Panjang Lebar
B Pendirian Pagar Keliling (t = 2,40 m) = 15.75 + 15.75 + 15.75 + 15.75 = 63.000 m
= 63.00 x 2.40 = 151.200 m²
Panjang Lebar
C Pekerjaan Bowplank (t = 1,5 m) = 17.80 + 22.00 + 17.80 + 22.00 = 79.600 m
= 79.60 x 1.50 = 119.400 m
Panjang Lebar
D Pendirian Gudang = 2.00 x 2.00 = 4.000 m²
Panjang Lebar
E Pendirian Pos Jaga = 2.00 x 3.00 = 6.000 m²
Panjang Lebar
G Pembuatan Kantor Sementara = 4.00 x 4.00 = 16.000 m²
A Galian Pondasi
Panjang Lebar Tinggi Volume
Galian Pondasi Batu Kali A = 49.75 x 1.00 x 1.05 = 52.238 m³
B Pondasi
Panjang Lebar Tinggi
Aanstamping A = 49.75 x 1.00 x 0.20 = 9.950 m³
A Pekerjaan Kolom
Panjang Lebar Tinggi Jumlah
Kolom Praktis 15/30 Lantai 1 dan 2 = 0.30 x 0.15 x 7.20 x 20.00 = 12.960 m³
Kolom Struktur 30/30 Lantai 1 dan 2 = 0.30 x 0.30 x 7.20 x 4.00 = 5.184 m³
B Pekerjaan Balok
Panjang Lebar Panjang
Balok B1 15/40 Lantai 1 = 0.15 x 0.40 x 73.00 = 4.380 m³
Balok B1 15/40 Lantai 2 = 0.15 x 0.40 x 27.00 = 1.620 m³
6.000 m³
Balok B1 15/40 Balok B2 15/30 Bekisting Balok B1 15/40 = 0.30 x 0.80 x 100.00 = 24.000 m³
Bekisting Balok B2 15/30 = 0.30 x 0.60 x 53.50 = 9.630 m³
A Lantai 1
Pasangan Dinding 1 Bata, 1 : 3 Panjang Tinggi Tebal Plester Dinding Plester
Line A 1.00 x 3.80 x 0.015 3.80 0.057 m2
Line B 3.25 x 3.80 x 0.015 12.35 0.185 m2
Line C 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line D 2.25 x 3.80 x 0.020 8.55 0.171 m2
Line E 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line F 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line G 3.00 x 3.80 x 0.025 11.40 0.285 m2
Line H 2.00 x 3.80 x 0.025 7.60 0.190 m2
Line I 2.00 x 3.80 x 0.030 7.60 0.228 m2
Line J 2.25 x 3.80 x 0.030 8.55 0.257 m2
Pasangan Dinding 1 Bata, 1 : 6
Line K 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line L 3.50 x 3.80 x 0.020 13.30 0.266 m2
Line M 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line N 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line O 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line P 2.25 x 3.80 x 0.020 8.55 0.171 m2
Line Q 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line R 3.50 x 3.80 x 0.020 13.30 0.266 m2
Line S 4.00 x 3.80 x 0.015 15.20 0.228 m2
Line T 4.00 x 3.80 x 0.015 15.20 0.228 m2
Pasangan Dinding 1/2 Bata, 1 : 3
Line U 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line V 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line W 4.00 x 3.80 x 0.020 15.20 0.304 m2
Line X 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line Y 1.00 x 3.80 x 0.020 3.80 0.076 m2
Pasangan Dinding 1/2 Bata, 1 : 6
Line Z 1.50 x 3.80 x 0.020 5.70 0.114 m2
Line A1 1.50 x 3.80 x 0.020 5.70 0.114 m2
Line B1 1.50 x 3.80 x 0.020 5.70 0.114 m2
Line C1 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line D1 3.00 x 3.80 x 0.020 11.40 0.228 m2
271.70 m 2
5.458 m2
Faktor Pengurang Pintu dan Jendela Lantai 1 Panjang Tinggi Jumlah
Jendela 1 1.38 x 1.92 x 2.00 5.299 m2
Pintu KM/WC/Gudang 0.92 x 1.96 x 2.00 3.606 m2
Jendela 2 0.72 x 1.92 x 7.00 9.677 m2
Pintu 1 3.06 x 2.16 x 2.00 13.219 m2
Pintu 2 0.92 x 0.40 x 3.00 1.104 m2
Jendela 3 2.34 x 1.94 x 1.00 4.540 m2
37.445 m2
B Lantai 2
Pasangan Dinding 1 Bata, 1 : 3 Panjang Tinggi Tebal Plester Dinding Plester
Line A 1.00 x 3.80 x 0.015 3.80 0.057 m2
Line B 3.25 x 3.80 x 0.015 12.35 0.185 m2
Line C 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line D 2.25 x 3.80 x 0.020 8.55 0.171 m2
Line E 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line F 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line G 3.00 x 3.80 x 0.025 11.40 0.285 m2
Line H 2.00 x 3.80 x 0.025 7.60 0.190 m2
Line I 2.00 x 3.80 x 0.030 7.60 0.228 m2
Line J 2.25 x 3.80 x 0.030 8.55 0.257 m2
Pasangan Dinding 1 Bata, 1 : 6
Line K 3.25 x 3.80 x 0.020 12.35 0.247 m2
Line L 4.00 x 3.80 x 0.020 15.20 0.304 m2
Line M 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line N 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line O 2.25 x 3.80 x 0.020 8.55 0.171 m2
Line P 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line Q 4.00 x 3.80 x 0.020 15.20 0.304 m2
Line R 4.00 x 3.80 x 0.020 15.20 0.304 m2
Line S 4.00 x 3.80 x 0.015 15.20 0.228 m2
Pasangan Dinding 1/2 Bata, 1 : 6
Line T 4.00 x 3.80 x 0.020 15.20 0.304 m2
Line U 4.50 x 3.80 x 0.020 17.10 0.342 m2
Line V 1.00 x 3.80 x 0.020 3.80 0.076 m2
Line W 3.25 x 3.80 x 0.020 12.35 0.247 m2
Line X 3.00 x 3.80 x 0.020 11.40 0.228 m2
Line Y 2.25 x 3.80 x 0.020 8.55 0.171 m2
263.15 m 2
5.363 m2
Pintu 1
Pintu 2
Jendela 3
Total = 138.25 m²
11 PEKERJAAN INSTALASI AIR DAN SANITASI 11 PEKERJAAN INSTALASI AIR DAN SANITASI
I UPAH
II BAHAN LOKAL
IV LAMPU DLL
HARGA (Rp)
4
42,200.00
55,600.00
55,600.00
55,600.00
55,600.00
47,000.00
50,000.00
58,000.00
64,700.00
55,600.00
100,000.00
52,000.00
55,000.00
75,000.00
140,000.00
230,000.00
250,000.00
150,000.00
191,500.00
152,000.00
550.00
2,400.00
125,000.00
72,000.00
84,000.00
480,000.00
19,200,000.00
10,200,000.00
7,800,000.00
7,800,000.00
9,600,000.00
5,400,000.00
4,200,000.00
19,800,000.00
10,700,000.00
8,300,000.00
8,300,000.00
10,100,000.00
5,900,000.00
4,500,000.00
142,000.00
2,250,000.00
16,000.00
3,000.00
17,500.00
28,000.00
30,000.00
32,000.00
42,350.00
52,800.00
79,200.00
85,800.00
112,200.00
211,200.00
27,500.00
38,500.00
40,000.00
43,500.00
51,000.00
200,000.00
172,000.00
112,500.00
119,000.00
86,000.00
3,650.00
800.00
1,650.00
1,800.00
1,400.00
4,250.00
6,600.00
66,000.00
3,500.00
8,000.00
125,000.00
10,000.00
23,500.00
99,000.00
165,000.00
165,000.00
165,000.00
192,000.00
146,000.00
106,000.00
152,000.00
198,000.00
92,500.00
198,000.00
152,000.00
4,000.00
2,650.00
1,200.00
47,400.00
59,200.00
55,200.00
67,200.00
42,000.00
36,000.00
48,000.00
61,500.00
119,000.00
1,950.00
1,350.00
10,000.00
15,000.00
12,100.00
300,000.00
18,000.00
18,000.00
11,000.00
1,700.00
7,200.00
245,000.00
660,000.00
990,000.00
990,000.00
12,000.00
11,500.00
12,600.00
46,800.00
47,500.00
38,500.00
84,000.00
40,800.00
43,000.00
49,000.00
36,000.00
32,500.00
50,000.00
44,000.00
84,000.00
43,000.00
44,000.00
59,000.00
98,000.00
165,000.00
183,000.00
122,000.00
134,000.00
201,000.00
207,000.00
231,000.00
286,000.00
115,000.00
66,000.00
40,800.00
66,000.00
46,500.00
41,000.00
10,800.00
9,900.00
46,200.00
6,600.00
46,200.00
29,000.00
9,600.00
17,500.00
247,500.00
99,000.00
132,000.00
34,800.00
62,400.00
42,250.00
62,400.00
56,100.00
93,000.00
99,000.00
62,400.00
22,000.00
52,800.00
54,000.00
79,200.00
85,800.00
21,000.00
30,000.00
36,000.00
960.00
1,430.00
600.00
15,000.00
396.00
9,000.00
6,000.00
7,700.00
6,600.00
6,000.00
12,100.00
60,000.00
9,900.00
15,600.00
79,000.00
10,200.00
42,000.00
15,600.00
16,800.00
9,600.00
22,200.00
4,500.00
7,000.00
2,400.00
36,000.00
42,000.00
11,000.00
12,000.00
33,000.00
42,000.00
15,600.00
54,000.00
15,600.00
60,000.00
12,000.00
4,500.00
4,500.00
8,250.00
28,500.00
4,500.00
30,000.00
30,000.00
26,400.00
4,000.00
102,000.00
960,000.00
330,000.00
225,000.00
210,000.00
165,000.00
138,600.00
69,000.00
16,500.00
26,500.00
183,000.00
8,800.00
7,500.00
22,000.00
21,000.00
263,000.00
185,600.00
145,900.00
106,200.00
77,000.00
63,500.00
50,000.00
33,300.00
27,000.00
263,000.00
185,600.00
145,900.00
106,200.00
77,000.00
63,500.00
50,000.00
33,300.00
27,000.00
39,600.00
23,400.00
