HARGA
SATU VOLUME HARGA
No. URAIAN SATUAN
AN
(Rp) (Rp)
A-01 1 M' Pagar Sementara Dari Kayu Tinggi 2 m
- Dolken Kayu Ø 8-10 / 400 cm Btg 12,500 28,000.00 35,000.00
- Semen Portland Kg 25,000 1,406.00 3,515.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Kayu balok terentang M3 0.0720 2,640,000.00 190,080.00
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Residu Kg 0.4000 8,100.00 3,240.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 269,315.90
Dibulatkan 269,316.00
A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m
- Dolken Kayu Ø 8-10 / 400 cm Btg 12,500 28,000.00 35,000.00
- Semen Portland Kg 25,000 1,406.00 3,515.00
- Seng Gelombang BJLS-30 Lbr 12,000 62,900.00 75,480.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Kayu balok terentang M3 0.0720 2,640,000.00 190,080.00
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Meni Besi Kg 0.4500 30,400.00 13,680.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 355,235.90
Dibulatkan 355,236.00
A-03 1 M' Pagar SementaraKawat Duri Tinggi 1,80 m
- Dolken Kayu Ø 8-10 / 400 cm Btg 10,000 28,000.00 28,000.00
- Semen Portland Kg 20,000 1,406.00 2,812.00
- Kawat Duri Kg 25,000 63,500.00 158,750.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 222,842.90
Dibulatkan 222,843.00
A-04 1 M2 Pengukuran Dan Pasang Bouwplank
- Kayu kaso 5/7 M3 0.0120 1,870,500.00 22,446.00
- Paku Biasa 2" - 5" Kg 0.0200 23,400.00 468.00
- Kayu papan albasia M3 0.0070 2,071,700.00 14,501.90
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 49,265.90
Dibulatkan 49,266.00
A-05 1 M2 Pembuatan Kantor Sementara dgn Lantai
Diplester
- Dolken Kayu Ø 8-10 / 400 cm Btg 12,500 28,000.00 35,000.00
- Kayu Balok terentang M3 0.1800 2,640,000.00 475,200.00
- Paku Biasa Kg 0.8500 23,400.00 19,890.00
- Besi Strip Kg 11,000 26,800.00 29,480.00
- Semen Portland Kg 350,000 1,406.00 49,210.00
- Pasir Pasang M3 0.1500 233,400.00 35,010.00
- Pasir beton M3 0.1000 255,400.00 25,540.00
- Koral Beton2/3 M3 0.1500 211,100.00 31,665.00
- Bata Merah Bh 300,000 775.00 23,250.00
- Seng Plat m' 0.2500 15,815.00 3,953.75
- Kawat harmonika M2 20,000 35,900.00 71,800.00
- Kaca Polos 3mm M2 0.0800 87,400.00 6,992.00
- Kunci Tanam Bh 0.1500 94,500.00 14,175.00
- Plywood 120 x 240 x 0,4 cm Lbr 0.0600 140,000.00 8,400.00
- Pekerja Oh 20,000 42,000.00 84,000.00
- Tukang Kayu Oh 20,000 65,000.00 130,000.00
- Tukang Batu Oh 10,000 65,000.00 65,000.00
- Kepala Tukang Oh 0.3000 75,000.00 22,500.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 1,135,065.75
Dibulatkan 1,135,066.00
A-06 1 M2 Pembuatan Gudang Semen dan Alat-alat
- Dolken Kayu Ø 8-10 / 400 cm Btg 17,000 28,000.00 47,600.00
- Kayu balok terentang M3 0.2100 2,640,000.00 554,400.00
- Paku Biasa Kg 0.3000 23,400.00 7,020.00
- Semen Portland Kg 105,000 1,406.00 14,763.00
- Pasir Beton M3 0.0300 255,400.00 7,662.00
- Koral Beton 2/3 M3 0.0500 211,100.00 10,555.00
- Seng Gelombang BJLS 30 Lbr 15,000 62,900.00 94,350.00
- Pekerja Oh 10,000 42,000.00 42,000.00
- Tukang Kayu Oh 20,000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 927,350.00
Dibulatkan 927,350.00
A-07 1 M2 Pembuatan Bedeng Buruh
- Dolken Kayu Ø 8-10 / 400 cm Btg 12,500 28,000.00 35,000.00
- Kayu balok terentang M3 0.1860 2,640,000.00 491,040.00
- Paku Biasa Kg 0.3000 23,400.00 7,020.00
- Semen Portland Kg 180,000 1,406.00 25,308.00
- Pasir Beton M3 0.0300 255,400.00 7,662.00
- Koral Beton 2/3 M3 0.0500 211,100.00 10,555.00
- Seng Gelombang BJLS 30 Lbr 15,000 62,900.00 94,350.00
- Pekerja Oh 10,000 42,000.00 42,000.00
