Anda di halaman 1dari 1

LAPORAN MINGGUAN

SKPD : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


PROGRAM : BELANJA PENAMBAHAN NILAI JARINGAN
KEGIATAN : BELANJA PENAMBAHAN NILAI JARINGAN
PEKERJAAN : PENINGKATAN KUALITAS JALAN PINTU MASUK KAWASAN
LOKASI : TN BALURAN, KABUPATEN SITUBONDO
TAHUN ANGGARAN : 2018
TANGGAL KONTRAK : 26 OKTOBER - 14 DESEMBER 2018 Minggu Ke : 4
WAKTU PELAKSANAAN : 50 HARI KELENDER Periode : 16-Nov-2018 S/d 22-Nov-2018

Realisasi Sampai Minggu Realisasi Realisasi Sampai


Harga Jumlah Bobot
Volume Bobot Lalu Minggu Ini Dengan Minggu Ini
No. Uraian Pekerjaan Sat. Satuan Harga Tertimbang
MC AKHIR (%)
(Rp) (Rp) Volume Bobot Volume Bobot Volume Bobot (%)

DIVISI I - U M U M
1.2 Mobilisasi Ls 1.00 3,500,000.00 3,500,000.00 0.86 0.37 0.32 - - 0.37 0.32 36.89%

DIVISI III - PEKERJAAN TANAH


3.1 Pembersihan dan Pembongkaran m² 433.22 31,000.00 13,429,820.00 3.30 - - - - - - 0.00%
3.3 (2) Urugan Pilihan m³ 126.17 119,000.00 15,014,230.00 3.69 118.37 3.46 13.12 0.38 131.49 3.85 104.22%
3.4 Penyiapan Badan Jalan m² 834.40 31,000.00 25,866,400.00 6.36 834.39 6.36 - - 834.39 6.36 100.00%

DIVISI V - PEKERJAAN PERKERASAN BERBUTIR


5.1(2) Lapis Pondasi Agregat Kelas B m³ 169.80 235,000.00 39,903,000.00 9.81 148.79 8.60 21.00 1.21 169.79 9.81 99.99%

DIVISI VI - PEKERJAAN ASPAL


6.1 (1) Lapis Resap Pengikat (Prime Coat) Liter 834.40 12,000.00 10,012,800.00 2.46 - - - - - - 0.00%
6.1 (2) Lapis Resap Perekat (Take Coat) Liter 333.76 13,000.00 4,338,880.00 1.07 - - - - - - 0.00%
6.7 (1) Asphalt Treated Base Leveling (ATB) Ton 116.15 764,000.00 88,738,600.00 21.82 - - - - - - 0.00%
6.8 (1) Asphalt Concrete (AC) Ton 77.77 764,000.00 59,416,280.00 14.61 - - - - - - 0.00%

DIVISI VIII - PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.4 (10) Kerb Pracetak (40 x 30 x 10 K - 350) m' 1,023.16 79,000.00 80,829,640.00 19.88 504.50 9.80 111.20 2.16 615.70 11.96 60.18%
8.4 (12) Paving 21 x 10,5 x 6 K - 350 m² 588.22 69,000.00 40,587,180.00 9.98 212.87 3.61 43.73 0.74 256.60 4.35 43.62%
Pasang topi uskup/stopper (abu - abu) K-350 m' 39.76 132,000.00 5,248,320.00 1.29 - - - - - - 0.00%
Urugan Pasir m³ 45.60 117,000.00 5,335,200.00 1.31 10.64 0.31 2.19 0.06 12.83 0.37 28.14%
Pasangan Batu Bata Merah 1pc : 4Ps m² 72.17 158,000.00 11,402,860.00 2.80 43.54 1.69 11.12 0.43 54.66 2.12 75.74%
Plesteran Halus 1 pc : 3 Ps m² 144.35 21,000.00 3,031,350.00 0.75 0.32 0.00 0.10 0.00 0.42 0.00 0.29%

JUMLAH TOTAL FISIK 406,654,560.00 100.00 5.00 39.15

JUMLAH HARGA 406,654,560.00

PPN 10 % 40,665,456.00

JUMLAH TOTAL 447,320,016.00

DIBULATKAN 447,320,000.00

REALISASI PEKERJAAN S/D MINGGU INI 39.15 %

PERSENTASE PEKERJAAN BERDASARKAN RENCANA 47.95 %

DEVIASI (-/+) -8.80 %

DIKETAHUI OLEH : DIPERIKSA OLEH : DILAPORAKAN OLEH :


( PPP ) SITE ENGINEER KONTRAKTOR PELAKSANA
PEJABAT PEMERIKSA DAN PENGAWASAN CV. SKALA MANDIRI NUSANTARA CV. DWI ALAM

HADIS, SE MOSHA DILAS FERRI YOGA.ST ABING


NIP 19700911 200604 1 002 TEAM LEADER Pimpinan Teknik