Anda di halaman 1dari 6

RENCANA ANGGARAN BIAYA

1.1 Perhitungan volume pekerjaan tubuh bendungan

Titik potong Volume


Beda elv. Inti Tubuh Bendung Fondasi
1 ke 2 5 1055.1332 1095.675 1761.751
2 k2 3 5 4035.096 5246.775 5889.695
3 ke 4 4 15406.022 18833.579 17077.048
4 ke 5 4 9855.5086 14551.183 10335.14
5,6,7 0 10765.0331 12616.495 13027.708
7 ke 8 4 2546.5572 5099.612 13995.08
8 ke 9 5 2457.3885 5074.947 3385.926
9 ke 10 4 2198.8746 5322.6866 3234.764
10 ke 11 5 892.296 3037.942 1485.477
Total 49211.9092 70878.8946 70192.589
ANA ANGGARAN BIAYA
DAFTAR HARGA SATUAN UPAH TENAGA

No Uraian Satuan Sewa (Rp)


1 Mandor Oh Rp 120,000
2 Kepala tukang kayu Oh Rp 116,000
3 Kepala tukang batu Oh Rp 115,000
4 Kepala Tukang besi Oh Rp 116,000
5 Tukang kayu Oh Rp 110,000
6 Tukang batu Oh Rp 110,000
7 Tukang besi Oh Rp 110,000
8 Tukang cat Oh Rp 110,000
9 Tukang pipa Oh Rp 110,000
10 Tukang anyam Oh Rp 110,000
11 Tukang bongkar bekisting Oh Rp 110,000
12 Pekerja Oh Rp 70,000
13 Pengemudi Oh Rp 100,000
14 Operator Oh Rp 100,000
ANALISA HARGA SATUAN PEKERJAAN
Nomor analisa :
Jenis Pekerjaan : Screen Gravel
Satuan : m3
Harga satuan (Rp.) :
Dasar analisa :

HARGA SAT. JLM. HARGA


No. URAIAN SAT. KOEFISIEN
Rp. Rp.
1 BAHAN
Gravel 2/3 m3 1.2 Rp 75,000 Rp 90,000

2 TENAGA
Mandor org/hr 0.01 Rp 120,000 Rp 1,200
Pekerja org/hr 0.3 Rp 70,000 Rp 21,000

3 ALAT

TOTAL Rp 112,200

ANALISA HARGA SATUAN PEKERJAAN


Nomor analisa :
Jenis Pekerjaan : Drain hole dia.2"-0.6m
Satuan : bh
Harga satuan (Rp.) :
Dasar analisa :

HARGA SAT. JLM. HARGA


No. URAIAN SAT. KOEFISIEN
Rp. Rp.
1 BAHAN
Pipa PVC 2' x 4 m m 0.15 Rp 100,000 Rp 15,000
Ijuk kg 0.5 Rp 4,200 Rp 2,100

2 TENAGA
Mandor org/hr 0.01 Rp 120,000 Rp 1,200
Pekerja org/hr 0.15 Rp 70,000 Rp 10,500

3 Alat
Alat bantu 6% tenaga hr 0.06 Rp 70,000 Rp 4,200

TOTAL Rp 33,000

ANALISA HARGA SATUAN PEKERJAAN


Nomor analisa :
Jenis Pekerjaan : Drain hole dia.2"-3m
Satuan : bh
Harga satuan (Rp.) :
Dasar analisa :

HARGA SAT. JLM. HARGA


No. URAIAN SAT. KOEFISIEN
Rp. Rp.
1 BAHAN
Pipa PVC 2' x 4 m m 1 Rp 100,000 Rp 100,000
Ijuk kg 0.5 Rp 4,200 Rp 2,100

2 TENAGA
Mandor org/hr 0.01 Rp 120,000 Rp 1,200
Pekerja org/hr 0.15 Rp 70,000 Rp 10,500

3 Alat
Alat bantu 6% tenaga hr 0.06 Rp 70,000 Rp 4,200

TOTAL Rp 118,000

ANALISA HARGA SATUAN PEKERJAAN


Nomor analisa :
Jenis Pekerjaan : Gebalan Rumput
Satuan : m3
Harga satuan (Rp.) :
Dasar analisa :

HARGA SAT. JLM. HARGA


No. URAIAN SAT. KOEFISIEN
Rp. Rp.
1 BAHAN
Rumput m2 1 Rp 10,000 Rp 10,000
Bambu buah 0.05 Rp 7,000 Rp 350

2 TENAGA
Mandor org/hr 0.01 Rp 120,000 Rp 1,200
Pekerja org/hr 0.15 Rp 70,000 Rp 10,500

3 Alat
Alat bantu 6% tenaga hr 0.06 Rp 70,000 Rp 4,200

TOTAL Rp 26,250
ANALISA MOBILISASI / DEMOBILISASI
PAKET : 3.3
PEKERJAAN : Terowongan 600 m

JARAK HARGA SAT. JLM. HARGA


No. URAIAN SAT. JUMLAH
KM Rp./Km Rp.

