R E K A P I T U L A S I
1 2 3
B PPN 10 % 81,971,800.00
C JUMLAH ( A + B ) 901,689,800.00
Terbilang : Sembilan Ratus Satu Juta Enam Ratus Delapan Puluh Sembilan Ribu Delapan Ratus Rupiah
1
DAFTAR KUANTITAS DAN HARGA
2
DAFTAR KUANTITAS DAN HARGA
3
DAFTAR KUANTITAS DAN HARGA
IX PEKERJAAN LAIN-LAIN
1 Pembuatan pot bunga type I Ls 10.00 bh 150,000.00 1,500,000.00
2 Pembuatan pot bunga type II Ls 4.00 bh 260,000.00 1,040,000.00
3 Tiang bendera Ls 2.00 unit 1,500,000.00 3,000,000.00
4 Pek.Plat Beton jalan masuk Ls 1.00 unit 3,100,000.00 3,100,000.00
5 Papan nama BPP Ls 2.00 unit 5,000,000.00 10,000,000.00
6 Pekejaan penangkal petir Ls 2.00 unit 780,000.00 1,560,000.00
7 Pek.Ornamen/gorga simalungun ditombak layar Ls 8.00 m2 180,000.00 1,440,000.00
8 Pek.Ornamen pada Kolom 20 x 20 Selasar Ls 36.00 m2 180,000.00 6,480,000.00
9 Pek.Ornamen /Kepala kerbau ditombak layar Ls 4.00 bh 720,000.00 2,880,000.00
SUB TOTAL X : PERKERASAN JALAN DENGAN SIRTU, CANSTEIN & CONBLOCK 37,819,782.63
4
PEMERINTAH KABUPATEN SIMALUNGUN
1 2 3 4 5 6 7 8 9 10 11
1 2 3 4 5 6 7 8 9 10 11
7 Bekisting Kolom Entrans --- 20 cm' x 20 cm' BKT-PRK 25.20 m2 226,210.38 5,700,501.58 0.70 5,700,501.58 5,700,501.58 0.70
6
PEMERINTAH KABUPATEN SIMALUNGUN
1 2 3 4 5 6 7 8 9 10 11
8 Tulangan Kolom Entrans --- 20 cm' x 20 cm' BESI-01 315.14 kg 12,009.03 3,784,525.71 0.46 3,784,525.71 3,784,525.71 0.46
9 Beton Cor Kolom Entrans --- 20 cm' x 20 cm' K-200 2.52 m3 881,471.74 2,221,308.78 0.27 2,221,308.78 2,221,308.78 0.27
10 Bekisting Ring Balok --- 15 cm' x 20 cm' BKT-PRK 67.92 m2 226,210.38 15,364,209.01 1.87 15,364,209.01 15,364,209.01 1.87
11 Tulangan Ring Balok --- 15 cm' x 20 cm' BESI-01 1,146.14 kg 12,009.03 13,764,029.64 1.68 13,764,029.64 13,764,029.64 1.68
12 Beton Cor Ring Balok --- 15 cm' x 20 cm' K-200 8.48 m3 881,471.74 7,474,880.36 0.91 7,474,880.36 7,474,880.36 0.91
13 Bekisting Plat Beton Meja Dapur BKT-PRK 1.42 m2 226,210.38 321,218.74 0.04 321,218.74 321,218.74 0.04
14 Tulangan Plat Beton Meja Dapur BESI-01 9.46 kg 12,009.03 113,605.42 0.01 113,605.42 113,605.42 0.01
15 Beton Cor Plat Beton Meja Dapur K-200 0.22 m3 881,471.74 193,923.78 0.02 193,923.78 193,923.78 0.02
IV PEKERJAAN DINDING & ATAP 0.00
1 Rangka Atap Baja Ringan Supersteell RNK-BJR 546.28 m2 143,963.60 78,644,435.41 9.59 47,186,661.24 47,186,661.24 5.76
