REKAPITULASI MUTUAL CHECK (MC-0)

KEGIATAN : PEMBANGUNAN DAN REHABILITASI GEDUNG


PEKERJAAN : PEMBANGUNAN GEREJA PANTEKOSTA DI BALIKPAPAN
LOKASI : JL. ARJUNA - GN. POLISI RT. 57 NO. 01, KEL. BARU ILIR KEC. BALIKPAPAN BARAT, KOTA BALIKPAPAN
SUMBER DANA : APBD PROVINSI KALIMANTAN TIMUR
TAHUN : 2019

PEKERJAAN TAMBAH DAN KURANG


KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.

I UMUM 41.605.000,00 - - 41.605.000,00 TETAP


II PEKERJAAN TANAH, PASIR DAN PANCANG 229.328.260,00 - - 229.328.260,00 TETAP
III PEKERJAAN KONSTRUKSI 1.379.311.192,79 49.251.080,00 -20.586.830,00 1.407.975.442,79 TAMBAH
IV PEKERJAAN DINDING & LANTAI 692.935.495,00 - - 692.935.495,00 TETAP
V PEKERJAAN ATAP DAN PLAFOND 103.346.140,00 - - 103.346.140,00 TETAP
VI PEKERJAAN KUSEN DAN PARTISI 185.671.000,00 - - 185.671.000,00 TETAP
VII PEKERJAAN LISTRIK & INSTALASI 90.747.000,00 - - 90.747.000,00 TETAP
VIII PEKERJAAN PENANGKAL PETIR 34.500.000,00 - - 34.500.000,00 TETAP
IX PEKERJAAN MEKANIKAL 135.942.500,00 - - 135.942.500,00 TETAP
X PEKERJAAN PENGECATAN DAN LAIN - LAIN 154.562.020,00 - - 154.562.020,00 TETAP
JUMLAH 3.047.948.607,79 49.251.080,00 -20.586.830,00 3.076.612.857,79
PPN 10% 304.794.860,78 4.925.108,00 -2.058.683,00 307.661.285,78
TOTAL JUMLAH 3.352.743.468,57 54.176.188,00 -22.645.513,00 3.384.274.143,57
54.176.188,00 -22.645.513,00 -31.530.675,00
BALIKPAPAN, OKTOBER 2019
DINAS PEKERJAAN UMUM PROV. KALIMANTAN TIMUR KONSULTAN PENGAWAS KONTRAKTOR
BIDANG CIPTA KARYA NUSANIWE KONSULTAN CV. SWAKARYA
PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK)

OKTORIANUS ARI MULYANTO, ST ANASTASIA DWI .A.S.


NIP. 19691015 198902 1 001 SITE ENGINEER SITE MANAGER
MUTUAL CHECK - 0 (MC-0)
KEGIATAN : PEMBANGUNAN DAN REHABILITASI GEDUNG
PEKERJAAN : PEMBANGUNAN GEREJA PANTEKOSTA DI BALIKPAPAN
LOKASI : JL. ARJUNA - GN. POLISI RT. 57 NO. 01, KEL. BARU ILIR KEC. BALIKPAPAN BARAT, KOTA BALIKPAPAN
SUMBER DANA : APBD PROVINSI KALIMANTAN TIMUR
TAHUN : 2019

PEKERJAAN TAMBAH DAN KURANG


KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.

I UMUM
1 Pengukuran dan pasang Bouwplank m1 71.000,00 70,00 4.970.000,00 - - - - 70,00 4.970.000,00 TETAP
2 Sistem Managemen Mutu K3 Konstruksi Unit 30.135.000,00 1,00 30.135.000,00 - - - - 1,00 30.135.000,00 TETAP
3 Mobilisasi dan demobilisasi alat pancang Bore Pile Ls 6.500.000,00 1,00 6.500.000,00 - - - - 1,00 6.500.000,00 TETAP
TOTAL PEKERJAAN UMUM 41.605.000,00 - - 41.605.000,00

II PEKERJAAN TANAH, PASIR DAN PANCANG


1 Galian tanah pondasi m3 79.000,00 44,91 3.547.890,00 - - - - 44,91 3.547.890,00 TETAP
2 Urugan tanah kembali m3 22.000,00 14,97 329.340,00 - - - - 14,97 329.340,00 TETAP
3 Urugan tanah peninggian peil lantai dan pemadatan ( Tanah Pilihan ) m3 180.000,00 42,71 7.688.160,00 - - - - 42,71 7.688.160,00 TETAP
4 Urugan pasir bawah pondasi tebal 5 cm m3 252.000,00 4,86 1.224.720,00 - - - - 4,86 1.224.720,00 TETAP
5 Urugan pasir bawah lantai tebal 10 cm m3 252.000,00 17,17 4.326.840,00 - - - - 17,17 4.326.840,00 TETAP
6 Pasang Pondasi Batu Gunung 1 : 4 m3 1.043.000,00 20,07 20.933.010,00 - - - - 20,07 20.933.010,00 TETAP
7 Pengeboran Tanah untuk Pancang Bored Pile Ø 30 cm m1 215.000,00 224,00 48.160.000,00 - - - - 224,00 48.160.000,00 TETAP
8 Pasang Pancang Bored Pile Ø 30 cm
- Beton Ready Mix K 300 m3 1.972.000,00 15,84 31.236.480,00 - - - - 15,84 31.236.480,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 5.594,09 111.881.820,00 - - - - 5.594,09 111.881.820,00 TETAP
TOTAL PEKERJAAN TANAH, PASIR DAN PANCANG 229.328.260,00 - - 229.328.260,00

