A. Wididarno, ST
Site Operational Manager
II GEDUNGWORKSHOP TERPADU
I PEKERJAAN KAP/ATAP 23.214 74.219% 17.229 24.505% 5.688 98.724% 22.917
II PEKERJAAN PASANGAN / PARTISI 4.670 82.259% 3.842 0.000% - 82.259% 3.842
III PEKERJAAN PLAFOND / RAILLING 1.484 0.520% 0.008 0.000% - 0.520% 0.008
IV PEKERJAAN KERAMIK 3.980 49.761% 1.981 0.000% - 49.761% 1.981
V PEKERJAAN PENGECATAN 0.644 31.144% 0.200 0.000% - 31.144% 0.200
VI PEKERJAAN SANITASI + INSTALASI AIR 2.013 - 72.343% 1.46 72.343% 1.456
VII PEKERJAAN KUSEN / PINTU / JENDELA 3.054 21.505% 0.657 44.196% 1.35 65.701% 2.006
VIII PEKERJAAN PENGGANTUNG / PENGUNCI 0.369 - - -
IX PEKERJAAN ATAP 22.161 55.692% 12.342 9.722% 2.15 65.414% 14.496
X PEKERJAAN TERAS DEPAN , PARIT KELILING BANGUNAN 2.044 - - -
XI PEKERJAAN SIRING + PARIT SEBELAH SIRING - - - -
XII PEKERJAAN HALAMAN PARKIR 3.926 - - -
XIII PEKERJAAN INSTALASI LISTRIK LANTAI SATU 1.324 4.872% 0.064 64.934% 0.86 69.806% 0.924
XIV PANEL SDP I 0.680 - 65.152% 0.44 65.152% 0.443
XV PEKERJAAN FIRE ALARM 0.633 - - -
XVI PEKERJAAN PENANGKAL PETIR TERMASUK BIAYA PERIJINAN DISNAKER 0.209 - - -
` XVII KESELAMATAN DAN KESEHATAN KERJA ( K3 ) 1.034 95.220% 0.985 0.000% - 95.220% 0.985
JUMLAH 71.860 37.729 11.951 49.680
I PEKERJAAN PENDAHULUAN
2 Pembersihan 1 m2 Lapangan dan Perataan termasuk kupas humus m² 1,666.81 0.412 1,666.81 1,666.81 100.00% 0.00% 100.00% 0.412 - 0.412
2.1 Pembersihan 1 m2 Lapangan dan Perataan termasuk kupas humus m² 105.43 0.011 105.43 105.43 100.00% 0.00% 100.00% 0.011 - 0.011
Jumlah I 0.423 0.423 - 0.423
II. BANGUNAN WORKSHOP TERPADU
I. PEKERJAAN KAP/ATAP
PEKERJAAN RANGKA ATAP BAJA + FINISHING CAT
- Lantai I (Elv. + 0.00)
1 Pek Angkur 4 M. 19 (P = 300) bh 136.00 0.084 37.20 - 37.20 27.35% 0.00% 27.35% 0.023 - 0.023
2 Pek. Base Plat 400 x 400 x 12 mm Kg 512.45 0.071 54.27 458.18 512.45 10.59% 89.41% 100.00% 0.008 0.064 0.071
3 Pek Grouting ttk 136.00 0.045 136.00 136.00 0.00% 100.00% 100.00% - 0.045 0.045
4 Pipa Baja OD 88,8 x 5mm (pipa dia. 3 Inch) - Posisi Kolom KD1 Kg 435.73 0.061 303.44 132.29 435.73 69.64% 30.36% 100.00% 0.042 0.018 0.061
5 Pipa Baja OD 273 x 9,3mm (pipa dia. 10 Inch) - Posisi Kolom KD1 Kg 18,316.25 2.548 14,698.93 3,617.31 18,316.25 80.25% 19.75% 100.00% 2.045 0.503 2.548
6 Pipa Baja OD 323,8 x 10,3mm (pipa dia. 12 Inch) - Posisi Kolom KD1 Kg 4,925.59 0.685 3,066.88 1,858.71 4,925.59 62.26% 37.74% 100.00% 0.427 0.259 0.685
Accessories
