0.7
0.6
0.5 Elevasi Top Saluran
0.4 Elevasi Tinggi Permukaan Air
0.3
0.2
0.1 Elevasi Permukaan Sawah
0 Elevasi Saluran eksisting
-0.1 Elevasi Dasar Saluran
-0.2
Luas Rata-Rata
Jarak Luas Penampang Volume
No Titik /Patok Penampang
(m) (m2) (m2) (m3)
1 P0 0.27
25.00 0.27 6.66
2 P1 0.27
25.00 0.28 7.11
3 P2 0.30
25.00 0.31 7.76
4 P3 0.32
25.00 0.31 7.76
5 P4 0.30
25.00 0.28 7.11
6 P5 0.27
25.00 0.29 7.31
7 P6 0.32
25.00 0.34 8.51
8 P7 0.36
25.00 0.39 9.81
9 P8 0.42
25.00 0.39 9.81
10 P9 0.36
25.00 0.35 8.71
11 P10 0.33
25.00 0.33 8.36
12 P11 0.33
25.00 0.35 8.71
13 P12 0.36 -
21.20 0.36 7.68
14 P13 0.36
60 40
21 40 21
82
Luas Total = 0.37 m2
78
60 40
P12 Luas 2 = (( 0.82 + 0.78 ) 2.00 ) x 0.15
15 = 0.12 m 2
21 40 21
82 Luas Total = 0.37 m2
78
21.20 0.37 7.76
60 40
P13 Luas 2 = (( 0.82 + 0.78 ) 2.00 ) x 0.15
= 0.12 m2
15
21 40 21 Luas Total = 0.37 m2
82
0.37
78
Luas Rata-
Luas
Jarak Rata Volume
No Titik /Patok Penampang
Penampang
(m) (m2) (m2) (m3)
1 P0 0.37
25.00 0.37 9.15
2 P1 0.37
25.00 0.37 9.15
3 P2 0.37
25.00 0.37 9.15
4 P3 0.37
25.00 0.37 9.15
5 P4 0.37
25.00 0.37 9.15
6 P5 0.37
25.00 0.37 9.15
7 P6 0.37
25.00 0.37 9.15
8 P7 0.37
25.00 0.37 9.15
9 P8 0.37
25.00 0.37 9.15
10 P9 0.37
25.00 0.37 9.15
11 P10 0.37
25.00 0.37 9.15
12 P11 0.37
25.00 0.37 9.15
13 P12 0.37 - -
21.20 0.37 7.76
14 P13 0.37 -
40
61
P4
Plesteran 1:4
40
P5
Plesteran 1:4
40
P6
Plesteran 1:4
40
20 Acian
61
P6
Plesteran 1:4
40
Lebar Rata-
Lebar
Titik Jarak Rata Volume
No Penampang
/Patok Penampang
(m) (m) (m) (m2)
1 P0 2.02
25.00 2.02 50.50
2 P1 2.02
25.00 2.02 50.50
3 P2 2.02
25.00 2.02 50.50
4 P3 2.02
25.00 2.02 50.50
5 P4 2.02
25.00 2.02 50.50
6 P5 2.02
25.00 2.02 50.50
7 P6 2.02
25.00 2.02 50.50
8 P7 2.02
25.00 2.02 50.50
9 P8 2.02
25.00 2.02 50.50
10 P9 2.02
25.00 2.02 50.50
11 P10 2.02
25.00 2.02 50.50
12 P11 2.02
25.00 2.02 50.50
13 P12 2.02
21.20 2.02 42.82
14 P13 2.02
Rahmad B. Sukamto
PERHITUNGAN VOLUME PEKERJAAN
Pekerjaan Plesteran
Plesteran 1 : 4
Panjang = (( 0.22 + 0.65 ) x 2) + 0.44
22 = 2.18 m
Plesteran 1:4
1,5 cm
44
Pekerjaan Acian
Acian 1 : 4
22
Panjang = (( 0.22 + 0.65 ) x 2) + 0.44
Acian = 2.18 m
65
44
REKAPITULASI PERHITUNGAN VOLUME PEKERJAAN
P3A : Sakinah Jaya
Nama Pekerjaan : Peningkatan Jaringan Irigasi Tersier DI Lomaya
Desa/Kabupaten : Bongopini / BoneBolango
Provinsi : Gorontalo
Tahun : 2017
Volume Pekerjaan
Galian Tanah Pasangan Batu Kali Plesteran dan Acian
