futsal 40 20 800
voli 18 9 162
basket 28.5 15 427.5
1389.5 69.475

pasang bata rollag 40 20 0.16 120 19.2


18 9 0.16 54 8.64
28.5 15 0.16 87 13.92
41.76

galian tanah pondasi 40 20 0.3 0.1 3.6


18 9 0.3 0.1 1.62
28.5 15 0.3 0.1 2.61
7.83

bowplank 40 20 120
18 9 54
28.5 15 87
261
jaring net 40 20 3 360
HARGA SATUAN UMUM UPAH, BAHAN DAN PERALATAN BIDANG KONSTRUKSI
( HARGA TIDAK TERMASUK PPN )
TAHUN 2019

No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

A. UPAH
L.01 Pekerja oh Rp 100,000
- Pembantu supir / kenek oh Rp 100,000
- Supir personil / mobil ringan oh Rp 120,000
- Supir material / truck oh Rp 150,000
- Pembantu operator oh Rp 100,000
- Operator kurang terlatih oh Rp 100,000
- Operator terlatih oh Rp 125,000
L.02 Tukang gali sumur oh Rp 125,000
L.02 Tukang ledeng / pipa oh Rp 125,000
L.02 Tukang listrik oh Rp 120,000
L.02 Tukang cat oh Rp 120,000
L.02 Tukang besi / tukang las oh Rp 125,000
L.02 Tukang kayu oh Rp 125,000
L.02 Tukang batu oh Rp 125,000
L.03 Kepala tukang oh Rp 150,000
- Mekanik pembantu oh Rp 125,000
- Mekanik oh Rp 175,000
L.04 Mandor oh Rp 150,000

B. MATERIAL/BAHAN
1 Air Ltr Rp 50
2 Alang-alang Ikat Rp 1,000
3 Alat-alat bantu set Rp 150,000
4 All socket reducer PVC ø 100 x 80 (mm) unit Rp 204,700
5 All socket reducer PVC ø 80 x 50 (mm) unit Rp 175,950
6 Aluminium foil m² Rp 6,000
7 Agregat kls A m3 Rp 296,316
8 Ampelas lembar Rp 5,000
9 Aspal kg Rp 16,815
10 Atap Alluminium Gelombang tebal 0.55 (Galvalum) m² Rp 58,750
11 Atap asbes gelombang uk. 1,50 x 0,90 (m) tebal 4 mm lembar Rp 51,000
12 Atap asbes gelombang uk. 1,80 x 1,05 (m) tebal 4 mm lembar Rp 63,000
13 Atap asbes gelombang uk. 2,10 x 1,05 (m) tebal 4 mm lembar Rp 73,500
14 Atap asbes gelombang uk. 2,40 x 1,05 (m) tebal 4 mm lembar Rp 84,000
15 Atap asbes gelombang uk. 2,70 x 1,05 (m) tebal 4 mm lembar Rp 94,500
16 Atap asbes gelombang uk. 3,00 x 1,05 (m) tebal 4 mm lembar Rp 105,000
17 Atap monolayer 3 mm (ex. Onduline Clasic) lembar Rp 155,000
18 Atap Genteng monolayer 3 mm (ex. Onduvilla) lembar Rp 48,800
19 Atap Genteng monolayer 3 mm (ex. Onduline Tile) lembar Rp 145,000
20 Nok / Ridge (ex. Onduline) lembar Rp 82,000
21 Atap genteng (standar KIA) buah Rp 5,500
22 Atap genteng beton ( jenis press) buah Rp 7,750
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

23 Atap genteng kodok buah Rp 5,000


24 Atap genteng keramik buah Rp 12,000
25 Atap metal (biasa / polos) lembar Rp 30,000
26 Atap metal Pasir lembar Rp 54,000
27 Atap seng fibreglass lembar Rp 122,500
28 Atap seng gelombang bjls 20 uk. 0,914 x 1,829 (m) lembar Rp 36,000
29 Atap Polycarbonat m2 Rp 115,000
30 Bak cuci piring (sink) stainless steel 1 lobang buah Rp 200,000
31 Bak cuci piring (sink) stainless steel 2 lobang buah Rp 448,750
32 asesoris bak cuci piring set Rp 35,000
33 Bak mandi fibreglass volume 0,15 m³ buah Rp 200,000
34 Bak mandi fibreglass volume 0,30 m³ buah Rp 230,000
35 Bak mandi fibreglass volume 1,00 m³ buah Rp 180,000
36 Batako buah Rp 1,625
37 Bata Ringan/Hebel (10 x 20 x 60 cm) m² Rp 17,500
38 Bata tempel hitam m² Rp 210,000
39 Bata paras m² Rp 130,000
40 Batu bata merah (lokal) bh Rp 1,600
41 Batu belah m³ Rp 325,000
42 Batu belah 15 - 20 (cm) m³ Rp 400,000
43 Batu pecah 0,5 - 1 (cm) m³ Rp 400,000
44 Batu pecah 1 - 2 (cm) m³ Rp 400,000
45 Batu pecah 2 - 3 (cm) m³ Rp 400,000
46 Batu pecah 3 - 5 (cm) m³ Rp 400,000
47 Batu pecah 5 - 7 (cm) m³ Rp 400,000
48 Batu pecah 7 - 10 (cm) m³ Rp 400,000
49 Batu pecah 0,5 - 1 (cm) (Kg) kg Rp 296
50 Batu pecah 1 - 2 (cm) (Kg) kg Rp 296
51 Batu pecah 2 - 3 (cm) (Kg) kg Rp 296
52 Batu pecah 3 - 5 (cm) (Kg) kg Rp 296
53 Batu pecah 5 - 7 (cm) (Kg) kg Rp 296
54 Batu pecah 7 - 10 (cm) (Kg) kg Rp 296
55 Baut klem buah Rp 296
56 Bensin Pertalite liter Rp 7,850
57 Besi baja profil IWF kg Rp 17,000
58 Besi baut kuda-kuda kg Rp 15,000
59 Besi beton kg Rp 11,131
60 Besi jaring kawat baja kg Rp 21,000
61 Besi prestressed polos kg Rp 13,000
62 Besi strip kg Rp 13,000
63 Besi hollow 4m x 4m x 1,2 mm m1 Rp 26,667
64 Besi hollow Plafond m1 Rp 5,000
65 Besi Wiremesh M-6 kg Rp 12,315 32.48
66 Besi Wiremesh M-8 kg Rp 13,619 58.74
67 Besi Wiremesh M-10 kg Rp 14,021 92.72
68 Bubungan atap (nok) alumunium standar 40 cm, swg. 22 m² Rp 25,000
69 Bubungan atap (nok) asbes sepasang lembar Rp 5,000
70 Bubungan atap (nok) genteng (standar KIA) buah Rp 5,000
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

71 Bubungan atap (nok) genteng beton buah Rp 8,000


72 Bubungan atap (nok) genteng kodok buah Rp 5,000
73 Bubungan atap (nok) genteng soka buah Rp 14,500
74 Bubungan atap (nok) metal (biasa / polos) buah Rp 37,500
75 Bubungan atap (nok) metal (standar Rainbow) m' Rp 35,000
76 Buis beton bertulang ø 40 cm buah Rp 180,000
77 Buis beton bertulang ø 60 cm buah Rp 400,000
78 Buis beton bertulang ø 80 cm buah Rp 700,000
79 Buis beton bertulang ø 100 cm buah Rp 750,000
80 Buis beton tak bertulang ø 100 cm buah Rp 580,000
81 Buis beton tak bertulang ø 80 cm tebal 5 cm buah Rp 180,000
82 Buis beton tak bertulang ø 60 cm buah Rp 250,000
83 Buis beton tak bertulang ø 40 cm buah Rp 150,000
84 Cat Dasar kg Rp 24,250
85 Cat genteng KW I kg Rp 38,000
86 Cat genteng KW II kg Rp 44,375
87 Cat jalan (road line) kg Rp 49,000
88 Cat jembatan kg Rp 58,000
89 Cat menie kg Rp 42,500
90 Cat minyak kg Rp 58,750
91 Cat tembok (ex platon) kg Rp 55,250
92 Cat tembok in(ex mowilex) kg Rp 66,000
93 Cat tembok ext (ex mowilex) kg Rp 100,000
94 Cat vernis kg Rp 71,000
95 Closed duduk lengkap tabung dan jet waser buah Rp 2,100,000
96 Closed jongkok keramik buah Rp 190,000
97 Closed jongkok + Flushing buah Rp 3,000,000
98 Closed jongkok porcelaint (lokal) buah Rp 421,250
99 Conblock tebal 6 cm (polos) segi enam buah Rp 1,700
100 Conblock tebal 6 cm (warna) segi enam buah Rp 1,700
101 Conblock tebal 6 cm segi enam (polos) m² Rp 42,500
102 conblock tebal 6 cm segi enam (warna) m² Rp 45,000
103 conblock tebal 6 cm persegi panjang (polos) bh Rp 1,600
104 Dempul kg Rp 35,000
105 Dina bolt / ramset buah Rp 2,250
106 Dop PVC ø 50 mm unit Rp 93,750
107 Door Closer unit Rp 200,000
108 Door Holder unit Rp 30,000
109 Door Stop unit Rp 20,000
110 Elektroda penghantar bumi untuk penangkal petir buah Rp 170,000
111 Emulsi liter Rp 12,337
112 Engsel pintu / jendela 3" buah Rp 17,500
113 Engsel pintu / jendela 4" buah Rp 23,500
114 Engsel pintu / jendela 5" buah Rp 33,500
115 Engsel pintu kaca 10 mm set Rp 900,000
116 Engsel Casement (Jendela Alumunium) bh Rp 26,000
117 Eternit asbes uk. 1 x 1 (m), tebal 4 mm m² Rp 25,000
118 Eternit asbes uk. 1 x 1 (m), tebal 5 mm m² Rp 23,000
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

119 Espagnolette buah Rp 182,000


120 Fibre Plat 0,60 x 1,20 (m), tebal 4 mm m² Rp 25,000
121 Fibre Plat 1,20 x 2,40 (m), tebal 4 mm m² Rp 67,500
122 Fitting bh Rp 25,000
123 Floor drain buah Rp 25,000
124 Formite/penjaga jarak bekisting/spacer bh Rp 1,500
125 Grease (minyak gemuk) kg Rp 18,750
126 Grendel (biasa) buah Rp 10,000
127 Grendel (istimewa) buah Rp 15,000
128 Gypsum board uk. 1.22 x 2.44 (m), tebal 9 mm lembar Rp 65,000
129 Glass block bh Rp 25,750
130 Grasblock m2 Rp 72,000
131 Handle jendela buah Rp 9,000
132 Handle pintu buah Rp 135,000
133 Handle untuk meubelair (furniture) + kunci buah Rp 12,000
134 ijuk kg Rp 15,000
135 inbow doos bh Rp 5,500
136 las doop bh Rp 1,250
137 isolasi listrik bh Rp 9,000
138 T doos bh Rp 2,000
139 Jendela nako (kerangka) m² Rp 159,000
140 jet washer buah Rp 90,000
141 Kabel biasa m' Rp 4,000
142 Kabel listrik NYA 2.5 mm² m' Rp 3,400
143 Kabel listrik NYM 2 x 2,5 mm² m' Rp 12,000
144 Kabel listrik NYM 3 x 2,5 mm² m' Rp 17,500
145 Kabel listrik NYY 4 x 2,5 mm² m' Rp 26,000
146 Kabel listrik NYY 4 x 4 mm² m' Rp 27,000
147 Klem Kabel no. 10 piece Rp 10,000
148 Klem Kabel no. 12 piece Rp 14,500
149 Kabel slink m' Rp 28,700
150 Kaca bening tebal 3 mm m² Rp 112,000
151 Kaca bening tebal 5 mm m² Rp 131,000
152 Kaca bening tebal 8 mm m² Rp 163,000
153 Kaca bening tebal 10 mm m² Rp 187,000
154 Kaca gelap (ray band) tebal 5 mm m² Rp 178,700
155 Kaca gelap (ray band) tebal 10 mm m² Rp 236,800
156 Kaca gelap (ray band) tebal 12 mm m² Rp 319,700
157 Kaca buram 12mm m² Rp 341,300
158 Kaca cermin 5 mm m² Rp 170,600
159 Kaca patri m² Rp 1,138,500
160 Kain kassa m2 Rp 4,000
161 Kait angin (biasa) buah Rp 10,000
162 Kait angin (istimewa) buah Rp 20,000
163 Kepek bh Rp 8,000
164 Kapur bakar kg Rp 30,000
165 Kapur sirih kg Rp 40,000
166 Karet kaca m' Rp 10,000
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