III PEKERJAAN KONSTRUKSI


1 Cor Beton lantai rabat t = 10 cm m3 1.199.000,00 17,17 20.586.830,00 - - -17,17 -20.586.830,00 - - KURANG
- Beton Ready Mix K 300 m3 1.972.000,00 - - 17,17 33.859.240,00 - - 17,17 33.859.240,00 TAMBAH
- Pembesian dengan Besi Polos kg 16.000,00 - - 961,99 15.391.840,00 - - 961,99 15.391.840,00 TAMBAH
2 Cor Beton lantai kerja t = 5 cm m3 1.199.000,00 1,51 1.810.490,00 - - - - 1,51 1.810.490,00
3 Cor beton Pilecap Type 1 ( PC1 ) 100 x 100 x 50 cm
- Beton Ready Mix K 300 m3 1.972.000,00 1,00 1.972.000,00 - - - - 1,00 1.972.000,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 265,14 5.302.886,40 - - - - 265,14 5.302.886,40 TETAP
- Bekisting Pilecap m2 198.000,00 4,13 817.660,80 - - - - 4,13 817.660,80 TETAP
4 Cor beton Pilecap Type 2 ( PC2 ) 100 x 150 x 50 cm
- Beton Ready Mix K 300 m3 1.972.000,00 2,10 4.141.200,00 - - - - 2,10 4.141.200,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 495,25 9.905.034,24 - - - - 495,25 9.905.034,24 TETAP
- Bekisting Pilecap m2 198.000,00 7,43 1.471.789,44 - - - - 7,43 1.471.789,44 TETAP
5 Cor beton Pilecap Type 3 ( PC3 ) 140 x 161 x 50 cm
- Beton Ready Mix K 300 m3 1.972.000,00 5,86 11.556.708,80 - - - - 5,86 11.556.708,80 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 1.413,22 28.264.384,51 - - - - 1.413,22 28.264.384,51 TETAP
- Bekisting Pilecap m2 198.000,00 24,08 4.767.840,00 - - - - 24,08 4.767.840,00 TETAP
LANTAI 1
6 Cor beton Tie Beam TB 1 25/55 cm
- Beton Ready Mix K 300 m3 1.972.000,00 5,43 10.710.425,00 - - - - 5,43 10.710.425,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 962,87 19.257.349,10 - - - - 962,87 19.257.349,10 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 405,26 6.484.199,04 - - - - 405,26 6.484.199,04 TETAP
- Bekisting Sloof m2 228.000,00 43,45 9.906.600,00 - - - - 43,45 9.906.600,00 TETAP
7 Cor beton Tie Beam TB 2 25/40 cm
- Beton Ready Mix K 300 m3 1.972.000,00 4,40 8.676.800,00 - - - - 4,40 8.676.800,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 695,37 13.907.450,88 - - - - 695,37 13.907.450,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 295,97 4.735.509,12 - - - - 295,97 4.735.509,12 TETAP
- Bekisting Sloof m2 228.000,00 35,20 8.025.600,00 - - - - 35,20 8.025.600,00 TETAP
8 Cor beton Beam B3 20/40 cm
- Beton Ready Mix K 300 m3 1.972.000,00 0,40 788.800,00 - - - - 0,40 788.800,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 79,86 1.597.178,88 - - - - 79,86 1.597.178,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 31,85 509.574,24 - - - - 31,85 509.574,24 TETAP
- Bekisting Sloof m2 228.000,00 4,00 912.000,00 - - - - 4,00 912.000,00 TETAP
9 Cor beton Beam B4 20/35 cm
- Beton Ready Mix K 300 m3 1.972.000,00 0,49 966.280,00 - - - - 0,49 966.280,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 111,42 2.228.474,88 - - - - 111,42 2.228.474,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 40,76 652.207,68 - - - - 40,76 652.207,68 TETAP
- Bekisting Sloof m2 228.000,00 4,90 1.117.200,00 - - - - 4,90 1.117.200,00 TETAP
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
10 Cor beton Beam B5 20/30 cm
- Beton Ready Mix K 300 m3 1.972.000,00 1,29 2.543.880,00 - - - - 1,29 2.543.880,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 224,63 4.492.608,12 - - - - 224,63 4.492.608,12 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 113,05 1.808.860,32 - - - - 113,05 1.808.860,32 TETAP
- Bekisting Sloof m2 228.000,00 12,90 2.941.200,00 - - - - 12,90 2.941.200,00 TETAP
11 Cor beton Beam B6 15/30 cm
- Beton Ready Mix K 300 m3 1.972.000,00 0,14 266.220,00 - - - - 0,14 266.220,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 31,88 637.633,62 - - - - 31,88 637.633,62 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 14,80 236.736,00 - - - - 14,80 236.736,00 TETAP
- Bekisting Sloof m2 228.000,00 1,80 410.400,00 - - - - 1,80 410.400,00 TETAP
12 Cor beton Balok Bordes B3 20/40 cm ( Lt. 1 - Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,08 165.648,00 - - - - 0,08 165.648,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 24,62 492.410,88 - - - - 24,62 492.410,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 10,10 161.572,32 - - - - 10,10 161.572,32 TETAP
- Bekisting Balok m2 317.000,00 1,14 361.380,00 - - - - 1,14 361.380,00 TETAP
13 Cor beton Balok Bordes B4 20/35 cm ( Lt. 1 - Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,25 498.916,00 - - - - 0,25 498.916,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 87,75 1.755.002,88 - - - - 87,75 1.755.002,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 32,18 514.900,80 - - - - 32,18 514.900,80 TETAP
- Bekisting Balok m2 317.000,00 3,63 1.150.710,00 - - - - 3,63 1.150.710,00 TETAP
14 Cor beton Balok Bordes B4 A 20/35 cm ( Lt. 1 - Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,12 226.780,00 - - - - 0,12 226.780,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 40,40 808.058,88 - - - - 40,40 808.058,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 15,02 240.287,04 - - - - 15,02 240.287,04 TETAP
- Bekisting Balok m2 317.000,00 1,65 523.050,00 - - - - 1,65 523.050,00 TETAP
15 Cor beton Kolom K1 45/35 cm ( Include Pedestal )
- Beton Ready Mix K 300 m3 1.972.000,00 6,93 13.665.960,00 - - - - 6,93 13.665.960,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 1.312,19 26.243.862,48 - - - - 1.312,19 26.243.862,48 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 434,02 6.944.256,00 - - - - 434,02 6.944.256,00 TETAP
- Bekisting Kolom m2 305.000,00 70,40 21.472.000,00 - - - - 70,40 21.472.000,00 TETAP
16 Cor beton Kolom K2 20/45 cm ( Include Pedestal )
- Beton Ready Mix K 300 m3 1.972.000,00 0,72 1.419.840,00 - - - - 0,72 1.419.840,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 135,35 2.706.997,25 - - - - 135,35 2.706.997,25 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 64,12 1.025.856,00 - - - - 64,12 1.025.856,00 TETAP
- Bekisting Kolom m2 305.000,00 10,40 3.172.000,00 - - - - 10,40 3.172.000,00 TETAP
17 Cor beton Kolom Praktis 10/10 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 0,92 1.282.480,00 - - - - 0,92 1.282.480,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 231,00 3.696.000,00 - - - - 231,00 3.696.000,00 TETAP
- Bekisting Kolom m2 305.000,00 18,48 5.636.400,00 - - - - 18,48 5.636.400,00 TETAP
18 Cor beton Balok Latai 10/20 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 0,66 920.040,00 - - - - 0,66 920.040,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 117,94 1.887.040,00 - - - - 117,94 1.887.040,00 TETAP
- Bekisting Balok m2 317.000,00 16,50 5.230.500,00 - - - - 16,50 5.230.500,00 TETAP
LANTAI 2
19 Cor beton Balok B1 25/55 cm ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 3,44 6.783.680,00 - - - - 3,44 6.783.680,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 780,32 15.606.436,10 - - - - 780,32 15.606.436,10 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 328,51 5.256.131,04 - - - - 328,51 5.256.131,04 TETAP
- Bekisting Balok m2 317.000,00 35,52 11.259.840,00 - - - - 35,52 11.259.840,00 TETAP
