Rencana Anggaran Biaya
Pekerjaan : Stuktur, Arsitektur, Finishing & Mekanikal/Elektrikal
Proyek : RUMAH TINGGAL type 36/60 m2
   R    E    K    A    P    I    T    U    L    A    S   
1 STRUKTUR, ARSITEKTUR & FINISHING
A STRUKTUR
A.1 PEKERJAAN PERSIAPAN Rp               374,400 0,578
A.2 PEKERJAAN PONDASI Rp           6,467,286 9,980
A.3 PEKERJAAN STRUKTUR Rp           7,162,322 11,053
SUB.TOTAL,.. Rp        14,004,008
B ARSITEKTUR
B.1 PEKERJAAN DINDING & BETON PRAKTIS Rp         14,266,405 22,016
B.2 PEKERJAAN ATAP Rp           9,738,590 15,029
SUBTOTAL,.. Rp        24,004,995

C FINISHING Rp        21,416,902 33,051


TOTAL PEKERJAAN STRUKTUR, ARSITEKTUR & FINISHING,... Rp        59,425,905
2 MEKANIKAL & ELEKTRIKAL

A MEKANIKAL Rp           1,657,920 2,559


B ELEKTRIKAL Rp           2,055,000 3,171
C SEPTICTANK & REMBESAN Rp           1,661,157 2,564
TOTAL PEKERJAAN MEKANIKAL & ELEKTRIKAL,... Rp           5,374,077
TOTAL,... Rp        64,799,982 100,00
Dibulatkan,... Rp        64,800,000
TERBILANG : # ENAM PULUH EMPAT JUTA DELAPAN RATUS RIBU RUPIAH #
Hal : Rencana Anggaran Biaya
Pekerjaan : Stuktur, Arsitektur, Finishing & Mekanikal/Elektrikal
Proyek : RUMAH TINGGAL type 36/60 m2
Keterangan Spek Material 
No. Uraian Pekerjaan Sat. Volume Harga Rp. Jumlah Rp.
Yang Dipakai

1 STRUKTUR, ARSITEKTUR & FINISHING

A STRUKTUR

A.1 PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bouwplank m' 24,00 Rp           10,850 Rp             260,400 0,402
2 Pembersihan site m2 60,00 Rp             1,900 Rp             114,000 0,176
Jumlah,... Rp             374,400 0,578
A.2 PEKERJAAN PONDASI
I PONDASI STRAUSSPILE Ø 30 cm
1 Galian tanah m3 13,48 Rp           23,300 Rp             314,131 0,485
2 Pondasi Spesi 1 : 7 m3 7,30 Rp        416,700 Rp         3,043,056 4,696
Jumlah,... Rp         3,357,187
II SLOOF
1 Begisting Kayu albasiah m2 18,34 Rp           28,200 Rp             517,075 0,798
2 Tulangan besi Mutu baja U‐24 kg 155,20 Rp           11,640 Rp         1,806,519 2,788
3 Cor beton Spesi 1 : 3 : 5 m3 0,92 Rp        684,000 Rp             627,091 0,968
Jumlah,... Rp         2,950,685
III ROLLAG BATA
1 Pasang rollag bata Spesi 1 : 5 m2 1,57 Rp           53,700 Rp               84,175 0,130
2 Plesteras Spesi 1 : 5 m2 3,14 Rp           24,000 Rp               75,240 0,116
Jumlah,... Rp             159,415