A PERALATAN
1 Excavator (2bh)+Trailer Unit 2 150 Rp 150,000 Rp 45,000,000
2 Crane (2bh) Unit 2 150 Rp 200,000 Rp 60,000,000
3 Concrete Vibrator Unit 4 150 Rp 30,450 Rp 18,270,000
4 Tone Boring Machine (1bh)+Trailer Unit 1 300 Rp 291,000 Rp 87,300,000
5 Jacking Pipe App (2)+Trailer Unit 2 300 Rp 300,000 Rp 180,000,000
6 Ordinary truck (1bh) Unit 2 150 Rp 50,000 Rp 15,000,000
7 Concrete Mixer (2bh) + Truck crane Unit 2 150 Rp 75,000 Rp 22,500,000
8 Pompa Grouting Unit 1 150 Rp 50,000 Rp 7,500,000
9 Generator (1bh)+truck Unit 2 150 Rp 100,000 Rp 30,000,000
10 mesin las Unit 1 150 Rp 50,000 Rp 7,500,000
11 Dump Truck Unit 4 150 Rp 85,650 Rp 51,390,000
Rp 524,460,000
B FASILITAS
1 Direksi keet 1 buah m2 20 Rp 300,000 Rp 6,000,000
2 Gudang m2 40 Rp 100,000 Rp 4,000,000
3 Asrama Unit 1 Rp 3,000,000 Rp 3,000,000
Rp 13,000,000
C TENAGA
1 Pimpinan Pelaksana orang 1 Rp 300,000 Rp 300,000
2 Teknik Konstruksi orang 1 Rp 300,000 Rp 300,000
3 Peralatan orang 4 Rp 200,000 Rp 800,000
4 Geologi orang 4 Rp 200,000 Rp 800,000
5 Supertend / Quality orang 4 Rp 200,000 Rp 800,000
6 Geodesi orang 4 Rp 200,000 Rp 800,000
7 Sipil Konstruksi orang 3 Rp 200,000 Rp 600,000
8 Mechanical orang 3 Rp 120,000 Rp 360,000
9 Pengukuran orang 3 Rp 150,000 Rp 450,000
10 Admistrasi orang 1 Rp 225,000 Rp 225,000
11 Bidang Teknik orang 1 Rp 300,000 Rp 300,000
Rp 5,735,000
TOTAL ( A+B+C) Rp 543,195,000
1.3 Rencana anggaran biaya

Nama Bagian Kode Analisa Volume Satuan Harga Satuan Jumlah Harga

pembersihan lahan 1.1 70192.59 M3 Rp 55,500.00 Rp 3,895,688,689.50

galian tanah dengan alat 1.2 70192.59 M3 Rp 200,315.00 Rp 14,060,628,465.54

timbunan kembali dengan alat 1.7 70192.59 M3 Rp 63,632.00 Rp 4,466,494,823.25

pas batu kali 1.5 141071.4836 M3 Rp 1,112,785.00 Rp 156,982,230,877.83

plesteran 1.6 190283.3928 M2 Rp 354,695.00 Rp 67,492,568,009.20

lapisan pasir 2 2523450 M3 Rp 162,600.00 Rp 410,312,970,000.00

bas course 2.1 1125 M3 Rp 494,868.15 Rp 556,726,668.75

sub base course 2.2 750 M3 Rp 284,693.60 Rp 213,520,200.00

clearing dan stripping 2.3 3750 M2 Rp 24,044.75 Rp 90,167,812.50

hand rail 2.4 3000 M Rp 391,060.00 Rp 1,173,180,000.00

bahu jalan 2.5 300 M3 Rp 296,693.60 Rp 89,008,080.00

penetrasi 2.6 275 M2 Rp 1,621,310.00 Rp 445,860,250.00

gorong -gorong diameter 1.5m 2.8 600 M3 Rp 917,895.40 Rp 550,737,240.00

Mobilisasi / Demobilisasi

Bendung & Saluran Pengelak 3.1 1 UNIT Rp 313,011,000.00 Rp 313,011,000.00

Base Camp 3.2 1 UNIT Rp 120,972,000.00 Rp 120,972,000.00

Terowongan 600 m 3.3 1 UNIT Rp 543,195,000.00 Rp 543,195,000.00

Rp 661,306,959,116.56

REAL COST Rp 661,306,959,116.56

PPn 10 % Rp 66,130,695,911.66

JUMLAH REAL COST Rp 727,437,655,028.21

DIBULATKAN Rp 727,437,655,000.00

TUJUH RATUS DUA PULUH TUJUH MILIAR EMPAT RATUS TIGA


Terbilang:
PULUH TUJUH JUTA ENAM RATUS LIMA PULUH LIMA RIBU RUPIAH.