16,200.00
12,000.00
9,600.00
6,500.00
5,875.00
4,250.00
106,480.00
113,135.00
53,570.00
76,780.00
232,925.00
166,375.00
133,100.00
1,996,500.00
66,550.00
199,650.00
53,240.00
66,550.00
86,515.00
46,585.00
33,275.00
79,860.00
166,375.00
133,100.00
25,400.00
15,840.00
21,780.00
27,500.00
891,000.00
2,420,000.00
31,200.00
36,000.00
42,000.00
186,000.00
396,000.00
495,000.00
790,000.00
365,000.00
363,000.00
396,000.00
561,000.00
92,400.00
79,200.00
528.00
80,000.00
160,000.00
420,000.00
850,000.00
33,000.00
4,620,000.00
9,600.00
48,000.00
96,000.00
107,000.00
118,000.00
21,000.00
52,800.00
210,000.00
329,000.00
145,200.00
30,000.00
15,000.00
90,000.00
553,000.00
590,000.00
43,200.00
60,000.00
28,200.00
43,500.00
9,000.00
15,000.00
63,000.00
1,920,000.00
2,880,000.00
48,000.00
132,000.00
46,200.00
60,000.00
14,400.00
66,000.00
79,200.00
92,400.00
35,000.00
42,500.00
165,900.00
147,700.00
123,200.00
17,800.00
16,200.00
15,200.00
14,200.00
10,600.00
375,000.00
425,300.00
486,000.00
6,700.00
364,500.00
425,300.00
425,000.00
18,600.00
16,800.00
19,920.00
22,800.00
21,960.00
28,080.00
31,920.00
10,000.00
25,000.00
8,000.00
5,000.00
63,000.00
64,200.00
46,800.00
40,800.00
40,000.00
82,500.00
75,000.00
150,000.00
7,700.00
8,800.00
10,450.00
48,000.00
20,350.00
21,450.00
22,000.00
27,500.00
31,900.00
55,000.00
3,500.00
10,000.00
12,500.00
15,000.00
2,300,000.00
105,000.00
275,000.00
1,450,000.00
400,000.00
3,500,000.00
750,000.00
ANALISA HARGA SATUAN
1.1.1 Bahan
0.012 M³ Kayu 5/7 @ Rp 16,000.00 = Rp 192.00
0.020 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 300.00
0.007 M³ Kayu papan 3/20 meranti @ Rp 5,900,000.00 = Rp 41,300.00
Jumlah (1) = Rp 41,792.00
1.1.2 Tenaga
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
1.1.1 Bahan
0.012 M³ Kayu 5/7 @ Rp 200,000.00 = Rp 2,400.00
0.020 Kg Paku biasa 2" - 5" @ Rp 22,200.00 = Rp 444.00
0.007 M³ Kayu papan 3/20 meranti @ Rp 38,500.00 = Rp 269.50
Jumlah (1) = Rp 3,113.50
1.1.2 Tenaga
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
Jumlah (1) + (2) = Rp 13,797.00
1.2.1 Bahan
0.180 M³ Kayu @ Rp 19,800,000.00 = Rp 3,564,000.00
0.850 Kg Paku biasa @ Rp 15,000.00 = Rp 12,750.00
35.000 Kg Semen Portland @ Rp 1,350.00 = Rp 47,250.00
0.150 M³ Pasir pasang @ Rp 100,000.00 = Rp 15,000.00
0.100 M³ Pasir beton @ Rp 100,000.00 = Rp 10,000.00
0.150 M³ Koral beton @ Rp 230,000.00 = Rp 34,500.00
30.000 Bh Bata merah @ Rp 550.00 = Rp 16,500.00
0.250 Lbr Seng plat @ Rp 41,000.00 = Rp 10,250.00
2.000 Bh Jendela nako @ Rp 79,200.00 = Rp 158,400.00
0.080 M² Kaca polos @ Rp 52,800.00 = Rp 4,224.00
0.150 Bh Kunci tanam @ Rp 145,200.00 = Rp 21,780.00
0.060 Lmb Plywood 4 mm @ Rp 62,400.00 = Rp 3,744.00
Jumlah (1) = Rp 3,898,398.00
1.2.2 Tenaga
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
1.000 Org Tukang batu @ Rp 55,600.00 = Rp 55,600.00
2.000 Org Pekerja @ Rp 42,200.00 = Rp 84,400.00
0.300 Org Kepala tukang @ Rp 58,000.00 = Rp 17,400.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 271,835.00
1.3.1 Bahan
0.210 M³ Kayu @ Rp 19,800,000.00 = Rp 4,158,000.00
0.300 Kg Paku biasa @ Rp 15,000.00 = Rp 4,500.00
10.500 Kg Semen Portland @ Rp 1,350.00 = Rp 14,175.00
0.030 M³ Pasir beton @ Rp 100,000.00 = Rp 3,000.00
0.050 M³ Koral beton @ Rp 230,000.00 = Rp 11,500.00
1.500 Lbr Seng gelombang bljs 32 @ Rp 66,000.00 = Rp 99,000.00
Jumlah (1) = Rp 4,290,175.00
1.3.2 Tenaga
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 168,235.00
1.4.1 Bahan
0.276 M³ Kayu @ Rp 19,800,000.00 = Rp 5,464,800.00
0.700 Kg Paku biasa @ Rp 15,000.00 = Rp 10,500.00
1.500 Lbr Seng gelombang bljs 30 @ Rp 66,000.00 = Rp 99,000.00
Jumlah (1) = Rp 5,574,300.00
1.4.2 Tenaga
1.500 Org Tukang kayu @ Rp 55,600.00 = Rp 83,400.00
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
0.150 Org Kepala tukang @ Rp 58,000.00 = Rp 8,700.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 137,535.00
1.5.1 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah = Rp 7,455.00
2.1.1 Tenaga
0.400 Org Pekerja @ Rp 42,200.00 = Rp 16,880.00
1.000 Org Tukang gali @ Rp 42,200.00 = Rp 42,200.00
1.000 Org Kepala tukang @ Rp 58,000.00 = Rp 58,000.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah = Rp 119,668.00
2.2.1 Tenaga
0.625 Org Pekerja @ Rp 42,200.00 = Rp 26,375.00
1.000 Org Tukang gali @ Rp 42,200.00 = Rp 42,200.00
1.000 Org Kepala tukang @ Rp 58,000.00 = Rp 58,000.00
0.062 Org Mandor @ Rp 64,700.00 = Rp 4,011.40
Jumlah = Rp 130,586.40
2.3.1 Tenaga
0.192 Org Pekerja @ Rp 42,200.00 = Rp 8,102.40
1.000 Org Tukang gali Rp 42,200.00 = Rp 42,200.00
1.000 Org Kepala tukang Rp 58,000.00 = Rp 58,000.00
0.019 Org Mandor @ Rp 64,700.00 = Rp 1,229.30
Jumlah = Rp 109,531.70
2.4.1 Tenaga
0.500 Org Pekerja @ Rp 42,200.00 = Rp 21,100.00
1.000 Org Tukang gali Rp 42,200.00 = Rp 42,200.00
1.000 Org Kepala tukang Rp 58,000.00 = Rp 58,000.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah = Rp 124,535.00
2.5 1 m³ Urugan pasir
2.5.1 Bahan
1.200 M³ Pasir urug @ Rp 55,000.00 = Rp 66,000.00
Jumlah (1) = Rp 66,000.00
2.5.2 Tenaga
0.300 Org Pekerja @ Rp 42,200.00 = Rp 12,660.00
1.000 Tukang gali Rp 42,200.00 = Rp 42,200.00
1.000 Kepala tukang Rp 58,000.00 = Rp 58,000.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 113,507.00
3.1.2 Tenaga
1.500 Org Pekerja @ Rp 42,200.00 = Rp 63,300.00
0.600 Org Tukang batu @ Rp 55,600.00 = Rp 33,360.00
0.060 Org Kepala tukang @ Rp 58,000.00 = Rp 3,480.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 104,992.50
4.1.1 Bahan
400.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 550.00 = Rp 220,000.00
32.950 Kg Semen portland @ Rp 1,350.00 = Rp 44,482.50
0.091 M³ Pasir pasang @ Rp 100,000.00 = Rp 9,100.00
Jumlah (1) = Rp 273,582.50
4.1.2 Tenaga
0.450 Org Pekerja @ Rp 42,200.00 = Rp 18,990.00
0.200 Org Tukang batu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 33,211.00
4.2.1 Bahan
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 550.00 = Rp 77,000.00
22.200 Kg Semen portland @ Rp 1,350.00 = Rp 29,970.00
0.102 M³ Pasir pasang @ Rp 100,000.00 = Rp 10,200.00
Jumlah (1) = Rp 117,170.00
4.2.2 Tenaga
0.450 Org Pekerja @ Rp 42,200.00 = Rp 18,990.00
0.200 Org Tukang batu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 33,211.00
4.3.1 Bahan
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 550.00 = Rp 38,500.00
14.370 Kg Semen portland @ Rp 1,350.00 = Rp 19,399.50
0.040 M³ Pasir pasang @ Rp 100,000.00 = Rp 4,000.00
Jumlah (1) = Rp 61,899.50
4.3.2 Tenaga
0.220 Org Pekerja @ Rp 42,200.00 = Rp 9,284.00
0.100 Org Tukang batu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.015 Org Mandor @ Rp 64,700.00 = Rp 970.50
Jumlah (2) = Rp 16,394.50
4.4.1 Bahan
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 550.00 = Rp 38,500.00
8.320 Kg Semen portland @ Rp 1,350.00 = Rp 11,232.00
0.049 M³ Pasir pasang @ Rp 100,000.00 = Rp 4,900.00
Jumlah (1) = Rp 54,632.00
4.4.2 Tenaga
0.220 Org Pekerja @ Rp 42,200.00 = Rp 9,284.00
0.100 Org Tukang batu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.015 Org Mandor @ Rp 64,700.00 = Rp 970.50
Jumlah (2) = Rp 16,394.50
4.5.1 Bahan
36.000 Bh Roster / terawang @ Rp 112,500.00 = Rp 4,050,000.00
12.800 Kg Semen portland @ Rp 1,350.00 = Rp 17,280.00
0.035 M³ Pasir pasang @ Rp 100,000.00 = Rp 3,500.00