167 Karpet talang, lebar 0,60 m' m' Rp 15,000


168 Kawat nyamuk logam m² Rp 35,000
169 Kawat nyamuk plastik m² Rp 58,750
170 Kawat berduri kg Rp 27,813
171 Kawat beton kg Rp 25,000
172 Kawat bronjong uk 3x1,5x0,5 m2 Rp 109,000
173 Kawat burung m² Rp 15,000
174 Kawat harmonika m² Rp 35,000
175 Kawat kassa / kawat loket m² Rp 16,000
176 Kawat Las Listrik Kg Rp 27,000
177 Kawat seng kg Rp 27,000
178 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang Rp 5,000
179 Kayu gelam ø 8 - 10 (cm) panjang 4 m / kiau batang Rp 10,000
180 Kayu gergajian kelas I, balok m³ Rp 3,500,000
181 Kayu gergajian kelas I, papan m³ Rp 3,750,000
182 Kayu gergajian kelas II, balok m³ Rp 2,500,000
183 Kayu gergajian kelas II, papan m³ Rp 2,500,000
184 Kayu gergajian kelas III, balok m³ Rp 2,000,000
185 Kayu gergajian kelas III, papan m³ Rp 1,800,000
186 Kayu gergajian kelas IV, balok m³ Rp 1,500,000
187 Kayu gergajian kelas IV, papan m³ Rp 1,500,000
188 Kayu untuk konstruksi jembatan m³ Rp 2,500,000
189 Kayu untuk perancah m³ Rp 1,650,000
190 Keramik 10 x 20 (cm) gelap m² Rp 67,500
191 Keramik 10 x 20 (cm) polos m² Rp 65,000
192 Keramik 10 x 20 (cm) terang m² Rp 62,500
193 Keramik 20 x 20 (cm) polos m² Rp 57,500
194 Keramik 20 x 25 (cm) gelap m² Rp 60,000
195 Keramik 30 x 30 (cm) gelap m² Rp 64,000
196 Keramik 30 x 30 (cm) polos m² Rp 52,500
197 Keramik 30 x 30 (cm) putih / berwarna m² Rp 53,500
198 Keramik 40 x 40 (cm) putih / berwarna m² Rp 54,000
199 Keramik 60 x 60 (cm) putih / berwarna ex granito m² Rp 150,000
200 Keramik 60 x 60 (cm) putih / berwarna ex KIA m² Rp 160,000
201 Keramik KM/WC anti slip 20 x 20 (cm) m² Rp 60,000
202 Knee / elbow PVC 1(inch) buah Rp 4,000
203 Knee / elbow PVC 3/4 (inch) buah Rp 3,750
204 Knee / elbow PVC 1/2 (inch) buah Rp 3,000
205 Kompon gypsum kg Rp 5,500
206 Kran air ø 0,75 (inch) buah Rp 21,750
207 Kran air ø 1,50 (inch) buah Rp 23,500
208 Kuas bh Rp 13,350
209 Kunci jendela (lokal) set Rp 10,000
210 Kunci pintu tanam (biasa) set Rp 120,000
211 Kunci pintu tanam (istimewa) set Rp 185,000
212 Kunci pintu untuk meubelair (furniture) set Rp 15,000
213 Kunci Selot buah Rp 12,500
214 Kunci Silinder buah Rp 62,500
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

215 Kunci tanam buah Rp 127,500


216 Kusen pintu / jendela alumunium 3" (warna silver) m' Rp 90,000
217 Kusen pintu / jendela alumunium 4" (warna silver) m' Rp 100,000
218 Kusen pintu / jendela alumunium 3" (warna gelap) m' Rp 95,000
219 Kusen pintu / jendela alumunium 4"(warna gelap) m' Rp 105,000
220 Lampu Baret titik Rp 220,000
221 Lampu pijar 18 watt Rp 80,000
222 Lampu TL D 36 Watt bh Rp 150,000
223 Lampu taman 20 W + aksesoris unit Rp 700,000
224 Lampu taman triple 20 W + aksesoris unit Rp 2,250,000
225 Lampu TL 20 W bh Rp 14,000
226 Lampu TL 40 W bh Rp 19,000
227 Lampu SL bulat 11 W bh Rp 30,000
228 Lampu SL bulat 32 W bh Rp 42,000
229 Fititing Downlight buah Rp 35,000
230 Lem (standar Aica Aibond) kg Rp 14,500
231 Lem (standar Fox) kg Rp 20,000
232 Lem Kayu kg Rp 20,000
233 List gypsum sedang m1 Rp 25,000
234 List gypsum kecil m1 Rp 21,500
235 Mata lampu + instalasi titik Rp 115,000
236 MCB 10 a 1 phasa bh Rp 60,000
237 Minyak bekisting liter Rp 27,500
238 Minyak pelarut/pengencer cat (solvent) liter Rp 8,000
239 Minyak pelumas (oli) liter Rp 35,000
240 Minyak solar liter Rp 12,150
241 Multiplek tebal 12 mm 4 x 8 (inch) lembar Rp 187,500
242 Multiplek tebal 15 mm 4 x 8 (inch) lembar Rp 250,000
243 Multiplek tebal 18 mm 4 x 8 (inch) lembar Rp 285,000
244 Multiplek tebal 6 mm uk. 1.22 x 2.44 (m) lembar Rp 93,750
245 Multiplek tebal 9 mm 4 x 8 (inch) lembar Rp 155,000
246 Pagar panel beton m2 Rp 300,000
247 Paku anti Karat kg Rp 22,000
248 Paku asbes kg Rp 35,000
249 Paku biasa (1/2" - 1") kg Rp 20,000
250 Paku biasa 2" - 5" kg Rp 18,000
251 Paku jembatan kg Rp 33,900
252 Paku kait kg Rp 14,900
253 Paku sekrup (kg) kg Rp 98,750
254 Paku skrup 1 cm – 2,5 cm bh Rp 250
255 Paku seng kg Rp 35,000
256 Paku tembok kg Rp 62,500
257 Panel listrik / MCB, 1 group / fase buah Rp 18,000
258 Panel listrik / MCB, 2 group / fase buah Rp 10,000
259 Panel listrik / MCB, 3 group / fase buah Rp 10,000
260 Panel listrik / MCB, 4 group / fase buah Rp 35,000
261 Parquette lantai m² Rp 125,000
262 Pasir ayak untuk beton (m3) m³ Rp 52,125
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

263 Pasir ayak untuk beton (kg) kg Rp 37


264 Pasir pasang m³ Rp 52,125
265 Pasir urug / timbun m³ Rp 50,000
266 Pelitur Jadi Ltr Rp 80,000
267 Pembersih / cleaner untuk keramik / porcelaint kg Rp 20,000
268 Pintu alumunium - swing + door closer m2 Rp 200,000
269 Pintu alumunium - swing + floorhinge m2 Rp 1,250,000
270 Pintu besi m² Rp 319,700
271 Pintu besi lipat (folding door) m² Rp 750,000
272 Pipa besi galvanis ø 0,5 (inch) m' Rp 16,667
273 Pipa besi galvanis ø 0,75 (inch) m' Rp 19,167
274 Pipa besi galvanis ø 1 (inch) m' Rp 22,500
275 Pipa besi galvanis ø 1,25 (inch) m' Rp 33,750
276 Pipa besi galvanis ø 1,5 (inch) m' Rp 37,500
277 Pipa besi galvanis ø 2 (inch) m' Rp 46,667
278 Pipa besi galvanis ø 3 (inch) m' Rp 187,667
279 Pipa besi galvanis ø 4 (inch) m' Rp 271,667
280 Pipa besi ø 0,5 (inch) m' Rp 21,600
281 Pipa besi ø 0,75 (inch) m' Rp 24,500
282 Pipa besi ø 1 (inch) m' Rp 30,800
283 Pipa besi ø 1,25 (inch) m' Rp 42,500
284 Pipa besi ø 1,5 (inch) m' Rp 48,100
285 Pipa besi ø 2 (inch) m' Rp 65,000
286 Pipa PVC ø 1/2 (inch) AW, panjang 4 m m' Rp 5,000
287 Pipa PVC ø 3/4 (inch) AW, panjang 4 m m' Rp 6,250
288 Pipa PVC ø 1(inch) AW, panjang 4 m m' Rp 9,500
289 Pipa PVC ø 1,5 (inch) AW, panjang 4 m m' Rp 15,500
290 Pipa PVC ø 2 (inch) AW, panjang 4 m m' Rp 20,000
291 Pipa PVC ø 2,5 (inch) AW, panjang 4 m m' Rp 30,000
292 Pipa PVC ø 3 (inch) AW, panjang 4 m m' Rp 40,000
293 Pipa PVC ø 4 (inch) AW, panjang 4 m m' Rp 62,500
294 Pipa PVC ø 6 (inch) AW, panjang 4 m m' Rp 175,000
295 pipa listrik 5/8' btg Rp 8,000
296 Plamuer tembok kg Rp 10,000
297 Plywood uk. 0,30 x 0,60 (m), tebal 4mm lembar Rp 75,000
298 Plywood uk. 0,30 x 0,60 (m), tebal 6mm lembar Rp 95,000
299 Plywood uk. 1,22 x 2,44 (m), tebal 4 mm lembar Rp 57,500
300 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lembar Rp 150,000
301 Pompa air (dengan otomatis) buah Rp 712,500
302 Pompa air (jet pump) buah Rp 1,915,000
303 Pompa air (non otomatis) buah Rp 430,000
304 Profil Aluminium "T" m' Rp 8,500
305 Profil Kaca m' Rp 10,000
306 Profil Daun Pintu Alumunium (warna siver) m' Rp 85,000
307 Profil Daun Jendela Alumunium (warna silver) m' Rp 55,000
308 Daun Pintu Alumunium (warna siver) m' Rp 1,500,000
309 Daun Jendela Alumunium (warna gelap) m' Rp 800,000
310 Daun Pintu Alumunium (warna gelap) m' Rp 1,600,000
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