20 Cor beton Balok B2 25/40 cm ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 3,75 7.385.140,00 - - - - 3,75 7.385.140,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 845,31 16.906.106,88 - - - - 845,31 16.906.106,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 359,69 5.755.052,16 - - - - 359,69 5.755.052,16 TETAP
- Bekisting Balok m2 317.000,00 29,96 9.497.320,00 - - - - 29,96 9.497.320,00 TETAP
21 Cor beton Balok B3 20/40 cm ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 1,76 3.478.608,00 - - - - 1,76 3.478.608,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 498,09 9.961.850,88 - - - - 498,09 9.961.850,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 196,53 3.144.445,92 - - - - 196,53 3.144.445,92 TETAP
- Bekisting Balok m2 317.000,00 17,64 5.591.880,00 - - - - 17,64 5.591.880,00 TETAP
22 Cor beton Balok B4 20/35 cm ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,12 226.780,00 - - - - 0,12 226.780,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 40,40 808.058,88 - - - - 40,40 808.058,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 15,02 240.287,04 - - - - 15,02 240.287,04 TETAP
- Bekisting Balok m2 317.000,00 1,65 523.050,00 - - - - 1,65 523.050,00 TETAP
23 Cor beton Balok B5 20/30 cm ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 1,33 2.626.704,00 - - - - 1,33 2.626.704,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 386,12 7.722.451,62 - - - - 386,12 7.722.451,62 TETAP
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
- Pembesian dengan Besi Polos kg 16.000,00 194,09 3.105.384,48 - - - - 194,09 3.105.384,48 TETAP
- Bekisting Balok m2 317.000,00 13,32 4.222.440,00 - - - - 13,32 4.222.440,00 TETAP
24 Cor beton Balok B6 15/30 cm ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,18 346.086,00 - - - - 0,18 346.086,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 68,35 1.366.953,12 - - - - 68,35 1.366.953,12 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 31,37 501.880,32 - - - - 31,37 501.880,32 TETAP
- Bekisting Balok m2 317.000,00 2,34 741.780,00 - - - - 2,34 741.780,00 TETAP
25 Cor beton Plat Dak tebal 12 cm Lv. + 4.00 ( Lt. 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 20,49 40.406.280,00 - - - - 20,49 40.406.280,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 1.743,31 27.892.926,00 - - - - 1.743,31 27.892.926,00 TETAP
- Bekisting Plat m2 380.000,00 177,78 67.557.160,00 - - - - 177,78 67.557.160,00 TETAP
26 Cor beton Balok Bordes B3 20/40 cm ( Lt. 2 - Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,08 165.648,00 - - - - 0,08 165.648,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 24,62 492.410,88 - - - - 24,62 492.410,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 10,10 161.572,32 - - - - 10,10 161.572,32 TETAP
- Bekisting Balok m2 317.000,00 1,14 361.380,00 - - - - 1,14 361.380,00 TETAP
27 Cor beton Balok Bordes B4 20/35 cm ( Lt. 2 - Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,25 498.916,00 - - - - 0,25 498.916,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 87,75 1.755.002,88 - - - - 87,75 1.755.002,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 32,18 514.900,80 - - - - 32,18 514.900,80 TETAP
- Bekisting Balok m2 317.000,00 3,63 1.150.710,00 - - - - 3,63 1.150.710,00 TETAP
28 Cor beton Balok Bordes B4 A 20/35 cm ( Lt. 2 - Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,12 226.780,00 - - - - 0,12 226.780,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 40,40 808.058,88 - - - - 40,40 808.058,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 15,02 240.287,04 - - - - 15,02 240.287,04 TETAP
- Bekisting Balok m2 317.000,00 1,65 523.050,00 - - - - 1,65 523.050,00 TETAP
29 Cor beton Kolom K1 45/35 cm ( lantai 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 6,24 12.299.364,00 - - - - 6,24 12.299.364,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 1.116,34 22.326.868,08 - - - - 1.116,34 22.326.868,08 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 358,06 5.729.011,20 - - - - 358,06 5.729.011,20 TETAP
- Bekisting Kolom m2 305.000,00 63,36 19.324.800,00 - - - - 63,36 19.324.800,00 TETAP
30 Cor beton Kolom K2 20/45 cm ( lantai 2 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,65 1.277.856,00 - - - - 0,65 1.277.856,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 115,15 2.302.967,81 - - - - 115,15 2.302.967,81 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 52,90 846.331,20 - - - - 52,90 846.331,20 TETAP
- Bekisting Kolom m2 305.000,00 9,36 2.854.800,00 - - - - 9,36 2.854.800,00 TETAP
31 Cor beton Kolom Praktis 10/10 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 0,69 961.860,00 - - - - 0,69 961.860,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 164,24 2.627.840,00 - - - - 164,24 2.627.840,00 TETAP
- Bekisting Kolom m2 305.000,00 13,86 4.227.300,00 - - - - 13,86 4.227.300,00 TETAP
32 Cor beton Balok Latai 10/20 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 0,64 892.160,00 - - - - 0,64 892.160,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 114,37 1.829.920,00 - - - - 114,37 1.829.920,00 TETAP
- Bekisting Balok m2 317.000,00 16,00 5.072.000,00 - - - - 16,00 5.072.000,00 TETAP
LANTAI 3
33 Cor beton Balok B1 25/55 cm ( Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 3,44 6.783.680,00 - - - - 3,44 6.783.680,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 780,32 15.606.436,10 - - - - 780,32 15.606.436,10 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 328,51 5.256.131,04 - - - - 328,51 5.256.131,04 TETAP
- Bekisting Balok m2 317.000,00 35,52 11.259.840,00 - - - - 35,52 11.259.840,00 TETAP
34 Cor beton Balok B2 25/40 cm ( Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 3,75 7.385.140,00 - - - - 3,75 7.385.140,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 845,31 16.906.106,88 - - - - 845,31 16.906.106,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 359,69 5.755.052,16 - - - - 359,69 5.755.052,16 TETAP
- Bekisting Balok m2 317.000,00 29,96 9.497.320,00 - - - - 29,96 9.497.320,00 TETAP
35 Cor beton Balok B3 20/40 cm ( Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 1,98 3.902.666,88 - - - - 1,98 3.902.666,88 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 558,70 11.173.939,20 - - - - 558,70 11.173.939,20 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 220,61 3.529.733,76 - - - - 220,61 3.529.733,76 TETAP
- Bekisting Balok m2 317.000,00 19,79 6.273.556,80 - - - - 19,79 6.273.556,80 TETAP
36 Cor beton Balok B5 20/30 cm ( Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 1,57 3.088.152,00 - - - - 1,57 3.088.152,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 453,85 9.076.902,12 - - - - 453,85 9.076.902,12 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 228,07 3.649.088,16 - - - - 228,07 3.649.088,16 TETAP
- Bekisting Balok m2 317.000,00 15,66 4.964.220,00 - - - - 15,66 4.964.220,00 TETAP
37 Cor beton Balok B6 15/30 cm ( Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,31 615.500,64 - - - - 0,31 615.500,64 TETAP
