 Rupiah
W

Biaya Pasti per Jam = (E+F) G 67,755.22 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 135,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 108,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 24,763


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 49,525.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 355,143.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 422,898.72 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.


A. URAIAN PERALATAN
1. Jenis Peralatan Water Tank E20
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 13,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1,300,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 3,691.01 Rupiah
W

b. Asuransi, dll = 0.002 x B F 26.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 3,717.01 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 112,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 90,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 1,138


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 2,275.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 243,768.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 247,485.51 Rupiah


E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Water pump E21
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp 4.5 M3
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 3,985,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 398,500.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 473.05 Rupiah
W

b. Asuransi, dll = 0.002 x B F 3.99 Rupiah


W
Biaya Pasti per Jam = (E+F) G 477.04 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 6,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 5,400.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 174


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 348.69 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 50,529.03 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 51,006.07 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Pipe boring machine E22
2. Tenaga Pw 153.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 3,340,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 334,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 604,378.55 Rupiah
W

b. Asuransi, dll = 0.002 x B F 3,340.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 607,718.55 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 172,125.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 137,700.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 146,125


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 292,250.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 786,056.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,393,774.55 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Flatbed Truck E23
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 T/Jam
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,240,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 124,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 147,198.99 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,240.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 148,438.99 Rupiah


C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12%-15%) x Pw x Ms H 213,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 171,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 54,250


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 108,500.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 585,356.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 733,794.99 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt liquid mixer E24
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 1,000.0 Liter
4. Alat a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 115,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,500,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 20,809.44 Rupiah
W

b. Asuransi, dll = 0.002 x B F 115.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 20,924.44 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 5,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 5,031


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 10,062.50 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 63,074.75 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 83,999.19 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Welding Set Machine E25
2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 250.0 Amp
4. Alat a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 1,200,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 120,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 340.71 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2.40 Rupiah


W

Biaya Pasti per Jam = (E+F) G 343.11 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 45,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 36,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 105


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 210.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 119,171.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 119,514.11 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Backhoe loader E26
2. Tenaga Pw 52.9 HP
3. Kapasitas Cp 11.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 5,460,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 546,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 648,150.41 Rupiah
W

b. Asuransi, dll = 0.002 x B F 5,460.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 653,610.41 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 59,512.50 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 47,610.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 238,875


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 477,750.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 861,603.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,515,213.91 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Tandem roller E27
2. Tenaga Pw 96.5 HP
3. Kapasitas Cp 9.6 Ton
4. Alat a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 4,369,780,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 436,978,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,240,684.21 Rupiah
W

b. Asuransi, dll = 0.002 x B F 8,739.56 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,249,423.77 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 108,562.50 Rupiah
2. Pelumas = (2.5%-3%) x Pw x Mp I 86,850.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 382,356


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 764,711.50 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,380,335.75 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 2,629,759.52 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Hydraulic Excavator E28
2. Tenaga Pw 93.0 HP
3. Kapasitas Cp 20.8 Ton
4. Alat a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,689,950,000.00 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 168,995,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 174,611.25 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,689.95 Rupiah


W

Biaya Pasti per Jam = (E+F) G 176,301.20 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 104,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 83,700.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 73,935


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 147,870.63 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 447,986.94 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 624,288.13 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt finisher E29
2. Tenaga Pw 72.4 HP
3. Kapasitas Cp 10.0 Ton
4. Alat a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 4,040,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 404,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 417,426.22 Rupiah
W

b. Asuransi, dll = 0.002 x B F 4,040.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 421,466.22 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 81,450.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,160.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 176,750


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 353,500.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 714,716.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,136,182.22 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Tracked Excavator E30
2. Tenaga Pw 55.0 HP
3. Kapasitas Cp 17.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,504,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 150,400,000.00 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 178,538.14 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,504.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 180,042.14 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 61,875.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 49,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 65,800


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 131,600.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 346,631.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 526,673.14 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Landfill Compactor E31
2. Tenaga Pw 435.0 HP
3. Kapasitas Cp 40.0 Ton
4. Alat a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 4,935,784,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 493,578,400.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 509,981.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 4,935.78 Rupiah