Titik / Jarak
No Luas Rata-
Patok (m) Luas Luas Rata-Rata Luas
Rata Lebar Lebar Rata-
Penampang Penampang Volume (m3) Penampang Volume (m3) Luasan (m2)
Penampang /meter (m) Rata (m)
(m2) (m )
2
(m )
2
(m2)
1 P0 0.27 0.37 2.02
25.00 0.27 6.66 0.37 9.15 2.02 50.50
2 P1 0.27 0.37 2.02
25.00 0.28 7.11 0.37 9.15 2.02 50.50
3 P2 0.30 0.37 2.02
25.00 0.31 7.76 0.37 9.15 2.02 50.50
4 P3 0.32 0.37 2.02
25.00 0.31 7.76 0.37 9.15 2.02 50.50
5 P4 0.30 0.37 2.02
25.00 0.28 7.11 0.37 9.15 2.02 50.50
6 P5 0.27 0.37 2.02
25.00 0.29 7.31 0.37 9.15 2.02 50.50
7 P6 0.32 0.37 2.02
25.00 0.34 8.51 0.37 9.15 2.02 50.50
8 P7 0.36 0.37 2.02
25.00 0.39 9.81 0.37 9.15 2.02 50.50
9 P8 0.42 0.37 2.02
25.00 0.39 9.81 0.37 9.15 2.02 50.50
10 P9 0.36 0.37 2.02
25.00 0.35 8.71 0.37 9.15 2.02 50.50
11 P10 0.33 0.37 2.02
25.00 0.33 8.36 0.37 9.15 2.02 50.50
12 P11 0.33 0.37 2.02
25.00 0.35 8.71 0.37 9.15 2.02 50.50
13 P12 0.36 0.37 2.02
21.20 0.36 7.68 0.37 7.76 2.02 42.82
14 P13 0.36 0.37 2.02
1.01
Diusulkan Oleh :
Ketua P3A Guyub Makaryo
Rahmad B. Sukamto
RENCANA ANGGARAN BIAYA (RAB)
JUMLAH 178,007,800.98
100.00
JUMLAH DIBULATKAN 178,000,000.00
TERBILANG : SERATUS TUJUH PULUH DELAPAN JUTA RUPIAH
Bongopini, 2017
Dibantu Oleh : Dibuat Oleh :
Tenaga Pendamping Masyarakat Tim Perencana
A UPAH
1 Pekerja OH 0.5630 85,000.00 47,855.00
B BAHAN - - -
C PERALATAN
Diusulkan Oleh :
Ketua P3A Guyub Makaryo
Rahmad B. Sukamto
ANALISA HARGA SATUAN
A UPAH
1 Pekerja OH 2.700 85,000.00 229,500.00
2 Tukang OH 0.900 125,000.00 112,500.00
B BAHAN
1 Batu Belah m3 1.200 195,000.00 234,000.00
2 Pasir pasang m 3
0.544 165,000.00 89,760.00
3 Portland Cement (PC) Kg 135.000 1,240.00 167,400.00
C PERALATAN
1 Molen - - -
Diusulkan Oleh :
Ketua P3A Guyub Makaryo
Rahmad B. Sukamto
ANALISA HARGA SATUAN
A UPAH
1 Pekerja OH 0.384 85,000.00 32,640.00
2 Tukang OH 0.192 125,000.00 24,000.00
B BAHAN
1 Pasir pasang m3 0.024 165,000.00 3,960.00
2 Portland Cement (PC) Kg 6.280 1,240.00 7,787.20
C PERALATAN - - -
Diusulkan Oleh :
Ketua P3A Guyub Makaryo
Rahmad B. Sukamto
ANALISA HARGA SATUAN
A UPAH
1 Pekerja OH 0.200 85,000.00 17,000.00
2 Tukang OH 0.100 125,000.00 12,500.00
B BAHAN
2 Portland Cement (PC) Kg 3.250 1,240.00 4,030.00
C PERALATAN - - -
Diusulkan Oleh :
Ketua P3A Guyub Makaryo
Rahmad B. Sukamto
Rekap Galian Tanah Pondasi
Volume Jumlah
No. Uraian Sat Koef Harga Satuan Jumlah Tenaga Kerja & Bahan
