Anda di halaman 1dari 2

REKAPITULASI

RENCANA ANGGARAN BIAYA (RAB) - PEKERJAAN ARSITEKTUR

Pekerjaan :
Lokasi :

Tahun Anggaran : 2019

2.2. PEKERJAAN ARSITEKTUR


JUMLAH HARGA
No. URAIAN PEKERJAAN
(Rp.)

2.2.A. PEKERJAAN ARSITEKTUR STANDART 8,295,507,981.58

A.1. PEKERJAAN LANTAI 1,088,491,575.21


I LANTAI DASAR Rp 260,395,410.08
II LANTAI DUA Rp 260,635,749.68
III LANTAI TIGA Rp 260,635,749.68
IV LANTAI EMPAT Rp 260,635,749.68
IV LANTAI ATAP Rp 46,188,916.09

A.2. PEKERJAAN DINDING 4,942,157,109.44


A.2.A. PEKERJAAN PASANGAN DAN PLESTERAN Rp 3,641,079,760.21
I LANTAI DASAR Rp 800,022,858.10
II LANTAI DUA Rp 921,050,467.42
III LANTAI TIGA Rp 921,050,467.42
IV LANTAI EMPAT Rp 921,050,467.42
IV LANTAI ATAP Rp 77,905,499.83

A.2.B. PEKERJAAN KUSEN PINTU / JENDELA + ASSESORIES Rp 1,301,077,349.24


I LANTAI DASAR Rp 405,013,537.85
II LANTAI DUA Rp 298,687,937.13
III LANTAI TIGA Rp 298,687,937.13
IV LANTAI EMPAT Rp 298,687,937.13

A.3. PEKERJAAN PLAFOND 1,031,923,165.60


I LANTAI DASAR Rp 177,566,158.81
II LANTAI DUA Rp 223,046,583.55
III LANTAI TIGA Rp 223,046,583.55
IV LANTAI EMPAT Rp 408,263,839.69

A.4. PEKERJAAN ATAP 275,472,674.29


I LANTAI ATAP Rp 275,472,674.29

A.5. PEKERJAAN UTILITAS 348,916,964.42


I LANTAI DASAR Rp 56,523,469.61
II LANTAI DUA Rp 97,464,498.27
III LANTAI TIGA Rp 97,464,498.27
IV LANTAI EMPAT Rp 97,464,498.27

A.6. PEKERJAAN FINISHING 608,546,492.62


A.6.A. PEKERJAAN PENGECATAN Rp 577,834,689.19
I LANTAI DASAR Rp 121,305,049.62
II LANTAI DUA Rp 137,344,549.98
III LANTAI TIGA Rp 137,344,549.98
IV LANTAI EMPAT Rp 158,453,687.26
VI LANTAI ATAP Rp 23,386,852.35

REKAP PEK. ARSITEKTUR


REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB) - PEKERJAAN ARSITEKTUR

Pekerjaan :
Lokasi :

Tahun Anggaran : 2019

2.2. PEKERJAAN ARSITEKTUR


JUMLAH HARGA
No. URAIAN PEKERJAAN
(Rp.)

A.6.B. PEKERJAAN ENTRANCE Rp 30,711,803.43

2.2.B. PEKERJAAN ARSITEKTUR NON STANDART 222,032,485.67

B.2. PEKERJAAN DRAINASE KELILING BAGIAN LUAR BANG.(*) 64,736,090.06


I DRAINASE LUAR/SEKELILING BANGUNAN Rp 61,126,383.98
II BAK KONTROL Rp 3,609,706.08
B.3. PEKERJAAN GROUND TANK DAN R. POMPA DI LUAR BANGUNAN 154,096,395.61
B.4. PEK. ALAT ANGKUT SAMPAH 3,200,000.00

SUB TOTAL : 8,517,540,467.25

REKAP PEK. ARSITEKTUR

Anda mungkin juga menyukai