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
- Pembesian dengan Besi Ulir kg 20.000,00 121,07 2.421.340,74 - - - - 121,07 2.421.340,74 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 55,63 890.127,36 - - - - 55,63 890.127,36 TETAP
- Bekisting Balok m2 317.000,00 4,16 1.319.227,20 - - - - 4,16 1.319.227,20 TETAP
38 Cor beton Plat Dak tebal 12 cm Lv. + 8.00 ( Lt. 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 20,68 40.782.537,60 - - - - 20,68 40.782.537,60 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 1.759,53 28.152.447,84 - - - - 1.759,53 28.152.447,84 TETAP
- Bekisting Plat m2 380.000,00 179,56 68.233.408,00 - - - - 179,56 68.233.408,00 TETAP
39 Cor beton Kolom K1 45/35 cm ( lantai 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 6,24 12.299.364,00 - - - - 6,24 12.299.364,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 1.116,34 22.326.868,08 - - - - 1.116,34 22.326.868,08 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 358,06 5.729.011,20 - - - - 358,06 5.729.011,20 TETAP
- Bekisting Kolom m2 305.000,00 63,36 19.324.800,00 - - - - 63,36 19.324.800,00 TETAP
40 Cor beton Kolom K2 20/45 cm ( lantai 3 )
- Beton Ready Mix K 300 m3 1.972.000,00 0,65 1.277.856,00 - - - - 0,65 1.277.856,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 115,15 2.302.967,81 - - - - 115,15 2.302.967,81 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 52,90 846.331,20 - - - - 52,90 846.331,20 TETAP
- Bekisting Kolom m2 305.000,00 9,36 2.854.800,00 - - - - 9,36 2.854.800,00 TETAP
41 Cor beton Balok Bordes B3 20/40 cm ( Lt. 3 - Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 0,13 250.680,64 - - - - 0,13 250.680,64 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 36,77 735.459,84 - - - - 36,77 735.459,84 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 15,54 248.572,80 - - - - 15,54 248.572,80 TETAP
- Bekisting Balok m2 317.000,00 1,73 546.888,40 - - - - 1,73 546.888,40 TETAP
42 Cor beton Kolom Praktis 10/10 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 1,27 1.770.380,00 - - - - 1,27 1.770.380,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 301,11 4.817.760,00 - - - - 301,11 4.817.760,00 TETAP
- Bekisting Kolom m2 305.000,00 25,41 7.750.050,00 - - - - 25,41 7.750.050,00 TETAP
43 Cor beton Balok Latai 10/20 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 0,78 1.087.320,00 - - - - 0,78 1.087.320,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 139,39 2.230.240,00 - - - - 139,39 2.230.240,00 TETAP
- Bekisting Balok m2 317.000,00 19,50 6.181.500,00 - - - - 19,50 6.181.500,00 TETAP
LANTAI ATAP
44 Cor beton Balok B1 25/55 cm ( Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 3,44 6.783.680,00 - - - - 3,44 6.783.680,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 780,32 15.606.436,10 - - - - 780,32 15.606.436,10 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 328,51 5.256.131,04 - - - - 328,51 5.256.131,04 TETAP
- Bekisting Balok m2 317.000,00 35,52 11.259.840,00 - - - - 35,52 11.259.840,00 TETAP
45 Cor beton Balok B2 25/40 cm ( Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 3,89 7.661.220,00 - - - - 3,89 7.661.220,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 876,87 17.537.402,88 - - - - 876,87 17.537.402,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 373,11 5.969.692,80 - - - - 373,11 5.969.692,80 TETAP
- Bekisting Balok m2 317.000,00 31,08 9.852.360,00 - - - - 31,08 9.852.360,00 TETAP
46 Cor beton Balok B3 20/40 cm ( Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 1,43 2.816.016,00 - - - - 1,43 2.816.016,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 403,40 8.067.962,88 - - - - 403,40 8.067.962,88 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 159,24 2.547.871,20 - - - - 159,24 2.547.871,20 TETAP
- Bekisting Balok m2 317.000,00 14,28 4.526.760,00 - - - - 14,28 4.526.760,00 TETAP
47 Cor beton Balok B5 20/30 cm ( Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 2,39 4.709.609,28 - - - - 2,39 4.709.609,28 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 691,81 13.836.232,80 - - - - 691,81 13.836.232,80 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 347,66 5.562.506,88 - - - - 347,66 5.562.506,88 TETAP
- Bekisting Balok m2 317.000,00 23,88 7.570.720,80 - - - - 23,88 7.570.720,80 TETAP
48 Cor beton Balok B6 15/30 cm ( Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 0,08 159.732,00 - - - - 0,08 159.732,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 31,88 637.633,62 - - - - 31,88 637.633,62 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 14,80 236.736,00 - - - - 14,80 236.736,00 TETAP
- Bekisting Balok m2 317.000,00 1,08 342.360,00 - - - - 1,08 342.360,00 TETAP
49 Cor beton Plat Dak tebal 12 cm Lv. + 12.00 ( Lt. Atap )
- Beton Ready Mix K 300 m3 1.972.000,00 22,03 43.444.737,60 - - - - 22,03 43.444.737,60 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 1.858,78 29.740.551,84 - - - - 1.858,78 29.740.551,84 TETAP
- Bekisting Plat m2 380.000,00 190,81 72.508.864,00 - - - - 190,81 72.508.864,00 TETAP
50 Cor beton Kolom Praktis 10/10 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 0,18 250.920,00 - - - - 0,18 250.920,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 44,00 704.000,00 - - - - 44,00 704.000,00 TETAP
- Bekisting Kolom m2 305.000,00 3,52 1.073.600,00 - - - - 3,52 1.073.600,00 TETAP
51 Cor beton Ringbalk 10/15 cm
- Beton Campuran 1 : 2 : 3 ( Site Mix ) m3 1.394.000,00 1,16 1.617.040,00 - - - - 1,16 1.617.040,00 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 290,00 4.640.000,00 - - - - 290,00 4.640.000,00 TETAP
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
- Bekisting Balok m2 317.000,00 29,00 9.193.000,00 - - - - 29,00 9.193.000,00 TETAP
TANGGA
52 Tangga Lt 1 ke Lt. 2 ( Tangga Depan )
- Beton Ready Mix K 300 m3 1.972.000,00 2,17 4.286.142,00 - - - - 2,17 4.286.142,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 179,54 3.590.752,46 - - - - 179,54 3.590.752,46 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 305,75 4.892.050,80 - - - - 305,75 4.892.050,80 TETAP
- Bekisting Plat m2 387.000,00 21,34 8.260.128,00 - - - - 21,34 8.260.128,00 TETAP
53 Tangga Lt 2 ke Lt. 3 ( Tangga Depan )
- Beton Ready Mix K 300 m3 1.972.000,00 2,17 4.286.142,00 - - - - 2,17 4.286.142,00 TETAP
- Pembesian dengan Besi Ulir kg 20.000,00 179,54 3.590.752,46 - - - - 179,54 3.590.752,46 TETAP
- Pembesian dengan Besi Polos kg 16.000,00 305,75 4.892.050,80 - - - - 305,75 4.892.050,80 TETAP
- Bekisting Plat m2 387.000,00 21,34 8.260.128,00 - - - - 21,34 8.260.128,00 TETAP
54 Tangga Besi Lt 1 ke Lt. 3 ( Tangga Belakang )
- Baja Canal C 125.50.20.3,2 kg 37.000,00 283,21 10.478.622,00 - - - - 283,21 10.478.622,00 TETAP
- Besi Siku L 50.50.4 kg 37.000,00 295,63 10.938.186,67 - - - - 295,63 10.938.186,67 TETAP
- Besi Plat tebal 4 mm kg 37.000,00 476,24 17.620.748,28 - - - - 476,24 17.620.748,28 TETAP
TOTAL PEKERJAAN KONSTRUKSI 1.379.311.192,79 49.251.080,00 -20.586.830,00 1.407.975.442,79