Sub Total  Pekerjaan Pondasi Rp         6,467,287 9,980


A.3 PEKERJAAN STRUKTUR
I KOLOM BETON
1 Tulangan besi Mutu baja U‐24 kg 33,82 Rp           11,640 Rp             393,618 0,607
2 Begisting Kayu albasiah m2 1,80 Rp           28,200 Rp               50,760 0,078
3 Cor beton Spesi 1 : 3 : 5 m3 0,09 Rp        684,000 Rp               61,560 0,095
Jumlah,... Rp             505,938
II BALOK BETON
1 Tulangan besi Mutu baja U‐24 kg 23,36 Rp           11,640 Rp             393,618 0,607
2 Begisting Kayu albasiah m2 1,58 Rp           28,200 Rp               50,760 0,078
3 Cor beton Spesi 1 : 3 : 5 m3 0,15 Rp        684,000 Rp               61,560 0,095
Jumlah,... Rp             505,938
III CANOPY BETON
1 Tulangan besi Mutu baja U‐24 kg 39,14 Rp           11,640 Rp             455,538 0,703
2 Stoot werk Bambu + kayu m2 4,04 Rp           37,100 Rp             149,699 0,231
3 Begisting Triplek 6 mm rangka kayu m2 4,04 Rp           53,000 Rp             213,855 0,330
4 Cor beton Spesi 1 : 2 : 3 m3 0,15 Rp        684,000 Rp             275,994 0,426
Jumlah,... Rp         1,095,086
IV KOLOM PRAKTIS, RINGBALK & AMPIG
1 Kolom beton praktis 10/10 cm Beton Spesi 1 : 3 : 5 m' 58,69 Rp           35,500 Rp         2,083,495
2 Ring balk 10/20 cm Beton Spesi 1 : 3 : 5 m' 41,74 Rp           35,500 Rp         1,419,550
3 Ampig 10/10 cm Beton Spesi 1 : 3 : 5 m' 38,73 Rp           35,500 Rp         1,374,915
4 Meja beton dapur Beton Spesi 1 : 3 : 5 m2 0,93 Rp        180,000 Rp             167,400
Jumlah,... Rp         5,045,360
Sub Total  Pekerjaan Struktur Rp         7,152,322
TOTAL PEKERJAAN STRUKTUR,.. Rp       13,994,009
Hal : Rencana Anggaran Biaya
Pekerjaan : Stuktur, Arsitektur, Finishing & Mekanikal/Elektrikal
Proyek : RUMAH TINGGAL type 36/60 m2
Keterangan Spek Material Yang 
No. Uraian Pekerjaan Sat. Volume Harga Rp. Jumlah Rp.
Dipakai

1 STRUKTUR, ARSITEKTUR & FINISHING

B ARSITEKTUR

B.1 PEKERJAAN DINDING 
1 Pasang dinding 1/2 bata Spesi 1:5 m2 121,615 Rp           53,500 Rp            6,506,402
2 Plesteran Spesi 1:5 m2 138,52 Rp           24,500 Rp           3,577,628
3 Acian m2 138,52 Rp           15,500 Rp           2,347,060
4 Tali air kusen m' 83,19 Rp             5,300 Rp               525,595
5 Dinding partisi Spesi 1:5 m2 1,65 Rp           69,500 Rp               152,100
6 Perapihan canopy Spesi 1:4 m2 6,20 Rp           32,500 Rp               350,500
7 Perapihan kolom Spesi 1:5 m2 5,00 Rp           32,500 Rp               194,500
8 Screed + acian canopy Spesi 1:4 m2 4,26 Rp           56,000 Rp               298,560
9 Pemadatan tanah Stemper m2 41,62 Rp             7,350 Rp                 97,500
10 Urugan pasir tebal 2 cm m2 0,83 Rp        248,500 Rp               209,255
Jumlah Rp. Rp         14,259,100
B.2 PEKERJAAN ATAP
1 Gordeng, kaso + reng Baja ringan m2 55,45 Rp           65,000 Rp           3,918,840
2 Penutup atap Genteng beton m2 55,45 Rp           75,000 Rp           4,230,535
3 Wuwung Nok genteng beton m' 9,30 Rp           59,000 Rp               551,395
4 Listplank GRC m' 19,45 Rp           50,000 Rp               520,000
5 Flashing ampig Spesi 1:4 m' 21,00 Rp           24,975 Rp               515,175
Jumlah Rp. Rp           9,735,945