14 Trekstang Besi dia. 12mm Polos, BJTP U24 - Posisi Ikatan Antar Gording / Purlin Kg 1,093.44 0.152 642.00 451.44 1,093.44 58.71% 41.29% 100.00% 0.089 0.063 0.152
15 Ikatan Angin dia. 16mm Polos, BJTP U24 - Posisi Ikatan Angin Kuda-Kuda Kg 2,406.65 0.335 1,380.66 1,025.98 2,406.65 57.37% 42.63% 100.00% 0.192 0.143 0.335
16 Plat Tebal 6mm - Koneksi Gording / Purlin Kg 1,024.32 0.142 - 1,024.32 1,024.32 0.00% 100.00% 100.00% - 0.142 0.142
17 Plat Tebal 8mm - Koneksi Gording / Purlin dan Koneksi Ikatan Angin Kg 366.96 0.051 220.18 146.79 366.96 60.00% 40.00% 100.00% 0.031 0.020 0.051
18 Plat Tebal 12mm - Koneksi Antar Kuda-Kuda KD2 s/d KD8 Kg 441.81 0.061 44.18 397.63 441.81 10.00% 90.00% 100.00% 0.006 0.055 0.061
19 Plat Tebal 10mm - Koneksi Antar Bracing Kuda-Kuda BRA s/d BRH Kg 2,030.89 0.283 1,218.53 812.36 2,030.89 60.00% 40.00% 100.00% 0.170 0.113 0.283
I. PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN DINDING
- Lantai Basement (Elevasi ± 0.00) 0.467 91.826% 0.428 8.174% 0.038 100.000% 0.467
- Lantai I (Elevasi ± 0.00) 0.249 35.339% 0.088 62.107% 0.154 97.446% 0.242
- Lantai II (Elevasi ± 4.00) 0.046 86.270% 0.040 0.000% - 86.270% 0.040
- Lantai III (Elevasi ± 8.00) 0.036 82.521% 0.030 0.000% - 82.521% 0.030
- Lantai IV (Elevasi ± 12.00) 0.021 0.000% - 0.000% - 0.000% -
Jumlah 0.819 0.586 0.193 0.779
B PEKERJAAN LANTAI
- Lantai Basement (Elevasi ± 0.00) 0.593 84.906% 0.504 15.094% 0.090 100.000% 0.593
- Lantai II (Elevasi ± 4.00) 0.345 88.869% 0.307 11.131% 0.038 100.000% 0.345
- Lantai III (Elevasi ± 8.00) 0.343 87.060% 0.299 12.940% 0.044 100.000% 0.343
- Lantai IV (Elevasi ± 12) 2.235 69.074% 1.543 30.926% 0.691 100.000% 2.235
Jumlah 3.516 2.652 0.863 3.516
C PEKERJAAN PINTU/JENDELA
- Lantai Basement (Elevasi ± 0.00) 0.570 87.862% 0.501 12.138% 0.069 100.000% 0.570
- Lantai I (Elevasi ± 0.00) 0.352 83.608% 0.294 16.392% 0.058 100.000% 0.352
II PEKERJAAN MEKANIKAL
A PEKERJAAN INSTALASI AIR BERSIH 0.024 - 100.000% 0.024 100.000% 0.024
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN 0.037 - 100.000% 0.037 100.000% 0.037
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) 2.829 85.915% 2.431 0.000% - 85.915% 2.431
IV. KESEHATAN DAN KESELAMATAN KERJA ( K3 ) 1.031 95.207% 0.982 0.000% - 95.207% 0.982
a. JUMLAH 28.140 11.969 12.387 24.355
I. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
- Lantai Basement (Elevasi ± 0.00)
1 Balok latai 10/30 cm M' 46.72 0.029 41.53 5.19 46.72 88.90% 11.10% 100.00% 0.026 0.003 0.029
2 Kanopi Jendel beton t. 8 cm