IV PEKERJAAN DINDING & LANTAI


1 Pas. Dinding Bata Ringan camp. 1 : 4 m2 324.000,00 680,62 220.520.880,00 - - - - 680,62 220.520.880,00 TETAP
2 Plesteran dinding 1 : 4 m2 114.000,00 1.334,48 152.130.435,00 - - - - 1.334,48 152.130.435,00 TETAP
3 Acian Dinding m2 54.000,00 1.334,48 72.061.785,00 - - - - 1.334,48 72.061.785,00 TETAP
4 Granite Tile 60/60 cm ( Polished ) (Lantai 1) m2 494.000,00 70,10 34.629.400,00 - - - - 70,10 34.629.400,00 TETAP
5 Granite Tile 60/60 cm ( Polished ) Warna Muda (Lantai 1) m2 499.000,00 52,42 26.157.580,00 - - - - 52,42 26.157.580,00 TETAP
6 Granite Tile 60/60 cm ( UnPolished ) Warna Tua (Lantai 1) m2 499.000,00 15,55 7.759.450,00 - - - - 15,55 7.759.450,00 TETAP
7 Pasangan ACP + Rangka m2 810.000,00 155,32 125.811.225,00 - - - - 155,32 125.811.225,00 TETAP
8 Pasang Benangan Listban dari Plesteran m1 72.500,00 42,00 3.045.000,00 - - - - 42,00 3.045.000,00 TETAP
9 Keramik lantai 30/30 cm ( UnPolish ) Km/Wc m2 309.000,00 31,36 9.690.240,00 - - - - 31,36 9.690.240,00 TETAP
10 Keramik Dinding 30/60 cm ( UnPolish ) Km/Wc m2 300.000,00 109,80 32.940.000,00 - - - - 109,80 32.940.000,00 TETAP
11 Plit Keramik 10/60 cm m1 55.000,00 87,90 4.834.500,00 - - - - 87,90 4.834.500,00 TETAP
12 Keramik Border 10/30 cm ( Unpolish ) Km/Wc m1 55.000,00 61,00 3.355.000,00 - - - - 61,00 3.355.000,00 TETAP
TOTAL PEKERJAAN DINDING & LANTAI 692.935.495,00 - - 692.935.495,00

V PEKERJAAN ATAP DAN PLAFOND


1 Waterproofing Dak Atap m2 238.000,00 152,00 36.176.000,00 - - - - 152,00 36.176.000,00 TETAP
2 Plafond gypsum 9 mm + rangka hollow m2 158.000,00 317,13 50.106.540,00 - - - - 317,13 50.106.540,00 TETAP
3 List Shadow Line m1 40.000,00 426,59 17.063.600,00 - - - - 426,59 17.063.600,00 TETAP
TOTAL PEKERJAAN ATAP DAN PLAFOND 103.346.140,00 - - 103.346.140,00