W

Biaya Pasti per Jam = (E+F) G 514,917.38 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 489,375.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 391,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 215,941


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 431,881.10 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,566,552.65 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 2,081,470.03 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Weed boat E32
2. Tenaga Pw 16.0 HP
3. Kapasitas Cp 40.0 Ton
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 9,500,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 950,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,503,645.64 Rupiah
W

b. Asuransi, dll = 0.002 x B F 12,666.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,516,312.31 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 18,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 14,400.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 554,167


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 1,108,333.33 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,732,756.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 3,249,068.31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt Cutter E33
2. Tenaga Pw 13.0 HP
3. Kapasitas Cp 120.0 mm
4. Alat a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 43,782,633.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 4,378,263.30 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 4,523.77 Rupiah
W

b. Asuransi, dll = 0.002 x B F 43.78 Rupiah


W

Biaya Pasti per Jam = (E+F) G 4,567.55 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 14,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 11,700.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 1,915


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 3,830.98 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah
Biaya Operasi per Jam = (H+I+J+K+L+M) P 69,927.47 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 74,495.02 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Slipform paver E34
2. Tenaga Pw 105.0 HP
3. Kapasitas Cp 2.55 M
4. Alat a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 6,000,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 600,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 851,771.17 Rupiah
W
b. Asuransi, dll = 0.002 x B F 6,000.00 Rupiah
W

Biaya Pasti per Jam = (E+F) G 857,771.17 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 118,125.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 94,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 262,500


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 525,000.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 20,714.00 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,142.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,037,981.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,895,752.17 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 20,714.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,142.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Rp./liter
5. Bahan Bakar Solar Ms 7,500.00 Rp./liter
6. Minyak Pelumas Mp 30,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
ANALISA BIAYA SEWA PERALATAN PE

TENAGA KAPASITAS HARGA ALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM
ALAT ALAT ALAT JAM SISA PENGEM- BIAYA ASURANSI

UMUR KERJA HARGA ALAT BALIAN PENGEM- DAN


ALAT 1 TAHUN ALAT MODAL BALIAN LAIN-LAIN
MODAL
(HP) - (Tahun) (Tahun) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.)
JENIS PERALATAN KODE
ALAT i(1+i)^A (B - C) x D 0.002 x B
(10% X B) ----------- ----------- -----------
(1+i)^A-1 W W