Jumlah (1) = Rp 4,070,780.00
4.5.2 Tenaga
0.300 Org Pekerja @ Rp 42,200.00 = Rp 12,660.00
0.100 Org Tukang batu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.015 Org Mandor @ Rp 64,700.00 = Rp 970.50
Jumlah (2) = Rp 19,770.50
6.1.1 Bahan
1.100 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 21,120,000.00
Jumlah (1) = Rp 21,120,000.00
6.1.2 Tenaga
6.000 Org Pekerja @ Rp 42,200.00 = Rp 253,200.00
20.000 Org Tukang kayu @ Rp 55,600.00 = Rp 1,112,000.00
2.000 Org Kepala tukang @ Rp 58,000.00 = Rp 116,000.00
0.300 Org Mandor @ Rp 64,700.00 = Rp 19,410.00
Jumlah (2) = Rp 1,500,610.00
6.2.2 Tenaga
6.000 Org Pekerja @ Rp 42,200.00 = Rp 253,200.00
18.000 Org Tukang kayu @ Rp 55,600.00 = Rp 1,000,800.00
2.000 Org Kepala tukang @ Rp 58,000.00 = Rp 116,000.00
0.300 Org Mandor @ Rp 64,700.00 = Rp 19,410.00
Jumlah (2) = Rp 1,389,410.00
6.3.1 Bahan
1.200 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 9,360,000.00
Jumlah (1) = Rp 9,360,000.00
6.3.2 Tenaga
6.000 Org Pekerja @ Rp 42,200.00 = Rp 253,200.00
18.000 Org Tukang kayu @ Rp 55,600.00 = Rp 1,000,800.00
2.000 Org Kepala tukang @ Rp 58,000.00 = Rp 116,000.00
0.300 Org Mandor @ Rp 64,700.00 = Rp 19,410.00
Jumlah (2) = Rp 1,389,410.00
6.4.1 Bahan
0.036 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 385,200.00
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 750.00
Jumlah (1) = Rp 385,950.00
6.4.2 Tenaga
0.350 Org Pekerja @ Rp 42,200.00 = Rp 14,770.00
1.050 Org Tukang kayu @ Rp 55,600.00 = Rp 58,380.00
0.105 Org Kepala tukang @ Rp 58,000.00 = Rp 6,090.00
0.018 Org Mandor @ Rp 64,700.00 = Rp 1,164.60
Jumlah (2) = Rp 80,404.60
6.5.1 Bahan
0.036 M³ Kayu borneo, papan @ Rp 8,300,000.00 = Rp 298,800.00
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 750.00
Jumlah (1) = Rp 299,550.00
6.5.2 Tenaga
0.350 Org Pekerja @ Rp 42,200.00 = Rp 14,770.00
1.050 Org Tukang kayu @ Rp 55,600.00 = Rp 58,380.00
0.105 Org Kepala tukang @ Rp 58,000.00 = Rp 6,090.00
0.018 Org Mandor @ Rp 64,700.00 = Rp 1,164.60
Jumlah (2) = Rp 80,404.60
6.6.1 Bahan
0.040 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 792,000.00
Jumlah (1) = Rp 792,000.00
6.6.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 198,935.00
6.7.1 Bahan
0.040 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 428,000.00
Jumlah (1) = Rp 428,000.00
6.7.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 198,935.00
6.8.1 Bahan
0.035 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 693,000.00
Jumlah (1) = Rp 693,000.00
6.8.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 159,148.00
6.9.1 Bahan
0.035 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 374,500.00
Jumlah (1) = Rp 374,500.00
6.9.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 159,148.00
6.10.1 Bahan
0.035 M³ Kayu borneo, papan @ Rp 8,300,000.00 = Rp 290,500.00
Jumlah (1) = Rp 290,500.00
6.10.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 159,148.00
6.11.1 Bahan
0.064 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 1,267,200.00
Jumlah (1) = Rp 1,267,200.00
6.11.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
3.000 Org Tukang kayu @ Rp 55,600.00 = Rp 166,800.00
0.300 Org Kepala tukang @ Rp 58,000.00 = Rp 17,400.00
0.300 Org Mandor @ Rp 64,700.00 = Rp 19,410.00
Jumlah (2) = Rp 245,810.00
6.12.1 Bahan
0.064 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 684,800.00
Jumlah (1) = Rp 684,800.00
6.12.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
3.000 Org Tukang kayu @ Rp 55,600.00 = Rp 166,800.00
0.300 Org Kepala tukang @ Rp 58,000.00 = Rp 17,400.00
0.200 Org Mandor @ Rp 64,700.00 = Rp 12,940.00
Jumlah (2) = Rp 239,340.00
6.13.1 Bahan
0.0196 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 388,080.00
0.030 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 450.00
0.300 Lt Lem kayu @ Rp 11,000.00 = Rp 3,300.00
1.000 Lbr Play wood 4' x 3' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
Jumlah (1) = Rp 454,230.00
6.13.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 150,061.00
6.14.1 Bahan
0.0196 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 209,720.00
0.030 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 450.00
0.300 Lt Lem kayu @ Rp 11,000.00 = Rp 3,300.00
1.000 Lbr Play wood 4' x 3' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
Jumlah (1) = Rp 275,870.00
6.14.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 150,061.00
6.15.1 Bahan
0.060 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 1,188,000.00
0.150 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 1,190,250.00
6.15.2 Tenaga
0.500 Org Pekerja @ Rp 42,200.00 = Rp 21,100.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.025 Org Mandor @ Rp 64,700.00 = Rp 1,617.50
Jumlah (2) = Rp 145,517.50
6.16.1 Bahan
0.060 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 642,000.00
0.150 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 644,250.00
6.16.2 Tenaga
0.500 Org Pekerja @ Rp 42,200.00 = Rp 21,100.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.025 Org Mandor @ Rp 64,700.00 = Rp 1,617.50
Jumlah (2) = Rp 145,517.50
6.17.1 Bahan
0.0196 M³ Kayu borneo, papan @ Rp 8,300,000.00 = Rp 162,680.00
0.030 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 450.00
0.300 Lt Lem kayu @ Rp 11,000.00 = Rp 3,300.00
1.000 Lbr Play wood 4' x 3' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
Jumlah (1) = Rp 228,830.00
6.17.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 150,061.00
6.18.1 Bahan
0.0196 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 388,080.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
0.300 Lt Lem kayu @ Rp 11,000.00 = Rp 3,300.00
1.000 Lbr Teakwood 4' x 8' x 4 mm @ Rp 99,000.00 = Rp 99,000.00
Jumlah (1) = Rp 494,880.00
6.18.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 150,061.00
6.19.1 Bahan
0.0196 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 209,720.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
0.300 Lt Lem kayu @ Rp 11,000.00 = Rp 3,300.00
1.000 Lbr Teakwood 4' x 8' x 4 mm @ Rp 99,000.00 = Rp 99,000.00
Jumlah (1) = Rp 316,520.00
6.19.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
2.000 Org Tukang kayu @ Rp 55,600.00 = Rp 111,200.00
0.200 Org Kepala tukang @ Rp 58,000.00 = Rp 11,600.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 150,061.00
6.20.1 Bahan
0.0196 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 388,080.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
0.800 Lt Lem kayu @ Rp 11,000.00 = Rp 8,800.00
1.000 Lbr Play wood 4' x 8' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
0.500 Lbr Formica @ Rp 247,500.00 = Rp 123,750.00
Jumlah (1) = Rp 587,530.00
6.20.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 189,848.00
6.21.1 Bahan
0.0196 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 209,720.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
0.800 Lt Lem kayu @ Rp 11,000.00 = Rp 8,800.00
1.000 Lbr Play wood 4' x 8' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
0.500 Lbr Formica 4' x 3' @ Rp 247,500.00 = Rp 123,750.00
Jumlah (1) = Rp 409,170.00
6.21.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 189,848.00
6.22.1 Bahan
0.0196 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 388,080.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