TOTAL PEKERJAAN ARSITEKTUR,… Rp. Rp         23,995,045


C FINISHING

I PEKERJAAN PLAFOND
Rangka hollow + gypsum board 9 
1 Penutup plafond dalam m2 22,35 Rp           50,000 Rp            1,750,000
mm
2 Penutup plafond luar & kamar mandi Rangka hollow + calsiboard 3 mm m2 10,20 Rp           50,000 Rp               510,000
3 list plafond Alumunium U 9mm m2 35,20 Rp           10,000 Rp               292,000
Jumlah Rp. Rp           2,552,000
II PEKERJAAN LANTAI
1 Finishing lantai teras depan & belakang Keramik 30 x 30 cm unpolish m2 2,50 Rp           93,500 Rp               743,454
2 Finishing lantai r.keluarga, k.tidur & Keramik 30 x 30 cm polish m2 29,35 Rp           58,000 Rp           2,343,188
3 Finishing lantai kamar mandi Keramik 30 x 30 cm unpolish m2 1,52 Rp           93,000 Rp               151,500
4 Plint lantai Coak/jegang 3 x 1 1/2 cm m2 37,15 Rp           12,500 Rp               524,000
5 Finishing lantai carport Rabat beton m2 2,95 Rp           24,975 Rp               375,377
Jumlah Rp. Rp           4,137,519
III PEKERJAAN DINDING
1 Finishing dinding kamar mandi Keramik 30 x 30 cm polish m2 5,45 Rp           50,000 Rp           1,750,000
2 Finishing bak mandi Keramik 30 x 30 cm polish m2 2,05 Rp           50,000 Rp               510,000
3 Finishing dinding dapur Keramik 30 x 30 cm polish m2 2,57 Rp           10,000 Rp               292,000
Jumlah Rp. Rp           2,552,000
IV PEKERJAAN SANITER
1 Closet jongkok set 1,00 Rp        125,000 Rp               125,000
2 Floor drain bh 1,00 Rp           25,000 Rp                 25,000
3 Kitchen zink bh 1,00 Rp        150,000 Rp               150,000
4 Kran kitchen zink bh 1,00 Rp           50,000 Rp                 50,000
5 Kran bh 3,00 Rp           25,000 Rp                 75,000
Jumlah Rp. Rp               425,000
V PEKERJAAN KUSEN, PINTU & JENDELA
1 Kusen Kayu meranti m' 48,50 Rp           50,000 Rp           2,522,000
2 Roster Kayu meranti m' 12,40 Rp           49,000 Rp               400,000
3 Pintu panel 81 x 196 cm Frame kayu meranti bh 1,00 Rp        400,000 Rp               400,000
4 Pintu double triplek 72 x 196 cm bh 3,00 Rp        500,000 Rp               500,000
5 Pintu triplek / formika 62 z 196 cm bh 1,00 Rp        300,000 Rp               300,000
6 Jendela 32 x 112 cm Kayu meranti bh 8,00 Rp        150,000 Rp           1,200,000
Jumlah Rp. Rp           5,322,000
Keterangan Spek Material Yang 
No. Uraian Pekerjaan Sat. Volume Harga Rp. Jumlah Rp.
Dipakai
VI PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Engsel pintu ps 5,00 Rp           29,000 Rp             145,000 0,224
2 Engsel jendela ps 8,00 Rp           24,000 Rp             192,000 0,296
3 Kunci pintu utama bh 1,00 Rp        275,000 Rp             275,000 0,424
4 Kunci pintu bh 4,00 Rp        225,000 Rp             900,000 1,389
5 Ram skar ps 8,00 Rp           42,500 Rp             340,000 0,525
6 Slot bh 8,00 Rp           17,500 Rp             140,000 0,216
7 Kaca polos 5 mm m2 2,29 Rp        100,000 Rp             229,440 0,354
8 Kaca buram 5 mm m2 0,20 Rp        150,000 Rp               29,280 0,045
Jumlah Rp. Rp         2,250,720
VII PEKERJAAN PENGECATAN
1 Cat dinding CENDANA m2 138,59 Rp           13,000 Rp          1,801,670 2,780
2 Cat plafond CENDANA m2 39,55 Rp           10,800 Rp             427,118 0,659
3 Cat kusen AVIAN m' 62,85 Rp           19,150 Rp          1,203,578 1,857
4 Cat pintu AVIAN bh 5,00 Rp        189,171 Rp             945,857 1,460
5 Cat jendela AVIAN m' 23,04 Rp           15,320 Rp             352,973 0,545
Jumlah Rp. Rp         4,731,196

TOTAL PEKERJAAN FINISHING,… Rp. Rp       21,416,902 33,051


2 MEKANIKAL DAN ELEKTRIKAL

A MEKANIKAL

I PEKERJAAN INSTALASI AIR BERSIH
1 Pipa PVC diameter 3/4 inch AW WAVIN m' 20,00 Rp           23,800 Rp             476,000 0,735
2 Pipa PVC diameter 1/2 inch AW WAVIN m' 16,00 Rp           22,400 Rp             358,400 0,553
3 Accessories WAVIN ts 1,00 Rp        166,880 Rp             166,880 0,258
Jumlah Rp. Rp         1,001,280
II PEKERJAAN INSTALASI AIR KOTOR, AIR BEKAS, AIR HUJAN
1 Pipa air kotor PVC diameter 3 inch D WAVIN m' 8,00 Rp           49,200 Rp             369,600 0,570
2 Pipa air kotor PVC diameter 2 inch D WAVIN m' 8,00 Rp           29,900 Rp             239,200 0,369
3 Accessories WAVIN ts 1,00 Rp           47,840 Rp               47,840 0,074
Jumlah Rp. Rp             656,640