HP Cp B A W B C D e1 e2
2 2a 3 4 5 6 7 8 9 10 11 12
Asphalt mixing plant E01 294.0 150.0 T/Jam 2,730,900,000.00 10.0 1,500.0 2,730,900,000.00 273,090,000.00 0.16275 266,664.84 3,641.20
Asphalt finisher E02 72.4 10.0 Ton 1,700,000,000.00 6.0 1,500.0 1,700,000,000.00 170,000,000.00 0.22961 234,199.53 2,266.67
Asphalt sprayer E03 5.0 1,400.0 Liter 300,000,000.00 5.0 2,000.0 300,000,000.00 30,000,000 0.26380 35,612.66 300.00
Bulldozer E04 155.0 40.0 T/Jam 1,570,000,000.00 5.0 2,000.0 1,570,000,000.00 157,000,000 0.26380 186,372.92 1,570.00
Compressor E05 65.0 5,000.0 Liter 283,275,000.00 5.0 2,000.0 283,275,000.00 28,327,500 0.26380 33,627.25 283.28
Crane E06 136.0 15.0 Ton 1,622,900,000.00 2.0 1,500.0 1,622,900,000.00 162,290,000 0.57619 561,059.71 2,163.87
Motor Grader E07 125.0 10.8 T/Jam 1,631,250,000.00 5.0 2,000.0 1,631,250,000.00 163,125,000 0.26380 193,643.84 1,631.25
Excavator E08 133.0 2.0 M3 6,768,160,000.00 5.0 2,000.0 6,768,160,000.00 676,816,000 0.26380 803,440.60 6,768.16
Wheel loader E09 96.0 9.31 M3 1,043,600,000.00 5.0 2,000.0 1,043,600,000.00 104,360,000 0.26380 123,884.57 1,043.60
Jack Hammer E10 3.0 1,330.0 - 34,000,000.00 5.0 2,000.0 34,000,000.00 3,400,000 0.26380 4,036.10 34.00
Three whells roller E11 55.0 8.0 Ton 372,985,000.00 5.0 2,000.0 372,985,000.00 37,298,500 0.26380 44,276.63 372.99
Vibrator roller E12 82.0 7.1 Ton 740,000,000.00 5.0 2,000.0 740,000,000.00 74,000,000 0.26380 87,844.56 740.00
Tire Roller E13 100.5 9.0 Ton 953,360,000.00 5.0 2,000.0 953,360,000.00 95,336,000 0.26380 113,172.28 953.36
Generator E14 180.0 130.0 KVA 1,230,654,000.00 5.0 2,000.0 1,230,654,000.00 123,065,400 0.26380 146,089.54 1,230.65
Drump truck 10 Ton E15 190.0 15.0 Ton 674,681,000.00 5.0 2,000.0 674,681,000.00 67,468,100 0.26380 80,090.62 674.68
Dump truck 3.5 Ton E16 62.0 8.0 Ton 111,000,000.00 5.0 2,000.0 111,000,000.00 11,100,000 0.26380 13,176.68 111.00
Truck trailer E17 175.0 20.0 T/Jam 300,500,000.00 5.0 2,000.0 300,500,000.00 30,050,000 0.26380 35,672.01 300.50
Concrete mixer E18 20.0 500.0 Liter 201,600,000.00 5.0 2,000.0 201,600,000.00 20,160,000 0.26380 23,931.71 201.60
Stone crusher E19 120.0 3.0 T/Jam 566,000,000.00 5.0 2,000.0 566,000,000.00 56,600,000 0.26380 67,189.22 566.00
Water Tank E20 100.0 4,000.0 Liter 13,000,000.00 4.0 1,000.0 13,000,000.00 1,300,000 0.31547 3,691.01 26.00
Water pump E21 6.0 4.5 M3 3,985,000.00 5.0 2,000.0 3,985,000.00 398,500 0.26380 473.05 3.99
Pipe boring machine E22 153.0 10.0 Ton 3,340,000,000.00 3.0 2,000.0 3,340,000,000.00 334,000,000 0.40211 604,378.55 3,340.00
Flatbed Truck E23 190.0 10.0 T/Jam 1,240,000,000.00 5.0 2,000.0 1,240,000,000.00 124,000,000 0.26380 147,198.99 1,240.00
Asphalt liquid mixer E24 5.0 1,000.0 Liter 115,000,000.00 3.0 2,000.0 115,000,000.00 11,500,000 0.40211 20,809.44 115.00
Welding Set Machine E25 40.0 250.0 Amp 1,200,000.00 4.0 1,000.0 1,200,000.00 120,000 0.31547 340.71 2.40
Backhoe loader E26 52.9 11.0 Ton 5,460,000,000.00 5.0 2,000.0 5,460,000,000.00 546,000,000 0.26380 648,150.41 5,460.00
Tandem roller E27 96.5 9.6 Ton 4,369,780,000.00 4.0 1,000.0 4,369,780,000.00 436,978,000 0.31547 1,240,684.21 8,739.56
Hydraulic Excavator E28 93.0 20.8 Ton 1,689,950,000.00 6.0 2,000.0 1,689,950,000.00 168,995,000 0.22961 174,611.25 1,689.95
Asphalt finisher E29 72.4 10.0 Ton 4,040,000,000.00 6.0 2,000.0 4,040,000,000.00 404,000,000 0.22961 417,426.22 4,040.00
Tracked Excavator E30 55.0 17.0 Ton 1,504,000,000.00 5.0 2,000.0 1,504,000,000.00 150,400,000 0.26380 178,538.14 1,504.00
Landfill Compactor E31 435.0 40.0 Ton 4,935,784,000.00 6.0 2,000.0 4,935,784,000.00 493,578,400 0.22961 509,981.60 4,935.78
Weed boat E32 16.0 40.0 Ton 9,500,000,000.00 5.0 1,500.0 9,500,000,000.00 950,000,000 0.26380 1,503,645.64 12,666.67
Asphalt Cutter E33 13.0 120.0 mm 43,782,633.00 6.0 2,000.0 43,782,633.00 4,378,263 0.22961 4,523.77 43.78
Slipform paver E34 105.0 2.55 M 6,000,000,000.00 4.0 2,000.0 6,000,000,000.00 600,000,000 0.31547 851,771.17 6,000.00

