NO. URAIAN PEKERJAAN VOLUME NILAI BOBOT TAHAP PENYE. TINGKAT PENY.
TIAP BG. THD. TIAP BG. PEK. TIAP BG. THD.
SEL. PEK. (%) (%) SEL.PEK.(%)
1 2 3 4 5 6
NO. URAIAN PEKERJAAN VOLUME NILAI BOBOT TAHAP PENYE. TINGKAT PENY.
TIAP BG. THD. TIAP BG. PEK. TIAP BG. THD.
SEL. PEK. (%) (%) SEL.PEK.(%)
1 2 3 4 5 6
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : XI ( Sebelas )
NO. URAIAN PEKERJAAN VOLUME NILAI BOBOT TAHAP PENYE. TINGKAT PENY.
TIAP BG. THD. TIAP BG. PEK. TIAP BG. THD.
SEL. PEK. (%) (%) SEL.PEK.(%)
1 2 3 4 5 6
NO. URAIAN PEKERJAAN VOLUME NILAI BOBOT TAHAP PENYE. TINGKAT PENY.
TIAP BG. THD. TIAP BG. PEK. TIAP BG. THD.
SEL. PEK. (%) (%) SEL.PEK.(%)
1 2 3 4 5 6
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : X ( Sepuluh )
NO. URAIAN PEKERJAAN VOLUME NILAI BOBOT TAHAP PENYE. TINGKAT PENY.
TIAP BG. THD. TIAP BG. PEK. TIAP BG. THD.
SEL. PEK. (%) (%) SEL.PEK.(%)
1 2 3 4 5 6
NO. URAIAN PEKERJAAN VOLUME NILAI BOBOT TAHAP PENYE. TINGKAT PENY.
TIAP BG. THD. TIAP BG. PEK. TIAP BG. THD.
SEL. PEK. (%) (%) SEL.PEK.(%)
1 2 3 4 5 6
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : IX ( Sembilan )
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
0.42
0.37
0.15
0.36
35.61
0.59
37.49
0.90
0.31
1.12
0.28
0.82
3.44
0.42
0.78
0.46
1.07
0.57
0.52
0.31
2.98
0.23
0.33
0.52
8.19
8.74
5.54
0.83
0.31
1.51
16.93
0.67
0.40
0.47
0.30
0.21
0.25
0.09
2.39
2.80
1.17
-
-
3.97
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
0.10
0.09
0.04
0.13
2.86
0.62
3.85
0.28
0.12
-
0.08
0.08
0.08
-
0.28
-
-
-
-
0.93
0.13
-
0.31
0.28
0.27
0.18
-
-
-
-
1.17
-
-
-
-
-
-
-
78.36
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
0.42
0.37
0.15
0.36
35.61
-
36.90
0.90
0.31
-
0.28
0.82
2.32
0.42
0.78
0.46
1.07
0.57
0.52
0.31
2.98
0.23
0.33
0.52
8.19
8.74
4.43
0.42
0.31
0.98
14.88
0.33
0.40
-
-
-
0.31
0.09
1.14
1.08
0.75
-
-
1.82
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
0.28
0.12
-
0.08
0.08
0.08
-
0.28
-
-
-
-
0.93
0.13
-
0.31
0.28
0.27
0.18
-
-
-
-
1.17
-
-
-
-
-
-
-
67.35
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
Minggu : VI ( Enam )
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
0.42
0.37
0.15
-
32.05
-
32.99
0.90
0.31
-
0.28
0.82
2.32
0.42
0.78
0.46
1.07
0.57
0.52
0.31
2.98
0.23
0.33
0.52
8.19
8.74
3.05
-
0.31
-
12.10
-
-
-
-
-
-
-
-
-
-
-
-
-
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
0.28
0.12
-
-
-
-
-
-
-
-
-
-
0.41
0.13
-
0.31
0.28
-
-
-
-
-
-
0.72
-
-
-
-
-
-
-
56.72
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : VI ( Enam )
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
Minggu : V ( Lima )
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
0.42
0.37
0.15
-
28.48
-
29.42
0.90
0.31
-
0.28
0.82
2.32
0.42
0.78
0.46
1.07
0.57
0.52
0.31
-
-
0.33
0.52
4.98
6.12
1.39
-
0.31
