RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : PEMELIHARAAN GEDUNG RSI


LOKASI : RUMAH SAKIT ISLAM TULUNGAGUNG

KODE HARGA SATUAN JUMLAH


No URAIAN PEKERJAAN VOLUME SAT.
ANALISA (Rp) ( Rp)
1 2 3 4 5 6 7
I PEKERJAAN RUANG IGD
1 Pengecatan Alur A.4.7.1.10c 32.49 m2 59,790.21 1,942,583.83
JUMLAH 1,942,583.83

II PEKERJAAN POLIKLINIK
1 Pas. Bata merah 1/2 bata cam 1:5 A.4.4.1.10 1.82 m2 135,927.33 247,387.74
2 Plesteran cam 1:5 tebal 15 mm A.4.4.2.5 3.64 m2 56,249.42 204,747.90
3 Pas. Keramik putih A.4.4.3.35b 1.82 m2 186,045.06 338,602.01
4 Pengecatan A.4.7.1.10 3.64 m2 19,981.41 72,732.32
JUMLAH 863,469.97

III PEKERJAAN RUANG RONTGEN


1 Pas. Bata merah 1/2 bata cam 1:5 A.4.4.1.10 0.30 m2 135,927.33 40,778.20
2 Plesteran cam 1:5 tebal 15 mm A.4.4.2.5 0.60 m2 56,249.42 33,749.65
3 Pengecatan A.4.7.1.10 0.60 m2 19,981.41 11,988.84
4 Pas. Keramik putih A.4.4.3.35b 6.75 m2 186,045.06 1,255,804.15
5 Bongkaran klosed dan bak mandi 1.00 Ls 500,000.00 500,000.00
JUMLAH 1,842,320.84

IV PEKERJAAN RUANG APOTEK


1 Pas. Kusen pintu dan jendela kayu balau A.4.6.1.2 0.04 m3 16,438,885.50 657,555.42
2 Pas. Daun pintu kayu balau A.4.6.1.5b 1.60 m2 961,555.80 1,538,489.28
3 Pas. Kunci selot A.4.6.2.11 1.00 bh 317,529.33 317,529.33
4 Pas. Engsel pintu A.4.6.2.5 2.00 bh 28,306.88 56,613.77
5 Pas. Dinding partisi 9.57 m2 205,000.00 1,961,850.00
6 Cat dinding dan partisi A.4.7.1.10 43.74 m2 19,981.41 873,986.74
7 Cat kayu A.4.7.1.4 8.65 bh 44,546.07 385,323.51
8 Pas. Instalasi lampu 4.00 titik 171,000.00 684,000.00
9 Pas. Stop kontak 2.00 bh 12,540.00 25,080.00
10 Pas. Saklar tunggal 2.00 bh 15,618.00 31,236.00
8 Pas. Lampu led 10 w 2.00 bh 85,500.00 171,000.00
JUMLAH 6,702,664.05

V PEKERJAAN RUANG LABORAT


1 Pas. Granit 5.32 m2 225,000.00 1,197,000.00
JUMLAH 1,197,000.00

VI PEKERJAAN RUANG VK BERSALIN


1 Pas. Dinding partisi alumunium 7.08 m2 550,000.00 3,894,000.00
2 Pas. Dinding alumunium sblh utara 5.52 m2 330,000.00 1,821,600.00
3 Pindah pintu lama 1.00 ls 200,000.00 200,000.00
JUMLAH 5,915,600.00

VII PEKERJAAN RUANG ICU


1 Pengecatan A.4.7.1.10 12.99 m2 19,981.41 259,558.48
2 Pas. Exhause 1.00 bh 564,300.00 564,300.00
3 Pas. Instalasi 1.00 titik 171,000.00 171,000.00
JUMLAH 994,858.48

VIII PEKERJAAN RUANG OK


1 Pas.penutup jendela A.4.5.1.7A 5.01 m2 43,349.18 217,179.41
2 Pas. Kusen alumunium A.4.2.1.11 62.50 m' 139,066.32 8,691,645.00
3 Pas. Daun pintu/jendela kaca bingkai alumunium A.4.2.1.13 9.73 m2 666,554.01 6,485,570.52
4 Pas. Engsel pegas 4.00 bh 500,000.00 2,000,000.00
5 Pas. Engsel jendela A.4.6.2.6 6.00 bh 30,115.67 180,693.99
6 Pas. Grendel jendela A.4.6.2.8 3.00 bh 36,613.67 109,841.00
7 Pas. Dinding partisi alumunium 19.38 m2 550,000.00 10,659,000.00
8 Pas. Intalasi blower 1.00 titik 171,000.00 171,000.00
9 Pas. Blower 1.00 bh 564,300.00 564,300.00
10 Cat dinding 137.81 m2 65,000.00 8,957,650.00
11 Bikin lengkungan 45.10 m' 17,000.00 766,700.00
JUMLAH 38,803,579.92

1
IX PEKERJAAN IPS
1 Galian tanah A.2.3.1.1 10.00 m3 19,981.41 199,814.07
2 urug pasir A.2.3.1.11 1.14 m3 261,578.70 298,199.72
3 Pas. Bata rollag A.4.4.1.4 6.00 m2 279,998.82 1,679,992.92
4 Pas. Beton sloof A.4.1.1.21 1.10 m3 256,663.02 282,329.32
5 Pas. Pembesian A.4.1.1.17 106.58 kg 14,204.12 1,513,874.58
6 Pas. Bekisting 2 x pakai A.4.1.1.21 5.80 m2 256,663.02 1,488,645.52
7 Rabat beton A.4.1.1.4 1.04 m3 1,024,148.98 1,065,114.94
8 Pas. Bata 1 : 5 A.4.4.1.10 43.00 m2 135,927.33 5,844,875.19
9 Plesteran A.4.4.2.5 86.00 m2 56,249.42 4,837,450.46
10 Acian A.4.4.2.27 99.00 m2 31,583.70 3,126,786.30
11 Pas. Pipa buangan A.5.1.1.31 4.00 m' 81,668.18 326,672.70
12 Pas. Atap galvalum A.4.7.1.4 24.00 m2 400,000.00 9,600,000.00
13 Pembersihan 1.00 Ls 74,167.19 74,167.19
JUMLAH 30,337,922.91

JUMLAH 88,600,000.00

Terbilang : Delapan puluh delapan juta enam ratus ribu rupiah

Tulungagung, 2019

Dibuat oleh :
CV. UNGGUL ADIKARSA

YOYOK ANDRIANTO,ST
Direktur