0.800 Lt Lem kayu @ Rp 11,000.00 = Rp 8,800.00
0.500 Lbr Teakwood 4' x 8' x 4 mm @ Rp 99,000.00 = Rp 49,500.00
0.500 Lbr Formica 4' x 8' @ Rp 247,500.00 = Rp 123,750.00
Jumlah (1) = Rp 574,630.00
6.22.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 189,848.00
6.23 1 m² Pasang pintu teakwood & formika, rangka kayu kamper (divernis)
6.23.1 Bahan
0.0196 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 209,720.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
0.800 Lt Lem kayu @ Rp 11,000.00 = Rp 8,800.00
0.500 Lbr Teakwood 4' x 8' x 4 mm @ Rp 99,000.00 = Rp 49,500.00
0.500 Lt Vernis @ Rp 36,000.00 = Rp 18,000.00
0.500 Lbr Formica 4' x 8' @ Rp 247,500.00 = Rp 123,750.00
Jumlah (1) = Rp 414,270.00
6.23.2 Tenaga
0.800 Org Pekerja @ Rp 42,200.00 = Rp 33,760.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.040 Org Mandor @ Rp 64,700.00 = Rp 2,588.00
Jumlah (2) = Rp 189,848.00
6.24.1 Bahan
0.0196 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 388,080.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
1.200 Lt Lem kayu @ Rp 11,000.00 = Rp 13,200.00
1.000 Lbr Play wood 4' x 8' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
1.000 Lbr Formica 4' x 8' @ Rp 247,500.00 = Rp 247,500.00
Jumlah (1) = Rp 715,680.00
6.24.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
2.600 Org Tukang kayu @ Rp 55,600.00 = Rp 144,560.00
0.260 Org Kepala tukang @ Rp 58,000.00 = Rp 15,080.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 205,075.00
6.25.1 Bahan
0.0196 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 209,720.00
0.300 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 4,500.00
1.200 Lt Lem kayu @ Rp 11,000.00 = Rp 13,200.00
1.000 Lbr Play wood 4' x 8' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
1.000 Lbr Formica 4' x 8' @ Rp 247,500.00 = Rp 247,500.00
Jumlah (1) = Rp 537,320.00
6.25.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
2.600 Org Tukang kayu @ Rp 55,600.00 = Rp 144,560.00
0.260 Org Kepala tukang @ Rp 58,000.00 = Rp 15,080.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 205,075.00
6.26.1 Bahan
1.100 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 21,120,000.00
15.000 Kg Besi strip @ Rp 300,000.00 = Rp 4,500,000.00
0.800 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 12,000.00
Jumlah (1) = Rp 25,632,000.00
6.26.2 Tenaga
4.000 Org Pekerja @ Rp 42,200.00 = Rp 168,800.00
12.000 Org Tukang kayu @ Rp 55,600.00 = Rp 667,200.00
1.200 Org Kepala tukang @ Rp 58,000.00 = Rp 69,600.00
0.200 Org Mandor @ Rp 64,700.00 = Rp 12,940.00
Jumlah (2) = Rp 918,540.00
Jumlah (1) + (2) = Rp 26,550,540.00
6.27.1 Bahan
1.100 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 11,220,000.00
15.000 Kg Besi strip @ Rp 300,000.00 = Rp 4,500,000.00
0.800 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 12,000.00
Jumlah (1) = Rp 15,732,000.00
6.27.2 Tenaga
4.000 Org Pekerja @ Rp 42,200.00 = Rp 168,800.00
12.000 Org Tukang kayu @ Rp 55,600.00 = Rp 667,200.00
1.200 Org Kepala tukang @ Rp 58,000.00 = Rp 69,600.00
0.200 Org Mandor @ Rp 64,700.00 = Rp 12,940.00
Jumlah (2) = Rp 918,540.00
6.28.1 Bahan
1.100 M³ Kayu borneo balok @ Rp 7,800,000.00 = Rp 8,580,000.00
15.000 Kg Besi strip @ Rp 300,000.00 = Rp 4,500,000.00
0.800 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 12,000.00
Jumlah (1) = Rp 13,092,000.00
6.28.2 Tenaga
4.000 Org Pekerja @ Rp 42,200.00 = Rp 168,800.00
12.000 Org Tukang kayu @ Rp 55,600.00 = Rp 667,200.00
1.200 Org Kepala tukang @ Rp 58,000.00 = Rp 69,600.00
0.200 Org Mandor @ Rp 64,700.00 = Rp 12,940.00
Jumlah (2) = Rp 918,540.00
6.29.2 Tenaga
4.000 Org Pekerja @ Rp 42,200.00 = Rp 168,800.00
12.000 Org Tukang kayu @ Rp 55,600.00 = Rp 667,200.00
1.200 Org Kepala tukang @ Rp 58,000.00 = Rp 69,600.00
0.200 Org Mandor @ Rp 64,700.00 = Rp 12,940.00
Jumlah (2) = Rp 918,540.00
6.30.1 Bahan
0.012 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 122,400.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 124,650.00
6.30.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
6.31.1 Bahan
0.012 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 93,600.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 95,850.00
6.31.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
6.32.1 Bahan
0.014 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 268,800.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 271,050.00
6.32.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
6.33.1 Bahan
0.014 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 142,800.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 145,050.00
6.33.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
Jumlah (1) + (2) = Rp 155,733.50
6.34.1 Bahan
0.014 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 109,200.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 111,450.00
6.34.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 10,683.50
6.35.1 Bahan
0.165 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 1,683,000.00
0.200 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 3,000.00
Jumlah (1) = Rp 1,686,000.00
6.35.2 Tenaga
0.120 Org Pekerja @ Rp 42,200.00 = Rp 5,064.00
0.120 Org Tukang kayu @ Rp 55,600.00 = Rp 6,672.00
0.012 Org Kepala tukang @ Rp 58,000.00 = Rp 696.00
0.006 Org Mandor @ Rp 64,700.00 = Rp 388.20
Jumlah (2) = Rp 12,820.20
6.36.1 Bahan
0.165 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 1,287,000.00
0.200 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 3,000.00
Jumlah (1) = Rp 1,290,000.00
6.36.2 Tenaga
0.120 Org Pekerja @ Rp 42,200.00 = Rp 5,064.00
0.120 Org Tukang kayu @ Rp 55,600.00 = Rp 6,672.00
0.012 Org Kepala tukang @ Rp 58,000.00 = Rp 696.00
0.006 Org Mandor @ Rp 64,700.00 = Rp 388.20
Jumlah (2) = Rp 12,820.20
6.37.1 Bahan
0.012 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 230,400.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
Jumlah (1) = Rp 231,900.00
6.37.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 16,082.50
6.38.1 Bahan
0.012 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 122,400.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
Jumlah (1) = Rp 123,900.00
6.38.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 16,082.50
6.39.1 Bahan
0.012 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 93,600.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
Jumlah (1) = Rp 95,100.00
6.39.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.015 Org Mandor @ Rp 64,700.00 = Rp 970.50
Jumlah (2) = Rp 12,200.50
6.40.1 Bahan
0.023 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 441,600.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 443,850.00
6.40.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.300 Org Tukang kayu @ Rp 55,600.00 = Rp 16,680.00
0.030 Org Kepala tukang @ Rp 58,000.00 = Rp 1,740.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 27,507.00
6.41.1 Bahan
0.023 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 234,600.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 236,850.00
6.41.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.300 Org Tukang kayu @ Rp 55,600.00 = Rp 16,680.00
0.030 Org Kepala tukang @ Rp 58,000.00 = Rp 1,740.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 27,507.00