- Tukang Kayu Oh 20,000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 861,935.00
Dibulatkan 861,935.00
A-08 1 M2 Membersihkan Lapangan dan Perataan
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 8,200.00
Dibulatkan 8,200.00
A-09 1M2 Pembuatan Jalan Sementara
- Batu Belah 15/20 M3 0.1500 205,500.00 30,825.00
- Batu Pecah 5/7 M3 0.0900 196,000.00 17,640.00
- Pasir Pasang M3 0.0100 233,400.00 2,334.00
- Pekerja Oh 10,000 42,000.00 42,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 96,799.00
Dibulatkan 96,799.00
A-10 1 M3 Bongkaran Beton Bertulang
- Pekerja Oh 66,670 42,000.00 280,014.00
- Mandor Oh 0.3330 80,000.00 26,640.00
Jumlah 306,654.00
Dibulatkan 306,654.00
A-11 1 M3 Bongkaran Dinding Tembok Bata Merah
- Pekerja Oh 66,670 42,000.00 280,014.00
- Mandor Oh 0.0330 80,000.00 2,640.00
Jumlah 282,654.00
Dibulatkan 282,654.00
A-12 1 M¹ Pagar beton Pracetak ( 5 x 50 x 213 ) cm
- Panel Beton Pracetak Lbr 0.9860 199,200.00 196,411.20
- Kolom Beton Pracetak Btg 0.5250 264,000.00 138,600.00
- Pasir Beton M3 0.0740 255,400.00 18,899.60
- Koral 2/3 M3 0.1460 211,100.00 30,820.60
- Semen abu - abu Kg 450,000 1,406.00 63,270.00
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 474,296.40
Dibulatkan 474,296.00
A-13 1 M¹ Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'
- Kawat ram ayam Lbr 0.4340 14,900.00 6,466.60
- Besi siku L 50.50.5 Kg 67,860 18,300.00 124,183.80
- Besi pelat (1,2 x 3) mm Kg 0.0424 18,300.00 775.92
- Baut bh 40,000 600.00 2,400.00
- Semen Portland Kg 25,000 1,406.00 3,515.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 166,813.22
Dibulatkan 166,813.00
A-14 1 M2 Pagar BRC lengkap dengan tiang
- BRC lengkap dengan tiang Lbr 0.4340 171,300.00 74,344.20
- Semen Portland Kg 20,000 1,406.00 2,812.00
- Kawat Duri Kg 25,000 63,500.00 158,750.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 265,378.10
Dibulatkan 265,378.00
A-15 1 M2 Steiger Werk / perancah dari Bambu
- Bambu Ø 6 - 10 (600) cm btng 10,000 25,000.00 25,000.00
- Tali ijuk kg 0.2500 23,400.00 5,850.00
- Pekerja org 0.2500 42,000.00 10,500.00
- Tukang kayu org 0.0170 65,000.00 1,105.00
- Kepala tukang org 0.0020 75,000.00 150.00
- Mandor org 0.0130 80,000.00 1,040.00
Jumlah 43,645.00
Dibulatkan 43,645.00
A-16 1 M' Cerucuk Bambu
- Bambu Ø 7 -10 (400) cm btng 12,500 25,000.00 31,250.00
- Pekerja org 0.5000 42,000.00 21,000.00
- Mandor org 0.0250 80,000.00 2,000.00
Jumlah 54,250.00
Dibulatkan 54,250.00
ANALISA HARGA SATUAN PEKERJAAN TANAH
HARGA
SATU VOLUME HARGA
No. URAIAN SATUAN
AN
(Rp) (Rp)
I-01 1 M2 Lantai Ubin Granito ukuran 40 x 40 cm
Setara Essenza
- Granito 40 x 40 cm m2 10,500 345,000.00 362,250.00
- Semen portland Kg 98,000 1,406.00 13,778.80
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 13,000 15,700.00 20,410.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 421,656.90
Dibulatkan 421,657.00
1 M2 Lantai Ubin Granito ukuran 30 x 30 cm
I-02 Setara Essenza
- Granito 30 x 30 cm m2 10,500 322,800.00 338,940.00
- Semen portland Kg 100,000 1,406.00 14,060.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 15,000 15,700.00 23,550.00
- Pekerja Oh 0.2600 42,000.00 10,920.00
- Tukang batu Oh 0.1250 65,000.00 8,125.00
- Kepala tukang Oh 0.0125 75,000.00 937.50
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 402,590.60
Dibulatkan 402,591.00
I-03 1 M¹ Plint Ubin Granito ukuran 10 x 40 cm
Setara Essenza
- Plint granito 10 x 40 cm Bh 26,500 27,600.00 73,140.00
- Semen portland Kg 12,000 1,406.00 1,687.20
- Pasir pasang M3 0.0030 233,400.00 700.20
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang batu Oh 0.0300 65,000.00 1,950.00