311 Rangka Baja Ringan m² Rp 300,000


312 Reducer PVC dari 1/2 (inch) ke 1 (inch) buah Rp 4,875
313 Reducer PVC dari 1/2 (inch) ke 3/4 (inch) buah Rp 4,625
314 Reducer PVC dari 3/4 (inch) ke 1 (inch) buah Rp 4,875
315 Rel Pintu Dorong buah Rp 250,000
316 Residu atau Ter liter Rp 50,000
317 Rolling dor - alumunium tebal m² Rp 350,000
318 Rolling dor - alumunium tipis m² Rp 300,000
319 Rolling door galfalum m² Rp 750,000
320 Roll Cat bh Rp 35,000
321 Rooflight fibreglass uk. 1,8 x 0,9 (m) lembar Rp 80,500
322 Rooster block uk. 12 x 11 x 24 (cm) buah Rp 20,000
323 Rooster block uk. 20 x 20 (cm) buah Rp 13,500
324 Rooster keramik 20 x 20 (cm) buah Rp 45,000
325 Rooster keramik 30 x 30 (cm) buah Rp 52,500
326 Rumah Lampu bh Rp 13,000
327 Sabun Kg Rp 15,000
328 Saklar tunggal buah Rp 16,000
329 Saklar dobel buah Rp 22,000
330 Saklar engkel buah Rp 23,000
331 Sealant Tube Rp 32,500
332 Sealtape buah Rp 5,000
333 Semen PC @ 50 kg kg Rp 1,500
334 Semen putih kg Rp 6,850
335 Semen warna kg Rp 15,000
336 Semen kolot (sika graut) kg Rp 10,000
337 Seng fibreglass lembar Rp 82,500
338 Seng plat BJLS 27 uk. 0.3 x 1.83 (m) lembar Rp 40,850
339 Seng plat BJLS 27 uk. 0.9 x 1.83 (m) lembar Rp 40,850
340 Seng Gelombang 3" x 6" BJLS 28 lembar Rp 38,500
341 Skrup fixer buah Rp 300
342 Shower buah Rp 225,000
343 Sirtu m³ Rp 259,250
344 sikat baja bh Rp 15,000
345 Slot jendela buah Rp 8,500
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

346 Slot pintu buah Rp 13,750


347 Slot ventilasi / bouwvenlight buah Rp 10,000
348 Socket PVC ø 1 (inch) buah Rp 4,500
349 Socket PVC ø 1/2 (inch) buah Rp 4,000
350 Socket PVC ø 3/4 (inch) buah Rp 4,000
351 Soda api Kg Rp 18,000
352 spring Knip bh Rp 10,000
353 Softboard uk. 1,20 x 2,40 (m), tebal 4 mm lembar Rp 613,000
354 Stone Coating kg Rp 45,000
355 Stop kontak titik Rp 17,500
356 Stop Kontak + Instalasi titik Rp 143,900
357 Sunscreen alumunium m² Rp 1,600,000
358 Tangki air / hydrant umum polyethylene 5.000 liter buah Rp 10,050,000
359 Tangki air fiberglass (oranye) 1.000 liter buah Rp 1,700,000
360 Tangki air fiberglass (oranye) 2.000 liter buah Rp 3,500,000
361 Tangki air fiberglass (oranye) 3.000 liter buah Rp 5,200,000
362 Tangki air fiberglass (oranye) 5.000 liter buah Rp 8,500,000
363 Tangki air fiberglass (oranye) 500 liter buah Rp 950,000
364 Teak Oil ltr Rp 3,500
365 Tempat sabun keramik buah Rp 60,000
366 Teralis pintu lubang Rp 1,200,000
367 Teralis jendela lubang Rp 475,000
368 Ter kg Rp 100,000
369 Thinner Kg Rp 30,000
370 Timbunan biasa m³ Rp 35,000
371 Timbunan pilihan / tanah puru m³ Rp 60,000
372 Triplek tebal 2.5 mm uk. 1.22 x 2.44 (m) lembar Rp 65,000
373 Triplek tebal 4 mm uk. 1.22 x 2.44 (m) lembar Rp 83,500
374 Urinoir Unit Rp 2,000,000
375 Wallpaper bermotif m² Rp 40,200
376 Wallpaper polos m² Rp 34,500
377 Wastafel set Rp 1,250,000
378 Listplank GRC Board/Calsiboard m1 Rp 60,000

PERPIPAAN AIR MINUM DAN AIR LIMBAH


1 Pipa HDPE PN 10 dia. 20 m' Rp 9,043
2 Pipa HDPE PN 10 dia. 25 m' Rp 11,724
3 Pipa HDPE PN 10 dia. 32 m' Rp 15,773
4 Pipa HDPE PN 10 dia. 40 m' Rp 24,817
5 Pipa HDPE PN 10 dia. 50 m' Rp 34,020
6 Pipa HDPE PN 10 dia. 63 m' Rp 54,047
7 Pipa HDPE PN 10 dia. 75 m' Rp 76,833
8 Pipa HDPE PN 10 dia. 90 m' Rp 107,954
9 Pipa HDPE PN 10 dia. 110 m' Rp 159,528
10 Pipa HDPE PN 10 dia. 160 m' Rp 326,235
11 Pipa HDPE PN 10 dia. 200 m' Rp 500,697
12 Pipa UPVC dia. 63 m' Rp 41,087
13 Pipa UPVC dia. 75 m' Rp 61,854
No. URAIAN / NAMA / JENIS BARANG SATUAN HARGA SATUAN 2019

14 Pipa UPVC dia. 90 m' Rp 83,681


15 Pipa UPVC dia. 110 m' Rp 120,636
16 Pipa UPVC dia. 160 m' Rp 249,663
17 Pipa UPVC dia. 200 m' Rp 379,998
18 Pipa Air Limbah dia. 63 m' Rp 52,018
19 Pipa Air Limbah dia. 75 m' Rp 66,202
20 Pipa Air Limbah dia. 90 m' Rp 79,754
21 Pipa Air Limbah dia. 110 m' Rp 101,483
22 Pipa Air Limbah dia. 160 m' Rp 186,359
23 Pipa Air Limbah dia. 200 m' Rp 278,064
A.4.1.1 HARGA SATUAN PEKERJAAN BETON

CATATAN : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

A. 4.1.1.1 Membuat 1 m3 beton mutu f'c = 7,4 Mpa (K100), slump (12 ± 2) cm, w/c = 0,87
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 247.000 1,500.00
2 Pasir ayak untuk beton (kg) kg 869.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 999.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.2 Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K125), slump (12 ± 2) cm, w/c = 0,78
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 276.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 828.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1012.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.3 Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K150), slump (12 ± 2) cm, w/c = 0,72
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 299.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 799.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1017.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa (K100), slump (3-6) cm, w/c = 0,97
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.200 100,000.00
2 Tukang Batu L.02 OH 0.200 125,000.00
3 Kepala Tukang L.03 OH 0.020 150,000.00
4 Mandor L.04 OH 0.060 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 230.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 893.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1027.000 296.30
4 Air ltr 200.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.5 Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K175), slump (12 ± 2) cm, w/c = 0,66
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 326.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 760.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1029.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.6 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K200), slump (12 ± 2) cm, w/c = 0,61
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 352.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 731.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1031.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K225), slump (12 ± 2) cm, w/c = 0,58
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 371.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 698.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1047.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.8 Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K250), slump (12 ± 2) cm, w/c = 0,56
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 384.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 692.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1039.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.9 Membuat 1 m3 beton mutu f'c = 24,0 Mpa (K275), slump (12 ± 2) cm, w/c = 0,53
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 406.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 684.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1026.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.10 Membuat 1 m3 beton mutu f'c = 26,4 Mpa (K300), slump (12 ± 2) cm, w/c = 0,52
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 1.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Kepala Tukang L.03 OH 0.028 150,000.00
4 Mandor L.04 OH 0.083 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 413.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 681.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1021.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.11 Membuat 1 m3 beton mutu f'c = 28,8 Mpa (K325), slump (12 ± 2) cm, w/c = 0,49
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 2.100 100,000.00
2 Tukang Batu L.02 OH 0.350 125,000.00
3 Kepala Tukang L.03 OH 0.035 150,000.00
4 Mandor L.04 OH 0.105 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 439.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 670.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1006.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.12 Membuat 1 m3 beton mutu f'c = 31,2 Mpa (K350), slump (12 ± 2) cm, w/c = 0,48
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 2.100 100,000.00
2 Tukang Batu L.02 OH 0.350 125,000.00
3 Kepala Tukang L.03 OH 0.035 150,000.00
4 Mandor L.04 OH 0.105 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Semen PC @ 50 kg kg 448.000 1,320.00
2 Pasir ayak untuk beton (kg) kg 667.000 37.23
3 Batu pecah 2 - 3 (cm) (Kg) kg 1000.000 296.30
4 Air ltr 215.000 50.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.070 100,000.00
2 Tukang besi / tukang las L.02 OH 0.070 125,000.00
3 Kepala Tukang L.03 OH 0.007 150,000.00
4 Mandor L.04 OH 0.004 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Besi beton kg 10.500 11,131.34
2 Kawat beton kg 0.150 25,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
G. Pembesian 1 kg dengan besi polos atau ulir

A. 4.1.1.18 Pembesian 10 kg kabel presstressed polos/strands


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.050 100,000.00
2 Tukang besi / tukang las L.02 OH 0.050 125,000.00
3 Kepala Tukang L.03 OH 0.005 150,000.00
4 Mandor L.04 OH 0.003 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Besi prestressed polos kg 10.500 13,000.00
2 Kawat beton kg 0.100 25,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
G. Pembesian 1 kg kabel presstressed polos/strands
A. 4.1.1.19.a Pemasangan 10 kg jaring kawat (wiremesh) - M6
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.025 100,000.00
2 Tukang besi / tukang las L.02 OH 0.025 125,000.00
3 Kepala Tukang L.03 OH 0.025 150,000.00
4 Mandor L.04 OH 0.001 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Besi Wiremesh M-6 kg 10.200 12,315.27
2 Kawat beton kg 0.050 25,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
G. Pemasangan 1 kg jaring kawat (wiremesh)-M6

A. 4.1.1.19.b Pemasangan 10 kg jaring kawat (wiremesh) - M8


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.025 100,000.00
2 Tukang besi / tukang las L.02 OH 0.025 125,000.00
3 Kepala Tukang L.03 OH 0.025 150,000.00
4 Mandor L.04 OH 0.001 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Besi Wiremesh M-8 kg 10.200 13,619.34
2 Kawat beton kg 0.050 25,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
G. Pemasangan 1 kg jaring kawat (wiremesh) - M8

A. 4.1.1.19.c Pemasangan 10 kg jaring kawat (wiremesh) - M10


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.025 100,000.00
2 Tukang besi / tukang las L.02 OH 0.025 125,000.00
3 Kepala Tukang L.03 OH 0.025 150,000.00
4 Mandor L.04 OH 0.001 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Besi Wiremesh M-10 kg 10.200 14,020.71
2 Kawat beton kg 0.050 25,000.00
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
G. Pemasangan 1 kg jaring kawat (wiremesh) - M10

A. 4.1.1.20 Membuat 1 m2 bekisting untuk pondasi


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.520 100,000.00
2 Tukang Kayu L.02 OH 0.260 125,000.00
3 Kepala Tukang L.03 OH 0.026 150,000.00
4 Mandor L.04 OH 0.026 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.040 1,800,000.00
2 Paku biasa 2" - 5" kg 0.300 18,000.00
3 Minyak bekisting liter 0.100 27,500.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.21 Membuat 1 m2 bekisting untuk sloof
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.520 100,000.00
2 Tukang Kayu L.02 OH 0.260 125,000.00
3 Kepala Tukang L.03 OH 0.026 150,000.00
4 Mandor L.04 OH 0.026 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.045 1,800,000.00
2 Paku biasa 2" - 5" kg 0.300 18,000.00
3 Minyak bekisting liter 0.100 27,500.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.22 Membuat 1 m2 bekisting untuk kolom


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.660 100,000.00
2 Tukang Kayu L.02 OH 0.330 125,000.00
3 Kepala Tukang L.03 OH 0.033 150,000.00
4 Mandor L.04 OH 0.033 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.040 1,800,000.00
2 Paku biasa 2" - 5" kg 0.400 18,000.00
3 Minyak bekisting liter 0.200 27,500.00
4 Kayu gergajian kelas II, balok m3 0.015 2,500,000.00
5 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 0.350 150,000.00
6 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 2.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.23 Membuat 1 m2 bekisting untuk balok