- Pembesian Ø 10 - 15 cm Kg 160.76 0.011 160.76 - 160.76 100.00% 0.00% 100.00% 0.011 - 0.011
- Begesting M² 12.81 0.012 12.81 - 12.81 100.00% 0.00% 100.00% 0.012 - 0.012
-Pembuatan 1 m3 beton mutu fc 7,4 MPa M3 0.76 0.004 0.72 0.04 0.76 95.00% 5.00% 100.00% 0.004 0.000 0.004
3 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm M' 97.50 0.060 92.63 4.88 97.50 95.00% 5.00% 100.00% 0.057 0.003 0.060
4 Pembuatan 1 m2 ring balok beton bertulang (10x15) M' 37.84 0.023 37.84 - 37.84 100.00% 0.00% 100.00% 0.023 - 0.023
5 Pemasangan dinding HB10 campuran 1PC:4PP M² 193.99 0.125 192.98 1.01 193.99 99.48% 0.52% 100.00% 0.124 0.001 0.125
6 Pemasangan plesteran Dinding HB10 tebal 10 mm M² 349.31 0.102 347.16 2.15 349.31 99.38% 0.62% 100.00% 0.101 0.001 0.102
7 Pemasangan Acian M² 349.31 0.070 347.16 2.15 349.31 99.38% 0.62% 100.00% 0.070 0.000 0.070
8 Pemasangan Grill Besi M' 9.67 0.010 9.67 9.67 0.00% 100.00% 100.00% - 0.010 0.010
9 Pasangan dinding Keramik 20x25 (tempat wudhu) M² 14.51 0.020 14.51 14.51 0.00% 100.00% 100.00% - 0.020 0.020
0.467 0.428 0.038 0.467
- Lantai I (Elevasi ± 0.00)
1 Kolom Praktis 11/11 cm M' 95.20 0.059 95.20 - 95.20 100.00% 0.00% 100.00% 0.059 - 0.059
2 Pembuatan Fitur Disabilitas
- Besi Beton Ø 10 - 15 cm kg 71.63 0.005 71.63 71.63 0.00% 100.00% 100.00% - 0.005 0.005
- Begesting M² 6.60 0.006 6.60 6.60 0.00% 100.00% 100.00% - 0.006 0.006
- Cor Beton M3 0.89 0.004 0.89 0.89 0.00% 100.00% 100.00% - 0.004 0.004
- Keramik 30 x 30 (kasar) M² 4.59 0.006 4.59 4.59 0.00% 100.00% 100.00% - 0.006 0.006
- Pas. Guiding Block M² 1.35 0.002 1.35 1.35 0.00% 100.00% 100.00% - 0.002 0.002
- Railing Tangga Stainless steel (disabilitas) M' 9.61 0.059 9.61 9.61 0.00% 100.00% 100.00% - 0.059 0.059
- Railing Tangga Stainless steel (disabilitas) ke Basement M' 11.11 0.069 11.11 11.11 0.00% 100.00% 100.00% - 0.069 0.069
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 19.95 0.013 19.95 - 19.95 100.00% 0.00% 100.00% 0.013 - 0.013
4 Pemasangan plesteran Dinding HB10 tebal 10 mm M² 39.90 0.012 32.97 6.94 39.90 82.62% 17.38% 100.00% 0.010 0.002 0.012
5 Pemasangan Acian M² 39.90 0.008 32.97 6.94 39.90 82.62% 17.38% 100.00% 0.007 0.001 0.008
6 Pas. Dinding Keramik 40x40 (pintu lift) M² 4.08 0.006
0.249 0.088 0.154 0.242
C PEKERJAAN PINTU/JENDELA
- Lantai Basement (Elevasi ± 0.00)
1 PEK. PINTU TYPE P2. uk 150 x 260 CM (6 unit)
- Kusen Alumunium M' 50.40 0.028 47.88 2.52 50.40 95.00% 5.00% 100.00% 0.027 0.001 0.028
- Daun Pintu Alumunium + Kaca 8 mm M² 17.64 0.145 16.76 0.88 17.64 95.00% 5.00% 100.00% 0.138 0.007 0.145