Rab
(Vol Rab x Koef)
105.24
A UPAH
1 Pekerja OH 0.5630 85,000 47,855 59.25
B BAHAN - - -
Volume Jumlah
No. Uraian Sat Koef Harga Satuan Jumlah Tenaga Kerja & Bahan
Rab
(Vol Rab x Koef)
117.5592
A UPAH
1 Pekerja OH 2.7000 85,000 ### 317.41
2 Tukang OH 0.9000 125,000 ### 105.80
B
BAHAN
1 Batu Belah m3 1.20 195,000 ### 141.07
2 Pasir pasang m3 0.54 165,000 89,760.00 63.95
3 Portland Cement (PC) Zak 2.70 62,000 ### 317.4098
Rekap Plesteran
Volume Jumlah
No. Uraian Sat Koef Harga Satuan Jumlah Tenaga Kerja & Bahan
Rab
(Vol Rab x Koef)
648.82
A UPAH
1 Pekerja OH 0.384 85,000.00 32,640.00 249.15
2 Tukang OH 0.192 125,000.00 24,000.00 124.57
B BAHAN
1 Pasir pasang m3 0.024 165,000.00 3,960.00 15.57
2 Portland Cement (PC) Zak 0.126 62,000.00 7,787.20 81.49
Rekap Acian
Volume Jumlah
No. Uraian Sat Koef Harga Satuan Jumlah Tenaga Kerja & Bahan
Rab
(Vol Rab x Koef)
648.82
A UPAH
1 Pekerja OH 0.200 85,000.00 17,000.00 129.76
2 Tukang OH 0.100 125,000.00 12,500.00 64.88
B BAHAN
2 Portland Cement (PC) Zak 0.065 62,000.00 4,030.00 42.17
A UPAH
1 Pekerja OH 755.571 85,000.00 Rp 64,223,521.40
2 Tukang OH 295.259 125,000.00 Rp 36,907,340.00
B BAHAN
1 Portland Cement (PC) Zak 441.07 62,000.00 Rp 27,346,645.78
2 Batu Belah M3 141.07 195,000.00 Rp 27,508,852.80
3 Pasir Pasang M3 79.52 165,000.00 Rp 13,121,440.99
C PERALATAN
27787720.716 Rp (441,074.93)
24687432 Rp 2,821,420.80
10338105.024 Rp 2,783,335.97
###
RENCANA PENGGUNAAN DANA (RPD)
JADWAL PELAKSANAAN
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
NO URAIAN KEGIATAN SAT VOLUME
12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug KET
(%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 1-Sep
100%
A PEKERJAAN PERSIAPAN Ls 1 5.00
JADWAL PELAKSANAAN
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
NO URAIAN KEGIATAN SAT VOLUME
12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug KET
(%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 1-Sep
100%
A PEKERJAAN PERSIAPAN Ls 1 5.00 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
RENCANA
REALISASI
0.16 22,250.00
0.03
0.03 -
0.03 1,780,000
0.05 8,900,000
0.01
0.03
0.03 Pemakaian Semen =
0.03 100% Pas Batu 9,828.25
0.03
0.04
0.11
0.01 70% Pas. Batu 11,787.23 229.00 Sak
0.02
0.01
0.06
0.07
0.03
95.00
2.83 104 87.31
55.02 90 488.81 305
24.93 326 488.81
12.22
100.00 #REF! #REF! Rp11,000,000 Rp9,750,000
#REF! #REF!