2 Atap Genteng Metal ATP-GM 546.28 m2 85,775.14 46,857,243.48 5.72 23,428,621.74 23,428,621.74 2.86
3 Rabung Genteng Metal RB-GM 97.00 m' 34,223.42 3,319,671.74 0.40 1,659,835.87 1,659,835.87 0.20
4 Lisplank Kayu kelas II LP-20 - II 81.00 m' 97,361.88 7,886,312.28 0.96 3,943,156.14 3,943,156.14 0.48
5 Cat Kilat Lisplank CAT-K-3 16.20 m2 51,520.59 834,633.56 0.10 - - -
6 Pekerjaan Flashing / Plat Seng Layar Ls 8.00 m2 15,000.00 120,000.00 0.01 60,000.00 60,000.00 0.01
7 Pasangan Batu Bata 1 : 4 BATA ½ -14 437.78 m2 91,334.21 39,984,290.45 4.88 39,984,290.45 39,984,290.45 4.88
8 Plesteran 1 : 4 PLESTER-14 951.06 m2 42,715.20 40,624,718.11 4.96 40,624,718.11 40,624,718.11 4.96
V PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Kosen pintu/ Jendela KUSEN - II 2.92 m3 9,240,491.70 26,982,235.76 3.29 26,982,235.76 26,982,235.76 3.29
2 Pintu Panel PINTU - II 38.64 m2 606,938.20 23,452,092.05 2.86 7,531,504.76 7,531,504.76 0.92
3 Jendela Kaca JKC - II 80.64 m2 505,183.03 40,737,959.54 4.97 - - -
7
PEMERINTAH KABUPATEN SIMALUNGUN
1 2 3 4 5 6 7 8 9 10 11
8
PEMERINTAH KABUPATEN SIMALUNGUN
1 2 3 4 5 6 7 8 9 10 11
1 2 3 4 5 6 7 8 9 10 11
1 2 3 4 5 6 7 8 9 10 11
11
PEMERINTAH KABUPATEN SIMALUNGUN
1 2 3 4 5 6 7 8 9 10 11
TOTAL 385,472,389.50
DIBULATKAN 385,472,194.00
Terbilang = Tiga Ratus Delapan Puluh Lima Juta Empat Ratus Enam Puluh Tiga Ribu Rupiah
12
PEMERINTAH KABUPATEN SIMALUNGUN
1 2 3 4 5 6 7 8 9 10 11
13
R E K A P I T U L A S I
1 2 3
B PPN 10 % 16,027,800.00
C JUMLAH ( A + B ) 176,305,800.00
Terbilang : Seratus Tujuh Puluh Enam Juta Tiga Ratus Lima Ribu Delapan Ratus Rupiah
Page 14 of 40
DAFTAR KUANTITAS DAN HARGA
1 Timbunan tanah pilihan (Lokasi Kec.Bah jambi) URG-T 240.00 m3 93,680.73 22,483,375.20
4 Pasangan Batu bata 1 : 4 utk Canstein BATA ½ -14 50.40 m2 94,375.82 4,756,541.33
7 Pas. Batu padas 1 : 4 utk Temb. Penahan PADAS-14 6.30 m3 564,882.34 3,558,758.74
9 Urugan tanah kembali utk Temb. Penahan UKTHG 0.61 m3 15,026.77 9,166.33
11 Pek.Rabat Beton Cor Lantai Jemur , tebal= 7 cm RABAT 56.00 m3 624,453.28 34,969,383.68
12 Pelapisan Lantai Jemur dengan Acian semen ACIAN - SB 800.00 m2 25,707.99 20,566,392.00
7 Pagar BRC tinggi 1.2 meter(Lokasi Kec.Pem.Bandar) Ls 56.00 m' 190,000.00 10,640,000.00
SUB TOTAL III : PEKERJAAN PLAT BETON & PAGAR BRC 24,697,290.14
Page 15 of 40
R E K A P I T U L A S I
1 2
A TOTAL BIAYA
B PPN 10 %
C JUMLAH ( A + B )