- Kaca 5 mm M² 3.26 0.003 3.10 0.16 3.26 95.00% 5.00% 100.00% 0.003 0.000 0.003
- Kunci Pintu swing Alumunium bh 6.00 0.012 6.00 6.00 0.00% 100.00% 100.00% - 0.012 0.012
- Handle Pintu full set 6.00 0.010 6.00 6.00 0.00% 100.00% 100.00% - 0.010 0.010
- Engsel Pintu bh 36.00 0.015 34.20 1.80 36.00 95.00% 5.00% 100.00% 0.014 0.001 0.015
- Grendel Pintu bh 12.00 0.007 11.40 0.60 12.00 95.00% 5.00% 100.00% 0.007 0.000 0.007
- Door Closer bh 12.00 0.037 12.00 12.00 0.00% 100.00% 100.00% - 0.037 0.037
4 PEK. TERALIS JENDELA M² 103.12 0.106 87.89 15.24 103.12 85.22% 14.78% 100.00% 0.090 0.016 0.106
4 PEK. TERALIS JENDELA M² 103.12 0.106 87.89 87.89 85.22% 0.00% 85.22% 0.090 - 0.090
4 PEK. TERALIS JENDELA M² 70.59 0.073 63.28 7.31 70.59 89.65% 10.35% 100.00% 0.065 0.008 0.073
D. PEKERJAAN PLAFOND
- Lantai Basement (Elevasi ± 0.00)
1 Pemasangan 1 m2 Rangka Besi Hollow Modul 60x60 cm Plafond M² 268.02 0.088 266.00 2.02 268.02 99.25% 0.75% 100.00% 0.088 0.001 0.088
2 Pemasangan 1 m2 Langit-langit Calsiboard (120x240x9) tebal 3,5 mm M² 268.02 0.077 239.40 28.62 268.02 89.32% 10.68% 100.00% 0.069 0.008 0.077
3 Pemasangan 1 m’ list langit-langit Gypsum kecil dan Standar M' 192.58 0.020 95.25 97.33 192.58 49.46% 50.54% 100.00% 0.010 0.010 0.020
0.185 0.166 0.019 0.185
- Lantai IV (Elevasi ± 12)
1 Pemasangan 1 m2 Rangka Besi Hollow Modul 60x60 cm Plafond M² 1,075.65 0.354 1,053.20 22.45 1,075.65 97.91% 2.09% 100.00% 0.347 0.007 0.354
2 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm M² 1,046.56 0.302 950.00 96.56 1,046.56 90.77% 9.23% 100.00% 0.274 0.028 0.302
3 Pemasangan 1 m2 Langit-langit Calsiboard (120x240x9) tebal 3,5 mm M² 29.08 0.008 29.08 0.00 29.08 99.98% 0.02% 100.00% 0.008 0.000 0.008
4 Pemasangan 1 m’ list langit-langit Gypsum kecil dan Standar M' 471.14 0.049 376.91 94.23 471.14 80.00% 20.00% 100.00% 0.039 0.010 0.049
0.713 0.668 0.045 0.713
TOTAL : I.D. PEKERJAAN PLAFOND 0.898 0.835 0.064 0.898
E. PEKERJAAN FINISHING
- Lantai Basement (Elevasi ± 0.00)
1 Pengecatan dinding dalam M² 530.24 0.102 42.10 488.14 530.24 7.94% 92.06% 100.00% 0.008 0.094 0.102
2 Pengecatan dinding luar M² 38.78 0.009 38.78 38.78 0.00% 100.00% 100.00% - 0.009 0.009
3 Pengecatan 1 m2 Plafond M² 268.02 0.051 268.02 268.02 0.00% 100.00% 100.00% - 0.051 0.051
0.162 0.008 0.154 0.162
- Lantai I (Elevasi ± 0.00)
1 Pengecatan ulang dinding lama (luar) M² 449.00 0.086 134.70 314.30 449.00 30.00% 70.00% 100.00% 0.026 0.060 0.086
