A PEKERJAAN LANTAI 1
Nilai Bobot
No Uraian Pekerjaan
(Rp.) (%) 1
1 PEKERJAAN PERSIAPAN Rp 57,130,201.18 2.870% 1.435%
2 PEKERJAAN TANAH Rp 31,960,787.13 1.606%
3 PEKERJAAN PONDASI DAN BETON Rp 1,244,598,475.55 62.527%
4 PEKERJAAN PASANGAN Rp 245,595,402.72 12.338%
5 PEKRJAAN KERAMIK Rp 182,734,632.92 9.180%
6 PEKERJAAN KAYU Rp 15,237,774.83 0.766%
7 PEKERJAAN BESI DAN PENGGANTUNG Rp 116,675,157.28 5.862%
8 PEKERJAAN SANITASI Rp 47,163,419.02 2.369%
9 PEKERJAAN PENGECATAN Rp 49,392,672.73 2.481%
SUB TOTAL Rp 1,990,488,523.35 100.000% 1.435%
BOBOT RENCANA (%) 1.435%
BOBOT REALISASI KOMULATIF (%) 1.435%
KURVA S
Waktu Pelaksanaan
2 3 4 5 6 7 8 9
1.435%
0.321% 0.321% 0.321% 0.321% 0.321%
10.421% 10.421% 10.421% 10.421% 10.421% 10.421%
2.056% 2.056% 2.056% 2.056% 2.056%
3.060%
2.056%
3.060% 3.060%
0.255% 0.255% 0.255%
1.954% 1.954% 1.954%
0.790% 0.790% 0.790%
1.241% 1.241%
5.372% 3.315% 2.209% 2.744% 2.744% 2.031% 1.241%
5.372% 3.315% 2.209% 2.744% 2.744% 2.031% 1.241%
85.717% 89.032% 91.241% 93.985% 96.729% 98.759% 100.000%