Terbilang : Lima Ratus Lima Puluh Dua Juta Enam Ratus Empat Puluh Delapan Ribu Delapan Ratus Rupiah
Pematang Siantar, 27
3 3 3
Page 16 of 40
DAFTAR KUANTITAS DAN HARGA
1 Mobilisasi, Transportasi Material & Demobilisasi Ls 1.00 lot 1.00 lot 1.00 lot
2 Pengukuran Patok-Patok dan Bowplank Ls 2.00 lot 2.00 lot 2.00 lot
3 Pembuatan Papan Nama Proyek Ls 2.00 lot 2.00 lot 2.00 lot
4 Laporan Pelaksanaan / Administrasi Kegiatan Ls 1.00 lot 1.00 lot 1.00 lot
II PEKERJAAN PONDASI
11 Urugan Kembali Tanah Galian utk Tapak UKTHG 11.42 m3 5.71 m3 5.71 m3
14 Pasangan Batu Padas untuk Pondasi Menerus PADAS-14 32.06 m3 16.03 m3 16.03 m3
15 Urugan Kembali Tanah Galian Pondasi Menerus UKTHG 12.82 m3 6.41 m3 6.41 m3
3 Beton Cor Sloof --- 20 cm' x 20 cm' K-200 4.88 m3 2.44 m3 2.44 m3
4 Bekisting Kolom Entrans --- 25 cm' x 25 cm' BKT-PRK 12.00 m2 6.00 m2 6.00 m2
5 Tulangan Kolom Entrans --- 25 cm' x 25 cm' BESI-01 89.60 kg 44.80 kg 44.80 kg
6 Beton Cor Kolom Entrans --- 25 cm' x 25 cm' K-200 1.20 m3 0.60 m3 0.60 m3
7 Bekisting Kolom Type 2 --- 20 cm' x 20 cm' BKT-PRK 61.44 m2 30.72 m2 30.72 m2
8 Tulangan Kolom Type 2 --- 20 cm' x 20 cm' BESI-01 690.04 kg 345.02 kg 345.02 kg
9 Beton Cor Kolom Type 2 --- 20 cm' x 20 cm' K-200 6.14 m3 3.07 m3 3.07 m3
10 Bekisting Ring Balok --- 20 cm' x 20 cm' BKT-PRK 39.04 m2 19.52 m2 19.52 m2
11 Tulangan Ring Balok --- 20 cm' x 20 cm' BESI-01 512.40 kg 256.20 kg 256.20 kg
12 Beton Cor Ring Balok --- 20 cm' x 20 cm' K-200 4.88 m3 2.44 m3 2.44 m3
3 Rabung Genteng Metal RB-GM 54.00 m' 27.00 m' 27.00 m'
4 Lisplank Kayu kelas II LP-20 - III 86.00 m' 43.00 m' 43.00 m'
Page 17 of 40
DAFTAR KUANTITAS DAN HARGA
1 Pintu Utama / Pintu besi uk 2,8 x 2,5 m' + Grendel Ls 2.00 unit 1.00 unit 1.00 unit
1 Pengadaan Genset 1500 VA Jenis bensin Ls 2.00 unit 1.00 unit 1.00 unit
2 Pek.instalasi titik api dan conduit Ls 20.00 Titik 10.00 Titik 10.00 Titik
7 Pek.Pagar BRC tinggi 1.2 mtr (Lokasi kec.Jawa Maraja) Ls 120.00 m' 120.00 m'
Page 18 of 40
S I
ARGA
3 3 3
Dibuat Oleh :
CV. HASORUAN
Page 19 of 40
ANIAN PERIKANAN KEHUTANAN
BAH JAMBI & KEC. PAM. BANDAR
HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
Page 20 of 40
ANIAN PERIKANAN KEHUTANAN
BAH JAMBI & KEC. PAM. BANDAR
HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
SUB TOTAL V : PEKERJAAN PINTU, JENDELA DAN VENTILASI 27,275,294.63 13,637,647.31 13,637,647.31