6.42 1 m² Pasang rangka langit-langit (30 x 60) cm, kayu borneo / Meranti
6.42.1 Bahan
0.023 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 179,400.00
0.150 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 2,250.00
Jumlah (1) = Rp 181,650.00
6.42.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.300 Org Tukang kayu @ Rp 55,600.00 = Rp 16,680.00
0.030 Org Kepala tukang @ Rp 58,000.00 = Rp 1,740.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 27,507.00
6.43.1 Bahan
0.027 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 518,400.00
0.200 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 3,000.00
Jumlah (1) = Rp 521,400.00
6.43.2 Tenaga
0.250 Org Pekerja @ Rp 42,200.00 = Rp 10,550.00
0.350 Org Tukang kayu @ Rp 55,600.00 = Rp 19,460.00
0.035 Org Kepala tukang @ Rp 58,000.00 = Rp 2,030.00
0.0125 Org Mandor @ Rp 64,700.00 = Rp 808.75
Jumlah (2) = Rp 32,848.75
6.44.1 Bahan
0.027 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 275,400.00
0.200 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 3,000.00
Jumlah (1) = Rp 278,400.00
6.44.2 Tenaga
0.250 Org Pekerja @ Rp 42,200.00 = Rp 10,550.00
0.350 Org Tukang kayu @ Rp 55,600.00 = Rp 19,460.00
0.035 Org Kepala tukang @ Rp 58,000.00 = Rp 2,030.00
0.0125 Org Mandor @ Rp 64,700.00 = Rp 808.75
Jumlah (2) = Rp 32,848.75
6.45 1 m² Pasang rangka langit-langit (30 x 30) cm, kayu borneo / Meranti
6,45,1 Bahan
0.027 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 210,600.00
0.200 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 3,000.00
Jumlah (1) = Rp 213,600.00
6.45.2 Tenaga
0.250 Org Pekerja @ Rp 42,200.00 = Rp 10,550.00
0.350 Org Tukang kayu @ Rp 55,600.00 = Rp 19,460.00
0.035 Org Kepala tukang @ Rp 58,000.00 = Rp 2,030.00
0.0125 Org Mandor @ Rp 64,700.00 = Rp 808.75
Jumlah (2) = Rp 32,848.75
6.46.1 Bahan
0.0072 M³ Kayu jati, papan @ Rp 19,800,000.00 = Rp 142,560.00
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 750.00
Jumlah (1) = Rp 143,310.00
6.46.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.200 Org Tukang kayu @ Rp 55,600.00 = Rp 11,120.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 17,113.50
6.47.1 Bahan
0.0072 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 77,040.00
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 750.00
Jumlah (1) = Rp 77,790.00
6.47.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.200 Org Tukang kayu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 16,823.50
6.48.2 Tenaga
0.110 Org Pekerja @ Rp 42,200.00 = Rp 4,642.00
0.220 Org Tukang kayu @ Rp 55,600.00 = Rp 12,232.00
0.022 Org Kepala tukang @ Rp 58,000.00 = Rp 1,276.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 18,473.50
6.49.1 Bahan
0.011 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 117,700.00
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 750.00
Jumlah (1) = Rp 118,450.00
6.49.2 Tenaga
0.110 Org Pekerja @ Rp 42,200.00 = Rp 4,642.00
0.220 Org Tukang kayu @ Rp 55,600.00 = Rp 12,232.00
0.022 Org Kepala tukang @ Rp 58,000.00 = Rp 1,276.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 18,473.50
6.50 1 m' Pasang lisplang ukuran 2 x(3 x 20) cm, kayu kamper
6.50.1 Bahan
0.0145 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 155,150.00
0.060 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 900.00
Jumlah (1) = Rp 156,050.00
6.50.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.250 Org Tukang kayu @ Rp 55,600.00 = Rp 13,900.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 26,532.50
6.51 1 m' Pasang lisplang ukuran 2 x(2 x 20) cm, kayu kamper
6.51.1 Bahan
0.0086 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 92,020.00
0.060 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 900.00
Jumlah (1) = Rp 92,920.00
6.51.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 13,595.00
6.52 1 m' Pasang lisplang ukuran 2 x(2 x 20) cm, kayu borneo / Meranti
6.52.1 Bahan
0.0088 M³ Kayu borneo, papan @ Rp 8,300,000.00 = Rp 73,040.00
0.060 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 900.00
Jumlah (1) = Rp 73,940.00
6.52.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 13,595.00
Jumlah (1) + (2) = Rp 87,535.00
6.53.1 Bahan
0.0195 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 198,900.00
0.007 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 74,900.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
Jumlah (1) = Rp 275,300.00
6.53.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.450 Org Tukang kayu @ Rp 55,600.00 = Rp 25,020.00
0.045 Org Kepala tukang @ Rp 58,000.00 = Rp 2,610.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 38,812.50
6.54.1 Bahan
0.0195 M³ Kayu borneo, balok @ Rp 7,800,000.00 = Rp 152,100.00
0.007 M³ Kayu borneo, papan @ Rp 8,300,000.00 = Rp 58,100.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
Jumlah (1) = Rp 211,700.00
6.54.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.450 Org Tukang kayu @ Rp 55,600.00 = Rp 25,020.00
0.045 Org Kepala tukang @ Rp 58,000.00 = Rp 2,610.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 38,812.50
6.55.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.450 Org Tukang kayu @ Rp 55,600.00 = Rp 25,020.00
0.045 Org Kepala tukang @ Rp 58,000.00 = Rp 2,610.00
0.075 Org Mandor @ Rp 64,700.00 = Rp 4,852.50
Jumlah (2) = Rp 38,812.50
6.56.1 Bahan
0.0195 M³ Kayu kamper, balok @ Rp 10,200,000.00 = Rp 198,900.00
0.007 M³ Kayu kamper, papan @ Rp 10,700,000.00 = Rp 74,900.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
0.560 Lt Lem kayu @ Rp 11,000.00 = Rp 6,160.00
1.000 Lbr Plywood 4' x 8' x 4 mm @ Rp 62,400.00 = Rp 62,400.00
Jumlah (1) = Rp 343,860.00
6.56.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.600 Org Tukang kayu @ Rp 55,600.00 = Rp 33,360.00
0.060 Org Kepala tukang @ Rp 58,000.00 = Rp 3,480.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 45,927.00
6.57.1 Bahan
0.007 M³ Kayu jati, balok @ Rp 19,200,000.00 = Rp 134,400.00
0.100 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 1,500.00
0.150 Kg Paku skrup 3,5" @ Rp 600.00 = Rp 90.00
Jumlah (1) = Rp 135,990.00
6.57.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
1.800 Org Tukang kayu @ Rp 55,600.00 = Rp 100,080.00
0.180 Org Kepala tukang @ Rp 58,000.00 = Rp 10,440.00
0.030 Org Mandor @ Rp 64,700.00 = Rp 1,941.00
Jumlah (2) = Rp 137,781.00
6.58.1 Bahan
0.400 Lbr Plywood 4' x 8' x 4 mm @ Rp 62,400.00 = Rp 24,960.00
0.050 Kg Paku biasa ½" - 1" @ Rp 15,000.00 = Rp 750.00
Jumlah (1) = Rp 25,710.00
6.58.2 Tenaga
0.025 Org Pekerja @ Rp 42,200.00 = Rp 1,055.00
0.075 Org Tukang kayu @ Rp 55,600.00 = Rp 4,170.00
0.0075 Org Kepala tukang @ Rp 58,000.00 = Rp 435.00
0.0013 Org Mandor @ Rp 64,700.00 = Rp 84.11
Jumlah (2) = Rp 5,744.11
6.59.1 Bahan
1.050 M' Kayu profil @ Rp 3,000.00 = Rp 3,150.00
Jumlah (1) = Rp 3,150.00
6.59.2 Tenaga
0.021 Org Pekerja @ Rp 42,200.00 = Rp 886.20
0.021 Org Tukang kayu @ Rp 55,600.00 = Rp 1,167.60
0.002 Org Kepala tukang @ Rp 58,000.00 = Rp 116.00
0.001 Org Mandor @ Rp 64,700.00 = Rp 64.70
Jumlah (2) = Rp 2,234.50
6.60.1 Bahan
0.040 M³ Kayu meranti, papan @ Rp 5,900,000.00 = Rp 236,000.00
Jumlah (1) = Rp 236,000.00
6.60.2 Tenaga
1.000 Org Pekerja @ Rp 42,200.00 = Rp 42,200.00
2.500 Org Tukang kayu @ Rp 55,600.00 = Rp 139,000.00