KETERANGAN : 1 Tingkat Suku Bunga = 10.00 % per-tahun


2 Upah Operator / Sopir / Mekanik = 20,714 Rupiah per-orang/jam
3 Upah Pembantu Operator/Sopir/Mekanik = 17,142 Rupiah per-orang/jam
4 Harga Bahan Bakar Bensin = 6,500 Rupiah per-liter
5 Harga Bahan Bakar Solar = 7,500 Rupiah per-liter
6 Minyak Pelumas = 30,000 Rupiah per-liter
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harg
ATAN PER JAM KERJA (I)

PER JAM BIAYA OPERASI PER JAM KERJA TOTAL


TOTAL BAHAN BAKAR & PELUMAS WORKSHOP PERBAIKAN dan PERAWATAN UPAH TOTAL BIAYA

BIAYA BAHAN MINYAK OPERATOR PEMBANTU BIAYA SEWA ALAT


PASTI / JAM BAKARPELUMAS BIAYA KOEF. BIAYA KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
/ SOPIR / JAM JAM KERJA
(Rp.) % % (Rp.) - (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
f1 x HP x 1 Orang 1 Orang
12 2.5 Harga BBM 6.25 (g1 x B') 12.5 (g2 x B') Per Per
(e1 + e2) s/d s/d + s/d ----- s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J
15 3 f2 x HP x 8.75 W 17.5 W = =
Harga Olie Rp20,714.0 Rp17,142.0
E f1 f2 F g1 G g2 G H I J K L
13 14 15 16 17 18 17 18 19 20 21 22 23
270,306.04 15.00 3.00 595,350.00 8.75 159,303 17.50 318,605.00 20,714.00 51,426.00 10,820,397.50 11,090,703.54 Pek. Ringan
236,466.19 15.00 3.00 146,610.00 8.75 99,167 17.50 198,333.33 20,714.00 17,142.00 481,966.00 718,432.19 Pek. Ringan
35,912.66 15.00 3.00 10,125.00 8.75 13,125.00 17.50 26,250.00 20,714.00 17,142.00 87,356.00 123,268.66 Pek. Berat
187,942.92 15.00 3.00 313,875.00 8.75 68,687.50 17.50 137,375.00 20,714.00 17,142.00 557,793.50 745,736.42 Pek. Berat
33,910.53 15.00 3.00 131,625.00 8.75 12,393.28 17.50 24,786.56 20,714.00 17,142.00 206,660.84 240,571.37 Pek. Berat
563,223.58 15.00 3.00 275,400.00 8.75 94,669.17 17.50 189,338.33 20,714.00 17,142.00 597,263.50 1,160,487.08 Pek. Ringan
195,275.09 15.00 3.00 253,125.00 8.75 71,367.19 17.50 142,734.38 20,714.00 17,142.00 505,082.56 700,357.65 Pek. Berat
810,208.76 15.00 3.00 269,325.00 8.75 296,107.00 17.50 592,214.00 20,714.00 17,142.00 1,195,502.00 2,005,710.76 Pek. Berat
124,928.17 15.00 3.00 194,400.00 8.75 45,657.50 17.50 91,315.00 20,714.00 17,142.00 369,228.50 494,156.67 Pek. Berat
4,070.10 15.00 3.00 6,075.00 8.75 1,487.50 17.50 2,975.00 20,714.00 17,142.00 48,393.50 52,463.60 Pek. Berat
44,649.61 15.00 3.00 111,375.00 8.75 16,318.09 17.50 32,636.19 20,714.00 17,142.00 198,185.28 242,834.89 Pek. Berat
88,584.56 15.00 3.00 166,050.00 8.75 32,375.00 17.50 64,750.00 20,714.00 17,142.00 301,031.00 389,615.56 Pek. Berat