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.660 100,000.00
2 Tukang Kayu L.02 OH 0.330 125,000.00
3 Kepala Tukang L.03 OH 0.033 150,000.00
4 Mandor L.04 OH 0.033 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.040 1,800,000.00
2 Paku biasa 2" - 5" kg 0.400 18,000.00
3 Minyak bekisting liter 0.200 27,500.00
4 Kayu gergajian kelas II, balok m3 0.018 2,500,000.00
5 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 0.350 150,000.00
6 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 2.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.24 Membuat 1 m2 bekisting untuk lantai
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.660 100,000.00
2 Tukang Kayu L.02 OH 0.330 125,000.00
3 Kepala Tukang L.03 OH 0.033 150,000.00
4 Mandor L.04 OH 0.033 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.040 1,800,000.00
2 Paku biasa 2" - 5" kg 0.400 18,000.00
3 Minyak bekisting liter 0.200 27,500.00
4 Kayu gergajian kelas II, balok m3 0.015 2,500,000.00
5 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 0.350 150,000.00
6 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 6.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.25 Membuat 1 m2 bekisting untuk dinding


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.660 100,000.00
2 Tukang Kayu L.02 OH 0.330 125,000.00
3 Kepala Tukang L.03 OH 0.033 150,000.00
4 Mandor L.04 OH 0.033 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.030 1,800,000.00
2 Paku biasa 2" - 5" kg 0.400 18,000.00
3 Minyak bekisting liter 0.200 27,500.00
4 Kayu gergajian kelas II, balok m3 0.020 2,500,000.00
5 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 0.350 150,000.00
6 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 3.000 5,000.00

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.26 Membuat 1 m2 bekisting untuk tangga


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.660 100,000.00
2 Tukang Kayu L.02 OH 0.330 125,000.00
3 Kepala Tukang L.03 OH 0.033 150,000.00
4 Mandor L.04 OH 0.033 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.030 1,800,000.00
2 Paku biasa 2" - 5" kg 0.400 18,000.00
3 Minyak bekisting liter 0.150 27,500.00
4 Kayu gergajian kelas II, balok m3 0.015 2,500,000.00
5 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 0.350 150,000.00
6 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 2.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.150 100,000.00
2 Tukang Kayu L.02 OH 0.050 125,000.00
3 Kepala Tukang L.03 OH 0.005 150,000.00
4 Mandor L.04 OH 0.008 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.026 1,800,000.00
2 Paku biasa 2" - 5" kg 0.600 18,000.00
3 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 0.500 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 5.300 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.300 125,000.00
4 Tukang besi / tukang las L.02 OH 1.050 125,000.00
5 Kepala Tukang L.03 OH 0.262 150,000.00
6 Mandor L.04 OH 0.265 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.200 1,800,000.00
2 Paku biasa 2" - 5" kg 1.500 18,000.00
3 Minyak bekisting liter 0.400 27,500.00
4 Besi beton kg 157.500 11,131.34
5 Kawat beton kg 2.250 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.29 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting)


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 5.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.560 125,000.00
4 Tukang besi / tukang las L.02 OH 1.400 125,000.00
5 Kepala Tukang L.03 OH 0.323 150,000.00
6 Mandor L.04 OH 0.283 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.270 1,800,000.00
2 Paku biasa 2" - 5" kg 2.000 18,000.00
3 Minyak bekisting liter 0.600 27,500.00
4 Besi beton kg 210.000 11,131.34
5 Kawat beton kg 3.000 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.30 Membuat 1 m3 Kolom beton bertulang (300 kg besi + bekisting)
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 7.050 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.650 125,000.00
4 Tukang besi / tukang las L.02 OH 2.100 125,000.00
5 Kepala Tukang L.03 OH 0.403 150,000.00
6 Mandor L.04 OH 0.353 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.400 1,800,000.00
2 Paku biasa 2" - 5" kg 4.000 18,000.00
3 Minyak bekisting liter 2.000 27,500.00
4 Besi beton kg 315.000 11,131.34
5 Kawat beton kg 4.500 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
9 Kayu gergajian kelas II, balok m3 0.150 2,500,000.00
10 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 3.500 150,000.00
11 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 20.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.31 Membuat 1 m3 Balok beton bertulang (200 kg besi + bekisting)


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 6.350 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.650 125,000.00
4 Tukang besi / tukang las L.02 OH 1.400 125,000.00
5 Kepala Tukang L.03 OH 0.333 150,000.00
6 Mandor L.04 OH 0.318 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.320 1,800,000.00
2 Paku biasa 2" - 5" kg 3.200 18,000.00
3 Minyak bekisting liter 1.600 27,500.00
4 Besi beton kg 210.000 11,131.34
5 Kawat beton kg 3.000 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
9 Kayu gergajian kelas II, balok m3 0.140 2,500,000.00
10 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 2.800 150,000.00
11 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 16.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.32 Membuat 1 m3 Kolom beton bertulang (150 kg besi + bekisting)


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 5.300 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.300 125,000.00
4 Tukang besi / tukang las L.02 OH 1.050 125,000.00
5 Kepala Tukang L.03 OH 0.265 150,000.00
6 Mandor L.04 OH 0.265 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.320 1,800,000.00
2 Paku biasa 2" - 5" kg 3.200 18,000.00
3 Minyak bekisting liter 1.600 27,500.00
4 Besi beton kg 157.500 11,131.34
5 Kawat beton kg 2.250 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
9 Kayu gergajian kelas II, balok m3 0.120 2,500,000.00
10 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 2.800 150,000.00
11 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 32.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
A. 4.1.1.33 Membuat 1 m3 Dinding beton bertulang (150 kg besi + bekisting)
Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 5.300 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.300 125,000.00
4 Tukang besi / tukang las L.02 OH 1.050 125,000.00
5 Kepala Tukang L.03 OH 0.262 150,000.00
6 Mandor L.04 OH 0.265 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.240 1,800,000.00
2 Paku biasa 2" - 5" kg 3.200 18,000.00
3 Minyak bekisting liter 1.600 27,500.00
4 Besi beton kg 157.500 11,131.34
5 Kawat beton kg 2.250 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
9 Kayu gergajian kelas II, balok m3 0.160 2,500,000.00
10 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 2.800 150,000.00
11 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 24.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.34 Membuat 1 m3 Dinding beton bertulang (200 kg besi + bekisting)


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 5.650 100,000.00
2 Tukang Batu L.02 OH 0.275 125,000.00
3 Tukang Kayu L.02 OH 1.560 125,000.00
4 Tukang besi / tukang las L.02 OH 1.400 125,000.00
5 Kepala Tukang L.03 OH 0.323 150,000.00
6 Mandor L.04 OH 0.283 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.250 1,800,000.00
2 Paku biasa 2" - 5" kg 3.000 18,000.00
3 Minyak bekisting liter 1.200 27,500.00
4 Besi beton kg 210.000 11,131.34
5 Kawat beton kg 3.000 25,000.00
6 Semen PC @ 50 kg kg 336.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.540 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.810 400,000.00
9 Kayu gergajian kelas II, balok m3 0.105 2,500,000.00
10 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 2.500 150,000.00
11 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau batang 14.000 5,000.00
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.35 Membuat 1 m1 Kolom praktis beton bertulang (11 x 11) cm


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.180 100,000.00
2 Tukang Batu L.02 OH 0.020 125,000.00
3 Tukang Kayu L.02 OH 0.020 125,000.00
4 Tukang besi / tukang las L.02 OH 0.020 125,000.00
5 Kepala Tukang L.03 OH 0.006 150,000.00
6 Mandor L.04 OH 0.009 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.002 1,800,000.00
2 Paku biasa 2" - 5" kg 0.010 18,000.00
3 Minyak bekisting liter 0.000 27,500.00
4 Besi beton kg 3.000 11,131.34
5 Kawat beton kg 0.450 25,000.00
6 Semen PC @ 50 kg kg 4.000 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.006 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.009 400,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)

A. 4.1.1.36 Membuat 1 m1 Ring balok beton bertulang (10 x 15) cm


Harga Satuan
No. Uraian Kode Satuan Koefisien
(RP)
A. TENAGA
1 Pekerja L.01 OH 0.297 100,000.00
2 Tukang Batu L.02 OH 0.033 125,000.00
3 Tukang Kayu L.02 OH 0.033 125,000.00
4 Tukang besi / tukang las L.02 OH 0.033 125,000.00
5 Kepala Tukang L.03 OH 0.010 150,000.00
6 Mandor L.04 OH 0.015 150,000.00
JUMLAH TENAGA KERJA
B. BAHAN
1 Kayu gergajian kelas III, papan m3 0.003 1,800,000.00
2 Paku biasa 2" - 5" kg 0.020 18,000.00
3 Minyak bekisting liter 0.000 27,500.00
4 Besi beton kg 3.600 11,131.34
5 Kawat beton kg 0.050 25,000.00
6 Semen PC @ 50 kg kg 5.500 1,320.00
7 Pasir ayak untuk beton (m3) m3 0.009 52,125.00
8 Batu pecah 2 - 3 (cm) m3 0.015 400,000.00
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A+B+C)
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
-
203,575.00

370,500.00
32,354.73
296,000.00
10,750.00
709,604.73

-
913,179.73
91,317.97
1,004,497.71

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

364,320.00
30,828.21
299,851.85
10,750.00
705,750.07

-
921,775.07
92,177.51
1,013,952.57

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00
394,680.00
29,748.48
301,333.33
10,750.00
736,511.82

-
952,536.82
95,253.68
1,047,790.50
lump (3-6) cm, w/c = 0,97
Jumlah Harga
(RP)

120,000.00
25,000.00
3,000.00
9,000.00
157,000.00

303,600.00
33,248.30
304,296.30
10,000.00
651,144.60

-
808,144.60
80,814.46
888,959.06

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

430,320.00
28,296.43
304,888.89
10,750.00
774,255.32

-
990,280.32
99,028.03
1,089,308.35

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

464,640.00
27,216.70
305,481.48
10,750.00
808,088.18

-
1,024,113.18
102,411.32
1,126,524.50
Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

489,720.00
25,988.04
310,222.22
10,750.00
836,680.26

-
1,052,705.26
105,270.53
1,157,975.78

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

506,880.00
25,764.64
307,851.85
10,750.00
851,246.49

-
1,067,271.49
106,727.15
1,173,998.64

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

535,920.00
25,466.79
304,000.00
10,750.00
876,136.79

-
1,092,161.79
109,216.18
1,201,377.96

Jumlah Harga
(RP)

165,000.00
34,375.00
4,200.00
12,450.00
216,025.00

545,160.00
25,355.09
302,518.52
10,750.00
883,783.61

-
1,099,808.61
109,980.86
1,209,789.47
Jumlah Harga
(RP)

210,000.00
43,750.00
5,250.00
15,750.00
274,750.00

579,480.00
24,945.54
298,074.07
10,750.00
913,249.61

-
1,187,999.61
118,799.96
1,306,799.57

Jumlah Harga
(RP)

210,000.00
43,750.00
5,250.00
15,750.00
274,750.00

591,360.00
24,833.84
296,296.30
10,750.00
923,240.14

-
1,197,990.14
119,799.01
1,317,789.15

Jumlah Harga
(RP)

7,000.00
8,750.00
1,050.00
600.00
17,400.00

116,879.10
3,750.00
120,629.10

-
138,029.10
13,802.91
151,832.01
15,183.20

Jumlah Harga
(RP)

5,000.00
6,250.00
750.00
450.00
12,450.00

136,500.00
2,500.00
139,000.00

-
151,450.00
15,145.00
166,595.00
16,659.50
Jumlah Harga
(RP)

2,500.00
3,125.00
3,750.00
150.00
9,525.00

125,615.76
1,250.00
126,865.76

-
136,390.76
13,639.08
150,029.84
15,002.98

Jumlah Harga
(RP)

2,500.00
3,125.00
3,750.00
150.00
9,525.00

138,917.26
1,250.00
140,167.26

-
149,692.26
14,969.23
164,661.49
16,466.15

Jumlah Harga
(RP)