Page 21 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 26,620,400.00
C JUMLAH ( A + B ) 292,824,400.00
Terbilang : Dua Ratus Delapan Puluh Tiga Juta Lima Ratus Delapan Puluh Empat Ribu Empat Ratus Rupiah
Page 22 of 40
DAFTAR KUANTITAS DAN HARGA
II PEKERJAAN PONDASI
11 Urugan Kembali Tanah Galian utk Tapak UKTHG 5.71 m3 15,213.88 86,871.25
14 Pasangan Batu Padas untuk Pondasi Menerus PADAS-14 16.03 m3 552,158.86 8,851,106.53
15 Urugan Kembali Tanah Galian Pondasi Menerus UKTHG 6.41 m3 15,213.88 97,520.97
3 Beton Cor Sloof --- 20 cm' x 20 cm' K-200 2.44 m3 902,440.55 2,201,954.94
4 Bekisting Kolom Entrans --- 25 cm' x 25 cm' BKT-PRK 6.00 m2 227,872.92 1,367,237.52
5 Tulangan Kolom Entrans --- 25 cm' x 25 cm' BESI-01 44.80 kg 12,263.57 549,407.94
6 Beton Cor Kolom Entrans --- 25 cm' x 25 cm' K-200 0.60 m3 902,440.55 541,464.33
7 Bekisting Kolom Type 2 --- 20 cm' x 20 cm' BKT-PRK 30.72 m2 227,872.92 7,000,256.10
8 Tulangan Kolom Type 2 --- 20 cm' x 20 cm' BESI-01 345.02 kg 12,263.57 4,231,176.92
9 Beton Cor Kolom Type 2 --- 20 cm' x 20 cm' K-200 3.07 m3 902,440.55 2,770,492.49
10 Bekisting Ring Balok --- 20 cm' x 20 cm' BKT-PRK 19.52 m2 227,872.92 4,448,079.40
11 Tulangan Ring Balok --- 20 cm' x 20 cm' BESI-01 256.20 kg 12,263.57 3,141,926.63
12 Beton Cor Ring Balok --- 20 cm' x 20 cm' K-200 2.44 m3 902,440.55 2,201,954.94
Page 23 of 40
DAFTAR KUANTITAS DAN HARGA
1 Pintu Utama / Pintu besi uk 2,8 x 2,5 m' + Grendel Ls 1.00 unit 6,300,000.00 6,300,000.00
7 Pek.Pagar BRC tinggi 1.2 mtr (Lokasi kec.Jawa Maraja) Ls 120.00 m' 180,000.00 21,600,000.00
Page 24 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 50,240,800.00
C JUMLAH ( A + B ) 552,648,800.00
Terbilang : Lima Ratus Lima Puluh Dua Juta Enam Ratus Empat Puluh Delapan Ribu Delapan Ratus Rupiah
Page 25 of 40
DAFTAR KUANTITAS DAN HARGA
II PEKERJAAN PONDASI
11 Urugan Kembali Tanah Galian utk Tapak UKTHG 11.42 m3 15,213.88 173,742.51
14 Pasangan Batu Padas untuk Pondasi Menerus PADAS-14 32.06 m3 552,158.86 17,702,213.05
15 Urugan Kembali Tanah Galian Pondasi Menerus UKTHG 12.82 m3 15,213.88 195,041.94
3 Beton Cor Sloof --- 20 cm' x 20 cm' K-200 4.88 m3 902,440.55 4,403,909.88
4 Bekisting Kolom Entrans --- 25 cm' x 25 cm' BKT-PRK 12.00 m2 227,872.92 2,734,475.04
5 Tulangan Kolom Entrans --- 25 cm' x 25 cm' BESI-01 89.60 kg 12,263.57 1,098,815.87