-
7.81
-
-
-
-
-
-
-
-
-
-
-
-
-
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
0.13
-
0.31
0.28
-
-
-
-
-
-
0.72
-
-
-
-
-
-
-
45.26
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : V ( Lima )
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
Minggu : IV ( Empat )
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
23.14
-
23.14
0.45
0.16
-
0.10
0.41
1.12
0.42
0.78
0.46
1.07
0.57
0.52
0.31
-
-
0.17
0.26
4.55
3.50
-
-
0.31
-
3.81
-
-
-
-
-
-
-
-
-
-
-
-
-
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
0.13
-
0.31
0.28
-
-
-
-
-
-
0.72
-
-
-
-
-
-
-
33.35
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : IV ( Empat )
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
17.80
-
17.80
-
-
-
-
-
-
0.42
0.78
0.46
1.07
0.57
0.52
0.31
-
-
-
-
4.13
1.75
-
-
0.16
-
1.90
-
-
-
-
-
-
-
-
-
-
-
-
-
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
0.13
-
0.31
0.28
-
-
-
-
-
-
0.72
-
-
-
-
-
-
-
24.56
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
Minggu : II ( Dua )
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
12.46
-
12.46
-
-
-
-
-
-
0.42
0.78
0.46
1.07
0.57
0.52
0.31
-
-
-
-
4.13
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
0.13
-
-
-
-
-
-
-
-
-
0.13
-
-
-
-
-
-
-
16.72
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : II ( Dua )
HARGA SATUAN
NO. U R A I A N SATUAN ( Rp )
1 2 3 4
A. BAHAN PENGISI
1 Pasir Pasang M3 180,000.00
2 Pasir Urug M3 155,000.00
3 Tanah Urug M3 80,000.00
4 Batu Belah 10/15 cm M3 320,000.00
5 Kerikil/Splite 3/5 cm M3 350,000.00
6 Kerikil/Splite 1/2 cm M3 480,000.00
7 Semen Portland Zak 113,000.00
8 Semen Portland Kg 2,260.00
9 Keramik Ukuran 40 x 40 cm Bh 14,200.00
10 Keramik Ukuran 20 x 20 cm Bh 3,050.00
11 Keramik Ukuran 20 x 25 cm Bh 4,100.00
B. BAHAN KAYU
1 Papan Klas III M3 3,200,000.00
2 Papan Kayu klas I tbl. 1.8 cm M3 6,200,000.00
3 Papan Kayu klas II M3 4,800,000.00
4 Kayu Klas II uk. 6/12 - 8/12 M3 4,650,000.00
5 Kayu Klas II uk. 3/5 - 4/6 M3 4,450,000.00
6 Kayu Klas I Uk. 8/8 cm ketam M3 6,950,000.00
7 Kayu Belian Uk. 8/8 cm ketam M3 10,100,000.00
8 Papan lap Uk. 1/7 M' 11,500.00
9 Kayu Klas III M3 3,150,000.00
10 Kalsiboard / GRC Lembar 98,000.00
C. BAHAN BESI
1 Kawat ikat beton Kg 38,250.00
2 Kawat Semen Kg 34,750.00
3 Paku Campuran Kg 31,800.00
4 Paku Genteng Metal Kg 49,500.00
5 Paku Zincalume Kg 52,000.00
6 Besi Beton Kg 18,400.00
HARGA SATUAN
NO. U R A I A N SATUAN ( Rp )
1 2 3 4
E. BAHAN ATAP
1 Atap Genteng Metal SWG 025 M2 54,000.00
2 Atap Zincalume 0.25 Colour M2 86,000.00
3 Plat Zincalume 0.25 Colour M2 88,750.00
Dibuat Oleh,
Konsultan Perencana
CV. MARS KREASI
JOKO SUBAGIO, ST
Team Leader
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
A. PEKERJAAN TANAH
1. 1 M3 Urugan Pasir ( SNI - B. 6. 11 )
C Jumlah A + B 1,080,845.00