0.086 0.026 0.060 0.086
H. PEKERJAAN HALAMAN
1 Pekerjaan Selasar Gedung
- Urungan Tanah M3 16.38 0.005 15.56 0.82 16.38 95.00% 5.00% 100.00% 0.005 0.000 0.005
- Urugan Pasir t = 5 cm M3 2.84 0.004 2.70 0.14 2.84 95.00% 5.00% 100.00% 0.003 0.000 0.004
- Pembesian Besi Polos Ø 10 kg 506.43 0.034 481.11 25.32 506.43 95.00% 5.00% 100.00% 0.033 0.002 0.034
- Cor Keliling Bangunan t=10 cm (fc' 12,2 Mpa) M3 5.69 0.031 5.40 0.28 5.69 95.00% 5.00% 100.00% 0.030 0.002 0.031
- Pasangan Keramik 30 x 30 cm Selasar Keliling Bangunan M² 56.88 0.072 56.88 56.88 0.00% 100.00% 100.00% - 0.072 0.072
TOTAL : II.B. PEKERJAAN INSTALASI AIR BUANGAN, AIR HUJAN DAN AIR KOTOR 0.037 - 0.037 0.037
Instalasi Air Conditioning (AC) Portable Floor unit 6.00 1.853 5.00 5.00 83.33% 0.00% 83.33% 1.544 - 1.544
a. Unit Air Conditioning (AC) :
- Fan Coil Unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 55.000 BTUH
F. PEKERJAAN LIFT
1 Pengadaan lift unit 2.00 9.061 0.20 1.40 1.60 10.00% 70.00% 80.00% 0.906 6.343 7.249
Type : Lift Penumpang Type Standard
2 Pekerjaan Pendukung
separator beam IWF 150 ( berat per M minimal 20 kg ) kg 2,880.00 0.401 2,880.00 2,880.00 0.00% 100.00% 100.00% - 0.401 0.401
kolom H Beam dudukan rel hoist way H Beam 100 ( per M min 14 Kg) kg 2,016.00 0.280 2,016.00 2,016.00 0.00% 100.00% 100.00% - 0.280 0.280
Struktur besi untuk pintu Siku 60.60.4 kg 627.20 0.087 627.20 627.20 0.00% 100.00% 100.00% - 0.087 0.087
Pasang AC 1/2 PK smart inverter panasonic Low Wattage unit 2.00 0.058
3 Test commissioning ls 1.00 0.062
TOTAL : II.F. PEKERJAAN LIFT 9.949 0.906 7.111 8.017
Accessories
Trekstang Besi dia. 12mm Polos, BJTP U24 - Posisi Ikatan Antar Gording / Purlin
Ikatan Angin dia. 16mm Polos, BJTP U24 - Posisi Ikatan Angin Kuda-Kuda
Plat (tebal 6,8,10,12 mm) koneksi gording/purlin dan bracing
Jarum Keras dia. 16mm - Ikatan Angin Kuda-Kuda KD1 s/d KD8
Pekerjaan Lantai - 2
Pas. Rangka hollow 40/40, Plafond Gypsum 9mm dan Cornice
List Plafond Profil U
Railling Tangga + Void Stainless Steel
VI PEKERJAAN SANITASI + INSTALASI AIR 2.013 - 2.013 1.456 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
VII PEKERJAAN KUSEN / PINTU / JENDELA 3.054 0.657 2.397 1.350 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Kusen Alumunium
Pintu Type (P1,P2,P3,P4,PD1,PD1A,PD2,PD3,PD4)
Jendela Type (J1,V1,Bovent)
Louvre Aluminium Type L1 (uk 135 x 190 cm) 64 unit
Louvre Aluminium Type L2 (uk 195 x 50 cm) 40 unit