53,407,800.98
RENCANA PENGGUNAAN DANA (RPD)
Pemakaian Semen =
100% Pas Batu 9,828.25
95.00
1.66 104 87.31
55.66 90 488.81 305
25.28 326 488.81
12.40
100.00 #REF! #REF! Rp11,000,000 Rp9,750,000
419.91
#REF! #REF!
o, 18 Mei 2017
t Oleh :
laksana
ro Sukanto
an Oleh ;
uyub Makaryo
B. Sukamto
RENCANA PENGGUNAAN DANA (RPD)
Realisasi Pekerjaan
Sampai
Bobot Bulan Lalu Bulan ini
Dengan Bulan
NO Uraian Pekerjaan Volume Satuan Ini
(%)
Bobot Bobot Bobot
Volume Volume Volume
(%) (%) (%)
Dibuat Oleh :
TPM
Novita Selviana Abukasi, S.T.
LAPORAN KEMAJUAN PELAKSANAAN
P3A : Guyub Makaryo Jenis Kegiatan : Peningkatan Jaringan Irigasi Tersier D.I Bulia
Desa : Bandung Rejo Minggu Ke : I (Satu)
Kecamatan : Boliyohuto Periode : 10 Mei 2017 - 24 Mei 2017
Kabupaten : Gorontalo Taggal Laporan : 02/06/2017
Provinsi : Gorontalo Tahun : 2017
Realisasi Pekerjaan
Sampai
Bobot Minggu Lalu Minggu ini
Dengan
NO Uraian Pekerjaan Volume Satuan Minggu Ini
(%)
Bobot Bobot Bobot
Volume Volume Volume
(%) (%) (%)
Dibuat Oleh :
TPM
Novita Selviana Abukasi, S.T.
LAPORAN KEMAJUAN PELAKSANAAN
P3A : Guyub Makaryo Jenis Kegiatan : Peningkatan Jaringan Irigasi Tersier D.I Bulia
Desa : Bandung Rejo Minggu Ke : I (Satu)
Kecamatan : Boliyohuto Periode : 25 Mei 2017 - 08 Juni 2017
Kabupaten : Gorontalo Taggal Laporan : 03/06/2017
Provinsi : Gorontalo Tahun : 2017
Realisasi Pekerjaan
Sampai
Bobot Minggu Lalu Minggu ini
Dengan
NO Uraian Pekerjaan Volume Satuan Minggu Ini
(%)
Bobot Bobot Bobot
Volume Volume Volume
(%) (%) (%)
Dibuat Oleh :
TPM
Novita Selviana Abukasi, S.T.
KURVA S KEMAJUAN PELAKSANAAN
P3A : Guyub Makaryo
Nama Pekerjaan : Peningkatan Jaringan Irigasi Tersier D.I Bulia
Desa : Bandung Rejo
Kabupaten : Gorontalo
Provinsi : Gorontalo
Tahun Anggaran : 2017
JADWAL PELAKSANAAN
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
NO URAIAN KEGIATAN SAT VOLUME
12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug KET
(%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 1-Sep
RENCANA
REALISASI #REF!
Diperiksa Oleh Dibantu Oleh :
Konsultan Manajemen Balai Tenaga Pendamping Masyarakat
JADWAL PELAKSANAAN
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
NO URAIAN KEGIATAN SAT VOLUME
3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct KET
(%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 23-Oct
JUMLAH 100.00
RENCANA MINGGUAN 1.12 0.14 2.25 0.88 0.74 6.86 6.86 9.71 11.46 11.54 11.76 11.48 11.48 11.48 1.94 0.32
KOMULATIF RENCANA MINGGUAN 1.12 1.26 3.50 4.39 5.13 11.99 18.84 28.55 40.01 51.55 63.30 74.78 86.26 97.73 99.68 100.00
REALISASI MINGGUAN
KOMULATIF REALISASI MINGGUAN
RENCANA
REALISASI
Diperiksa Oleh Dibantu Oleh :
Konsultan Manajemen Balai Tenaga Pendamping Masyarakat
50
Realisasi
Rencana
Diperiksa Oleh : Dibuat Oleh :
KONSULTAN MANAJEMEN BALAI TENAGA PENDAMPING MASYARAKAT