2,500.00
3,125.00
3,750.00
150.00
9,525.00

143,011.22
1,250.00
144,261.22
-
153,786.22
15,378.62
169,164.84
16,916.48

Jumlah Harga
(RP)

52,000.00
32,500.00
3,900.00
3,900.00
92,300.00

72,000.00
5,400.00
2,750.00
80,150.00

-
172,450.00
17,245.00
189,695.00
Jumlah Harga
(RP)

52,000.00
32,500.00
3,900.00
3,900.00
92,300.00

81,000.00
5,400.00
2,750.00
89,150.00

-
181,450.00
18,145.00
199,595.00

Jumlah Harga
(RP)

66,000.00
41,250.00
4,950.00
4,950.00
117,150.00

72,000.00
7,200.00
5,500.00
37,500.00
52,500.00
10,000.00
184,700.00

-
301,850.00
30,185.00
332,035.00

Jumlah Harga
(RP)

66,000.00
41,250.00
4,950.00
4,950.00
117,150.00

72,000.00
7,200.00
5,500.00
45,000.00
52,500.00
10,000.00
192,200.00

-
309,350.00
30,935.00
340,285.00
Jumlah Harga
(RP)

66,000.00
41,250.00
4,950.00
4,950.00
117,150.00

72,000.00
7,200.00
5,500.00
37,500.00
52,500.00
30,000.00
204,700.00

-
321,850.00
32,185.00
354,035.00

Jumlah Harga
(RP)

66,000.00
41,250.00
4,950.00
4,950.00
117,150.00

54,000.00
7,200.00
5,500.00
50,000.00
52,500.00
15,000.00

184,200.00

-
301,350.00
30,135.00
331,485.00

Jumlah Harga
(RP)

66,000.00
41,250.00
4,950.00
4,950.00
117,150.00
54,000.00
7,200.00
4,125.00
37,500.00
52,500.00
10,000.00
165,325.00

-
282,475.00
28,247.50
310,722.50
Jumlah Harga
(RP)

15,000.00
6,250.00
750.00
1,200.00
23,200.00

47,520.00
10,800.00
2,500.00
60,820.00

-
84,020.00
8,402.00
92,422.00

Jumlah Harga
(RP)

530,000.00
34,375.00
162,500.00
131,250.00
39,300.00
39,750.00
937,175.00

360,000.00
27,000.00
11,000.00
1,753,186.43
56,250.00
443,520.00
28,147.50
324,000.00
3,003,103.93

-
3,940,278.93
394,027.89
4,334,306.83

Jumlah Harga
(RP)

565,000.00
34,375.00
195,000.00
175,000.00
48,450.00
42,450.00
1,060,275.00

486,000.00
36,000.00
16,500.00
2,337,581.91
75,000.00
443,520.00
28,147.50
324,000.00
3,746,749.41

-
4,807,024.41
480,702.44
5,287,726.85
Jumlah Harga
(RP)

705,000.00
34,375.00
206,250.00
262,500.00
60,450.00
52,950.00
1,321,525.00

720,000.00
72,000.00
55,000.00
3,506,372.87
112,500.00
443,520.00
28,147.50
324,000.00
375,000.00
525,000.00
100,000.00
6,261,540.37

-
7,583,065.37
758,306.54
8,341,371.90

Jumlah Harga
(RP)

635,000.00
34,375.00
206,250.00
175,000.00
49,950.00
47,700.00
1,148,275.00

576,000.00
57,600.00
44,000.00
2,337,581.91
75,000.00
443,520.00
28,147.50
324,000.00
350,000.00
420,000.00
80,000.00
4,735,849.41

-
5,884,124.41
588,412.44
6,472,536.85

Jumlah Harga
(RP)

530,000.00
34,375.00
162,500.00
131,250.00
39,750.00
39,750.00
937,625.00

576,000.00
57,600.00
44,000.00
1,753,186.43
56,250.00
443,520.00
28,147.50
324,000.00
300,000.00
420,000.00
160,000.00
4,162,703.93

-
5,100,328.93
510,032.89
5,610,361.83
Jumlah Harga
(RP)

530,000.00
34,375.00
162,500.00
131,250.00
39,300.00
39,750.00
937,175.00

432,000.00
57,600.00
44,000.00
1,753,186.43
56,250.00
443,520.00
28,147.50
324,000.00
400,000.00
420,000.00
120,000.00
4,078,703.93

-
5,015,878.93
501,587.89
5,517,466.83

Jumlah Harga
(RP)

565,000.00
34,375.00
195,000.00
175,000.00
48,450.00
42,450.00
1,060,275.00

450,000.00
54,000.00
33,000.00
2,337,581.91
75,000.00
443,520.00
28,147.50
324,000.00
262,500.00
375,000.00
70,000.00
4,452,749.41
-
5,513,024.41
551,302.44
6,064,326.85

Jumlah Harga
(RP)

18,000.00
2,500.00
2,500.00
2,500.00
900.00
1,350.00
27,750.00

3,600.00
180.00
-
33,394.03
11,250.00
5,280.00
312.75
3,600.00
57,616.78

-
85,366.78
8,536.68
93,903.46

Jumlah Harga
(RP)

29,700.00
4,125.00
4,125.00
4,125.00
1,500.00
2,250.00
45,825.00

5,400.00
360.00
-
40,072.83
1,250.00
7,260.00
469.13
6,000.00
60,811.96

-
106,636.96
10,663.70
117,300.65
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A. 4.4.1.1 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1 batu, camp. 1 SP : 2PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.600 100,000.00 60,000.00
2 Tukang Batu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L,04 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 92,500.00
B. BAHAN
1 Batu bata merah (lokal) buah 96.000 1,600.00 153,600.00
2 Semen PC @ 50 kg kg 43.500 1,320.00 57,420.00
3 Pasir pasang m3 0.080 52,125.00 4,170.00
JUMLAH HARGA BAHAN 215,190.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 307,690.00
E. Profit 10% xD 30,769.00
F. Harga Satuan Pekerjaan (D+E) 338,459.00

A. 4.4.1.2 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1 batu, camp. 1 SP : 3PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.600 100,000.00 60,000.00
2 Tukang Batu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L,04 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 92,500.00
B. BAHAN
1 Batu bata merah (lokal) buah 96.000 1,600.00 153,600.00
2 Semen PC @ 50 kg kg 32.950 1,320.00 43,494.00
3 Pasir pasang m3 0.091 52,125.00 4,743.38
JUMLAH HARGA BAHAN 201,837.38
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 294,337.38
E. Profit 10% xD 29,433.74
F. Harga Satuan Pekerjaan (D+E) 323,771.11

A. 4.4.1.3 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1 batu, camp. 1 SP : 4PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.600 100,000.00 60,000.00
2 Tukang Batu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L,04 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 92,500.00
B. BAHAN
1 Batu bata merah (lokal) buah 96.000 1,600.00 153,600.00
2 Semen PC @ 50 kg kg 26.550 1,320.00 35,046.00
3 Pasir pasang m3 0.093 52,125.00 4,847.63
JUMLAH HARGA BAHAN 193,493.63
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 285,993.63
E. Profit 10% xD 28,599.36
F. Harga Satuan Pekerjaan (D+E) 314,592.99
A. 4.4.1.4 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1 batu, camp. 1 SP : 5PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.600 100,000.00 60,000.00
2 Tukang Batu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L,04 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 92,500.00
B. BAHAN
1 Batu bata merah (lokal) buah 96.000 1,600.00 153,600.00
2 Semen PC @ 50 kg kg 22.220 1,320.00 29,330.40
3 Pasir pasang m3 0.102 52,125.00 5,316.75
JUMLAH HARGA BAHAN 188,247.15
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 280,747.15
E. Profit 10% xD 28,074.72
F. Harga Satuan Pekerjaan (D+E) 308,821.87

A. 4.4.1.5 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1 batu, camp. 1 SP : 6PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.600 100,000.00 60,000.00
2 Tukang Batu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L,04 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 92,500.00
B. BAHAN
1 Batu bata merah (lokal) buah 96.000 1,600.00 153,600.00
2 Semen PC @ 50 kg kg 18.500 1,320.00 24,420.00
3 Pasir pasang m3 0.122 52,125.00 6,359.25
JUMLAH HARGA BAHAN 184,379.25
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 276,879.25
E. Profit 10% xD 27,687.93
F. Harga Satuan Pekerjaan (D+E) 304,567.18

A. 4.4.1.7 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1/2 batu, camp. 1 SP : 2PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Tukang Batu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L,04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,250.00
B. BAHAN
1 Batu bata merah (lokal) buah 45.000 1,600.00 72,000.00
2 Semen PC @ 50 kg kg 18.950 1,320.00 25,014.00
3 Pasir pasang m3 0.038 52,125.00 1,980.75
JUMLAH HARGA BAHAN 98,994.75
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 145,244.75
E. Profit 10% xD 14,524.48
F. Harga Satuan Pekerjaan (D+E) 159,769.23
A. 4.4.1.8 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1/2 batu, camp. 1 SP : 3PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Tukang Batu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L,04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,250.00
B. BAHAN
1 Batu bata merah (lokal) buah 45.000 1,600.00 72,000.00
2 Semen PC @ 50 kg kg 14.370 1,320.00 18,968.40
3 Pasir pasang m3 0.040 52,125.00 2,085.00
JUMLAH HARGA BAHAN 93,053.40
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 139,303.40
E. Profit 10% xD 13,930.34
F. Harga Satuan Pekerjaan (D+E) 153,233.74

A. 4.4.1.9 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1/2 batu, camp. 1 SP : 4PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Tukang Batu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L,04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,250.00
B. BAHAN
1 Batu bata merah (lokal) buah 45.000 1,600.00 72,000.00
2 Semen PC @ 50 kg kg 11.500 1,320.00 15,180.00
3 Pasir pasang m3 0.043 52,125.00 2,241.38
JUMLAH HARGA BAHAN 89,421.38
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 135,671.38
E. Profit 10% xD 13,567.14
F. Harga Satuan Pekerjaan (D+E) 149,238.51

A. 4.4.1.10 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1/2 batu, camp. 1 SP : 5PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Tukang Batu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L,04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,250.00
B. BAHAN
1 Batu bata merah (lokal) buah 45.000 1,600.00 72,000.00
2 Semen PC @ 50 kg kg 9.680 1,320.00 12,777.60
3 Pasir pasang m3 0.045 52,125.00 2,345.63
JUMLAH HARGA BAHAN 87,123.23
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 133,373.23
E. Profit 10% xD 13,337.32
F. Harga Satuan Pekerjaan (D+E) 146,710.55

A. 4.4.1.11 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1/2 batu, camp. 1 SP : 6PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Tukang Batu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L,04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,250.00
B. BAHAN
1 Batu bata merah (lokal) buah 45.000 1,600.00 72,000.00
2 Semen PC @ 50 kg kg 8.320 1,320.00 10,982.40
3 Pasir pasang m3 0.049 52,125.00 2,554.13
JUMLAH HARGA BAHAN 85,536.53
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 131,786.53
E. Profit 10% xD 13,178.65
F. Harga Satuan Pekerjaan (D+E) 144,965.18
A. 4.4.1.12 Pemasangan 1 m2 dinding bata merah (8x8x20) cm tebal 1/2 batu, camp. 1 SP : 8PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Tukang Batu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L,04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,250.00
B. BAHAN
1 Batu bata merah (lokal) buah 45.000 1,600.00 72,000.00
2 Semen PC @ 50 kg kg 6.500 1,320.00 8,580.00
3 Pasir pasang m3 0.050 52,125.00 2,606.25
JUMLAH HARGA BAHAN 83,186.25
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 129,436.25
E. Profit 10% xD 12,943.63
F. Harga Satuan Pekerjaan (D+E) 142,379.88

