PROJECT MASTER SCHEDULE (PMS) : PEKERJAAN PEMBUATAN LAPANGAN PENUMPUKAN SELUAS 20.

000M2 DITERMINAL PETI KEMAS KARIANGAU

ID WBS Task Name Duration Start Finish % 2020


Complete April July
M M M M M M M M M M M M M M M M M M M M M
1 1 PEKERJAAN PEMBUATAN PENUMPUKAN SELUAS 20.000 120 days Fri 01-05-20 Fri 28-08-20 0%
M2 DITERMINAL PETI KEMAS KARIANGAU
2 1.1 PEKERJAAN SIPIL 120 days Fri 01-05-20 Fri 28-08-20 0%
3 1.1.1 PEKERJAAN PENDAHULUAN 120 days Fri 01-05-20 Fri 28-08-20 0%
4 1.1.1.1 Mobilisasi dan demobilisasi 21 days Fri 01-05-20 Thu 21-05-20 0%
5 1.1.1.2 Membuat Direksi Keet 4 days Fri 01-05-20 Mon 04-05-20 0%
6 1.1.1.3 Pengukuran Lokasi 120 days Fri 01-05-20 Fri 28-08-20 0%
7 1.1.1.4 Penyediaan Air Kerja 120 days Fri 01-05-20 Fri 28-08-20 0%
8 1.1.1.5 Penyediaan Listrik Kerja 120 days Fri 01-05-20 Fri 28-08-20 0%
9 1.1.1.6 Papan Nama Proyek 2 days Fri 01-05-20 Sat 02-05-20 0%
10 1.1.2 PEKERJAAN PEMATANGAN TANAH 42 days Fri 01-05-20 Thu 11-06-20 0%
11 1.1.2.1 Cut n Fill Lahan 30 days Fri 01-05-20 Sat 30-05-20 0%

12 1.1.2.2 Pembersihan Lokasi 14 days Fri 15-05-20 Thu 28-05-20 0%


13 1.1.2.3 Meratakan Tanah + Pemadatan Mencapai CBR diatas 2,521 days Fri 22-05-20 Thu 11-06-20 0%
14 1.1.2.4 Urugan Sirtu tebal 10 Cm 3 days Fri 29-05-20 Sun 31-05-20 0%
15 1.1.3 PEKERJAAN PERKERASAN BETON 86 days Fri 29-05-20 Sat 22-08-20 0%

16 1.1.3.1 Urugan Pasir tebal 4 Cm 21 days Fri 05-06-20 Thu 25-06-20 0%


17 1.1.3.2 Beton Wet lean Concrete tebal 15 Cm 30 days Fri 19-06-20 Sat 18-07-20 0%
18 1.1.3.3 Lembaran Plastik Tipis 30 days Fri 19-06-20 Sat 18-07-20 0%
19 1.1.3.4 Plat tebal 30 Cm Beton bertulang K 400 = 6000 M³ 72 days Fri 12-06-20 Sat 22-08-20 0%
20 1.1.3.4.1 Beton K 400 42 days Sun 12-07-20 Sat 22-08-20 0%
21 1.1.3.4.2 Besi Beton 56 days Fri 12-06-20 Thu 06-08-20 0%
22 1.1.3.4.3 Begesting 42 days Fri 03-07-20 Thu 13-08-20 0%
23 1.1.3.5 Balok 6,3/15 Cm Potongan A-A = 16.22 M³ 49 days Fri 29-05-20 Thu 16-07-20 0%
24 1.1.3.5.1 Beton K 400 14 days Fri 03-07-20 Thu 16-07-20 0%
25 1.1.3.5.2 Besi Beton 30 days Fri 29-05-20 Sat 27-06-20 0%
26 1.1.3.5.3 Begesting 14 days Fri 19-06-20 Thu 02-07-20 0%
27 1.1.3.6 Besi Tie Bar ø 19 - 60 Cm 35 days Fri 19-06-20 Thu 23-07-20 0%
28 1.1.3.7 Joint Sealer (dibentuk) 30 days Fri 17-07-20 Sat 15-08-20 0%
29 1.1.3.8 Balok 6,3/15 Cm Potongan B-B = 17.22 M³ 44 days Fri 05-06-20 Sat 18-07-20 0%
30 1.1.3.8.1 Beton K 400 14 days Sun 05-07-20 Sat 18-07-20 0%
31 1.1.3.8.2 Besi Beton 30 days Fri 05-06-20 Sat 04-07-20 0%
32 1.1.3.8.3 Begesting 14 days Fri 26-06-20 Thu 09-07-20 0%
33 1.1.3.9 Pipa PVC ø 32 Mm jarak 30 Cm panjang 60 Cm 35 days Fri 19-06-20 Thu 23-07-20 0%
34 1.1.3.10 Besi Dowel ø 32 Mm jarak 30 Cm panjang 60 Cm 35 days Fri 19-06-20 Thu 23-07-20 0%
35 1.1.3.11 Joint Sealer di isi stereoform 30 days Sun 12-07-20 Mon 10-08-20 0%
36 1.1.4 PEKERJAAN DRAINASE BETON BERTULANG TERTUTUP 35 Pdays
= 700 M Sun 12-07-20 Sat 15-08-20 0%
37 1.1.4.1 Galian Tanah 14 days Sun 12-07-20 Sat 25-07-20 0%
38 1.1.4.2 Urugan pasir tebal 15 Cm 7 days Sun 19-07-20 Sat 25-07-20 0%
39 1.1.4.3 Lantai Kerja Beton Tumbuk tebal 5 Cm 7 days Sun 19-07-20 Sat 25-07-20 0%
40 1.1.4.4 Beton Bertulang K 400 = 59.5 M³ 35 days Sun 12-07-20 Sat 15-08-20 0%
41 1.1.4.4.1 Beton K 400 14 days Sun 26-07-20 Sat 08-08-20 0%
42 1.1.4.4.2 Besi Beton 21 days Sun 12-07-20 Sat 01-08-20 0%

43 1.1.4.4.3 Begesting 14 days Sun 19-07-20 Sat 01-08-20 0%

44 1.1.4.4.4 Pelat Beton Bertulang K-250 14 days Sun 02-08-20 Sat 15-08-20 0%
45 1.2 PENGGANTIAN TANAMAN 55 days Sun 05-07-20 Fri 28-08-20 0%
46 1.2.1 PEKERJAAN PENGGANTIAN POHON 55 days Sun 05-07-20 Fri 28-08-20 0%
47 1.2.1.1 Pohon Mahoni Ø 0 s/d 20 cm 53 days Sun 05-07-20 Wed 26-08-20 0%
48 1.2.1.2 Pohon Trembesi Ø 0 s/d 20 cm 53 days Sun 05-07-20 Wed 26-08-20 0%
49 1.2.1.3 Pohon Mahoni Ø 0 s/d 20 cm 18 days Sun 09-08-20 Wed 26-08-20 0%
50 1.2.1.4 Pohon Mahoni Ø 20 s/d 30 cm 11 days Sun 16-08-20 Wed 26-08-20 0%
51 1.2.1.5 Pohon Mahoni Ø 0 s/d 20 cm 27 days Sun 02-08-20 Fri 28-08-20 0%
52 1.2.1.6 Pohon Mahoni Ø 20 s/d 30 cm 27 days Sun 02-08-20 Fri 28-08-20 0%
53 1.2.1.7 Kayu galam Ø 8 cm 39 days Sun 19-07-20 Wed 26-08-20 0%

REV.1 ́̅ #◌ୀ$◌ୀ #◌ୀ$◌ୀ ̅ #◌ୀ$◌ୀ