0.250 Org Kepala tukang @ Rp 58,000.00 = Rp 14,500.00
0.050 Org Mandor @ Rp 64,700.00 = Rp 3,235.00
Jumlah (2) = Rp 198,935.00
7.3.2 Tenaga
0.400 Org Pekerja @ Rp 42,200.00 = Rp 16,880.00
0.200 Org Tukang kayu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.002 Org Mandor @ Rp 64,700.00 = Rp 129.40
Jumlah (2) = Rp 29,289.40
7.5.2 Tenaga
0.400 Org Pekerja @ Rp 42,200.00 = Rp 16,880.00
0.200 Org Tukang kayu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.002 Org Mandor @ Rp 64,700.00 = Rp 129.40
Jumlah (2) = Rp 29,289.40
7.6.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.075 Org Tukang kayu @ Rp 55,600.00 = Rp 4,170.00
0.008 Org Kepala tukang @ Rp 58,000.00 = Rp 464.00
0.008 Org Mandor @ Rp 64,700.00 = Rp 517.60
Jumlah (2) = Rp 11,059.60
Jumlah (1) + (2) = Rp 44,174.80
7.7.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.075 Org Tukang kayu @ Rp 55,600.00 = Rp 4,170.00
0.008 Org Kepala tukang @ Rp 58,000.00 = Rp 464.00
0.008 Org Mandor @ Rp 64,700.00 = Rp 517.60
Jumlah (2) = Rp 11,059.60
7.8.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.070 Org Tukang kayu @ Rp 55,600.00 = Rp 3,892.00
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,658.90
7.10.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.070 Org Tukang kayu @ Rp 55,600.00 = Rp 3,892.00
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,658.90
7.11.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.070 Org Tukang kayu @ Rp 55,600.00 = Rp 3,892.00
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,658.90
Jumlah (1) + (2) = Rp 38,494.10
7.12.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.13.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.14.1 Bahan
0.800 Lbr Asbes gelombang @ Rp 66,000.00 = Rp 52,800.00
0.120 Kg Paku Pancing @ Rp 960.00 = Rp 115.20
Jumlah (1) = Rp 52,915.20
7.14.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.15.1 Bahan
0.370 Lbr Asbes gelombang @ Rp 66,000.00 = Rp 24,420.00
0.120 Kg Paku Pancing @ Rp 960.00 = Rp 115.20
Jumlah (1) = Rp 24,535.20
7.15.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.16.1 Bahan
0.380 Lbr Asbes gelombang @ Rp 66,000.00 = Rp 25,080.00
0.120 Kg Paku Pancing @ Rp 960.00 = Rp 115.20
Jumlah (1) = Rp 25,195.20
7.16.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.17.1 Bahan
0.460 Lbr Asbes gelombang @ Rp 66,000.00 = Rp 30,360.00
0.120 Kg Paku Pancing @ Rp 960.00 = Rp 115.20
Jumlah (1) = Rp 30,475.20
7.17.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.18.1 Bahan
0.490 Lbr Asbes gelombang @ Rp 66,000.00 = Rp 32,340.00
0.120 Kg Paku Pancing @ Rp 960.00 = Rp 115.20
Jumlah (1) = Rp 32,455.20
7.18.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.19.2 Tenaga
0.140 Org Pekerja @ Rp 42,200.00 = Rp 5,908.00
0.067 Org Tukang kayu @ Rp 55,600.00 = Rp 3,725.20
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.007 Org Mandor @ Rp 64,700.00 = Rp 452.90
Jumlah (2) = Rp 10,492.10
7.20.1 Bahan
2.400 Lbr Bubung stel gelombang @ Rp 66,000.00 = Rp 158,400.00
6.000 Bh Paku sekrup 3,5" @ Rp 960.00 = Rp 5,760.00
Jumlah (1) = Rp 164,160.00
7.20.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
7.21.1 Bahan
2.100 Lbr Nok stel gelombang @ Rp 9,600.00 = Rp 20,160.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 23,760.00
7.21.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
7.22.1 Bahan
2.050 Lbr Nok stel gelombang @ Rp 9,600.00 = Rp 19,680.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 23,280.00
7.22.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
7.23.1 Bahan
1.200 Lbr Nok paten @ Rp 46,200.00 = Rp 55,440.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 59,040.00
7.23.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
Jumlah (1) + (2) = Rp 70,547.60
7.24.1 Bahan
1.200 Lbr Nok paten @ Rp 46,200.00 = Rp 55,440.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 59,040.00
7.24.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
7.25.1 Bahan
1.200 Lbr Nok paten @ Rp 46,200.00 = Rp 55,440.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 59,040.00
7.25.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
7.26.1 Bahan
1.100 Lbr Nok stel rata @ Rp 9,600.00 = Rp 10,560.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 14,160.00
7.26.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.150 Org Tukang kayu @ Rp 55,600.00 = Rp 8,340.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 13,572.80
7.27.1 Bahan
1.100 Lbr Nok stel rata @ Rp 9,600.00 = Rp 10,560.00
6.000 Bh Paku sekrup 3,5" @ Rp 600.00 = Rp 3,600.00
Jumlah (1) = Rp 14,160.00
7.27.2 Tenaga
0.084 Org Pekerja @ Rp 42,200.00 = Rp 3,544.80
0.125 Org Tukang kayu @ Rp 55,600.00 = Rp 6,950.00
0.013 Org Kepala tukang @ Rp 58,000.00 = Rp 754.00
0.004 Org Mandor @ Rp 64,700.00 = Rp 258.80
Jumlah (2) = Rp 11,507.60
7.28.1 Bahan
11.00 Bh Genteng beton @ Rp 3,650.00 = Rp 40,150.00
0.030 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 450.00
Jumlah (1) = Rp 40,600.00
7.28.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 15,227.00
7.29.1 Bahan
3.500 Bh Nok genteng beton @ Rp 46,200.00 = Rp 161,700.00
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 = Rp 750.00
10.800 Kg Semen abu - abu @ Rp 1,950.00 = Rp 21,060.00
0.032 M³ Pasir pasang @ Rp 100,000.00 = Rp 3,200.00
1.000 Kg Semen warna @ Rp 1,950.00 = Rp 1,950.00
Jumlah (1) = Rp 188,660.00
7.29.2 Tenaga
0.400 Org Pekerja @ Rp 42,200.00 = Rp 16,880.00
0.200 Org Tukang kayu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.020 Org Mandor @ Rp 64,700.00 = Rp 1,294.00
Jumlah (2) = Rp 30,454.00
7.30.1 Bahan
0.700 Lbr Seng gelombang 3" x 6" bkls 28 @ Rp 66,000.00 = Rp 46,200.00
0.020 Kg Paku biasa ½" - 1" @ Rp 1,950.00 = Rp 39.00
Jumlah (1) = Rp 46,239.00
7.30.2 Tenaga
0.120 Org Pekerja @ Rp 42,200.00 = Rp 5,064.00
0.060 Org Tukang kayu @ Rp 55,600.00 = Rp 3,336.00
0.006 Org Kepala tukang @ Rp 58,000.00 = Rp 348.00
0.006 Org Mandor @ Rp 64,700.00 = Rp 388.20
Jumlah (2) = Rp 9,136.20
Jumlah (1) + (2) = Rp 55,375.20
7.31.1 Bahan
0.300 Lbr Seng plat 3" x 6" bjls 28 @ Rp 41,000.00 = Rp 12,300.00
0.040 Kg Paku biasa ½" - 1" @ Rp 1,950.00 = Rp 78.00
Jumlah (1) = Rp 12,378.00
7.31.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.070 Org Tukang kayu @ Rp 55,600.00 = Rp 3,892.00
0.008 Org Kepala tukang @ Rp 58,000.00 = Rp 464.00
0.006 Org Mandor @ Rp 64,700.00 = Rp 388.20
Jumlah (2) = Rp 11,074.20
7.32.1 Bahan
1.050 M² Atap aluminium gelombang tebal 0,55 @ Rp 790,000.00 = Rp 829,500.00
0.020 Kg Paku hak panjang 15 cm @ Rp 1,430.00 = Rp 28.60
Jumlah (1) = Rp 829,528.60
7.32.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.750 Org Tukang kayu @ Rp 55,600.00 = Rp 41,700.00
0.008 Org Kepala tukang @ Rp 58,000.00 = Rp 464.00
0.006 Org Mandor @ Rp 64,700.00 = Rp 388.20
Jumlah (2) = Rp 48,882.20
8.1.1 Bahan
6.480 Kg Semen portland @ Rp 1,350.00 = Rp 8,748.00
0.019 M³ Pasir pasang @ Rp 100,000.00 = Rp 1,900.00
Jumlah (1) = Rp 10,648.00
8.1.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.150 Org Tukang batu @ Rp 55,600.00 = Rp 8,340.00
0.015 Org Kepala tukang @ Rp 58,000.00 = Rp 870.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 18,297.00
8.2.1 Bahan
3.680 Kg Semen portland @ Rp 1,350.00 = Rp 4,968.00
0.023 M³ Pasir pasang @ Rp 100,000.00 = Rp 2,300.00