VI PEKERJAAN KUSEN DAN PARTISI


KUSEN
1 Kusen Type PJ1 Unit 17.947.000,00 2,00 35.894.000,00 - - - - 2,00 35.894.000,00 TETAP
2 Kusen Type P1 Unit 1.982.000,00 1,00 1.982.000,00 - - - - 1,00 1.982.000,00 TETAP
3 Kusen Type P2 Unit 2.150.000,00 3,00 6.450.000,00 - - - - 3,00 6.450.000,00 TETAP
4 Kusen Type P3 Unit 3.260.000,00 3,00 9.780.000,00 - - - - 3,00 9.780.000,00 TETAP
5 Kusen Type P4 Unit 1.635.000,00 8,00 13.080.000,00 - - - - 8,00 13.080.000,00 TETAP
6 Kusen Type P5 Unit 2.190.000,00 2,00 4.380.000,00 - - - - 2,00 4.380.000,00 TETAP
7 Kusen Type PG Unit 920.000,00 1,00 920.000,00 - - - - 1,00 920.000,00 TETAP
8 Kusen Type J1 Unit 4.276.000,00 4,00 17.104.000,00 - - - - 4,00 17.104.000,00 TETAP
9 Kusen Type J2 Unit 6.023.000,00 1,00 6.023.000,00 - - - - 1,00 6.023.000,00 TETAP
10 Kusen Type J3 Unit 4.094.000,00 1,00 4.094.000,00 - - - - 1,00 4.094.000,00 TETAP
11 Kusen Type J4 Unit 15.813.000,00 2,00 31.626.000,00 - - - - 2,00 31.626.000,00 TETAP
12 Kusen Type J5 Unit 3.719.000,00 6,00 22.314.000,00 - - - - 6,00 22.314.000,00 TETAP
13 Kusen Type J6 Unit 8.311.000,00 1,00 8.311.000,00 - - - - 1,00 8.311.000,00 TETAP
14 Kusen Type J7 Unit 12.797.000,00 1,00 12.797.000,00 - - - - 1,00 12.797.000,00 TETAP
15 Kusen Type J8 Unit 1.070.000,00 1,00 1.070.000,00 - - - - 1,00 1.070.000,00 TETAP
16 Kusen Type BV1 Unit 702.000,00 7,00 4.914.000,00 - - - - 7,00 4.914.000,00 TETAP
17 Kusen Type BV2 Unit 411.000,00 12,00 4.932.000,00 - - - - 12,00 4.932.000,00 TETAP
TOTAL PEKERJAAN KUSEN DAN PARTISI 185.671.000,00 - - 185.671.000,00

VII PEKERJAAN LISTRIK & INSTALASI


A PEKERJAAN PANEL
PANEL-PANEL
Pengadaan dan pemasangan panel, termasuk aksesoris dan alat bantu
1 Panel Lantai 1 (Penerangan) Unit 4.350.000,00 1,00 4.350.000,00 - - - - 1,00 4.350.000,00 TETAP
2 Panel Lantai 2 (Penerangan) Unit 4.350.000,00 1,00 4.350.000,00 - - - - 1,00 4.350.000,00 TETAP
3 Panel Lantai 3 (Penerangan dan AC) Unit 5.347.000,00 1,00 5.347.000,00 - - - - 1,00 5.347.000,00 TETAP
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
KABEL FEEDER
4 Instalasi Jaringan Kabel Feeder (Dari Panel Induk Ke Bangunan) m1 340.000,00 40,00 13.600.000,00 - - - - 40,00 13.600.000,00 TETAP

B PEKERJAAN PENERANGAN
LANTAI 1
FIXTURE
Pengadaan & Pemasangan General light fixture dan fitting,
termasuk : support assesories yang diperlukan ;
1 Lampu Downlight 15 Watt Buah 225.000,00 21,00 4.725.000,00 - - - - 21,00 4.725.000,00 TETAP
2 Lampu Downlight 15 Watt Expose Buah 320.000,00 10,00 3.200.000,00 - - - - 10,00 3.200.000,00 TETAP
ASSESORIES
Pengadaan & Pemasangan Assesories, Saklar, Kotak Kontak, termasuk : gland, clamp,
tees,
3 Saklar Tunggal Buah 50.000,00 1,00 50.000,00 - - - - 1,00 50.000,00 TETAP
4 Saklar Ganda Buah 60.000,00 5,00 300.000,00 - - - - 5,00 300.000,00 TETAP
5 Stop Kontak 16A - 1 Phase Buah 110.000,00 8,00 880.000,00 - - - - 8,00 880.000,00 TETAP
KABEL PENERANGAN, SAKLAR & KOTAK KONTAK
Pengadaan & Pemasangan Instalasi Penerangan, Saklar, Kotak Kontak
termasuk : gland, clamp, tees, alat bantu, assesories, dll
6 Instalasi Titik Penerangan, NYM 3C - 2,5 mm2 c/w Conduit dia 20 Titik 350.000,00 21,00 7.350.000,00 - - - - 21,00 7.350.000,00 TETAP
7 Instalasi Stop Kontak 16A - 1 Phase, NYM 3C - 2,5 mm2 c/w conduit dia 20 Titik 340.000,00 8,00 2.720.000,00 - - - - 8,00 2.720.000,00 TETAP

LANTAI 2
FIXTURE
Pengadaan & Pemasangan General light fixture dan fitting,
termasuk : support assesories yang diperlukan ;
1 Lampu Downlight 5 Watt Buah 105.000,00 2,00 210.000,00 - - - - 2,00 210.000,00 TETAP
2 Lampu Downlight 15 Watt Buah 225.000,00 31,00 6.975.000,00 - - - - 31,00 6.975.000,00 TETAP
3 Lampu Downlight 15 Watt Expose Buah 320.000,00 12,00 3.840.000,00 - - - - 12,00 3.840.000,00 TETAP
ASSESORIES
Pengadaan & Pemasangan Assesories, Saklar, Kotak Kontak, termasuk : gland, clamp,
tees,
4 Saklar Tunggal Buah 50.000,00 3,00 150.000,00 - - - - 3,00 150.000,00 TETAP
5 Saklar Ganda Buah 60.000,00 5,00 300.000,00 - - - - 5,00 300.000,00 TETAP
6 Stop Kontak 16A - 1 Phase Buah 110.000,00 12,00 1.320.000,00 - - - - 12,00 1.320.000,00 TETAP

KABEL PENERANGAN, SAKLAR & KOTAK KONTAK


Pengadaan & Pemasangan Instalasi Penerangan, Saklar, Kotak Kontak
termasuk : gland, clamp, tees, alat bantu, assesories, dll
7 Instalasi Titik Penerangan, NYM 3C - 2,5 mm2 c/w Conduit dia 20 Titik 350.000,00 45,00 15.750.000,00 - - - - 45,00 15.750.000,00 TETAP
8 Instalasi Stop Kontak 16A - 1 Phase, NYM 3C - 2,5 mm2 c/w conduit dia 20 Titik 340.000,00 12,00 4.080.000,00 - - - - 12,00 4.080.000,00 TETAP