6 Beton Cor Kolom Entrans --- 25 cm' x 25 cm' K-200 1.20 m3 902,440.55 1,082,928.66
7 Bekisting Kolom Type 2 --- 20 cm' x 20 cm' BKT-PRK 61.44 m2 227,872.92 14,000,512.20
8 Tulangan Kolom Type 2 --- 20 cm' x 20 cm' BESI-01 690.04 kg 12,263.57 8,462,353.84
9 Beton Cor Kolom Type 2 --- 20 cm' x 20 cm' K-200 6.14 m3 902,440.55 5,540,984.98
10 Bekisting Ring Balok --- 20 cm' x 20 cm' BKT-PRK 39.04 m2 227,872.92 8,896,158.80
11 Tulangan Ring Balok --- 20 cm' x 20 cm' BESI-01 512.40 kg 12,263.57 6,283,853.27
12 Beton Cor Ring Balok --- 20 cm' x 20 cm' K-200 4.88 m3 902,440.55 4,403,909.88
Page 26 of 40
DAFTAR KUANTITAS DAN HARGA
1 Pintu Utama / Pintu besi uk 2,8 x 2,5 m' + Grendel Ls 2.00 unit 6,300,000.00 12,600,000.00
7 Pek.Pagar BRC tinggi 1.2 mtr (Lokasi kec.Jawa Maraja) Ls 120.00 m' 180,000.00 21,600,000.00
Page 27 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 16,027,800
C JUMLAH ( A + B ) 176,305,800
Terbilang : Seratus Tujuh Puluh Enam Juta Tiga Ratus Lima Ribu Delapan Ratus Rupiah
3 3 3
Page 28 of 40
DAFTAR KUANTITAS DAN HARGA
1 Mobilisasi, Transportasi Material & Demobilisasi Ls 1.00 lot 1.00 lot 1.00 lot 1,000,000.00
2 Pengukuran Patok-Patok dan Bowplank Ls 2.00 lot 2.00 lot 2.00 lot 540,000.00
3 Pembuatan Papan Nama Proyek Ls 2.00 lot 2.00 lot 2.00 lot 320,000.00
4 Laporan Pelaksanaan / Administrasi Kegiatan Ls 1.00 lot 1.00 lot 1.00 lot 1,000,000.00
1 Timbunan tanah pilihan (Lokasi Kec.Bah jambi) URG-T 240.00 m3 240.00 m3 m3 93,680.73
3 Rabat Beton Cor utk Canstein RABAT 1.08 m3 0.54 m3 0.54 m3 624,453.28
4 Pasangan Batu bata 1 : 4 utk Canstein BATA ½ -14 50.40 m2 25.20 m2 25.20 m2 94,375.82
7 Pas. Batu padas 1 : 4 utk Temb. Penahan PADAS-14 6.30 m3 6.30 m3 m3 564,882.34
9 Urugan tanah kembali utk Temb. Penahan UKTHG 0.61 m3 0.61 m3 m3 15,026.77
11 Pek.Rabat Beton Cor Lantai Jemur , tebal= 7 cm RABAT 56.00 m3 28.00 m3 28.00 m3 624,453.28
12 Pelapisan Lantai Jemur dengan Acian semen ACIAN - SB 800.00 m2 400.00 m2 400.00 m2 25,707.99
7 Pagar BRC tinggi 1.2 meter(Lokasi Kec.Pem.Bandar) Ls 56.00 m' m' 56.00 m' 190,000.00
Page 29 of 40
ERTANIAN PERIKANAN KEHUTANAN
A BAH JAMBI & KEC. PAM. BANDAR
3 3 3
Dibuat Oleh :
CV. PUTRA SIMBODU MAJU
Page 30 of 40
ERTANIAN PERIKANAN KEHUTANAN
A BAH JAMBI & KEC. PAM. BANDAR
HARGA HARGA
JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
SATUAN SATUAN
(Rp.) (Rp.) (Rp.)
(Rp.) (Rp.)
