RINCIAN ANGGARAN BIAYA

PEMBUATAN PETA TOPOGRAFI BADAN SUNGAI WASAI

NO KEGIATAN VOLUME SATUAN HARGA

1 PENGUKURAN
SEWA ALAT (TOTAL STATION) 8 hari 1,000,000
UPAH:
SURVEYOR (2 Org x Rp. 300.000/Org) 8 hari 600,000
PEMEGANG RAMBU (4 Org x Rp. 250.000/Org) 8 hari 1,000,000
Transport & Uang Makan (6 org x Rp. 150.000) 8 hari 750,000

2 PENGOLAHAN DATA 1 keg 5,000,000

3 PENGGAMBARAN PETA 1 keg 5,000,000

4 CETAK PETA 5 lembar 300,000

TOTAL
JUMLAH

8,000,000

4,800,000
8,000,000
6,000,000

5,000,000

5,000,000

1,500,000

38,300,000