Dihit. Pemasangan 1 m2 dinding batako uk. 15 x 30 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.0833 100,000.00 8,330.00
2 Tukang Batu L.02 OH 0.0833 125,000.00 10,412.50
3 Kepala tukang L.03 OH 0.0083 150,000.00 1,245.00
4 Mandor L,04 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 21,187.50
B. BAHAN
1 Batako bh 18.000 1,625.00 29,250.00
2 Semen PC @ 50 kg Kg 7.238 1,320.00 9,554.69
3 Pasir pasang m3 0.028 52,125.00 1,451.16
JUMLAH HARGA BAHAN 40,255.85
C. PERALATAN
Peralatan % 10.000 - -

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 61,443.35
E. Profit 10% xD 6,144.33
F. Harga Satuan Pekerjaan (D+E) 67,587.68
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A. 2.2.1.1 Pembuatan 1 m2 Pagar sementara dari kayu tinggi 2 meter
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.400 100,000.00 40,000.00
2 Tukang Kayu L.02 OH 0.200 125,000.00 25,000.00
3 Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L.04 OH 0.020 150,000.00 3,000.00
JUMLAH TENAGA KERJA 71,000.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 1.250 5,000.00 6,250.00
2 Semen PC @ 50 kg kg 5.000 1,320.00 6,600.00
3 Pasir ayak untuk beton (m3) m3 0.005 52,125.00 260.63
4 Batu pecah 2 - 3 (cm) m3 0.009 400,000.00 3,600.00
5 Kayu gergajian kelas IV, balok m3 0.072 1,500,000.00 108,000.00
6 Paku biasa 2" - 5" kg 0.060 18,000.00 1,080.00
7 Residu atau Ter ltr 0.400 50,000.00 20,000.00
JUMLAH HARGA BAHAN 145,790.63
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 216,790.63
E. Profit 10% xD 21,679.06
F. Harga Satuan Pekerjaan (D+E) 238,469.69

A. 2.2.1.2 Pembuatan 1 m2 Pagar sementara dari seng gelombang tinggi 2 meter


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.200 100,000.00 20,000.00
2 Tukang Kayu L.02 OH 0.400 125,000.00 50,000.00
3 Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L.04 OH 0.020 150,000.00 3,000.00
JUMLAH TENAGA KERJA 76,000.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 1.250 5,000.00 6,250.00
2 Atap seng gelombang bjls 20 uk. 0,914 x 1, lbr 1.200 36,000.00 43,200.00
3 Semen PC @ 50 kg kg 2.500 1,320.00 3,300.00
4 Pasir ayak untuk beton (m3) m3 0.005 52,125.00 260.63
5 Batu pecah 2 - 3 (cm) m3 0.009 400,000.00 3,600.00
6 Kayu gergajian kelas IV, balok m3 0.072 1,500,000.00 108,000.00
7 Paku biasa 2" - 5" kg 0.060 18,000.00 1,080.00
8 Cat menie ltr 0.450 42,500.00 19,125.00
JUMLAH HARGA BAHAN 184,815.63
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 260,815.63
E. Profit 10% xD 26,081.56
F. Harga Satuan Pekerjaan (D+E) 286,897.19

A. 2.2.1.3 Pembuatan 1 m2 Pagar sementara dari kawat duri tinggi 1,8 meter
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.200 100,000.00 20,000.00
2 Tukang Kayu L.02 OH 0.300 125,000.00 37,500.00
3 Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L.04 OH 0.020 150,000.00 3,000.00
JUMLAH TENAGA KERJA 63,500.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 1.000 5,000.00 5,000.00
2 Kawat berduri kg 25.000 27,812.50 695,312.50
3 Semen PC @ 50 kg kg 2.000 1,320.00 2,640.00
4 Pasir ayak untuk beton (m3) m3 0.005 52,125.00 260.63
5 Batu pecah 2 - 3 (cm) m3 0.009 400,000.00 3,600.00
6 Paku biasa 2" - 5" kg 0.060 18,000.00 1,080.00
JUMLAH HARGA BAHAN 707,893.13
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 771,393.13
E. Profit 10% xD 77,139.31
F. Harga Satuan Pekerjaan (D+E) 848,532.44
A. 2.2.1.4 Pengukuran dan pemasangan 1 m' bouwplank
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.100 100,000.00 10,000.00
2 Tukang Kayu L.02 OH 0.100 125,000.00 12,500.00
3 Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
4 Mandor L.04 OH 0.005 150,000.00 750.00
JUMLAH TENAGA KERJA 24,750.00
B. BAHAN
1 Kayu gergajian kelas IV, balok m3 0.012 1,500,000.00 18,000.00
2 Paku biasa 2" - 5" Kg 0.020 18,000.00 360.00
3 Kayu gergajian kelas IV, papan m3 0.007 1,500,000.00 10,500.00
JUMLAH HARGA BAHAN 28,860.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 53,610.00
E. Profit 10% xD 5,361.00
F. Harga Satuan Pekerjaan (D+E) 58,971.00

A. 2.2.1.5 Pembuatan 1 m2 kantor sementara lantai plesteran


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.000 100,000.00 200,000.00
2 Tukang Kayu L.02 OH 2.000 125,000.00 250,000.00
3 Tukang Batu L.02 OH 1.000 125,000.00 125,000.00
4 Kepala Tukang L.03 OH 0.300 150,000.00 45,000.00
5 Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 627,500.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 1.250 5,000.00 6,250.00
2 Kayu gergajian kelas IV, papan m3 0.180 1,500,000.00 270,000.00
3 Paku biasa 2" - 5" kg 0.080 18,000.00 1,440.00
4 Besi strip kg 1.100 13,000.00 14,300.00
5 Semen PC @ 50 kg kg 35.000 1,320.00 46,200.00
6 Pasir pasang m3 0.150 52,125.00 7,818.75
7 Pasir ayak untuk beton (m3) m3 0.100 52,125.00 5,212.50
8 Batu pecah 2 - 3 (cm) m3 0.150 400,000.00 60,000.00
9 Batu bata merah (lokal) bh 30.000 1,600.00 48,000.00
10 Seng plat BJLS 27 uk. 0.9 x 1.83 (m) Lbr 0.250 40,850.00 10,212.50
11 Jendela nako (kerangka) bh 0.200 159,000.00 31,800.00
12 Kaca bening tebal 3 mm m2 0.080 112,000.00 8,960.00
13 Kunci tanam bh 0.150 127,500.00 19,125.00
14 Plywood uk. 1,22 x 2,44 (m), tebal 4 mm Lbr 0.060 57,500.00 3,450.00
JUMLAH HARGA BAHAN 532,768.75
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 1,160,268.75
E. Profit 10% xD 116,026.88
F. Harga Satuan Pekerjaan (D+E) 1,276,295.63

A. 2.2.1.6 Pembuatan 1 m2 rumah jaga (konstruksi kayu)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.000 100,000.00 100,000.00
2 Tukang Kayu L.02 OH 1.500 125,000.00 187,500.00
3 Kepala Tukang L.03 OH 0.150 150,000.00 22,500.00
4 Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 317,500.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 3.000 5,000.00 15,000.00
2 Kayu gergajian kelas IV, papan m3 0.276 1,500,000.00 414,000.00
3 Paku biasa 2" - 5" kg 0.700 18,000.00 12,600.00
4 Atap seng gelombang bjls 20 uk. 0,914 x 1, Lbr 1.500 36,000.00 54,000.00
JUMLAH HARGA BAHAN 495,600.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 813,100.00
E. Profit 10% xD 81,310.00
F. Harga Satuan Pekerjaan (D+E) 894,410.00
A. 2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.000 100,000.00 100,000.00
2 Tukang Kayu L.02 OH 2.000 125,000.00 250,000.00
3 Kepala Tukang L.03 OH 0.200 150,000.00 30,000.00
4 Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 387,500.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 1.700 5,000.00 8,500.00
2 Kayu gergajian kelas IV, papan m3 0.210 1,500,000.00 315,000.00
3 Paku biasa 2" - 5" kg 0.300 18,000.00 5,400.00
4 Semen PC @ 50 kg kg 10.500 1,320.00 13,860.00
5 Pasir ayak untuk beton (m3) m3 0.030 52,125.00 1,563.75
6 Batu pecah 2 - 3 (cm) m3 0.050 400,000.00 20,000.00
7 Atap seng gelombang bjls 20 uk. 0,914 x 1, Lbr 1.500 36,000.00 54,000.00
8 Seng plat BJLS 27 uk. 0.9 x 1.83 (m) Lbr 0.250 40,850.00 10,212.50
JUMLAH HARGA BAHAN 428,536.25
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 816,036.25
E. Profit 10% xD 81,603.63
F. Harga Satuan Pekerjaan (D+E) 897,639.88

A. 2.2.1.8 Pembuatan 1 m2 bedeng pekerja


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.000 100,000.00 100,000.00
2 Tukang Kayu L.02 OH 2.000 125,000.00 250,000.00
3 Kepala Tukang L.03 OH 0.200 150,000.00 30,000.00
4 Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 387,500.00
B. BAHAN
1 Kayu dolken ø 3 - 6 (cm) panjang 4 m / kiau btg 1.250 5,000.00 6,250.00
2 Kayu gergajian kelas IV, papan m3 0.186 1,500,000.00 279,000.00
3 Paku biasa 2" - 5" kg 0.300 18,000.00 5,400.00
4 Semen PC @ 50 kg kg 18.000 1,320.00 23,760.00
5 Pasir ayak untuk beton (m3) m3 0.030 52,125.00 1,563.75
6 Batu pecah 2 - 3 (cm) m3 0.050 400,000.00 20,000.00
7 Atap seng gelombang bjls 20 uk. 0,914 x 1, Lbr 1.500 36,000.00 54,000.00
8 Plywood uk. 1,22 x 2,44 (m), tebal 4 mm Lbr 1.350 57,500.00 77,625.00
JUMLAH HARGA BAHAN 467,598.75
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 855,098.75
E. Profit 10% xD 85,509.88
F. Harga Satuan Pekerjaan (D+E) 940,608.63

A. 2.2.1.9 Pembersihan 1 m2 lapangan dan perataan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.100 100,000.00 10,000.00
2 Mandor L.04 OH 0.050 -
JUMLAH TENAGA KERJA 10,000.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 10,000.00
E. Profit 10% xD 1,000.00
F. Harga Satuan Pekerjaan (D+E) 11,000.00

A. 2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Tukang Kayu L.02 OH 0.300 125,000.00 37,500.00
2 Kepala Tukang L.03 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 42,000.00
B. BAHAN
1 Kayu gergajian kelas IV, papan btg 0.036 1,500,000.00 54,000.00
2 Paku biasa 2" - 5" m3 0.080 18,000.00 1,440.00
JUMLAH HARGA BAHAN 55,440.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 97,440.00
E. Profit 10% xD 9,744.00
F. Harga Satuan Pekerjaan (D+E) 107,184.00
A. 2.2.1.12 Pembuatan 1 m2 jalan sementara
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.000 100,000.00 100,000.00
2 Mandor L.04 OH 0.005 150,000.00 750.00
JUMLAH TENAGA KERJA 100,750.00
B. BAHAN
1 Batu belah btg 0.150 325,000.00 48,750.00
2 Batu pecah 2 - 3 (cm) m3 0.090 400,000.00 36,000.00
3 Pasir urug / timbun kg 0.010 50,000.00 500.00
JUMLAH HARGA BAHAN 85,250.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 186,000.00
E. Profit 10% xD 18,600.00
F. Harga Satuan Pekerjaan (D+E) 204,600.00

A. 2.2.1.13 Pembongkaran 1 m3 beton bertulang


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 13.334 100,000.00 1,333,400.00
2 Mandor L.04 OH 0.666 150,000.00 99,900.00
JUMLAH TENAGA KERJA 1,433,300.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 1,433,300.00
E. Profit 10% xD 143,330.00
F. Harga Satuan Pekerjaan (D+E) 1,576,630.00

