Anda di halaman 1dari 10

A Fabrikasi Steel Structure

1 Group = 6 Orang
Welder = 1 Orang
Skill = 1 Orang
Semi Skill = 2 Orang
Rigger = 2 Orang
Total 6 Orang

Produksi = 750 kg/hari Fasilitas workshop terseddia overhead crane

B Erection
1 Group = 9 Orang
Rigger = 4 Orang
Welder = 1 Orang
Skill = 2 Orang
Semi Skill = 2 Orang
Total 9 Orang

C Target produksi = 1.5


ton/hari
2
Piping
A Fabrikasi < 10 inchi
1 Group = 4 Orang
Pipe Pitter = 1 Orang
Semi skill = 2 Orang
Welder = 1 Orang
Total = 4 Orang

Target Produksi = 36
Dia.Inch
40

B Fabrikasi 10 s.d 20 inchi


1 Group = 6 Orang
Pipe Pitter = 2 Orang
Semi skill = 2 Orang
Welder = 2 Orang
Total = 6 Orang

Target Produksi = 40 Dia.Inch

C Fabrikasi > 20 inchi


1 Group = 8 Orang
Pipe Pitter = 2 Orang
Semi skill = 4 Orang
Welder = 2 Orang
Total = 8 Orang

Target Produksi = 80 Dia.Inch

D Fabrikasi Support Pipa


1 Group = 4 Orang
Pipe Pitter = 1 Orang
Semi skill = 2 Orang
Welder = 1 Orang
Total = 4 Orang

Target Produksi = 300


kg/hari
400
= Asumsi rata2 material UNP dan Siku

= 600
kg/hari
700
= Asumsi rata2 material HBeam dan WF
E Erection Support Pipa
1 Group = 4 Orang
Pipe Pitter = 1 Orang
Semi skill = 2 Orang
Welder = 1 Orang
Total = 4 Orang

Target Produksi = 500 kg/hari


= Asumsi rata2 material UNP dan Siku

1 Group = 6 Orang
Pipe Pitter = 1 Orang
Semi skill = 2 Orang
Welder = 1 Orang
Rigger = 2 Orang
Total = 6 Orang

Target Produksi = 1.2 ton/hari


= Asumsi rata2 material HBeam dan WF
Ducting
A Fabrikasi
1 Group = 8 Orang
Pipe Pitter = 2 Orang
Semi skill = 4 Orang
Welder = 2 Orang
Total = 8 Orang

Target produksi = 300


kg/hari
400

B Erection

1 Group = 12 Orang
Pipe Pitter = 2 Orang
Semi skill = 4 Orang
Welder = 2 Orang
Rigger = 4 Orang
Total = 12 Orang

Target produksi = 300


kg/hari
400

Target produksi = 700 kg/hari


= Asumsi tidak termasuk mobilisasi dari workshop ke site