TOTAL PEKERJAAN MEKANIKAL,… Rp. Rp         1,657,920 2,559


B ELEKTRIKAL
I PANEL
1 Box panel MG bh 1,00 Rp           65,000 Rp               65,000 0,100
2 Instalasi + MCB 6 A MG bh 1,00 Rp           75,000 Rp               75,000 0,116
3 Instalasi + MCB 4 A MG bh 1,00 Rp           75,000 Rp               75,000 0,116
4 Pengkabelan dari meteran PLN ke box panel Kabel nym 3 x 2 1/2 m' 2,00 Rp           15,000 Rp               30,000 0,046
Jumlah Rp. Rp             245,000
II INSTALASI
1 Instalasi penerangan Kabel nym 2 x 1 1/2 titik 8,00 Rp           75,000 Rp             600,000 0,926
2 Instalasi stop kontak Kabel nym 2 x 1 1/3 titik 5,00 Rp           75,000 Rp             375,000 0,579
3 Sparing antena TV titik 1,00 Rp           50,000 Rp               50,000 0,077
Jumlah Rp. Rp         1,025,000
III ARMATURE
1 Lampu downlight + lampu SL ex china bh 8,00 Rp           75,000 Rp             600,000 0,926
2 Saklar engkle BROCO bh 2,00 Rp           15,000 Rp               30,000 0,046
3 Saklar double BROCO bh 2,00 Rp           20,000 Rp               40,000 0,062
4 Stop kontak BROCO bh 5,00 Rp           15,000 Rp               75,000 0,116
5 Stop kontak antena BROCO bh 1,00 Rp           40,000 Rp               40,000 0,062
Jumlah Rp. Rp             785,000

TOTAL PEKERJAAN ELEKTRIKAL,… Rp. Rp         2,055,000 3,171

TOTAL PEKERJAAN MEKANIKAL & ELEKTRIKAL,… Rp. Rp          3,712,920
Keterangan Spek Material Yang 
No. Uraian Pekerjaan Sat. Volume Harga Rp. Jumlah Rp.
Dipakai
3 SEPTICTANK & REMBESAN

I SEPTICTANK ( 2 M3 )
1 Galian tanah Spesi 1:7 m3 2,25 Rp           58,200 Rp             130,950 0,202
2 Pasang dinding 1/2 bata Spesi 1:6 m2 7,50 Rp           53,700 Rp             402,750 0,622
3 Plester & aci Spesi 1:3:5 m2 9,19 Rp           32,450 Rp             298,134 0,460
4 Tutup beton bertulang WAVIN m3 1,50 Rp        184,450 Rp             276,675 0,427
5 Outlet knie PVC 3" WAVIN bh 1,00 Rp           15,000 Rp               15,000 0,023
6 Inlet knie PVC 3" WAVIN bh 1,00 Rp           15,000 Rp               15,000 0,023
7 Pipa PVC 3" WAVIN m' 1,00 Rp           46,300 Rp               46,300 0,071
8 Vent pipa PVC 1" m' 2,00 Rp           26,600 Rp               53,200 0,082
Jumlah Rp. Rp         1,238,009
II REMBESAN
1 Galian tanah m3 0,70 Rp           58,250 Rp               40,957 0,063
2 Pasang 1/4 bata m2 3,75 Rp           26,850 Rp             100,688 0,155
3 Kamprotan m2 0,56 Rp             8,000 Rp               30,000 0,046
4 Tutup beton bertulang Spesi 1:3:5 m2 1,00 Rp        180,450 Rp             101,503 0,157
5 Lapisan injuk, pasir, split & batu belah Ls 1,65 Rp        150,000 Rp             150,000 0,231
Jumlah Rp. Rp             423,148
TOTAL PEKERJAAN SEPTICTANK & REMBESAN,… Rp. Rp         1,661,157 2,564

TOTAL ,… Rp. Rp       64,799,982 100,000