LANTAI 3
FIXTURE
Pengadaan & Pemasangan General light fixture dan fitting,
termasuk : support assesories yang diperlukan ;
1 Lampu Downlight 5 Watt Buah - - - - - - - - - TETAP
2 Lampu Downlight 15 Watt Buah - - - - - - - - - TETAP
3 Lampu Downlight 15 Watt Expose Buah - - - - - - - - - TETAP
ASSESORIES
Pengadaan & Pemasangan Assesories, Saklar, Kotak Kontak, termasuk : gland, clamp,
tees,
4 Saklar Tunggal Buah - - - - - - - - - TETAP
5 Saklar Ganda Buah - - - - - - - - - TETAP
6 Stop Kontak 16A - 1 Phase Buah 110.000,00 14,00 1.540.000,00 - - - - 14,00 1.540.000,00 TETAP
7 Stop Kontak AC 20A - 1 Phase Buah 110.000,00 6,00 660.000,00 - - - - 6,00 660.000,00 TETAP
KABEL PENERANGAN, SAKLAR & KOTAK KONTAK
Pengadaan & Pemasangan Instalasi Penerangan, Saklar, Kotak Kontak
termasuk : gland, clamp, tees, alat bantu, assesories, dll
8 Instalasi Titik Penerangan, NYM 3C - 2,5 mm2 c/w Conduit dia 20 Titik - - - - - - - - - TETAP
9 Instalasi Stop Kontak 16A - 1 Phase, NYM 3C - 2,5 mm2 c/w conduit dia 20 Titik 340.000,00 14,00 4.760.000,00 - - - - 14,00 4.760.000,00 TETAP
10 Instalasi Stop Kontak AC 20A - 1 Phase Titik 340.000,00 6,00 2.040.000,00 - - - - 6,00 2.040.000,00 TETAP

LANTAI ATAP
FIXTURE
Pengadaan & Pemasangan General light fixture dan fitting,
termasuk : support assesories yang diperlukan ;
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
1 Lampu TL RM 2 x 36 Watt Buah - - - - - - - - - TETAP
ASSESORIES
Pengadaan & Pemasangan Assesories, Saklar, Kotak Kontak, termasuk : gland, clamp,
tees,
2 Saklar Ganda Buah - - - - - - - - - TETAP
3 Stop Kontak 16A - 1 Phase Buah 110.000,00 1,00 110.000,00 - - - - 1,00 110.000,00 TETAP
KABEL PENERANGAN, SAKLAR & KOTAK KONTAK
Pengadaan & Pemasangan Instalasi Penerangan, Saklar, Kotak Kontak
termasuk : gland, clamp, tees, alat bantu, assesories, dll
4 Instalasi Titik Penerangan, NYM 3C - 2,5 mm2 c/w Conduit dia 20 Titik - - - - - - - - - TETAP
5 Instalasi Stop Kontak 16A - 1 Phase, NYM 3C - 2,5 mm2 c/w conduit dia 20 Titik 340.000,00 1,00 340.000,00 - - - - 1,00 340.000,00 TETAP

6 Testing dan Comissioning Ls 1.800.000,00 1,00 1.800.000,00 - - - - 1,00 1.800.000,00 TETAP


TOTAL PEKERJAAN LISTRIK & INSTALASI 90.747.000,00 - - 90.747.000,00

VIII PEKERJAAN PENANGKAL PETIR


Pengadaan & Pemasangan Sistem Penangkal Petir, termasuk : accessories dan alat bantu
lainnya ;
Berdasarkan gambar, spesifikasi teknis, aanwijzing dan klarifikasi.
1 Air terminal splitz penerima/early streamer lengkap dengan tiang Unit 15.000.000,00 1,00 15.000.000,00 - - - - 1,00 15.000.000,00 TETAP
tinggi menyesuaikan lengkap dengan accessoriesnya
2 Kabel down conductor NYY 1X50mm2 m' 135.000,00 50,00 6.750.000,00 - - - - 50,00 6.750.000,00 TETAP
3 Instalasi elektroda pertanahan,tahanan maksimal 2 OHM Unit 6.000.000,00 1,00 6.000.000,00 - - - - 1,00 6.000.000,00 TETAP
4 Bak kontrol 60x60 cm Unit 300.000,00 1,00 300.000,00 - - - - 1,00 300.000,00 TETAP
5 Lampu obstruction 60W lengkap dengan instalasinya Set 4.550.000,00 1,00 4.550.000,00 - - - - 1,00 4.550.000,00 TETAP

PEKERJAAN LAIN - LAIN


6 Testing dan Perijinan instansi terkait ls 1.900.000,00 1,00 1.900.000,00 - - - - 1,00 1.900.000,00 TETAP
TOTAL PEKERJAAN PENANGKAL PETIR 34.500.000,00 - - 34.500.000,00

IX PEKERJAAN MEKANIKAL
A PEKERJAAN SANITASI
LANTAI 1
1 Septictank Biotech Kap. 3 m3 Unit 9.000.000,00 2,00 18.000.000,00 - - - - 2,00 18.000.000,00 TETAP
2 Kitchen Zinc bh 2.400.000,00 1,00 2.400.000,00 - - - - 1,00 2.400.000,00 TETAP
3 Kran Air bh 250.000,00 3,00 750.000,00 - - - - 3,00 750.000,00 TETAP
4 Wastafel Custom dari Keramik unit 2.800.000,00 1,00 2.800.000,00 - - - - 1,00 2.800.000,00 TETAP
5 Kaca Cermin m2 340.000,00 2,54 863.600,00 - - - - 2,54 863.600,00 TETAP

LANTAI 2
1 Kloset Jongkok bh 700.000,00 2,00 1.400.000,00 - - - - 2,00 1.400.000,00 TETAP
2 Shower bh 715.000,00 2,00 1.430.000,00 - - - - 2,00 1.430.000,00 TETAP
3 Floor Drain bh 325.000,00 2,00 650.000,00 - - - - 2,00 650.000,00 TETAP
4 Kran Air bh 250.000,00 3,00 750.000,00 - - - - 3,00 750.000,00 TETAP
5 Wastafel Custom dari Keramik Unit 2.800.000,00 1,00 2.800.000,00 - - - - 1,00 2.800.000,00 TETAP
6 Kaca Cermin m2 340.000,00 2,71 921.400,00 - - - - 2,71 921.400,00 TETAP
LANTAI 3
1 Kloset Jongkok bh 700.000,00 3,00 2.100.000,00 - - - - 3,00 2.100.000,00 TETAP
2 Shower bh 715.000,00 3,00 2.145.000,00 - - - - 3,00 2.145.000,00 TETAP
3 Floor Drain bh 325.000,00 6,00 1.950.000,00 - - - - 6,00 1.950.000,00 TETAP
4 Kran Air bh 250.000,00 3,00 750.000,00 - - - - 3,00 750.000,00 TETAP
5 Wastafel + Aksesoris Unit 3.400.000,00 2,00 6.800.000,00 - - - - 2,00 6.800.000,00 TETAP
6 Meja Washtafel Unit 1.800.000,00 2,00 3.600.000,00 - - - - 2,00 3.600.000,00 TETAP
7 Kaca Cermin m2 340.000,00 1,60 544.000,00 - - - - 1,60 544.000,00 TETAP
LANTAI ATAP
1 Tandon Air Stainless Kap. 1000 L + Accessories bh 3.850.000,00 8,00 30.800.000,00 - - - - 8,00 30.800.000,00 TETAP
2 Roof Drain + Accessories bh 700.000,00 15,00 10.500.000,00 - - - - 15,00 10.500.000,00 TETAP