Jumlah (1) = Rp 7,268.00
8.2.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.150 Org Tukang batu @ Rp 55,600.00 = Rp 8,340.00
0.015 Org Kepala tukang @ Rp 58,000.00 = Rp 870.00
0.010 Org Mandor @ Rp 64,700.00 = Rp 647.00
Jumlah (2) = Rp 18,297.00
8.3.1 Bahan
10.800 Kg Semen portland @ Rp 1,350.00 = Rp 14,580.00
0.026 M³ Pasir pasang @ Rp 100,000.00 = Rp 2,600.00
Jumlah (1) = Rp 17,180.00
8.3.2 Tenaga
0.250 Org Pekerja @ Rp 42,200.00 = Rp 10,550.00
0.200 Org Tukang batu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.0125 Org Mandor @ Rp 64,700.00 = Rp 808.75
Jumlah (2) = Rp 23,638.75
8.4.1 Bahan
6.240 Kg Semen portland @ Rp 1,350.00 = Rp 8,424.00
0.030 M³ Pasir pasang @ Rp 100,000.00 = Rp 3,000.00
Jumlah (1) = Rp 11,424.00
8.4.2 Tenaga
0.250 Org Pekerja @ Rp 42,200.00 = Rp 10,550.00
0.200 Org Tukang batu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.0125 Org Mandor @ Rp 64,700.00 = Rp 808.75
Jumlah (2) = Rp 23,638.75
8.5.1 Bahan
11.750 Kg Semen portland @ Rp 1,350.00 = Rp 15,862.50
0.035 M³ Pasir pasang @ Rp 100,000.00 = Rp 3,500.00
Jumlah (1) = Rp 19,362.50
8.5.2 Tenaga
0.300 Org Pekerja @ Rp 42,200.00 = Rp 12,660.00
0.200 Org Tukang batu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.013 Org Mandor @ Rp 64,700.00 = Rp 841.10
Jumlah (2) = Rp 25,781.10
8.6.1 Bahan
14.150 Kg Semen portland @ Rp 1,350.00 = Rp 19,102.50
0.039 M³ Pasir pasang @ Rp 100,000.00 = Rp 3,900.00
Jumlah (1) = Rp 23,002.50
8.6.2 Tenaga
0.320 Org Pekerja @ Rp 42,200.00 = Rp 13,504.00
0.250 Org Tukang batu @ Rp 55,600.00 = Rp 13,900.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.015 Org Mandor @ Rp 64,700.00 = Rp 970.50
Jumlah (2) = Rp 29,824.50
9.1.2 Tenaga
0.030 Org Pekerja @ Rp 42,200.00 = Rp 1,266.00
0.030 Org Tukang kayu @ Rp 55,600.00 = Rp 1,668.00
0.007 Org Kepala tukang @ Rp 58,000.00 = Rp 406.00
0.0015 Org Mandor @ Rp 64,700.00 = Rp 97.05
Jumlah (2) = Rp 3,437.05
9.2.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0035 Org Mandor @ Rp 64,700.00 = Rp 226.45
Jumlah (2) = Rp 9,320.45
9.3.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0035 Org Mandor @ Rp 64,700.00 = Rp 226.45
Jumlah (2) = Rp 9,320.45
9.4.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0035 Org Mandor @ Rp 64,700.00 = Rp 226.45
Jumlah (2) = Rp 9,320.45
9.5.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0035 Org Mandor @ Rp 64,700.00 = Rp 226.45
Jumlah (2) = Rp 9,320.45
9.6.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0035 Org Mandor @ Rp 64,700.00 = Rp 226.45
Jumlah (2) = Rp 9,320.45
9.7.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0035 Org Mandor @ Rp 64,700.00 = Rp 226.45
Jumlah (2) = Rp 9,320.45
9.8.2 Tenaga
0.600 Org Pekerja @ Rp 42,200.00 = Rp 25,320.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.003 Org Mandor @ Rp 64,700.00 = Rp 194.10
Jumlah (2) = Rp 31,654.10
9.9.2 Tenaga
0.030 Org Pekerja @ Rp 42,200.00 = Rp 1,266.00
0.030 Org Tukang kayu @ Rp 55,600.00 = Rp 1,668.00
0.005 Org Kepala tukang @ Rp 58,000.00 = Rp 290.00
0.003 Org Mandor @ Rp 64,700.00 = Rp 194.10
Jumlah (2) = Rp 3,418.10
9.10 1 m² Langit - langit asbes (1,00 x 1,00)m, Tebal 3,2 mm, rangka borneo / Meranti
9.10.1 Bahan
0.012 M³ Kayu borneo, balok @ Rp 5,400,000.00 = Rp 64,800.00
0.060 Kg Paku biasa @ Rp 15,000.00 = Rp 900.00
1.100 Lbr Asbes 1,00 x 1,00 m @ Rp 40,800.00 = Rp 44,880.00
Jumlah (1) = Rp 110,580.00
9.10.2 Tenaga
0.180 Org Pekerja @ Rp 42,200.00 = Rp 7,596.00
0.320 Org Tukang kayu @ Rp 55,600.00 = Rp 17,792.00
0.032 Org Kepala tukang @ Rp 58,000.00 = Rp 1,856.00
0.009 Org Mandor @ Rp 64,700.00 = Rp 582.30
Jumlah (2) = Rp 27,826.30
9.11.2 Tenaga
0.270 Org Pekerja @ Rp 42,200.00 = Rp 11,394.00
0.400 Org Tukang kayu @ Rp 55,600.00 = Rp 22,240.00
0.040 Org Kepala tukang @ Rp 58,000.00 = Rp 2,320.00
0.0135 Org Mandor @ Rp 64,700.00 = Rp 873.45
Jumlah (2) = Rp 36,827.45
9.12.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.050 Org Tukang kayu @ Rp 55,600.00 = Rp 2,780.00
0.005 Org Kepala tukang @ Rp 58,000.00 = Rp 290.00
0.005 Org Mandor @ Rp 64,700.00 = Rp 323.50
Jumlah (2) = Rp 7,613.50
10.1.2 Tenaga
0.006 Org Pekerja @ Rp 42,200.00 = Rp 253.20
0.060 Org Tukang besi @ Rp 55,600.00 = Rp 3,336.00
0.006 Org Kepala tukang @ Rp 58,000.00 = Rp 348.00
0.0003 Org Mandor @ Rp 64,700.00 = Rp 19.41
Jumlah (2) = Rp 3,956.61
10.2.2 Tenaga
0.650 Org Tukang besi konstruksi @ Rp 55,600.00 = Rp 36,140.00
0.650 Org Pekerja @ Rp 42,200.00 = Rp 27,430.00
0.065 Org Kepala tukang @ Rp 58,000.00 = Rp 3,770.00
0.032 Org Mandor @ Rp 64,700.00 = Rp 2,070.40
Jumlah (2) = Rp 69,410.40
10.3.2 Tenaga
1.050 Org Tukang besi konstruksi @ Rp 55,600.00
1.050 Org Pekerja @ Rp 42,200.00 = Rp 44,310.00
0.105 Org Kepala tukang @ Rp 58,000.00 = Rp 6,090.00
0.00525 Org Mandor @ Rp 64,700.00 = Rp 339.68
Jumlah (2) = Rp 50,739.68
10.4.2 Tenaga
1.200 Org Tukang las @ Rp 55,600.00 = Rp 66,720.00
1.200 Org Pekerja @ Rp 42,200.00 = Rp 50,640.00
0.012 Org Kepala tukang @ Rp 58,000.00 = Rp 696.00
0.0006 Org Mandor @ Rp 64,700.00 = Rp 38.82
Jumlah (2) = Rp 118,094.82
10.5.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0005 Org Mandor @ Rp 64,700.00 = Rp 32.35
Jumlah (2) = Rp 10,392.35
10.6.2 Tenaga
0.100 Org Pekerja @ Rp 42,200.00 = Rp 4,220.00
0.100 Org Tukang kayu @ Rp 55,600.00 = Rp 5,560.00
0.010 Org Kepala tukang @ Rp 58,000.00 = Rp 580.00
0.0005 Org Mandor @ Rp 64,700.00 = Rp 32.35
Jumlah (2) = Rp 10,392.35
10.7.2 Tenaga
0.200 Org Pekerja @ Rp 42,200.00 = Rp 8,440.00
0.200 Org Tukang kayu @ Rp 55,600.00 = Rp 11,120.00
0.020 Org Kepala tukang @ Rp 58,000.00 = Rp 1,160.00
0.001 Org Mandor @ Rp 64,700.00 = Rp 64.70
Jumlah (2) = Rp 20,784.70
10.8.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.400 Org Tukang kayu @ Rp 55,600.00 = Rp 22,240.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.00125 Org Mandor @ Rp 64,700.00 = Rp 80.88
Jumlah (2) = Rp 30,100.88
10.9.2 Tenaga
0.040 Org Pekerja @ Rp 42,200.00 = Rp 1,688.00
0.400 Org Tukang kayu @ Rp 55,600.00 = Rp 22,240.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.00125 Org Mandor @ Rp 64,700.00 = Rp 80.88
Jumlah (2) = Rp 25,458.88
10.10.2 Tenaga
0.150 Org Pekerja @ Rp 42,200.00 = Rp 6,330.00
0.250 Org Tukang kayu @ Rp 55,600.00 = Rp 13,900.00
0.025 Org Kepala tukang @ Rp 58,000.00 = Rp 1,450.00
0.00125 Org Mandor @ Rp 64,700.00 = Rp 80.88
Jumlah (2) = Rp 21,760.88
12.6.2 Tenaga
0.700 Org Pekerja @ Rp 42,200.00 = Rp 29,540.00
0.340 Org Tukang batu @ Rp 55,600.00 = Rp 18,904.00
0.034 Org Kepala tukang @ Rp 58,000.00 = Rp 1,972.00
0.035 Org Mandor @ Rp 64,700.00 = Rp 2,264.50
Jumlah (2) = Rp 52,680.50
13.3 1 m² Pengecatan bidang kayu baru ( 1 lapis plamir ), 1 lapis cat dasar,
2 lapis cat penutup.
13.3.1 Bahan
0.200 Kg Cat meni @ Rp 16,800.00 = Rp 3,360.00
0.150 Kg Plamir @ Rp 10,200.00 = Rp 1,530.00
0.170 Kg Cat dasar @ Rp 15,600.00 = Rp 2,652.00
0.260 Kg Cat penutup 2 kali @ Rp 15,600.00 = Rp 4,056.00
Jumlah (1) = Rp 11,598.00
13.3.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.009 Org Tukang cat @ Rp 55,600.00 = Rp 500.40
0.006 Org Kepala tukang @ Rp 58,000.00 = Rp 348.00
0.0025 Org Mandor @ Rp 64,700.00 = Rp 161.75
Jumlah (2) = Rp 3,964.15
13.4 1 m² Pengecatan bidang kayu baru ( 1 lapis plamir ), 1 lapis cat dasar,
3 lapis cat penutup.
