ENGINEER'S ESTIMATE
KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA SANITASI
PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5-10 KK)
LOKASI : DESA WAWUGAGA
TAHUN ANGGARAN : 2020

JUMLAH HARG
NO URAIAN PEKERJAAN
(Rp)
A PEKERJAAN PERSIAPAN 1,800,000.00

B PEKERJAAN TANAH 23,225,096.40

C TANGKI SEPTIK PABRIKASI 200,500,000.00

D PEKERJAAN SAMBUNGAN RUMAH (SR) 83,250,390.21

E ANGKUTAN BAHAN PABRIKASI 18,720,000.00

REAL COST 327,495,486.61

PPN 10 % 32,749,548.66

JUMLAH 360,245,035.27

DIBULATKAN 360,000,000.00
TERBILANG :

TIGA RATUS ENAM PULUH JUTA RUPIAH

Sigi Biromaru, 2019


AHLI TEKNIK BANGUNAN GEDUNG
CV. CELEBES ARDHIATAMA CONSULTANT
KHAIDIR, ST
ENGINEER'S ESTIMATE

KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA SANITASI


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5-10 KK)
LOKASI : DESA WAWUGAGA
TAHUN ANGGARAN : 2020

Harga Satuan Jumlah Harga


No. Uraian Pekerjaan Satuan Volume
(Rp) (Rp)
A PEKERJAAN PERSIAPAN
1 Papan Nama Proyek Ls 1.00 300,000 300,000
2 Alat Perlindunga Diri Ls 1.00 250,000 250,000
3 Petugas K3 Ls 1.00 250,000 250,000
4 Kotak P3K Ls 1.00 250,000 250,000
3 Pembersihan Awal Ls 1.00 750,000 750,000
Jumlah Pekerjaan Persiapan 1,800,000
B PEKERJAAN TANAH
1 Galian Tanah Biasa M3 137.68 63,855.00 8,791,556.40
2 Urugan Tanah Kembali M3 120.36 47,300.00 5,693,028.00
3 Urugan Pasir M3 7.20 1,213,960.00 8,740,512.00
Jumlah Pekerjaan Tanah 23,225,096.40
C TANGKI SEPTIK PABRIKASI
1 Pengadaan Tangki Septik Pabrikasi 6 M3 Unit 5.00 40,100,000.00 200,500,000.00
Jumlah Pekerjaan Tangki Septik Pabrikasi 200,500,000.00
D PEKERJAAN SAMBUNGAN RUMAH (SR)
1 Bak Kontrol Bh 18.00 1,104,719.00 19,884,942.00
2 Klosed Jongkok Bh 50.00 200,000.00 10,000,000.00
3 Beton Dudukan Klosed M3 4.28 4,806,527.00 20,591,161.67
4 Plesteran 1 Pc : 3 Ps M2 65.80 82,723.30 5,443,193.14
5 Acian M2 65.80 35,123.00 2,311,093.40
6 Pipa PVC Dia 3" ` M 412.00 60,000.00 24,720,000.00
7 Elbow Ø 3" Bh 4.00 30,000.00 120,000.00
8 Tee Bh 6.00 30,000.00 180,000.00
Jumlah Pekerjaan Sambungan Rumah (SR) 83,250,390.21
E ANGKUTAN BAHAN PABRIKASI
1 Tangki Septik Pabrikasi 6 M3 Unit 5.00 1,800,000.00 9,000,000.00
2 Pipa PVC Dia 3" Btg 103.00 70,000.00 7,210,000.00
3 Elbow Ø 3" Bh 4.00 1,000.00 4,000.00
4 Tee Bh 6.00 1,000.00 6,000.00
5 Klosed Jongkok Bh 50.00 50,000.00 2,500,000.00
Jumlah Pekerjaan Angkutan Bahan Pabrikasi 18,720,000.00

360,000,000.00
474,839,400.00
ANALISA PEKERJAAN

KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA SANITASI


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5-10 KK)
LOKASI : DESA WAWUGAGA
TAHUN ANGGARAN : 2020

1 M³ Galian Tanah Biasa Sedalam 1 Meter s/d 2 Meter


Tenaga
Pekerja 0.675 Oh 75,000.00 50,625.000
Mandor 0.068 Oh 110,000.00 7,425.000
Jumlah 58,050.000
Overhead + Profit 10 % 5,805.000
Harga Satuan Pekerjaan 63,855.000

1 M³ Urugan Tanah Kembali


Tenaga
Pekerja 0.5000 Oh 75,000.00 37,500.00
Mandor 0.0500 Oh 110,000.00 5,500.00
Jumlah 43,000.00
Overhead + Profit 10 % 4,300.00
Harga Satuan Pekerjaan 47,300.00

1 M³ Urugan Pasir
Bahan
Pasir Urug 1.2000 M³ 900,000.00 1,080,000.00
Tenaga
Pekerja 0.3000 Oh 75,000.00 22,500.00
Mandor 0.0100 Oh 110,000.00 1,100.00
Jumlah 1,103,600.00
Overhead + Profit 10 % 110,360.00
Harga Satuan Pekerjaan 1,213,960.00