- Kepala tukang Oh 0.0030 75,000.00 225.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 82,032.40
Dibulatkan 82,032.00
1 M¹ Plint Ubin Granito ukuran 10 x 30 cm
I-04 Setara Essenza
- Plint granito 10 x 30 cm Bh 33,300 25,900.00 86,247.00
- Semen portland Kg 16,500 1,406.00 2,319.90
- Pasir pasang M3 0.0032 233,400.00 746.88
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0900 42,000.00 3,780.00
- Tukang batu Oh 0.0900 65,000.00 5,850.00
- Kepala tukang Oh 0.0090 75,000.00 675.00
- Mandor Oh 0.0045 80,000.00 360.00
Jumlah 101,548.78
Dibulatkan 101,549.00
I-05 1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia
- Keramik corak 10 x 20 cm m2 10,000 56,000.00 56,000.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 92,670.20
Dibulatkan 92,670.00
1 M2 Lantai Keramik corak 20 x 20 cm setara
I-06 Mulia
- Keramik corak 20 x 20 cm m2 10,000 62,500.00 62,500.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 99,170.20
Dibulatkan 99,170.00
I-07 1 M2 Lantai Keramik polos 30 x 30 cm setara
Mulia
- Keramik polos 30 x 30 cm m2 10,000 53,000.00 53,000.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 89,670.20
Dibulatkan 89,670.00
1 M2 Lantai Keramik corak 30 x 30 cm Setara
I-08 Mulia
- Keramik corak 30 x 30 cm m2 10,000 58,000.00 58,000.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 94,670.20
Dibulatkan 94,670.00
I-09 1 M2 Lantai Keramik polos 40 x 40 cm Setara
Mulia
- Keramik polos 40 x 40 cm m2 10,000 56,800.00 56,800.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 93,470.20
Dibulatkan 93,470.00
1 M2 Lantai Keramik corak 40 x 40 cm Setara
I-10 Mulia
- Keramik corak 40 x 40 cm m2 10,000 65,500.00 65,500.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 102,170.20
Dibulatkan 102,170.00
I-11 1 M2 Lantai Keramik Corak 10 x 20 cm setara Roman
- Keramik corak 10 x 20 cm m2 10,000 72,200.00 72,200.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 108,870.20
Dibulatkan 108,870.00
1 M2 Lantai Keramik corak 20 x 20 cm setara
I-12 Roman
- Keramik corak 20 x 20 cm m2 10,000 75,200.00 75,200.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 111,870.20
Dibulatkan 111,870.00
1 M2 Lantai Keramik polos 30 x 30 cm setara
I-13 Roman
- Keramik polos 30 x 30 cm m2 10,000 68,900.00 68,900.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 105,570.20
Dibulatkan 105,570.00
1 M2 Lantai Keramik corak 30 x 30 cm Setara
I-14 Roman
- Keramik corak 30 x 30 cm M2 10,000 76,600.00 76,600.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,270.20
Dibulatkan 113,270.00
1 M2 Lantai Keramik polos 40 x 40 cm setara
I-15 Roman
- Keramik polos 40 x 40 cm m2 10,000 72,500.00 72,500.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 109,170.20
Dibulatkan 109,170.00
I-16 1 M2 Lantai Keramik corak 40 x 40 cm Setara
Roman
- Keramik corak 40 x 40 cm m2 10,000 77,000.00 77,000.00
- Semen portland Kg 80,000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,670.20
Dibulatkan 113,670.00
I-17 1 M2 Lantai Marmer
- Marmer m2 10,600 550,000.00 583,000.00
- Semen portland Kg 81,900 1,406.00 11,515.14
- Pasir pasang M3 0.0450 233,400.00 10,503.00
- Semen warna Kg 0.6500 15,700.00 10,205.00
- Pekerja Oh 0.7000 42,000.00 29,400.00
- Tukang batu Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0350 80,000.00 2,800.00
Jumlah 672,798.14
Dibulatkan 672,798.00
I-18 1 M2 Lantai Parquet Jati
- Parquet jati M2 10,500 375,400.00 394,170.00
- Lem vinyl Kg 0.6000 44,000.00 26,400.00
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0325 80,000.00 2,600.00
Jumlah 475,845.00