B PEKERJAAN LANTAI 3.516 2.652 0.863 0.863 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
- Lantai Basement (Elevasi - 4.00)
- Lantai I (Elevasi ± 0.00)
- Lantai II (Elevasi ± 4.00)
- Lantai III (Elevasi ± 8.00)
D:\Data Proyek\poltekba\Action Plan sd Minggu
- Lantai IV (Elevasi 38\action plant-juli agst
± 12.00)
Bobot % Bulan JULI Bulan AGUSTUS
NO URAIAN PEKERJAAN Realisasi Renc. Bobot MINGGU-32 MINGGU-33 MINGGU-34 MINGGU-35 MINGGU-36 MINGGU-37 MINGGU-38 KETERANGAN
Cco-02 Sisa Bobot
s/d M-31 s/d M-38 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2
C PEKERJAAN PINTU/JENDELA 2.399 1.982 0.417 0.353 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
- Lantai Basement (Elevasi - 4.00)
- Lantai I (Elevasi ± 0.00)
- Lantai II (Elevasi ± 4.00)
- Lantai III (Elevasi ± 8.00)
- Lantai IV (Elevasi ± 12.00)
D PEKERJAAN PLAFOND 0.898 0.835 0.064 0.064 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
- Lantai Basement (Elevasi - 4.00)
- Lantai IV (Elevasi ± 12.00)
E PEKERJAAN FINISHING 1.655 0.660 0.995 0.995 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
- Cat dinding Lantai Basement (Elevasi - 4.00)
- Cat dinding Lantai I (Elevasi ± 0.00)
- Cat dinding Lantai II (Elevasi ± 4.00)
- Cat dinding Lantai III (Elevasi ± 8.00)
- Cat dinding Lantai IV (Elevasi ± 12.00)
F PEKERJAAN SANITAIR 0.278 - 0.278 0.278 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
G PEKERJAAN ATAP CANOPY 0.878 0.124 0.754 -
H PEKERJAAN HALAMAN 1.767 0.624 1.143 1.143 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
II PEKERJAAN MEKANIKAL 13.027 3.337 9.690 7.356 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
III PEKERJAAN ELEKTRIKAL 1.872 0.188 1.684 1.141 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
IV KESELAMATAN DAN KESEHATAN KERJA ( K3 ) 1.031 0.982 0.049 -
28.140 11.969 16.171 12.387 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.631 0.564 0.564 0.564 0.595 0.595 0.595 0.595 0.595 0.595 0.595 0.451 0.451 0.451 0.451 0.451 0.451 0.451 0.420 0.378 0.378 0.378 0.378 0.378 0.344 0.323 0.323 0.323 0.323 0.323 0.323
Jumlah bobot % 100.000 49.698 50.301 24.337 4.416 4.416 3.584 4.168 3.159 2.654 1.940
Jumlah komulatif % (sd M-38) 74.036 54.114 58.530 62.114 66.282 69.441 72.095 74.036
M-32 M-33 M-34 M-35 M-36 M-37 M-38 Balikpapan, 20 Juli 2020
KETERANGAN : RENCANA SCHEDULE 49.315 51.373 55.457 60.003 64.381 88.616 73.271 PT. Kharisma Menara Abadi
RENCANA ACTION PLANT 54.114 58.530 62.114 66.282 69.441 72.095 74.036 Dibuat :
A. Wididarno,ST
Ops. Manager