C Jumlah A + B 1,049,380.00
C Jumlah A + B 50,364.80
C Jumlah A + B 118,416.00
5. 1 M2 Pasang Lantai Keramik Uk. 40 X 40 cm ( SNI 24.41 )
C Jumlah A + B 209,980.80
C Jumlah A + B 197,480.80
C Jumlah A + B 203,230.80
C. PEKERJAAN KAYU
1 1 M3 Rangka Badan Kayu Klas I ( BOW - F.27 b/ M3 )
C Jumlah A + B 11,125,450.00
C Jumlah A + B 6,702,922.50
C Jumlah A + B 132,160.00
C Jumlah A + B 16,125.00
6. 1 M2 Pek. Ventilasi jalusi kayu klas II (BOW - F.34)
C Jumlah A + B 206,485.00
D. PEKERJAAN ATAP
1. 1 M2 Pekerjaan Atap Genteng Metal (BOW - H.2 )
C Jumlah A + B 119,780.00
C Jumlah A + B 127,150.00
3. 10 M' Bumbungan / Plat Zincalume Colour 0.25
B BAHAN
1 Plat Zincalume 0.25 Colour M' 3.5000 88,750.00 310,625.00
2. Papan kayu klas II M3 0.0720 4,800,000.00 345,600.00
3. Paku Campuran Kg 0.1000 31,800.00 3,180.00
Jumlah 659,405.00
C Jumlah A + B 706,655.00
Harga satuan 1 M' 70,665.50
E. PEKERJAAN PENGECATAN
1. 10 M2 Pekerjaan Mendempul& 1 x cat dasar ( 1,5 K 2 + K 23 + K 30 )
C Jumlah A + B 278,937.50
Harga satuan 1 M2 27,893.75
2. 10 M2 Pekerjaan 2 x Mengecat dengan cat kilat ( K. 23 & K. 30 )
C Jumlah A + B 295,605.00
Harga Satuan 1 M2 29,560.50
C Jumlah A + B 157,690.00
Harga Satuan 1 M2 15,769.00
4. 10 M2 Cat tembok ( K. 36 + K. 23 )
HARGA SATUAN BIAYA SATUAN
NO. U R A I A N SATUAN KUANTITAS (RP) (Rp.)
A TENAGA KERJA
1 Pekerja Hari / orang 0.5000 75,000.00 37,500.00
2 Tukang cat Hari / orang 0.7500 92,500.00 69,375.00
3 Kepala Tukang Hari / orang 0.0750 140,000.00 10,500.00
4 Mandor Hari / orang 0.0250 95,000.00 2,375.00
Jumlah 119,750.00
B BAHAN
1. Cat tembok Kg 2.6000 16,850.00 43,810.00
2. Amplas Lembar 1.0000 4,250.00 4,250.00
Jumlah 48,060.00
C Jumlah A + B 167,810.00
Harga Satuan 1 M2 16,781.00
JOKO SUBAGIO, ST
Team Leader
Konsultan Perencana
CV. MARS KREASI
YANTI OKTAVIANA, ST
Team Leader
ENGINEER ESTIMATE ( EE )
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN (Rp.)
(Rp.)
1 2 3 4 5
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN (Rp.)
(Rp.)
1 2 3 4 5
Dibuat Oleh;
Konsultan Perencana
CV. MARS KREASI
JOKO SUBAGIO, ST
Team Leader
ENGINEER ESTIMATE ( EE )
REKAPITULASI
JUMLAH
NO. URAIAN PEKERJAAN
(Rp.)
I PEKERJAAN PERSIAPAN + PONDASI + LANTAI 180,028,430.87
TERBILANG : EMPAT RATUS DELAPAN PULUH JUTA DUA RATUS RIBU RUPIAH
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
N KONSTRUKSI FISIK (BOBOT)
Minggu : I ( Satu )
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
7.12
-
7.12
-
-
-
-
-
-
0.42
0.39
-
-
-
-
-
-
-
-
-
0.80
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TINGKAT PENY.
TIAP BG. THD.
SEL.PEK.(%)
6
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
7.93
Dibuat Oleh :
Konsultan Pengawas
MU'MININ. ST
Team Leader
LAPORAN KEMAJUAN
KONSTRUKSI FISIK
Minggu Ke : I ( Satu )