Page 31 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 9,524,463.61
C JUMLAH ( A + B ) 104,769,100.00
Terbilang : Seratus Empat Juta Tujuh Ratus Enam Puluh Sembilan Ribu Seratus Rupiah
Page 32 of 40
DAFTAR KUANTITAS DAN HARGA
1 Timbunan tanah pilihan (Lokasi Kec.Bah jambi) URG-T 240.00 m3 93,680.73 22,483,375.20
4 Pasangan Batu bata 1 : 4 utk Canstein BATA ½ -14 25.20 m2 94,375.82 2,378,270.66
7 Pas. Batu padas 1 : 4 utk Temb. Penahan PADAS-14 6.30 m3 564,882.34 3,558,758.74
9 Urugan tanah kembali utk Temb. Penahan UKTHG 0.61 m3 15,026.77 9,166.33
11 Pek.Rabat Beton Cor Lantai Jemur , tebal= 7 cm RABAT 28.00 m3 624,453.28 17,484,691.84
12 Pelapisan Lantai Jemur dengan Acian semen ACIAN - SB 400.00 m2 25,707.99 10,283,196.00
Page 33 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 6,503,336.39
C JUMLAH ( A + B ) 71,536,700.00
Terbilang : Tujuh Puluh Satu Juta Lima Ratus Tiga Puluh Enam Ribu Tujuh Ratus Rupiah
Page 34 of 40
DAFTAR KUANTITAS DAN HARGA
3 Pasangan Batu bata 1 : 4 utk Canstein BATA ½ -14 25.20 m2 94,375.82 2,378,270.66
7 Pek.Rabat Beton Cor Lantai Jemur , tebal= 7 cm RABAT 28.00 m3 624,453.28 17,484,691.84
8 Pelapisan Lantai Jemur dengan Acian semen ACIAN - SB 400.00 m2 25,707.99 10,283,196.00
1 Pagar BRC tinggi 1.2 meter(Lokasi Kec.Pem.Bandar) Ls 56.00 m' 190,000.00 10,640,000.00
Page 35 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 23,620,400.00
C JUMLAH ( A + B ) 259,824,400.00
Terbilang : Dua Ratus Lima Puluh Sembilan Juta Delapan Ratus Dua Puluh Empat Ribu Empat Ratus Rupiah
Page 36 of 40
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN LUMBUNG BADAN PELAKSANA PENYULUHAN PERTANIAN PERIKANAN KEHUTANAN
DAN KETAHANAN PANGAN KAB. SIMALUNGUN DI KEC. PAM. BANDAR
II PEKERJAAN PONDASI
11 Urugan Kembali Tanah Galian utk Tapak UKTHG 5.71 m3 15,213.88 86,871.25
14 Pasangan Batu Padas untuk Pondasi Menerus PADAS-14 16.03 m3 552,158.86 8,851,106.53
15 Urugan Kembali Tanah Galian Pondasi Menerus UKTHG 6.41 m3 15,213.88 97,520.97
3 Beton Cor Sloof --- 20 cm' x 20 cm' K-200 2.44 m3 902,440.55 2,201,954.94
4 Bekisting Kolom Entrans --- 25 cm' x 25 cm' BKT-PRK 6.00 m2 227,872.92 1,367,237.52
5 Tulangan Kolom Entrans --- 25 cm' x 25 cm' BESI-01 44.80 kg 12,263.57 549,407.94
6 Beton Cor Kolom Entrans --- 25 cm' x 25 cm' K-200 0.60 m3 902,440.55 541,464.33
7 Bekisting Kolom Type 2 --- 20 cm' x 20 cm' BKT-PRK 30.72 m2 227,872.92 7,000,256.10
8 Tulangan Kolom Type 2 --- 20 cm' x 20 cm' BESI-01 345.02 kg 12,263.57 4,231,176.92
9 Beton Cor Kolom Type 2 --- 20 cm' x 20 cm' K-200 3.07 m3 902,440.55 2,770,492.49
10 Bekisting Ring Balok --- 20 cm' x 20 cm' BKT-PRK 19.52 m2 227,872.92 4,448,079.40
11 Tulangan Ring Balok --- 20 cm' x 20 cm' BESI-01 256.20 kg 12,263.57 3,141,926.63
12 Beton Cor Ring Balok --- 20 cm' x 20 cm' K-200 2.44 m3 902,440.55 2,201,954.94
Page 37 of 40
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN LUMBUNG BADAN PELAKSANA PENYULUHAN PERTANIAN PERIKANAN KEHUTANAN
DAN KETAHANAN PANGAN KAB. SIMALUNGUN DI KEC. PAM. BANDAR
1 Pintu Utama / Pintu besi uk 2,8 x 2,5 m' + Grendel Ls 1.00 unit 6,300,000.00 6,300,000.00
Page 38 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 36,144,863.61
C JUMLAH ( A + B ) 397,593,500.00
Terbilang : Tiga Ratus Sembilan Puluh Tujuh Juta Lima Ratus Sembilan Puluh Tiga Ribu Lima Ratus Rupiah
Page 39 of 40
R E K A P I T U L A S I
1 2 3
B PPN 10 % 30,123,736.39
C JUMLAH ( A + B ) 331,361,100.00
Terbilang : Tiga Ratus Tiga Puluh Satu Juta Tiga Ratus Enam Puluh Satu Ribu Seratus Rupiah
Page 40 of 40