13.4.1 Bahan
0.200 Kg Cat meni @ Rp 16,800.00 = Rp 3,360.00
0.150 Kg Plamir @ Rp 10,200.00 = Rp 1,530.00
0.170 Kg Cat dasar @ Rp 15,600.00 = Rp 2,652.00
0.350 Kg Cat penutup 3 kali @ Rp 15,600.00 = Rp 5,460.00
Jumlah (1) = Rp 13,002.00
13.4.2 Tenaga
0.070 Org Pekerja @ Rp 42,200.00 = Rp 2,954.00
0.105 Org Tukang cat @ Rp 55,600.00 = Rp 5,838.00
0.004 Org Kepala tukang @ Rp 58,000.00 = Rp 232.00
0.0025 Org Mandor @ Rp 64,700.00 = Rp 161.75
Jumlah (2) = Rp 9,185.75
13.8 1 m² Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis
cat penutup )
13.8.1 Bahan
0.100 Kg Plamir @ Rp 15,600.00 = Rp 1,560.00
0.100 Kg Cat dasar @ Rp 15,600.00 = Rp 1,560.00
0.260 Kg Cat penutup 2x @ Rp 15,600.00 = Rp 4,056.00
Jumlah (1) = Rp 7,176.00
13.8.2 Tenaga
0.020 Org Pekerja @ Rp 42,200.00 = Rp 844.00
0.063 Org Tukang cat @ Rp 55,600.00 = Rp 3,502.80
0.0063 Org Kepala tukang @ Rp 58,000.00 = Rp 365.40
0.0025 Org Mandor @ Rp 64,700.00 = Rp 161.75
Jumlah (2) Rp 4,873.95
13.9 1 m² Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
13.9.1 Bahan
0.120 Kg Cat dasar @ Rp 15,600.00 = Rp 1,872.00
0.180 Kg Cat penutup 2x @ Rp 15,600.00 = Rp 2,808.00
Jumlah (1) = Rp 4,680.00
13.9.2 Tenaga
0.028 Org Pekerja @ Rp 42,200.00 = Rp 1,181.60
0.042 Org Tukang cat @ Rp 55,600.00 = Rp 2,335.20
0.0042 Org Kepala tukang @ Rp 58,000.00 = Rp 243.60
0.0025 Org Mandor @ Rp 64,700.00 = Rp 161.75
Jumlah (2) = Rp 3,922.15
1 PEKERJAAN PERSIAPAN
1 Pengukuran dan pas. Bouwplank m1 119.40 Rp 52,475.50 Rp 6,265,574.70
2 Pendirian pagar keliling m2 151.20 Rp 13,797.00 Rp 2,086,106.40
3 Pembuatan kantor sementara m2 16.00 Rp 4,170,233.00 Rp 66,723,728.00
4 Pembuatan gudang m2 4.00 Rp 4,458,410.00 Rp 17,833,640.00
5 Pembuatan rumah jaga m2 6.00 Rp 5,711,835.00 Rp 34,271,010.00
6 Pembersihan dan perataan lahan m2 240.19 Rp 7,455.00 Rp 1,790,597.81
7 Pembongkaran ls Rp 3,000,000.00 Rp 3,000,000.00
8 Pembersihan pasca pekerjaan ls Rp 3,000,000.00 Rp 3,000,000.00
Jumlah
2 PEKERJAAN TANAH
1 Galian tanah m3 102.64 Rp 119,668.00 Rp 12,282,424.35
2 Galian tanah keras m3 97.75 Rp 130,586.40 Rp 12,764,820.60
3 Urug pasir bawah pondasi m3 4.89 Rp 55,000.00 Rp 268,812.50
4 Pemadatan tanah m3 102.64 Rp 124,535.00 Rp 12,781,961.06
5 Urugan sirtu m3 78.20 Rp 75,000.00 Rp 5,865,000.00
6 Urug tanah kembali m3 102.64 Rp 52,000.00 Rp 5,337,150.00
Jumlah
3 PEKERJAAN PONDASI
1 Pas. Batu kosongan m3 19.55 Rp 255,885.30 Rp 5,002,557.62
2 Pas. Pondasi batu kali m3 18.77 Rp 484,042.50 Rp 9,084,509.64
Jumlah
4 PEKERJAAN BETON
1 Pek. Balok sloof
a. Beton m3 4.40 Rp 864,490.00 Rp 3,802,675.39
b. Bekisting m2 58.65 Rp 405,442.50 Rp 23,779,202.63
c. Pembesian kg 175.00 Rp 11,469.61 Rp 2,007,181.75
2 Pek. Pelat
a. Beton m3 114.25 Rp 864,490.00 Rp 98,763,660.05
b. Bekisting m2 27.39 Rp 1,174,968.80 Rp 32,182,395.43
c. Pembesian kg 175.00 Rp 11,469.61 Rp 2,007,181.75
3 Pek. kolom beton
a. Beton m3 18.14 Rp 636,556.00 Rp 11,549,672.06
b. Bekisting m2 72.58 Rp 1,076,200.80 Rp 78,106,349.26
c. Pembesian kg 225.00 Rp 11,469.61 Rp 2,580,662.25
4 Pek. balok ring
a. Beton m3 3.17 Rp 634,756.00 Rp 2,013,763.41
b. Bekisting m2 72.58 Rp 1,174,968.80 Rp 85,274,535.63
c. Pembesian kg 175.00 Rp 11,469.61 Rp 2,007,181.75
5 Pek. balok
a. Beton m3 8.41 Rp 636,556.00 Rp 5,351,844.57
b. Bekisting m2 33.63 Rp 1,174,968.80 Rp 39,514,200.74
c. Pembesian kg 175.00 Rp 11,469.61 Rp 2,007,181.75
6 Pek. Tangga beton
a. Beton m3 0.22 Rp 864,490.00 Rp 193,645.76
b. Bekisting m3 0.22 Rp 270,295.00 Rp 60,546.08
c. Pembesian kg 175.000 Rp 11,469.61 Rp 2,007,181.75
Jumlah
Jumlah
6 PEKERJAAN KUSEN, DAUN PINTU & JENDELA
1 Kusen pintu dan jendela, kayu kamper m3 10.01 Rp 12,609,410.00 Rp 126,227,507.56
2 Pas. pintu panil kamper m2 46.91 Rp 626,935.00 Rp 29,408,517.75
3 Pas. Pintu & jendela kaca kamper m2 19.83 Rp 533,648.00 Rp 10,581,599.46
4 Pas. pintu dobel plywood, rangka kamper m2 5.41 Rp 425,931.00 Rp 2,304,116.34
5 Pasang kaca 3 mm m2 4.54 Rp 67,971.53 Rp 308,563.53
6 Pasang kaca 5 mm m2 14.98 Rp 69,291.53 Rp 1,037,709.88
Jumlah
Jumlah
8 PEKERJAAN LANGIT-LANGIT
Langit-langit eternit 1.00X1.00
1 Pas. Rangka 1.00X1.00, Kayu Meranti m2 0.12 Rp 107,300.50 Rp 13,391.10
2 Pas. List plafon m1 135.36 Rp 5,384.50 Rp 728,845.92
Jumlah
9 PEKERJAAN CAT
1 Melabur kayu dengan teer m2 72.15 Rp 6,183.20 Rp 446,098.09
2 Pengecatan Dinding baru m2 462.70 Rp 12,049.95 Rp 5,575,550.42
3 Pengecatan Plafon baru m2 228.25 Rp 22,187.75 Rp 5,064,353.94
4 Pengecatan Kayu baru m2 12.63 Rp 15,562.15 Rp 196,596.64
Jumlah
10 PEKERJAAN LISTRIK
1 Pas. Instalasi titik lampu ttk 4.00 Rp 105,000.00 Rp 420,000.00
2 Pas. Instalasi Stop Kontak ttk 10.00 Rp 105,000.00 Rp 1,050,000.00
3 Pas. Sakelar tunggal bh 3.00 Rp 10,000.00 Rp 30,000.00
4 Pas. sakelar ganda bh 3.00 Rp 12,500.00 Rp 37,500.00
5 Pas. Lampu TL 20 w bh 4.00 Rp 82,500.00 Rp 330,000.00
6 Pas. lampu pijar 15 w bh 6.00 Rp 22,000.00 Rp 132,000.00
7 Penangkal petir bh 3.00 Rp 750,000.00 Rp 2,250,000.00
Jumlah
11 PEKERJAAN SANITASI
1 Pas. Closet jongkok bh 1.00 Rp 102,000.00 Rp 102,000.00
2 Pas. Closet duduk bh 1.00 Rp 330,000.00 Rp 330,000.00
4 Pas. Wastafel bh 2.00 Rp 225,000.00 Rp 450,000.00
5 Pas. Bak cuci stainless bh 2.00 Rp 183,000.00 Rp 366,000.00
6 Sumur resapan + septictank unit 2.00 Rp 3,500,000.00 Rp 7,000,000.00
7 Pas. Saluran beton Ø 40 m1 15.00 Rp 52,800.00 Rp 792,000.00
8 Pas. Instalasi pipa pvc 3/4" m1 17.00 Rp 5,875.00 Rp 99,875.00
9 Pas. Instalasi pipa pvc 3" m1 20.00 Rp 23,400.00 Rp 468,000.00
10 Pas. Kran air 1/2'-3/4' bh 5.00 Rp 21,780.00 Rp 108,900.00
Jumlah
Jumlah
Jumlah
Rp 134,970,657
Rp 49,300,169
Rp 14,087,067
Rp 393,209,062
Rp 115,340,329
Rp 169,868,015
Rp 68,582,612
Rp 742,237
Rp 11,282,599
Rp 4,249,500
Rp 9,716,775
Rp 8,029,065
Rp 39,261,544
Rp 1,018,639,630
REKAPITULASI
NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT (%)
A SUB PEKERJAAN :
1 PEKERJAAN PERSIAPAN Rp. 134,970,657 13.25
2 PEKERJAAN TANAH Rp. 49,300,169 4.84
3 PEKERJAAN PONDASI Rp. 14,087,067 1.38
4 PEKERJAAN BETON Rp. 393,209,062 38.60
5 PEKERJAAN PASANGAN & PLESTERAN Rp. 115,340,329 11.32
6 PEKERJAAN KUSEN, DAUN PINTU & JENDELA Rp. 169,868,015 16.68
7 PEKERJAAN RANGKA ATAP & PENUTUP ATAP Rp. 68,582,612 6.73
8 PEKERJAAN LANGIT-LANGIT Rp. 742,237 0.07
9 PEKERJAAN CAT Rp. 11,282,599 1.11
10 PEKERJAAN LISTRIK Rp. 4,249,500 0.42
11 PEKERJAAN SANITASI Rp. 9,716,775 0.95
12 PEKERJAAN KUNCI & PENGGANTUNG Rp. 8,029,065 0.79
13 PEKERJAAN PENUTUP (PAS. KERAMIK) Rp. 39,261,544 3.85
SATU MILYAR SERATUS DUA PULUH JUTA LIMA RATUS TIGA RIBU RUPIAH