44 1.1.4.4.4 Pelat Beton Bertulang K-250 14 days Sun 02-08-20 Sat 15-08-20 0%
45 1.2 PENGGANTIAN TANAMAN 55 days Sun 05-07-20 Fri 28-08-20 0%
46 1.2.1 PEKERJAAN PENGGANTIAN POHON 55 days Sun 05-07-20 Fri 28-08-20 0%
47 1.2.1.1 Pohon Mahoni Ø 0 s/d 20 cm 53 days Sun 05-07-20 Wed 26-08-20 0%
48 1.2.1.2 Pohon Trembesi Ø 0 s/d 20 cm 53 days Sun 05-07-20 Wed 26-08-20 0%
49 1.2.1.3 Pohon Mahoni Ø 0 s/d 20 cm 18 days Sun 09-08-20 Wed 26-08-20 0%
50 1.2.1.4 Pohon Mahoni Ø 20 s/d 30 cm 11 days Sun 16-08-20 Wed 26-08-20 0%
51 1.2.1.5 Pohon Mahoni Ø 0 s/d 20 cm 27 days Sun 02-08-20 Fri 28-08-20 0%
52 1.2.1.6 Pohon Mahoni Ø 20 s/d 30 cm 27 days Sun 02-08-20 Fri 28-08-20 0%
53 1.2.1.7 Kayu galam Ø 8 cm 39 days Sun 19-07-20 Wed 26-08-20 0%