ESTIMASI ANGGARAN BIAYA

PROJECT PEMBANGUNAN RUMAH TINGGAL 3 LT

LOKASI : JAKARTA

NO URAIAN PEKERJAAN BOBOT JUMLAH HARGA

I PEKERJAAN PERSIAPAN 2,30% Rp. 40.776.250


II PEKERJAAN TANAH & PONDASI 3,07% Rp. 54.451.130
III PEKERJAAN STRUKTUR 20,00% Rp. 354.834.879
IV PEKERJAAN ATAP 8,06% Rp. 142.946.215
V PEKERJAAN DINDING 12,86% Rp. 228.088.378
VI PEKERJAAN KUSEN , PINTU & JENDELA 15,17% Rp. 269.088.000
VII PEKERJAAN PLAFOND 3,44% Rp. 61.074.220
VIII PEKERJAAN PELAPIS LANTAI & DINDING KERAMIK 17,93% Rp. 318.065.249
IX PEKERJAAN BESI/RAILLING/KISI-KISI 1,37% Rp. 24.386.590
X PEKERJAAN PENGECATAN 2,12% Rp. 37.531.668
XI PEKERJAAN SANITARY 7,00% Rp. 124.102.870
XII PEKERJAAN INSTALASI AIR BERSIH & KOTOR 3,76% Rp. 66.659.360
XIII PEKERJAAN INSTALASI LISTRIK 1,95% Rp. 34.636.950
XIV PEKERJAAN LUAR HALAMAN 0,97% Rp. 17.174.080
XV PEKERJAAN LAIN-LAIN 0,00% Rp. -

SUB TOTAL BIAYA PEMBANGUNAN 100,00% 1.773.815.838


JASA KONTRAKTOR ( 10 % ) 177.381.584
TOTAL BIAYA PEMBANGUNAN + JASA KONTRAKTOR 1.951.197.422
DIBULATKAN 1.951.198.000
Luas Bangunan (M²) 438
Harga per M² Bangunan ( Sebelum PPN ) 4.456.000
Januari 2020