B PEKERJAAN PERPIPAAN AIR BERSIH


LANTAI 1
1 Pipa PVC AW Ø3/4" (Dari Sumber Air ke Pipa Tegak) m' 38.000,00 30,00 1.140.000,00 - - - - 30,00 1.140.000,00 TETAP
2 Pipa PVC AW Ø3/4" (Dari Pipa Tegak Ke Bangunan Lantai 1) m' 38.000,00 15,00 570.000,00 - - - - 15,00 570.000,00 TETAP
LANTAI 2
1 Pipa PVC AW Ø3/4" (Dari Pipa Tegak Ke Bangunan Lantai 2) m' 38.000,00 15,00 570.000,00 - - - - 15,00 570.000,00 TETAP
LANTAI 3
1 Pipa PVC AW Ø3/4" (Dari Pipa Tegak Ke Bangunan Lantai 3) m' 38.000,00 25,00 950.000,00 - - - - 25,00 950.000,00 TETAP
LANTAI ATAP
PEKERJAAN TAMBAH DAN KURANG
KONTRAK MC 0
HARGA PEKERJAAN TAMBAH PEKERJAAN KURANG
NO. URAIAN PEKERJAAN SAT KETERANGAN
SATUAN JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
VOLUME VOLUME VOLUME VOLUME
(Rp) Rp. Rp. Rp. Rp.
1 Pipa PVC AW Ø3/4" (Dari Pipa Tegak Ke Tandon) m' 38.000,00 20,00 760.000,00 - - - - 20,00 760.000,00 TETAP
2 Pipa PVC AW Ø3" m' 110.000,00 12,00 1.320.000,00 - - - - 12,00 1.320.000,00 TETAP
PIPA RISER/TEGAK
1 Pipa PVC AW Ø2" (Input Ke Tandon) m' 80.000,00 12,00 960.000,00 - - - - 12,00 960.000,00 TETAP
2 Pipa PVC AW Ø2" (Output Ke Bangunan) m' 80.000,00 36,00 2.880.000,00 - - - - 36,00 2.880.000,00 TETAP

C PEKERJAAN PERPIPAAN AIR KOTOR


LANTAI 1
1 Pipa PVC AW Ø3" m' 110.000,00 8,00 880.000,00 - - - - 8,00 880.000,00 TETAP
2 Pipa PVC AW Ø4" m' 137.500,00 30,00 4.125.000,00 - - - - 30,00 4.125.000,00 TETAP
LANTAI 2
1 Pipa PVC AW Ø3" m' 110.000,00 10,00 1.100.000,00 - - - - 10,00 1.100.000,00 TETAP
2 Pipa PVC AW Ø4" m' 137.500,00 12,00 1.650.000,00 - - - - 12,00 1.650.000,00 TETAP
3 Clean Out Ø3" bh 147.500,00 2,00 295.000,00 - - - - 2,00 295.000,00 TETAP
4 Clean Out Ø4" bh 170.000,00 1,00 170.000,00 - - - - 1,00 170.000,00 TETAP
LANTAI 3
1 Pipa PVC AW Ø3" m' 110.000,00 15,00 1.650.000,00 - - - - 15,00 1.650.000,00 TETAP
2 Pipa PVC AW Ø4" m' 137.500,00 15,00 2.062.500,00 - - - - 15,00 2.062.500,00 TETAP
3 Clean Out Ø4" bh 170.000,00 6,00 1.020.000,00 - - - - 6,00 1.020.000,00 TETAP
LANTAI ATAP
1 Pipa PVC AW Ø4" m' 137.500,00 10,00 1.375.000,00 - - - - 10,00 1.375.000,00 TETAP
2 Pipa PVC AW Ø6" m' 247.000,00 35,00 8.645.000,00 - - - - 35,00 8.645.000,00 TETAP
3 Clean Out Ø6" bh 247.000,00 4,00 988.000,00 - - - - 4,00 988.000,00 TETAP
PIPA RISER/TEGAK
1 Pipa PVC AW Ø4" m' 137.500,00 36,00 4.950.000,00 - - - - 36,00 4.950.000,00 TETAP
2 Pipa PVC AW Ø6" m' 247.000,00 24,00 5.928.000,00 - - - - 24,00 5.928.000,00 TETAP
TOTAL PEKERJAAN PENANGKAL PETIR 135.942.500,00 - - 135.942.500,00

X PEKERJAAN PENGECATAN DAN LAIN - LAIN


1 Pengecatan dinding dan beton bagian dalam ( Interior ) Keseluruhan m2 51.000,00 983,45 50.155.950,00 - - - - 983,45 50.155.950,00 TETAP
2 Pengecatan dinding dan beton bagian Luar ( Exterior ) Keseluruhan m2 75.000,00 245,86 18.439.500,00 - - - - 245,86 18.439.500,00 TETAP
3 Pengecatan plafond Gypsump dan Multiplek m2 51.000,00 317,13 16.173.630,00 - - - - 317,13 16.173.630,00 TETAP
4 Pengecatan kilap Rangka besi Tangga, Rangka Kanopy , kusen dan Daun Pintu m2 51.000,00 130,94 6.677.940,00 - - - - 130,94 6.677.940,00 TETAP
5 Cerobong Asap dari Stainless Steel + Accessories Unit 3.200.000,00 2,00 6.400.000,00 - - - - 2,00 6.400.000,00 TETAP
6 Pasang Reling Tangga Besi Hollow Stanless Steel 5 x 5 cm dan Besi Hollow 2 x 4 cm m1 950.000,00 30,70 29.165.000,00 - - - - 30,70 29.165.000,00 TETAP
7 Pasang Reling Rangga Besi Galvanis ( Tangga Belakang ) m1 725.000,00 38,00 27.550.000,00 - - - - 38,00 27.550.000,00 TETAP
TOTAL PEKERJAAN PENGECATAN DAN LAIN - LAIN 154.562.020,00 - - 154.562.020,00