A. 2.2.1.14 Pembongkaran 1 m3 dinding tembok bata


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 6.667 100,000.00 666,700.00
2 Mandor L.04 OH 0.333 150,000.00 49,950.00
JUMLAH TENAGA KERJA 716,650.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 716,650.00
E. Profit 10% xD 71,665.00
F. Harga Satuan Pekerjaan (D+E) 788,315.00

A. 2.2.1.16 Pembuatan 1 m2 panel beton pracetak 5x40x240 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.375 100,000.00 37,500.00
2 Tukang batu L.02 OH 0.125 125,000.00 15,625.00
3 Kepala Tukang L.03 OH 0.012 150,000.00 1,800.00
4 Mandor L.04 OH 0.019 150,000.00 2,850.00
JUMLAH TENAGA KERJA 57,775.00
B. BAHAN
1 Panel beton pracetak Lbr 0.986 130,000.00 128,180.00
2 Kolom beton pracetak btg 0.525 245,000.00 128,625.00
3 Semen PC @ 50 kg kg 45.000 1,320.00 59,400.00
4 Pasir ayak untuk beton (m3) m3 0.074 52,125.00 3,857.25
5 Batu pecah 2 - 3 (cm) m3 0.146 400,000.00 58,400.00
JUMLAH HARGA BAHAN 378,462.25
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 436,237.25
E. Profit 10% xD 43,623.73
F. Harga Satuan Pekerjaan (D+E) 479,860.98
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
A. 4.7.1.1 1 m2 Pengikisan/ pengerokan permukaan cat lama
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.015 100,000.00 1,500.00
2 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 1,950.00
B. BAHAN
1 Soda api kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 900.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 2,850.00
E. Profit 10% * D 285.00
F. Harga Satuan Pekerjaan (D+E) 3,135.00

A. 4.7.1.2 1 m2 Pencucian bidang permukaan tembok yang pernah dicat


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.015 100,000.00 1,500.00
2 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 1,950.00
B. BAHAN
1 Sabun kg 0.050 15,000.00 750.00
JUMLAH HARGA BAHAN 750.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 2,700.00
E. Profit 10% * D 270.00
F. Harga Satuan Pekerjaan (D+E) 2,970.00

A. 4.7.1.3 1 m2 Pengerokan karat pada permukaan baja cara manual


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.015 100,000.00 1,500.00
2 Mandor L.04 OH 0.008 150,000.00 1,200.00
JUMLAH TENAGA KERJA 2,700.00
B. BAHAN
1 Sabun kg 0.050 15,000.00 750.00
JUMLAH HARGA BAHAN 750.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 3,450.00
E. Profit 10% * D 345.00
F. Harga Satuan Pekerjaan (D+E) 3,795.00

A. 4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.070 100,000.00 7,000.00
2 Tukang cat L.02 OH 0.009 120,000.00 1,080.00
3 Kepala Tukang L.03 OH 0.006 150,000.00 900.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 9,430.00
B. BAHAN
1 Cat menie kg 0.200 42,500.00 8,500.00
2 Plamuer tembok kg 0.150 10,000.00 1,500.00
3 Cat dasar kg 0.170 24,250.00 4,122.50
4 Cat minyak kg 0.260 58,750.00 15,275.00
5 Kuas bh 0.010 13,350.00 133.50
6 Thinner kg 0.030 30,000.00 900.00
7 Ampelas lbr 0.200 5,000.00 1,000.00
JUMLAH HARGA BAHAN 31,431.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 40,861.00
E. Profit 10% * D 4,086.10
F. Harga Satuan Pekerjaan (D+E) 44,947.10
A. 4.7.1.5 1 m2 Pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.070 100,000.00 7,000.00
2 Tukang cat L.02 OH 0.105 120,000.00 12,600.00
3 Kepala Tukang L.03 OH 0.004 150,000.00 600.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 20,650.00
B. BAHAN
1 Cat menie kg 0.200 42,500.00 8,500.00
2 Plamuer tembok kg 0.150 10,000.00 1,500.00
3 Cat dasar kg 0.170 24,250.00 4,122.50
4 Cat minyak kg 0.350 58,750.00 20,562.50
5 Kuas bh 0.010 13,350.00 133.50
6 Thinner kg 0.030 30,000.00 900.00
7 Ampelas lbr 0.200 5,000.00 1,000.00
JUMLAH HARGA BAHAN 36,718.50
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 57,368.50
E. Profit 10% * D 5,736.85
F. Harga Satuan Pekerjaan (D+E) 63,105.35

A. 4.7.1.6 Pelaburan 1 m2 bidang kayu degan teak oil


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.040 100,000.00 4,000.00
2 Tukang cat L.02 OH 0.063 120,000.00 7,560.00
3 Kepala Tukang L.03 OH 0.063 150,000.00 9,450.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 21,460.00
B. BAHAN
1 Teak Oil liter 0.360 3,500.00 1,260.00
JUMLAH HARGA BAHAN 1,260.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 22,720.00
E. Profit 10% * D 2,272.00
F. Harga Satuan Pekerjaan (D+E) 24,992.00

A. 4.7.1.8 Pelaburan 1 M2 bidang kayu cat residu dan cat


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.100 100,000.00 10,000.00
2 Mandor L.04 OH 0.006 150,000.00 900.00
JUMLAH TENAGA KERJA 10,900.00
B. BAHAN
1 Residu atau ter liter 0.350 50,000.00 17,500.00
JUMLAH HARGA BAHAN 17,500.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 28,400.00
E. Profit 10% * D 2,840.00
F. Harga Satuan Pekerjaan (D+E) 31,240.00

A. 4.7.1.9 Pelaburan 1 m2 bidang kayu dengan vernis


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.160 100,000.00 16,000.00
2 Tukang cat L.02 OH 0.160 120,000.00 19,200.00
3 Kepala Tukang L.03 OH 0.016 150,000.00 2,400.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
38,050.00
B. BAHAN
1 Cat Vernis liter 0.150 71,000.00 10,650.00
2 Dempul kg 0.050 35,000.00 1,750.00
3 Ampelas lb 0.100 5,000.00 500.00
12,900.00
C. PERALATAN

-
D. Jumlah (A+B+C) 50,950.00
E. Profit 10% * D 5,095.00
F. Harga Satuan Pekerjaan (D+E) 56,045.00
A. 4.7.1.10 1 m2 Pengecatan tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.020 100,000.00 2,000.00
2 Tukang cat L.02 OH 0.063 120,000.00 7,560.00
3 Kepala Tukang L.03 OH 0.006 150,000.00 945.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
10,955.00
B. BAHAN
1 Plamuer tembok kg 0.100 10,000.00 1,000.00
2 Cat dasar kg 0.100 24,250.00 2,425.00
3 Cat tembok in(ex mowilex) kg 0.260 66,000.00 17,160.00
20,585.00
C. PERALATAN

-
D. Jumlah (A+B+C) 31,540.00
E. Profit 10% * D 3,154.00
F. Harga Satuan Pekerjaan (D+E) 34,694.00

A. 4.7.1.11 1 m2 Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.028 100,000.00 2,800.00
2 Tukang cat L.02 OH 0.042 120,000.00 5,040.00
3 Kepala Tukang L.03 OH 0.004 150,000.00 630.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 8,920.00
B. BAHAN
1 Cat dasar kg 0.120 24,250.00 2,910.00
2 Cat tembok in(ex mowilex) kg 0.180 66,000.00 11,880.00
JUMLAH HARGA BAHAN 11,880.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 20,800.00
E. Profit 10% * D 2,080.00
F. Harga Satuan Pekerjaan (D+E) 22,880.00

A. 4.7.1.13 1 M2 Pelaburan tembok dengan kapur sirih


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.150 100,000.00 15,000.00
2 Tukang cat L.02 OH 0.001 120,000.00 120.00
3 Kepala Tukang L.03 OH 0.000 150,000.00 15.00
4 Mandor L.04 OH 0.003 150,000.00 375.00
15,510.00
B. BAHAN
1 Kapur sirih kg 0.150 40,000.00 6,000.00
2 Ampelas lembar 0.100 5,000.00 500.00
3 Alang-alang ikat 0.250 1,000.00 250.00
6,750.00
C. PERALATAN

-
D. Jumlah (A+B+C) 22,260.00
E. Profit 10% * D 2,226.00
F. Harga Satuan Pekerjaan (D+E) 24,486.00

A. 4.7.1.14 1 M2 Pelaburan tembok lama dengan kapur sirih ( pemeliharaan )


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.040 100,000.00 4,000.00
2 Tukang cat L.02 OH 0.005 120,000.00 600.00
3 Kepala Tukang L.03 OH 0.001 150,000.00 75.00
4 Mandor L.04 OH 0.003 150,000.00 375.00
5,050.00
B. BAHAN
1 Kapur sirih kg 0.300 40,000.00 12,000.00
2 Ampelas lembar 0.200 5,000.00 1,000.00
3 Alang-alang ikat 0.250 1,000.00 250.00
13,250.00
C. PERALATAN

-
D. Jumlah (A+B+C) 18,300.00
E. Profit 10% * D 1,830.00
F. Harga Satuan Pekerjaan (D+E) 20,130.00
A. 4.7.1.15 Pemasangan 1 m2 wallpaper
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.020 100,000.00 2,000.00
2 Tukang cat L.02 OH 0.200 120,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L.04 OH 0.003 150,000.00 375.00
JUMLAH TENAGA KERJA 29,375.00
B. BAHAN
1 Wallpaper polos m2 1.200 34,500.00 41,400.00
2 Lem (standar Fox) kg 0.200 20,000.00 4,000.00
JUMLAH HARGA BAHAN 45,400.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 74,775.00
E. Profit 10% * D 7,477.50
F. Harga Satuan Pekerjaan (D+E) 82,252.50

A. 4.7.1.16 Pengecatan 1 m2 permukaan baja dengan menie besi


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.020 100,000.00 2,000.00
2 Tukang cat L.02 OH 0.200 120,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.020 150,000.00 3,000.00
4 Mandor L.04 OH 0.003 150,000.00 375.00
JUMLAH TENAGA KERJA 29,375.00
B. BAHAN
1 Cat menie kg 0.100 42,500.00 4,250.00
2 Kuas bh 0.010 13,350.00 133.50
JUMLAH HARGA BAHAN 4,383.50
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 33,758.50
E. Profit 10% * D 3,375.85
F. Harga Satuan Pekerjaan (D+E) 37,134.35

A. 4.7.1.17 Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.250 100,000.00 25,000.00
2 Tukang cat L.02 OH 0.225 120,000.00 27,000.00
3 Kepala Tukang L.03 OH 0.023 150,000.00 3,375.00
4 Mandor L.04 OH 0.008 150,000.00 1,125.00
JUMLAH TENAGA KERJA 56,500.00
B. BAHAN
1 Cat menie kg 0.100 42,500.00 4,250.00
2 Thinner liter 0.010 30,000.00 300.00
3 Kayu untuk perancah m3 0.002 1,650,000.00 3,300.00
4 Kuas bh 0.010 13,350.00 133.50
JUMLAH HARGA BAHAN 7,983.50
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 64,483.50
E. Profit 10% * D 6,448.35
F. Harga Satuan Pekerjaan (D+E) 70,931.85

A. 4.7.1.21 Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.400 100,000.00 40,000.00
2 Tukang cat L.02 OH 0.700 120,000.00 84,000.00
3 Kepala Tukang L.03 OH 0.070 150,000.00 10,500.00
4 Mandor L.04 OH 0.020 150,000.00 3,000.00
JUMLAH TENAGA KERJA 137,500.00
B. BAHAN
1 Thinner liter 0.010 30,000.00 300.00
2 Cat dasar kg 0.300 24,250.00 7,275.00
JUMLAH HARGA BAHAN 7,575.00
PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 145,075.00
E. Profit 10% * D 14,507.50
F. Harga Satuan Pekerjaan (D+E) 159,582.50