114,125.64 15.00 3.00 203,512.50 8.75 41,709.50 17.50 83,419.00 20,714.00 17,142.00 366,497.00 480,622.64 Pek. Berat
147,320.20 15.00 3.00 364,500.00 8.75 53,841.11 17.50 107,682.23 20,714.00 17,142.00 563,879.34 711,199.53 Pek. Berat
80,765.30 15.00 3.00 384,750.00 8.75 29,517.29 17.50 59,034.59 20,714.00 17,142.00 511,157.88 591,923.18 Pek. Berat
13,287.68 15.00 3.00 125,550.00 8.75 4,856.25 17.50 9,712.50 20,714.00 17,142.00 177,974.75 191,262.43 Pek. Berat
35,972.51 15.00 3.00 354,375.00 8.75 13,146.88 17.50 26,293.75 20,714.00 17,142.00 431,671.63 467,644.14 Pek. Berat
24,133.31 15.00 3.00 40,500.00 8.75 8,820.00 17.50 17,640.00 20,714.00 17,142.00 104,816.00 128,949.31 Pek. Berat
67,755.22 15.00 3.00 243,000.00 8.75 24,762.50 17.50 49,525.00 20,714.00 17,142.00 355,143.50 422,898.72 Pek. Berat
3,717.01 15.00 3.00 202,500.00 8.75 1,137.50 17.50 2,275.00 20,714.00 17,142.00 243,768.50 247,485.51 Pek. Ringan
477.04 15.00 3.00 12,150.00 8.75 174.34 17.50 348.69 20,714.00 17,142.00 50,529.03 51,006.07 Pek. Berat
607,718.55 15.00 3.00 309,825.00 8.75 146,125.00 17.50 292,250.00 20,714.00 17,142.00 786,056.00 1,393,774.55 Pek. Berat
148,438.99 15.00 3.00 384,750.00 8.75 54,250.00 17.50 108,500.00 20,714.00 17,142.00 585,356.00 733,794.99 Pek. Berat
20,924.44 15.00 3.00 10,125.00 8.75 5,031.25 17.50 10,062.50 20,714.00 17,142.00 63,074.75 83,999.19 Pek. Berat
343.11 15.00 3.00 81,000.00 8.75 105.00 17.50 210.00 20,714.00 17,142.00 119,171.00 119,514.11 Pek. Ringan
653,610.41 15.00 3.00 107,122.50 8.75 238,875.00 17.50 477,750.00 20,714.00 17,142.00 861,603.50 1,515,213.91 Pek. Berat
1,249,423.77 15.00 3.00 195,412.50 8.75 382,355.75 17.50 764,711.50 20,714.00 17,142.00 1,380,335.75 2,629,759.52 Pek. Ringan
176,301.20 15.00 3.00 188,325.00 8.75 73,935.31 17.50 147,870.63 20,714.00 17,142.00 447,986.94 624,288.13 Pek. Berat
421,466.22 15.00 3.00 146,610.00 8.75 176,750.00 17.50 353,500.00 20,714.00 17,142.00 714,716.00 1,136,182.22 Pek. Berat
180,042.14 15.00 3.00 111,375.00 8.75 65,800.00 17.50 131,600.00 20,714.00 17,142.00 346,631.00 526,673.14 Pek. Berat
514,917.38 15.00 3.00 880,875.00 8.75 215,940.55 17.50 431,881.10 20,714.00 17,142.00 1,566,552.65 2,081,470.03 Pek. Berat
1,516,312.31 15.00 3.00 32,400.00 8.75 554,166.67 17.50 1,108,333.33 20,714.00 17,142.00 1,732,756.00 3,249,068.31 Pek. Ringan
4,567.55 15.00 3.00 26,325.00 8.75 1,915.49 17.50 3,830.98 20,714.00 17,142.00 69,927.47 74,495.02 Pek. Berat
857,771.17 15.00 3.00 212,625.00 8.75 262,500.00 17.50 525,000.00 20,714.00 17,142.00 1,037,981.00 1,895,752.17 Pek. Berat

am) x Harga BBM Solar , (kolom 16)


DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

No. URAIAN KO
DE

1 11,090,703.54 E01
2 718,432.19 E02
3 123,268.66 E03
4 745,736.42 E04
5 240,571.37 E05
6 1,160,487.08 E06
7 700,357.65 E07
8 2,005,710.76 E08
9 494,156.67 E09
10 52,463.60 E10
11 242,834.89 E11
12 389,615.56 E12
13 480,622.64 E13
14 711,199.53 E14
15 591,923.18 E15
16 191,262.43 E16
17 467,644.14 E17
18 128,949.31 E18
19 422,898.72 E19
20 247,485.51 E20
21 51,006.07 E21
22 1,393,774.55 E22
23 733,794.99 E23
24 83,999.19 E24
25 119,514.11 E25
26 1,515,213.91 E26
27 2,629,759.52 E27
28 624,288.13 E28
29 1,136,182.22 E29
30 526,673.14 E30
31 2,081,470.03 E31
32 3,249,068.31 E32
33 74,495.02 E33
34 1,895,752.17 E34
URAIAN ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan galian untuk saluran


SATUAN PEMBAYARAN : M3

No. URAIAN KODE KOEFISIEN


I. ASUMSI
1. Menggunakan alat berat
2. Lokasi pekerjaan : sepanjang jalan
3. Kondisi jalan : ringan / baik sekali
4. Jam kerja efektif per hari Tk 7
5. Faktor pengembangan bahan Fk 1.2

II. URUTAN KERJA


1. Penggalian dilakukan dengan menggunakan excavator
Selanjutnya excavator menuangkan material hasil galian
2. ke dalam dump truck

Dump truck membuang material hasil galian keluar lokasi


3. jalan sejauh L 1
4. Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT, DAN TENAGA


1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
a. EXCAVATOR
Kapasitas bucket KB 0.5
Faktor bucket f 0.9
Faktor efisiensi alat fe 0.83

Waktu siklus
Menggali Wg 0.25
Memuat Wp1 0.25
Putar Wp2 0.25
buang Wb 0.25
CT1 1

KP1 18.68

Koefisien alat/M3 = 1 : KP1 0.0535

B. DUMP TRUCK
Kapasitas muat C 4
Faktor efisiensi alat Fe 0.83
Kecepatan angkut V1 40
Kecepatan balik V2 60

Waktu siklus
Waktu tempuh isi = ( L : V1 ) x 60 t1 1.50
Waktu tempuh kosong = ( L : V2 ) x 60 t2 1
Waktu muat : ( C : KP1 ) x 60 t3 12.85
Lain-lain t4 3.5
CT2 18.85

KP2 8.81

Koefisien alat = 1 : KP2 0.1135

C. ALAT BANTU 1
Diperlukan alat-alat bantu kecil
Sekop
Keranjang + Sapu

3. TENAGA
Produksi menentukan :
Excavator KP1 18.68
Produksi galian per hari = Tk x KP1 KPt 130.76

Kebutuhan tenaga :
Pekerja P 2
Mandor M 1

Koefisien tenaga/M3
Pekerja = ( Tk x P ) : KPt 0.1071
Mandor = ( Tk x M ) : KPt 0.0535

4. HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


Lihat perhitungan

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam PEREKAMAN
ANALISA MASING-MASING HARGA SATUAN
Di dapat harga satuan pekerjaan
Rp. /M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa pelaksanaan : bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : M3
n untuk saluran

SATUAN KETERANGAN

Jam

Km

M3

menit
menit
menit
menit
menit

M3/Jam

Jam
M3

Km/Jam
Km/Jam

menit
menit
menit
menit
menit

M3/Jam

Jam

LS Lump Sum

M3/Jam
M3

orang
orang

Jam
Jam
ANALISA

JENIS PEKERJAAN : Pekerjaan galian untuk saluran


SATUAN PEMBAYARAN : M3

HARGA JUMLAH
PERKIRAAN
NO. KOMPONEN SATUAN SATUAN HARGA
KUANTITAS (Rp.) (Rp.)
A. TENAGA
1. Pekerja Jam 0.1071 5,714.29 611.81
2. Mandor Jam 0.0535 10,000.00 535.33
JUMLAH HARGA TENAGA 1,147.14
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
1. Excavator jam 0.0535 204,415.93 10,943.04
2. Dump Truck jam 0.1135 123,080.43 13,970.54
3. Alat Bantu LS 1 500