2.2.A. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDART 1,284,895,099.61
A.1. PEKERJAAN INSTALASI PLAMBING 413,072,685.03
I INSTALASI AIR BERSIH Rp 236,794,266.89 II INSTALASI AIR KOTOR & AIR BEKAS Rp 107,259,120.72 III INSTALASI AIR HUJAN Rp 55,868,371.23 IV INSTALASI VENT Rp 13,150,926.18
I PEKERJAAN PANEL Rp 304,262,180.43 II PEKERJAAN INSTALASI KABEL FEEDER Rp 139,596,673.35 III PEKERJAAN KABEL LADDER (RAK KABEL) Rp 51,914,262.95 IV PEKERJAAN ARMATUR LAMPU, SAKLAR & STOP KONTAK Rp 136,325,764.15 V PEKERJAAN INSTALASI FINAL Rp 196,940,198.25 VI PEKERJAAN SISTEM PENTANAHAN Rp 12,380,872.95 VII PEKERJAAN PENANGKAL PETIR Rp 30,402,462.50
2.2.B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDART 1,596,043,532.43
B.1. PEKERJAAN PEMADAM KEBAKARAN 68,969,051.01
I INSTALASI PEMIPAAN HYDRANT Rp 68,969,051.01 B.2. PEKERJAAN INSTALASI ELEKTRONIK 85,147,077.59 I PEKERJAAN SYSTEM TV Rp 28,626,227.37 II PEKERJAAN FIRE ALARM Rp 56,520,850.22 B.3. PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN) 1,441,927,403.83 I PEKERJAAN INSTALASI PLAMBING Rp 682,748,831.50 II PEKERJAAN PEMADAM KEBAKARAN Rp 548,210,312.73 III PENYAMBUNGAN DAYA PLN Rp 192,000,000.00 IV PEKERJAAN INSTALASI KABEL FEEDER Rp 18,968,259.60