1 Bh Bak Kontrol (60 x 60)


Bahan
Batu Bata 186.0000 Bh 900.00 167,400.00
Semen Portland 114.0000 Kg 3,000.00 342,000.00
Pasir Pasang 0.1840 M³ 900,000.00 165,600.00
Kerikil 0.0330 M³ 900,000.00 29,700.00
Besi Beton 4.8500 Kg 11,000.00 53,350.00
Tenaga -
Pekerja 2.16 Oh 75,000.00 162,000.00
Tukang 0.72 Oh 90,000.00 64,800.00
Kepala Tukang 0.0720 Oh 105,000.00 7,560.00
Mandor 0.1080 Oh 110,000.00 11,880.00
Jumlah 1,004,290.00
Overhead + Profit 10 % 100,429.00
Harga Satuan Pekerjaan 1,104,719.00

1 M² Plesteran 1 Pc : 3 Ps Tebal 15 MM
Bahan
Portland Cement 7.7760 Kg 3,000.00 23,328.00
Pasir Pasang 0.0230 M³ 900,000.00 20,700.00
Tenaga
Pekerja 0.2000 Oh 75,000.00 15,000.00
Tukang Batu 0.1500 Oh 90,000.00 13,500.00
Kepala Tukang 0.0150 Oh 105,000.00 1,575.00
Mandor 0.0100 Oh 110,000.00 1,100.00
Jumlah 75,203.00
Overhead + Profit 10 % 7,520.30
Harga Satuan Pekerjaan 82,723.30

1 M² Acian
Bahan
Portland Cement 3.2500 Kg 3,000.00 9,750.00
Tenaga
Pekerja 0.1500 Oh 75,000.00 11,250.00
Tukang Batu 0.1000 Oh 90,000.00 9,000.00
Kepala Tukang 0.0100 Oh 105,000.00 1,050.00
Mandor 0.0080 Oh 110,000.00 880.00
Jumlah 31,930.00
Overhead + Profit 10 % 3,193.00
Harga Satuan Pekerjaan 35,123.00

1 M³ Beton K 175
Bahan
Portland Cement 326.0000 Kg 3,000.00 978,000.00
Pasir 1.8400 M³ 900,000.00 1,656,000.00
Kerikil 1.7500 M³ 900,000.00 1,575,000.00
Tenaga
Pekerja 1.6500 Oh 75,000.00 123,750.00
Tukang Batu 0.2750 Oh 90,000.00 24,750.00
Kepala Tukang 0.0280 Oh 105,000.00 2,940.00
Mandor 0.0830 Oh 110,000.00 9,130.00
Jumlah 4,369,570.00
Overhead + Profit 10 % 436,957.00
Harga Satuan Pekerjaan 4,806,527.00
DAFTAR HARGA UPAH

KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA SANITASI


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5-10 KK)
LOKASI : DESA WAWUGAGA
TAHUN ANGGARAN : 2020

Harga Satuan
No. Uraian Pekerjaan Satuan Keterangan
(Rp)
1 Mandor OH 110,000.00
2 Kepala Tukang OH 105,000.00
3 Tukang Batu OH 90,000.00
4 Pekerja OH 75,000.00
DAFTAR HARGA BAHAN

KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA SANITASI


PEKERJAAN : PEMBANGUNAN TANGKI SEPTIK SKALA KOMUNAL (5-10 KK)
LOKASI : DESA WAWUGAGA
TAHUN ANGGARAN : 2020

Harga Satuan
No. Uraian Pekerjaan Satuan Keterangan
(Rp)
1 Pipa PVC 3" M¹ 61,000.00
2 Elbow PVC 3" Bh 30,000.00
3 Tee Bh 30,000.00
4 Tangki Septik Bio Fiber Glass Isi 6 M3 Bh 40,100,000.00
5 Klosed Jongkok Bh 200,000.00
6 Semen Portland Kg 3,000.00
7 Batu Bata Bh 900.00
8 Besi Beton Kg 11,000.00
9 Kerikil M³ 900,000.00
10 Pasir Pasang M³ 900,000.00
11 Pasir Urug M³ 900,000.00

20,000,000
28,000,000
TANGKI SEPTIK

Volume Jumlah
4 5 50
632
GALIAN TANAH

Panjang Lebar Tinggi Volume Jumlah Total Panjang Lebar


4.80 3.00 1.34 19.30 5.00 96.48 632.00 0.20

URUGAN PASIR

Panjang Lebar Tinggi Volume Jumlah Total


4.80 3.00 0.10 1.44 5.00 7.20

PASANGAN PONDASI BATU BATA

Panjang Lebar Tinggi Volume Jumlah Total


4.00 1.70 0.20 1.36 5.00 6.80

URUGAN TANAH

V Galian V Urg PasirV Pas. Bata V Tangki


Volume U Tanah
Jumlah Total
19.30 1.44 1.36 4 12.50 5.00 62.48

PIPA PVC 4"

Panjang Jumlah Total


6.00 50.00 300.00

PIPA PVC 6"

Panjang Jumlah Total


30.00 5.00 150.00

Plesteran dan acian

0.34 0.6
0.7 0.7
2 2
0.476 0.84 1.316 50 65.8

Dudukan
0.7
0.6
0.34
0.6
0.08568 50 4.284

3,000,000
257,040
Tinggi Volume Jumlah Total Total
0.40 50.56 1.00 50.56 147.04

360,000,000
360,000,000