Dihit. Coating Batu Alam


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.160 100,000.00 16,000.00
2 Tukang cat L.02 OH 0.160 120,000.00 19,200.00
3 Kepala Tukang L.03 OH 0.016 150,000.00 2,400.00
4 Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 38,050.00
B. BAHAN
1 Stone Coating liter 0.150 45,000.00 6,750.00
JUMLAH HARGA BAHAN 6,750.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 44,800.00
E. Profit 10% * D 4,480.00
F. Harga Satuan Pekerjaan (D+E) 49,280.00
RENCANA ANGGARAN BIAYA (RAB) PENAWARAN
PEMBANGUNAN LAPANGAN OLAHRAGA MULTI FUN
SMP NEGERI 4 PAYUNG

NO URAIAN PEKERJAAN ANALISA

I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan Ls
2 Pengukuran/Pas bowplank Ls
3 Papan Nama Proyek Ls
4 Galian Tanah Pondasi + penyesuaian peil lantai m3
5 Pasang Bata Rollag 1/2 bata 1:4 m2
6 Urugan Pasir bawah lantai m3
7 Tanah timbun m3
8 Cor lantai t=5 cm m3
9 Pengecatan Ls

JUMLAH I
II PEKERJAAN GAWANG FUTSAL
1 Pipa Besi dia 3,5", t= 2 mm m1
2 Pipa Besi dia 2,5", t= 2 mm m1
3 Pengelasan Ls
4 Jaring Net m2
JUMLAH III
III PEKERJAAN NET VOLLY
1 Pipa Besi dia 4" m1
2 Net Volly Ls
JUMLAH III
IV PEKERJAAN RANGKA, NET BASKET
1 Papan mutiplek t=9mm dilapis pomika m2
2 Net Bola Basket + besi bh
3 Roda set
4 Pipa Besi 3,5" m1
5 Pengelasan Ls
JUMLAH III
REKAPITULASI
I PEKERJAAN PERSIAPAN
II PEKERJAAN GAWANG FUTSAL
III PEKERJAAN NET VOLLY
IV PEKERJAAN RANGKA, NET BASKET
JUMLAH TOTAL BIAYA PEKERJAAN
TERBILANG : Seratus Tujuh Delapan Juta Delapan Ratus Tiga Puluh Satu Ribu Rupiah
RAB) PENAWARAN
HRAGA MULTI FUNGSI
YUNG
#REF!

HARGA SATUAN JUMLAH


VOLUME SATUAN
( Rp ) ( Rp )

1.00 - 350,000.00 350,000.00


1.00 - 750,000.00 750,000.00
1.00 - 200,000.00 200,000.00
2.40 B1 68,212.50 163,710.00
60.00 dihitung D.8 136,930.91 8,215,854.60
56.00 B.11 144,717.66 8,104,188.96
144.00 B.13 197,166.51 28,391,977.44
800.00 B.6.4 (02) 146,283.49 117,026,792.00
1.00 - 500,000.00 500,000.00

163,702,523.00

14.00 - 107,000.00 1,498,000.00


28.04 - 53,000.00 1,486,120.00
1.00 - 500,000.00 500,000.00
18.46 - -
3,484,120.00

7.46 - 135,000.00 1,007,100.00


1.00 - 105,000.00 105,000.00
1,112,100.00

4.32 - 230,000.00 993,600.00


2.00 - 100,000.00 200,000.00
8.00 - 85,000.00 680,000.00
73.92 - 107,000.00 7,909,440.00
1.00 - 750,000.00 750,000.00
10,533,040.00

163,702,523.00
3,484,120.00
1,112,100.00
10,533,040.00
178,831,783.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A. 2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.750 125,000.00 93,750.00
2 Mandor L.04 OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 97,500.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 97,500.00
E. Profit 10% xD
F. Harga Satuan Pekerjaan (D+E) 97,500.00

A. 2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.900 100,000.00 90,000.00
2 Mandor L.04 OH 0.045 150,000.00 6,750.00
JUMLAH TENAGA KERJA 96,750.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 96,750.00
E. Profit 10% xD 9,675.00
F. Harga Satuan Pekerjaan (D+E) 106,425.00

A. 2.3.1.3. Penggalian 1 m3 tanah biasa sedalam 3 m


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 1.050 100,000.00 105,000.00
2 Mandor L.04 OH 0.067 150,000.00 10,050.00
JUMLAH TENAGA KERJA 115,050.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 115,050.00
E. Profit 10% xD 11,505.00
F. Harga Satuan Pekerjaan (D+E) 126,555.00

A. 2.3.1.4. Penggalian 1 m3 tanah keras sedalam 1 m


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 1.000 100,000.00 100,000.00
2 Mandor L.04 OH 0.032 150,000.00 4,800.00
JUMLAH TENAGA KERJA 104,800.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 104,800.00
E. Profit 10% xD 10,480.00
F. Harga Satuan Pekerjaan (D+E) 115,280.00
A. 2.3.1.5. Penggalian 1 m3 tanah cadas sedalam 1 m
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 1.500 100,000.00 150,000.00
2 Mandor L.04 OH 0.060 150,000.00 9,000.00
JUMLAH TENAGA KERJA 159,000.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 159,000.00
E. Profit 10% xD 15,900.00
F. Harga Satuan Pekerjaan (D+E) 174,900.00

A. 2.3.1.6. Penggalian 1 m3 tanah lumpur sedalam 1 m


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 1.200 100,000.00 120,000.00
2 Mandor L.04 OH 0.045 150,000.00 6,750.00
JUMLAH TENAGA KERJA 126,750.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 126,750.00
E. Profit 10% xD 12,675.00
F. Harga Satuan Pekerjaan (D+E) 139,425.00

A. 2.3.1.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 m


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.050 100,000.00 5,000.00
2 Mandor L.04 OH 0.005 150,000.00 750.00
JUMLAH TENAGA KERJA 5,750.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 5,750.00
E. Profit 10% xD 575.00
F. Harga Satuan Pekerjaan (D+E) 6,325.00

A. 2.3.1.8. Pembuangan 1 m3 tanah sejauh 30 m


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.330 100,000.00 33,000.00
2 Mandor L.04 OH 0.010 150,000.00 1,500.00
JUMLAH TENAGA KERJA 34,500.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 34,500.00
E. Profit 10% xD 3,450.00
F. Harga Satuan Pekerjaan (D+E) 37,950.00
A. 2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.500 100,000.00 50,000.00
2 Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 57,500.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 57,500.00
E. Profit 10% xD 5,750.00
F. Harga Satuan Pekerjaan (D+E) 63,250.00

A. 2.3.1.10. Pemadatan tanah 1 m3 tanah ( per 20 cm)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.500 100,000.00 50,000.00
2 Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 57,500.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 57,500.00
E. Profit 10% xD 5,750.00
F. Harga Satuan Pekerjaan (D+E) 63,250.00

A. 2.3.1.11. Pengurugan 1 m3 dengan pasir urug


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Mandor L.04 OH 0.010 150,000.00 1,500.00
JUMLAH TENAGA KERJA 31,500.00
B. BAHAN
1 Pasir pasang m3 1.200 52,125.00 62,550.00
JUMLAH HARGA BAHAN 62,550.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 94,050.00
E. Profit 10% xD 9,405.00
F. Harga Satuan Pekerjaan (D+E) 103,455.00

A. 2.3.1.11.a. Pengurugan 1 m3 dengan tanah biasa/subur


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.300 100,000.00 30,000.00
2 Mandor L.04 OH 0.010 150,000.00 1,500.00
JUMLAH TENAGA KERJA 31,500.00
B. BAHAN
1 Timbunan biasa m3 1.200 35,000.00 42,000.00
JUMLAH HARGA BAHAN 42,000.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 73,500.00
E. Profit 10% xD 7,350.00
F. Harga Satuan Pekerjaan (D+E) 80,850.00
A. 2.3.1.13. Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.150 100,000.00 15,000.00
2 Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 17,250.00
B. BAHAN
1 Ijuk kg 6.000 15,000.00 90,000.00
JUMLAH HARGA BAHAN 90,000.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 107,250.00
E. Profit 10% xD 10,725.00
F. Harga Satuan Pekerjaan (D+E) 117,975.00

A. 2.3.1.14. Pemasangan 1 m3 sirtu padat


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
1 Pekerja L.01 OH 0.250 100,000.00 25,000.00
2 Mandor L.04 OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 28,750.00
B. BAHAN
1 Sirtu m3 1.200 259,250.00 311,100.00
JUMLAH HARGA BAHAN 311,100.00
C. PERALATAN

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 339,850.00
E. Profit 10% xD 33,985.00
F. Harga Satuan Pekerjaan (D+E) 373,835.00
RENCANA ANGGARAN BIAYA (RAB) PENAWARAN
PEMBANGUNAN LAPANGAN OLAHRAGA MULTI FUN
SMP NEGERI 4 PAYUNG

NO URAIAN PEKERJAAN SATUAN

I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan m2
2 Pembuatan Bedeng/Barak Pekerja Ls
2 Pengukuran/Pas bowplank m1
3 Papan Nama Proyek Ls
4 Galian Tanah Pondasi + penyesuaian peil lantai m3
5 Pasang Bata Rollag 1 bata 1:5 m2
6 Urugan Pasir bawah lantai m3
7 Tanah timbun m3
8 Cor lantai t=10 cm m3
9 Pengecatan m2

JUMLAH I
II PEKERJAAN GAWANG FUTSAL
1 Pipa Besi dia 3,5", t= 2 mm m1
2 Pipa Besi dia 2,5", t= 2 mm m1
3 Pengelasan Ls
4 Jaring Net Futsal m2
JUMLAH III
III PEKERJAAN NET VOLLY
1 Pipa Besi dia 4" m1
2 Net Volly Ls
JUMLAH III
IV PEKERJAAN RANGKA, NET BASKET
1 Papan mutiplek t=9mm dilapis pomika m2
2 Net Bola Basket + besi bh
3 Roda set
4 Pipa Besi 3,5" m1
5 Pengelasan Ls
JUMLAH III
REKAPITULASI
I PEKERJAAN PERSIAPAN
II PEKERJAAN GAWANG FUTSAL
III PEKERJAAN NET VOLLY
IV PEKERJAAN RANGKA, NET BASKET
JUMLAH TOTAL BIAYA PEKERJAAN
TERBILANG : Dua Ratus Lima Puluh Enam Juta Sembilan Rat
RAB) PENAWARAN
HRAGA MULTI FUNGSI
YUNG

#REF!

HARGA SATUAN JUMLAH


VOLUME ANALISA
( Rp ) ( Rp )

1,389.50 - 10,000.00 13,895,000.00


1.00 - 1,750,000.00 1,750,000.00
261.00 - 53,610.00 13,992,210.00
1.00 350,000.00 350,000.00
7.83 97,500.00 763,425.00
41.76 280,747.15 11,724,000.98
138.95 94,050.00 13,068,247.50
138.95 73,500.00 10,212,825.00
138.95 913,179.73 126,886,323.78
1,389.50 34,694.00 48,207,313.00

240,849,345.27

14.00 - 120,000.00 1,680,000.00


28.04 - 55,000.00 1,542,200.00
1.00 - 600,000.00 600,000.00
18.46 - 14,000.00 258,440.00
4,080,640.00

7.46 - 135,000.00 1,007,100.00


1.00 - 100,000.00 100,000.00
1,107,100.00

4.32 - 250,000.00 1,080,000.00


2.00 - 100,000.00 200,000.00
8.00 - 85,000.00 680,000.00
73.92 - 107,000.00 7,909,440.00
1.00 - 1,000,000.00 1,000,000.00
10,869,440.00

240,849,345.27
4,080,640.00
1,107,100.00
10,869,440.00
256,900,000.00
m Juta Sembilan Ratus Ribu Rupiah