Pekerjaan : Belanja Bahan Baku Bangunan Untuk Pemeliharaan Rutin Jalan dan Jembatan

Lokasi : Propinsi Bali


Tahun : 2020

NO URAIAN VOLUME SATUAN BOBOT


1 2 3 4 5 6 7 8 9

Pasir Pasang (Sedang) 622.00 M3


1 3.082 0.257 0.257 0.257 0.257 0.257 0.257 0.257 0.257

M3
2 Batu Kali 1,845.00 10.196 0.850 0.850 0.850 0.850 0.850 0.850 0.850 0.850

M3
3 Agregat Kelas A 72.00 0.398

M3
4 Agregat Kelas B 990.00 5.848 0.731

Zak
5 Semen/ PC (50 Kg) 3,187.00 4.069 0.407 0.407 0.407 0.407 0.407 0.407 0.407

kg
6 Aspal Emulsi CSS-1 45,800.00 9.164 0.458 0.458 0.458 0.458 0.458

kg
7 Aspal Emulsi CRS-1 294,600.00 55.015 2.751 2.751 2.751 2.751 2.751

M3
8 Agregat Halus 1,348.00 6.422 0.535 0.535 0.535

M3
9 Agregat Kasar 1,172.00 5.807 0.484 0.484 0.484 0.484

Roll
10 Wiremesh M6 1.00 0.001 0.001

Rencana 100.00 0.26 0.85 1.51 4.72 5.21 5.74 5.74 5.74 2.24

Komulatif 0.26 1.11 2.62 7.34 12.55 18.29 24.03 29.77 32.02
210.00
7.00 30.00
T I M E S C H E D U L E

MINGGU KE
10 11 12 13 14 15 16 17 18 19 20 21 22 23

0.257 0.257 0.257 0.257

0.850 0.850 0.850 0.850

0.080 0.080 0.080 0.080 0.080

0.731 0.731 0.731 0.731 0.731 0.731 0.731

0.407 0.407 0.407

0.458 0.458 0.458 0.458 0.458 0.458 0.458 0.458 0.458

2.751 2.751 2.751 2.751 2.751 2.751 2.751 2.751 2.751

0.535 0.535 0.535 0.535 0.535 0.535 0.535 0.535 0.535

0.484 0.484 0.484 0.484 0.484 0.484 0.484 0.484

2.32 2.32 2.32 1.92 0.81 4.96 4.96 4.23 4.23 4.23 4.23 4.23 4.23 3.74

34.34 36.67 38.99 40.91 41.72 46.68 51.63 55.86 60.09 64.32 68.55 72.77 77.00 80.75
KETERANGAN
24 25 26 27 28 29 30

Jangka waktu pelaksanaan

210 (Dua Ratus Sepuluh) hari

kalender

P
H
O
0.458 0.458 0.458 0.458 0.458 0.458

2.751 2.751 2.751 2.751 2.751 2.751

- -

3.21 3.21 3.21 3.21 3.21 3.21 -

83.96 87.16 90.37 93.58 96.79 100.00 100.00


T I M E S C H E D U L E

Pekerjaan : Belanja Bahan Baku Bangunan Untuk Pemeliharaan Rutin Jalan dan Jembatan

Lokasi : Propinsi Bali

Tahun : 2020

BULAN KE=
NO URAIAN VOLUME SATUAN BOBOT KETERANGAN
1 2 3 4 5 6 7

1 Pasir Pasang (Sedang) 622.00 M3 3.082 0.770 1.027 1.284 - - - - Jangka waktu pelaksanaan

2 Batu Kali 1,845.00 M3 10.196 2.549 3.399 4.248 - - - - 210 (Dua Ratus Sepuluh) hari

3 Agregat Kelas A 72.00 M3 0.398 - - 0.318 0.080 - - - kalender

4 Agregat Kelas B 990.00 M3 5.848 - - 3.655 2.193 - - -

5 Semen/ PC (50 Kg) 3,187.00 Zak 4.069 0.814 1.628 1.628 - - - -

6 Aspal Emulsi CSS-1 45,800.00 kg 9.164 0.458 1.833 - 1.375 1.833 2.291 1.375

7 Aspal Emulsi CRS-1 294,600.00 kg 55.015 2.751 11.003 - 8.252 11.003 13.754 8.252

8 Agregat Halus 1,348.00 M3 6.422 - 1.605 - 1.605 2.141 1.070 -

9 Agregat Kasar 1,172.00 M3 5.807 - 1.936 - 1.452 1.936 0.484 -

10 Wiremesh M6 1.00 Roll 0.001 - 0.001 - - - - -

Rencana 100.00 7.34 22.43 11.13 14.96 16.91 17.60 9.63

Komulatif 7.34 29.77 40.91 55.86 72.77 90.37 100.00


REKAPITULASI DAFTAR KUANTITAS DAN HARGA

Pekerjaan : Belanja Bahan Baku Bangunan Untuk Pemeliharaan Rutin Jalan da


Lokasi : Propinsi Bali
Tahun : 2020

NO URAIAN VOLUME SATUAN


1 Pasir Pasang (Sedang) 622.00 M3
2 Batu Kali 1,845.00 M3
3 Agregat Kelas A 72.00 M3
4 Agregat Kelas B 990.00 M3
5 Semen/ PC (50 Kg) 3,187.00 Zak
6 Aspal Emulsi CSS-1 45,800.00 kg
7 Aspal Emulsi CRS-1 294,600.00 kg
8 Agregat Halus 1,348.00 M3
9 Agregat Kasar 1,172.00 M3
10 Wiremesh M6 1.00 Roll
Jumlah
PPn 10%
Total
Dibulatkan
S DAN HARGA

unan Untuk Pemeliharaan Rutin Jalan dan Jembatan

HARGA (Rp) JUMLAH (Rp)


260,000.00 161,720,000 3.082
290,000.00 535,050,000 10.196
290,000.00 20,880,000 0.398
310,000.00 306,900,000 5.848
67,000.00 213,529,000 4.069
10,500.00 480,900,000 9.164
9,800.00 2,887,080,000 55.015
250,000.00 337,000,000 6.422
260,000.00 304,720,000 5.807
55,000.00 55,000 0.001
5,247,834,000 100.000
524,783,400
5,772,617,400
5,772,617,000

Kediri, 19 April 2020


CV. DWI CIPTA SARANA

HERU PRASETYO HADI


Direktur
0.0018
9900
JADWAL PELAKSANAAN PEKERJAAN

Pekerjaan : : Belanja Bahan Baku Bangunan Untuk Pemeliharaan Rutin Jalan dan Jembatan
Lokasi : : Propinsi Bali
Tahun : : 2020

BULAN KE-
NO URAIAN KETERANGAN
1 2 3 4 5 6 7
1 Persiapan Jangka waktu pelaksanaan
a Mobilisasi personil dan peralatan 210 (seratus delapan puluh) hari
b Menyusun rencana kerja kalender
c Koordinasi dengan instansi terkait
2 Droping bahan material
3 PHO
4 Penyampaian Laporan akhir pekerjaan